Professional Documents
Culture Documents
Method of Statment - Deck Slab
Method of Statment - Deck Slab
Method of Statment - Deck Slab
EGYPT
Date
15/12/2021
AIN SOKHNA PORT DEVELOPMENT - EGYPT Doc. No:
Table of Contents
1. SCOPE ........................................................................................................................................................................ 3
2. Reference documents. ............................................................................................................................................... 3
3. MATERIALS................................................................................................................................................................. 3
3.1. Form Work ........................................................................................................................................................ 3
3.2. Reinforcement .................................................................................................................................................. 3
3.3. Concrete............................................................................................................................................................ 3
4. SEQUENCE OF CONSTRUCTION OF DECK SLAB ........................................................................................................... 4
4.1. Pile head breaking ............................................................................................................................................ 4
4.2. Execution of transverse beams ........................................................................................................................ 5
4.2.1. Excavation till transverse bottom level ....................................................................................................... 5
4.2.2. Casting of plan concrete (blinding concrete) ............................................................................................... 5
4.2.3. Reinforcement fabrication and fixing for transverse beams ...................................................................... 5
4.2.4. Formwork for crossbeams............................................................................................................................ 6
4.2.5. Casting of crossbeams .................................................................................................................................. 7
4.2.6. Removal of form work ................................................................................................................................. 7
4.2.7. Protection of the concrete ........................................................................................................................... 7
4.3. Execution of deck slab ...................................................................................................................................... 7
4.3.1. Backfilling between beams .......................................................................................................................... 7
4.3.2. Fabrication of deck slab reinforcement ....................................................................................................... 8
4.3.3. Casting of deck slab ...................................................................................................................................... 8
4.3.4. Curing of slab. ............................................................................................................................................... 8
5. HEALTH AND SAFETY .................................................................................................................................................. 8
6. ENVIRONMENT .......................................................................................................................................................... 9
7. INSPECTION AND TESTING (QA/QC) ........................................................................................................................... 9
7.1. Controls on Formwork ..................................................................................................................................... 9
7.2. Controls on Reinforcement .............................................................................................................................. 9
7.3. Controls for Concrete Prior to Concreting ....................................................................................................... 9
7.4. Controls during Concreting ............................................................................................................................ 10
Page 2 of 10
AIN SOKHNA PORT DEVELOPMENT - EGYPT Doc. No:
1. SCOPE
This document describes the principles of the construction method proposed for the deck slab including
(Front Beam, Back Beam, Transverse Beams and RC Slab) works to be constructed for the “970 m length
for the container quay at Sokhna port” project, as well as the main equipment, which is anticipated, for
the execution of the works.
2. Reference documents.
- Project Technical Specifications
- Egyptian Code
3. MATERIALS
3.1. Form Work
Formwork will be done using metal or timber based on the site conditions and height of the casted element,
the metal form work shall be provided by an approved supplier with approved design for the dimensions,
location of supports and duration of usage.
3.2. Reinforcement
Ready-to-install reinforcement shall be prepared on site.
The reinforcement cages will be prefabricated according to approved design and shop drawings. They shall
be equipped with sufficient concrete spacers, lifting devices etc. to ensure a proper installation of the main
bars and stirrups. The different cage segments shall be spliced tightly with steel wires considering the required
lap length.
3.3. Concrete
Ready mix concrete complying with project specifications and ACI 336. 1-5 shall be used. Concrete should be
of average slump of 150mm. This means that at the beginning of pouring slump should about 180mm and
should not fall below 120 mm at the end of pouring (about 3 hours). Cement content is at least 350 kg/m3 as
per project specifications.
Additives shall be used to guarantee the required slump during the time of pouring the whole pile. A
retardation period of four to five hours in setting time is required to assure the integrity of concrete element.
Page 3 of 10
AIN SOKHNA PORT DEVELOPMENT - EGYPT Doc. No:
As per the approved drawings, this pile cut-off level is +1.6M while the water level is expected to be 0.00 level thus no
groundwater expected in this event and no need for dewatering works to be considered in this phase.
After excavation is completed at the required level, surveying works will be done to mark the cut-off level for the
exposed piles, the exposed piles concrete shall be tested to obtain the required strength prior to the commencement
of the crushing works.
After the marking is done, a mechanical equipment is expected to start the crushing works, small jack hummers will
be mounted on mechanical equipment to allow for the crushing works. Kindly see the picture below.
Rig operator will be manoeuvring around the exposed pile section to allow or concrete crushing without damaging the
exposed steel, however exposed reinforcement may need to be bended to allow for crushing of the concrete in the
middle section
The small jackhammers will allow for crushing the concrete in small
particles to allow for the crushed concrete to be demobilizing from
site and avoid cracks in the main shaft of the pile
Page 4 of 10
AIN SOKHNA PORT DEVELOPMENT - EGYPT Doc. No:
Page 5 of 10
AIN SOKHNA PORT DEVELOPMENT - EGYPT Doc. No:
For the front beam and rear beam, a need for side supports shall be considered as per the site condition. Please
refer to the picture below
For the middle piles tie rods may be considered for lateral support in addition to the bracings, final design shall be
submit for the consultant’s approval prior to supplying the form works.
Section for the form works support for the transverse beams
Detailed design for the form work (height, thickness, location of tie rods and bracing system if required) shall be
submit though an approved subcontractor to carry out the supply of the form work.
Page 6 of 10
AIN SOKHNA PORT DEVELOPMENT - EGYPT Doc. No:
Request will be sent to the consultant prior to dismantling the form work.
Protection of the sides of the concrete shall be done by the approved materials from the consultant, the isolation
shall comply with the project specs and consultant approvals and comments. Protection an isolation works shall be
conducted on the both sides of the concrete beams after the curing is completed.
Top mesh will be installed and fabricated as per the approved drawings in addition to the beams top reinforcement.
All steel reinforcement shall comply with the project specs and approved drawings.
In pattern of construction joint additional preparations may be required for the fabrication of the work, in the case
of a construction joint additional works may be considered based on the consultant approvals.
A minimum of 2 pumps shall be used to allow for the casting, length of the pump is decided based on the site
conditions. The concreting shall be in continuous matter along with the vibration to avoid cold joints.
Upon casting the top level of the concrete will be maintained as per the approved drawings (+2.5) and finishing shall
consider using levelling machines like power trowel or equivalent.
Page 8 of 10
AIN SOKHNA PORT DEVELOPMENT - EGYPT Doc. No:
6. ENVIRONMENT
In addition to the ordinary environmental rules, the following shall be considered to protect the
ground against pollution
- Used oil shall be collected while changing in order not to contaminate the ground and shall be
disposed safely in designated areas.
- Equipment shall be fuel fed by manual pumps through hoses in order to avoid spillage on the ground.
Surveying points shall be marked for the exact location of the inner side of the form works (4 corners) before
the erection of the works, skilled form workers shall fix the form sides to fit the exact side (2 point) that should
hold the shatter. Initial check shall be done by the surveyor prior to the final check by the consultant.
A copy of the steel delivery note shall be provided to the consultant along with the material inspection request
(MIR) for his approval and visual inspection if required.
Upon delivery to the site, a sample shall be collected from the steel to allow for destructive testing. The sample
shall be tested in a certified lab with tensile destructive tests to define the tensile strength for at least 1 sample
from each supplier. Additional tests may be required subject to the satisfaction of the consultant.
Before the actual concreting, slump tests have to be made to confirm the workability of the concrete in
addition to concrete sampling. Concrete samples shall be done to cover the project test requirements.
Sampling will be done by the supplier’s certified technician, box dimensions shall be 150x150x150mm as per
the Egyptian standards. Preparation of the cube shall be done by the technician after checking the slump of
the vehicle, random checking will be done on the ordered quantity.
Page 9 of 10
AIN SOKHNA PORT DEVELOPMENT - EGYPT Doc. No:
The dismantle of the cubes shall be done after 2 days of casting to allow for concretes initial settlement, the
cubes will be marked by the name of the element and the casted day, then stored in a cold designated area
before sending it to the lab for testing,
Concreting will be performed by pouring the concrete continuously into the hopper and through the pump
then passed to the formwork in layers if required. The height of each concrete layer shall not exceed 45CM
to allow for proper vibration and compaction works to be conducted on the freshly casted concrete.
The total volume of concrete consumed by each element will be calculated and compared to the theoretical
volume of the same element to define the overcasting and wastage.
Concrete testing will be reported to the consultant for his satisfaction and approvals.
Page 10 of 10