Download as pdf or txt
Download as pdf or txt
You are on page 1of 23

6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Final Exam (Summative Assessment 3)


Due Jun 8 at 7pm Points 50 Questions 50
Available Jun 8 at 7:30am - Jun 8 at 7pm about 12 hours Time Limit 60 Minutes

Instructions
Choose the correct answer.

Attempt History
Attempt Time Score
LATEST Attempt 1 59 minutes 42 out of 50

 Correct answers are hidden.

Score for this quiz: 42 out of 50


Submitted Jun 8 at 9:35am
This attempt took 59 minutes.

Question 1 1 / 1 pts

Which is not an advantage of earthship homes?

Energy Efficiency

Resellability

Buildability

Self-Sustainability

https://tip.instructure.com/courses/29661/quizzes/424563 1/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Incorrect
Question 2 0 / 1 pts

Alternative building methods involve Eco and Green Developments which


are designed to maximize energy requirements.

True

False

Question 3 1 / 1 pts

Earthbag construction is an inexpensive method to create structures


which are both strong and can be quickly built.

True

False

Question 4 1 / 1 pts

https://tip.instructure.com/courses/29661/quizzes/424563 2/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

The picture above is an example of?

strawbale construction

cordwood construction

rammed earth construction

cob construction

Question 5 1 / 1 pts

The exterior of an adobe wall can be covered with glass to increase heat
collection. In a passive solar home, this is called a ________ wall.

Phobre

Trombe

https://tip.instructure.com/courses/29661/quizzes/424563 3/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Tombe

Pombre

Question 6 1 / 1 pts

A compilation of elements that are primarily in tension, with the


compression being transferred to a central mast and down into the
ground.

Three-dimensional structures

Draped cables

Linear structures

Surface-stressed structures

Question 7 1 / 1 pts

They are most effective if the curvature is compatible with spatial design
objectives, and the horizontal thrust is resisted by a compression ring or
by infrastructures, such as grandstands.

Suspended structures

Tensile structures

Stayed structures

Cable structures

https://tip.instructure.com/courses/29661/quizzes/424563 4/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Question 8 1 / 1 pts

The first pneumatic structures were invented by _______ in the late 1940s
during World War II by the United States Army.

Big Bird

Lev Zetlin

Jawerth

Walter Bird

Incorrect
Question 9 0 / 1 pts

Suspended Structures are those with vertical planes i.e. floors are
supported by cables (hangers) hung from the parabolic sag of large, high-
strength steel cables.

True

False

Question 10 1 / 1 pts

Synclastic surfaces are those in which the centres of curvature are


located on opposing sides of the surface.

True

https://tip.instructure.com/courses/29661/quizzes/424563 5/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

False

Question 11 1 / 1 pts

Anticlastic surfaces are those in which the centres or curvature are on the
same side of the surface.

True

False

Incorrect
Question 12 0 / 1 pts

Are the most common type of thin-shell structures.

Cable structure

Tensile structure

Linear structures

Surface-stressed structures

Question 13 1 / 1 pts

Three-dimensional tensile structures is a compilation of elements that are


primarily in compression, with the tension being transferred to a central
mast and down into the ground.

https://tip.instructure.com/courses/29661/quizzes/424563 6/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

True

False

Incorrect Question 14 0 / 1 pts

Air supported structures also require some continuous air supply to make
up for pressure loss due to membrane leaks.

True

False

Question 15 1 / 1 pts

Cable Truss Curtain Wall Systems are more expensive than the other
systems and so many details for the joints, load distribution calculations,
safety.

True

False

Question 16 1 / 1 pts

Cable-truss structures can be described as a system of straight bars and


cables joined at their ends from a rigid framework.

https://tip.instructure.com/courses/29661/quizzes/424563 7/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

True

False

Question 17 1 / 1 pts

Developed a cable truss with diagonal brace cables separating top


support and bottom stabilizing cables that resist wind uplift.

Jawerth

Lev Zetlin

Jaworth

Lez Vetlin

Incorrect
Question 18 0 / 1 pts

The image above is an example of what anticlastic shape?

https://tip.instructure.com/courses/29661/quizzes/424563 8/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

arch

saddle

point

wave

Question 19 1 / 1 pts

Identify the image above.

H-shape

Partially-encased

Twin-section

https://tip.instructure.com/courses/29661/quizzes/424563 9/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Cruciform

Question 20 1 / 1 pts

Which is not true about pneumatic structures?

stabilized by the pressure of compressed air

usually fabricated of a membrane of an impervious material

evenly pressurized for its best stability

very lightweight and flexible opened structure

Question 21 1 / 1 pts

Conventional steel buildings are traditional metal structures constructed


by rolled steel sections which are designed individually and fabricated at
site using welding and cutting.

True

False

Incorrect
Question 22 0 / 1 pts

Pre engineered buildings are factory-built buildings of steel that are


shipped to site and bolted together.

https://tip.instructure.com/courses/29661/quizzes/424563 10/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

True

False

Question 23 1 / 1 pts

Conventional buildings are being preferred over pre-engineered buildings


for industrial construction due to its fast construction.

True

False

Question 24 1 / 1 pts

Pre-Engineered steel building is portal frame construction comprises of


primary and secondary framing and bracing system.

True

False

Question 25 1 / 1 pts

Primary framing of a PEB is an assembly of built up I-Shaped


steel members & that framing consist trusses or castellated beams etc.

True

https://tip.instructure.com/courses/29661/quizzes/424563 11/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

False

Question 26 1 / 1 pts

Spaceship Earth is the flagship attraction of Expo 86 and the signature


symbol of the park.

True

False

Question 27 1 / 1 pts

Building a geodesic dome needs very skilled labors.

True

False

Question 28 1 / 1 pts

The word geodesic is Latin and means 'earth providing'.

True

False

https://tip.instructure.com/courses/29661/quizzes/424563 12/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Question 29 1 / 1 pts

Pins are the force members in a geodesic dome that act in compressive
and tensile forces to resist loading.

True

False

Question 30 1 / 1 pts

A dome is typically an element of architecture that resembles the lower


half of a sphere.

True

False

Incorrect Question 31 0 / 1 pts

https://tip.instructure.com/courses/29661/quizzes/424563 13/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Identify

Folded Plate and Barrel Vault

Dome and Barrel Vault

Barrel and Slab

Folded Plate - Tapered Ends

Question 32 1 / 1 pts

Folded plates are assemblies of flat plates rigidly connected together


along their edges in such a way so as to make the structural system
capable of carrying loads without.

https://tip.instructure.com/courses/29661/quizzes/424563 14/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

True

False

Question 33 1 / 1 pts

Identify

Intersection Shell - Folded Plate

Intersection Shell - Cross Form

Intersection - Polygonal Plan, Shallow Intersection

Groined Vault - Polygonal Plan

Question 34 1 / 1 pts

https://tip.instructure.com/courses/29661/quizzes/424563 15/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Four of the rectangular hyperbolic paraboloidal surfaces may be arranged


so that the outer edge of the shell is level and the low point is at the
center where it is supported by a column.

The Groined Vault

Umbrella Shells

HP Flower Dome

Trumpet Shell

Question 35 1 / 1 pts

Identify

El Oceanográfico

https://tip.instructure.com/courses/29661/quizzes/424563 16/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Lotus Temple

PalaTiziano

Cosmic Ray Pavilion

Question 36 1 / 1 pts

A conoidal surface, is formed by drawing curve lines between straight


lines such as a circle and a straight line.

True

False

Question 37 1 / 1 pts

Umbrella shells has four of the rectangular hyperbolic paraboloidal


surfaces may be arranged so that the outer edge of the shell is level and
the highest point is at the center where it is supported by a column.

True

False

Question 38 1 / 1 pts

https://tip.instructure.com/courses/29661/quizzes/424563 17/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

The strongest form of shell is the monolithic shell, which is cast as a


single unit. The most common monolithic form is the dome, but ellipsoids
and cylinders and variations thereof are also possible.

True

False

Question 39 1 / 1 pts

The name applied to this shell is derived from the resemblance of the
shape to the term for a cattle brand.

Butterfly Shells

Corrugated Curves

Lazy Z

Lazy S

Question 40 1 / 1 pts

https://tip.instructure.com/courses/29661/quizzes/424563 18/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Identify the picture shown above.

shell structure

lazy s structure

pleated structure

folded plate structure

Question 41 1 / 1 pts

Is the most used component in several construction sites because it suits


any type of architecture which adopt to the requirements.

precast slab

precast beam

precast wall

https://tip.instructure.com/courses/29661/quizzes/424563 19/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

precast column

Question 42 1 / 1 pts

Which is not a benefit of prestressed concrete?

No cracks even at top load conditions

More material efficiency overall

Better durability, shear strength, and fatigue resistance

The ability to work for spans less 35 meters

Question 43 1 / 1 pts

Precast products are financially expensive.

True

False

Question 44 1 / 1 pts

The process of making a component using the precast construction takes


a shorter time.

True

https://tip.instructure.com/courses/29661/quizzes/424563 20/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

False

Question 45 1 / 1 pts

A type of precast slab which provides maximum structural efficiency by


reducing the dead weight.

hollow core slab

solid core slab

double-tee unit

biaxial voided slab

Incorrect Question 46 0 / 1 pts

Are the latest precast slab that are more efficient than traditional floor
structure.

biaxial voided slab

double-tee unit

solid core slab

hollow core slab

Question 47 1 / 1 pts

https://tip.instructure.com/courses/29661/quizzes/424563 21/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Is an exposed structural system that also serves as the façade.

cast-in-situ concrete slab system

cast-in-place concrete wall system

cast-in-place concrete slab system

cast-in-situ concrete wall system

Question 48 1 / 1 pts

Is a method of constructing concrete buildings by casting the floor or roof


slab on top of the previous slab and then raising (jacking) the slab up with
hydraulic jacks.

Lift slab

Slipform

Waffle slab

Spanstress

Question 49 1 / 1 pts

Is thickened slab region that includes either drop panels or column


capitals at columns to resist heavier loads and thus permit longer spans.

Flat Plate

https://tip.instructure.com/courses/29661/quizzes/424563 22/23
6/8/22, 9:37 AM Final Exam (Summative Assessment 3): AR 421-ARCH41S1 - Building Technology 5 - Alternative Building Construction Systems

Flat Slab

Hollow Core

Double Tees

Question 50 1 / 1 pts

Prestressing is done after the concrete attains sufficient strength.