Professional Documents
Culture Documents
AESG DGCL KSU CX Specification
AESG DGCL KSU CX Specification
Issue 01
Revision 00
AESG has prepared this report in accordance with the instructions of their Client for their
sole and specific use. Any other persons who use any information contained herein do so at
their own risk.
Ref. No:
AESG – DGCL– PCS - 001
2
King Salman University
Project Commissioning Specification
Table of Contents
1 Introduction................................................................................................................................4
1.1 Purpose.........................................................................................................................................................4
1.2 Project Philosophy........................................................................................................................................4
2 Abbreviations and Acronyms.......................................................................................................5
2.1 Terms & Definitions......................................................................................................................................6
2.2 Reference Documentation............................................................................................................................8
3 Commissioning Team.................................................................................................................10
3.1 Employer / Employer’s Representative Appointment.................................................................................10
3.2 Contractor Appointment.............................................................................................................................10
3.3 MEP Sub-contractor Appointment..............................................................................................................10
3.4 Minimum Qualifications..............................................................................................................................10
4 General Requirements...............................................................................................................12
4.1 Commissionability Design Reviews.............................................................................................................12
4.2 T&C Method Statement Submission...........................................................................................................13
4.3 Commissioning Documentation Submission...............................................................................................13
5 Testing and Commissioning Process...........................................................................................14
5.1 Stage-1: Pre-Construction & Factory Tests (FAT)........................................................................................16
5.2 Stage-2: Static Testing Completion.............................................................................................................16
5.3 Stage-3: Pre-Commissioning.......................................................................................................................18
5.4 Stage-4: Dynamic Commissioning...............................................................................................................20
5.5 Stage-5: IST/Systems Performance Testing.................................................................................................22
5.6 : 6-12 months Defects Period – On and Off-Site.........................................................................................24
6 Documentation & Non-Conformance.........................................................................................25
6.1 Content of Test Certificates........................................................................................................................25
6.2 Content of CAS (Commissioning Assets Schedule)......................................................................................26
7 Building Management Control Philosophy.................................................................................26
8 Final Testing and Commissioning Report....................................................................................27
Ref. No:
AESG – DGCL– PCS - 001
3
King Salman University
Project Commissioning Specification
1 Introduction
1.1 Purpose
The purpose of this document is to ensure that Commissioning requirements are met in
line with the Owners project requirements and the Commissioning Plan. Furthermore,
adherence to this specification will ensure the project commissioning is in line with
industry standards and accepted best practices.
Commissioning is a systematic process of ensuring that all building systems perform
interactively according to the design intent and the Owner’s operational needs. This is
achieved by ensuring commissioning begins in the design phase to document and review
the design intent, continuing through construction, acceptance, and the warranty period
with actual verification of performance.
The commissioning process shall encompass and coordinate the traditionally separate
functions of system documentation, equipment start-up, control system calibration,
testing and balancing, performance testing and training.
Ref. No:
AESG – DGCL– PCS - 001
4
King Salman University
Project Commissioning Specification
Ref. No:
AESG – DGCL– PCS - 001
5
King Salman University
Project Commissioning Specification
Ref. No:
AESG – DGCL– PCS - 001
6
King Salman University
Project Commissioning Specification
End User: Parties using the completed building, including occupants, facilities
management staff, maintenance Contractors.
O&M Manual: A series of documents detailing the design, mode of operation and
maintenance requirements of building services systems.
Performance testing: Evaluation of a system which has been commissioned and is
operating within permitted tolerances, proving that commissioned installations meet the
performance requirements and relevant standards commissioning codes, and guides.
Pre-commissioning: Work activities necessary to advance an installation from a stage
of static completion to a dynamic stage where is ready for commissioning including
systematic checks of its suitability for commissioning.
Start-up/Energization: The process of bringing a piece of equipment to a live status
via energization and carrying out the necessary tests prior to setting to stand alone
commissioning.
Static Completion: The state of an installation when, in accordance with the Building
Services Documents are clean and ready for setting to work.
Substantial Completion: Substantial completion is an agreed point in the project when
the work is complete and being used for its intended purpose. Substantial completion
occurs once the commissioning team has fully tested the equipment and it is ready to be
placed in service.
System: Assembly of interacting components working together to satisfy specific
operational requirements of the project.
Test Instruments: Instruments used for testing and commissioning.
Test Packs / Commissioning Inspection Request: The Commissioning Test Packages
(System, Subsystem or equipment orientated) are made up of the combined Test results
(Agreed details, checklists, drawings, Installation approval, Approved Material Submittal
etc. as per the approved RAMS) prior to commencing the witnessing of Commissioning of
the system.
Verification: The process by which specific documents, components, equipment,
assemblies, systems, and interfaces among systems are confirmed to comply with Project
Requirements.
Ref. No:
AESG – DGCL– PCS - 001
7
King Salman University
Project Commissioning Specification
Ref. No:
AESG – DGCL– PCS - 001
8
King Salman University
Project Commissioning Specification
In addition to the requirements noted in the specifications, drawings and schedules, all
requirements shall follow the local and statutory bodies: -
Ref. No:
AESG – DGCL– PCS - 001
9
King Salman University
Project Commissioning Specification
3 Commissioning Team
Ref. No:
AESG – DGCL– PCS - 001
10
King Salman University
Project Commissioning Specification
The MEP sub-contractor must ensure dedicated Commissioning Engineers for each
discipline are allocated to the project, encompassing all MEP disciplines including
mechanical, electrical, ELV & Public Health. The Engineers cannot be members of the
construction/installation team, full-time dedicated commissioning resources must be
allocated. The selected person and team are to fulfil the requirements of Section 4.4.
3.4.1.1 Education
1. MEP / Building Services Engineering Degree
i. BSc Mechanical Engineering
ii. BSc Electrical Engineering
iii. BSc Building Services Engineering
2. MEP / Building Services Engineering College Diploma
i. HNC, HND or equivalent
3. MEP / Building Services Engineering College Certificate
i. ONC, OND or equivalent
ii. MEP Trade Time Served + City & Guilds Certificate
3.4.1.2 Experience
1. Minimum 10 years of job-related experience + Engineering Degree
2. Minimum 12 years of job-related experience + College Diploma
3. Minimum 15 years of job-related experience + College or Trade Certificate
3.4.1.3 Industry Accreditations
1. Chartered Engineer, desirable but not essential
2. Incorporated Engineer, desirable but not essential
3. CSA Grade 6 qualified, desirable but not essential
4. Certified Commissioning Authority with BCA, ACG or NEBB, desirable but not
essential
3.4.2.1 Education
1. MEP / Building Services Engineering Degree
i. BSc Mechanical Engineering
Ref. No:
AESG – DGCL– PCS - 001
11
King Salman University
Project Commissioning Specification
4 General Requirements
To successfully hand over this project, the Contractor must demonstrate completion of a
successful commissioning process, proving that all equipment, systems and components
have been correctly installed, tested and commissioned and are operational in
accordance with the specified requirements and performance objectives.
The technical requirements for each MEP discipline will be explained in the respective
project specifications issued by the Engineer. Below outlines the requirements for the
commissioning process.
Ref. No:
AESG – DGCL– PCS - 001
12
King Salman University
Project Commissioning Specification
7. Design credentials for ELV Systems (Cause & Effect matrix, Egress path design,
Emergency lighting calculation)
This review will consider how, and if, the systems can be correctly commissioned to
comply with the requirements of the specifications and other contract documents.
Any discrepancies or issues identified via this process should be raised by the
Commissioning specialist and submit a comprehensive report detailing their findings. The
Commissioning Review form, which will be issued on a system by system, or drawing by
drawing, basis for the engineer’s review.
A sample copy of the Commissioning Review Form shall be submitted separately to this
document for review by the engineer.
Ref. No:
AESG – DGCL– PCS - 001
13
King Salman University
Project Commissioning Specification
Ref. No:
AESG – DGCL– PCS - 001
14
King Salman University
Project Commissioning Specification
Ref. No:
AESG – DGCL– PCS - 001
15
King Salman University
Project Commissioning Specification
5.2.1 Planning
The Planning of the start-up and commissioning exercises shall include listing of all the
equipment and schedules of all the activities.
The Testing and Commissioning for each and every system is to be carried out by the
MEP contractor as per the manufacturers manuals and requirements. For larger
equipment such as AHU, MDB, MCC’s, generators etc. suppliers of these equipment to be
present at the time of start up to ensure warranties are not compromised. Furthermore,
all procedures to be in line with the submitted Cx Plan and EPCR.
As a minimum all the start-up procedures for all equipment should be clearly defined and
identified by the MEP contractor. From necessary documents such as project
specifications, drawings and contract documentation the contractor shall form a list of all
the equipment/systems that will be tested. This will be collated using Commissioning
Activity Schedules (CAS) and be segregated into sub systems (LV, ELV, P&D, FLS etc.).
All pieces of equipment will have its own asset code in line with clients’ requirements
which is required to be submitted to the engineer for approval.
The sequence for starting up each piece of equipment is to be established and system in
a coordinated manner that supports the start-up of the other equipment and systems
that rely on it. This can further explain through the use of weekly commissioning
meetings, chaired by the Lead CxM for the project.
Ref. No:
AESG – DGCL– PCS - 001
16
King Salman University
Project Commissioning Specification
The MEP contractor with the direction of the Commissioning Agency is to conduct start-up
meetings and establish sequences, schedule the work and gather data required to
schedule the start-up of the equipment and systems. The start-up schedule must fit into
the overall testing and commissioning dates established for the project.
Start-up meetings should focus specifically on the system being discussed. Multiple start-
up meetings may be necessary, depending on the number of systems involved in the
project.
The Commissioning specialist will prepare and submit commissioning and testing
progress reports at regular intervals as agreed with engineer and the engineer’s
representative which shall include the following information:
1. Activities completed
2. Activities not completed and actions been taken
3. Forthcoming events and specific actions required
4. Progress against the commissioning and master project programme
The TAB specialist contractor is required to outline the TAB works and collaborate with
the controls contractor prior to starting the TAB works. Included in the approach, is an
explanation of the intended use of the building control system. The MEP contractor is
required to review the plan and approach for understanding and coordination issues and
may comment if necessary.
The controls contractor reviews the feasibility of using the building control system for
assistance in the TAB work. The TAB sub-contractor at a minimum should submit weekly
written reports of discrepancies, contract interpretation requests and lists of completed
Ref. No:
AESG – DGCL– PCS - 001
17
King Salman University
Project Commissioning Specification
A framework including the cable pulling & panel installation works is to be created by the
MEP contractor and collaborate with the consumer equipment operative prior to starting
the energization process. The approach is in conjunction with an explanation of the
intended use of the consumer equipment operative systems, including but not limited to
HVAC & ELV systems. The MEP Contractors Commissioning Coordinator is required to
review the plan and approach for understanding and coordination issues and may
comment if necessary.
The MEP contractor reviews the expediency with Building Envelope for hindrance to
energization process. The MEP contractor at a minimum should submit weekly written
reports of discrepancies, contract interpretation requests and lists of completed tests to
the MEP Contractors Commissioning Coordinator /Commissioning Manager. This
facilitates quicker resolution of problems and will result in a more complete energization
process.
The MEP Contractor shall carry out the testing and commissioning all equipment and
integral systems, in stages if required, i.e., in conjunction with installation to ensure that
it is in proper working order and capable of performing all its functions in accordance with
the Specification.
All testing and commissioning shall be carried out according to the requirements of the
relevant BS, BSCP, IEE Regulations or other standards and regulations as may be stated
or implied in this Specification.
The T&C process shall be in accordance with provisions of the following standards and
codes mentioned below, in addition to the requirements indicated on the Design
Drawings or indicated in the Specification:
1. BSI Group, (BS) British Standards:
i. BS 7671 Requirements for Electrical Installations - IEE Wiring Regulations.
ii. BS 5266 Emergency lighting Code of practice for the emergency lighting of
premises-
To be read in conjunction with BS EN 1838 and BS EN 50172.
Ref. No:
AESG – DGCL– PCS - 001
18
King Salman University
Project Commissioning Specification
iii. BS 5839-1 + A2 Fire detection and fire alarm systems for buildings - Code
of practice for system design, installation, commissioning, and
maintenance.
iv. BS EN 81 Safety rules for the construction and installation of lifts.
2. International Electrical Testing Association, NETA Standards.
3. National Electrical Manufacturers Association, NEMA Standards.
4. National Fire Protection Association, NFPA Standards.
5. International Electro-technical Commission, IEC Standards:
6. Institution of Electrical Engineers (UK), IEE Standards:
Ref. No:
AESG – DGCL– PCS - 001
19
King Salman University
Project Commissioning Specification
2. Pipe work has been pressure tested, flushed in accordance with standard
procedures and the system is filled
3. All air systems are cleaned as required and the required filters are in place (if still in
construction phase)
4. The electrical services are complete and ready for energizing
5. All safety controls are installed and ready for start up
6. All controls instruments, valves and actuators are installed
Any deficiencies that are found during the verification, the MEP contractor should prepare
an Outstanding Work List to clearly states all the issues with the system. These are to be
completed and inspected before any start up and approved by the engineer.
For the equipment start up the MEP contractor and their suppliers (where required) must
document and record all the readings and test results to show that the
equipment/system had started up in line with the recommendations. In turn this is to be
witnessed and confirmed by the Commissioning Agent.
This is important as it will maintain the equipment warranty with the manufacturer. A
copy of these documents to be issued to the engineer’s representative for record
purposes
1. All prestart up documents are in place and approved by the engineer’s
representative
2. Start-up of the equipment to be done in a logical and organized manor to ensure
there is no effect on the system as a whole
3. Verify all the equipment are operating correctly as per the design and relevant
specification
4. Ensure any issues that have been detected during the start-up have been fixed and
cleared
5. At all times safe operation of the start-up and qualified personnel to adhere to all
HSE requirements
Ref. No:
AESG – DGCL– PCS - 001
20
King Salman University
Project Commissioning Specification
1. The testing intent is to assure that all electrical equipment, both Contractor and
Employer supplied, is operational within industry and manufacturer's tolerances and
is installed in accordance with the Specification
2. Use the International Electrical Testing Association (NETA) guidelines for all testing
procedure and acceptance test values of results.
3. Test all cable, equipment, and systems to assure proper installation, setting,
connections and functioning in compliance with Section 5.3.1.1
4. Test all the measuring, protective equipment & trip devices for applicable
functionality by means of Primary or secondary injections as per feasibility
5. Test all Circuit breaking equipment for applicable functionality by means of Primary
or secondary injections as per feasibility
1. The testing intent is to assure that all ELV/ Specialist equipment, both Contractor
and
Employer supplied, is operational within industry and manufacturer's tolerances and
is installed in accordance with the Specification
2. Each phase of commissioning shall be documented and witnessed, which is not
limited to:
Equipment & associated cabling static tests
Individual components functionality/activation via point-to-point test
Equipment stand-alone test with all-inclusive components
Interface with Third party equipment prior to final IST
Ref. No:
AESG – DGCL– PCS - 001
21
King Salman University
Project Commissioning Specification
TAB works shall be performed by an accredited and specialist agency that will be
employed by the MEP contractor. All pre-qualification details to be issued to the engineer
for approval prior to the commencement of works.
The TAB specialist will conduct and report on preliminary checks, pre-commissioning
checks, commissioning procedures, setting to work, regulation and measurement of air
flow. These activities shall be in accordance with CIBSE Commissioning Code A and as
defined in BSRIA Application Guides.
Environmental testing (with and without temporary heat loads), with BMS monitoring and
proving of thermal and air movement operations. In accordance with BSRIA BG 44,
seasonal tests are to be carried out in peak summer and winter conditions. The
Contractor is to make sure that environmental testing will be carried out in presence of
the engineer.
1. The contractor is to carry out environmental testing to prove the performance of
the systems
2. Environmental testing shall be undertaken in all rooms provided with temperature
&/or humidity control
3. With the direction of the engineer the contractor is to record temperature and
humidity in specific locations
4. The corresponding external conditions shall also be recorded at regular intervals
whilst the tests are in progress.
5. The final locations of the test instruments shall be agreed with the Engineer prior to
commencement of the environmental testing period.
Ref. No:
AESG – DGCL– PCS - 001
22
King Salman University
Project Commissioning Specification
The Integrated System Test (IST) is the final building test that demonstrates all systems
are operating in automatic control and that all interfacing is complete and operational.
The test combines the interaction between the following systems but not limited to:
1. Fire - PAVA
2. Generators
3. UPS Systems
4. Security (Access Control)
5. Emergency lighting
6. Mechanical Systems
7. Fire Protection Systems
8. Lifts
9. BMS
In conjunction with the Project Team and the required sub-contractors, the Lead
Commissioning Agent will produce an Integrated System Test document and test packs
that will outline the purpose of the test, the personnel involved, the sequence of testing,
and the Cause & Effect for each individual test scenario.
In summary the document will identify:
1. Agreed list of tests
2. Responsibility matrix
3. Test pre-requisites
4. Tick / sign-off sheets
5. Test packs
A full cause and effect testing programme shall be developed in conjunction with the fire
alarm specialist and agreed with the engineer and the engineer’s representative. The MEP
Contractor shall identify on the shop drawings, the required zoning arrangement for the
fire alarm system and provide a Cause-and-Effect Matrix Schedule to determine the main
panel operation and signalling facilities.
The Contractor shall develop the simplified fire alarm cause and effect matrix as part of
the design development. The matrix shall also be used for demonstrating the systems
during the commissioning of the system.
The cause-and-effect strategy shall be based on the phased evacuation of the
development, with the system arrangements being multi-staged and zoned as required to
provide the required functionality.
The final cause and effect arrangements shall be agreed with the Engineer’s
representative and the local authority having jurisdiction prior to implementation
Ref. No:
AESG – DGCL– PCS - 001
23
King Salman University
Project Commissioning Specification
1. In the event of detectors or input devices being actuated selected warning devices
and output interfaces will be operated
2. It being possible to configure the systems such that any input can be linked to any
output.
3. The System will be multi-staged and zoned to give phased evacuation of the
development.
4. Time for staff investigation of the cause of the alarm following initiation of the first
actuation device
5. The Voice Alarm system clearly and appropriately announces required instruction.
6. Designated air handling equipment is signalled to provide smoke control operation.
7. Civil defence is automatically notified.
8. Scheduled normally held open doors are released and closed. Scheduled
electromagnetically locked doors are opened.
9. Initiate emergency procedures on Lighting control systems, overriding of sound
systems and notification to security system.
10. Provide full battery back up to the Fire Alarm system capable of powering the
complete system for a period of at least 24 hours in the event of mains power
failure. Ensure the system shall still have sufficient capacity in the batteries to
operate the system during a full fire condition for a further period of 3 hours
11. Provide an automatic call facility from the fire alarm system to make an automatic
call out to the Civil Defence under fire alarm conditions.
● Planning and scoping: In this step, the building owner or operator establishes the
goals and objectives of the MBCx process and identifies the building systems and
components to be monitored.
● Installation and commissioning of monitoring equipment: Monitoring equipment is
installed to collect data on the energy usage of building systems and components.
Ref. No:
AESG – DGCL– PCS - 001
24
King Salman University
Project Commissioning Specification
● Data collection and analysis: Data is collected from the monitoring equipment and
analysed to identify opportunities for energy savings and to optimize system
performance.
● Implementation of energy-saving measures: Based on the analysis of the data,
energy-saving measures are implemented to improve the energy efficiency of building
systems and components.
Ref. No:
AESG – DGCL– PCS - 001
25
King Salman University
Project Commissioning Specification
Ref. No:
AESG – DGCL– PCS - 001
26
King Salman University
Project Commissioning Specification
Ref. No:
AESG – DGCL– PCS - 001
27
King Salman University
Project Commissioning Specification
Ref. No:
AESG – DGCL– PCS - 001
28