PROCEDURE ELECTRICAL & INSTRUMENT

DEPARTEMENT

Rev. No : 0
AEI-PRC-003 Panel Installation Procedure Page 1 of 3

PANEL INSTALLATION PROCEDURE

Document Status : Master Copy No :


PROCEDURE ELECTRICAL & INSTRUMENT
DEPARTEMENT

Rev. No : 0
AEI-PRC-003 Panel Installation Procedure Page 2 of 3

1. Purposed
This procedure is used as a guide in performing panel installation / setup panel work. So the
panel is ready to use
2. Preparation
a. Equipment
1. GIS Panel
2. Supervisory Panel
3. Relay Panel

b. Material
1. Cable Scun
2. Termination kit
3. Waste Clothes
4. Insulation cable, ties cable, tagging cable, etc

c. Tools
1. Hot marker / marker number
2. Drilling machine
3. Screw driver
4. Cutting plier
5. Striper wire
6. Combination plier
7. Cable scun press
8. Cutter
9. Measuring tape
10.Multi tester
11.Wiring tools
12.Handpallet
13.etc

3. Detail Procedure
3.1. Check Panel Document( Specification & Drawing, installation instruction)
3.1.1 Check document ( specification, dimension, guide installation, wiring, etc)
3.1.2 Check Accessories Panel
3.1.3 Check drawing
3.1.4 Check Actual location
PROCEDURE ELECTRICAL & INSTRUMENT
DEPARTEMENT

Rev. No : 0
AEI-PRC-003 Panel Installation Procedure Page 3 of 3

3.2 Panel Installation


3.2.1 Measure the floor where we want to install the switchgear with a tape
measure and draw and outline of it.
3.2.2 Mark the floor for the location of the anchor bolts with a felt tip marker. Drill
holes for the anchor bolts into the floor using the power drill. Insert the
anchor bolts into the holes and tighten the anchor bolts with the socket
wrench
3.2.3 Set the lower frame in position on the floor
3.2.4 Attach a nut onto each anchor bolt
3.2.5 Lift the Panel into position with a service trolley by using a small crane/hand
pallet, secure your switch gear cubicle the lower frame by inserting the bolts
the bolt holes. Tighten each bolt fully with the socket wrench, complete all
the wiring and cable connections

3.3 Wiring Panel


3.3.1 Refer to Wiring procedure / Termination Cable Procedure