ARIYALUR
Raw Mill - False Air Report
Date 14.07.2021
PH fan outlet
Mill I/L 7
PH fan O/L to Mill Inlet
Mill outlet 8.1 7.86%
Mill Fan I/L
Fan outlet 8.8 5.43%
Across the system 12.86%
BH O/L 10.1
Across BH 10.66%
14.07.2021
Sl.
Duct dia. Duct area Temp.
Location
No.
m m2 oC
Cement mill
1 2.2 3.8 240
booster fan inlet
2 Recirculationair 4 12.57 80.5
ARIYALUR
Coal Mill - False Air Report
Date 14.07.2021
False Air
Description O2 %
%
ARIYALUR
Preheater - False Air Report
Date 13.07.2021
False Air
Description O2 %
%
Volume