The document summarizes financial details related to a construction project, including:
- Payments of Rs. 120 lakhs for bearings, with Rs. 50 lakhs approved and the balance pending approval.
- Advance payments of Rs. 28 lakhs made 20 months ago for steel, but work was delayed due to design changes.
- A pending Rs. 20.5 lakhs bill submitted to the department.
- Rs. 27 lakhs worth of reinforcement steel and Rs. 45 lakhs held up due to GST/VAT differences.
- Total amounts held up with the department and additional site investments total Rs. 576.5 lakhs.
The document summarizes financial details related to a construction project, including:
- Payments of Rs. 120 lakhs for bearings, with Rs. 50 lakhs approved and the balance pending approval.
- Advance payments of Rs. 28 lakhs made 20 months ago for steel, but work was delayed due to design changes.
- A pending Rs. 20.5 lakhs bill submitted to the department.
- Rs. 27 lakhs worth of reinforcement steel and Rs. 45 lakhs held up due to GST/VAT differences.
- Total amounts held up with the department and additional site investments total Rs. 576.5 lakhs.
The document summarizes financial details related to a construction project, including:
- Payments of Rs. 120 lakhs for bearings, with Rs. 50 lakhs approved and the balance pending approval.
- Advance payments of Rs. 28 lakhs made 20 months ago for steel, but work was delayed due to design changes.
- A pending Rs. 20.5 lakhs bill submitted to the department.
- Rs. 27 lakhs worth of reinforcement steel and Rs. 45 lakhs held up due to GST/VAT differences.
- Total amounts held up with the department and additional site investments total Rs. 576.5 lakhs.
POT-PTFE Bearing 12000 Since 3 All bearings are supplied for a
Paymcnt months total value - Rs. 120 00 lacs
Provisio for payment in original agreemcnt is available for Rs. 50 lakhs. For the balance quantity. approva for variation is yet to be given and pending since 6 months
Dcad investmcnt Sincc
Advance payments made 2800 Sincc 20 to Jindal Steel months October20. Work was delayed badly on account of changes and approvals of design of POT-PTFE beanngs by department 20.50 Since PVC bill submitted I month PVC Bill pending with month back but yct to be passcd department Stock available at site 8 Cost of reinforcement 2700 steel available at site as on date 9 Difference of GST & 45.00 since 2 years Support and guidance VAT requested from department in preparation of bill 10 Security deposit & EMD 112.00 available with the department Total amount held up in 416.50 Railway Additional Investmentin thesite of work: S Details Amount| Remarks no (Rs in Lakhs) Cost of shuttering materials for deck slab 100.00 The shuttering materials are procured & retaining wall, and made available since 2 years 2 Cost of Plant & equipment mobilized at 60.00 Available at site site Total Additional investment in the site of 160.00 Work
Total of amount held up in Railways Rs. 416.50+ Additional investment in the site of work Rs. 160.00 = Rs. 576.50 Lakhs