Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 128

CERTIFICATE OF PAYMENT No.

1
Project: Moyale Water Supply project
Client: SRS Irrigation and Development Bureau
Contractor: IQRA General Construction Company
Sub. Contractor: FUREY General Construction

BILL NO. ITEM DESCRIPTION Unit

CONSTRUCTION OF 100 m3 GROUND RC CIRCULAR BOOSTER


BILL 4 1
RESERVIOR

BILL 6 CONSTRUCTION OF GENERATOR HOUSE at Booster station 1

BILL 7 CONSTRUCTION OF BOOSTER STATION PUMP HOUSE 1

CONSTRUCTION OF GUARD HOUSE 100M3 BOOSTER


BILL 8 1
RESERVOIR

BILL 9 CONSTRUCTION OF WATER POINTS 12

Bill 10 CONSTRUCTION OF CATTLE TROUGHS 1

BILL 13 CONSTRUCTION OF OPERATORS DWELLING 1

TOTAL
VAT (15%)
GRAND TOTAL

Prepared By:- Approved By:- _______


Sub Contractor:________________________________ Prime Contractor
Amount

Previous Current Todate

1,447,230.96 216,157.26 1,663,388.22

504,934.49 301,149.84 806,084.33

119,872.00 1,345,716.95 1,465,588.95

361,910.11 28,105.00 390,015.11

1,605,048.14 230,200.50 1,835,248.65

91,030.88 762,705.24 853,736.11

1,344,487.97 848,559.19 2,193,047.16


5,474,514.55 3,732,593.98 9,207,108.53
821,177.18 559,889.10 1,381,066.28
6,295,691.73 4,292,483.08 10,588,174.81

Approved By:- ____________________


Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Client- SMALI REGIONAL STATE IRRIGATION DEVELOPMENT BUREAU
Consultant:- SOMALI , DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
2nd Interim Pay
BILL No. 4: CONSTRUCTION OF 100 m3 BOOSTER STATION RESERVIOR
ITEM DESCRIPTION UNIT

4.1 Earth work


4.1.1 Top soil striping to 200mm depth m2
4.1.2 Foundation excavation in normal soil to a depth not exceeding 1m m3
4.1.3 Ditto but to a depth of 1.5m m3
4.1.4 Extra over for excavation in soft rock m3
4.1.5 Extra over for excavation in hard rock m3
4.1.6 Cartaway all excavated material m3
4.1.7 Selected granular material fill m3
4.1.8 Fill hard core with hard basaltic stone m2
4.2 Concrete Work
4.2.1 70 mm thick C-20 mass concrete m2
4.2.2 Reinforced Concrete(C-30)
a) Base slab m3
b) Concrete Wall m3
4.2.3 230 mm thick roof slab (C-25) m3
4.2.4 C-15 10cm thick concrete paving m2
4.3 Provide and fix steel fomwork to
4.3.1 Wall m2
4.3.2 Soffit of suspended slab m2
4.4 Provide,cut,bend & fix reinforced steel bar.
4.4.1 Diametre 10mm deformed bar Kg
4.4.2 Diametre 12mm deformed bar Kg
4.4.3 Diametre 14mm deformed bar Kg
4.5 Accessories and Finishing
4.5.1 Provide and apply three coat of Plaster to internal walls m2
4.5.2 Rendering to external wall m2
4.5.3 Provide and apply 50 mm cement screed to floor & roof slab m2

4.5.4 Supply and install external water level indicator complete with No
necessary accessories
Supply and fix external galvanised steel (6m) and internal stainless
4.5.5 steel (4.5m) ladder complete with safety cage as per the design to the No
satisfaction of the engineer.
4.5.6 Provide & install uPVC water stops m

4.5.7 Provide and fix 6mm sheet metal 800x800mm access cover with 40x40 no
angle iron frame with latck and lock for valve chamber and reservoir
Vent Pipes no
4.6 Supply and Installation of Pipes, Valves and Fittings
Supply and Install Steel DN200 Inlet pipes, fittings and valves of
4.6.1 PN10 with all required accessories
4.6.1.1 Flanged Bell Mouth No
4.6.1.2 Double Flanged Pipe With Central Puddle L=1.0m No
4.6.1.3 Double Flanged 90 Degree Bend No
4.6.1.4 Double Flanged Short Pipe L=3.34m No
4.6.1.5 Double Flanged 90 Degree Duck Foot Bend No
4.6.1.6 Double Flanged Short Pipe L=0.25m No
4.6.1.7 Double Flanged Gate Valve No
4.6.1.8 Dismantling Piece No
4.6.1.9 Flanged Adapter No
Supply and fix Pipe support including pipe clamp, wall bracket, foot
4.6.1.10 plate and anchor bolts LS
Supply and Install Steel DN200 Outlet pipes, fittings and valves of
4.6.2 PN10 with all required accessories
4.6.2.1 Flanged Suction Strainer No
4.6.2.2 Double Flanged Pipe With Puddle L= 1.0m No
4.6.2.3 Double Flanged Gate Valve No
4.6.2.4 Double Flanged Woltman Water Meter No
4.6.2.5 Dismantling Piece No
4.6.2.6 Double Flanged Short Pipe L=0.25m No
4.6.2.7 Flanged Adapter No
Supply and Install Steel Over Flow and Drainage pipes, fittings
4.6.3 and valves
4.6.3.1 DN65, PN10 Steel Flanged Bell Mouth No
4.6.3.2 DN65, PN10 Steel Double Flanged Pipe With Puddle L=1.42m No
4.6.3.3 DN65, PN10 Steel Double Flanged 90 Degree Bend No
4.6.3.4 DN65, PN10 Steel Double Flanged Short Pipe L=2.92m No
4.6.3.5 DN65/DN65, PN10 Steel All Flanged Tee No
4.6.3.6 DN65, PN10 Steel Flanged Adapter No
4.6.3.7 DN50, PN10 Steel Single Flanged Pipe Short L=0.1m No
4.6.3.8 DN50, PN10 Steel Double Flanged Pipe With Puddle L=1.0m No
4.6.3.9 DN50, PN10 Steel Double Flanged Gate Valve No
4.6.3.10 DN65/DN50, PN10 Steel Double Flanged Eccentric Reducer No
Supply and fix Pipe support including pipe clamp, wall bracket, foot
4.6.3.11 plate and anchor bolts LS

Total for one 100 m3 Reservoir

Prepared By:-
Sub Contractor:________________________________
ROJECT

2nd Interim Payment


R
Quantity Amount in Birr
Previous Current Todate Unit Price Previous Current Todate

80.13 80.13 40.00 3,205.15 0.00 3,205.15


- 540.00 0.00 0.00 0.00
- 640.00 0.00 0.00 0.00
7.73 7.73 950.00 7,343.97 0.00 7,343.97
5.15 5.15 1,100.00 5,669.03 0.00 5,669.03
74.73 74.73 320.00 23,913.01 0.00 23,913.01
18.04 18.04 720.00 12,987.24 0.00 12,987.24
12.88 12.88 535.00 6,893.03 0.00 6,893.03
-
51.54 51.54 280.00 14,430.26 0.00 14,430.26
- 0.00 0.00 0.00
18.04 18.04 7,500.00 135,283.72 0.00 135,283.72
19.64 19.64 7,500.00 147,295.98 0.00 147,295.98
10.16 10.16 7,500.00 76,218.05 0.00 76,218.05
35.06 35.06 7,500.00 262,985.40 0.00 262,985.40
-
165.92 165.92 525.00 87,106.74 0.00 87,106.74
43.88 43.88 525.00 23,037.79 0.00 23,037.79
-
570.69 570.69 135.00 77,043.29 0.00 77,043.29
1,450.41 1,450.41 135.00 195,805.76 0.00 195,805.76
2,517.87 2,517.87 135.00 339,912.54 0.00 339,912.54
- 0.00 0.00 0.00
72.53 72.53 303.00 0.00 21,977.80 21,977.80
78.03 78.03 59.00 0.00 4,603.71 4,603.71
78.35 78.35 290.00 0.00 22,721.75 22,721.75

- 7,500.00 0.00 0.00 0.00


2.00 2.00 12,500.00 0.00 25,000.00 25,000.00
44.22 44.22 3,000.00 0.00 132,654.00 132,654.00

1.00 1.00 3,200.00 0.00 3,200.00 3,200.00


4.00 4.00 1,500.00 0.00 6,000.00 6,000.00
- 0.00 0.00 0.00

- 0.00 0.00 0.00


- 6,200.00 0.00 0.00 0.00
1.00 1.00 16,100.00 16,100.00 0.00 16,100.00
- 14,060.00 0.00 0.00 0.00
- 36,000.00 0.00 0.00 0.00
- 14,060.00 0.00 0.00 0.00
- 4,500.00 0.00 0.00 0.00
- 21,400.00 0.00 0.00 0.00
- 13,050.00 0.00 0.00 0.00
- 9,500.00 0.00 0.00 0.00

- 10,000.00 0.00 0.00 0.00

- 0.00 0.00 0.00


- 20,100.00 0.00 0.00 0.00
1.00 1.00 8,500.00 8,500.00 0.00 8,500.00
- 21,400.00 0.00 0.00 0.00
- 15,000.00 0.00 0.00 0.00
- 13,050.00 0.00 0.00 0.00
- 4,500.00 0.00 0.00 0.00
- 9,500.00 0.00 0.00 0.00

- 0.00 0.00 0.00


- 4,500.00 0.00 0.00 0.00
1.00 1.00 3,500.00 3,500.00 0.00 3,500.00
- 7,500.00 0.00 0.00 0.00
- 7,500.00 0.00 0.00 0.00
- 8,500.00 0.00 0.00 0.00
- 3,200.00 0.00 0.00 0.00
- 3,000.00 0.00 0.00 0.00
- 2,300.00 0.00 0.00 0.00
- 7,800.00 0.00 0.00 0.00
- 6,500.00 0.00 0.00 0.00
- 15,000.00 0.00 0.00 0.00
1,447,230.96 216,157.26 1,663,388.22

Approved By:- ____________________


Prime Contractor
1st Interim Payment
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Client- SMALI REGIONAL STATE IRRIGATION DEVELOPMENT BUREAU
Consultant:- SOMALI , DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:- FUREEY GENERAL CONSTRUCTION
2nd Interim Payment
BILL No. 4: CONSTRUCTION OF 100 m3 BOOSTER STATION RESERVIOR
T D S Unit Description
4.1 Earth work
4.1.1. Top soil stripping to 200cm(Site clearing)
3.142 5.05 radius (R')= 4.05+1 m Π=3.142
5.05
80.13 m2
3.142 4.05 4.1.2. Excavation in normal soil to a depth not exceeding 1m
4.05 radius (R')= 4.05 m Π=3.142

0.00 m3
4.1.3 Ditto but to a depth of 1.5m
3.142 4.05 radius(R')= 4.05 m Π=3.142 d =1.20m
4.05
1.20
61.84 m3
3.142 4.05 4.1.4 Excavation in soft rock
4.05 radius(R')= 4.05 m Π=3.142 d =0.15
0.15
7.73 m3
3.142 4.05 4.1.5 Excavation in hard rock
4.05 radius (R')= 4.05 m Π=3.142 d=0.10
0.10
5.15 m3
4.1.6 Cartawy
74.73 m 3

3.142 4.05 4.1.7 Select material

4.05 radius(R')= 4.05 m Π=3.142 d=0.35 m


0.35
18.04 m3
3.142 4.05 4.18 Hard core
4.05 radius (R')= 4.05 m Π=3.142 d=0.25 m
0.25
12.88 m3
4.2 Concrete work
3.142 4.05 4.2.1. 70 mm thick C-20 mass concrete
4.05 radius(R')= 4.05 m Π=3.142
51.54 m 2

4.2.2 Reinforced Concrete(C-30)


3.142 4.05 a) Base Slab
4.05 radius (R')= 4.05 m Π=3.142 d=0.35 m
0.35
18.04 m3
b) Concrete wall
3.142 3.55 radius External(R)=3.55m, Internal(r)=3.3m, Π=3.142 h=3.65 m
3.30 V=π *((R)2 - (r)2) *h
3.65
19.64 m3
4.2.3 Roof Slab
3.142 3.75 radius( R'' ) = 3.3+0.25+0.2=3.75m Π=3.142 h=0.23 m
3.75 A= π*(R''*R'') * h
0.23
10.16 m3
4.2.4 C-15 10cm thick concrete paving
3.142 5.25 radius Ext.(r'')=4.05+1.20=5.25m, Int.(R')= 4.05m, Π=3.142
4.05 A= π x ((r2xr2)-(r1xr1))
35.06 m2
4.3 Form work
4.3.1 Wall
3.14 4.05 a) To the base slab
0.35 radius (R')= 4.05 m Π=3.142 h =0.35m
8.90 m2 l.s.a=2R'h
b) For shear wall
3.14 3.30 i. Internal radius (r)=3.3m, Π=3.142 h=3.50 m
3.50 (l.s.a=2πrh)
72.53 m2
3.14 3.55 ii. External radius (R)=3.55m, Π=3.142 h=3.50 m
3.50 (l.s.a=2πRh)
78.03 m2
3.14 3.30 iii. Internal/above R.slab/ (l.s.a=2πrh)
0.15 Internal radius (r)=3.3m, Π=3.142 h=0.15 m
3.11 m 2

3.14 3.55 iv.External/above R.slab/ (l.s.a=2πRh)


0.15 External radius (R)=3.55m, Π=3.142 h=0.15 m
3.34 m 2

165.92 m2
4.3.2 Soffit of suspended slab
3.14 3.50 i. Pondo A= π*(R''*R'')
3.50 radius( R''' ) = 3.3+0.2=3.50m Π=3.142
38.47 m 2

3.14 3.75 ii. Sponda (Ls.a=2πR''h)


0.23 radius( R'' ) = 3.3+0.25+0.2=3.75m Π=3.142 h=0.23 m
5.42 m 2

43.88 m2
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR 1st Interim Payment
Sub. Cotractor:- FUREEY GENERAL CONSTRUCTION
100 m3 Ground Reservior Bar Schedule
Bar bending dimensions No. of Total Length (m)
Postion Bar Dia No of Distribute
Bar name or Description C/C L1 S1 S2 Total L bars in Dia Dia Remark
No. (mm) members d length Dia 10mm Dia 12mm Dia 14mm Dia 24
(m) (m) (m) (m) member 16mm 20mm
1.00 12 0.20 0.30 4.13 0.17 4.60 109.00 2.00 21.51 1,001.93
Shear Wall 2.00 10 0.19 21.49 21.49 21.00 1.00 3.88 451.29
3.00 10 0.19 22.56 22.56 21.00 1.00 3.88 473.66
Roof Slab 4.00 14 0.14 1222.51 1.00 1.00 1,222.51
5.00 14 0.17 861.82 1.00 1.00 861.82
Base Slab
6.00 12 0.16 631.42 1.00 1.00 631.42
Total Length (m) 924.945 1,633.35 2,084.33 - - -
Unit Wt./ml 0.617 0.89 1.21 1.58 2.47 3.55
Total Wt. (Kg) 570.691 1,450.41 2,517.87 - - -

Prepared By:- Approved By:- ____________________


Sub Contractor:________________________________ Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Client- SMALI REGIONAL STATE IRRIGATION DEVELOPMENT BUREAU
Consultant:- SOMALI , DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
2nd Interim Payment
BILL No. 6: CONSTRUCTION OF GENERATOR HOUSE
Quantity
Item No. Description Unit
Previous
6.1 Earth Work

6.1.1 Clearing of site to remove top soil to a depth of 200 mm m2


53.76

6.1.2 Excavation for footing and foundation wall m3


7.44
6.1.3 Excavation for floor slab 0.3 m depth m3
9.11

Cart away and deposit excavated surplus material to a distance


6.1.4 m3
not exceeding 1km from site
16.55

6.1.5 Fill 250 mm thick hard core m2


7.59

6.2 Concrete, Masonry and Block Work

Reinforced concrete grade C-25 with minimum cement content


360 kg/m3 cast into formwork and vibrated around
reinforcement bars in

6.2.1 Lean concrete m3

6.2.2 R.C. grade beam m3


0.96
6.2.3 R.C. column and lintels m3
1.02
6.2.4 R.C. top tie beams m 3
0.96
6.2.5 R.C. generator seat m 3
2.25
6.2.6 Mass concrete fill on floor slab m3
5.25
Provide, cut, bend and fix in position reinforced steel bar.
6.3 All according to structural drawing. Price shall include
tying wires

6.3.1 Diameter 6 mm bar kg


104.48

6.3.2 Diameter 10 mm deformed bar kg


232.09
6.3.3 Diameter 12 mm deformed bar kg
233.58
6.4 Stone Masonry
Provide and construct 400 mm thick pointed stone masonry for
6.4.1 m3
Foundation Wall 6.31
6.4.2 Provide, cut and fix formwork to
6.4.3 Grade beam m2 10.24
6.4.4 Tie beam m2
10.24
6.4.5 Generator seat m2
4.50
6.4.6 Column m2 20.48
6.5 Block work

Supply and raise 200mm thick concrete block wall (class A of


6.5.1 m2
the ES CD3.301) with cement mortar mix 1:3
77.32
Supply and raise 150mm thick concrete block wall (class A of
6.5.2 m2
the ES CD3.301) with cement mortar mix 1:3
6.6 Carpentry and Roofing

Supply, assemble and fix in position eucalyptus roof truss


6.6.1 price shall include the application of three coats and external No
anti-termite treatment as per the drawing
8.00
Supply, assemble and fix in position equalyptus Rafters DN
6.6.2 100mm including three coats of anti - termite external m
treatment 40.00
Supply and fix purlin in Zigba wood size 50 x 70 mm nailed
6.6.3 into eucalyptus truss including three coats of anti - termite m
external treatment 100.80

6.6.4 Verticals, diagonals and chords (DN 100mm) m


90.00
Supply and fix roof cover in G-28 mm corrugated galvanized
6.6.5 iron sheet fixed into zigba wood purlin with dome headed m2
galvanized nails (purlin and ridge cover measured separately) 62.59
6.6.6 Supply and fix 25 x 250 mm facia board m

Supply and fix edge gutter formed in G-28 flat galvanized


metal sheet including support brackets 1mm thick shaped steel
6.6.7 plate spaced at a maximum spacing of 1000 mm c/c and fixed m
to purlin - price includes metal primer and two coats of
synthetic enamel paint

Supply and fix 120 x 60 mm G-28 galvanized iron down pipe


6.6.8 including 1mm thick metal support brackets fixed at a m
maximum interval of 1000 mm fixed to walls or columns

6.6.9 Doors and windows as per the drawing

Supply and fix 2.98 x 2 m metal door and three layers of


6.6.10 No
synthetic paint to the frames

6.6.11 Supply and fix 5.4 x 0.63 m metal frame with wires mesh m

Supply and fix 1.4 x 0.9 m metal frame window with 2 mm


6.6.12 thick clear glass and three layers of synthetic paint to the No
frames
Supply and fix 0.78 x 0.9 m metal frame window with 2 mm
6.6.13 thick clear glass and three layers of synthetic paint to the No
frames
Supply and fix 0.9 x 2 m metal door and three layers of
6.6.14 No
synthetic paint to the frames

6.7 Loading & unloading Ramp

6.7.1 Concrete, Masonry and Block Work

6.7.1.1 Mass concrete fill on ramp m3

Provide, cut, bend and fix in position reinforced steel bar. All
6.7.1.2
according to structural drawing. Price shall include tying wires

6.7.1.3 Diameter 10 mm bar kg

Provide and construct 400 mm thick pointed stone masonry for


6.7.1.4 m3
Fuel Tank Seat
6.7.2 Block work
Supply and raise 200mm thick concrete block wall (class A of
6.7.2.1 m2
the ES CD3.301) with cement mortar mix 1:3

6.8 Finishing

Finishing work shall include all surface pre-cleaning, polishing


6.8.1
and cleaning at the end of finishing

Apply three coats of plaster in cement mortar to internal


6.8.2 m2
cement concrete block wall

Apply cement mortar pointing to all external cement concrete


6.8.3 m2
block wall

Apply 3 coats of plastic paint to internal walls and synthetic


6.8.4 m2
paint to metal doors and windows

6.8.5 20 mm cement screed m2

6.9 Electrical Installation

6.9.1 Supply and install the required electrical installation LS

6.10 Miscellaneous
6.10.1 Supply and fix anchor bolt in the R.C. generator seat No
6.10.2 Stone pavement around building m2
TOTAL CARRIED TO SUMMARY

Prepared By:-
Sub Contractor:________________________________
OJECT

2nd Interim Payment

Quantity Amount in Birr


Unit Rate
Current Todate Previous Current Todate

53.76 40.00 2,150.40 0.00 2,150.40

7.44 540.00 4,017.60 0.00 4,017.60

9.11 540.00 4,918.32 0.00 4,918.32

16.55 320.00 5,295.36 0.00 5,295.36

7.59 535.00 4,060.65 0.00 4,060.65

- 0.00 0.00 0.00

1.42 1.42 7,500.00 0.00 10,671.00 10,671.00

0.96 7,500.00 7,200.00 0.00 7,200.00

1.02 7,500.00 7,680.00 0.00 7,680.00


0.96 7,500.00 7,200.00 0.00 7,200.00
2.25 7,500.00 16,875.00 0.00 16,875.00

5.25 7,500.00 39,375.00 0.00 39,375.00


- 0.00 0.00 0.00

104.48 135.00 14,105.08 0.00 14,105.08

232.09 135.00 31,332.25 0.00 31,332.25

233.58 135.00 31,533.24 0.00 31,533.24

- 0.00 0.00 0.00

6.31 3,800.00 23,985.60 0.00 23,985.60

-
10.24 520.00 5,324.80 0.00 5,324.80
10.24 520.00 5,324.80 0.00 5,324.80
4.50 520.00 2,340.00 0.00 2,340.00
20.48 520.00 10,649.60 0.00 10,649.60
- 0.00 0.00 0.00

77.32 630.00 48,711.60 0.00 48,711.60

- 630.00 0.00 0.00 0.00

- 0.00 0.00 0.00

8.00 2,100.00 16,800.00 0.00 16,800.00

40.00 570.00 22,800.00 0.00 22,800.00

100.80 570.00 57,456.00 0.00 57,456.00

90.00 570.00 51,300.00 0.00 51,300.00

62.59 1,350.00 84,499.20 0.00 84,499.20


28.80 28.80 1,200.00 0.00 34,560.00 34,560.00

16.80 16.80 950.00 0.00 15,960.00 15,960.00

9.20 9.20 300.00 0.00 2,760.00 2,760.00

- 0.00 0.00 0.00

1.00 1.00 32,000.00 0.00 32,000.00 32,000.00

5.40 5.40 18,500.00 0.00 99,900.00 99,900.00

1.00 1.00 17,500.00 0.00 17,500.00 17,500.00

1.00 1.00 16,500.00 0.00 16,500.00 16,500.00

- 16,900.00 0.00 0.00 0.00

- 0.00 0.00 0.00

- 0.00 0.00 0.00

- 7,500.00 0.00 0.00 0.00

- 0.00 0.00 0.00

- 135.00 0.00 0.00 0.00

- 3,800.00 0.00 0.00 0.00


- 0.00 0.00 0.00
- 650.00 0.00 0.00 0.00

- 0.00 0.00 0.00

- 0.00 0.00 0.00

68.28 68.28 303.00 0.00 20,688.84 20,688.84

77.32 77.32 150.00 0.00 11,598.00 11,598.00

68.28 68.28 150.00 0.00 10,242.00 10,242.00

37.00 37.00 290.00 0.00 10,730.00 10,730.00

- 0.00 0.00 0.00

- 75,000.00 0.00 0.00 0.00

- 0.00 0.00 0.00


- 950.00 0.00 0.00 0.00
32.80 32.80 550.00 0.00 18,040.00 18,040.00
MMARY 504,934.49 301,149.84 806,084.33

Approved By:- ____________________


Prime Contractor
1st Interim Payment
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Client- SMALI REGIONAL STATE IRRIGATION DEVELOPMENT BUREAU
Consultant:- SOMALI , DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION

BILL No. 6: CONSTRUCTION OF GENERATOR HOUSE


T D S Unit

1 8.40
6.40
53.76 m2

2 7.80
0.50
0.60
4.68 m3
2 4.60
0.50
0.60
2.76 m3
7.44 m3

1 6.60
4.60
0.30
9.11 m3

16.55 m3
1 6.60
4.60
0.25
7.59 m3

2 12.80
0.40
0.05
0.51 m3
1 6.60
4.60
0.03
0.91 m3
1.42 m3

2 7.40
0.20
0.20
0.59 m3
2 4.60
0.20
0.20
0.37 m3
0.96 m3

8 3.20
0.20
0.20
1.02 m3

2 7.40
0.20
0.20
0.59 m3
2 4.60
0.20
0.20
0.37 m3
0.96 m3

1 3
1.5
0.5
2.25 m3
1 7.00
5.00
0.15
5.25 m3

2 7.40
0.40
0.60
3.55 m3
2 4.60
0.50
0.60
2.76 m3
6.31

4 7.40
0.20
5.92 m2
4 5.40
0.20
4.32 m2
10.24 m2

4 7.40
0.20
5.92 m2
4 5.40
0.20
4.32 m2
10.24 m2
2 4.50
0.50
4.50 m2
8 3.20
0.80
20.48 m2
2 7.40
3.20
47.36 m2
2 5.00
3.20
32.00 m2

2 5.40
1.20
6.48 m2

1 3.00
2.20
6.60 m2
2 1.20
0.80
1.92 m2
77.32 m2

2 4
8 No

2 4m
5 no
40 m

2 8.4 m
6.00 no
100.8 m

2 7.50 m
6.00 no
90 m

2 4.89
6.40
62.59 m2

2 7.20
3.20
46.08 m2
2 4.80
3.20
30.72 m2

1 3.00
2.20
6.60 m2
2 1.20
0.80
1.92 m2
68.28 m2

2 7.40
3.20
47.36 m2
2 5.00
3.20
32.00 m2

2 5.40
1.20
6.48 m2

1 3.00
2.20
6.60 m2
2 1.20
0.80
1.92 m2
77.32 m2

2 7.20
3.20
46.08 m2
2 4.80
3.20
30.72 m2

1 3.00
2.20
6.60 m2
2 1.20
0.80
1.92 m2
68.28 m2

1 7.40
5.00
37.00 m2

2 9.40
1.00
18.80 m2
2 7.00
1.00
14.00 m2
32.80 m2

2 8.40
16.80 m
2 6.00
12.00 m
28.80 m

2 8.40
16.80 m
2 4.60
9.20 m

Prepared By:-
Sub Contractor:_______________________
IVIL WORKS OF MOYALE WATER SUPPLY PROJECT
ATE IRRIGATION DEVELOPMENT BUREAU
N & SUPERVISION WORKS INTERPRISE
ONTRACTOR
AL CONSTRUCTION
2nd Interim Payment
OF GENERATOR HOUSE
Description
6.1 Earth work
6.1.1. site clearing

6.1.2. Excavation for footing and foundation wall


1.2.1. Trench Excavation
i. Long side

ii. Short side

6.1.3 Excavation under floor slab 0.3m depth

6.1.4. Cartawy

6.1.5. Fill 250mm thick hard core

6.2. Concrete Work


6.2.1 Lean concrete
6.2.1.1 Lean concrete under massonary
6.2.1.2 Lean concrete above hard core

6.2.2 R.C. grade beam


i. Long side

ii. Short side

6.2.3.Column and lintels

6.2.4 Top tie beams


i. Long side

ii. Short side

6.2.5 R.C. generator seat

6.2.6 Mass concrete fill on floor slab


6.4 Stone Masonry 40cm thick
i. Long side

ii. Short side

6.4.2 Formwork
6.4.3 Grade beam
i. Long side

ii. Short side

6.4.4 Top tie beam


i. Long side

ii. Short side

6.4.5 Generator seat

6.4.6 Column

6.5 Block wall (200mm thick class A)


i. Long side

ii. Short side

iii. Above the top tie beam

iv. Deduction
1. Door

2. Window

Net area of block work


6.6 Carpentry and Roofing
6.6.1 eucalyptus roof truss

6.6.2 Equalyptus Rafters DN 100mm

6.6.3 Purlin in Zigba wood

6.6.4 Verticals, diagonals and chords

6.6.5 Roof cover in G-28


l = 1+ (1.2)2 +(7.4/2)2
6.8. Finishing
6.8.2. Apply three coats of plaster in cement mortar to internal wall
i. Long side

ii. Short side

iv. Deduction
1. Door

2. Window

Net area
6.8.3. Apply pointing to all external cement concrete block wall
i. Long side

ii. Short side

iii. Above the top tie beam

iv. Deduction
1. Door

2. Window

Net area
6.8.4. Apply 3 coats of plastic paint to internal walls
i. Long side
ii. Short side

iv. Deduction
1. Door

2. Window

Net area
6.8.5. 20 mm cement screed

6.10.2. Stone pavement around building


i. Long side

ii. Short side

iii. Above the top tie beam


6.6.6..Supply and fix 25 x 250 mm facia board
i. Long side

ii. Short side

6.6.7. Gutter formed in G-28 flat galvanized metal

6.6.8 G-28 galvanized iron down pipe

Approved By:- ____________________


Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Client- SMALI REGIONAL STATE IRRIGATION DEVELOPMENT BUREAU
Consultant:- SOMALI , DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:- FUREEY GENERAL CONSTRUCTION

Generator House
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
Column 1.00 10 0.10 3.18 0.10
Stirup 2.00 6 0.20
3.00 10 5.16 0.10
4.00 10 5.16 0.07
Grade & Top tie Beam
5.00 10 3.16 0.07
6.00 10 7.16 0.10
7.00 6 0.20
Stirup
8.00 6 0.20
9.00 12 0.15 0.46 2.66 0.46
10.00 12 0.15 2.66
Generator Seat
11.00 12 0.15 0.46 1.46 0.46
12.00 12 0.15 1.46

Prepared By:-
Sub Contractor:________________________________

Bar bending dimensions


Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
13.00 10 0.20
Ramp
14.00 10 0.20
CT

2nd Interim Payment

dimensions No. of Total Length (m)


No of Distribute
Total L bars in
members d length Dia 6mm Dia 8mm Dia 10mm Dia 12mm
(m) member
3.38 4.00 8.00 108.16
0.74 17.00 8.00 3.20 100.64
5.26 2.00 8.00 84.16
5.23 2.00 4.00 41.84
3.23 2.00 4.00 25.84
7.26 2.00 8.00 116.16
0.74 125.00 2.00 24.80 185.00
0.74 125.00 2.00 24.80 185.00
3.58 36.00 1.00 128.88
2.66 36.00 1.00 95.76
2.38 10.00 1.00 23.80
1.46 10.00 1.00 14.60
Total Length (m) 470.640 - 376.160 263.04
Unit Wt./ml 0.222 0.395 0.617 0.89
Total Wt. (Kg) 104.482 - 232.091 233.58

Approved By:- __________


Prime Contractor

dimensions No. of Total Length (m)


No of Distribute
Total L bars in
members d length Dia 6mm Dia 8mm Dia 10mm Dia 12mm
(m) member
3.00 14.00 1.00 2.50 42.00
2.50 16.00 1.00 3.00 40.00
Total Length (m) - - 82.000 -
Unit Wt./ml 0.222 0.395 0.617 0.89
Total Wt. (Kg) - - 50.594 -
ment

tal Length (m)


Remark
Dia 14mm Dia 16mm Dia 20mm Dia 24

- - - -
1.21 1.58 2.47 3.55
- - - -

roved By:- ____________________


me Contractor

tal Length (m)


Remark
Dia 14mm Dia 16mm Dia 20mm Dia 24

- - - -
1.21 1.58 2.47 3.55
- - - -
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION

BILL No. 7: CONSTRUCTION OF BOOSTER STATION PUMP HOUSE

ITEM NO DESCRIPTION UNIT

7.1 Earth Work

7.1.1 Clearing of site to remove top soil to a depth of 200 mm m2

7.1.2 Excavation for foundation wall m3


Cart away and deposit excavated surplus material to a distance not
7.1.3 m3
exceeding 1km from site
Provide, place and compact in layers approved selected granular material
7.1.4 m3
for base slab and column foundation

7.1.5 Fill 250 mm thick hard core m2

7.2 Concrete, Masonry and Block Work


Reinforced concrete grade C-25 with minimum cement content 360 kg/m3
cast into formwork and vibrated around reinforcement bars in
7.2.1 m3
Basement Bottom Slab
7.2.2 Basement Wall m3

7.2.3 Beams m3

7.2.4 Pump seats m3

7.2.5 Footing pad, Stair, Column & lintaile m3

Provide, cut, bend and fix in position reinforced steel bar. All
according to structural drawing. Price shall include tying wires

7.2.6 Diameter 6 mm bar kg

Diameter 8 mm deformed bar kg

7.2.7 Diameter 10 mm deformed bar kg


7.2.8 Diameter 12 mm deformed bar kg

Diameter 14 mm deformed bar kg

Diameter 16 mm deformed bar kg

Stone Masonry

Provide and construct 400 mm thick pointed stone masonry for Foundation
7.2.10 m3
Wall

7.3 Provide, cut and fix formwork to

7.3.1 Grade beam m2

7.3.2 Tie beam m2

7.3.3 Generator seat m2

7.3.4 Column and lintels m2

7.4 Block work


Supply and raise 200mm thick concrete block wall (class A of the ES
7.4.1 m2
CD3.301) with cement mortar mix 1:3
Supply and raise 100mm thick concrete block wall (class A of the ES
7.4.2 m2
CD3.301) with cement mortar mix 1:3
7.5 Carpentry and Roofing

Supply, assemble and fix in position eucalyptus roof truss price shall
7.5.1 include the application of three coats and external anti-termite treatment as No
per the drawing
Supply, assemble and fix in position equalyptus Rafters DN 100mm
7.5.2 m
including three coats of anti - termite external treatment

Supply and fix purlin in Zigba wood size 50 x 70 mm nailed into eucalyptus
7.5.3 m
truss including three coats of anti - termite external treatment

7.5.4 Verticals, diagonals and chords (DN 100mm) m


Supply and fix roof cover in G-28 mm corrugated galvanized iron sheet
7.5.5 fixed into zigba wood purlin with dome headed galvanized nails (purlin and m2
ridge cover measured separately)
7.5.6 Supply and fix 25 x 250 mm facia board m
Supply and fix edge gutter formed in G-28 flat galvanized metal sheet
including support brackets 1mm thick shaped steel plate spaced at a
7.5.7 m
maximum spacing of 1000 mm c/c and fixed to purlin - price includes metal
primer and two coats of synthetic enamel pa

Supply and fix 120 x 60 mm G-28 galvanized iron down pipe including
7.5.8 1mm thick metal support brackets fixed at a maximum interval of 1000 mm m
fixed to walls or columns

Doors and windows as per the drawing


Supply and fix 1.5 x 2 m metal door and three layers of synthetic paint to
7.5.8 No
the frames
Supply and fix 1.2 x 0.9 m metal frame window with 2 mm thick clear glass
7.5.9 No
and three layers of synthetic paint to the frames
Supply and fix 1.0 x 0.9 m metal frame window with 2 mm thick clear glass
7.5.10 No
and three layers of synthetic paint to the frames
7.6 Finishing
Finishing work shall include all surface pre-cleaning, polishing and
cleaning at the end of finishing
Apply three coats of plaster in cement mortar to internal cement concrete
7.6.1 m2
block wall
7.6.2 Apply cement mortar pointing to all external cement concrete block wall m2
Apply 3 coats of plastic paint to internal walls and synthetic paint to metal
7.6.3 m2
doors and windows
7.6.4 20 mm cement screed m2

7.7 Electrical Installation

7.7.1 Supply and install the required electrical installation LS

7.8 Compound Work

7.8.1 Clearing top soil to a depth of 30cm m2


Provide and fill Selected granular excavated fill material and compacted
7.8.2 m3
every 20cm layer to standard proctor density.
Type II barbed wires fencing consists of 2.5 mm barbed wire horizontal and
7.8.3 diagonal member fixed to 2100 mm long concrete posts spaced every m
2000mm, including all necessary material as per the drawing
7.8.4 Supply and construct type II gate as per the drawing No.

7.8.5 Compound lighting as per the drawing LS


7.9 Miscellaneous

7.9.1 Supply and fix anchor bolt in the R.C. generator seat No

7.9.2 Stone pavement around building m2

Total Carried to Summary

Prepared By:-
Sub Contractor:________________________________
OJECT

2nd Interim Payment

Amount in
Quantity
Birr
Previous Current Todate UNIT PRICE Previous Current Todate

150.00 150.00 40.00 6,000.00 0.00 6,000.00

68.20 68.20 540.00 36,828.00 0.00 36,828.00

68.20 68.20 320.00 21,824.00 0.00 21,824.00

44.00 44.00 720.00 31,680.00 0.00 31,680.00

44.00 44.00 535.00 23,540.00 0.00 23,540.00

-
0.00 0.00 0.00

-
0.00 0.00 0.00

-
15.40 15.40 7,500.00 115,500.00 115,500.00

-
8.10 8.10 7,500.00 60,750.00 60,750.00

-
8.64 8.64 7,500.00 64,800.00 64,800.00

-
4.86 4.86 7,500.00 36,450.00 36,450.00

-
4.35 4.35 7,500.00 32,625.00 32,625.00

-
0.00 135.00 0.00 0.00

-
359.00 359.00 135.00 48,464.96 48,464.96

-
155.48 155.48 135.00 20,990.34 20,990.34
-
2,236.62 2,236.62 135.00 301,944.15 301,944.15

-
- 0.00 135.00 0.00 0.00

-
672.70 672.70 135.00 90,814.69 90,814.69

-
0.00 0.00 0.00

-
6.06 6.06 3,800.00 23,028.00 23,028.00

-
0.00 0.00 0.00

-
22.02 22.02 520.00 11,450.40 11,450.40

-
51.75 51.75 520.00 26,910.00 26,910.00

-
11.34 11.34 520.00 5,896.80 5,896.80

-
67.46 67.46 520.00 35,079.20 35,079.20

-
0.00 0.00 0.00

-
106.92 106.92 630.00 67,356.45 67,356.45

-
0.00 630.00 0.00 0.00

-
4.40 4.40 2,200.00 9,680.00 9,680.00

-
173.20 173.20 570.00 98,724.00 98,724.00

-
87.60 87.60 570.00 49,932.00 49,932.00

-
40.20 40.20 570.00 22,914.00 22,914.00

-
78.11 78.11 1,350.00 105,448.50 105,448.50

-
31.80 31.80 1,200.00 38,160.00 38,160.00
-

0.00 950.00 0.00 0.00

-
0.00 300.00 0.00 0.00

-
0.00 0.00 0.00

-
0.00 32,000.00 0.00 0.00

-
0.00 29,500.00 0.00 0.00

-
0.00 29,050.00 0.00 0.00

-
0.00 0.00 0.00

-
0.00 0.00 0.00

-
104.04 104.04 303.00 31,522.61 31,522.61

-
106.92 106.92 150.00 16,037.25 16,037.25

-
0.00 150.00 0.00 0.00

-
41.34 41.34 290.00 11,988.60 11,988.60

-
0.00 0.00 0.00

-
0.00 75,000.00 0.00 0.00

-
0.00 0.00 0.00

-
0.00 40.00 0.00 0.00

-
0.00 720.00 0.00 0.00

-
0.00 11,500.00 0.00 0.00

-
0.00 22,000.00 0.00 0.00

-
0.00 7,050.00 0.00 0.00
-
0.00 0.00 0.00

-
0.00 950.00 0.00 0.00

-
35.00 35.00 550.00 19,250.00 19,250.00

119,872.00 1,345,716.95 1,465,588.95

Approved By:- ____________________


Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
2nd Interim Payment
TAKE OFF SHEET PUMP HOUSE
TAKE OFF SHEET PUMP HOUSE
ITEM L*W*H QTY DESCREPTION
7.1 Earth Work
7.1.1 site clearing to remove the top soil
1 12.00 L= 12 m W = 12.5 m
12.50
150.00 m2
7.1.2 Excavation for footing and foundation wall
1 8.00 L= 8 m W = 5.5 m D= 1.55 m
5.50
1.55
68.20 m3
7.1.3 Cart away
68.20 m3

1 8.00 7.1.4 Selected granular material for base

5.50 L= 8 m W = 5.5 m D= 0.1 m


0.40
17.60 m3
1 8.00 7.1,5 Fill 250 mm thick hard core
5.50 L= 8 m W = 5.5 m
44.00 m2
7.2 Concrete
1 8.00 7.2.1 Basement Bottom Slab
5.50
0.35
15.40 m3
7.2.2 Basement Wall
2 8.00 i. Along Axis 1 & 3
0.30
1.00
4.80 m3
2 5.50 ii. Along Axis A & D
0.30
1.00
3.30 m3
8.10 m3
7.2.3 Beams
2 11.00 i. Grade Beam Along Axis 1 & 3
0.30
0.30
1.98 m3
3 5.50 ii. Grade Beam Along Axis A', A, & D
0.30
0.30
1.48 m3
3 11.00 iii. TTB Along Axis 1, 2 & 3
0.30
0.30
2.97 m3
5 4.90 iv. TTB Along Axis A', A,B, C & D
0.30
0.30
2.21 m3
8.64 m3
3 1.80 7.2.4. Pump Seatings
0.90
1.00
4.86 m3
7.2.5 Footing pad, Stair, Column & lintaile
i. Footing pad
2 1.50
1.50
0.50
2.25 m3
2 2.00 ii. Stair
1.50
0.28
1.68 m3
2 0.30 iii. Foundation Column (C3)
0.30
2.00
0.36 m3
iv. Elevation Column
12 0.30 C1, C2 & C3
0.30
3.60
3.89 m3
1 2.00 v. Lintels
0.20
0.15
0.06 m3
4.35 m3
7.2.10 Stone Masonary
2 2.70 i. Along Axis 1 & 3 b/n Axis A' & A
0.60
3.24 m2
1 4.70 ii. Along Axis A' b/n Axis 1 & 3
0.60
2.82 m2
6.06 m2
7.3. Provide, cut and fix formwork to
1 27.00 7.2.1 Basement Bottom Slab
0.35
9.45 m2
7.2.2 Basement Wall
1 27.00
1.00
27.00 m2
7.2.3 Beams
2 11.00 i. Grade Beam Along Axis 1 & 3
0.60 (two sides)
13.20 m2
3 4.90 ii. Grade Beam Along Axis A', A, & D
0.60
8.82 m2
22.02 m2
3 11.00 iii. TTB Along Axis 1, 2 & 3
0.90 (three sides)
29.70 m2
5 4.90 iv. TTB Along Axis A', A,B, C & D
0.90
22.05 m2
51.75 m2
3 5.40 7.2.4. Pump Seatings
0.70
11.34 m2
7.2.5 Footing pad, Stair, Column & lintaile
i. Footing pad
2 6.00
0.50
6.00 m2
2 7.00 ii. Stair
0.28
3.92 m2
2 2.00 iii. Foundation Column for C3
1.20 (four sides)
4.80 m2
iv. Elevation Column
12 3.60 C1, C2 & C3
1.20 (four sides)
51.84 m2
1 2.00 v. Lintels
0.45 (three sides)
0.90 m2
67.46 m2
7.4.1. Block work
2 8.00 i. Axis 1 & 2
3.60
57.60 m2
ii. Axis A & B
2 5.50
3.60
39.60 m2
2 6.70 ii. Upper Part of top tie beam
1.45
9.72 m2
106.92
Carpentry and Roofing
7.5.1. Lamp sum
7.5.2.Equalyptus Rafters DN 100mm
8 10.70 i. to axis 1, 2 & 3 direction per 0.9m space
85.60 m
12 7.30 ii. to axis A, B & C direction per 1m space
87.60 m
173.20
7.5.3. Purlin in Zigba wood size 50 x 70 mm
12 7.30
87.60 m
7.5.4.Verticals, diagonals and chords (DN100mm)
12 3.35

40.20 m
7.5.5. roof cover in G-28 mm corrugated galvanized
iron sheet
2 10.70
3.65
78.11 m2
7.6 Finishing
7.6.1. plaster in cement mortar to internal cement
concrete block wall
2 7.80 i. Axis 1 & 2
3.60
56.16 m2
ii. Axis A & B
2 5.30
3.60
38.16 m2
2 6.70 ii. Upper Part of top tie beam
1.45
9.72 m2
104.04
7.6.2. pointing to all external cement concrete block
wall
2 8.00 i. Axis 1 & 2
3.60
57.60 m2
2 5.50 ii. Axis A & B
3.60
39.60 m2
2 6.70 ii. Upper Part of top tie beam
1.45
9.72 m2
106.92 m2
7.6.3. Apply 3 coats of plastic paint to internal
walls and synthetic paint to metal doors and
windows
2 7.80 i. Axis 1 & 2
3.60
56.16 m2
ii. Axis A & B
2 5.30
3.60
38.16 m2
94.32
7.6.4. 20 mm cement screed
1 7.80
5.30
41.34 m2
7.9.2. Stone pavement around building
2 10.00 i. Axis 1 & 2
1.00
20.00 m2
ii. Axis A & B
2 7.50
1.00
15.00 m2
35.00 m2
7.5.6. Supply and fix 25 x 250 mm facia board
2 9.20 i. Axis 1 & 2
18.40 m
2 6.70 ii. Axis A & B
13.40 m
31.80 m
ROJECT
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:- FUREEY GENERAL CONSTRUCTION
Pump House Bar Schedule
Bar bending & cut dimensions
Bar Dia
Bar name or Description Postion No. C/C L1 S1 S2
(mm)
(m) (m) (m)

Long S. Y Axis 12 0.20 0.30 1.30 0.30


Basement Wall Along Axis
1&3
Long S. X Axis 10 0.20 0.30 8.00 0.30

Short S. Y Axis 12 0.20 0.30 1.30 0.30


Basement Wall Along Axis
A&D
Short S. X Axis 10 0.20 0.30 1.30 0.30

Long S. 12 0.20 0.30 8.00 0.30


Basement Bottom Slab
Short S. 12 0.20 0.30 5.30 0.30

Short S. With V &


H 16 0.13 0.90 0.80 0.90

Pump Seatings Long S. With V & 16 0.12 0.90 1.70 0.90


H
Only Round H 16 3.40 1.80 0.60

V 16 0.15
Stair
H 16 0.15
Gread Beam Along Axis 1, Long S. 12 0.20 10.95 0.20
2 &3
Stirups of IMB 8 0.20 0.50 0.10 0.70

Gread Beam Along Axis Short S. 12 0.20 5.25 0.20


A', A, & D

Stirups of IMB 8 0.20 0.50 0.10 0.70

TTB Along Axis 1,2 & 3 Long S. 12 0.20 10.95 0.20

Stirups of TTB 8 0.20 1.00 0.10


TTM Along Axis A', Short S. 12 0.20 5.25 0.20
A,B,C & D

Stirups of TTB 8 0.20 0.96 0.20

Footing pad F3 of C3 12 0.20 0.30 1.45 0.30

C1 12 0.24 1.80

Foundation Columns C2 12 0.24 1.80

C3 12 0.60 4.00 0.60

Stirups of FC 8 0.15 0.96 0.20

Elevation Columns C1,2 & 3 12 0.20 3.60


Stirups EC C1,2 & 3 8 0.20 1.00 0.10
Total Length (m)
Unit Wt./ml
Total Wt. (Kg)

Prepared By:-
Sub Contractor:________________________________
T

2nd Interim

cut dimensions Total Length (m)


No. of bars in No of Distribute
Total L members members d length Dia 6mm Dia 8mm Dia 10mm Dia 12mm
(m)

1.90 82.00 2.00 8.00 311.60

8.60 12.00 2.00 1.00 206.40

1.90 54.00 2.00 5.30 205.20

1.90 12.00 2.00 1.00 45.60

8.60 27.00 2.00 5.30 464.40

5.90 41.00 2.00 8.00 483.80

2.60 28.00 3.00 1.70

3.50 9.00 3.00 0.90

5.80 1.00 3.00

3.50 18.00 1.00 1.20

1.50 22.00 1.00 1.50

11.35 4.00 3.00 136.20

1.30 56.00 3.00 11.00 218.40

5.65 4.00 3.00 67.80

1.30 27.00 3.00 5.30 105.30

11.35 4.00 3.00 136.20

1.10 56.00 2.00 11.00 123.20


5.65 4.00 5.00 113.00

1.16 26.00 5.00 4.90 150.80

2.05 18.00 2.00 1.50 73.80

2.04 8.00 12.00 195.84

2.04 8.00 4.00 65.28

5.20 8.00 2.00 83.20

1.16 8.00 2.00 1.00 18.56

3.80 4.00 12.00 182.40


1.10 19.00 14.00 3.60 292.60
Total Length (m) 0.00 908.86 252.000 2,518.72
Unit Wt./ml 0.222 0.395 0.617 0.888
Total Wt. (Kg) - 359.00 155.484 2,236.62

Approved By:- ________


Prime Contractor
2nd Interim Payment

Total Length (m)


Remark
Dia 14mm Dia 16mm Dia 20mm Dia 24

218.40

94.50

17.40

63.00

33.00
- 426.30 - -
1.208 1.578 2.466 3.551
- 672.70 - -

pproved By:- ____________________


ime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
2nd Interim Payment
BILL No. 8: CONSTRUCTION OF GUARD HOUSE AT BOOSTER STATION of 100m3

Quantity
Item No. Item Description Unit
Previous Current
8.1 Earth Work and Excavation
8.1.1 Top soil stripping to 200mm depth m2 16.00
8.1.2 Stripped level to a depth not exceeding 1m m 3
2.64
Trench excavation for stone masonry foundation wall in
8.1.3 normal material to a depth not exceeding 1.5m m3 2.97

8.1.4 Excavation for foundation in soft rock formation m3 1.46


8.1.5 Ditto but in hard rock formation m3 1.09
Filling and compacting at every 15 cm layer selected
8.1.6 granular materials under floor slab m3 1.56

8.1.7 Ditto but around the stone masonry foundation wall m3 1.00

8.1.8 250mm thick hard core well blinded with crushed stone m2 1.32
Disposal of surplus excavated materials as directed by th
8.1.9
engineer
m3 8.17
8.2 Masonry Work
50cm Basaltic or equivalent stone masnory foundation
8.2.1 wall bedded in cement sand mortar of mix ratio 1:3 below m3 1.56
and above NGL
8.3 Concrete Work
50mm thick lean concrete in C-10 under stone masonry
8.8.1
foundation wall
m2 6.25
8.3.2 Ditto but underfloor above the hard core m2 4.00
8.4 Grade C-25 Reinforced concrete
10cm concrete Above the hard core for the floor with dia.
8.4.1 8mm bar mesh on both directions with 15cm c/c m3 5.29

8.4.2 For Grade beams, column, lintels and Top tie beam m3 6.53
8.4.4 Form Work for floor slab, beams, and columns m2 16.4
8.4.5 High yield reinforced steel bars to specification
8.4.5.1 φ10 mm kg 61.206
8.4.5.2 φ6 mm kg 26.107
8.5 Carpentry and Joiney
Truss made eculyptus poles of diam. 8cm for upper and
8.5.1 lower chords and 8cm for vertical and inclined members nr. 6
as per the drawing at 80cm spacing
8.5.2 5x7cm zigba wood purlin as shown in the drawing m 21
8.5.3 G- 28 C.I.S Roof cover m 2
13.23
8.6 Electrical Installation
Light points in thermoplastic conduit of diam.13mm fed
8.6.1 through PVC insulated conductors of 2x2.5mm2 nr

Flush mounting switch points in thermoplastic conduit of


8.6.2 dia 16mm fed through PVC insulated conductors of nr

16A/1P sockets points in thermoplastic conduit of


dia.16mm fed through PVC insulated conductors of
2x2.5mm2 including junction boxes with covers &
8.6.3 nr
insulating screw cap connectors all for flush mounting

Flourescent fittings type philips TMS 022/1181+1xTLD


8.6.4 nr
18 W/840 lamp
4x16mm2 PVC insulated power cable inside dia.32mm
8.6.5 sum
PVC conduit
Distribution board (DB-R2) for flush mounting with
8.6.6 sum
lockable door and accessories
8.6.7 4 pcs of ABB of 10A, 1-ph nr
8.6.8 1 pcs of ABB of 16A, 1-ph nr
8.6.9 3 pc of ABB of 20A, 1-ph nr
8.6.10 3 pc of ACB of 25A, 1-ph nr
8.7 Metal Work
LTZ steel framed doors and windows including as per the
8.7.1 drawings with approved cylinderical lock,hinges and all
necessary asseseries
8.7.1.1 Door of size 1000x2000mm nr. 1.00
8.7.1.2 Window of size 1000x1000mm nr. 1.00
8.8 Wall Works with its Finishing
200mm thick HCB wall bedded in cement sand
8.8.1 m2 23.99
mortar of 1:3 mix ratio
Three coats of plastering in cement sand mortar of 1:3
8.8.2 mix ratio for external and internal surface of wall m2 23.99

8.8.3 30mm thick cement sand screed for the floor m2 5.29
Three coats of Painting of internal and external walls
8.8.4 including beam and column surface with plastic emulsion m2
paint
8.8.5 Painting of metal doors and windows sum 1.00
TOTAL FOR BILL No. 8
Total Carried To Summary one in No.
OJECT

100m3

Quantity Amount in Birr


UNIT
Todate PRICE Previous Current Todate

16.00 540.00 8,640.00 0.00 8,640.00


2.64 540.00 1,428.30 0.00 1,428.30

1,930.50
2.97 650.00 0.00 1,930.50
1.46 450.00 656.10 0.00 656.10
1.09 500.00 546.75 0.00 546.75

1,015.63
1.56 650.00 0.00 1,015.63
1.00 1,460.00 1,460.00 0.00 1,460.00

707.54
1.32 535.00 0.00 707.54

3,674.92
8.17 450.00 0.00 3,674.92
0.00 - 0.00 0.00

5,937.50
1.56 3,800.00 0.00 5,937.50
0.00 - 0.00 0.00

28,125.00
6.25 4,500.00 0.00 28,125.00
4.00 4,500.00 18,000.00 0.00 18,000.00
0.00 - 0.00 0.00

39,675.00
5.29 7,500.00 0.00 39,675.00
6.53 7,500.00 48,975.00 0.00 48,975.00
16.40 7,500.00 123,000.00 0.00 123,000.00

61.21 135.00 8,262.86 0.00 8,262.86


26.11 135.00 3,524.47 0.00 3,524.47
12,600.00
6.00 2,100.00 0.00 12,600.00
21.00 570.00 11,970.00 0.00 11,970.00
13.23 1,350.00 17,860.50 0.00 17,860.50

-
0.00 2,750.00 0.00 0.00

-
0.00 650.00 0.00 0.00

0.00 3,200.00 0.00 0.00

-
0.00 2,800.00 0.00 0.00

-
0.00 15,000.00 0.00 0.00

-
0.00 4,000.00 0.00 0.00
0.00 1,800.00 - 0.00 0.00
0.00 1,800.00 - 0.00 0.00
0.00 1,800.00 - 0.00 0.00
0.00 1,800.00 - 0.00 0.00
0.00 - 0.00 0.00

-
0.00 0.00 0.00
1.00 15,000.00 - 15,000.00 15,000.00
1.00 13,000.00 - 13,000.00 13,000.00
0.00 - 0.00 0.00

15,115.91
23.99 630.00 0.00 15,115.91

7,270.03
23.99 303.00 0.00 7,270.03
5.29 290.00 1,534.10 0.00 1,534.10

-
0.00 85.00 0.00 0.00
1.00 105.00 - 105.00 105.00
361,910.11 28,105.00 390,015.11
361,910.11 28,105.00 390,015.11
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
2nd Interim Payment
BILL No. 8: CONSTRUCTION OF GUARD HOUSE AT BOOSTER STATION of 100m3
T D S Unit Description
8.1 Earth work
8.1.1. site clearing
1 4.00
4.00
16.00 m2
2 2.30 8.1.3 Excavation to a depth not
2.30 exceeding 1m
0.25
2.64 m3
2 5.40 8.1.3. .Trench Excavation
0.50
0.55
2.97 m3
1 2.70 8.1.4 Excavation in soft rock
2.70
0.20
1.46 m3
1 2.70 8.1.5. Excavation in hard rock
2.70
0.15
1.09 m3
8.1.6.Filling and compacting with
select
1 2.50
2.50
0.25
1.56 m3
2 5.00 8.1.7 Ditto but around the stone
0.40 masonry foundation wall
0.25
1.00 m3
1 2.30 8.1.8 250mm thick hard core
2.30
0.25
1.32 m3
8.1.9 Disposal of surplus
8.17 m3
8.2 Masonary Work
4 2.50 8.2.1 50cm Basaltic stone masnory
0.40
0.40
1.56 m3
8.3 Concrete Work
1 2.50 8.3.1 50mm thick lean concrete
2.50 (under the masonary foundation)
6.25 m2
8.3.2 Ditto but under floor
2 5.00 above the hard core
0.40
4.00 m2
8.4 Grade C-25 Reinforced concrete
8.4.1 10cm concrete
1 2.30
2.30
5.29 m2
4 2.50 8.4.2 concrete work for,
0.20 I. Grade beam
0.20
0.40 m3
4 2.50 ii. Column
0.20
0.20
0.40 m3
2 1.00 iii. Lintels
0.20
0.10
0.04 m3
4 2.50 Iv. Top tie beam
0.20
0.20
0.40 m3
6.53 m3
8.4.4 Form Work for
8 2.5 I. Grade beam
0.2
4 m2
ii. Column
16 2.5
0.2
8 m2
4 1 iii. Lintels
0.1
0.4 m2
8 2.5 Iv. Top tie beam
0.2
4 m2
16.4 m2
8.5 Carpentry and Joiney
8.5.1 Truss made eculyptus poles
6 nr
7 3 8.5.2 5x7cm zigba wood purlin a
21 m

2 3.5 6.5.3 G- 28 C.I.S Roof cover


1.89
13.23 m2
8.8 Wall Works with its Finishing
4 2.5 8.8.1 200mm thick HCB wall
2.5 I. walls below top tie beam
25 m 2

2 2.50 ii. abovethe top tie beam


0.95
2.38 m2
Deduction
1 2.00 1. Door
1.00
2.00 m2
1 1.54 2. Window
0.90
1.38 m2
23.99 m2 Net area of block work
8.8.2 Plastering
2 2.05
4.1 m2

8.8.3 30mm thick cement screed for


1 2.3 the floor
2.3
5.29 m2

Prepared By:- Approved By:- ____________________


Sub Contractor:_______________________Prime Contractor
PROJECT

N of 100m3
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION

Guard House
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
Column 1.00 10 0.15 2.50 0.15
Stirup 2.00 6 0.20
Grade Beam 3.00 10 0.15 2.50 0.15
Top tie Beam 4.00 10 0.15 2.50 0.15
Stirup 5.00 6 0.20
Lintels 6.00 10 0.10 1.00 0.10

Prepared By:-
Sub Contractor:________________________________
2nd Interim Payment

dimensions No. of Total Length (m)


No of Distribute
Total L bars in
members d length Dia 6mm Dia 8mm Dia 10mm Dia 12mm
(m) member
2.80 4.00 4.00 44.80
0.70 14.00 4.00 2.50 39.20
2.80 2.00 4.00 22.40
2.80 2.00 4.00 22.40
0.70 14.00 8.00 2.50 78.40
1.20 4.00 2.00 9.60
Total Length (m) 117.600 - 99.200 -
Unit Wt./ml 0.222 0.395 0.617 0.89
Total Wt. (Kg) 26.107 - 61.206 -

Approved By:- _________


Prime Contractor
Total Length (m)
Remark
Dia 14mm Dia 16mm Dia 20mm Dia 24

- - - -
1.21 1.58 2.47 3.55
- - - -

Approved By:- ____________________


Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
2nd Interim Payment
BILL No. 9: CONSTRUCTION OF WATER POINT

Quantity
Item No. Item Description Unit
Previous

Earth work
9.1

Site clearing up to adepth of 20cm to remove top vegitative soil


9.1.1 m2 41.48

Excavation work up to a depth of 50 cm to reduce level for placing


9.1.2 hard core m3 9.84

Excavation in soft rock formation


9.1.3 m3 1.18

Ditto but in hard rock farmation


9.1.4 m3 0.98

cart away surplus excavated material to a distance not exceeding


9.1.5 1kmfrom the site m3 9.84

Filling and spread under hard core with selected site material &
compact in layers not exceeding to a thickness of 15cm as per the
9.1.6 recommendation of the supervising Engineer m3 4.92

Masonry work
9.2

25 cm thick basaltic or equivalent stone Hard core well rolled,


9.2.1 consolidated & blinded with crushed stone m2 19.68

Hard stone masonry work for foundation bedded with cemement


9.2.2 sand mortar 1:3 in ratio m3 1.56

Hard stone masonry work for stand bedded with cemement sand
9.2.3 mortar 1:3 in ratio m3 0.22
15 cm wide dressed stone open channel drainage to soak away pit
9.2.4 m2 3.96

9.3 Concrete work

15cm thick mass concrete over hard core as shown in the drawing
9.3.1 m2 14.70

pointening of the masonary stand


9.3.2 m2 5.91

cement screeding
9.3.3 m2 2.60

Provide,cut,bend and fix in position 10mm reinforced steel bar for


9.4 foundation @200mm c/c in both direction for top and bottom
mesh.price shall include tying wires

Diameter 10mm ribbed bar


9.4.1 kg
96.75
supply and install the required pipes,fittings,gate,water han,water
9.4.2 meter and other fitttingss as per the drawing LS
1.00
Fencing and Gate Work
9.5

Excavation for foundation of posts for fencing, dimensions 50 x 50 x


9.5.1 70cm including disposal of surplus material m3

Supply & fix mesh wire up to a height not less than 2.50m, fixed to the
9.5.2 concrete poles by caped including all necessary fixing materials. m

Supply & installation precasted concrete poles 13X13cm for fencing,


9.5.3 length 3m fixed at 2m interval Pcs

Cyclopean concrete work for foundation of fencing Poles


9.5.4 m3

Supply and fix (2x2m)double leaf grilled size gate made of 60x60mm
9.5.5 RHS frame of thickness 10mm nr

Drainage system and water disposal


9.6

Supply & installation of mesh wire of height not less than


9.6.1 2.20meter ,tied to the posts by tying wires, including all necessary m2
fixing materials
Stone pitched trapizoidal drainage ditch pointed with mortar (1:3) (top
width=40cm,bottom width =20cm and depth=30cm)around the public
9.6.2 tap as per the drawing m

Supply and instalaltion of HDPE 75PN10pipe for connections to water


9.7 points from the new pipe m

Total for Bill No 7

Grand Total of 2 water points

Carried to Summary

Prepared By:-
Sub Contractor:________________________________
T

2nd Interim Payment

Quantity Amount in Birr


Unit Price
Current Todate Previous Current Todate

41.48 82.96 40.00 1659.2 1,659.20 3,318.40

9.84 19.68 540.00 5313.6 5,313.60 10,627.20

1.18 2.3616 800.00 944.64 944.64 1,889.28

0.98 1.968 950.00 934.8 934.80 1,869.60

9.84 19.68 680.00 6691.2 6,691.20 13,382.40

4.92 9.84 260.00 1279.2 1,279.20 2,558.40

19.68 39.36 3,500.00 68880 68,880.00 137,760.00

1.56 3.12 1,700.00 2652 2,652.00 5,304.00

0.22 0.45 1,600.00 360 360.00 720.00


3.96 7.92 650.00 2574 2,574.00 5,148.00

0.98 15.684 1,360.00 19992 1,338.24 21,330.24

5.91 11.82 90.00 531.9 531.90 1,063.80

2.60 5.2 320.00 832 832.00 1,664.00

96.75 193.4912 120.00 11609.472 11,609.47 23,218.94

1.00 2 9,500.00 9500 9,500.00 19,000.00

0 230.00 0 0.00 0.00

0 1,200.00 0 0.00 0.00

0 1,150.00 0 0.00 0.00

0 3,989.00 0 0.00 0.00

0 1,615.00 0 0.00 0.00

0 650.00 0 0.00 0.00


0 453.00 0 0.00 0.00

0 467.00 0 0.00 0.00

133,754.01 115,100.25 248,854.26

1,605,048.14 230,200.50 1,835,248.65

1,605,048.14 230,200.50 1,835,248.65

Approved By:- ____________________


Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRIS
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
2nd Interim Payment
BILL No. 9: CONSTRUCTION OF WATER POINT
T D S Unit Description
9.1 Earth work
9.1.1. site clearing
1 6.10
6.80
41.48 m2
1 4.10 9.1.2. Excavation
4.80
0.50
9.84 m3

1 4.10 9.1.3.Excavation in soft rock


4.80
0.06
1.18 m3

1 4.10 9.1.4.Excavation in hard rock


4.80
0.05
0.98 m3
9.1.5. Cartawy
9.84 m 3

1 4.10 9.1.6. Select material


4.80
0.25
4.92 m3

9.2 Massonary

1 4.10 9.2.1. hard core


4.80
19.68 m2
9.2.2 Hard stone massonary
/Foundation bedded or Lower
1 1.30 part/
0.60
2.00
1.56 m3
1 0.30 9.2.3 Hard stone massonary
0.75 /Stand bedded or Uper part/
1.00
0.22 m3
9.2.4. Open Channel Drainage
1 19.80
0.20
3.96 m2
9.3 Concrete Work
9.3.1.
Lean concrete under
1 4.10 massonary
4.80
0.05
0.98 m3
15cm thick RC concrete
1 3.50
4.20
14.70 m2
9.3.2. Pointing of the
2 3.30 Massonary Stand
0.60 Lower part
3.96 m2
2 1.30 Uper part
0.75
1.95 m2
Sum 5.91 m2

9.3.3 cement screeding


1 1.30
2.00
2.60 m2

Prepared By:- Approved By:- ____________________


Sub Contractor:_______________________Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUP
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
2nd Interim Payment
Water point
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
1.00 10 0.20 3.50
Foundation baded Slab
2.00 10 0.20 4.20

Prepared By:-
Sub Contractor:________________________________
dimensions No. of Total Length (m)
No of Distribute
Total L bars in
members d length Dia 6mm Dia 8mm Dia 10mm Dia 12mm
(m) member
3.50 22.00 1.00 4.20 77.00
4.20 19.00 1.00 3.50 79.80
Total Length (m) - - 156.800 -
Unit Wt./ml 0.222 0.395 0.617 0.89
Total Wt. (Kg) - - 96.746 -

Approved By:- ______________


Prime Contractor
Total Length (m)
Remark
Dia 14mm Dia 16mm Dia 20mm Dia 24

- - - -
1.21 1.58 2.47 3.55
- - - -

Approved By:- ____________________


Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION

BILL No.10: CONSTRUCTION OF CATTLE TROUGHS OF CAMEL


CONSTRUCTION OF CATTLE TROUGHS

Item No. Item Description Unit

Earth work
10.1

Site clearing up to adepth of 20cm to remove top vegitative soil


m2
10.1.1
Excavation work up to a depth of 50 cm to reduce level for placing hard
core m3
10.1.2
Excavation in soft rock formation
10.1.3 m3

Ditto but in hard rock farmation


10.1.4 m3

cart away surplus excavated material to a distance not exceeding


10.1.5 1kmfrom the site m3

Filling and spread under hard core with selected site material & compact
in layers not exceeding to a thickness of 15cm as per the
recommendation of the supervising Engineer m3

10.1.6

10.1.7 Had core m3


10.2 Concrete Work
10.2.1 70 mm thick C-20 mass concrete m2
102.2 Reinforced Concrete(C-30)
a)Base slab m3
b)Concrete Wall m3
Hard stone masonry pavment work arround the shear wall 2m
wide bedded with cemement sand mortar 1:3 in ratio m2
10.3
10.4 Provide and fix steel fomwork to
bottom slab & Wall m2
10.5 Provide,cut,bend & fix reinforced steel bar.
Diametre 8mm deformed bar Kg
10.6 Supply and installation of all pipe works as per the standard drawings ls

Total for Bill No 8


Grand Total of 2 cattle troughs Carried to Summary

CONSTRUCTION OF CATTLE TROUGH OF GOAT

Item No. Item Description Unit

10.1 Earth work


10.1.1 Site clearing up to adepth of 20cm to remove top vegitative soil m2
Excavation work up to a depth of 50 cm to reduce level for placing hard
m3
10.1.2 core
10.1.3 Excavation in soft rock formation m3
10.1.4 Ditto but in hard rock farmation m3
cart away surplus excavated material to a distance not exceeding
10.1.5 1kmfrom the site m3
Filling and spread under hard core with selected site material & compact
in layers not exceeding to a thickness of 15cm as per the m3
10.1.6 recommendation of the supervising Engineer

10.1.7 Had core m3


10.2 Concrete Work
10.2.1 70 mm thick C-20 mass concrete m2
102.2 Reinforced Concrete(C-30)
a)Base slab m3
b)Concrete Wall m3
Hard stone masonry pavment work arround the shear wall 2m
wide bedded with cemement sand mortar 1:3 in ratio m2
10.3
10.4 Provide and fix steel fomwork to
bottom slab & Wall m2
10.5 Provide,cut,bend & fix reinforced steel bar.
Diametre 8mm deformed bar Kg
10.6 Supply and installation of all pipe works as per the standard drawings ls

Total for Bill No 8


Grand Total of 1 cattle troughs Carried to Summary
Summary

Prepared By:-
Sub Contractor:________________________________
PROJECT

2nd Interim Payment


OF CAMEL

Quantity Amount in Birr


Unit Price
Previous Current Todate Previous Current Todate

188.50 188.50 40.00 7540 0.00 7,540.00

113.10 113.10 550.00 62205 0.00 62,205.00

1.00 1.00 850.00 850 0.00 850.00

0.88 0.88 1,100.00 962.5 0.00 962.50

114.98 114.98 65.00 7473.375 0.00 7,473.38

18.75 18.75 640.00 12000 0.00 12,000.00

91,030.88 0.00 91,030.88


15.63 15.63 641.00 0 10,015.63 10,015.63
0
62.50 62.50 280.00 0 17,500.00 17,500.00
0.00 0 0.00 0.00
8.62 8.62 7,500.00 0 64,687.50 64,687.50
7.18 7.18 7,500.00 0 53,838.75 53,838.75

250.00 250.00 250.00 0 62,500.00 62,500.00


64.69 64.69 525.00 0 33,962.25 33,962.25

529.78 529.78 135.00 0 71,520.56 71,520.56


1.00 1.00 19,000.00 0.00 19,000.00 19,000.00
0.00 333,024.68 333,024.68
91,030.88 333,024.68 424,055.56
91,030.88 333,024.68 424,055.56

Quantity Amount in Birr


Unit Price
Previous Current Todate Previous Current Todate

188.50 188.50 40.00 0 7,540.00 7,540.00

113.10 113.10 550.00 0 62,205.00 62,205.00


1.00 1.00 850.00 0 850.00 850.00
0.88 0.88 1,100.00 0 962.50 962.50

114.98 114.98 65.00 0 7,473.38 7,473.38

18.75 18.75 640.00 0 12,000.00 12,000.00


0.00 91,030.88 91,030.88
15.63 15.63 641.00 0 10,015.63 10,015.63
0
62.50 62.50 280.00 0 17,500.00 17,500.00
0.00 0 0.00 0.00
9.38 9.38 7,500.00 0 70,312.50 70,312.50
7.18 7.18 7,500.00 0 53,838.75 53,838.75

250.00 250.00 250.00 0 62,500.00 62,500.00

64.69 64.69 525.00 0 33,962.25 33,962.25

529.78 529.78 135.00 0 71,520.56 71,520.56


1.00 1.00 19,000.00 0.00 19,000.00 19,000.00
0.00 338,649.68 338,649.68
0.00 429,680.56 429,680.56
0.00 429,680.56 429,680.56
Previous Current Todate
91,030.88 762,705.24 853,736.11

Approved By:- ____________________


Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION
2nd Interim Payment
BILL No.10: CONSTRUCTION OF CATTLE TROUGHS OF CAMEL
T D S Unit Description
10.1 Earth work
10.1.1. site clearing
1 6.50
29.00
188.50 m2
1 6.50 10.1.2. Excavation
29.00
0.60
113.10 m3
1 2.50 10.1.3.Excavation in soft rock
25.00
0.02
1.00 m3
1 2.50 10.1.4.Excavation in hard rock
25.00
0.01
0.88 m3
10.1.5. Cartawy
114.98 m 3

1 2.50 10.1.6. Select material


25.00
0.30
18.75 m3
10.1.7 hard core
1 2.50
25.00
0.25
15.63 m3

10.2 Concrete Work


1 2.50 10.2.1 Lean concrete
25.00
62.50 m2
10.2.2'Reinforced Concrete(C-30)
1 2.50 a)Bottom slab
25.00
0.15
9.38 m3
b) Shear wall
2 0.20 i. Left & Right long side
0.35
25.00
3.50 m3
1 0.40 ii. centeral side of long side
0.35
25.00
3.50 m3
4 0.85 i. Left & Right side of Short side
0.35
0.15
0.18 m3
SUM 7.18 m3
10.3 Stone masonry pavment work arround the
cattle trough 2m wide bedded with cemement
sand mortar 1:3 in ratio

2 50
2.5
250 m2
10.4 Form work
Sear wall & bottom slab
2 25 i. Outer long side wall & bottom slab
0.5
25.00 m2
2 2.5 ii. Outer short side wall & bottom slab
0.5
2.5 m2
4 25 iii. Inner long side of wall
0.36
36 m2
4 1.7 iv. Inner short side of wall
0.35 A=1/2(b1+b2)*h
1.19 m2
64.69 m2

Prepared By:- Approved By:- ____________________


Sub Contractor:____________________ Prime Contractor
25

0.3
0.15 0.95

0.5 0.36
0.25 0.75 0.5

2.5
PROJECT

BILL No.10: CONSTRUCTION CATTLE TROUGHS OF GOAT


T D S Unit

1 6.50
29.00
188.50 m2
1 6.50
29.00
0.60
113.10 m3
1 2.50
25.00
0.02
1.00 m3
1 2.50
25.00
0.01
0.88 m3

114.98 m3
1 2.50
25.00
0.30
18.75 m3

1 2.50
25.00
0.25
15.63 m3

1 2.30
25.00
57.50 m2

1 2.30
25.00
0.15
8.62 m3

2 0.20
0.25
25.00
2.50 m3
1 0.40
0.25
25.00
2.50 m3
4 0.85
0.25
0.15
0.13 m3
SUM 5.13 m3

2 27
2
108 m2
1 2.3
2
4.6 m2
112.6

2 25
0.4
20.00 m2
2 2.5
0.4
2 m2
4 25
0.25
25 m2
4 1.7
0.25
0.85 m2
47.85 m2

0.15
TRUCTION CATTLE TROUGHS OF GOAT
Description
10.1 Earth work
10.1.1. site clearing

10.1.2. Excavation

10.1.3.Excavation in soft rock

10.1.4.Excavation in hard rock

10.1.5. Cartawy

10.1.6. Select material

10.1.7 hard core

10.2 Concrete Work


10.2.1 Lean concrete
10.2.2'Reinforced Concrete(C-30)
a)Bottom slab

b) Shear wall
i. Left & Right long side

ii. centeral side of long side

i. Left & Right side of Short side

10.3 Stone masonry pavment work arround the


cattle trough 2m wide bedded with cemement
sand mortar 1:3 in ratio

10.4 Form work


Sear wall & bottom slab
i. Outer long side wall & bottom slab

ii. Outer short side wall & bottom slab

iii. Inner long side of wall


iv. Inner short side of wall
A=1/2(b1+b2)*h
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION

1&4 2

Cuttle Trough
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)

1.00 8 0.20 1.20 2.45 0.82

Section A-A
2.00 8 0.20 0.60 1.12 0.16
3.00 8
4.00 8 0.20 1.18 24.90 1.20
Section B-B
5.00 8

Prepared By:-
Sub Contractor:________________________________
CT

2nd Interim Payment

dimensions No. of Total Length (m)


No of Distribute
Total L bars in
members d length Dia 6mm Dia 8mm Dia 10mm Dia 12mm
(m) member

4.47 126.00 1.00 25.00 563.22

1.88 126.00 1.00 25.00 236.88


2.45 4.00 1.00 9.80
27.28 14.00 1.00 2.50 381.92
24.90 6.00 1.00 149.40

Total Length (m) - 1,341.220 - -


Unit Wt./ml 0.222 0.395 0.617 0.89
Total Wt. (Kg) - 529.782 - -

Approved By:- ____________


Prime Contractor
Total Length (m)
Remark
Dia 14mm Dia 16mm Dia 20mm Dia 24

33 berga

28 berga

- - - -
1.21 1.58 2.47 3.55
- - - -

Approved By:- ____________________


Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION

BILL No.13: CONSTRUCTION OF OPERATORS DWELLING /Main H & Service Quarter/

Item No. Description Unit


13.1 Earth Work

13.1.1 m2
Clearing of site to remove top soil to a depth of 200 mm
13.1.2 m3
Excavation for stone masonry foundation; 0.6m width and 1.0 m depth
13.1.3 m3
Backfill to depth of not less than 450mm
13.1.4 Cart away and deposit excavated surplus material to a distance not m3
exceeding 1km.
13.1.5 Supply, fill and compact layer by layer of selected material m3

13.1.6 Provide and fill hard core with hard basaltic or equivalent stone, well m2
compacted and blinded with crushed stone to a finished thickness of
25 cm
13.2 Masonry Work
Supply and raise 500 mm thick and 1000mm high trachitic or
13.2.1 equivalent stone masonry foundation wall below ground level bedded m3
in cement mortar mix 1:3
13.3
Concrete Work
13.3.1 m2
Provide 50mm thick lean concrete with mix ratio (1:3:6)
Reinforced concrete grade C-25 with minimum cement content 360
kg/m3 cast into formwork and vibrated around reinforcement bars
in:price shall include form work
13.3.2 For beams and Lintels m3
13.3.3 For columns m3
Mass concrete fill on floor slab (100mm)
13.3.4 m3

13.3.5 m3
Concrete grade C-20 for the drainage ditch and walkaway

Provide and fix formwork for


13.3.6 m2
For beams and Lintels
13.3.7 m2
For columns
Drainage Ditch
13.3.8 m2
Provide, cut, bend and fix in position reinforced steel bar. All
13.4 according to structural drawing. Price shall include tying wires
Diameter 6 mm reinforcement bar
13.4.1 kg
Diameter 8 mm reinforcement bar
13.4.2 kg
Diameter 12 mm reinforcement bar
13.4.3 kg
Diameter 14 mm reinforcement bar
13.4.4 kg
Block work
13.5
Supply and raise 200mm thick concrete block (class B of the ES
13.5.1 CD3.301) wall laid in cement mortar mix 1:3 m2
Roofing and Carpentry
13.6
Supply, assemble and fix in position Φ120 mm eucalyptus top and
13.6.1 bottom roof truss member, price shall include the application of three m
coats and external anti-termite treatment as per the drawing

Supply, assemble and fix in position Φ80 mm eucalyptus bracing roof


13.6.2 truss member, price shall include the application of three coats and m
external anti-termite treatment as per the drawing

Supply and fix purlin in zigba wood size 50 x 70 mm nailed into


13.6.3 eucalyptus truss including three coats of anti - termite external m
treatment
Supply and fix roof cover in G-28 mm corrugated galvanized iron
13.6.4 sheet fixed into zigba wood purlin with dome headed galvanized nails m2
(purlin and ridge cover measured separately)

Supply and fix edge gutter formed in G-28 flat galvanized metal sheet
including support brackets 1mm thick shaped steel plate spaced at a
13.6.5 maximum spacing of 1000 mm c/c and fixed to purlin - price includes m
metal primer and two coats of synthetic enamel paint

Supply & fix diameter 100mm down pipe in G-30 including 1mm
13.6.6 thick metal support brackets fixed at a maximum interval of 1000 mm m
fixed to walls or columns
Supply and fix 25 x 250 mm fascia board to purlin
13.6.7 m
Supply and fix 40 x 50 mm ceiling battons
13.6.8 m
Supply and fix chipwod ceiling
13.6.9 m2
Supply and fix ribbed sheet
13.6.10 m2
Supply and fix metal door size 900 x 2200 mm price includes 4mm
13.6.11 thick glass and three layers of synthetic paint to the frames No
Supply and fix wooden door size 900 x 2200 mm price includes
13.6.12 scynthetic paintings No
Supply and fix metal door size 800 x 2200 mm price includes 4mm
13.6.13 thick glass and three layers of synthetic paint to the frames No
Supply and fix metal door size 700 x 2100 mm price includes 4mm
13.6.13 thick glass and three layers of synthetic paint to the frames No
Supply and fix metal window size 1000 x 1000 mm price includes
13.6.15 4mm thick glass and three layers of synthetic paint to the frames No
Supply and fix metal window size 1200 x 1400 mm price includes
13.6.16 4mm thick glass and three layers of synthetic paint to the frames No
Supply and fix metal window size 750 x 500 mm price includes 4mm
13.6.17 thick glass and three layers of synthetic paint to the frames No

13.7 Finishing
Finishing work shall include all surface pre-cleaning, polishing and
cleaning at the end of finishing
Floor screed in cement mortar 20 mm thick
13.7.1 m2
Plastic tile floor finish for the main house
13.7.2 m2
Ceramic tile floor and wall finish for the service quarter
13.7.3 m2
Apply three coats of plaster in cement mortar to internal cement
13.7.4 concrete blocks, all beams and columns m2
Apply cement mortar pointing to all external cement concrete block
13.7.5 wall m2
Apply 3 coats of plastic paint to internal walls
13.7.6 m2

13.8 Electrical Installation

Sub-Distribution board for operators dwelling


1 pcs Main MCB of 10A/1P, Icu=6kA
13.8.1 no
2pcs MCB of 16A/1P, Icu=6kA
13.8.2 no
1pcs MCB of 63A/3P, Icu=25kA
13.8.3 no
With 25% reserve space
13.8.4 No

13.8.5
Light Fitting and Lamps
TMS 012/1.36 or 1X36w Fluorescent
13.8.6 No
TMS 095/1.36 or 1X36w Fluorescent
13.8.7 No

13.8.8
Sockets and Switch Outlets
16A/1P socket outlet points
13.8.9 No
25A/1P socket outlet points
13.8.10 NO
wall mounted single pole switch
13.8.11 NO
wall mounted 2 pole switch
13.8.12 NO

Pvc Pipe
PVC conduit of 16mm diameter including junction boxes with covers
13.8.13 and insulating screw cap connectors. M
PVC conduit of 20mm diameter including junction boxes with covers
13.8.13 and insulating screw cap connectors. M

Electrical Wires and Cables


PVC insulated copper cables of 2x2.5mm2 for lighting
13.8.15 M
PVC insulated copper cables of 3x2.5mm2 for socket outlet
13.8.16 M
PVC insulated copper cables of 3x4mm2 for stove socket outlet
13.8.17 M

Installation cost for Operators Dwelling


sub distribution board
13.8.18 points
socket installation
13.8.19 points
switches and corresponding lighting bulb
13.8.20 points

13.9 Construction of Septic Tank


13.9.1 m2
Site clearing to depth of 20cm
13.9.2 m3
Excavation of soil to depth of 2mts. In ordinary soil
13.9.3 m3
Cart away of surplus excavated materials to a distance of 1- 2kms
13.9.4 m3
Supply and compact approved backfill selected material
13.9.5 Basaltic or equivalent stone masonry wall bedded in cement mortar m3
1:3
13.9.6 m2
Lean concrete in C-15 under foundation slab.
13.9.7 m3
Reinforced concrete slab (C-25) as per the drawing
13.9.8 Provide, cut and fix in position zigba formwork including soffit and m2
scaffolding for cover slab.
13.9.9 m2
Supply and construct H.C.B baffle partition wall
13.9.10 m2
Plastering of internal wall and partition wall in cement mortar 1:3
13.9.11 Ls
Supply and install PVC vent pipe with cover cap as per the drawing
13.9.12 m
Supply and install drainage PVC pipe DN100
13.9.13 No.
Supply and install reinforced precast concrete cover to septic tank.
Provide, cut, bend and fix in position reinforced steel bar. All
according to structural drawing. Price shall include tying wires

13.9.14 kg
Diameter 8 mm plain bar
13.10
Construction of Soakaway Pit
13.10.1 m2
Site clearing to depth of 20cm
13.10.2 m3
Excavation of soil to depth of 2.5mts. In ordinary soil
13.10.3 m3
Cart away of surplus excavated materials to a distance of 1- 2kms
13.10.4 m3
Supply and compact approved backfill selected material
13.10.5 Basaltic or equivalent stone masonry wall bedded in cement mortar m3
1:3
13.10.6 m2
Lean concrete in C-15 under masonry wall.
13.10.7 Reinforced concrete slab (C-25) as per the drawing price includes dia, m3
8 bar with a spacing of 200 mesh
13.10.8 Provide, cut and fix in position zigba formwork including soffit and m2
scaffolding for cover slab.
13.10.9 Ls
Supply and install PVC vent pipe with cover cap
13.10.10 No.
Supply and install reinforced precast concrete cover to septic tank.
13.10.11 Supply and put in place coarse gravel, fine gravel and sand depth as Ls
per the drawing
Total to be carried Summary

Prepared By:-
Sub Contractor:________________________________
Y PROJECT

2nd Interim Payment


ce Quarter/
Quantity Unit Rate Amount in Birr
Previous Current Todate (Birr) Previous Current Todate

105.49 105.49 40.00 4,219.40 0.00 4,219.40

42.42 42.42 540.00 22,904.10 0.00 22,904.10

12.45 12.45 720.00 8,964.00 0.00 8,964.00

42.42 42.42 320.00 13,572.80 0.00 13,572.80


19.78 19.78 720.00 14,239.80 0.00 14,239.80

14.00 14.00 535.00 7,487.99 0.00 7,487.99


0.00 0.00 0.00 0.00

16.87 16.87 3,800.00 64,119.30 0.00 64,119.30

0.00 0.00 0.00 0.00

108.04 108.04 630.00 68,062.05 0.00 68,062.05

8.48 8.48 7,500.00 63,630.75 0.00 63,630.75


1.62 1.62 7,500.00 12,120.00 0.00 12,120.00

5.60 5.60 7,500.00 41,988.75 0.00 41,988.75

6.64 6.64 7,500.00 0.00 49,800.00 49,800.00


80.17 80.17 525.00 42,087.94 0.00 42,087.94

32.32 32.32 525.00 16,968.00 0.00 16,968.00

24.90 24.90 525.00 0.00 13,072.50 13,072.50

193.64 193.64 135.00 26,141.93 0.00 26,141.93

21.15 21.15 135.00 2,855.02 0.00 2,855.02

641.55 641.55 135.00 86,608.98 0.00 86,608.98

0.00 135.00 0.00 0.00 0.00

133.91 133.91 630.00 84,360.15 0.00 84,360.15

0.00 0.00 0.00 0.00

133.27 133.27 2,100.00 279,867.00 0.00 279,867.00

123.70 123.70 1,800.00 222,660.00 0.00 222,660.00

112.50 112.50 1,350.00 151,875.00 0.00 151,875.00

81.30 81.30 1,350.00 109,755.00 0.00 109,755.00

0.00 250.00 0.00 0.00 0.00

0.00 150.00 0.00 0.00 0.00

41.50 41.50 570.00 0.00 23,655.00 23,655.00


372.51 372.51 150.00 0.00 55,875.94 55,875.94

55.99 55.99 1,200.00 0.00 67,182.00 67,182.00

22.75 22.75 120.00 0.00 2,730.00 2,730.00

6
6.00 28,000.00 0.00 168,000.00 168,000.00

0.00 27,000.00 0.00 0.00 0.00

0.00 28,000.00 0.00 0.00 0.00

0.00 26,000.00 0.00 0.00 0.00

4
4.00 21,000.00 0.00 84,000.00 84,000.00

4
4.00 24,000.00 0.00 96,000.00 96,000.00

0.00 17,500.00 0.00 0.00 0.00

55.99 55.99 290.00 0.00 16,235.65 16,235.65

0.00 950.00 0.00 0.00 0.00

0.00 950.00 0.00 0.00 0.00

117.79 117.79 303.00 0.00 35,688.85 35,688.85

133.91 133.91 250.00 0.00 33,476.25 33,476.25

0.00 120.00 0.00 0.00 0.00

0.00 2,500.00 0.00 0.00 0.00

0.00 2,500.00 0.00 0.00 0.00


0.00 4,500.00 0.00 0.00 0.00

0.00 5,000.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 550.00 0.00 0.00 0.00

0.00 550.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 600.00 0.00 0.00 0.00

0.00 600.00 0.00 0.00 0.00

0.00 600.00 0.00 0.00 0.00

0.00 600.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 100.00 0.00 0.00 0.00

0.00 150.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 350.00 0.00 0.00 0.00

0.00 420.00 0.00 0.00 0.00

0.00 650.00 0.00 0.00 0.00

0.00 650.00 0.00 0.00 0.00

0.00 350.00 0.00 0.00 0.00

0.00 350.00 0.00 0.00 0.00


22.96 22.96 40.00 0.00 918.40 918.40

20.00 20.00 540.00 0.00 10,800.00 10,800.00

20.00 20.00 320.00 0.00 6,400.00 6,400.00

4.54 4.54 720.00 0.00 3,265.92 3,265.92

5.99 5.99 3,800.00 0.00 22,777.20 22,777.20

7.56 7.56 520.00 0.00 3,931.20 3,931.20

2.65 2.65 7,500.00 0.00 19,845.00 19,845.00

9.36 9.36 520.00 0.00 4,867.20 4,867.20

0.69 0.69 650.00 0.00 450.45 450.45

20.81 20.81 303.00 0.00 6,306.19 6,306.19

2.00 2.00 350.00 0.00 700.00 700.00

6.00 6.00 1,200.00 0.00 7,200.00 7,200.00

2.00 2.00 9,500.00 0.00 19,000.00 19,000.00

70.55 70.55 135.00 0.00 9,523.84 9,523.84

23.04 23.04 40.00 0.00 921.60 921.60

22.50 22.50 540.00 0.00 12,150.00 12,150.00

22.50 22.50 320.00 0.00 7,200.00 7,200.00

5.40 5.40 720.00 0.00 3,888.00 3,888.00

6.72 6.72 3,800.00 0.00 25,536.00 25,536.00

7.84 7.84 720.00 0.00 5,644.80 5,644.80


1.18 1.18 7,500.00 0.00 8,820.00 8,820.00

9.61 9.61 520.00 0.00 4,997.20 4,997.20

1.00 1.00 700.00 0.00 700.00 700.00

1.00 1.00 9,500.00 0.00 9,500.00 9,500.00

1.00 1.00 7,500.00 0.00 7,500.00 7,500.00


Summary 1,344,487.97 848,559.20 2,193,047.16

Approved By:- ____________________


Prime Contractor
BILL No.13: CONSTRUCTION OF OPERATORS DWELLING /Main House & Service Quarter/.
i. Main House
T D S Unit Description
13.1 Earth work
13.1.1 site clearing to a depth of 200 mm
L= 6.5+2 =8.5m W = 6.25+2=8.25 m
1 8.50
8.25
70.13 m2

13.1.2 Trench Excavation for masonary

i. Long side ( L= 6.5m ,W = 0.6m, D= 0.75m)


3 6.50
0.60
0.75
8.77 m3
3 6.25 ii. Short side( L= 6.25 m ,W = 0.5m, D= 0.6m)
0.50
0.60
4.69 m3

iii. Excavation under OGL/below slab


1 6.50 L= 6.5 W= 6.25, D= 0.5
6.25
0.50
20.31 m3
Sum 33.78 m3

13.1.3 Backfill to depth not less than 450mm


2 12.75 (arround the masnary)
L= 6.5m + 6.25=12.75m, W =0.2*2=0.4m & D=0.75
0.40 m
0.75
7.65 m3
13.1.4 Cart away
33.78 m 3

1 6.50 13.1.5. Supply, fill & compact Selected material


6.25
0.30
12.19 m3
1 6.50 13.1.6 Provide and fill hard core
6.25
0.25
10.16 m3
13.2 Masonry Work

3 6.50 13.2.1 Supply and raise 500 mm thick and 1000mm high
i. Long side ( L=6.5 m ,W = 0.4m, D= 0.75m)
0.40
0.75
5.85 m3

3 6.25 ii. Short side( L= 6.25 m ,W = 0.4m, D= 0.75m)


0.40
0.75
4.69 m3
Sum 10.54 m3
13.3 Concrete Work

13.3.1 Provide 50mm thick lean concrete

6 12.75 13.3.1.1. Lean concrete under massonary


0.40
28.05 m2
13.3.1.2 Lean concrete above hard core
1 6.50
6.25
40.63 m2
Sum 68.68 m2
13.3.2 For beams and Lintels
i. Grade Beams
3 6.50 /Long side/
0.30
0.30
1.76 m3
3 6.25 /short side/
0.30
0.30
1.41 m3
ii. Top tie Beam
3 6.50 /Long side/
0.30
0.30
1.76 m3
3 6.25 /short side/
0.30
0.30
1.41 m3
iii. Lintel
2 1.00 i.Window
0.20
0.20
0.08 m3
2 1.20
0.20
0.20
0.10 m3
1 1.25 ii. Door
0.20
0.20
0.05 m3
3 0.90
0.20
0.20

0.11 m3

6.66 m3
9 3.20 13.3.3. Column
0.20
0.20
1.15 m3
13.3.4 Floor slab
1 6.50
6.25
0.10
4.06 m3
Provide and fix formwork for
13.3.6 For beams and Lintels
i. Grade Beams
3 3.90 /Long side/ (Perimeter= 6.5*0.3*2=3.9 m2)
11.70 m 2

3 3.75 /short side/ (Perimeter= 6.25*0.3*2=3.75 m2)


9.38 m 2

ii. Top tie Beam


3 5.85 /Long side/ (Perimeter= 6.5*0.3*3=5.85 m2)
17.55 m 2

3 5.63 /short side/ (Perimeter= 6.25*0.3*3=5.63 m2)


14.06 m2
iii. Lintel
2 0.60 Windows
1.20 m2 /3*1*0.2=0.6m2/
1 0.72 /3*1.2*0.2=0.72m2/
0.72 m2
3 0.54 Door
1.62 m2
1 0.75 /3*1.25*0.2=0.75m2/
0.75 m 2

56.98 m2
13.3.7 Column
9 2.56 /3.2*0.2*4=2.56m2/
23.04 m2
13.5 Block work

13.5.1Class B, 200mm thick HCB wall


2 6.50 i. Long side
3.20
41.60 m2
2 6.25 ii. Short side
3.20
40.00 m2
iii. abovethe top tie beam
2 6.50
1.20
7.80
iv. Deduction
1 1.20 1. Door
2.20
2.64 m2
2 1.00 2. Window
1.00
2.00 m2
1 1.10
1.40
1.54 m2
83.22 m2 Net area of block work
13.6 Roofing and Carpentry
13.6.1 Φ120 mm eucalyptus top and bottom roof truss
member
7 8.01
56.07
5 7.5
37.5
93.57 m

13.6.2 Φ80 mm eucalyptus bracing roof truss membe


6 9
54
5 6
30
84

6 8.00 13.6.3 purlin in zigba wood size 50 x 70 mm


48.00 m
5 7.50
37.50 m
85.50 m
13.6.4 . Roof cover in G-28 mm GIS
1 8.51
7.50
63.81 m2
13.7. Finishing
13.7.1 Floor screed in cement mortar 20 mm thick

1 6.50
6.25
40.63 m2
13.7.4. plaster in cement mortar to internal cement
concrete blocks, all beams and columns
2 6.30 i. Long side
3.20
40.32 m2
2 6.05 ii. Short side
3.20
38.72 m2
79.04 m2
iv. Deduction
1 1.20 1. Door
2.20
2.64 m2
2 1.00 2. Window
1.00
2.00 m2
1 1.10
1.40
1.54 m2
6.18 m2
72.86 m2 Net area
13.7.5. Apply cement mortar pointing to all external
cement concrete block wall
2 6.50 i. Long side
3.20
41.60 m2

2 6.25 ii. Short side


3.20
40.00 m2
iii. abovethe top tie beam
2 6.50
1.20
7.80 m2
89.40 m2
iv. Deduction
1 1.20 1. Door
2.20
2.64 m2
2 1.00 2. Window
1.00
2.00 m2
1 1.10
1.40
1.54 m2
6.18 m2
83.22 m2 Net area
13.6.7 Supply and fix 25 x 250 mm fascia board to
purlin
2 6.50 i. Long side
13.00 m
2 6.25 ii. Short side
12.50 m
25.50 m
13.6.8.Supply and fix 40 x 50 mm ceiling battons
2 6.50 i. Long side
13.00 m
16 15.63 ii. Short side
253.91 m
266.91 m
13.6.9. Supply and fix chipwod ceiling

1 6.50
6.25
40.63 m2
13.6.10. Supply and fix ribbed sheet
2 7.50 /Long side/
0.50
7.50 m2
2 6.25 /short side/
0.50
6.25 m2
13.75 m2
13.3.5. Concrete grade C-20 for the drainage ditch and
walkaway
2 6.50 /Long side/
1.60
0.10
2.08 m3
2 6.25 /short side/
1.60
0.10
2.00 m3
4.08 m3
Provide and fix formwork for
13.3.8. Drainage Ditch
2 6.50 Long side
0.60
7.80 m2
2 6.25 short side
0.60
7.50 m2
15.30 m2
13.9. Construction of Septic Tank
13.9.1. Site clearing to depth of 20cm
1 5.60 L= 3.6+2 =5.6m W = 2.1+2=4.1 m
4.10
22.96 m2
13.9.2 Excavation of soil to depth of 2mts. In ordinary
soil
1 4.00
2.50
2.00
20.00 m3
13.9.3 Cart away of surplus excavated materials to a
distance of 1- 2kms
20.00 m3
13.9.4 Supply and Backfill selected material
1 3.60
2.10
0.60
4.54 m3
13.9.5 Basaltic or equivalent stone masonry wall
2 3.60 Long side
1.85
0.45
5.99 m3
2 2.10 short side
1.85
0.45
3.50 m3
9.49 m3
13.9.6 Lean concrete in C-15 under foundation slab.
1 3.60
2.10
7.56 m2
13.9.7 Reinforced concrete slab (C-25) as per the
drawing
1 3.60 Bottom Slab
2.10
0.15
1.13 m3
1 3.60 Top Slab
2.10
0.20
1.51 m3
2.65 m3

13.9.8 Provide, cut and fix in position zigba formwork


including soffit and scaffolding for cover slab.
1 3.90
2.40
9.36 m2
13.9.9 Supply and construct H.C.B baffle partition wall
1 2.10
1.65
0.20
0.69 m3
13.9.10 Plastering of internal wall and partition wall in
cement mortar 1:3
2 3.15 Long side
1.85
11.66 m2
3 1.65 short side
1.85
9.16 m2
20.81 m2
13.10 Construction of Soakaway Pit
13.10.1. Site clearing to depth of 20cm
1 4.80 L= 2.8+2 =4.8 m W = 2.8+2 =4.8 m
4.80
23.04 m2
13.10.2 Excavation of soil to depth of 2mts. In ordinary
soil
1 3.00
3.00
2.50
22.50 m3
13.10.3 Cart away of surplus excavated materials to a
distance of 1- 2kms
22.50 m3
13.10.4 Supply and Backfill selected material
1 3.00
3.00
0.60
5.40 m3
13.10.5 Basaltic or equivalent stone masonry wall
2 2.80 Long side
2.40
0.50
6.72 m3
2 2.80 short side
2.40
0.50
6.72 m3
13.44 m3
13.10.6 Lean concrete in C-15 under foundation slab.
1 2.80
2.80
7.84 m2
13.10.7 Reinforced concrete slab (C-25) as per the
drawing
1 2.80 Top Slab
2.80
0.15
1.18 m3
13.10.8 Provide, cut and fix in position zigba formwork
including soffit and scaffolding for cover slab.

1 3.10
3.10
9.61 m2

Prepared By:- Approved By:- ____________________


Sub Contractor:_________________ Prime Contractor
Project: - CONSTRUCTION OF CIVIL WORKS OF MOYALE WATER SUPPLY PROJECT
Employer:- SOMALY REGIONAL IRRIGATION OFFICE
Consultant:- SOMALY DESIGN & SUPERVISION WORKS INTERPRISE
Contractor:- IQRA GENERAL CONTRACTOR
Sub. Cotractor:-FUREEY GENERAL CONSTRUCTION

BILL No.13: CONSTRUCTION OF OPERATORS DWELLING /Main House & Service Quarter/.
Main House/OD/
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
Column 1.00 12 0.25 3.15 0.25
Stirups 2.00 6 0.20 0.30 0.30 0.10

On Axis A, 12 0.20 5.90 0.20


B&C
Grade Beam 12 0.07 5.90 0.07
On Axis 1, 12 0.20 6.45 0.20
2&3 12 0.07 6.45 0.07
On Axis A, 12 0.20 5.90 0.20
B&C 12 0.07 5.90 0.07
Top tie Beam
On Axis 1, 12 0.20 6.45 0.20
2&3 12 0.07 6.45 0.07
On Axis A,
B&C 6 0.13 0.30 0.30 0.10

On Axis 1,
2&3 6 0.13 0.30 0.30 0.10
Stirup
On Axis A,
B&C 6 0.13 0.30 0.30 0.10

On Axis 1,
2&3 6 0.13 0.30 0.30 0.10
8 0.05 1.25 0.05
D1
8 0.10 1.25 0.10
8 0.05 0.85 0.05
D2
8 0.10 0.85 0.10
LINTELE
8 0.05 1.34 0.05
W1
8 0.10 1.34 0.10
8 0.05 0.85 0.05
w2
8 0.10 0.85 0.10
D1 6 0.20 0.30 0.20 0.10
D2 6 0.20 0.30 0.20 0.10
Stirup
W1 6 0.20 0.30 0.20 0.10
Stirup
W2 6 0.20 0.30 0.20 0.10

Service Quarter/OD/
Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
Column 1.00 12 0.25 2.90 0.25
Stirups 2.00 6 0.20 0.30 0.30 0.10
On Axis A 12 0.15 4.75 0.15
&B 12 0.07 4.75 0.07
Grade Beam
On Axis 1 12 0.15 3.15 0.15
&2 12 0.07 3.15 0.07
On Axis A 12 0.15 4.75 0.15
&B 12 0.07 4.75 0.07
Top tie Beam
On Axis 1 12 0.15 3.15 0.15
&2 12 0.07 3.15 0.07
On Axis A,
B&C 6 0.13 0.30 0.30 0.10

On Axis 1,
2&3 6 0.13 0.30 0.30 0.10
Stirup
On Axis A,
B&C 6 0.13 0.30 0.30 0.10

On Axis 1,
2&3 6 0.13 0.30 0.30 0.10
8 0.05 0.90 0.05
D1 & 2
8 0.10 0.90 0.10
8 0.05 1.15 0.05
LINTELE W1
8 0.10 1.15 0.10
8 0.05 0.95 0.05
w2
8 0.10 0.95 0.10
6 0.20 0.30 0.20 0.10
D1 & 2
Stirup 6 0.20 0.30 0.20 0.10
W2 6 0.20 0.30 0.20 0.10

Construction of Septic Tank


Bar bending dimensions
Postion Bar Dia
Bar name or Description C/C
No. (mm)
Postion Bar Dia
Bar name or Description C/C L1 S1 S2
No. (mm)
(m) (m) (m)
x 8 0.20 3.55 0.10 0.10
Bottom Slab
y 8 0.20 2.05 0.10 0.10
x 8 0.20 3.55 0.15 0.15
Top Slab
y 8 0.20 2.05 0.15 0.15

Prepared By:-
Sub Contractor:________________________________
CT

2nd Interim Payment

uarter/.

dimensions No. of Total Length (m)


No of Distribute
Total L bars in
members d length Dia 6mm Dia Dia
Dia 12mm
Dia
(m) member 8mm 10mm 14mm
3.65 4.00 9 131.40
0.70 17.00 9 3.20 107.10
6.30 2.00 2.5 31.50
6.04 2.00 2.5 30.20
6.85 2.00 3 41.10
6.59 2.00 3 39.54
6.30 2.00 2.5 31.50
6.04 2.00 2.5 30.20
6.85 2.00 3 41.10
6.59 2.00 3 39.54
0.70 49.00 2.5 6.20 85.75

0.70 51.00 2.5 6.50 89.25

0.70 49.00 3 6.20 85.75

0.70 51.00 3 6.50 107.10


1.35 2.00 1 2.70
1.45 2.00 1 2.90
0.95 2.00 3 5.70
1.05 2.00 3 6.30
1.44 2.00 1 2.87
1.54 2.00 1 3.07
0.95 2.00 3 5.70
1.05 2.00 3 6.30
0.60 8.00 1 1.30 4.80
0.60 6.00 3 0.90 10.80
0.60 8.00 1 1.40 4.80
0.60 6.00 3 1.00 10.80
Total Length (m) 506.15 35.54 0.00 416.08 0.00
Unit Wt./ml 0.22 0.40 0.62 0.89 1.21
Total Wt. (Kg) 112.37 14.04 0.00 369.48 0.00

dimensions No. of Total Length (m)


No of Distribute
Total L bars in
members d length Dia 6mm Dia Dia
Dia 12mm
Dia
(m) member 8mm 10mm 14mm
3.40 4.00 9 122.40
0.70 16.00 9 3.00 100.80
5.05 2.00 3.0 30.30
4.89 2.00 3.0 29.34
3.45 2.00 2.4 16.56
3.29 2.00 2.4 15.79
5.05 2.00 3.0 30.30
4.89 2.00 3.0 29.34
3.45 2.00 2.4 16.56
3.29 2.00 2.4 15.79
0.70 38.00 3.0 4.80 79.80

0.70 26.00 3.0 3.20 54.60

0.70 38.00 2.4 4.80 63.84

0.70 26.00 2.4 3.20 43.68


1.00 2.00 2 4.00
1.10 2.00 2 4.40
1.25 2.00 1 2.50
1.35 2.00 1 2.70
1.05 2.00 1 2.10
1.15 2.00 1 2.30
0.60 7.00 2 1.20 8.40
0.60 7.00 1 1.20 4.20
0.60 6.00 3 1.00 10.80
Total Length (m) 366.12 18.00 0.00 306.38 0.00
Unit Wt./ml 0.22 0.40 0.62 0.89 1.21
Total Wt. (Kg) 81.28 7.11 0.00 272.07 0.00

dimensions No. of Total Length (m)


No of Distribute
bars in
members d length
member
No. of
No of Distribute
Total L bars in Dia Dia Dia
members d length Dia 6mm Dia 12mm
(m) member 8mm 10mm 14mm
3.75 12.00 1 2.10 45.00
2.25 19.00 1 3.60 42.75
3.85 12.00 1 2.10 46.20
2.35 19.00 1 3.60 44.65
Total Length (m) 0.00 178.60 0.00 0.00 0.00
Unit Wt./ml 0.22 0.40 0.62 0.89 1.21
Total Wt. (Kg) 0.00 70.55 0.00 0.00 0.00

Approved By:- ____________________


Prime Contractor
ngth (m)
Dia Dia Remark
Dia 24
16mm 20mm
0.00 0.00 0.00
1.58 2.47 3.55
0.00 0.00 0.00

ngth (m)
Dia Dia Remark
Dia 24
16mm 20mm

0.00 0.00 0.00


1.58 2.47 3.55
0.00 0.00 0.00

ngth (m)
Remark
Dia Dia Remark
Dia 24
16mm 20mm

0.00 0.00 0.00


1.58 2.47 3.55
0.00 0.00 0.00

By:- ____________________

You might also like