Itp Concrete Works

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

REDCON Construction Company S.A.

PROJECT GOLDEN GATE


INSPECTION AND TEST PLAN

Contractor REDCON Construction CO.


Package No. ...........................
Description of Work CONCRETE WORKS Ref. ITP No. 1
Location ............................. Date

Inspection Parties / Type of Inspection


Project Test Method /
Work phase (description of Inspection / Codes and Record (ICL,
Specification Type of Acceptance Criteria Frequency (Internal Checking ,Witness or Hold Point) Remarks
Testing) Standards Test Report)
Ref. Inspection
CONTRACTOR
CONSL. RA
SC C
Submittal

Approved Last Design&IFC R Approved


R R&H
Approval of shop drawings
Revision Conforms to specification/drawings Prior to start work Submittal
Drawing

Specs,E.S.C& Specs,E.S.C&B R Approved


R R&H
Approval of method statement Conforms to specification&E.S.C Prior to start work Submittal
BOQ OQ
Approval Concrete Mix Design for all Approved Mix Specs,E.S.C&B Approved
R R&H
Design T&R Conforms to specification and data sheet of admixtures Prior to start work Submittal
grades & Trial Mix Results. OQ
REV. 1 of fresh
Approval of curing compound Approved E.S.C.&Data Approved
R Conforms to specification,data sheet of curing compound Prior to start work R R&H
concrete Material Sheet Submittal

Inspection

Checking the bouderies,cooridinates,alignment and


Approval shop Approval shop level as per approval shop drawings also surveying R R&H
Survey setting out works I proir to work progress IR
drawings drawings points is identified and protected.

Checking the number of supports , framing,


Approval shop Approval shop dimensional check , positions of any cast ,bracing as
Formwork Inspection I proir to work progress IR R R&H
drawings drawings per approval shop drawings also surface and overall
cleanlines.
Checking the number of reinforcement bars ,
Approval shop Approval shop R R&H
Reinforcement Inspection I diameter,position,spacing , rebar condition and rebar proir to work progress IR
drawings drawings
cover as per approval shop drawings.
Checking all surveying, civil ,mechanical ,electrical
Approval shop Approval shop Before any pouring R R&H
Concrete Pouring Release I works approved according to approved drawing last IR
drawings drawings operation
revision
All resources inculding Before any pouring
Placing Concrete MS MS R equipments ,tools,manpower ,sufficient lighting,all Visual R w
operation
field tests,safety regulations
Curing compound of concrete is used as per data After concrete surface
Concrete curing data sheet data sheet Visual sheet and recommendations of manufactures. Visual R w
is hardened

For vertical formwork to columns 24 hours after


pouring For slabs ,beams and props of slab and R R
Removal formwork Release MS MS Visual After any pouring IR
beams ten days or twice of big span plus two days
which is bigger after pouring

Approval shop Approval shop Visual , checking concrete dimension , alignment , level , R R
Concrete after pouring After removal formwork Visual
drawings drawings measure surface as per shop approval drawings
Tests

Approved Mix Approved Mix Design,Specs&E.S.C Concrete Pour


Slump Test Design&E.S.C Specs&E.S.C Slump Cone Every Truck Card
W&H W&H
Approved Mix Concrete Pour
Concrete Temperature Design&E.S.C Specs&E.S.C Thermometer Concrete temperture is not more than 35 c Every Truck Card
W&H W&H
Nine of cubes must be
taken from every day Concrete Cube
R R
Crushing cubes test Specs&E.S.C Specs&E.S.C T According to concrete grade
pour or each 100 m3 of Test Report
concrete pour.
ABBREVIATIONS : VERIFICATION CODES
SC - Subcontractor I - Inspection W - Witness Point
✘ CONSTRUCTION ✘ CONSUL ✘ OTHE C - Contractor C - Internal Checking Point H - Hold Point
RA - Regulatory Authority R - Review T - Test
MANAGER TANT RS