Professional Documents
Culture Documents
00-180000-4700000203-CH2-CIV-SPC-000002 Rev.02.00 - Pdf. (Geotech)
00-180000-4700000203-CH2-CIV-SPC-000002 Rev.02.00 - Pdf. (Geotech)
00-180000-4700000203-CH2-CIV-SPC-000002 Rev.02.00 - Pdf. (Geotech)
INVESTIGATIONS
NEOM WATER DESALINATION PLANT TO GAYAL
TRANSMISSION SYSTEM
00-180000-4700000203-CH2-CIV-SPC-000002 Rev 02.00
OCTOBER 2021
Document history
Document approval
1 ABBREVIATIONS ................................................................................................................ 5
2 EXECUTIVE SUMMARY ...................................................................................................... 6
3 GENERAL ............................................................................................................................. 7
3.1 Introduction............................................................................................................................ 7
3.2 Objective of the Project ......................................................................................................... 7
3.3 Scope of Project .................................................................................................................... 7
3.4 Project Site ............................................................................................................................ 7
3.5 TOR for Soil and Geophysical Investigation Works .............................................................. 8
4 SITE APPRAISAL .............................................................................................................. 10
4.1 Existing Information ............................................................................................................. 10
4.2 Ground Model ..................................................................................................................... 10
5 SCOPE OF GEOTECHNICAL INVESTIGATION............................................................... 11
5.1 Exploratory Holes ................................................................................................................ 11
5.2 Field Testing ........................................................................................................................ 12
5.3 Laboratory Testing .............................................................................................................. 12
5.4 Reporting ............................................................................................................................. 13
6 SCOPE OF GEOPHYSICAL INVESTIGATION ................................................................. 14
6.1 Electrical Resistivity Tests................................................................................................... 14
6.2 P&S Suspension Logging (Seismic Downhole) .................................................................. 14
6.3 Field Testing ........................................................................................................................ 14
6.4 Reporting ............................................................................................................................. 14
7 SPECIFICATION ................................................................................................................ 15
7.1 Schedule 1: Information and site-specific requirements ..................................................... 15
7.2 Schedule 2: Exploratory Holes ............................................................................................ 28
7.3 Schedule 3: Employer’s Representative Facilities .............................................................. 33
7.4 Schedule 4: Specification Amendments ............................................................................. 33
7.5 Schedule 5: Specification Additions .................................................................................... 35
8 DRAWINGS ........................................................................................................................ 36
APPENDIX A: EXPLORATORY HOLES LOCATION PLAN .............................................................. 37
APPENDIX B: TYPICAL STANDPIPE PIEZOMETER DETAILS FOR GROUNDWATER
MONITORING ..................................................................................................................... 38
List of Figures
Figure 3-1: Water Transmission System layout (source: Google Earth Pro.) ......................................... 8
Figure 4-1 : Available Ground Investigation Information ....................................................................... 10
Terms of Reference have been provided for the geotechnical and geophysical investigations along the
alignment as detailed in this document.
3.1 Introduction
NEOM intends to award a Design & Build Construction package for building a 1,068 MLD pumping
station in Duba which will pump potable water to Gayal via twin 2,000 mm diameter pipes over
approximately 115 km.
The scope of works includes concept design of all civil and electromechanical works related to the
proposed pipeline conveyance system, culvert, and pumping station.
The overall objective of the project is to provide the necessary infrastructure required to transfer potable
water to Gayal. It is also proposed to connect to the existing 1,200 mm diameter pipeline and a number
of reservoirs and connection provisions along the route.
A potable water pumping station of up to 1,068 MLD capacity to transfer the potable water from
the proposed NEOM desalination plant to Gayal. The capacity of the pump station shall be
confirmed based on the overall demand required by the NEOM masterplan.
The pump station shall also accommodate two future pump groups that will supply water to the
Hisma Desert & Upper Valley and Southern Hub Reservoirs. The tentative flows for these pump
groups is 750 MLD and 323 MLD respectively.
A potable water conveyance line of twin 2,000 mm diameter carbon steel pipes is proposed to
convey the potable water from the proposed pump station to Gayal.
The twin pipeline is to be laid within a utility culvert with provision for a third 2,000 mm diameter
pipeline in the future
The scope of work for the project related to the potable water conveyance works to Gayal includes the
following:
Concept design for the conveyance pipeline including all associated fittings and valve works.
Concept design for the culvert housing the conveyance pipeline.
Concept design for the potable water pump station including associated civil, electrical and
mechanical works including Motor Control and SCADA.
The project site is located in the coastal region of NEOM. NEOM is the planned independent economic
zone in the Northwest of Saudi Arabia. The proposed General Layout plan for the project area showing
the proposed alignment of the potable water conveyance system is shown in Figure 3-1:
The services to be rendered by the contractor under this TOR are aimed at providing a comprehensive
Geotechnical Report package necessary for the design and construction of the transmission pipeline
and pump station.
The main objective of the geotechnical investigation is to conduct Geotechnical surveys / investigations
for the project site and determine:
Some previous investigation information is available along the parts of the route at selected potential
quarry zones to evaluate the suitability of the material for use in earthworks. The location of the existing
boreholes and Trial Pits is shown in Figure 4-1.
As per available information the following geological conditions are expected to be encountered on site:
Boreholes and Trial Pits are proposed to be undertaken to determine the nature and condition of the
ground material from existing ground surface level and to confirm the existing ground investigation
information.
Investigation point quantities at the proposed development are shown in Table 5-1. Sketches showing
the locations of the proposed exploratory holes are included in Appendix A.
Table 5-1: Summary of exploratory hole quantities and depths at the proposed development
Depth
Investigation Number
(m)
Boreholes (Culvert) 51 10 to 20
Depth of
Minimum Requirements/Frequency of
Type of Project Exploration
Exploration points
points
Large area Structures - Desk Study.
(Hangars, storage yards, - Walkover survey. Minimum depth of
industrial facilities, - Geological Mapping 1/10,000. borehole 15m.
commercial centres) - Boreholes at 500m grid pattern.
- Desk Study.
Large Diameter - Walkover survey. Minimum depth of
Pipelines/Culverts - Geological Mapping 1/10,000. borehole 10m.
- Minimum 1 borehole every 2,000m.
Seismic Site Class - Geological mapping 1/10,000. Minimum depth of
- Geophysical Testing: MASW, P&S boreholes 30m.
suspension Logging, Cross-hole seismic test.
- Boreholes at 1,000m grid pattern.
The chainages indicated in Table 5-3 relate to each pump station to allow changes to the alignment to
be made without affecting the chainage reference along the whole pipeline alignment. As such, each
chainage is prefixed with the pumpstation where the chainage measurement begins.
Laboratory testing of soil and rock samples shall be undertaken to determine the physical, mechanical
and chemical properties of the strata. Laboratory testing shall be undertaken by an SASO/UKAS
accredited laboratory, approved by the Employer. Laboratory tests required for the retrieved soil and
rock samples are listed in the following:
5.4 Reporting
A ground investigation report shall be prepared in accordance with appropriate International Standards
(ASTM, BSI, European Norm). The reporting shall be in accordance with the requirements set out in
schedule S1.21 of the Specification section of this document and the following references.
NEOM-NEN-PRC-001
NEOM-NEN-PRC-002
NEOM-NEN-PRC-005
NEOM-NEN-SCH-005
Geophysical investigations are required to measure soil resistivity at the same interval as the
geotechnical investigations to be used for cathodic protection calculation (as per ASTM STP 741) by
the Design-Build contractor, identify any potential cavities within the Pumping stations site, and identify
the depth of the bedrock formation and any potential hidden faults.
Investigation point quantities at the proposed development are shown in Table 6-1. Sketches showing
the locations of the proposed exploratory holes are included in Appendix A.
Table 6-1: Summary of geophysical survey quantities at the proposed development
Suspension P-S velocity logging is a method for determining shear (Vs) and compressional (Vp) wave
velocity profiles as a function of depth, in addition to supplementing stratigraphic information obtained
in soil and rock formations. This method is deployed in a single hole. It is used to define the Seismic
Site Class according to Eurocode 8, EN 1998-1:2004, Table 3.1.
Investigation point quantities at the proposed development are shown in Table 6-2. Sketches showing
the locations of the proposed exploratory holes are included in Appendix A.
Table 6-2: Summary of P&S Suspension Logging Seismic quantities at the proposed development
Electrical resistivity testing shall be undertaken as per ASTM G57 and to cover the range of soil
types encountered. Testing shall be done at all borehole and trial pit locations along the alignment
and at pump station location in accordance with schedule S1.14 of the Specification section of this
document.
P&S Suspension Logging Test to be realized according to ASTM D7400 / D7400M: Standard Test
Methods for Downhole Seismic Testing. Testing shall be done at the pumping station location in
accordance with schedule S1.14 of the Specification section of this document
6.4 Reporting
The Specification shall be the Specification for Ground Investigation published by Thomas Telford
Services Ltd in 2012, with information, amendments and additions as described in the following
schedules:
In so far as any Specification Amendment or Specification Addition may conflict with or be inconsistent
with any provision of the Specification for Ground Investigation, the Specification Amendment or
Specification Addition shall prevail.
Whereby the provisions of the Amendments any Clause is amended or substituted by another provision,
such Clause shall be read and construed as if such amendment were part of such Clause or as if the
Clause were drawn in its amended or substituted form.
The Specification Amendments or Specification Additions are numbered in accordance with the
numbering of the Specification of Ground Investigation. Specification Amendments comprise new
Clauses replacing or expanding on existing Clauses. Specification Additions comprise completely new
sections or Clauses numbered to follow the standard sections/Clauses.
Investigation Supervisor S1.2 The Employer’s Representative shall take the role of
Investigation Supervisor.
Description of site S1.3 The required ground investigation works are proposed as
described in Section 1 and 2 of this report.
Main works proposed S1.4 The purpose of this additional ground investigation
and purpose of this contract is the following:
contract
• To provide data on the ground conditions and
groundwater levels and assess the ground
conditions at the Site.
• 12 Standpipe Piezometers
Laboratory Testing:
Reporting:
Geology and ground S1.6 The current assessment of the geology of the site has
conditions been inferred from available information as provided in
Section 2 of this document. No assurance is given to its
accuracy.
General requirements S1.8 Upon receipt of an order from the Employer, the
(Specification Section 3) contractor is required to submit a programme clearly
particular stating when he can commence site operations and the
restrictions/relaxations completion date.
Breakdown delays
General
Surveying
The first drill run in each hole shall not exceed 1.0 m in
length. Subsequent drill runs shall not normally exceed
3.0 m in length and the core barrel shall be removed from
the drill hole as often as is required to obtain the best
possible core recovery. A minimum core recovery of 90%
is required. When any recovery is less than 90% from a
drill run then the next drill run shall utilize a plastic core
liner (if not already in use). If 90% recovery is still not
obtained, the core run with plastic liner shall be reduced
to 50% of the previous length, unless otherwise directed
by the Employer, and so on down to a minimum length of
0.5 m. The Employer may specify in situ Testing between
drill runs.
Sampling and monitoring S1.12 Where fine grained soils are encountered exhibiting
during intrusive cohesion a 100 mm undisturbed sample shall be
investigation recovered using a thin walled open tube sample (Shelby
(Specification Section 7) tube).
Particular
restrictions/relaxations All samples shall be stored in the shade and removed
daily to the contractor’s laboratory.
Bulk Sampling
Groundwater Sampling
Groundwater measurement
The test should penetrate the granular base and into the
soils beneath. The depth of test shall be a minimum 1.5m
from the surface of the pavement.
Geophysical testing S1.14 Electrical Resistivity Tests shall be conducted using the
(Specification Section 9) Wenner Electrode Configuration for field tests in
Particular accordance with ASTM G57.
restrictions/relaxations
The spacing of the electrodes shall be at 1m, 2m, 3m and
5m intervals in both directions.
CBR tests
Density
Daily records S1.18 Daily reports and driller’s logs shall be submitted to the
(Specification Section Employer at the start of the following day.
13) Particular
restrictions/relaxations Draft engineer’s logs shall be submitted to the Employer
within three working days after the completion of each
borehole.
Soil
(d) Hydrometer
Chemical
(b) pH value
Rock
• Flooding risk
• Settlement Analysis
Easting Northing
Boreholes
Pump Station
PS-BH-01 30 Refer to App. A Refer to App. A
Piezometer
P&S Suspension
Logging
Pump Station
PS-BH-02 15 “ “
Piezometer
CU-BH-01 10 “ “ Culvert
CU-BH-02 10 “ “ Culvert
Culvert
CU-BH-03 20 “ “
Piezometer
CU-BH-04 10 “ “ Culvert
CU-BH-05 10 “ “ Culvert
CU-BH-06 10 “ “ Culvert
CU-BH-07 10 “ “ Culvert
CU-BH-08 10 “ “ Culvert
Culvert
CU-BH-09 20 “ “ Piezometer
Wadi Crossing
CU-BH-10 10 “ “ Culvert
Culvert
CU-BH-11 20 “ “ Piezometer
Wadi Crossing
CU-BH-12 10 “ “ Culvert
CU-BH-13 10 “ “ Culvert
CU-BH-14 10 “ “ Culvert
CU-BH-15 10 “ “ Culvert
Culvert
Piezometer
CU-BH-16 20 “ “
Wadi Crossing
Urban Area
CU-BH-17 10 “ “ Culvert
CU-BH-18 10 “ “ Culvert
CU-BH-20 10 “ “ Culvert
CU-BH-21 10 “ “ Culvert
Culvert
CU-BH-22 20 “ “ Piezometer
Wadi Crossing
CU-BH-23 10 “ “ Culvert
CU-BH-24 10 “ “ Culvert
CU-BH-25 10 “ “ Culvert
CU-BH-26 10 “ “ Culvert
CU-BH-27 10 “ “ Culvert
CU-BH-28 10 “ “ Culvert
CU-BH-29 10 “ “ Culvert
CU-BH-30 10 “ “ Culvert
CU-BH-31 10 “ “ Culvert
CU-BH-32 10 “ “ Culvert
Culvert
CU-BH-33 20 “ “
Piezometer
CU-BH-34 10 “ “ Culvert
CU-BH-35 10 “ “ Culvert
CU-BH-36 10 “ “ Culvert
CU-BH-37 10 “ “ Culvert
CU-BH-38 10 “ “ Culvert
Culvert
CU-BH-39 20 “ “ Piezometer
Road Crossing
CU-BH-40 10 “ “ Culvert
CU-BH-41 10 “ “ Culvert
CU-BH-42 10 “ “ Culvert
Culvert
CU-BH-43 20 “ “ Piezometer
Road Crossing
CU-BH-44 10 “ “ Culvert
CU-BH-46 10 “ “ Culvert
CU-BH-47 10 “ “ Culvert
CU-BH-48 10 “ “ Culvert
Culvert
CU-BH-49 20 “ “
Piezometer
CU-BH-50 10 “ “ Culvert
Culvert
CU-BH-51 20 “ “
Piezometer
Trial Pit
CU-TP-01 3 “ “ Culvert
CU-TP-02 3 “ “ Culvert
CU-TP-03 3 “ “ Culvert
CU-TP-04 3 “ “ Culvert
CU-TP-05 3 “ “ Culvert
CU-TP-06 3 “ “ Culvert
CU-TP-07 3 “ “ Culvert
CU-TP-08 3 “ “ Culvert
CU-TP-09 3 “ “ Culvert
CU-TP-10 3 “ “ Culvert
CU-TP-11 3 “ “ Culvert
CU-TP-12 3 “ “ Culvert
CU-TP-13 3 “ “ Culvert
CU-TP-14 3 “ “ Culvert
CU-TP-15 3 “ “ Culvert
CU-TP-16 3 “ “ Culvert
CU-TP-17 3 “ “ Culvert
CU-TP-19 3 “ “ Culvert
CU-TP-20 3 “ “ Culvert
CU-TP-21 3 “ “ Culvert
CU-TP-22 3 “ “ Culvert
CU-TP-23 3 “ “ Culvert
CU-TP-24 3 “ “ Culvert
CU-TP-25 3 “ “ Culvert
CU-TP-26 3 “ “ Culvert
CU-TP-27 3 “ “ Culvert
CU-TP-28 3 “ “ Culvert
CU-TP-29 3 “ “ Culvert
CU-TP-30 3 “ “ Culvert
CU-TP-31 3 “ “ Culvert
CU-TP-32 3 “ “ Culvert
CU-TP-33 3 “ “ Culvert
CU-TP-34 3 “ “ Culvert
CU-TP-35 3 “ “ Culvert
CU-TP-36 3 “ “ Culvert
CU-TP-37 3 “ “ Culvert
CU-TP-38 3 “ “ Culvert
CU-TP-39 3 “ “ Culvert
CU-TP-40 3 “ “ Culvert
CU-TP-41 3 “ “ Culvert
CU-TP-42 3 “ “ Culvert
CU-TP-43 3 “ “ Culvert
CU-TP-44 3 “ “ Culvert
CU-TP-46 3 “ “ Culvert
CU-TP-47 3 “ “ Culvert
CU-TP-48 3 “ “ Culvert
CU-TP-49 3 “ “ Culvert
CU-TP-50 3 “ “ Culvert
CU-TP-51 3 “ “ Culvert
ERT-CU-01 to
ERT-CU-51
P&S Suspension
PS-DH-01 30 “ “
Logging
Note:
1) BH = Boreholes, TP = Trial Pit, ERT = Electrical Resistivity Test, DH= Down Hole
2) The proposed coordinates are indicative and shall be confirmed on-site. The GI Contractor can
shift the GI location away from the designated location, depending on the escarpment location
and any other site constraint.
3) Depth of Boreholes and trial pit can be modified according to site investigation during drilling
and excavation work with the agreement of the Engineer.
Personal Protective S3.6 All appropriate PPE and H & S equipment shall be
Equipment for Employer’s provided for the Employer’s Representative when
Representative visiting the site.
Clause 3.5.2 Add the The professional attendant shall be responsible for
following informing all personnel on site employed by the
Contractor of the specific requirements of this
Specification.
Clause 3.7.2 Delete the final The Contractor shall be responsible for locating all
sentence and buried utilities (services) at each exploratory hole
replace new location. As a minimum, available drawings from
sentence service utility company shall be checked. The
Contractor shall exercise the greatest care during
the execution of the Works to avoid damage to or
interference with any existing utilities and shall be
responsible for any such damage caused by him or
his agents directly or arising indirectly from
anything done or omitted to be done. The
Contractor shall carry out all temporary works
necessary to adequately support and protect any
existing services.
Clause 3.8.3 Delete the final Prior to commencing all Boreholes, the
sentence and Geotechnical Investigation Contractor shall scan
replace new for cables and investigate the presence of under
sentence Ground services by means of a CAT scan followed
by 1.2 m hand-excavation
Clause 3.18 Add the The Contractor shall obtain the greatest possible
following information from each test hole and careful
methods of working shall take priority over speed
of working.
Clause 5.4.3 Delete and The first drill run in each hole shall not exceed 1 m
replace with the in length. Subsequent drill runs shall not normally
following exceed 3 m in length and the core barrel shall be
removed from the drill hole as often as is required
to obtain the best possible core recovery. When
any recovery is less than 90% from a drill run then
the next drill run shall be reduced to 50% of the
previous length, unless otherwise directed by the
Employer’s Representative, and so on down to a
minimum length of 0.5 m.
Clause 5.4.5 Delete Sub- Depth shall be indicated on the core box by
clause 3 and durable markers at one metre intervals and at all
replace with the significant changes of strata and at the end of each
following drill run. Rigid core spacers shall be used to
indicate missing lengths. The location, exploratory
hole number and the depth of coring relating to the
contents of each box shall be clearly indicated in
indelible ink on labels, inside the box, on the top
and on each end of the box. All markers and labels
shall be such as to facilitate subsequent
photography. All core boxes other than those to be
retained by the Employer shall remain the property
of the Contractor.
Clause 3.27 Core Storage As part of the Contractor’s offices and stores, the
and Logging Geotechnical Investigation Contractor shall provide secure
Facilities and weatherproof facilities on site for the purpose of core
storage and logging. The logging facilities shall be suitable
for the purpose of preparation of the core for examination
(Clause 5.36), photography and examination of the core.
Clause 3.28.1 General All temporary building and facilities provided by the
Geotechnical Investigation Contractor shall comply with
Local Authority By-Laws and NEOM-NEV-PRC-501-01.00-
Interim Sustainability Requirements for the Built
Environment and NEOM-NEV-STD-501 Interim Standard
Sustainability Requirements for the Built Environment.
Clause 3.28.3 Other services The Geotechnical Investigation Contractor shall make his
own arrangements for the supply of electricity, telephone
or other services that he may require for the Site
Operations.
CU-TP14
CHAINAGE 26+602
0
+ 00 E=745977.803
27 N=3063040.237 CU-TP13
EGYPT RED SEA
CHAINAGE 25+000
0 E=747027.402
00 N=3061860.666
26+
PROJECT LOCATION
CU-TP12
0
00
CHAINAGE 23+000
NOTES & LEGEND
+
25
E=748632.602
CU-BH14 N=3060697.723
00
1. ALL COORDINATES ARE AS PER WGS 84: UTM ZONE 36.
CHAINAGE 26+000
+0
E=746351.001
24
2. COORDINATES SHOWN ON THE DRAWING ARE TENTATIVE AND BE CONFIRMED AS PER
CU-TP11
N=3062568.353 LOCAL CONDITIONS ON SITE.
00
CHAINAGE 21+000
+0
E=749732.855
23
N=3059086.849
CU-BH13 00
+0
CHAINAGE 24+000 22
E=747813.394
N=3061245.076 CU-TP10
00 CHAINAGE 19+000
+0 E=750659.845
21
CU-BH12 N=3057331.341
CHAINAGE 22+000
E=749227.436 00
+0
N=3059949.356 20
CU-TP09
CHAINAGE 17+000
19+
000 E=751236.118
N=3055416.676
LEGENDS
CU-BH11
CHAINAGE 20+235 BOREHOLE
E=750134.536
00
N=3058438.756 18+0 CU-TP08 TRIAL PIT
CHAINAGE 15+000
E=752453.988
N=3053881.841
00 BH : BOREHOLE
17+0 TP : TRIAL PIT
CU-BH10 DH : DOWNHOLE SEISMIC
CHAINAGE 18+000 PS : PUMP STATION
E=750961.875 CU : CULVERT
00
+0
N=3056378.304
CU-TP07
16
CHAINAGE 13+000
E=752865.319
00
+0 N=3051951.922
15
CU-BH09
CHAINAGE 15+578
00
E=752132.132 14+0
N=3054360.640
CU-TP06
CHAINAGE 11+000
13+000
E=752788.113
N=3050034.597
CU-BH08
CHAINAGE 14+000
E=752798.041
N=3052946.211 00
12+0
CU-TP05
CHAINAGE 9+000
00 ISSUED FOR APPROVAL CC 28.10.21
E=753873.072
N=3048357.922 REV DESCRIPTION APP DATE
0
00
11+ PURPOSE OF ISSUE:
CU-BH07
CHAINAGE 12+000
E=752951.995 0 CLIENT:
0
N=3050975.599 +0
10 CU-TP04
CHAINAGE 7+000
E=754573.720
00
9+0 N=3046494.133
CU-BH06
CHAINAGE 10+000
E=753347.868 0
8+00
N=3049205.939 DESIGN CONSULTANT NAME & LOGO (s): CONTRACTOR NAME & LOGO (s):
CU-TP03
CHAINAGE 5+000
E=755346.755
00
7+0 N=3044653.095
CU-BH05
CHAINAGE 8+000
E=754219.723
00
N=3047426.457 6+0
CU-TP02 DESIGN CONSULTANT / CONTRACTOR: NEOM'S REVIEW:
CHAINAGE 3+000
E=756164.227 DRAWN: SS 28.10.21
00
5+0 N=3042831.664
CHECKED: CB 28.10.21 CHECKED:
CU-BH04
CU-TP01 APPROVED: CC 28.10.21 APPROVED:
CHAINAGE 6+000
E=754944.699 CHAINAGE 1+000
N=3045568.074 000 E=757053.455
4+
C:\pw_workdir\lon002\singhs\d0272485\CH2-GEO-DRG-001001.dwg Oct 28, 2021 - 3:01PM SS021720
N=3041040.219
SCALE: 1:50000 SHEET SIZE: A1
CU-BH01 DISCIPLINE NAME:
CHAINAGE 0+090 GEOTECHNICAL
000
3+ E=757828.849
CU-BH03 N=3041325.375
CHAINAGE 4+000
GEOTECHNICAL INVESTIGATION PLAN
E=755719.602 PS-BH01
000
N=3043727.380 2+ DH-PS-01 OVERALL ALIGNMENT PLAN SHEET 1 OF 3
E=758194.412
E=3041336.825 PROJECT NAME:
000
0+ TRANSMISSION SYSTEM FROM
000 PS-TP01
1+ E=758320.243
CU-BH02 E=3041115.916
NEOM DESALINATION PLANT TO GAYAL
CHAINAGE 2+000
E=756608.837
N=3041935.939 PS-TP02
E=757846.236
NEOM
E=3041172.838
KINGDOM OF SAUDI ARABIA
PS-BH02
REGION WBS CODE CONTRACT CODE-WORK ORDER/SERVICE ORDER
E=757971.355
E=3040959.249
00
CU-TP30
+0
GULF OF AQABA
CHAINAGE 59+000
61
CU-BH31 E=732177.470
00
CHAINAGE 60+000 N=3091471.228
+0
E=731387.645
60
TABUK SAUDI ARABIA
00
N=3092084.561
CU-TP29
+0
GULF OF SUEZ
59
CHAINAGE 57+229
E=733340.541
00 N=3090166.756
8+0
5
CU-BH30
CHAINAGE 58+000 CU-TP28
E=732918.377 000 EGYPT RED SEA
7+ CHAINAGE 54+621
N=3090812.800 5
E=734934.418
N=3088172.426
00
6 +0 PROJECT LOCATION
5
CU-BH29 CU-TP27
CHAINAGE 56+000 CHAINAGE 53+000 NOTES & LEGEND
00
E=734114.108 E=735300.620
+0
N=3089224.787 N=3086741.435 1. ALL COORDINATES ARE AS PER WGS 84: UTM ZONE 36.
55
54+000 2. COORDINATES SHOWN ON THE DRAWING ARE TENTATIVE AND BE CONFIRMED AS PER
LOCAL CONDITIONS ON SITE.
CU-BH28
CU-TP26
CHAINAGE 54+000
CHAINAGE 51+000
E=735270.220 0
N=3087696.859 +00 E=736472.996
53 N=3085130.670
000
52+
CU-BH27
CHAINAGE 52+000 00 CU-TP25
E=735919.589 51+0 CHAINAGE 49+000
N=3085956.084 E=737095.567
N=3083238.209
50+
000 LEGENDS
CU-BH26 BOREHOLE
CHAINAGE 50+000 CU-TP24
E=736745.105 CHAINAGE 47+000 TRIAL PIT
0
N=3084168.630 +00 E=738207.940
49 N=3081591.675
BH : BOREHOLE
CU-BH25 000
TP : TRIAL PIT
CHAINAGE 48+000 48+
DH : DOWNHOLE SEISMIC
E=737723.240 PS : PUMP STATION
N=3082460.133 CU-TP23 CU : CULVERT
000 CHAINAGE 45+000
47+
E=738959.765
CU-BH24 N=3079780.861
CHAINAGE 46+000
E=738720.681 00
+0
N=3080736.676 46
00 CU-TP22
CU-BH23 45+0
CHAINAGE 43+000
CHAINAGE 44+000 E=739634.409
E=739238.826 N=3077903.745
N=3078820.690
00
44+0
CU-TP21
CU-BH22 000 CHAINAGE 41+000
CHAINAGE 42+000 43+ E=740496.826
E=740065.289 N=3076099.241 00 ISSUED FOR APPROVAL CC 28.10.21
N=3077001.336
REV DESCRIPTION APP DATE
000
42+ PURPOSE OF ISSUE:
CU-TP20 CLIENT:
CU-BH21 00 0
CHAINAGE 39+000
CHAINAGE 40+000 41+
E=741350.187
E=740924.366 N=3074290.453
N=3075195.255
000
40+
CU-TP19
CU-BH20 000
CHAINAGE 38+000 39+ CHAINAGE 37+000 DESIGN CONSULTANT NAME & LOGO (s): CONTRACTOR NAME & LOGO (s):
E=742047.822
E=741748.754
N=3072438.320
N=3073380.985
38+000
00 CU-TP18
CU-BH19 37+0 CHAINAGE 35+000
CHAINAGE 36+000 DESIGN CONSULTANT / CONTRACTOR: NEOM'S REVIEW:
E=742707.802
E=742358.075
N=3070555.264 DRAWN: SS 28.10.21
N=3071492.114
000 CHECKED: CB 28.10.21 CHECKED:
36+
APPROVED: CC 28.10.21 APPROVED:
CU-TP17
CU-BH18 00 0
35+ CHAINAGE 33+000
C:\pw_workdir\lon002\singhs\d0272485\CH2-GEO-DRG-001002.dwg Oct 28, 2021 - 3:04PM SS021720
CU-BH16
CHAINAGE 30+000 000 NEOM
31+
E=744811.936
N=3066059.399 KINGDOM OF SAUDI ARABIA
30+000
REGION WBS CODE CONTRACT CODE-WORK ORDER/SERVICE ORDER
GULF OF SUEZ
PROJECT LOCATION
GAYAL CU-TP49
CHAINAGE 97+000
E=702467.112
N=3112345.628
CU-TP48
97+240 CHAINAGE 95+000
97+000 E=704214.236
N=3111469.301
CU-TP47
00
CHAINAGE 93+000
+0
E=705957.645
96
N=3110489.236
00
LEGENDS
+0
CU-TP46
CU-BH49
95
CHAINAGE 91+000
CHAINAGE 96+000
00
E=707763.879
+0
E=703342.532 BOREHOLE
N=3109648.717 CU-TP45
94
N=3111959.333
0
CHAINAGE 89+571
0
+0
CHAINAGE 87+000
0
+0
E=705085.940 E=711594.996
92
000
TP : TRIAL PIT
000
CU-BH47 CU-TP43
DH : DOWNHOLE SEISMIC
90+
CHAINAGE 92+000 00
CHAINAGE 85+000
PS : PUMP STATION
89+0
E=706829.349 E=713314.059
00
CU-TP42 CU : CULVERT
N=3109999.204 N=3107573.625
88+0
CU-BH46
00
CHAINAGE 83+290
CHAINAGE 90+544
87+0
E=714896.342
0
E=708194.708
00
CU-BH45 N=3107159.027
+
N=3109499.000
86
CHAINAGE 88+562 CU-TP41
0
E=710081.994 CHAINAGE 81+000
00
N=3108898.783 CU-BH44 E=716930.635
+
85
CHAINAGE 86+000
84+000
N=3106122.501
000
E=712530.074
CU-TP40
N=3108194.404
83+
CHAINAGE 79+000
0
00
E=718739.223
CU-BH43
+
N=3105275.002
82
CHAINAGE 84+218 CU-TP39
00
E=713996.215
+0
CU-BH42 CHAINAGE 77+000
81
N=3107219.379 E=720576.680
00
CHAINAGE 82+000
N=3104485.222
0
E=716063.606
80+
000
N=3106620.759
79+
CU-BH41 CU-TP38
000
CHAINAGE 80+000 CHAINAGE 75+000
78+
E=717820.495 E=722089.986
000
00 ISSUED FOR APPROVAL CC 28.10.21
N=3105669.892 N=3103279.282
77+
CU-BH40 REV DESCRIPTION APP DATE
000
CHAINAGE 78+000 PURPOSE OF ISSUE:
76+
E=719657.952
N=3104880.112
0
CU-BH39 +00 CU-TP37 CLIENT:
CHAINAGE 76+127 75
CHAINAGE 73+071
E=721360.855 E=723055.985
N=3104102.835 0
+00 N=3101626.987
74
CU-BH38
CHAINAGE 74+000 000
E=722659.850 73+
N=3102457.543 CU-TP36 DESIGN CONSULTANT NAME & LOGO (s): CONTRACTOR NAME & LOGO (s):
CHAINAGE 71+000
E=723724.700 CU-BH51
000 N=3099666.801 CHAINAGE 4+000
72+ E=728093.509
N=3098844.504
CU-BH37
CHAINAGE 72+000
000 CU-TP51
E=723401.823 71+
N=3100613.242 CU-TP35 CHAINAGE 3+000
CHAINAGE 69+000 E=728283.622 DESIGN CONSULTANT / CONTRACTOR: NEOM'S REVIEW:
E=724577.137 N=3097864.683
000 N=3097858.212 DRAWN: SS 28.10.21
70+
CU-BH50 CHECKED: CB 28.10.21 CHECKED:
CHAINAGE 2+000
CU-BH36 APPROVED: CC 28.10.21 APPROVED:
E=728305.073
CHAINAGE 70+000
000 N=3096865.037
E=724146.029 69+ CU-TP34
N=3098760.512 CHAINAGE 67+000
C:\pw_workdir\lon002\singhs\d0272485\CH2-GEO-DRG-001003.dwg Oct 28, 2021 - 3:05PM SS021720
0
GEOTECHNICAL
0
E=728209.976
+0
68
N=3095872.139
CU-BH35
00
CHAINAGE 68+000 GEOTECHNICAL INVESTIGATION PLAN
+0
67
E=725124.691 CU-BH33
N=3097053.211
00
CHAINAGE 64+000 OVERALL ALIGNMENT PLAN SHEET 3 OF 3
+0
E=728315.677
66
CU-BH34 N=3094645.434 PROJECT NAME:
00
CHAINAGE 66+000 TRANSMISSION SYSTEM FROM
+0
CU-TP32
65
E=726747.328
CHAINAGE 63+000
N=3095884.002 NEOM DESALINATION PLANT TO GAYAL
00
E=729078.051
+0
N=3093998.298
64
CU-TP33
CHAINAGE 65+000 CU-TP31
00
E=727553.302 CHAINAGE 61+000 NEOM
+0
N=3095292.570 E=730602.800
63
CU-BH32
CHAINAGE 62+000 N=3092704.026 KINGDOM OF SAUDI ARABIA
00
E=729840.426
+0
REGION WBS CODE CONTRACT CODE-WORK ORDER/SERVICE ORDER
62
N=3093351.162
00
+0
61
CU-BH31 DRAWING NUMBER
00
CHAINAGE 60+000
+0
E=731387.645 ORIGINATOR DISCIPLINE DOCUMENT TYPE SEQUENTIAL NUMBER REV NO.
60
00
N=3092084.561
+0
CH2 GEO DRG 001003 00
59
Appendix A: Exploratory Holes Location Plan