Professional Documents
Culture Documents
Payment 2-1
Payment 2-1
1
Project: Moyale Water Supply project
Client: SRS Irrigation and Development Bureau
Contractor: IQRA General Construction Company
Sub. Contractor: FUREY General Construction
TOTAL
VAT (15%)
GRAND TOTAL
4.5.4 Supply and install external water level indicator complete with No
necessary accessories
Supply and fix external galvanised steel (6m) and internal stainless
4.5.5 steel (4.5m) ladder complete with safety cage as per the design to the No
satisfaction of the engineer.
4.5.6 Provide & install uPVC water stops m
4.5.7 Provide and fix 6mm sheet metal 800x800mm access cover with 40x40 no
angle iron frame with latck and lock for valve chamber and reservoir
Vent Pipes no
4.6 Supply and Installation of Pipes, Valves and Fittings
Supply and Install Steel DN200 Inlet pipes, fittings and valves of
4.6.1 PN10 with all required accessories
4.6.1.1 Flanged Bell Mouth No
4.6.1.2 Double Flanged Pipe With Central Puddle L=1.0m No
4.6.1.3 Double Flanged 90 Degree Bend No
4.6.1.4 Double Flanged Short Pipe L=3.34m No
4.6.1.5 Double Flanged 90 Degree Duck Foot Bend No
4.6.1.6 Double Flanged Short Pipe L=0.25m No
4.6.1.7 Double Flanged Gate Valve No
4.6.1.8 Dismantling Piece No
4.6.1.9 Flanged Adapter No
Supply and fix Pipe support including pipe clamp, wall bracket, foot
4.6.1.10 plate and anchor bolts LS
Supply and Install Steel DN200 Outlet pipes, fittings and valves of
4.6.2 PN10 with all required accessories
4.6.2.1 Flanged Suction Strainer No
4.6.2.2 Double Flanged Pipe With Puddle L= 1.0m No
4.6.2.3 Double Flanged Gate Valve No
4.6.2.4 Double Flanged Woltman Water Meter No
4.6.2.5 Dismantling Piece No
4.6.2.6 Double Flanged Short Pipe L=0.25m No
4.6.2.7 Flanged Adapter No
Supply and Install Steel Over Flow and Drainage pipes, fittings
4.6.3 and valves
4.6.3.1 DN65, PN10 Steel Flanged Bell Mouth No
4.6.3.2 DN65, PN10 Steel Double Flanged Pipe With Puddle L=1.42m No
4.6.3.3 DN65, PN10 Steel Double Flanged 90 Degree Bend No
4.6.3.4 DN65, PN10 Steel Double Flanged Short Pipe L=2.92m No
4.6.3.5 DN65/DN65, PN10 Steel All Flanged Tee No
4.6.3.6 DN65, PN10 Steel Flanged Adapter No
4.6.3.7 DN50, PN10 Steel Single Flanged Pipe Short L=0.1m No
4.6.3.8 DN50, PN10 Steel Double Flanged Pipe With Puddle L=1.0m No
4.6.3.9 DN50, PN10 Steel Double Flanged Gate Valve No
4.6.3.10 DN65/DN50, PN10 Steel Double Flanged Eccentric Reducer No
Supply and fix Pipe support including pipe clamp, wall bracket, foot
4.6.3.11 plate and anchor bolts LS
Prepared By:-
Sub Contractor:________________________________
ROJECT
0.00 m3
4.1.3 Ditto but to a depth of 1.5m
3.142 4.05 radius(R')= 4.05 m Π=3.142 d =1.20m
4.05
1.20
61.84 m3
3.142 4.05 4.1.4 Excavation in soft rock
4.05 radius(R')= 4.05 m Π=3.142 d =0.15
0.15
7.73 m3
3.142 4.05 4.1.5 Excavation in hard rock
4.05 radius (R')= 4.05 m Π=3.142 d=0.10
0.10
5.15 m3
4.1.6 Cartawy
74.73 m 3
165.92 m2
4.3.2 Soffit of suspended slab
3.14 3.50 i. Pondo A= π*(R''*R'')
3.50 radius( R''' ) = 3.3+0.2=3.50m Π=3.142
38.47 m 2
43.88 m2
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR 1st Interim Payment
Sub. Cotractor:- FUREEY GENERAL CONSTRUCTION
100 m3 Ground Reservior Bar Schedule
Bar bending dimensions No. of Total Length (m)
Postion Bar Dia No of Distribute
Bar name or Description C/C L1 S1 S2 Total L bars in Dia Dia Remark
No. (mm) members d length Dia 10mm Dia 12mm Dia 14mm Dia 24
(m) (m) (m) (m) member 16mm 20mm
1.00 12 0.20 0.30 4.13 0.17 4.60 109.00 2.00 21.51 1,001.93
Shear Wall 2.00 10 0.19 21.49 21.49 21.00 1.00 3.88 451.29
3.00 10 0.19 22.56 22.56 21.00 1.00 3.88 473.66
Roof Slab 4.00 14 0.14 1222.51 1.00 1.00 1,222.51
5.00 14 0.17 861.82 1.00 1.00 861.82
Base Slab
6.00 12 0.16 631.42 1.00 1.00 631.42
Total Length (m) 924.945 1,633.35 2,084.33 - - -
Unit Wt./ml 0.617 0.89 1.21 1.58 2.47 3.55
Total Wt. (Kg) 570.691 1,450.41 2,517.87 - - -
6.6.11 Supply and fix 5.4 x 0.63 m metal frame with wires mesh m
Provide, cut, bend and fix in position reinforced steel bar. All
6.7.1.2
according to structural drawing. Price shall include tying wires
6.8 Finishing
6.10 Miscellaneous
6.10.1 Supply and fix anchor bolt in the R.C. generator seat No
6.10.2 Stone pavement around building m2
TOTAL CARRIED TO SUMMARY
Prepared By:-
Sub Contractor:________________________________
OJECT
-
10.24 520.00 5,324.80 0.00 5,324.80
10.24 520.00 5,324.80 0.00 5,324.80
4.50 520.00 2,340.00 0.00 2,340.00
20.48 520.00 10,649.60 0.00 10,649.60
- 0.00 0.00 0.00
1 8.40
6.40
53.76 m2
2 7.80
0.50
0.60
4.68 m3
2 4.60
0.50
0.60
2.76 m3
7.44 m3
1 6.60
4.60
0.30
9.11 m3
16.55 m3
1 6.60
4.60
0.25
7.59 m3
2 12.80
0.40
0.05
0.51 m3
1 6.60
4.60
0.03
0.91 m3
1.42 m3
2 7.40
0.20
0.20
0.59 m3
2 4.60
0.20
0.20
0.37 m3
0.96 m3
8 3.20
0.20
0.20
1.02 m3
2 7.40
0.20
0.20
0.59 m3
2 4.60
0.20
0.20
0.37 m3
0.96 m3
1 3
1.5
0.5
2.25 m3
1 7.00
5.00
0.15
5.25 m3
2 7.40
0.40
0.60
3.55 m3
2 4.60
0.50
0.60
2.76 m3
6.31
4 7.40
0.20
5.92 m2
4 5.40
0.20
4.32 m2
10.24 m2
4 7.40
0.20
5.92 m2
4 5.40
0.20
4.32 m2
10.24 m2
2 4.50
0.50
4.50 m2
8 3.20
0.80
20.48 m2
2 7.40
3.20
47.36 m2
2 5.00
3.20
32.00 m2
2 5.40
1.20
6.48 m2
1 3.00
2.20
6.60 m2
2 1.20
0.80
1.92 m2
77.32 m2
2 4
8 No
2 4m
5 no
40 m
2 8.4 m
6.00 no
100.8 m
2 7.50 m
6.00 no
90 m
2 4.89
6.40
62.59 m2
2 7.20
3.20
46.08 m2
2 4.80
3.20
30.72 m2
1 3.00
2.20
6.60 m2
2 1.20
0.80
1.92 m2
68.28 m2
2 7.40
3.20
47.36 m2
2 5.00
3.20
32.00 m2
2 5.40
1.20
6.48 m2
1 3.00
2.20
6.60 m2
2 1.20
0.80
1.92 m2
77.32 m2
2 7.20
3.20
46.08 m2
2 4.80
3.20
30.72 m2
1 3.00
2.20
6.60 m2
2 1.20
0.80
1.92 m2
68.28 m2
1 7.40
5.00
37.00 m2
2 9.40
1.00
18.80 m2
2 7.00
1.00
14.00 m2
32.80 m2
2 8.40
16.80 m
2 6.00
12.00 m
28.80 m
2 8.40
16.80 m
2 4.60
9.20 m
Prepared By:-
Sub Contractor:_______________________
IVIL WORKS OF MOYALE WATER SUPPLY PROJECT
ATE IRRIGATION DEVELOPMENT BUREAU
N & SUPERVISION WORKS INTERPRISE
ONTRACTOR
AL CONSTRUCTION
2nd Interim Payment
OF GENERATOR HOUSE
Description
6.1 Earth work
6.1.1. site clearing
6.1.4. Cartawy
6.4.2 Formwork
6.4.3 Grade beam
i. Long side
6.4.6 Column
iv. Deduction
1. Door
2. Window
iv. Deduction
1. Door
2. Window
Net area
6.8.3. Apply pointing to all external cement concrete block wall
i. Long side
iv. Deduction
1. Door
2. Window
Net area
6.8.4. Apply 3 coats of plastic paint to internal walls
i. Long side
ii. Short side
iv. Deduction
1. Door
2. Window
Net area
6.8.5. 20 mm cement screed
Generator House
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
Column 1.00 10 0.10 3.18 0.10
Stirup 2.00 6 0.20
3.00 10 5.16 0.10
4.00 10 5.16 0.07
Grade & Top tie Beam
5.00 10 3.16 0.07
6.00 10 7.16 0.10
7.00 6 0.20
Stirup
8.00 6 0.20
9.00 12 0.15 0.46 2.66 0.46
10.00 12 0.15 2.66
Generator Seat
11.00 12 0.15 0.46 1.46 0.46
12.00 12 0.15 1.46
Prepared By:-
Sub Contractor:________________________________
- - - -
1.21 1.58 2.47 3.55
- - - -
- - - -
1.21 1.58 2.47 3.55
- - - -
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
7.2.3 Beams m3
Provide, cut, bend and fix in position reinforced steel bar. All
according to structural drawing. Price shall include tying wires
Stone Masonry
Provide and construct 400 mm thick pointed stone masonry for Foundation
7.2.10 m3
Wall
Supply, assemble and fix in position eucalyptus roof truss price shall
7.5.1 include the application of three coats and external anti-termite treatment as No
per the drawing
Supply, assemble and fix in position equalyptus Rafters DN 100mm
7.5.2 m
including three coats of anti - termite external treatment
Supply and fix purlin in Zigba wood size 50 x 70 mm nailed into eucalyptus
7.5.3 m
truss including three coats of anti - termite external treatment
Supply and fix 120 x 60 mm G-28 galvanized iron down pipe including
7.5.8 1mm thick metal support brackets fixed at a maximum interval of 1000 mm m
fixed to walls or columns
7.9.1 Supply and fix anchor bolt in the R.C. generator seat No
Prepared By:-
Sub Contractor:________________________________
OJECT
Amount in
Quantity
Birr
Previous Current Todate UNIT PRICE Previous Current Todate
-
0.00 0.00 0.00
-
0.00 0.00 0.00
-
15.40 15.40 7,500.00 115,500.00 115,500.00
-
8.10 8.10 7,500.00 60,750.00 60,750.00
-
8.64 8.64 7,500.00 64,800.00 64,800.00
-
4.86 4.86 7,500.00 36,450.00 36,450.00
-
4.35 4.35 7,500.00 32,625.00 32,625.00
-
0.00 135.00 0.00 0.00
-
359.00 359.00 135.00 48,464.96 48,464.96
-
155.48 155.48 135.00 20,990.34 20,990.34
-
2,236.62 2,236.62 135.00 301,944.15 301,944.15
-
- 0.00 135.00 0.00 0.00
-
672.70 672.70 135.00 90,814.69 90,814.69
-
0.00 0.00 0.00
-
6.06 6.06 3,800.00 23,028.00 23,028.00
-
0.00 0.00 0.00
-
22.02 22.02 520.00 11,450.40 11,450.40
-
51.75 51.75 520.00 26,910.00 26,910.00
-
11.34 11.34 520.00 5,896.80 5,896.80
-
67.46 67.46 520.00 35,079.20 35,079.20
-
0.00 0.00 0.00
-
106.92 106.92 630.00 67,356.45 67,356.45
-
0.00 630.00 0.00 0.00
-
4.40 4.40 2,200.00 9,680.00 9,680.00
-
173.20 173.20 570.00 98,724.00 98,724.00
-
87.60 87.60 570.00 49,932.00 49,932.00
-
40.20 40.20 570.00 22,914.00 22,914.00
-
78.11 78.11 1,350.00 105,448.50 105,448.50
-
31.80 31.80 1,200.00 38,160.00 38,160.00
-
-
0.00 300.00 0.00 0.00
-
0.00 0.00 0.00
-
0.00 32,000.00 0.00 0.00
-
0.00 29,500.00 0.00 0.00
-
0.00 29,050.00 0.00 0.00
-
0.00 0.00 0.00
-
0.00 0.00 0.00
-
104.04 104.04 303.00 31,522.61 31,522.61
-
106.92 106.92 150.00 16,037.25 16,037.25
-
0.00 150.00 0.00 0.00
-
41.34 41.34 290.00 11,988.60 11,988.60
-
0.00 0.00 0.00
-
0.00 75,000.00 0.00 0.00
-
0.00 0.00 0.00
-
0.00 40.00 0.00 0.00
-
0.00 720.00 0.00 0.00
-
0.00 11,500.00 0.00 0.00
-
0.00 22,000.00 0.00 0.00
-
0.00 7,050.00 0.00 0.00
-
0.00 0.00 0.00
-
0.00 950.00 0.00 0.00
-
35.00 35.00 550.00 19,250.00 19,250.00
40.20 m
7.5.5. roof cover in G-28 mm corrugated galvanized
iron sheet
2 10.70
3.65
78.11 m2
7.6 Finishing
7.6.1. plaster in cement mortar to internal cement
concrete block wall
2 7.80 i. Axis 1 & 2
3.60
56.16 m2
ii. Axis A & B
2 5.30
3.60
38.16 m2
2 6.70 ii. Upper Part of top tie beam
1.45
9.72 m2
104.04
7.6.2. pointing to all external cement concrete block
wall
2 8.00 i. Axis 1 & 2
3.60
57.60 m2
2 5.50 ii. Axis A & B
3.60
39.60 m2
2 6.70 ii. Upper Part of top tie beam
1.45
9.72 m2
106.92 m2
7.6.3. Apply 3 coats of plastic paint to internal
walls and synthetic paint to metal doors and
windows
2 7.80 i. Axis 1 & 2
3.60
56.16 m2
ii. Axis A & B
2 5.30
3.60
38.16 m2
94.32
7.6.4. 20 mm cement screed
1 7.80
5.30
41.34 m2
7.9.2. Stone pavement around building
2 10.00 i. Axis 1 & 2
1.00
20.00 m2
ii. Axis A & B
2 7.50
1.00
15.00 m2
35.00 m2
7.5.6. Supply and fix 25 x 250 mm facia board
2 9.20 i. Axis 1 & 2
18.40 m
2 6.70 ii. Axis A & B
13.40 m
31.80 m
ROJECT
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:- FUREEY GENERAL CONSTRUCTION
Pump House Bar Schedule
Bar bending & cut dimensions
Bar Dia
Bar name or Description Postion No. C/C L1 S1 S2
(mm)
(m) (m) (m)
V 16 0.15
Stair
H 16 0.15
Gread Beam Along Axis 1, Long S. 12 0.20 10.95 0.20
2 &3
Stirups of IMB 8 0.20 0.50 0.10 0.70
C1 12 0.24 1.80
Prepared By:-
Sub Contractor:________________________________
T
2nd Interim
218.40
94.50
17.40
63.00
33.00
- 426.30 - -
1.208 1.578 2.466 3.551
- 672.70 - -
Quantity
Item No. Item Description Unit
Previous Current
8.1 Earth Work and Excavation
8.1.1 Top soil stripping to 200mm depth m2 16.00
8.1.2 Stripped level to a depth not exceeding 1m m 3
2.64
Trench excavation for stone masonry foundation wall in
8.1.3 normal material to a depth not exceeding 1.5m m3 2.97
8.1.7 Ditto but around the stone masonry foundation wall m3 1.00
8.1.8 250mm thick hard core well blinded with crushed stone m2 1.32
Disposal of surplus excavated materials as directed by th
8.1.9
engineer
m3 8.17
8.2 Masonry Work
50cm Basaltic or equivalent stone masnory foundation
8.2.1 wall bedded in cement sand mortar of mix ratio 1:3 below m3 1.56
and above NGL
8.3 Concrete Work
50mm thick lean concrete in C-10 under stone masonry
8.8.1
foundation wall
m2 6.25
8.3.2 Ditto but underfloor above the hard core m2 4.00
8.4 Grade C-25 Reinforced concrete
10cm concrete Above the hard core for the floor with dia.
8.4.1 8mm bar mesh on both directions with 15cm c/c m3 5.29
8.4.2 For Grade beams, column, lintels and Top tie beam m3 6.53
8.4.4 Form Work for floor slab, beams, and columns m2 16.4
8.4.5 High yield reinforced steel bars to specification
8.4.5.1 φ10 mm kg 61.206
8.4.5.2 φ6 mm kg 26.107
8.5 Carpentry and Joiney
Truss made eculyptus poles of diam. 8cm for upper and
8.5.1 lower chords and 8cm for vertical and inclined members nr. 6
as per the drawing at 80cm spacing
8.5.2 5x7cm zigba wood purlin as shown in the drawing m 21
8.5.3 G- 28 C.I.S Roof cover m 2
13.23
8.6 Electrical Installation
Light points in thermoplastic conduit of diam.13mm fed
8.6.1 through PVC insulated conductors of 2x2.5mm2 nr
8.8.3 30mm thick cement sand screed for the floor m2 5.29
Three coats of Painting of internal and external walls
8.8.4 including beam and column surface with plastic emulsion m2
paint
8.8.5 Painting of metal doors and windows sum 1.00
TOTAL FOR BILL No. 8
Total Carried To Summary one in No.
OJECT
100m3
1,930.50
2.97 650.00 0.00 1,930.50
1.46 450.00 656.10 0.00 656.10
1.09 500.00 546.75 0.00 546.75
1,015.63
1.56 650.00 0.00 1,015.63
1.00 1,460.00 1,460.00 0.00 1,460.00
707.54
1.32 535.00 0.00 707.54
3,674.92
8.17 450.00 0.00 3,674.92
0.00 - 0.00 0.00
5,937.50
1.56 3,800.00 0.00 5,937.50
0.00 - 0.00 0.00
28,125.00
6.25 4,500.00 0.00 28,125.00
4.00 4,500.00 18,000.00 0.00 18,000.00
0.00 - 0.00 0.00
39,675.00
5.29 7,500.00 0.00 39,675.00
6.53 7,500.00 48,975.00 0.00 48,975.00
16.40 7,500.00 123,000.00 0.00 123,000.00
-
0.00 2,750.00 0.00 0.00
-
0.00 650.00 0.00 0.00
-
0.00 2,800.00 0.00 0.00
-
0.00 15,000.00 0.00 0.00
-
0.00 4,000.00 0.00 0.00
0.00 1,800.00 - 0.00 0.00
0.00 1,800.00 - 0.00 0.00
0.00 1,800.00 - 0.00 0.00
0.00 1,800.00 - 0.00 0.00
0.00 - 0.00 0.00
-
0.00 0.00 0.00
1.00 15,000.00 - 15,000.00 15,000.00
1.00 13,000.00 - 13,000.00 13,000.00
0.00 - 0.00 0.00
15,115.91
23.99 630.00 0.00 15,115.91
7,270.03
23.99 303.00 0.00 7,270.03
5.29 290.00 1,534.10 0.00 1,534.10
-
0.00 85.00 0.00 0.00
1.00 105.00 - 105.00 105.00
361,910.11 28,105.00 390,015.11
361,910.11 28,105.00 390,015.11
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
2nd Interim Payment
BILL No. 8: CONSTRUCTION OF GUARD HOUSE AT BOOSTER STATION of 100m3
T D S Unit Description
8.1 Earth work
8.1.1. site clearing
1 4.00
4.00
16.00 m2
2 2.30 8.1.3 Excavation to a depth not
2.30 exceeding 1m
0.25
2.64 m3
2 5.40 8.1.3. .Trench Excavation
0.50
0.55
2.97 m3
1 2.70 8.1.4 Excavation in soft rock
2.70
0.20
1.46 m3
1 2.70 8.1.5. Excavation in hard rock
2.70
0.15
1.09 m3
8.1.6.Filling and compacting with
select
1 2.50
2.50
0.25
1.56 m3
2 5.00 8.1.7 Ditto but around the stone
0.40 masonry foundation wall
0.25
1.00 m3
1 2.30 8.1.8 250mm thick hard core
2.30
0.25
1.32 m3
8.1.9 Disposal of surplus
8.17 m3
8.2 Masonary Work
4 2.50 8.2.1 50cm Basaltic stone masnory
0.40
0.40
1.56 m3
8.3 Concrete Work
1 2.50 8.3.1 50mm thick lean concrete
2.50 (under the masonary foundation)
6.25 m2
8.3.2 Ditto but under floor
2 5.00 above the hard core
0.40
4.00 m2
8.4 Grade C-25 Reinforced concrete
8.4.1 10cm concrete
1 2.30
2.30
5.29 m2
4 2.50 8.4.2 concrete work for,
0.20 I. Grade beam
0.20
0.40 m3
4 2.50 ii. Column
0.20
0.20
0.40 m3
2 1.00 iii. Lintels
0.20
0.10
0.04 m3
4 2.50 Iv. Top tie beam
0.20
0.20
0.40 m3
6.53 m3
8.4.4 Form Work for
8 2.5 I. Grade beam
0.2
4 m2
ii. Column
16 2.5
0.2
8 m2
4 1 iii. Lintels
0.1
0.4 m2
8 2.5 Iv. Top tie beam
0.2
4 m2
16.4 m2
8.5 Carpentry and Joiney
8.5.1 Truss made eculyptus poles
6 nr
7 3 8.5.2 5x7cm zigba wood purlin a
21 m
N of 100m3
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
Guard House
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
Column 1.00 10 0.15 2.50 0.15
Stirup 2.00 6 0.20
Grade Beam 3.00 10 0.15 2.50 0.15
Top tie Beam 4.00 10 0.15 2.50 0.15
Stirup 5.00 6 0.20
Lintels 6.00 10 0.10 1.00 0.10
Prepared By:-
Sub Contractor:________________________________
2nd Interim Payment
- - - -
1.21 1.58 2.47 3.55
- - - -
Quantity
Item No. Item Description Unit
Previous
Earth work
9.1
Filling and spread under hard core with selected site material &
compact in layers not exceeding to a thickness of 15cm as per the
9.1.6 recommendation of the supervising Engineer m3 4.92
Masonry work
9.2
Hard stone masonry work for stand bedded with cemement sand
9.2.3 mortar 1:3 in ratio m3 0.22
15 cm wide dressed stone open channel drainage to soak away pit
9.2.4 m2 3.96
15cm thick mass concrete over hard core as shown in the drawing
9.3.1 m2 14.70
cement screeding
9.3.3 m2 2.60
Supply & fix mesh wire up to a height not less than 2.50m, fixed to the
9.5.2 concrete poles by caped including all necessary fixing materials. m
Supply and fix (2x2m)double leaf grilled size gate made of 60x60mm
9.5.5 RHS frame of thickness 10mm nr
Carried to Summary
Prepared By:-
Sub Contractor:________________________________
T
9.2 Massonary
Prepared By:-
Sub Contractor:________________________________
dimensions No. of Total Length (m)
No of Distribute
Total L bars in
members d length Dia 6mm Dia 8mm Dia 10mm Dia 12mm
(m) member
3.50 22.00 1.00 4.20 77.00
4.20 19.00 1.00 3.50 79.80
Total Length (m) - - 156.800 -
Unit Wt./ml 0.222 0.395 0.617 0.89
Total Wt. (Kg) - - 96.746 -
- - - -
1.21 1.58 2.47 3.55
- - - -
Earth work
10.1
Filling and spread under hard core with selected site material & compact
in layers not exceeding to a thickness of 15cm as per the
recommendation of the supervising Engineer m3
10.1.6
Prepared By:-
Sub Contractor:________________________________
PROJECT
2 50
2.5
250 m2
10.4 Form work
Sear wall & bottom slab
2 25 i. Outer long side wall & bottom slab
0.5
25.00 m2
2 2.5 ii. Outer short side wall & bottom slab
0.5
2.5 m2
4 25 iii. Inner long side of wall
0.36
36 m2
4 1.7 iv. Inner short side of wall
0.35 A=1/2(b1+b2)*h
1.19 m2
64.69 m2
0.3
0.15 0.95
0.5 0.36
0.25 0.75 0.5
2.5
PROJECT
1 6.50
29.00
188.50 m2
1 6.50
29.00
0.60
113.10 m3
1 2.50
25.00
0.02
1.00 m3
1 2.50
25.00
0.01
0.88 m3
114.98 m3
1 2.50
25.00
0.30
18.75 m3
1 2.50
25.00
0.25
15.63 m3
1 2.30
25.00
57.50 m2
1 2.30
25.00
0.15
8.62 m3
2 0.20
0.25
25.00
2.50 m3
1 0.40
0.25
25.00
2.50 m3
4 0.85
0.25
0.15
0.13 m3
SUM 5.13 m3
2 27
2
108 m2
1 2.3
2
4.6 m2
112.6
2 25
0.4
20.00 m2
2 2.5
0.4
2 m2
4 25
0.25
25 m2
4 1.7
0.25
0.85 m2
47.85 m2
0.15
TRUCTION CATTLE TROUGHS OF GOAT
Description
10.1 Earth work
10.1.1. site clearing
10.1.2. Excavation
10.1.5. Cartawy
b) Shear wall
i. Left & Right long side
1&4 2
Cuttle Trough
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
Section A-A
2.00 8 0.20 0.60 1.12 0.16
3.00 8
4.00 8 0.20 1.18 24.90 1.20
Section B-B
5.00 8
Prepared By:-
Sub Contractor:________________________________
CT
33 berga
28 berga
- - - -
1.21 1.58 2.47 3.55
- - - -
13.1.1 m2
Clearing of site to remove top soil to a depth of 200 mm
13.1.2 m3
Excavation for stone masonry foundation; 0.6m width and 1.0 m depth
13.1.3 m3
Backfill to depth of not less than 450mm
13.1.4 Cart away and deposit excavated surplus material to a distance not m3
exceeding 1km.
13.1.5 Supply, fill and compact layer by layer of selected material m3
13.1.6 Provide and fill hard core with hard basaltic or equivalent stone, well m2
compacted and blinded with crushed stone to a finished thickness of
25 cm
13.2 Masonry Work
Supply and raise 500 mm thick and 1000mm high trachitic or
13.2.1 equivalent stone masonry foundation wall below ground level bedded m3
in cement mortar mix 1:3
13.3
Concrete Work
13.3.1 m2
Provide 50mm thick lean concrete with mix ratio (1:3:6)
Reinforced concrete grade C-25 with minimum cement content 360
kg/m3 cast into formwork and vibrated around reinforcement bars
in:price shall include form work
13.3.2 For beams and Lintels m3
13.3.3 For columns m3
Mass concrete fill on floor slab (100mm)
13.3.4 m3
13.3.5 m3
Concrete grade C-20 for the drainage ditch and walkaway
Supply and fix edge gutter formed in G-28 flat galvanized metal sheet
including support brackets 1mm thick shaped steel plate spaced at a
13.6.5 maximum spacing of 1000 mm c/c and fixed to purlin - price includes m
metal primer and two coats of synthetic enamel paint
Supply & fix diameter 100mm down pipe in G-30 including 1mm
13.6.6 thick metal support brackets fixed at a maximum interval of 1000 mm m
fixed to walls or columns
Supply and fix 25 x 250 mm fascia board to purlin
13.6.7 m
Supply and fix 40 x 50 mm ceiling battons
13.6.8 m
Supply and fix chipwod ceiling
13.6.9 m2
Supply and fix ribbed sheet
13.6.10 m2
Supply and fix metal door size 900 x 2200 mm price includes 4mm
13.6.11 thick glass and three layers of synthetic paint to the frames No
Supply and fix wooden door size 900 x 2200 mm price includes
13.6.12 scynthetic paintings No
Supply and fix metal door size 800 x 2200 mm price includes 4mm
13.6.13 thick glass and three layers of synthetic paint to the frames No
Supply and fix metal door size 700 x 2100 mm price includes 4mm
13.6.13 thick glass and three layers of synthetic paint to the frames No
Supply and fix metal window size 1000 x 1000 mm price includes
13.6.15 4mm thick glass and three layers of synthetic paint to the frames No
Supply and fix metal window size 1200 x 1400 mm price includes
13.6.16 4mm thick glass and three layers of synthetic paint to the frames No
Supply and fix metal window size 750 x 500 mm price includes 4mm
13.6.17 thick glass and three layers of synthetic paint to the frames No
13.7 Finishing
Finishing work shall include all surface pre-cleaning, polishing and
cleaning at the end of finishing
Floor screed in cement mortar 20 mm thick
13.7.1 m2
Plastic tile floor finish for the main house
13.7.2 m2
Ceramic tile floor and wall finish for the service quarter
13.7.3 m2
Apply three coats of plaster in cement mortar to internal cement
13.7.4 concrete blocks, all beams and columns m2
Apply cement mortar pointing to all external cement concrete block
13.7.5 wall m2
Apply 3 coats of plastic paint to internal walls
13.7.6 m2
13.8.5
Light Fitting and Lamps
TMS 012/1.36 or 1X36w Fluorescent
13.8.6 No
TMS 095/1.36 or 1X36w Fluorescent
13.8.7 No
13.8.8
Sockets and Switch Outlets
16A/1P socket outlet points
13.8.9 No
25A/1P socket outlet points
13.8.10 NO
wall mounted single pole switch
13.8.11 NO
wall mounted 2 pole switch
13.8.12 NO
Pvc Pipe
PVC conduit of 16mm diameter including junction boxes with covers
13.8.13 and insulating screw cap connectors. M
PVC conduit of 20mm diameter including junction boxes with covers
13.8.13 and insulating screw cap connectors. M
13.9.14 kg
Diameter 8 mm plain bar
13.10
Construction of Soakaway Pit
13.10.1 m2
Site clearing to depth of 20cm
13.10.2 m3
Excavation of soil to depth of 2.5mts. In ordinary soil
13.10.3 m3
Cart away of surplus excavated materials to a distance of 1- 2kms
13.10.4 m3
Supply and compact approved backfill selected material
13.10.5 Basaltic or equivalent stone masonry wall bedded in cement mortar m3
1:3
13.10.6 m2
Lean concrete in C-15 under masonry wall.
13.10.7 Reinforced concrete slab (C-25) as per the drawing price includes dia, m3
8 bar with a spacing of 200 mesh
13.10.8 Provide, cut and fix in position zigba formwork including soffit and m2
scaffolding for cover slab.
13.10.9 Ls
Supply and install PVC vent pipe with cover cap
13.10.10 No.
Supply and install reinforced precast concrete cover to septic tank.
13.10.11 Supply and put in place coarse gravel, fine gravel and sand depth as Ls
per the drawing
Total to be carried Summary
Prepared By:-
Sub Contractor:________________________________
Y PROJECT
6
6.00 28,000.00 0.00 168,000.00 168,000.00
4
4.00 21,000.00 0.00 84,000.00 84,000.00
4
4.00 24,000.00 0.00 96,000.00 96,000.00
3 6.50 13.2.1 Supply and raise 500 mm thick and 1000mm high
i. Long side ( L=6.5 m ,W = 0.4m, D= 0.75m)
0.40
0.75
5.85 m3
0.11 m3
6.66 m3
9 3.20 13.3.3. Column
0.20
0.20
1.15 m3
13.3.4 Floor slab
1 6.50
6.25
0.10
4.06 m3
Provide and fix formwork for
13.3.6 For beams and Lintels
i. Grade Beams
3 3.90 /Long side/ (Perimeter= 6.5*0.3*2=3.9 m2)
11.70 m 2
56.98 m2
13.3.7 Column
9 2.56 /3.2*0.2*4=2.56m2/
23.04 m2
13.5 Block work
1 6.50
6.25
40.63 m2
13.7.4. plaster in cement mortar to internal cement
concrete blocks, all beams and columns
2 6.30 i. Long side
3.20
40.32 m2
2 6.05 ii. Short side
3.20
38.72 m2
79.04 m2
iv. Deduction
1 1.20 1. Door
2.20
2.64 m2
2 1.00 2. Window
1.00
2.00 m2
1 1.10
1.40
1.54 m2
6.18 m2
72.86 m2 Net area
13.7.5. Apply cement mortar pointing to all external
cement concrete block wall
2 6.50 i. Long side
3.20
41.60 m2
1 6.50
6.25
40.63 m2
13.6.10. Supply and fix ribbed sheet
2 7.50 /Long side/
0.50
7.50 m2
2 6.25 /short side/
0.50
6.25 m2
13.75 m2
13.3.5. Concrete grade C-20 for the drainage ditch and
walkaway
2 6.50 /Long side/
1.60
0.10
2.08 m3
2 6.25 /short side/
1.60
0.10
2.00 m3
4.08 m3
Provide and fix formwork for
13.3.8. Drainage Ditch
2 6.50 Long side
0.60
7.80 m2
2 6.25 short side
0.60
7.50 m2
15.30 m2
13.9. Construction of Septic Tank
13.9.1. Site clearing to depth of 20cm
1 5.60 L= 3.6+2 =5.6m W = 2.1+2=4.1 m
4.10
22.96 m2
13.9.2 Excavation of soil to depth of 2mts. In ordinary
soil
1 4.00
2.50
2.00
20.00 m3
13.9.3 Cart away of surplus excavated materials to a
distance of 1- 2kms
20.00 m3
13.9.4 Supply and Backfill selected material
1 3.60
2.10
0.60
4.54 m3
13.9.5 Basaltic or equivalent stone masonry wall
2 3.60 Long side
1.85
0.45
5.99 m3
2 2.10 short side
1.85
0.45
3.50 m3
9.49 m3
13.9.6 Lean concrete in C-15 under foundation slab.
1 3.60
2.10
7.56 m2
13.9.7 Reinforced concrete slab (C-25) as per the
drawing
1 3.60 Bottom Slab
2.10
0.15
1.13 m3
1 3.60 Top Slab
2.10
0.20
1.51 m3
2.65 m3
1 3.10
3.10
9.61 m2
BILL No.13: CONSTRUCTION OF OPERATORS DWELLING /Main House & Service Quarter/.
Main House/OD/
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
Column 1.00 12 0.25 3.15 0.25
Stirups 2.00 6 0.20 0.30 0.30 0.10
On Axis 1,
2&3 6 0.13 0.30 0.30 0.10
Stirup
On Axis A,
B&C 6 0.13 0.30 0.30 0.10
On Axis 1,
2&3 6 0.13 0.30 0.30 0.10
8 0.05 1.25 0.05
D1
8 0.10 1.25 0.10
8 0.05 0.85 0.05
D2
8 0.10 0.85 0.10
LINTELE
8 0.05 1.34 0.05
W1
8 0.10 1.34 0.10
8 0.05 0.85 0.05
w2
8 0.10 0.85 0.10
D1 6 0.20 0.30 0.20 0.10
D2 6 0.20 0.30 0.20 0.10
Stirup
W1 6 0.20 0.30 0.20 0.10
Stirup
W2 6 0.20 0.30 0.20 0.10
Service Quarter/OD/
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
Column 1.00 12 0.25 2.90 0.25
Stirups 2.00 6 0.20 0.30 0.30 0.10
On Axis A 12 0.15 4.75 0.15
&B 12 0.07 4.75 0.07
Grade Beam
On Axis 1 12 0.15 3.15 0.15
&2 12 0.07 3.15 0.07
On Axis A 12 0.15 4.75 0.15
&B 12 0.07 4.75 0.07
Top tie Beam
On Axis 1 12 0.15 3.15 0.15
&2 12 0.07 3.15 0.07
On Axis A,
B&C 6 0.13 0.30 0.30 0.10
On Axis 1,
2&3 6 0.13 0.30 0.30 0.10
Stirup
On Axis A,
B&C 6 0.13 0.30 0.30 0.10
On Axis 1,
2&3 6 0.13 0.30 0.30 0.10
8 0.05 0.90 0.05
D1 & 2
8 0.10 0.90 0.10
8 0.05 1.15 0.05
LINTELE W1
8 0.10 1.15 0.10
8 0.05 0.95 0.05
w2
8 0.10 0.95 0.10
6 0.20 0.30 0.20 0.10
D1 & 2
Stirup 6 0.20 0.30 0.20 0.10
W2 6 0.20 0.30 0.20 0.10
Prepared By:-
Sub Contractor:________________________________
CT
uarter/.
ngth (m)
Dia Dia Remark
Dia 24
16mm 20mm
ngth (m)
Remark
Dia Dia Remark
Dia 24
16mm 20mm
By:- ____________________