11-181000-4800000121-RGF-GEO-RPT-000004-00 SO-003 Factual GI Report
11-181000-4800000121-RGF-GEO-RPT-000004-00 SO-003 Factual GI Report
Mohammed
01 Original For Review 30.03.2022 Shahzad Shafiq Hamid Ismail
Aboueishe
Signatures:
11-180000-4800000121-RGF-GEO-RPT-000004 R e v 0 1 , M a r c h 2 0 2 2
Document approval
Job Title Geotechnical Engineer Sr. Geotechnical Engineer Manager, Western Region
TABLE OF CONTENTS
3. FIELD INVESTIGATION 11
3.1 Excavation of Trial Pits 11
3.2 Percolation Test 11
3.3 Insitu CBR Test 12
3.3.1 Procedure 13
3.4 Plate Load Tests 13
4. LABORATORY TESTING 15
4.1 General 15
4.2 Soil Classification Tests 16
4.3 Proctor Test and CBR Tests 16
4.4 Chemical Tests 16
FIGURES
TABLES
Laydown No. 02
- Trial Pit Logs
- Field Density Tests
- Double Cycle Plate Load Tests
- Percolation Test
- Insitu CBR Tests
DESCRIPTION
-------------------------------------------------------------------------------------------------------------------------
APPENDIX-A FIELD DATA
Laydown No. 05
- Trial Pit Logs
- Field Density Tests
- Double Cycle Plate Load Tests
- Percolation Test
- Insitu CBR Tests
APPENDIX-C PHOTOGRAPHS
Laydown No. 01
- Trial Pits
Laydown No. 03
- Trial Pits
Laydown No. 05
- Trial Pits
This factual report relates to three (3) Laydown Areas (LD-1, LD-3 & LD-5).
The scope of work for Laydown Areas includes excavation of trial pits as well
as relevant insitu & laboratory testing. All field and laboratory works were
performed according to the stipulated scope and specifications.
Upon receipt of the Service Order from Neom and getting permissions from
concerned authorities, Riyadh Geotechnique and Foundations (RGF)
mobilized necessary equipment and personnel at Laydown site on
December 27, 2021 on the project site and the field investigation was
completed on January 29, 2022.
The field test results are presented in APPENDIX-A, whereas the laboratory
test results are presented in APPENDIX-B of this report. The as-built
coordinates and elevations of the trial pits are shown on TABLE-A.
Photographs of trial pits are presented as a separate APPENDIX-C to this
report. Laboratory testing schedules for trial pits were prepared by RGF and
forwarded to EPM for necessary approval. The approved laboratory testing
schedules are presented in APPENDIX-D of this report.
1. Laydown No. 01
a) Excavation of six (6) trial pits down to 3.0 meters depth or refusal,
whichever comes first, field density test and collection of bulk
samples for classification & CBR testing.
b) Performance of six (6) double cycle Plate Load tests at 0.5 meter
depth in trial pits.
d) Performance of six (6) insitu CBR test at 0.5 meter depth in trial pits.
2. Laydown No. 03
a) Excavation of nine (9) trial pits down to 3.0 meters depth or refusal,
whichever comes first, field density test and collection of bulk
samples for classification & CBR testing.
b) Performance of nine (9) double cycle Plate Load tests at 0.5 meter
depth in trial pits.
d) Performance of nine (9) insitu CBR test at 0.5 meter depth in trial
pits.
3 Laydown No. 05
a) Excavation of nine (9) trial pits down to 3.0 meters depth or refusal,
whichever comes first, field density test and collection of bulk
samples for classification & CBR testing.
b) Performance of nine (9) double cycle Plate Load tests at 0.5 meter
depth in trial pits.
d) Performance of nine (9) insitu CBR test at 0.5 meter depth in trial
pits.
q=
Vp= Storage volume of the pit between 75% and 25% of the water depth
ap= Area of the base and sides of the pit at 50% of the water depth
tp= Elapsed time to empty between 75% and 25% of the water depth
In-situ field California Bearing Ratio tests were performed at 0.5 meter depth
in trial pits to determine in situ CBR value in accordance with ASTM D4429
at designated locations.
A loaded truck was used for applying the load by means of a mechanical
screw jack. The other equipment used are 5 cm diameter loading plunger,
extension rods, jacks, proving ring assembly, dial gauge, datum frame,
annular surcharge plate 25 cm in diameter and 5 kg. in weight, with a central
hole and slot width of 5.32 cm.
The load is applied to the plunger by means of the jack such that the rate of
penetration is approximately 1.3mm/minute. The load readings are noted for
penetrations 0.0, 0.6, 1.27, 1.91, 2.54, 3.81, 5.08, 6.35, 7.62, 8.89 and
10.16mm. The load is released, and moisture content specimen is taken
from underneath the plunger.
2. The loading jack, the reference beams and the gauges for observing
settlements were installed.
3. The test plate was loaded in equal load increments to the maximum plate
pressure. Plate settlements were noted against each load increment.
4. After reaching the maximum plate pressure the plate was unloaded in
three decrements and rebound for each decrement was recorded.
5. All pressure versus settlement data was recorded in tabular form and
presented as pressure versus settlement curves for each plate load test.
4.1 GENERAL
The samples retrieved from the boreholes and trial pits were logged,
examined in the field, preserved and transported to RGF testing laboratory
in Jeddah for relevant laboratory testing. Laboratory test schedules were
prepared for each exploratory borehole and presented to EPM for approval.
The laboratory test results are presented in APPENDIX-B of this report.
Soil samples collected from the boreholes were subjected to the following
tests as per latest ASTM / BS or equivalent Standards.
Proctor tests and CBR tests were performed on the bulk soil samples
according to testing schedule. The tests were performed according to the
ASTM D1557 and ASTM D1883, respectively.
Chemical tests were performed on the selected soil samples. The testing
program included determination of pH (BS-1377), Acid Soluble Chloride
(BS-1377), Acid Soluble Sulphate (BS-1377) and Carbonate Contents
(ASTM D4737) of soil samples.
The Bad Quadrangle (Sheet 28A) & Al-Muwaylih (Sheet 27A) lies in the
north province of Arabian Shield, on the eastern edge of Red Sea rift
(between latitude 28o 00’ and 29o 00’ N and longitude 34o30’ and 36o30’.
FIGURE-2 shows the location of the Al- Bad & Al-Muwaylih Quadrangle
(sheet 28A & 27A). The quadrangle is in the northern part of the Hijaz
region. A flat low-laying coastal plain is succeeded eastwards by the rock
mountains. The regional geology applicable to NEOM site is presented as
follows:
Oldest deposits in this site area are numerous small granitic plugs and
irregular bodies that are intruded into other formations and the oldest granitic
plutons. The small intrusions are diffucklt to recognise. They are variable in
mineralogy, composition and appearance. Most consists of medium grained
leucocratic monzogranite, some of syenogranite and micrograinte, there
intrusions are of various ages and some shows resemblances to Aliya or
Lawz units.
Paleozoic sedimentary rocks crop-out in the western area of the site. The
Cambrian Siq Sandstone unconformably overlies the Proterozoic basement.
The lower part of the Khuraybah formation consists of reefal limestone that
flanks the edge of the proterozoic basement rocks along the al-Khurabah
coastal section.
Quaternary deposits in the area are of continental and marine origin. Along
the Al-Khurabah coastal section, alluvial gravel sheets and terraces slope
CLIENT :
NEOM
PROJECT NAME:
NEAM DESALINATION PLANT TO
GAYAL TRANSMISSION SYSTEM
CONTRACTOR :
FIGURE 2
TABLE-B
SUMMARY OF LABORATORY TESTS RESULTS OF TRIAL PITS (LD-01)
CBR
TRIAL Natural
Sample % Passing Through Open.Sieve (mm) Atterberg Limit Modified Proctor
PIT Moisture
Depth (m) Description of Material Symbol AASHTO
90% MDD 95% MDD 100% MDD
TP-01 B-1 0.60 100 98 53 5 1.30 - NP - 1.92 6.1 13 15 18 21 24 28 Brown, poorly-graded SAND. SP A-3
" B-2 1.20 97 95 50 5 1.36 - NP - - - - - - - - - Brown, poorly-graded SAND with silt. SP-SM A-3
" S-6 2.50 100 95 25 5 0.82 - NP - - - - - - - - - Brown, poorly-graded SAND with silt. SP-SM A-1-b
TP-02 B-1 0.60 97 90 43 6 1.82 - NP - 1.94 6.1 15 18 21 24 26 30 Brown, poorly-graded SAND with silt. SP-SM A-1-b
" S-5 2.00 95 92 35 6 0.82 - NP - - - - - - - - - Brown, poorly-graded SAND with silt. SP-SM A-1-b
T-04 B-1 0.60 100 98 50 8 2.00 - NP - 1.93 6.1 14 16 20 23 25 28 Brown, poorly-graded SAND with silt. SP-SM A-1-b
TABLE-B
SUMMARY OF LABORATORY TESTS RESULTS OF TRIAL PITS (LD-01)
CBR
TRIAL Natural
Sample % Passing Through Open.Sieve (mm) Atterberg Limit Modified Proctor
PIT Moisture
Depth (m) Description of Material Symbol AASHTO
90% MDD 95% MDD 100% MDD
" S-6 2.50 98 93 34 10 1.71 - NP - - - - - - - - - Brown, well-graded SAND with silt. SW-SM A-1-b
" B-2 1.00 100 98 76 31 1.89 - NP - 2.02 6.0 15 18 20 24 28 32 Light brown, silty SAND. SM A-2-4
TP-06 B-1 0.60 100 97 42 8 4.86 - NP - 1.96 6.9 13 16 19 22 25 29 Brown, well-graded SAND with silt. SW-SM A-1-b
" B-2 1.10 96 88 23 6 1.94 - NP - - - - - - - - - Brown, well-graded SAND with silt. SW-SM A-1-b
- - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - -
TABLE-C
SUMMARY OF LABORATORY TESTS RESULTS OF TRIAL PITS (LD-03)
CBR
TRIAL Natural
Sample % Passing Through Open.Sieve (mm) Atterberg Limit Modified Proctor
PIT Moisture
Depth (m) Description of Material Symbol AASHTO
90% MDD 95% MDD 100% MDD
TP-03 B-1 0.60 100 95 33 6 4.93 - NP - - - - - - - - - Greyish brown, poorly-graded SAND with silt. SP-SM A-1-b
" B-2 1.20 100 95 27 6 4.50 - NP - 1.95 6.2 12 14 18 21 23 27 Greyish brown, well-graded SAND with silt. SW-SM A-1-b
" B-3 1.80 93 87 29 71 3.22 - NP - - - - - - - - - Greyish brown, well-graded SAND with silt. SW-SM A-1-b
TABLE-C
SUMMARY OF LABORATORY TESTS RESULTS OF TRIAL PITS (LD-03)
CBR
TRIAL Natural
Sample % Passing Through Open.Sieve (mm) Atterberg Limit Modified Proctor
PIT Moisture
Depth (m) Description of Material Symbol AASHTO
90% MDD 95% MDD 100% MDD
" B-3 2.00 99 93 25 6 3.8 30 22 8 - - - - - - - - Greyish brown, well-graded SAND with clay. SW-SC A-2-4
TP-07 B-1 0.6 100 98 32 3 2.78 - NP - 1.98 6.9 13 17 19 23 24 29 Brown, poorly-graded SAND. SP A-1-b
" S-7 2.5 94 78 22 3 4.48 - NP - Brown, poorly-graded SAND with gravel. SP A-1-b
TABLE-C
SUMMARY OF LABORATORY TESTS RESULTS OF TRIAL PITS (LD-03)
CBR
TRIAL Natural
Sample % Passing Through Open.Sieve (mm) Atterberg Limit Modified Proctor
PIT Moisture
Depth (m) Description of Material Symbol AASHTO
90% MDD 95% MDD 100% MDD
" B-3 1.20 93 82 23 3 1.76 - NP - - - - - - - - - Brown, well-graded SAND with gravel. SW A-1-b
- - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - -
TABLE-D
SUMMARY OF LABORATORY TESTS RESULTS OF TRIAL PITS (LD-05)
CBR
TRIAL Natural
Sample % Passing Through Open.Sieve (mm) Atterberg Limit Modified Proctor
PIT Moisture
Depth (m) Description of Material Symbol AASHTO
90% MDD 95% MDD 100% MDD
" S-5 2.00 80 45 9 2 1.01 - NP - - - - - - - - - Brown, well-graded GRAVEL with sand. GW A-1-a
TP-02 B-1 0.60 84 54 11 5 2.62 - NP - 2.16 7.0 14 16 38 43 57 62 Brown, well-graded SAND with gravel. SW A-1-a
" S-4 1.50 84 59 12 5 3.36 - NP - - - - - - - - - Brown, well-graded SAND with gravel. SW A-1-a
TP-04 B-1 0.60 68 39 8 3 3.13 - NP - 2.19 6.7 14 16 38 42 63 68 Brown, well-graded GRAVEL with sand. GW A-1-a
TP-05 B-2 1.20 93 66 23 13 7.08 - NP - 2.18 7.1 15 18 40 45 60 65 Brown, silty SAND with gravel. SM A-1-a
" S-5 2.00 79 45 8 5 2.16 - NP - - - - - - - - - Brown, well-graded GRAVEL with sand. GW A-1-a
TABLE-D
SUMMARY OF LABORATORY TESTS RESULTS OF TRIAL PITS (LD-05)
CBR
TRIAL Natural
Sample % Passing Through Open.Sieve (mm) Atterberg Limit Modified Proctor
PIT Moisture
Depth (m) Description of Material Symbol AASHTO
90% MDD 95% MDD 100% MDD
" S-5 1.50 97 85 60 18 1.31 - NP - - - - - - - - - Brown, silty SAND with gravel. SM A-2-4
TP-08 B-1 0.60 87 66 24 13 1.85 - NP - 2.07 6.5 26 31 42 46 58 64 Brown, silty SAND with gravel. SM A-1-a
- - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - -
SAMPLE
(m)
Light brown, silty medium to fine SAND with gravel. Bulk Sample at 0.60 & 1.20
Gravels are angular to sub-rounded medium to meters
coarse igneous origin.
B-1
1
Field CBR Test at 0.50
B-2 meters
Plate Load Test at 0.50
meters
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Soakaway Test performed
3
----End of Trial Pit at 3.00 meters---- Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00 meters
5
TRIAL PITS GAYAL-LD-1.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 02
SAMPLE
(m)
Light brown, silty medium to fine SAND with gravel. Bulk Sample at 0.60 & 1.20
Gravels are angular to sub-rounded medium to meters
coarse of igneous origin.
B-1
1
Field CBR Test at 0.50
B-2 meters
Plate Load Test at 0.50
meters
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Soakaway Test performed
3
----End of Trial Pit at 3.00 meters---- Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00 meters
5
TRIAL PITS GAYAL-LD-1.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 03
SAMPLE
(m)
3
----End of Trial Pit at 3.00 meters---- Small Sample at 0.00, 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
meters
5
TRIAL PITS GAYAL-LD-1.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 04
SAMPLE
(m)
1
Field CBR Test at 0.50
B-2 meters
Plate Load Test at 0.50
meters
From 1.60~3.00 meters B-3 Field Density Test at 0.50,
Light brown, poorly-graded medium to fine SAND. 1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Soakaway Test performed
Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00 meters
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-1.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 05
SAMPLE
(m)
1
B-2 Field CBR Test at 0.50
From 1.00~3.00 meters B-3 meters
Greyish brown, silty medium to fine SAND with Plate Load Test at 0.50
gravel, cobble & boulders. Gravel and are angular meters
to sub-rounded of limestone. Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Soakaway Test performed
5
TRIAL PITS GAYAL-LD-1.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 06
SAMPLE
(m)
1
Field CBR Test at 0.50
From 1.10~3.00 meters B-2 meters
Greyish brown, weakly cemented silty SAND with B-3 Plate Load Test at 0.50
gravel and cobble of cemented sand. meters
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Soakaway Test performed
Small Sample at 0.00 ,0.50,
1.00, 1.10, 1.50, 2.00, 2.50 &
3.00 meters
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-1.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
FIELD DENSITY TESTS
LAYDOWN No. 1
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-1 / TP - 01 REPORT DATE : 30.01.2022
SAMPLING DATE : - TEST START DATE : 24.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 25.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-1 / TP - 02 REPORT DATE : 30.01.2022
SAMPLING DATE : - TEST START DATE : 24.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 25.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-1 / TP - 03 REPORT DATE : 30.01.2022
SAMPLING DATE : - TEST START DATE : 25.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 26.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-1 / TP - 04 REPORT DATE : 30.01.2022
SAMPLING DATE : - TEST START DATE : 26.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 27.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-1 / TP - 05 REPORT DATE : 30.01.2022
SAMPLING DATE : - TEST START DATE : 27.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 28.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-1 / TP - 06 REPORT DATE : 06.02.2022
SAMPLING DATE : - TEST START DATE : 29.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 30.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
DOUBLE CYCLE PLATE LOAD TESTS
LAYDOWN No. 1
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 4.08 2.52
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
1.0
2.0
Settlement (mm)
3.0
4.0
5.0
6.0
7.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-1 / TP - 02
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 24.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 6.38
30 3723.0 1.32 1.14 30 3723.0 1.32 7.97
60 7486.0 2.65 2.38 60 7486.0 2.65 9.91
80 9924.6 3.51 3.75 80 9924.6 3.51 11.53
100 12627.6 4.47 5.30 100 12627.6 4.47 13.91
120 15136.8 5.35 6.78 120 15136.8 5.35 14.78
140 17605.2 6.23 8.04 140 17605.2 6.23 15.97
120 15136.8 5.35 8.01 120 15136.8 5.35 15.70
100 12627.6 4.47 7.94 100 12627.6 4.47 15.60
80 9924.6 3.51 7.80 80 9924.6 3.51 15.45
60 7486.0 2.65 7.45 60 7486.0 2.65 15.18
30 3723.0 1.32 6.97 30 3723.0 1.32 14.77
0 0.0 0.00 6.38 0 0.0 0.00 14.14
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 8.04 6.38
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
6.0
Settlement (mm)
8.0
10.0
12.0
14.0
16.0
18.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-1 / TP - 03
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 25.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 13.80
30 3723.0 1.32 3.08 30 3723.0 1.32 15.24
60 7486.0 2.65 7.72 60 7486.0 2.65 17.12
80 9924.6 3.51 9.95 80 9924.6 3.51 18.43
100 12627.6 4.47 12.04 100 12627.6 4.47 19.22
120 15136.8 5.35 14.05 120 15136.8 5.35 20.12
140 17605.2 6.23 15.86 140 17605.2 6.23 20.99
120 15136.8 5.35 15.82 120 15136.8 5.35 20.95
100 12627.6 4.47 15.74 100 12627.6 4.47 20.87
80 9924.6 3.51 15.59 80 9924.6 3.51 20.68
60 7486.0 2.65 15.33 60 7486.0 2.65 20.42
30 3723.0 1.32 14.91 30 3723.0 1.32 19.96
0 0.0 0.00 13.80 0 0.0 0.00 19.30
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 15.86 13.80
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
5.0
Settlement (mm)
10.0
15.0
20.0
25.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-1 / TP - 04
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 26.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 3.59
30 3723.0 1.32 1.02 30 3723.0 1.32 4.15
60 7486.0 2.65 3.08 60 7486.0 2.65 4.69
80 9924.6 3.51 3.76 80 9924.6 3.51 4.93
100 12627.6 4.47 4.38 100 12627.6 4.47 5.23
120 15136.8 5.35 4.82 120 15136.8 5.35 5.81
140 17605.2 6.23 4.93 140 17605.2 6.23 6.40
120 15136.8 5.35 4.88 120 15136.8 5.35 6.36
100 12627.6 4.47 4.79 100 12627.6 4.47 6.31
80 9924.6 3.51 4.65 80 9924.6 3.51 6.20
60 7486.0 2.65 4.39 60 7486.0 2.65 5.84
30 3723.0 1.32 4.03 30 3723.0 1.32 5.34
0 0.0 0.00 3.59 0 0.0 0.00 4.75
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 4.93 3.59
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
1.0
2.0
Settlement (mm)
3.0
4.0
5.0
6.0
7.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-1 / TP - 05
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 27.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 4.76
30 3723.0 1.32 1.74 30 3723.0 1.32 6.90
60 7486.0 2.65 4.22 60 7486.0 2.65 10.00
80 9924.6 3.51 5.37 80 9924.6 3.51 12.54
100 12627.6 4.47 6.55 100 12627.6 4.47 14.18
120 15136.8 5.35 7.66 120 15136.8 5.35 15.61
140 17605.2 6.23 8.29 140 17605.2 6.23 17.08
120 15136.8 5.35 8.24 120 15136.8 5.35 17.05
100 12627.6 4.47 8.13 100 12627.6 4.47 16.92
80 9924.6 3.51 7.74 80 9924.6 3.51 16.64
60 7486.0 2.65 7.05 60 7486.0 2.65 16.19
30 3723.0 1.32 5.94 30 3723.0 1.32 15.63
0 0.0 0.00 4.76 0 0.0 0.00 15.04
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 8.29 4.76
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
6.0
Settlement (mm)
8.0
10.0
12.0
14.0
16.0
18.0
20.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-1 / TP - 06
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 29.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 4.16
30 3723.0 1.32 1.99 30 3723.0 1.32 5.73
60 7486.0 2.65 3.48 60 7486.0 2.65 7.83
80 9924.6 3.51 4.38 80 9924.6 3.51 9.91
100 12627.6 4.47 5.49 100 12627.6 4.47 11.47
120 15136.8 5.35 6.30 120 15136.8 5.35 12.88
140 17605.2 6.23 6.79 140 17605.2 6.23 13.91
120 15136.8 5.35 6.74 120 15136.8 5.35 13.86
100 12627.6 4.47 6.62 100 12627.6 4.47 13.75
80 9924.6 3.51 6.31 80 9924.6 3.51 13.53
60 7486.0 2.65 4.96 60 7486.0 2.65 12.96
30 3723.0 1.32 4.71 30 3723.0 1.32 12.33
0 0.0 0.00 4.16 0 0.0 0.00 11.53
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 6.79 4.16
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
14.0
16.0
UNSOAKED SOAKED
PERCOLATION TEST
LAYDOWN No. 1
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 20 40 60 80 100 120 140 160 180
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 50 100 150 200 250
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 20 40 60 80 100 120 140 160 180 200
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 20 40 60 80 100 120
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 20 40 60 80 100 120 140
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 20 40 60 80 100 120
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
0.0000 0.00 0 0 70
0.0250 3.00 27 9
60
0.0500 5.00 46 15
50
0.0750 7.00 64 21
40
0.1000 11.00 101 34 3
30
0.1500 14.00 128 43
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0000 0.00 0 0 70
0.0250 3.00 27 9
60
0.0500 5.00 46 15
50
0.0750 8.00 73 24
40
0.1000 11.00 101 34 3
30
0.1500 14.00 128 43
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0000 0.00 0 0
120
0.0250 4.00 37 12
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0250 3.00 27 9
80
0.0500 6.00 55 18
0.0750 9.00 82 27 60
0.1000 13.00 119 40 4
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0000 0.00 0 0
80
0.0250 3.00 27 9
0.0500 5.00 46 15
60
0.0750 8.00 73 24
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0250 3.00 27 9
80
0.0500 6.00 55 18
0.0750 9.00 82 27 60
0.1000 13.00 119 40 4
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TRIAL PIT LOGS
LAYDOWN No. 3
SAMPLE
(m)
Brownish grey, silty medium to fine SAND with Bulk Sample at 0.60 & 1.20
gravel and cobbles. Gravels are angular to meters
sub-rounded medium to coarse of igneous origin.
B-1
1
Field CBR Test at 0.50
B-2 meters
Plate Load Test at 0.50
meters
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Soakaway Test performed
3
----End of Trial Pit at 3.00 meters---- Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00 meters
5
TRIAL PITS GAYAL-LD-3.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 02
SAMPLE
(m)
Brown, silty medium to fine SAND with gravel. Bulk Sample at 0.60 & 1.20
Gravels are angular to sub-rounded medium to meters
coarse of igneous origin.
B-1
1
Field CBR Test at 0.50
B-2 meters
Plate Load Test at 0.50
meters
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Soakaway Test performed
3
----End of Trial Pit at 3.00 meters---- Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00 meters
5
TRIAL PITS GAYAL-LD-3.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 03
SAMPLE
(m)
Brown, fine to medium SAND with gravel, cobbles B-3 Field Density Test at 0.50,
2 and boulders. (Slightly weathered limestone). 1.00, 1.50 & 2.00 meters
3
Small Sample at 0.50, 1.00,
1.50, 2.00 & 2.30 meters
5
TRIAL PITS GAYAL-LD-3.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 04
SAMPLE
(m)
1
Field CBR Test at 0.50
B-2 meters
Plate Load Test at 0.50
meters
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
From 2.00~3.00 meters B-3
Brown, slightly cemented silty medium to fine Soakaway Test performed
SAND wtih gravel. Gravels are angular to Small Sample at
sub-rounded medium to coarse of igneous origin. 0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00 meters
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-3.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 05
SAMPLE
(m)
1
Field CBR Test at 0.50
From 0.60~3.00 meters B-2 meters
Greyish brown, silty fine to medium SAND with Plate Load Test at 0.50
gravel and boulders. Gravels are angular fine of meters
igneous origin. Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Soakaway Test performed
Small Sample at 0.00 ,0.50,
0.60, 1.00, 1.50, 2.00, 2.50 &
3.00 meters
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-3.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 06
SAMPLE
(m)
2
From 2.00~3.00 meters B-3 Field Density Test at 0.50,
Brown, slightly cemented silty medium to fine 1.00, 1.50, 2.00, 2.50 & 3.00
SAND with gravel. Gravels are angular to meters
sub-rounded medium to coarse of igneous origin. Soakaway Test performed
3
----End of Trial Pit at 3.00 meters---- Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00 meters
5
TRIAL PITS GAYAL-LD-3.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 07
SAMPLE
(m)
3
----End of Trial Pit at 3.00 meters---- Small Sample at 0.00,0.50,
1.00, 1.30, 1.50, 2.00, 2.50 &
3.00 meters
5
TRIAL PITS GAYAL-LD-3.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 08
SAMPLE
(m)
2
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
meters
Soakaway Test performed
3
----End of Trial Pit at 3.00 meters---- Small Sample at 0.00,0.50,
0.80, 1.00, 1.50, 2.00, 2.50 &
3.00 meters
5
TRIAL PITS GAYAL-LD-3.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 09
SAMPLE
(m)
2
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
meters
Soakaway Test performed
3
----End of Trial Pit at 3.00 meters---- Small Sample at 0.00, 0.30,
0.50, 1.00, 1.50, 2.00, 2.50 &
3.00 meters
5
TRIAL PITS GAYAL-LD-3.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
FIELD DENSITY TESTS
LAYDOWN No. 3
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-3 / TP - 01 REPORT DATE : 29.01.2022
SAMPLING DATE : - TEST START DATE : 15.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 16.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-3 / TP - 02 REPORT DATE : 29.01.2022
SAMPLING DATE : - TEST START DATE : 16.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 17.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-3 / TP - 03 REPORT DATE : 29.01.2022
SAMPLING DATE : - TEST START DATE : 16.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 17.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4
LAYER : - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-3 / TP - 04 REPORT DATE : 29.01.2022
SAMPLING DATE : - TEST START DATE : 17.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 18.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.00 2.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-3 / TP - 05 REPORT DATE : 23.01.2022
SAMPLING DATE : - TEST START DATE : 17.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 18.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.00 2.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-3 / TP - 06 REPORT DATE : 23.01.2022
SAMPLING DATE : - TEST START DATE : 18.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 19.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.00 2.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-3 / TP - 07 REPORT DATE : 23.01.2022
SAMPLING DATE : - TEST START DATE : 20.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 21.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.00 2.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-3 / TP - 08 REPORT DATE : 23.01.2022
SAMPLING DATE : - TEST START DATE : 20.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 21.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.00 2.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-3 / TP - 09 REPORT DATE : 23.01.2022
SAMPLING DATE : - TEST START DATE : 22.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 23.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.00 2.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
DOUBLE CYCLE PLATE LOAD TESTS
LAYDOWN No. 3
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 7.61 5.61
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-3 / TP - 02
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 16.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 27.40
30 3723.0 1.32 3.65 30 3723.0 1.32 30.55
60 7486.0 2.65 9.16 60 7486.0 2.65 33.34
80 9924.6 3.51 14.02 80 9924.6 3.51 36.33
100 12627.6 4.47 18.42 100 12627.6 4.47 38.94
120 15136.8 5.35 22.42 120 15136.8 5.35 41.00
140 17605.2 6.23 28.21 140 17605.2 6.23 42.98
120 15136.8 5.35 28.15 120 15136.8 5.35 42.63
100 12627.6 4.47 28.05 100 12627.6 4.47 42.54
80 9924.6 3.51 27.92 80 9924.6 3.51 42.30
60 7486.0 2.65 27.79 60 7486.0 2.65 42.01
30 3723.0 1.32 27.66 30 3723.0 1.32 41.58
0 0.0 0.00 27.40 0 0.0 0.00 41.11
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 28.21 27.40
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
5.0
10.0
15.0
Settlement (mm)
20.0
25.0
30.0
35.0
40.0
45.0
50.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-3 / TP - 03
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 16.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 7.40
30 3723.0 1.32 1.32 30 3723.0 1.32 8.58
60 7486.0 2.65 2.93 60 7486.0 2.65 10.06
80 9924.6 3.51 5.28 80 9924.6 3.51 10.93
100 12627.6 4.47 7.54 100 12627.6 4.47 12.40
120 15136.8 5.35 9.64 120 15136.8 5.35 13.65
140 17605.2 6.23 11.82 140 17605.2 6.23 14.96
120 15136.8 5.35 11.77 120 15136.8 5.35 14.72
100 12627.6 4.47 11.67 100 12627.6 4.47 14.70
80 9924.6 3.51 11.21 80 9924.6 3.51 14.64
60 7486.0 2.65 10.41 60 7486.0 2.65 13.50
30 3723.0 1.32 9.26 30 3723.0 1.32 12.82
0 0.0 0.00 7.40 0 0.0 0.00 11.30
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 11.82 7.40
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
14.0
16.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-3 / TP - 04
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 17.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 5.44
30 3723.0 1.32 1.87 30 3723.0 1.32 6.34
60 7486.0 2.65 3.50 60 7486.0 2.65 6.94
80 9924.6 3.51 4.28 80 9924.6 3.51 8.04
100 12627.6 4.47 5.10 100 12627.6 4.47 9.12
120 15136.8 5.35 5.56 120 15136.8 5.35 10.82
140 17605.2 6.23 6.02 140 17605.2 6.23 12.52
120 15136.8 5.35 6.00 120 15136.8 5.35 12.50
100 12627.6 4.47 5.96 100 12627.6 4.47 12.38
80 9924.6 3.51 5.83 80 9924.6 3.51 12.22
60 7486.0 2.65 5.71 60 7486.0 2.65 12.01
30 3723.0 1.32 5.63 30 3723.0 1.32 11.54
0 0.0 0.00 5.44 0 0.0 0.00 11.00
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 6.02 5.44
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
14.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-3 / TP - 05
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 17.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 9.09
30 3723.0 1.32 3.21 30 3723.0 1.32 10.45
60 7486.0 2.65 5.99 60 7486.0 2.65 11.34
80 9924.6 3.51 7.43 80 9924.6 3.51 12.08
100 12627.6 4.47 8.72 100 12627.6 4.47 13.13
120 15136.8 5.35 10.04 120 15136.8 5.35 13.87
140 17605.2 6.23 11.43 140 17605.2 6.23 14.76
120 15136.8 5.35 11.38 120 15136.8 5.35 14.71
100 12627.6 4.47 11.28 100 12627.6 4.47 14.62
80 9924.6 3.51 10.93 80 9924.6 3.51 14.30
60 7486.0 2.65 10.46 60 7486.0 2.65 13.80
30 3723.0 1.32 9.68 30 3723.0 1.32 13.12
0 0.0 0.00 9.09 0 0.0 0.00 12.42
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 11.43 9.09
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
14.0
16.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-3 / TP - 06
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 18.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 3.44
30 3723.0 1.32 1.55 30 3723.0 1.32 4.66
60 7486.0 2.65 2.22 60 7486.0 2.65 5.56
80 9924.6 3.51 3.00 80 9924.6 3.51 6.44
100 12627.6 4.47 4.00 100 12627.6 4.47 7.04
120 15136.8 5.35 4.92 120 15136.8 5.35 8.16
140 17605.2 6.23 5.62 140 17605.2 6.23 9.33
120 15136.8 5.35 5.59 120 15136.8 5.35 9.28
100 12627.6 4.47 5.51 100 12627.6 4.47 9.20
80 9924.6 3.51 5.41 80 9924.6 3.51 9.10
60 7486.0 2.65 5.25 60 7486.0 2.65 8.71
30 3723.0 1.32 4.84 30 3723.0 1.32 8.16
0 0.0 0.00 3.44 0 0.0 0.00 7.10
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 5.62 3.44
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
1.0
2.0
3.0
Settlement (mm)
4.0
5.0
6.0
7.0
8.0
9.0
10.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-3 / TP - 07
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 20.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 15.07
30 3723.0 1.32 3.20 30 3723.0 1.32 17.23
60 7486.0 2.65 7.24 60 7486.0 2.65 20.25
80 9924.6 3.51 10.94 80 9924.6 3.51 22.31
100 12627.6 4.47 13.67 100 12627.6 4.47 24.31
120 15136.8 5.35 16.09 120 15136.8 5.35 25.68
140 17605.2 6.23 19.09 140 17605.2 6.23 27.69
120 15136.8 5.35 19.04 120 15136.8 5.35 27.65
100 12627.6 4.47 18.96 100 12627.6 4.47 27.55
80 9924.6 3.51 18.70 80 9924.6 3.51 27.39
60 7486.0 2.65 18.30 60 7486.0 2.65 26.97
30 3723.0 1.32 17.16 30 3723.0 1.32 26.23
0 0.0 0.00 15.07 0 0.0 0.00 25.09
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 19.09 15.07
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
5.0
10.0
Settlement (mm)
15.0
20.0
25.0
30.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-3 / TP - 08
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 20.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 1.96
30 3723.0 1.32 0.75 30 3723.0 1.32 2.68
60 7486.0 2.65 1.36 60 7486.0 2.65 3.43
80 9924.6 3.51 1.93 80 9924.6 3.51 3.74
100 12627.6 4.47 2.57 100 12627.6 4.47 4.13
120 15136.8 5.35 3.14 120 15136.8 5.35 4.49
140 17605.2 6.23 3.83 140 17605.2 6.23 4.92
120 15136.8 5.35 3.80 120 15136.8 5.35 4.89
100 12627.6 4.47 3.73 100 12627.6 4.47 4.80
80 9924.6 3.51 3.59 80 9924.6 3.51 4.64
60 7486.0 2.65 3.39 60 7486.0 2.65 4.46
30 3723.0 1.32 3.02 30 3723.0 1.32 3.88
0 0.0 0.00 1.96 0 0.0 0.00 3.44
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 3.83 1.96
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
1.0
2.0
Settlement (mm)
3.0
4.0
5.0
6.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-3 / TP - 09
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 22.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 6.27
30 3723.0 1.32 1.99 30 3723.0 1.32 6.71
60 7486.0 2.65 3.81 60 7486.0 2.65 7.52
80 9924.6 3.51 4.67 80 9924.6 3.51 8.32
100 12627.6 4.47 5.73 100 12627.6 4.47 9.46
120 15136.8 5.35 6.81 120 15136.8 5.35 10.34
140 17605.2 6.23 7.83 140 17605.2 6.23 11.29
120 15136.8 5.35 7.79 120 15136.8 5.35 11.25
100 12627.6 4.47 7.71 100 12627.6 4.47 11.16
80 9924.6 3.51 7.61 80 9924.6 3.51 11.05
60 7486.0 2.65 7.43 60 7486.0 2.65 10.92
30 3723.0 1.32 7.17 30 3723.0 1.32 10.41
0 0.0 0.00 6.27 0 0.0 0.00 9.98
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 7.83 6.27
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
UNSOAKED SOAKED
PERCOLATION TEST
LAYDOWN No. 3
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 10 20 30 40 50 60 70 80 90
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 20 40 60 80 100 120
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 50 100 150 200 250
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 50 100 150 200 250
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 10 20 30 40 50 60
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 10 20 30 40 50 60
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 20 40 60 80 100 120 140 160 180 200
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 5 10 15 20 25 30 35 40 45 50
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 20 40 60 80 100 120 140 160 180 200
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
0.0000 0.00 0 0
120
0.0250 5.00 46 15
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0250 3.00 27 9
80
0.0500 6.00 55 18
0.0750 10.00 92 31 60
0.1000 13.00 119 40 4
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0000 0.00 0 0 35
0.0250 2.00 18 6
30
0.0500 4.00 37 12
25
0.0750 5.00 46 15
20
0.1000 6.00 55 18 2
15
0.1500 8.00 73 24
0.2000 9.00 82 27 2 10
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0000 0.00 0 0
80
0.0250 3.00 27 9
0.0500 5.00 46 15
60
0.0750 8.00 73 24
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0000 0.00 0 0
80
0.0250 3.00 27 9
0.0500 6.00 55 18
60
0.0750 8.00 73 24
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0250 3.00 27 9
80
0.0500 6.00 55 18
0.0750 8.00 73 24 60
0.1000 11.00 101 34 3
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
300
0.0000 0.00 0 0
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TRIAL PIT LOGS
LAYDOWN No. 5
SAMPLE
(m)
Greyish brown, silty medium to coarse SAND with Bulk Sample at 0.60m &
gravel and cobbles. Gravels are angular medium to 1.20m
coarse of igneous origin.
Brown, well-graded SAND with silt, gravel and B-1
cobble of igneous origin.
1
Field CBR Test at 0.50
Brown, well-graded GRAVEL with sand and cobble. B-2 meters
Plate Load Test at 0.50
meters
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00m
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-5.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 02
SAMPLE
(m)
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-5.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 03
SAMPLE
(m)
Brownish grey, slightly cemented silty medium to Bulk Sample at 0.60m &
fine SAND with gravel and cobbles. Gravels are 1.20m
angular to sub-rounded medium to coarse of
igneous origin.
B-1
Brown, well-graded SAND with silt, gravel and
1 cobbles of igneous origin.
Field CBR Test at 0.50
B-2 meters
Plate Load Test at 0.50
meters
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Brown, well-graded GRAVEL wioth silt and sand.
Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00m
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-5.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 04
SAMPLE
(m)
Brownish grey, slightly cemented silty medium to Bulk Sample at 0.60m &
fine SAND with gravel and cobbles. Gravels are 1.20m
angular to sub-rounded medium to coarse of
igneous origin.
B-1
Brown, well-graded GRAVEL with sand and
1 cobbles.
Field CBR Test at 0.50
B-2 meters
Plate Load Test at 0.50
Brown, well-graded GRAVEL with silt, sand and meters
cobbles. Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00m
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-5.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 05
SAMPLE
(m)
Brownish grey, slightly cemented silty medium to Bulk Sample at 0.60m &
fine SAND with gravel and cobbles. Gravels are 1.20m
angular to sub-rounded of igneous origin.
B-1
1
Field CBR Test at 0.50
Brown, silty SAND with gravel and cobbles of B-2 meters
igneous origin. Plate Load Test at 0.50
meters
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Brown, well-graded GRAVEL with sand and
cobbles of igneous origin. Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00m
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-5.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 06
SAMPLE
(m)
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-5.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 07
SAMPLE
(m)
Brownish grey, slightly cemented silty medium to Bulk Sample at 0.60m &
fine SAND with gravel and cobbles. Gravels are 1.20m
angular to sub-rounded medium to coarse of
igneous origin.
B-1
1
Field CBR Test at 0.50
Brown, well-graded SAND with silt, gravel and B-2 meters
cobbles of igneous origin. Plate Load Test at 0.50
meters
Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
Greyish brown, poorly-graded SAND with silt, 2.50 & 3.00m
gravel and cobbles of igneous origin.
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-5.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 08
SAMPLE
(m)
Brownish grey to greyish brown, silty medium to Bulk Sample at 0.60m &
fine SAND with gravel and cobbles. Gravels are 1.20m
angular to sub-rounded medium to coarse of
igneous origin.
B-1
1
Field CBR Test at 0.50
B-2 meters
Plate Load Test at 0.50
Brown, well-graded SAND with silt, gravel and meters
cobbles of igneous origin. Field Density Test at 0.50,
1.00, 1.50, 2.00, 2.50 & 3.00
2 meters
Small Sample at
0.00,0.50,1.00, 1.50, 2.00,
2.50 & 3.00m
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-5.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
RIYADH GEOTECHNIQUE AND FOUNDATIONS CO. TP No. 09
SAMPLE
(m)
3
----End of Trial Pit at 3.00 meters----
5
TRIAL PITS GAYAL-LD-5.GPJ RGME.GDT 23-3-22
D 1.50m B
7
C
FIELD DENSITY TESTS
LAYDOWN No. 5
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-5 / TP - 01 REPORT DATE : 12.01.2022
SAMPLING DATE : - TEST START DATE : 26.12.2021
SAMPLE RECEIVING DATE : TEST FINISH DATE : 27.12.2021
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-5 / TP - 02 REPORT DATE : 12.01.2022
SAMPLING DATE : - TEST START DATE : 28.12.2021
SAMPLE RECEIVING DATE : TEST FINISH DATE : 29.12.2021
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-5 / TP - 03 REPORT DATE : 12.01.2022
SAMPLING DATE : - TEST START DATE : 26.12.2021
SAMPLE RECEIVING DATE : TEST FINISH DATE : 27.12.2021
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-5 / TP - 04 REPORT DATE : 12.01.2022
SAMPLING DATE : - TEST START DATE : 29.12.2021
SAMPLE RECEIVING DATE : TEST FINISH DATE : 30.12.2021
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-5 / TP - 05 REPORT DATE : 12.01.2022
SAMPLING DATE : - TEST START DATE : 26.12.2021
SAMPLE RECEIVING DATE : TEST FINISH DATE : 27.12.2021
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-5 / TP - 06 REPORT DATE : 12.01.2022
SAMPLING DATE : - TEST START DATE : 01.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 02.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-5 / TP - 07 REPORT DATE : 12.01.2022
SAMPLING DATE : - TEST START DATE : 30.12.2021
SAMPLE RECEIVING DATE : TEST FINISH DATE : 01.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-5 / TP - 08 REPORT DATE : 12.01.2022
SAMPLING DATE : - TEST START DATE : 02.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 03.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
P.O. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
FIELD DENSITY TEST
ASTM-1556/D-1556M-e1
CLIENT : NEOM Company
PROJECT : NEOM Desalination Plant to Gayal Transmission System PROJECT NO. : 21J4037
LOCATION : LD-5 / TP - 09 REPORT DATE : 20.01.2022
SAMPLING DATE : - TEST START DATE : 12.01.2022
SAMPLE RECEIVING DATE : TEST FINISH DATE : 13.01.2022
SAMPLING BY: R.G.F. ENV. CONDITION TEMP. : - HUMIDITY : -
DESCRIPTION :
TEST NO.: 1 2 3 4 5 6
LAYER : - - - - - -
SAMPLE DEPTH : m 0.50 1.00 1.50 2.00 2.50 3.00
REMARKS :
APPROVED BY:
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIL-14.02
15.07.2019
DOUBLE CYCLE PLATE LOAD TESTS
LAYDOWN No. 5
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 10.62 8.67
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
6.0
Settlement (mm)
8.0
10.0
12.0
14.0
16.0
18.0
20.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-5 / TP - 02
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 28.12.2021
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 5.42
30 3723.0 1.32 1.90 30 3723.0 1.32 6.23
60 7486.0 2.65 3.74 60 7486.0 2.65 7.13
80 9924.6 3.51 4.49 80 9924.6 3.51 8.04
100 12627.6 4.47 5.43 100 12627.6 4.47 8.76
120 15136.8 5.35 5.79 120 15136.8 5.35 9.96
140 17605.2 6.23 6.58 140 17605.2 6.23 11.03
120 15136.8 5.35 6.53 120 15136.8 5.35 11.01
100 12627.6 4.47 6.47 100 12627.6 4.47 10.97
80 9924.6 3.51 6.40 80 9924.6 3.51 10.92
60 7486.0 2.65 6.29 60 7486.0 2.65 10.89
30 3723.0 1.32 6.09 30 3723.0 1.32 10.54
0 0.0 0.00 5.42 0 0.0 0.00 9.55
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 6.58 5.42
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-5 / TP - 03
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 29.12.2021
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 8.57
30 3723.0 1.32 2.97 30 3723.0 1.32 13.19
60 7486.0 2.65 5.27 60 7486.0 2.65 16.00
80 9924.6 3.51 6.55 80 9924.6 3.51 18.80
100 12627.6 4.47 7.83 100 12627.6 4.47 21.33
120 15136.8 5.35 9.03 120 15136.8 5.35 23.51
140 17605.2 6.23 10.12 140 17605.2 6.23 25.51
120 15136.8 5.35 10.10 120 15136.8 5.35 25.49
100 12627.6 4.47 10.07 100 12627.6 4.47 25.45
80 9924.6 3.51 10.00 80 9924.6 3.51 25.42
60 7486.0 2.65 9.93 60 7486.0 2.65 25.38
30 3723.0 1.32 9.60 30 3723.0 1.32 25.18
0 0.0 0.00 8.57 0 0.0 0.00 24.74
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 10.12 8.57
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
5.0
10.0
Settlement (mm)
15.0
20.0
25.0
30.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-5 / TP - 04
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 29.12.2021
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 4.80
30 3723.0 1.32 1.44 30 3723.0 1.32 5.40
60 7486.0 2.65 2.37 60 7486.0 2.65 6.01
80 9924.6 3.51 3.09 80 9924.6 3.51 6.57
100 12627.6 4.47 3.84 100 12627.6 4.47 6.95
120 15136.8 5.35 4.65 120 15136.8 5.35 7.30
140 17605.2 6.23 5.51 140 17605.2 6.23 7.54
120 15136.8 5.35 5.44 120 15136.8 5.35 7.50
100 12627.6 4.47 5.25 100 12627.6 4.47 7.31
80 9924.6 3.51 5.39 80 9924.6 3.51 7.12
60 7486.0 2.65 5.15 60 7486.0 2.65 6.93
30 3723.0 1.32 4.98 30 3723.0 1.32 6.75
0 0.0 0.00 4.80 0 0.0 0.00 6.53
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 5.51 4.80
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
1.0
2.0
Settlement (mm)
3.0
4.0
5.0
6.0
7.0
8.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-5 / TP - 05
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 30.12.2021
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 3.34
30 3723.0 1.32 1.17 30 3723.0 1.32 4.03
60 7486.0 2.65 2.38 60 7486.0 2.65 5.10
80 9924.6 3.51 3.02 80 9924.6 3.51 5.59
100 12627.6 4.47 3.68 100 12627.6 4.47 6.15
120 15136.8 5.35 4.02 120 15136.8 5.35 6.63
140 17605.2 6.23 4.26 140 17605.2 6.23 7.17
120 15136.8 5.35 4.23 120 15136.8 5.35 7.15
100 12627.6 4.47 4.18 100 12627.6 4.47 7.10
80 9924.6 3.51 4.03 80 9924.6 3.51 6.98
60 7486.0 2.65 3.79 60 7486.0 2.65 6.82
30 3723.0 1.32 3.60 30 3723.0 1.32 6.68
0 0.0 0.00 3.34 0 0.0 0.00 6.38
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 4.26 3.34
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
1.0
2.0
Settlement (mm)
3.0
4.0
5.0
6.0
7.0
8.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-5 / TP - 06
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 01.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 4.94
30 3723.0 1.32 1.79 30 3723.0 1.32 6.26
60 7486.0 2.65 3.25 60 7486.0 2.65 8.17
80 9924.6 3.51 4.52 80 9924.6 3.51 9.54
100 12627.6 4.47 5.47 100 12627.6 4.47 10.70
120 15136.8 5.35 6.37 120 15136.8 5.35 11.50
140 17605.2 6.23 6.85 140 17605.2 6.23 12.35
120 15136.8 5.35 6.79 120 15136.8 5.35 12.31
100 12627.6 4.47 6.65 100 12627.6 4.47 12.25
80 9924.6 3.51 6.32 80 9924.6 3.51 12.13
60 7486.0 2.65 5.88 60 7486.0 2.65 11.89
30 3723.0 1.32 5.41 30 3723.0 1.32 11.77
0 0.0 0.00 4.94 0 0.0 0.00 11.29
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 6.85 4.94
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
14.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-5 / TP - 07
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 30.12.2021
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 5.63
30 3723.0 1.32 1.74 30 3723.0 1.32 6.82
60 7486.0 2.65 3.81 60 7486.0 2.65 7.76
80 9924.6 3.51 5.21 80 9924.6 3.51 8.95
100 12627.6 4.47 6.10 100 12627.6 4.47 10.04
120 15136.8 5.35 6.61 120 15136.8 5.35 10.60
140 17605.2 6.23 7.06 140 17605.2 6.23 11.09
120 15136.8 5.35 6.99 120 15136.8 5.35 11.02
100 12627.6 4.47 6.78 100 12627.6 4.47 10.84
80 9924.6 3.51 6.58 80 9924.6 3.51 10.62
60 7486.0 2.65 6.36 60 7486.0 2.65 10.37
30 3723.0 1.32 6.16 30 3723.0 1.32 10.08
0 0.0 0.00 5.63 0 0.0 0.00 9.80
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 7.06 5.63
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-5 / TP - 08
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 02.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 7.23
30 3723.0 1.32 1.65 30 3723.0 1.32 8.01
60 7486.0 2.65 3.92 60 7486.0 2.65 8.95
80 9924.6 3.51 5.76 80 9924.6 3.51 9.53
100 12627.6 4.47 7.07 100 12627.6 4.47 10.33
120 15136.8 5.35 7.93 120 15136.8 5.35 10.91
140 17605.2 6.23 8.71 140 17605.2 6.23 11.83
120 15136.8 5.35 8.67 120 15136.8 5.35 11.80
100 12627.6 4.47 8.60 100 12627.6 4.47 11.60
80 9924.6 3.51 8.45 80 9924.6 3.51 11.38
60 7486.0 2.65 8.18 60 7486.0 2.65 11.02
30 3723.0 1.32 7.84 30 3723.0 1.32 10.47
0 0.0 0.00 7.23 0 0.0 0.00 9.80
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 8.71 7.23
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
14.0
UNSOAKED SOAKED
PLATE LOAD TEST
(DIN - 18134)
CLIENT : NEOM Company PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
TEST NO. : 1 LOCATION : LD-5 / TP - 09
DESCRIPTION : DEPTH : -
Plate Dia. : 60 cm NORTHNG : -
Jack Capacity : 25 ton EASTING : -
2
Plate Area : 2827.8 cm Elevation : -
Dial Gauge Least Count : 0.01 mm Test Date : 12.01.2022
Tested By : Sajid
Test Data
LOADING / UNLOADING Average Settlement LOADING / UNLOADING Average Settlement
(Bar) (kg) Pressure UNSOAKED (Bar) (kN) Pressure SOAKED *
1st Cycle 2nd Cycle
kg/cm 2 (mm) kpa (mm)
0 0 0 0.00 0 0 0.00 6.32
30 3723.0 1.32 2.33 30 3723.0 1.32 8.40
60 7486.0 2.65 4.02 60 7486.0 2.65 10.24
80 9924.6 3.51 5.08 80 9924.6 3.51 11.34
100 12627.6 4.47 6.19 100 12627.6 4.47 12.39
120 15136.8 5.35 6.94 120 15136.8 5.35 13.34
140 17605.2 6.23 7.59 140 17605.2 6.23 14.13
120 15136.8 5.35 7.58 120 15136.8 5.35 14.11
100 12627.6 4.47 7.53 100 12627.6 4.47 14.05
80 9924.6 3.51 7.44 80 9924.6 3.51 13.94
60 7486.0 2.65 7.34 60 7486.0 2.65 13.85
30 3723.0 1.32 6.90 30 3723.0 1.32 12.90
0 0.0 0.00 6.32 0 0.0 0.00 12.32
* The area around plate was soaked for two(2) hours before starting second cycle.
Residual
Plate Settlement at Maximum
2
Maximum Load (kN) Maximum Pressure (kg/cm ) Settlement upon
Pressure (mm)
Unloading (mm)
1st Load Cycle
17605.2 6.23 7.59 6.32
UNSOAKED
Pressure (kg/cm2)
0 1 2 3 4 5 6 7
0.0
2.0
4.0
Settlement (mm)
6.0
8.0
10.0
12.0
14.0
16.0
UNSOAKED SOAKED
PERCOLATION TEST
LAYDOWN No. 5
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 5 10 15 20 25 30 35 40
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 5 10 15 20 25 30 35 40
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 10 20 30 40 50 60 70 80 90
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 10 20 30 40 50 60 70 80
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 50 100 150 200 250 300
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 10 20 30 40 50 60
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 5 10 15 20 25 30
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 5 10 15 20 25 30 35 40 45 50
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
1.40
1.20
Infiltration Rate (Inner Ring) cms/min.
1.00
0.80
0.60
0.40
0.20
0.00
0 20 40 60 80 100 120 140 160 180 200
Time in min.
REMARKS : Soil Infiltration Rate Testing test carried out in accordance with BRE Digest 365
0.0500 4.00 37 12
40
0.0750 6.00 55 18
0.1000 8.00 73 24 2 30
0.1500 10.00 92 31
20
0.2000 12.00 110 37 2
10
0.2500 15.00 137 46
0.3000 17.00 156 52 0
0.0 0.1 0.2 0.3 0.4 0.5
0.3500 20.00 183 61
Penetration (in)
0.4000 23.00 211 70
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0500 5.00 46 15
40
0.0750 6.00 55 18
0.1000 8.00 73 24 2 30
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0250 2.00 18 6 50
0.0500 3.00 27 9
40
0.0750 5.00 46 15
0.1000 6.00 55 18 2 30
0.1500 9.00 82 27
20
0.2000 12.00 110 37 2
10
0.2500 14.00 128 43
0.3000 17.00 156 52 0
0.0 0.1 0.2 0.3 0.4 0.5
0.3500 20.00 183 61
Penetration (in)
0.4000 23.00 211 70
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0250 5.00 46 15
150
0.0500 10.00 92 31
0.0750 15.00 137 46
100
0.1000 20.00 183 61 6
0.1500 27.00 247 82
0.2000 32.00 293 98 7 50
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0750 8.00 73 24 40
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0500 4.00 37 12
40
0.0750 6.00 55 18
0.1000 8.00 73 24 2 30
0.1500 10.00 92 31
20
0.2000 12.00 110 37 2
10
0.2500 15.00 137 46
0.3000 18.00 165 55 0
0.0 0.1 0.2 0.3 0.4 0.5
0.3500 21.00 192 64
Penetration (in)
0.4000 24.00 220 73
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0250 4.00 37 12
80
0.0500 8.00 73 24
0.0750 10.00 92 31 60
0.1000 12.00 110 37 4
0.1500 17.00 156 52 40
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
TEST REPORT
FIELD CALIFORNIA BEARING RATIO
ASTM D4429-09a
0.0750 6.00 55 18 40
0.1000 8.00 73 24 2
30
0.1500 11.00 101 34
20
0.2000 14.00 128 43 3
0.2500 17.00 156 52 10
APPROVED BY:
LAB. IN-CHARGE
RGF-JED-PHY-SOIL-08-05
20.01.2020
APPENDIX-B
LABORATORY TESTING
RESULTS
LAYDOWN No. 1
NO: K-9
RGF- YNB-PHY-SOIL-15·02
01.08.2021 Copy Right Resrved by RGF
t../,-=?-' I ~
P~O. Do)t 302:',:1, ....anl'KJ M4iin;lv~h. MVAS 5-:;l000.. KSA TC!!h!·ph~~ +~6 (',11'1) 1l::'-S.O:t..'192 I !lI25-0993 F.&)(~ +S)G6 (.14) 3250.1>",,6 F.rn:,)!l~ ,(Or~yanbu@~~lae-c>s.<:.h.tn'(;'t:.c<>:n')
"~':",,,*'(>o-: A~~NAA_.an,""nd ,~l:l"~OI:rt. I-t,.1 A)-rvlOl)'_an (',.hVk:t. n.<:.••
'V,a!,\bU A.i~S1n."lrl'r'<J'/:l
NO: 8-2
K-3
OF SAMPLE + CAN (WET) (gms) 529.77
OF SAMPLE + CAN (DRY) (gms) 521.78
• OF WATER (gms) 7.99
31.40
WT. OF DRY SAMPLE (gms) 490.38
CONTENT (%) 1.63
RGF-YNS·PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
I ~~ ~lc.-L:.-~(j/~ -:: ·~~~~~I~
An EftD Company .~.=~. ~ RIYADH GEOTECHNIClUE & FOUNDATIONS CO.
P~O. Uo>e 3027'1, Vfln.l».J AI"S-.,...;:'ly,,*h. MYI\S 5;1000.. K~A "c>J0J3hone~ +!£HS()' {11l.} a;;(::>099~ I 32"5Q!).93 1"',..,,)(; .966 (.l.4t a:l:5C94t6 Errtl\U!: ItV..yitf'ob"H!1'crl3>1!'~t1Jlth:.'lt!!l"CO""'"
I.c,,>-I;,,>,ak.o:\ Al·Nol)'.......:H'J1H," ~tr«':'..,t. th~1 A)-""'ah~n DohtTtcl;, R.<:•• ""'",nbu Af~Sln.;lol'i!l?h
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
~ID [r; 1 1_::'A ..::_--,_::--/U I ~ -;;,
-'
-~~:
-:;. ----U.
t../'" ~~ ,-~
::.r:.. .
AnERlcCH"P<'"Y '~.!';'.l'?:.!' v_M RIVADH GEOTECHNIOUE & FOUNDATIONS CO_
P.o. DOM 30".27:1, V.:iIt'JIbu AI,...s'n;1y:'1"I~ MYAS 5::1000.. KSA TeJi!Z"phol"'\e~ .. 9<>6 (:1"'1) 32:s..0992 132S0993 Fr.,..! .9154 (14) 32509.,.6 Et't\:a.1J-:: "'-R'...yanbil-l@et'a.eo~i:enc:e~.colYl
1.0000:.<1otlon! ......1"N.-:w.......-..u ....<1ond StJ""""",t. "I<.~I Ai-MOlhan Dblid:ct. n.c., 'V<3n.bu AJ_Sfn..:;It.,.iJh
RGF· YNB·PHY·SOIL·15·02
01.08.2021 Copy Right Resrved by RGF
~
: Neom desalination plant to gayal transmisssion system. (WoO 1) DATE SAMPLED: 24.01.2022
TP : 02 Depth: 0.50 m DATE RECEIVED: 31.01.2022
I;)AMt"LLI:. DESCRIPTION Sample NO.: S-1
RGF-YNB-PHY-SOIL-15-02
01082021 Copy Right Resrved by RGF
.,....::-l..;;;......~U l,!!t :.: w ~~~ ~l:?/ f ~
An ERB Company I l?g RIVADH GEOTECHNIClUE & FOUNDATIONS CO_
, ""',..~"'" ..."" Fnx~ ¥.S)G-6. (.14) 32:s.o946 Frntsotl1 rtlr-Y.:lnbu(!'j)~tl'&«"l':XlGtlt::rtc~ ..,eon'S
-_. -> - ~-~ -_. Dh.tric.t. R.C.~ Y,a,ubu Al--SlrulV.itI~
PROJECT Neom desalination to gayal transmisssion system. (LD·O 1) DATE SAMPLED: 24.01.2022
RGF -YNB-PHY-SOIL-15-02
01,08,2021 Copy Right Resrved by RGF
-t!"""'ilc.-L::.-~IJI.!fI ::;:: ~~~~~./j::.r~
-' -- + -..-
I -"
RGF-YNB-PHY-SOIL-15-02
0108_2021 Copy Right Resrved by RGF
/ " ' . -;+---u • I --.1 ··/~ __
1 ~'ID ~ "C- L:..-<......::.--' U I ~ :.:: ~~;:-C i../ ~___ f ~------
A" ERII C<>",,,..ny "2.... ,om· ~ RIVADH GEOTECHNIClUE & FOUNDATIONS CO.
J.~_O. nOM 30,27'1. YIH.. bu AhSi"';'l'V~h. MYAS 5;1000, Y.5.A 'tI'J",phone~ +966 (:1'1) a:2.s.o99~ 13:250'",,)93 f.'.'3r)o!! -..966 C14) a~S0'94(i. Ert1o";).H~ r,"'~y,l)nbu@lCl'~g'IN!>:i,.C,i-er..::>e::I.ccu'n
I.OC..a-I~';'O~ A1-N.::tIN".ill'H>.nd St"H"J'tl:t". H<\I A~-tvlah~_n rJObu-tc". H.";--:., Y .., u'lbu N-S~n.<1ol.,. ... h
CLIENT
PROJECT
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
~~
C_ [lJ]
v "'----'" l.;::_A_::.--V I~ _...
¥ -
-~:
----7 -1! ~ L.;:..;./
.. f~
:"'!1 Eftl corr>panY~.!' v.~~ RIVADH GEOTECHNIGUE & FOUNDATIONS CO_
P.O. 8o)ot g0271. YOlnbU AA.6h~;'ty~h. MYAS ~:tOOO. t':.SA T~Jeophot""1 ~:!)6(50 ( .... A) a2:~~)!):Z 1.3:.l5-()!;)9~ V3~: ,*966 ('14). 325094G (;)TI,:aJ,,:: 'n'..y$lnbu«Jt-ef'l$;.~(>~i.ene:""ll,COtn
"".>i·.~tJ<'>n:.. A-l.Nik.....,nnand St1"~l(rt. ,. ••,H A,,"Mat"'''.Tl r-.H... :t'rt(:S-. R,C.• v,;,.nbu At-Slf~ly;Jh
Neom desalination
NO: S-1
8-14
OF SAMPLE + CAN (WET) (gms) 288.00
OF SAMPLE + CAN (DRY) (gms) 278.30
• OF WATER (gms) 9.70
• OF CAN (gms) 49.35
WT. OF DRY SAMPLE (gms) 228.95
WATER CONTENT (%) 4.24
RGF· YNB-PHY·SOIL-15-02
01,08.2021 Copy Right Resrved by RGF
I ~lf)~ t.-I.....:::-L::...--U-' 13' ;:.;: -;. --il.
• ~~.;"O V
-::..r:.. . .
t...;:--'.-/ f - ~
AnERlcompa.ny ,,<?~J~J'. u.:" RIVADH GEOTECHNIGUE & FOUNDATIONS CO_
f'~<). ~)Q>l :;10,2,7-:1. Yant;;U AJ,..sft~;lY~h# -M.VAS S:1000~ KSA .,~)<! *9G<i (14) 3250946 Fn'lo:aHo:: rn'-y;;)nbU(@etf~~~rH::e".C::ot'rt
ettal At-tvt",h""n D~litTkt. R"C •• Y~n.lnJ N-$in..«tVOJh
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
-r - 1.-
"'-- "'--"""~
{ ., ~U/ I~ ...... ~ t.../,-:?~I~
An ERD CO"'p".oy RIVADH GEOTECHNIOUE & FOUNDATIONS co.
'f'.O~ UQ)t Sa2;71., YnnbU N",<;.n~lYQ.h~ ",,<tVA."> 5"1000" Y.5A Te}~pho~~ ..96& (:tAl a:ZS0992 ; 32S>09903
\.().;-.aHt>n~ A)_Nowv..,.n.;:onU $>\;J-_t.... ~1 At-M~h.n.
RGF-YNB·PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
~~~";'if~/j~
".0.00)1302.7'1, ....lU.. b1-t AI~mf,>;'lY""h. MVAS SliOOO, KSA T~fe-phonf!o! .,.966 ('141a:::l5o(}>g!).2! ;a:"nsO",.,)!>::t
It><~~lk>o~. .Al·N"".......,;!."~,.t~d StHl'.....I• •• ~i Al-Muh;;,n
RGF·YNB-PHY·SOIL·15·02
01 08.2021 Copy Right Resrved by RGF
~n _ _ =_ vump~ny I
,-_.
. .-~~.
r.L
--.....-,
n "C.- L:-~U 11' ~~
.-y J" L;:./.,/ j ~
RIVADH GEOTECHNIOUE & FOUNDATIONS CO.
- . ":.
f>,O~ UO)oil .9027:1., V;u,):bti Ai",-«iln;tY::lt.. M'VA5 z,,1UOO, KSA TttJ~phol~::: ... 966 (.1.4} a2.~92 13..2s.ogg:3 I';;:;.;.:: t966 (14) 32S094q. tct'r.aU1 :t1lf'..y.a....bl-I@>.effg.e-03..::Jcellt.c;e"'.iI:'on')
lOf::atf<,a.. :. ,A)-Nil",a"~f\d $lTV"(l1"~ "'f!.~1 Ai_N"IUhliOf\ r..lt"".dc~. i't,C•• Y~ntH' Al-Sfnatv,ah
RGF·YNB-PHY-SOIL-1S-02
01082021 Copy Right Resrved by RGF
C--t-::... A_=..--U I~ ,-- .... ~~ ~'-::;~f~
RIVADH GEOTECHNIClUE & FOUNDATIONS CO.
p.o, no""- 30271. YntfuU Af~5Jt'>,alVi')h. MYAS 5;1000,. y.5.A Te,c.ph6he;; +966 {:l.4} a.250992 /325CY..,)9:<)
tot;·,""Uon~ .Aj-NiliJVan~nd St."-"'""""t~ t-l,... :
$r.J... MOlh<*H
o
ENVT. COND TEMP 24.7 C HUMIDITY: 41%
Test Started Date 01.02.2022 Test Completed Date: 02.02.2022
S-6
N-3
RGF-YNB-PHY-SOIL.. 15..02
0108.2021 Copy Right Resrved by RGF
I <QlJ) I~lc::...- L::..-L:.----- u I" ,::
-'
Go
-;- Ai
--?"~,;' (..,/"' L2../ ,-~
- -::.r:.. .
AnlERlco<npany ".i'.!'f.!~' ~ RIVADH GEOTECHNIClUE & FOUNDATIONS CO_
1",0. (!.o)C 302:7:l. YlH~bu Al...-5ln;'yao. ,...,VAS 5:1000.. Y.SA Tt?-Jll-phoo..: -+966 (:14) 32S0992 I :9-25-0£>93 I;~x~ -4>966 (14-)- 3250"946 En'\~H! rn'.y~l'lbullf>oeltlg'l!'o~l-enc:oe:.$.cotn
Lt>.:-.a'I...... o~ .AI-Na.....,~\n~.nd Sl'¥'ff-<:>l~ H~l.A)-M<Jh:;,-n rJOhtv'o:;t. fi;,<,_ •• Y.ilntn..l Af_Sfn.;'~V.;:ah
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
~~
om,
~
,
'----"'L:-~U
.... - -' -- I"~
~ _ -- _ ~ ~ '----"
__ ~ "". ~~-. - I --v. 1--,_
--~.---.
RGF- YNB-PHY-SOIL-15-02
01082021 Copy Right Resrved by RGF
,-=--, mel" n c... L:::.--l.....::.---' tJ-' Il ' ~.
-
_...
-1! t.,/'" ~
~:
_r-
'I;:.f_ A..-/
-~~.
ERI RIYADH GEOTECHNIClUE & FOUNDATIONS CO.
P,o. {l¢~ :\lO,;t7'. YtuHHJ A'~~lt:"..aIVt)h~ "",,-VAS .51000.. Y.5A Tt':l"",ph~e: +!!)(>6 ( l 4 ' ~J,2S09~2 / S2509U'3 F;')X: +t;)G6 (:14) 32!,>Q!)l\(; €J't\alf~ tnf~y.,r.!bt:.tlXPfl~f3f!eos.clef'l"C:00 ••ebJh
It).<',\i:I!t/<'H'H ,(d"NAA .......~ln~"(1 $t,-o::-"",'... th.i A'_MOlh~n D~"'l'·~I;;~. {(,<;. •• V~nl~u Al~Sfn.al.,..,.h
NO: $-3
B-16
OF SAMPLE + CAN (WET) (gms) 402.20
OF SAMPLE + CAN (DRY) (gms) 398.90
OF WATER (gms) 3.30
47.68
. OF DRY SAMPLE (gms) 351.22
CONTENT (%) 0.94
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy RighI Resrved by RGF
Eftl
~=-~-.il ..... -
~'---~
1.- I -- .~-'UI ..
,"..0. Uo:.o 3027'1, Y;tobu AJ6fn;lY~'h. J\.1l:YAS £3000., KSA Tn'4't'hftl;¥W!'; ..966 (:14) 325.0<_~92 13250993 Y:'Xf *9,,-di ~:14) 32509"" "'Ina"::' "-n/-yanb'I.J@>~ ... JB""'a-M:I*lrf\C~I(.COM
'Oi,'\;Ulfinl. ,Al.Nallv"tn.:tnd 1>t.To::l'"",t. H~I .Al~tv1<ih;;)n bhit1'tct. «.<':.•• Y,;u'\bu A1-S1n.llv.,h
0
ENVT. COND TEMP 23.9 C HUMIDITY: 40%
Test Started Date 01.02.2022 Test Completed Date: 02.02.2022
--------
0
ENVT. COND TEMP 23.9 C HUMIDITY: 40%
Test Started Date 01.02.2022 Test Completed Date: 02.02.2022
------
RGF-YNB-PHY-SOIL-15-02
0108.2021 Copy Right Resrved by RGF
"t::.:-L::-L::.--'U /.!!J ~~
..... "'"
t-/ L::.--~
... f~ -
An ERB Compa:ny RIVADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. Uo>t 3()27:1, .....,1u.. bu Af.SJn;"Yfih. -'V1YAS s:'tooo,.. KSA Ttbh:·pht:tna'~ .~& (-:J,4)a;l.~(}iH)21 B2S0!l93 J.'~: +~(f.6 (:14' <12509.116 F.rn"$ll~r(J.¥y.;)nbv@~t •.s.e;O:'l<i:tH·\C:'I!::s;,<Otn
l.Q~'i\1IH<"o~ Aj·,Na......... o;,)l'H' :$>tT~~ ......Ai--"""'Olh""H t'lh»tl1:Ct. Pt.C•• Y""nilu Ai-$J¥\.<.tV<J;h
RGF-YNB-PHY-SOIL-15-02
01 08.2021 Copy Right Resrved by RGF
r-==-r"',,",,-" c.- L:-L::---'U I ~ ,";:: - ~~ J" l.::?~ f ~
AnERIi RIVADH GEOTECHNIClUE & FOUNDATIONS ,CO.
p~o_ no'll :J02:7'j;. Y~""'bU Al><Sin;l'!r';tl~~ MVAS ~::u:)(.)o'" Kr.A. TC''II'a:;hoh~~ .,966 (:1"l) 3750"~'92 I 325-O!:)9::l Fax~ 4-966- (:1..4) 32!;.Q,?4G fi,l'l'll';l)I,'Z. ru'-v.anb'um:t~tt.n.~O>1;.;::tet'l~>C.I'a:,col'll'1l
lO-t.--..-tk»n:. M.N ....YV.ao..lono :'i.1.r"",-w1. Hioll.Af-~ ... h.'in bi~lY·k.t. R,<..~ ..... "'nbu A;-shl.4>ty..h
o
ENVT. COND TEMP 23.6 C HUMIDITY: 40%
Test Started Date 01.02.2022 Test Completed Date: 02.02.2022
S-1
NO: XP-4
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
-;'...A.J • r
~'7f) [~II . . . . . . LA.....::_/f) 1J'i ~~~-:c
.". _ "" _ G>
~"'::-'.-/' I;..J____
_ I --. I w. ;A.. - / '
0
ENVT. COND TEMP 23.6 C HUMIDITY: 40%
Test Started Date 01.02.2022 Test Completed Date: 02.02.2022
-------
SAMPLE NO:
CAN NO: S-2
WT. OF SAMPLE + CAN (WET) (gms) 340.40
. OF SAMPLE + CAN (DRY) (gms) 336.90
• OF WATER (gms) 3.50
WT. OF CAN (gms) 20.35
WT. OF DRY SAMPLE (gms) 316.55
WATER CONTENT (%) 1.11
RGF-YNB·PHY-SOIL·15·02
01082021 Copy Right Resrved by RGF
~ID IZlll...::-l..::.-~U I;, if'-=?/ I ~
AnERlcon>p~"y I~.-'''''':' v.~. RIVADH GEOTECHNIOUE & FOUNDATIONS CO~
p,o~ Ih~)oI302:7". ·.rnl':lUH AI""st",,;\.y ..h. N)YAS 5.1000.. ~5A "r~~ephOfle! +96.6 (:1.4) a2'!:>09!a2' /212'5.0!)'93
il~x:.. HtC)tl~ A}_N;,o......-... n,;:.n~i $t:rC)'II;!r-. 1-'till.nJ_"'-"ahllOH
RGF-YNB-PHY-SOIL-15-02
01.082021 Copy Right Resrved by RGF
v '----'"
- "'---
I -" /
~ -- -ttl
v !J' _ft!_ _ ~ ~~...-Jj~
An ERI Company RIVADH GEOTECHNIOUE & FOUNDATIONS CO.
:P.O~ no.. ::J077:t. Y;),fibu N~-5ir.~'Y;H1<~ MVAS 53000".. K.5A T"'l~ph~! *966 (34) ~25<)9!)~,/ ;i);;l~::;)
t.o<<atfoo!. N-N ..."""an...nd Sl.,'.,.o(rt~ .~Qi AJ-Mllh~n
SAMPLE NO:
SAMPLE NO:
RGF-YNB-PHY-SOIL-15-02
01,08,2021 Copy Right Resrved by RGF
"c'-L:-L::...-U I~ ~~ ~'-=?../ I ~
An IEftl COlTlP''''Y I ''!II-'W~ ~I RIVADH GEOTECHNIClUE & FOUNDATIONS CO.
P.O. OQ>O< 30;r.7'1. Y~nbU AI<1S(~;'I'!!I~h • .r.>'t'YA-:'!' 51000.. t(SA TtH.:il'~"'hone: +~(i~ (":i ...... a-2'SO"';'U2 I 32&099:;) F ..X: .~;(;.o(~ (14) U::t$O!')·'U" f>"ot'naa~ rf('.,.y':''''bu«P~t~g~¢>1l.?iel\C:'J!':'S,(;orrt
l<X.·atk.>n~ .AA~N""w'H'flnd 5t11·~ ..tr~ H;)l A\-r.IIuh.;.n OhJ;~l~'K. «..c .. 'Viwl,hl,~ A~-$i......,.tv~h
CLIENT
PROJECT
E NO:
RGF· YNB·PHY·SOIL·15·02
01.08.2021 Copy Right Resrved by RGF
~~ v. ~t....::.-L.:::...--'U f!, ~~y
- _. i.../" ~/
I~
An ERI Compan:" ~~~"',u Gi!J1 RIVADH GEOTECHNIClUE & FOUNDATIONS CO_
P.o.. OQ)t 1>027'1. Y:lonbu Ahs'n~1y$jh~ MV/\$ 5;1000" Y.SA TeJ~phQ~: .!H:;6 (:14) 3:2!>Q<")9;J; I 32${.)993 :r"f"y,aht:ouII?J>1Ii1t;s.~I>!t,.clenc~._COM
....~,-~... lfoo!.A~,N.'l_ar.R .. ~d 'S'I;J"1r'(¥t. H~l AI··Mahan
CLIENT
PROJECT
E NO:
S-11
OF SAMPLE + CAN (WET) (gms) 289.00
OF SAMPLE + CAN (DRY) (gms) 277.10
OF WATER (gms) 11.90
19.47
. OF DRY SAMPLE (gms) 257.63
R CONTENT (%) 4.62
RGF-YNB-PHY-SOIL-15-02
01,08.2021 Copy Right Resrved by RGF
€'j;{f) [~~l"-
v "'--" l.::.-~(J/~ '..
.. w .~.-y
_. if~
_ :::.r'If~
...... ERI C<>mpa"y I<;f. c.' i i'.l~ ~
~£
SAMPLE NO:
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
-=:;;;;:---~, c.- L:-l..:::----'U I.!' ;: G> -~. -1! ~ L:--~ I ~
~:~
An ............ """'pany I ~I RIVADH GEOTECHNIOUE & FOUNDATIONS CO_
Oo>t 3027:1. YlU'.Ibu AlMSlr.;lyo»h. -IV1VA;:" 53000~ KSA TeJIli!'J"'hc:»H'!': +96.6 (3~) 32S.00c;:0s)2 /3250993 f':..x: -.966 (:1.4) 32509.0\-6 E".t'lo311.;."."',..ya ..... lbu@.etl.e.t!'t:>~i-.e,...:ce".c:orn
lo~::at~oo:.A~·N.,. ........U\.H.d 5tn:-ol"'. H..al AI-~uh<ln Dh;tTic.t. '{,c .• Y,;"nhu A;I~S~n~~~V ... h
SAMPLE NO:
RGF-YNB-PHY-SOIL-15-02
0108.2021 Copy Right Resrved by RGF
r-=~~-n 'C.- L:::.-~(; f ~ ::: Go ~ .:;;;~ J" c;..,..,J I ~
AnERI RIYADH GEOTECHNIQUE; FOUN;;ATIONS CO.
P.O_ Box 30.;0',7:1, Ynobu AJ"SJt'4;lY;')h~ MYAYo S::tOOO.. KSA TCJC-tloho.n<o-~ +966 (:14) 325>0:992 132509?3 F:::lrX; ... ~(i<ij. (14) S:Z::'O'?4t:). ID"na'lJ~ '·n'o0f',u.r.bu@.e:Ha~~h.tn':;'I!z •.C<>M
"'tX,"'*tfoo::..l'Ll-N;.t\N.. u....;:H~d Sl.t,..."""et. H"'II Al-~""h~n rJOt"t.~I~~, R.C" ~""r(bu .A:k5jn.;,I>i".",h
0
ENVT. COND TEMP 24.5 C HUMIDITY: 37%
Test Started Date 01.02.2022 Test Completed Date: 02.02.2022
------
NO:
M-33
OF SAMPLE + CAN (WET) (gms) 363.50
OF SAMPLE + CAN (DRY) (gms) 356.90
OF WATER (gms) 6.60
26.46
WT. OF DRY SAMPLE (gms) 330.44
RGF-YNB-PHY-SOIL-1S-02
01.08.2021 Copy Right Resrved by RGF
~ I ." -"Uf !' --- -~' . .Ai, ;.,.~ 'l::.r:. A~
~~
, ",,- t." G>
~'!) V ""---" '----'-- _ -" ~~..,. 4.....-' _:/' ~
NO:
M-12
OF SAMPLE + CAN (WET) (gms) 321.00
. OF SAMPLE + CAN (DRY) (gms) 319.00
. OF WATER (gms) 2.00
OF CAN (gms) 26.52
OF DRY SAMPLE (gms) 292.48
WATER CONTENT (%) 0.68
RGF-YNB-PHY -SOIL-1S·02
01082021 Copy Right Resrved by RGF
1 fi.:~ ~1-c:.-L::.-~Ull' j-~~f~
An IERI C<>mpa"y ~.l':'.!~' ~ RIVADH GEOTECHNIClUE & FOUNDATIONS CO.
r~~o. OQ>ot 30.>1:7:1. Yanbu At'Sin~IYiin'h> ,...,VAS 5:1000.. KSA Tcl.,e.phcJ1.-e; ,.,966 {14} a _ ;;l.!i.O~9:Z / 32509'97)
'.!;>Catioo::: A)-N •.nN".. ~n»ru'
$lr~("t ••• ",1 A~lV1ah;;.x\
NO:
A-8
OF SAMPLE + CAN (WET) (gms) 353.60
OF SAMPLE + CAN (DRY) (gms) 351.10
2.50
WT. OF CAN (gms) 23.45
. OF DRY SAMPLE (gms) 327.65
R CONTENT (%) 0.76
RGF-YN6-PHY-SOIL-15-02
01082021 Copy Right Resrved by RGF
.;;.r --!! ~ l.;;.J
f An Eftl Com",,",
1'.0. no>\; .!KJV1, 'ian!".. A1~srn;'ly;o.h. MYA' $'1000, l:SA 'l'clfjphon¢:
t:.A..:::_l.:;;.,.r [II~ :.: _0.
RIYADH GEOTECHNIGUE & FOUNDATIONS CO.
+"'" (14) ::l:.I:!}0!)g2/3:t!!'~3
~+7 .,.Y'/::.r: ~4..;'
RGF-YNB-PHY-SOIL-Ol-04
01.08.2021 Copy Rights Reserved By RGF
Cl.:-l..;../V I~ ~.d i../ l;?..J I ~
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
".0. tb"Jl !U)rt'1, Y"'hbuAt-5Tn~IY"'h> MYA5 !H(}(:)o. XSA TcIC):lhone; -..966 tIll) 3250(19".12 I :12!>C~9~ 1'...,,; .... 966 (t.,) :l:t50!:M(J f)h,,!1, ~R'.vanb,,@~,I"cQld(,fI(;C!U:Otn
l,t.<:"'lh)(,: A!,Ni:lw.uuod :st{~i!(. H~I At<MaW"t, Phlil<:t.lt.ot'.: .• V.llibu AI:.:$Ii .... 'yah
«
~~O
r5 :;;30
i>2 20
5:: 10
o
100 10 (jRIIIN SilT IN JII.L1MITERS 0.1 0.01 0.001
RGF -YNIl-PHY·SOIL-01-04
01.08.2021 Copy Rights Reservecl By RGF
f An EOI compnny
CA.~-l;./[JI~ ~ .~~ J"y..--l I ~ =
RIYADH GEOTECHNIGUE & FOUNDATIONS CO.
P.O. t).Q"aO:Y/1. Yanbu AkSfo;"YilIh, MVA1 5tO()O.;<s..A "tcleplu;w>e; -..96CS( )c4) ~2~()!}9Z I ~2!\.09:!i3 I'al<: -+966 (14) jZ:'H)94d tlnJlll: q:~"v'lI'1b\jMt::-{IK¢OrK.It'fi~(:).('Qm
t~"'U"h: Al.NJ"""j,'>OlIu(l $\f~~~. H,;! AI.M.'Ih:H. Oh.tlld. R.<: •• Yill,b'U Aj.,;Slilal., .. h
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-01) DATE SAMPLED: 24.01.2022
SAMPLE SOURCE TP: 01 DEPTH: 2.50 m DATE RECEIVED: 31.01.2022
SAMPLE DESCRIPTION: Brown poorly graded SAND with silt. SAMPLE NO.: S-6
ENVT. CONDo TEMP. 23.8 o C HUMIDITY: 35%
DATE STARTED: 01.02.2022 DATE COMPLETED: 03.02.2022
RGF-YNB·PHY·SOIL·01-04
01.08.2021 Copy Rights Reserved By RGF
I(c~ ~ l.;../[JI~~~jy.)f~
f AnERlcompanv ~~.
(.',0', (..;tn., J)O~11. y",llhu Al~51n;Uy ..h. MYA$ 5"1000. X5A
v ...
t=.A..:.;__
RIVADH GEOTECHNIQUE & FOUNDATIONS CO.
"f>e!e-ph6ne< -.900 (14) :)2:S099.l/12~Q!J9.3 ,,,,xc ..
:1)6($ fl.t) :!'2!Sti9A(S :i1m')U; q.r·yl>nJ;".,@<:oIHeQli~t-a<,.,,. ..(,I;~,,,,,
lU;;:.tifJi)! Al,N;:tW3rui1tl(t st<~t. H~ AI-Mah",n l)fst(ki. h>C •• y..Iot.<J A),$ln.(>llI'.ah
RGF·YNB·PHY·SOIL·01·04
01.08.2021 Copy Rights Reserved By RGF
'CL:-l.;;,/UI,,~~~Y..JI~
RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
P_O. tk!lt\, .,0271, VISr>bU A"1Jn~Jy::.h. MYA$ ~i()()o, kSA 'telt:l'hone; -.-!W-(i t~4~ a~~g:t I :)2~3 p",,,: ~9/$6 (til) 1\25094(5 !'rn.>1I, fiRf''I'anb''@\:'f18¢Q~dt"f'!(;e!l,-(.o>n
I.(](:.all(;of); j\.1-"'~ .......;(I"W:hd Sl(.:~t, tI,,1 AI,M3h~j, DI,.,hJ;;:t, R.,c,. y .. r.I.>1J Ah11fli.lyal1
6H
4" 3" 3/4" 3/8" 4 10 40 100 200
100
90
1;; 80
o
z
70
C/i
C/)
<
"
~
w
22 20
g: 10
o
100 10 lmAIN SIZI: IN JIlUMFTFRS 0.1 0.01 0.001
RGF-YNB·PHY·SOIL·01-04
01.08.2021 Copy Rights Reserved By RGF
CL-l.:;../V I, ~t:?Y c../,-:-?.) r ~
RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
V.O. tw. a027i.. YI)MU AI·,srt>;;"yp.. MVJ\S S1iX1O, /($A 'fele"hOf_e: .... ~6:1 h -.1) Zl:t~O~:l!' 1.):;t50!;1-93 frut; +<)(!/) f" 011) .,~:;og-a(S t'm03l1: c1\r..... ;!Inbll~I:".18C'U)de-n.cc,.>.etltrl
l{J(... tf{]A~ AI~Naw:.'lt.... u('I ~t'-e<tt. 1\.:0\ AI.M~h~h t>r",t/IcL A.C .... y,tlll!v AI,~lil$'y .. h
SIEVE
SIZE
1 I
SPEC.
LIMIT
WEIGHT
RETAINED
% RETAIHED % PASSING
I
WATER CONTENT: (ASTM D 2216-19)
3"
21/2" CAN NO. K-9
2" 0.0 0.0 100.0 WT.(SOIL+CAN) WET: 2206.80 grm.
1 112" 89.1 4.5 95.5 WT.(SOIL+CAN) DRY: 2190.60 gms.
1" 89.1 4.5 95.5 WT.OFWATER 16.20
3/4" 107.6 5.4 94.6 WT.OFCAN 205.20 gms.
3/8" 136.4 6.9 93.1 WT. OF DRY SOIL 1985.40 gms.
166.1 8.4 91.6 WATER CONTENT: 0.82 %
361.9 18.2 81.8 REMARKS:
805.7 40.6 59.4 NON PLASTIC
1294.7 65.2 34.8
1617.4 81.5 18.5
#100 1786.7 90.0 10.0
#200 1857.1 93.5 6.5
PAN 1859.2
TOTAL SOIL WT. 1985.40
:ASTNl15 J2'lJ:2-V
U.S. STANDARD SIEVE SIZE UNIFIED SOIL CLASSIFICATION SYSTEM
Saeed
Checked By/Reviewed By: _ _ _ __ Akhtar
_ _ __
RGF ·YNI3-PHY·SOIL·01·04
01.08.2021 Copy Rights Reserved By RGF
' -... -;,;:. .
f AnERlcompany
~m
~~~.
".0.00)(802"7:1, V .. nbu At-.S!n;ly;:ah, MYA'S !>'1O()(J, ~t>A
~ GL--l.::----V/~~~V'_=?.)I-~
U,,! RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
'telr'phone: ...966 (14) 3:.t:lo0992 13:.t50~9.3 t'al<:--+9GCi (101) ~2'S094Ci Em"lI; faf~yanbu@el!HeoK'(.onc(:~.com
~OC .. tlCJ('~ AI.N.dwanolJld !\tlor;'<:-t. lul j'lI.I\.~,:l.})""(, DBtilc.i. It.(~ V.!;,bu Ahjlil""t,..;.ah
Neom desalination plant to gayal transmisssion system. (LD-O 1) DATE SAMPLED: 25.01.2022
TP: 03 DEPTH: 0.60 m DATE RECEIVED: 31.01.Z0ZZ
SAMPLE DESCRIPTION: Brown silty SAND. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 23.2 a C HUMIDITY: 34%
DATE STARTED: 01.02.2022 DATE COMPLETED: 03.02.2022
RGF ·YNB·PHY·SOIL·01·04
01.08,2021 Copy Rights Reserved By RGF
~.-------,-..,....." t.:...-L--l.:.---'U I~ ~~ J:'G..) I~ ..... __ of. ..
RGF·YNB-PHY ·SOIL-01-04
01.08.2021 Copy Rights Reserved Ily RGF
1~~Cl::-l.:..--iJl,::~ ·~~c./y..)l~
f An Enl Company "
QW>
W!~tohl"
RGF-YNB-PHY -SOIL-01·04
01.08.2021 Copy Rights Reserved By RGF
III
C~L;./VI-, =: ·.:7~if,-:-?.)f~
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. nOll ao:.t:r.1. Y:n'>tIUAI"!S1 ... ~! ....h. MVJ\$ :>"1000, KSA "t.;:lephooe: ·t966 (14) 32~"'92 / 32~'93 (~.,.; .96t1 114) ;a-Z~:H)94(} fFm,,!J; '1tf.'V.. nbu'@efr~o~dt'()CC:o'<';UJn
loe.. U","~ AI~N~w"fi')Hd st-h'o!l. Mal Al.M.3i• .,tl D!ihkt. A.C .• "I';;.-,"u Al"ihl;iotY.Joh
~
100
90
80
w
u 70
5';~o
~ 1§50
;:: 1l'40
@;$30
~ 20
15:: 10
o 1M 100 0.01 0.001
10 GRAIN SI/.E IN MII.J.JMETII(S 0.1
RGF·YNB-PHY -SOIL-01-04
01.08.2021 Copy Rights Reserved By RGF
~
P.O. IJOJOl
f An ERI Coml"'ny
ao,,.,, V~r>bu At<oSffj~lyah, <VIVA!) l)~OOO~ X!iA
CL-t..::---{JI~ ~~ ~l:?.) 1~
RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
'Toe'~..hvne; ~() (14) :t2~? I :t2~3 t'a",; ... ;tSti (14j3'2:!>094i} f!HMIJ; qif~y"'nbu@ellfl:eu:K.!e~.(:om
LU<:t<UOO: Al.N .. wa'.iHwSt.... tt, Hal AI.Mah"f. ()j,.tth.t. It.<: •• V.lr.bu Ak$ltlatll'.:ih
RGF -YNB-PHY-SOIL·Ol-04
01.08.2021 Copy Rights Reserved By RGF
f An ER. Com""ny
""0. -aol'i ;30:C71. Y.;:.;f>bu At,!fJ~';'V.l>h. MYA$ $:{OOO, X!9J\
CL:-i....:-'U I~ ~~ cYl;?...J I
RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
"telephone.: ..-960 (HI) 31'W992 I ~'250993 I'.. ,,! +9«:>~ ('-4) '~!if;l!:UH~ flm.lll. rnr,,,~oL>lJ@I':.le¢t;lM:;J(;'f),,::c"A:I:l,"
liJU\'U".fi: A"NAW':tIt... ~tI(' Stt-C"'!. Hitl AH,";3h..",. t>f~tO<.'" I\.C., "-,r,\I<.4 Ak!*,,,,,I)1>1h
WEIGHT
RETAINED
% RETAINED I % PASSING II WATER CONTENT: (ASTM D 2216-19)
3"
Z 1/Z" CAN NO. JF-3
Z" wr.{SOIL+CAN) WET: 2014.15 gms.
1 112" WT.{SOIL+CAN) DRY: 1934.90 gms.
1" wr. OF WATER 79.25
3/4" 0.0 0.0 100.0 WT.OFCAN 304.30 gms.
3/8" Z4.Z 1.5 98.5 wr. OF DRY SOIL 1630.60 gms.
#4 43.8 2.7 97.3 WATER CONTENT: 4.86 %
#10 147.5 9.0 91.0 REMARKS: NON-PLASTIC
#20 509.9 31.3
#40 950.5 58.3
#60 1243.5 76.3
#100 1395.5 85.6 I 14.4
#200 1506.0 92.4 I 7.6
PAN 1509.2
TOTAL SOIL WT. 1630.60 gms
RGF-YNB·PHY ·SOIL·01·04
01.0B.2021 Copy Rights Reserved By RGF
I ~~ ~. -C:-l:.-L-'{jI~~r.:J~,-:?-"I~
f AnERlcompony ~~' .."m
P.O. Uo",",,0273, V",obuAI.5Jo;lyah. MYA'$ 5-:1()()1}. y.'SA
l.(;I(;.IoUuf,:
RIVADH GEOTECHNIOUE & FOUNDATIONS CO.
"'elepl"~ffie; +900 (l.ll) 31:5-0992/ ~1:509!J.3
A'~N..,.'Wa ...;.1I)(f
1<;:.,.: ... 9tJ(i {lol) ::!J2~094U ~m.:.ll; rflr~y&nblla>i:"IKeo~c.it..,<:e,..tom
.$h'«t. Hal AI,M.-:ohIU'I Dlslrld. Ii..'-:., Y.l{',bU A.I-:$II1 ..I)I.lh
~ 20
it 10
o
100 10 GRAIN SIZI: IN Jll.l.ltvll:TFRS
0.1 0.01 0.001
RGF-YNB-PHY -SOIL-01-04
01.08.2021 Copy Rights Reserved l3y RGF
'C.-L-\...:---'U I ~ ~r.tY t../ y.,J I ~
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
~.o. 30l<. 3027:1. Y.;mbuAt.$ln~r)'llt" MYAS :110()(),)($.4 'fO!lcph<:il'1«!1 "",~r}6 (14) 3250992 1:)15-0993 fI"lII:; T?66 (1.IJ) 32:~()946 £m"n: tr<I'vtlnb<.l@r:'<l~eOldl:'flt;('".(om
. lQc..lOlI>?f.: AI.N;aw""'~jj{t ~t(,,'t;t. lUi Al.M.ah.. t. Dh;tfl(.t,IU':•• Y.l>'lbu AkSltWly~h
RGF·YN B·PHY-SOIL·01·04
01.0B.Z021 Copy Rights Reserved By RGF
P,Q. BoX 30:2"11, Yanbu At~Sin;fY~h~ MYAS 5"1.000.. KSA Telephone: -+966 ('111) 3250992/32S0993 f.lx: ,.966 {I") 32509"6 Em::tn~ r8r~yGnbu@t!rlBt!osdenc:e$.tom
lOC.ltl(}m A!MNawammd Street.. Hal AI-Mahan D!stfjct~ R.C... YMtbu AI Slnalyah
PROJECT: Neom desalination plant to !loyal transmisssion system. (LD-01 ) DATE SAMPLED; 24.01.2022
SAMPLE SOURCE: TP 01 DEPTH: O.60m DATE RECEIVED; 31.01.2022
SAMPLE DESCRIPTION: Brown poorly graded SAND. SAMPLE NO.: B-1
ENVT .COND. TEMP.: -=2-=3-:.5:-10rrC=--------:-H-:-:-U-:-M-:-~DI=T:-::Y-:---3-5%-0
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
..... LL
t:
.l!l
t:
o
U
.... PL
.l!l
<1:l
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY -SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
GL-l.;../U I, :;: .....:;,;~ ~ '-:?~ ,~
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
p,o, Box 30271, Yanbu Al-sJn~IV~h-" MVAS 5:1oo0,,}(SA rclephOlltt: -t965 ('14)32S(}992 J 32:50993 fax;: +966 {14) 3250')46 EmaU! rgf-yanbu@erlgeo5eh!-nt::es.COM
Lo(:O)tlQm AI-Naw.anand St~et, HaJ Ai~Mahan Distri<:t~ R.C... Yanbu At-Slnalyah
PROJECT: Neom desalination plant to gayal transmisssion system. (LO-01) DATE SAMPLED: 24.01.2022
SAMPLE SOURCE: TP 01 DEPTH: 1. 20m DATE RECEIVED: 31.01.2022
SAMPLE DESCRIPTION: Brown poorly graded SAND with silt. SAMPLE NO.: B-2
ENVT.COND.TEMP.: 24.1 DC HUMIDITY: 36%
STARTED DATE: 01.02.2022 DATE COMPLETED: 03.02.2022
L I QUI D LIM I T
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
..... LL
c
.l!l
c
o
U
... PL
.l!l
('\\
5
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
I
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved Gy RGF
AnERI
P_O. Box 302"11. Vanbu Al..sln~lyah. MYAS 51000.. KSA lejephollC'~ ",.9G6 (:14) 3250992/3250993 Fa)!! <t9S6 (14) 3:250946 Emal\: rg1..yanbu@cngcosdenC::o"HGm
Locution: Al-N~w~n ....nd Stt-cat. H••I Al·MAhan ot.l>tri.c-rz R.C., Yilnbu I\l-Slnillyah
PROJECT: Neom desalination plant to gayal transmisssion system. (LO-01) DATE SAMPLED:
SAMPLE SOURCE: TP 01 DEPTH: 2.50 m DATE RECEIVED:
----
SAMPLE DESCRIPTION:
--------------------------------
Brown poorly graded SAND with silt. SAMPLE NO.:
-----
S-6
ENVT.COND.TEMP.: 23.8 DC HUMIDITY: 35%
STARTED DATE: 01.02.2022 DATE COMPLETED: 03.02.2022
L I QUI D LIM I T
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
....!: LL
....!:
(J)
o
U
... PL
.l!:!
l\:I
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
Tested By: _ _ _ _ _ __
M.lrfan Checked By/Reviewed By:
- -Saeed
--- Akhtar
--
Approved by: Awais Nisar Yasin
RGF -YAN-PI-lY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
:---r==r"91 v " I - I - -,...tU I - w • -"j. Ai. ;:, I -, 11::.r:.:-..""/
AnERI ~,[~ ~~H~O~~~NI~~~~N~IO::O.
P.O. Box 30271. Y.1nbu Al..sJ03Iy:t1f\. MVAS 51000. KSA Tet~phon~t -t966 {'14) 3;2S0'.l92/3250-P.l3 32~0946 Etndll: rgf-yaf1butfPc:rI8t!mcl~l"I,<s.r::om
location! At-NaW3t'Hlnd Strcnt, Hai AI-M;,lhan Al-Sina'y.a.h
PROJECT: Neom desalination plant to )layal transmisssion system. (W-01) DATE SAMPLED: 24.01.2022
SAMPLE SOURCE: TP 02 DEPTH: O.60m DATE RECEIVED: 31.01.2022
SAMPLE DESCRIPTION:
----------------------------------
Brown poorly graded SAND with silt. SAMPLE NO.: B-1
ENVT.COND.TEMP.: 23.6 oC HUMIDITY: 36%
STARTED DATE: 01.02.2022 DATE COMPLETED: 03.02.2022
L I QUI D LIMIT
RUN NUMBER 1 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH
NON-PLASTIC
WTWATER
gms
%
NO. OF BLOWS
-c
.2
c
LL
o
U
-
~
~
Q)
t il
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL
.
+ DISH
____
'.~~_r~.~"~.~,.~~~·~_ ~~~~>~ ~"~.~"
RGF-YAN-PHY -50IL-02-04
01-08-2021 Copy Rights Reserved By RGF
P.O. so:.t 30271~ Y.lnbU Al.SlnaIYOIh. MYAS SiOOu. KSA Tef~phot'le: -t9G6 (14) 3250"'>92 / 32:509;)3 f:lx: ·.966 (14)3250946 ErnaH! ys'-v.mbu@erlg.etlsdences.com
l{)(:;)tlom Ai-Naw.o)nand Str(l~t:.. H;;I Al-Mah.m Dls.trict,. R.C., Yanbu At·Slnn.y ... h
NON-PLASTIC
..... LL
c:
Q)
.....
c:
o
U
... PL
J!l(ll
s:
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
CONTENT
NON-PLASTIC
PROJECT: Neom desalination plant to !layal transmisssion system. (LD-O 1) DATE SAMPLED: 24.01.2022
SAMPLE SOURCE: TP 02 DEPTH: 2.00 m DATE RECEIVED: 31.01.2022
SAMPLE DESCRIPTION: Brown poorly graded SAND with silt. SAMPLE NO.: 5-5
o
ENVT.COND.TEMP.: 24.2 C HUMIDITY: 36%
STARTED DATE: 01.02.2022 DATE COMPLETED: 03.02.2022
L I QUI D LIMIT
RUN NUMBER 1 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WT WATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
....s:::: LL
.l!l
c:
o
U
~ PL
.l!l
rn
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER
NON·PLASTIC
WT DISH
WT DRY SOIL
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
·CA•.:_l..;./U I, ~~ J:'~.) j ~
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O, Box 30'271, Vanhu Al*S!n;:lIYOlh. MVAS 51000. KSA Tej~phone~ ,t9&5 (:14) 325(j<")~2 J 3250993 F.:nt: .966 {liS} 3250946 EmaU: ret>yanbl.l@etIBeosclC"hc~~_com
liJCM'Cf)l Al-Nawammd Sttu4t~ Hal AI-Mahan Dtstrict. R.e... Y.anbu N-5I'n"'vtlh
L I QUI D LIM I T
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
....s::: LL
....s:::
Q)
o
U
... PL
....m
Q)
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 4 CONTENT
No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AYE. PLASTIC LIMIT
RGF·YAN·PHY·50Il-02-04
01-08·2021 Copy Rights Reserved By RGF
1!IGL:-L;../{JJ~~~if~.)I~
AnERI .vw RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. Box :302:'11. Y3nbu At~sln~lvah~ MYAS 51000. KSA Telephone: +!l66 ('14) 3250992 J 3250993 f'BC! ·H)66 (14) :.nSO~:)46 Emalh rgt.y'():nbu(;.'tIcrls(:!o5cknces.com
loc.,Uon: AI-Naw.. n~nd Str~.at. Hal AI-M;)han District. H.C... Y.;.)nbu AHilnnly3h
PROJECT: Neom desalination plant to !layal transmisssion system. (LD-01) DATE SAMPLED: 25.01.2022
SAMPLE SOURCE: TP 03 DEPTH: 2.00 m DATE RECEIVED: 31.01.2022
SAMPLE DESCRIPTION: Brown poorly graded SAND with silt a: gravel. SAMPLE NO.: S-5
ENVT.COND.TEMP.: 23.7 DC HUMIDITY: 35%
STARTED DATE: 01.02.2022 DATE COMPLETED: 03.02.2022
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
....c: LL
2
c:
o
U
... PL
2III
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
..... LL
r::
.....
Q)
r::
o
U
.... PL
2n:l
S
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN-PHY-SOIL-02.-04
01-08-2.02.1 Copy Rights Reserved By RGF
Gl:.-l.;../U/~ ~~ t../~.)f~
An ERt Company RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. sox 30:n 1. vanbu At~sln3fy;ah," MVAS 51000.. KSA feiephone: +!)66 (:14) 3250992 / 3250!J!J3 F\lX: .. 966 (14) 3250946 Emi:llh rs.f.yanbu@NIa.coselel1tcs.com
LOCuUom I\I~N3w3nand Str0et# Hat AI~Mah<lo t}t$tri<::'t:~ R.C., Yanbu Al-SfnOl:iyah
L I QUI D LIMIT
RUN NUMBER 2 3 4
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WT WATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
,.., LL
t::
.e
t::
o
U
... PL
.ero
s:
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WT WATER gms
NON -PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN-PHY-SOIL·02-04
01·08·2021 Copy Rights Reserved By RGF
r-"~--r=9'\itl=91·GL:-l;../(j I~ ~~ ~0.)'~
AnERlc.,m~,:,~' I~I RIYADH GEOTEC':NIQUE ~~OUN~ATJONS CO.
f).O. SO);! 302·11. Vanbu At..sln;IY3h~ MYAS 5:1000. KSA Tc.lephoM: -t966 (:14) 3250',)92 / 3250993 32~tJ946 Em:lll: r8f~y.mbuG...'OcrlBC()ldenc~~uom
FOol<': ..-966 (14)
location; A.·N:iwan~nd Street~ Hal AlooMtlhan O!strkt. R.C.,. Y,anlm AI·Sfna\yan
PROJECT: Neom desalination plant to !layal transmisssion system. (LO-01) DATE SAMPLED: 26.01.2022
SAMPLE SOURCE: TP 04 DEPTH: 2.S0m DATE RECEIVED: 31.01.2022
SAMPLE DESCRIPTION:
----------------------------------
Brown well graded SAND with silt. SAMPLE NO.: S-6
ENVT.COND.TEMP.: 23.7 DC HUMIDITY: 36%
STARTED DATE: 01.02.2022 DATE COMPLETED: 03.02.2022
L I D LIMIT
RUN NUMBER 1 2 3 4 5
DISH No.
SOIL + DISH
NON-PLASTIC
gms
gms
%
...
t:
LL
.l!lc:
o
(j
... PL
.l!lClI
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
M.lrfan
Tested By: _ _ _ _ ___ Checked By/Reviewed By: Saeed Akhtar
---------
Approved by: Awais Nisar Yasin
27.01.2022
SAMPLE SOURCE: TP 05 DEPTH: 31.01.2022
SAMPLE DESCRIPTION: Brown poorly graded SAND. B-1
ENVT.COND.TEMP.: 23.5 DC HUMIDITY: 34%
STARTED DATE: 01.02.2022 DATE COMPLETED: 03.02.2022
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH
WT WET SOIL + DISH gms
WfDRY SOIL + DISH gms
NON-PLASTIC
gms
gms
gms
MOISTURE CONTENT %
NO. OF BLOWS
..... LL
c:
~
c:
o
U
... PL
~
III
$:
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
- - - + - - - - - - · · · · 1 - 1- - - - - - 1
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN-PHY-50IL-02-04
01-08-2021 Copy Rights Reserved By RGF
~~=1Cl::-~{jI,~~~,-:?..JI~
AnERt RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
PD. Box 30271. Yanbu AI~SJnaly3h. MYAS S:1000~ KSA 'Telephone: -t966 (:14) 3250992/3250993 fax: 40!}66 (111) 3250946 Emalh r61~y;,')l1bu@ct!8cosdl!nces.com
locatton: "t-Nawanand Strl(lct. Haj Al-Mahan 01s:trict. R.C.~ Vanbu Al-Sinalyah
L I QUI D LIMIT
RUN NUMBER 1 2 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
....t: LL
2t:
o
U
... PL
2<Il
~
Number of Blows N-P
PI
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-OZ-04
01-08-2021 Copy Rights Reserved By RGF
P.O. So" 3Q271,. vanbuAt~Sjt'j~IY"h. MVA-"t 5:tOOO~ KSA ·Telcphorw~ -t966 (14) 3250"::}92/32S0!.l93 F;l)O:~ +966 (14) ~2S0946 Eman~ r8t~Y+lnbu@>crI8-cosdetH~::~!li.G:nm
location:: Af-N3wanond Street, H:ll AI-Mah;;ln otstriGt. R.C... YOlnl1U At Srt):)IY3h
NON-PLASTIC
....t: LL
....t:
Cll
o
U
... PL
.I!l
III
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER z 3 4 CONTENT
DISH No.
WT WET SOIL + DISH
I WT DRY SOIL + DISH gms
WTWATER
NON-PLASTIC
WT DISH
WT DRY SOIL
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
Tested By: _ _ _ _ _ __
M.lrfan Checked By/Reviewed By: Saeed Akhtar
---------
Approved by: Awais Nisar Yasin
RGF-YAN-PHY -50IL-02-04
01-03-2021 Copy Rights Reserved By RGF
~~=> Cl.:-l.;../U I" :;::,7r.:J! J"~.) I ~
An ERI RIYADH GEOTECHN laUE & FOUNDATIONS co.
P.O. Sox 30;nl~ VanbuAl..sln~jY:ih. MVAS 51000. kSA "Tclt:ph()t'i{!~ ,t966 (1.4) 32S{Y..)92/3250993 F;,)(: ·.966 {14} 3250946 t;"malh r8t~Y.lt1bu@'erlseo..dp.ncC'!$,cam
lOC:ltibt'it AI-NOlW;.'Jot'iiHUJ Stt"j!.fit. t-I~J AI-Mahan ()tstfict~ R.C.~ Vonbu AI-SrOillyah
L I QUI D LIM IT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER
WT DISH
WT DRY SOIL
MOISTURE CONTENT
NO. OF BLOWS
.....s::: LL
.&
s:::
o
(j
... PL
.&
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
I- .~,~-~,~-------,-
WT DRY SOIL + DISH gms
WTWATER gms
NON -PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN·PHY-SOIL·02-04
01-08'2021 Copy Rights Reserved By RGF
~~"""""'C-L:..-l.:-r(j IJ ~~ ~y~ I~
AnERt RIYADH GEOTECHNlaUE & FOUNDATIONS CO.
P.O. ao)!: 30271 p YanbuAt~Sjn~fyah. MVAS 5jOOO. KSA Tcjtphotlt!'! ,t966 (:14) 32509!J:2 J 3250993 fa)(~ '+966 (14) 3250!)-46 Em.:oll: r8t~y...nbuti'Pc"'lacosd~nC:II!$"com
l,.ee.;)tlQrH f\i~NaWOlnantt StrC".f!t.. Hal At-Mahan Otstrh::t, R.C.~ Yaobu AI·Slntl.'1ah
PROJECT: Neom desaUnation plant to gayal transm;sss;on system. (LD-D1) DATE SAMPLED:
SAMPLE SOURCE: TP 06 DEPTH: 2.00m DATE RECEIVED;
-31.01.2022
---
SAMPLE DESCRIPTION:
-----------------
Greyish Brown poorly graded SAND with silt 8: gravel. SAMPLE NO.: 5-6
ENVT.COND.TEMP.: 24.2 C
o HUMIDITY: 36%
--- -
STARTED DATE: 01.02.2022 DATE COMPLETED: 03.02.2022
LIMIT
RUN NUMBER 2 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
....c LL
.....c
(I)
o
()
.... PL
.i!lro
!'!
Number of Blows N-P
PI
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 4 CONTENT
DISH No.
_W_T_W_ET_S_O_IL_+_D_IS_H_ ......... _!'!l: __~_+__.___ .
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
Tested By: _ _ _ _ _ __
M.lrfan Checked By/Reviewed By: _ _Saeed
___ _ __
Akhtar
RGF·YAN·PHY·SOIL·02-04
01·08-2021 Copy Rights Reserved By RGF
P.O. (0)( 3027l., Y:II'"1bU At.Sin;lyah~ MYAS 5:1000.. KS,r., Tclephofl~: .. 966 (l.01) 3250992/3250993 H'I)(: .. 966 (l.4) 3.250946 Email: rBf.~yanbu@~rI8-C0:5C;~tlc.es.-com
I..oc.tltlon. ,r.,t-N",w;)nand Strcct, H;JI AI·MO)h;;ln oJs.trlct, R.C" Yoanbu Al-SlnalYi."Ih
L I QUI D LIMIT
RUN NUMBER 1 2 3 1 4 I 5
DISH No. F-4 F-10 K-10
WT WET SOIL + DISH gms 31.77 34.55 31.90
WT DRY SOIL + DISH gms 29.06 31.55 30.10
WTWATER gms 2.71 3.00 1.80
WT DISH gms 20.35 20.88 22.88
WT DRY SOIL gms 8.71 10.67 7.22
MOISTURE CONTENT % 31.11 28.12 24.93
NO. OF BLOWS 16 24 34
...... 36.00 LL 28
c:
~ 32.00
<3.... 28.00
PL 22
ro
(l)
24.00
5: 20.00
Number of Blows PI 6
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DiSH No. P-4 P-3
WT WET SOIL + DISH gms 29.85 32.56
WT DRY SOIL + DISH gms 27.66 29.75
WTWATER gms 2.19 2.81
WT DISH gms 17.50 17.25
WT DRY SOIL gms 10.16 12.50
MOISTURE CONTENT % 21.56 22.48
PLASTIC LIMIT 22.02
AVE. PLASTIC LIMIT 22
TRIAL NO. 1 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 5845 5975 6065 6056 5985
WEIGHT OF WET SOIL gms 1683.0 1813.0 1903.0 1894.0 1823.0
WET DENSITY gm/cc 1.803 1.943 2.039 2.029 1.953
1.94
1.92
MAX. DRY DENSITY gm/cc: 1.92
1.90 / '\
OPT. MOISTURE CONTENT % : 6. 12
1.88
/ I
\
~
0
E 1.86 I \
Remarks: Method "A" is used
Ol
>
l- 1.84 I \
iii
z
w
0 1.82
/
I
>DC
0 1.80 \
Tested by: M.IRFAN 1.78
/ \
-----
Checked BylReviewed By: 1.76
I
Saeed Akhtar
1.74
1 3 5 7 9 11
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
F· YNB·PHY·SOll·03·04
·CA.:_~(JI, ~~ J't;.;)r~
RIYADH G~OTECHN1QUE &. FOUNDATIONS co.
P.O. 80)( 30271J Yilobu AJ"Sfn;lyah# MYA$ S1000.. KBJ-\ Tel&phorw: ·,965 (l.t) .:i2S099'2; /32SM93 ,,~! 49~fi (14) $15.094($ fma,lh '-8f"yahbulkP'.I!r;8~~nces,tt}m
lO{~Uoo~ AJ-N;)w.ammd SticelJ- Hat At-Mahtln D;sbftl~ 11.'('1 Ywnbu A!-$JNI~~h
2 3 4 5
R ADDED % 2% 4% 6% 8% 10%
IL + MOULD (WET) gms 5916 5987 6081 6089 6065
T OF WET SOIL gms 1754.0 1825.0 1919.0 1927.0 1903.0
SITY gm/cc 1.879 1.956 2.056 2.065 2.039
CAN NO. A-3 A-10 K-10 5-3 A-6
WT. SOIL + CAN (WET) gms 415.33 429.56 450.36 434.27 437.89
WT. SOIL + CAN (DRY) gms 408.33 416.48 426.85 403.28 401.88
WT.OFWATER g 13.08 23.51 30.99 36.01
WT. OF CAN gms 37.54 40.75 40.55 41.88
gms 378.9 386.1 362.7 360.0
% 1.88 3.45 6.09 8.54 10.00
gm/cc 1.84 1.89 1.94 1.90 1.85
1.97
Tested by:
Checked By/Reviewed By:
M.ARFAN
1.85
<1?
II \
Saeed Akhtar
1.83
o 2 4 6 8 10 12
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
F· YNB·PHY·SOll·OJ·04
~~- ~ J Ij ••;..J~
·r'" I - ( - "'U" J .. '"
"'"'-'''--''~ ~ "...,"" ~ ~ V ..
,#1'-",.I""
'
r '
...
I
TRIAL NO. 1 2 3 4 5
WATER ADDED % Z% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 5978 6054 6150 6155 6125
WEIGHT OF WET SOIL gms 1816.0 189Z.0 1988.0 1993.0 1963.0
WET DENSITY gm/cc 1.946 Z.027 Z.130 2.136 2.103
2.04
2.02
MAX. DRY DENSITY gm/cc: 2.01
OPT. MOISTURE CONTENT %: 6.07 2.00 - /~
1!E 1.98
/
/ \
Remarks: Method He is used
(J)
i': 1.96 / \
CM.D.D =2.06'1/cc
U5
z
III
! \
~ 1.94
CO.M.C =5.35 % 0::
0
1.92 / \'I'
Tested by: WISAL
--------
Checked By/Reviewed By: 1.90
I
Saeed Akhtar
1.88
2 3 4 5 6 7 8 9 10 11
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
YNB -PHY·SOIL·03-04
P.O. Rox a02}1, y~l)buAJxSln;tyahl MYA'5. 51000. KSA Td~phc>n.f': ·~966 (14)325.0992./ 315(}<:)9] f.i)x: +966 (14) 3250946 [m~1)! rg'~y:lI)bu@etlg~o.sd~nc~u::om
Loc~tlQn~ AJ~Nawlln~nd Str~et,Hal AI-M<)h;}n Oh1rkt, A.c., Y~nbu Al-S1na!yJh
~rc~~ff~="
TRIAL NO. 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 5920 5995 6070 6085 6066
WEIGHT OF WET SOIL gms 1758.0 1833.0 1908.0 1923.0 1904.0
WET DENSITY gm/cc 1.884 1.964 2.044 2.061 2.040
~'
MAX. DRY DENSITY gm/cc: 1.93 ~~
1.92
OPT. MOISTURE CONTENT % : 6.06
/ \
\
::i
E 1.90
/ ~
Remarks: Method "A" is used
(J)
i'::
UJ
II \
z
~ 1.88
/
1.86
II \
Checked By/Reviewed By: / ~
Saeed Akhtar
1.84 '------
2 3 4 5 6 7 8 9 10 11
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
F- YNB-PHY-50IL-03-04
t:.t.;.. l.;../U I" ~~ c/~) I ~
':::':":::=-=..:.:::.:.:!:::2.1~==~ RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. (10)( 302"11. YlU'lbu AJ.Slt~;lyah.; MYA~ 51000~ KSA ·l£!)~ptlone: +966 (.1 It) 3250992-/3250993 f;.lx: +966 (14) 32S0946 Ernllll: r8'~Y.k1nbu@erre:~nS(JeflC.e!",Com
l(K,aOQn~ .N~Na.w;mi}nd -Stf~lIl't. Hvl AI-Milh.m Ohtrkt". R,c•• Yvobu At-S1n.. ly.Jh
TRIAL NO. 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 6011 6078 6165 6175 6165
WEIGHT OF WET SOIL gms 1849.0 1916.0 2003.0 2013.0 2003.0
WET DENSITY gm/cc 1.981 2.053 2.146 2.157 2.146
CAN NO. A-4 A-5 F-5 A-10 A-5
WT. SOIL + CAN (WET) gms 418.66 422.55 453.20 438.70 438.66
WT. SOIL + CAN (DRY) gms 410.56 408.66 429.66 408.36 401.55
WT. OF WATER gms 8.10 13.89 23.54 30.34 37.11
WT. OF CAN gms 40.32 38.55 39.65 42.15 40.85
WT. OF DRY SOIL gms 370.2 370.1 390.0 366.2 360.7
WATER CONTENT % 2.19 3.75 6.04 8.28 10.29
DRY DENSITY gm/cc 1.94 1.98 2.02 1.99 1.95
2.04
2.03
MAX. DRY DENSITY gm/cc: 2.02 ....
2.02 /' ~
OPT. MOISTURE CONTENT %: 6.04
2.01
/ \
U
u 2.00
/ \
\
E
Ol 1.99 - / \ f------
Remarks: Method UK is used
>
t::
\
r
if) j
z 1.98
w
0
\
> 1.97
0::
0
1.96 1/ 1\
Tested by: JAMSHID ALI 1.95 / \
Checked By/Reviewed By:
1.94 /
10/
\$>
Saeed Akhtar
1.93
2 3 4 5 6 7 8 9 10 11
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
IRr,F- YNR - PHY ·501 L·03·04
~~.CL-~{;.}J~~J.l;-.)I~
::::..::::..:.:..:.::::'~=====~ RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. [lox 302111 Yaobu AJ",Sln;l'1;;}hl MYAS Sl000~ KS).\ T~h:'ph01)t'~ -f966 (14) 32S0992/.325~)93 r~)(! °'"966 {14} 3250946 El'I)"31J: tg,,,,y;::,nbu"@~tI8eOM:~J~n«!s.com
loc.<IUCtfn .A1-NlJw;.Hltlnd S1rC~1.., !-fiJl A}-Mo:Ihan DbMitt f R.C" Y30bu AI-Sln-.."ly.ah
-" '"!i-;".',ifZ~;nq·{,,.}:,-Jh.M';:. ,tiffi:;i:<t.:im'lh"~*l:iI,Qo"'~%~""''''';X'*~''?fi>..{~i<>''''
TRIAL NO. 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 5965 6035 6122 6125 6122
WEIGHT OF WET SOIL gms 1803.0 1873.0 1960.0 1963.0 1960.0
WET DENSITY gm/cc 1. 932 2.007 2.100 2.103 2.100
CAN NO. A-10 6-10 P-10 P-10 6-2
WT. SOIL + CAN (WET) gms 421.99 433.62 444.60 435.26 438.99
WT. SOIL + CAN (DRY) gms 410.78 416.57 418.36 402.55 398.90
WT.OFWATER gms 11.21 17.05 26.24 32.71 40.09
WT. OF CAN gms 41.55 41.30 39.55 42.88 43.25
WT. OF DRY SOIL gms 369.2 375.3 378.8 359.7 355.7
WATER CONTENT % 3.04 4.54 6.93 9.09 11.27
DRY DENSITY gm/cc 1.88 1.92 1.96 1.93 1.89
2.00
'"
~
u
u
>
1.94 / 1\\
Remarks: Method "'A"' is used I-
iii
z
w 1.92
j \
0
>
0::
0
1.90
I \
~~
Tested by: M.TUFAIL
Checked By/Reviewed By:
1.88
/
Saeed Akhtar
1.86
2 3 4 5 6 7 8 9 10 11 12
MOISTURE CONTENT %
App roved By:
Awais Nisar Yasin
-c...-L..-~(f/.!' i f l.:?...J I ~
RIVADH GEOTECHNIOUE & FOUNDATIONS CO.
P.O. noX 30271... V::tnbu .r.I.Sfh;'lyah~ M"'A..~ S1iO()()~ KSA Tele-.phonel ·.966 (:14) a2.s.&<)<)2':.I3;;l'SO"~lc'''3 :~~S()j}"6
f'>3.lr<! d)S6 (14) J:rn:Jll! 'e'~y~l.nb.jl(pe .. lg",o'll:;:~n.!;ot!"1;.~(:>rn
t.oc,.."JOt'lo: AI·Nii_..n.otnd -5lT~t'I~ ttaJ AI.M.,.h<ul t~b~,kt. J:(,C,. y<,r"hu AI·~h~.,ly"h
~:-~:-~-'Ai:~~
21J4037
CLIENT: ~N~E~O~M~.~_ _ _ _ _-:-:--===-:=~~~_ PROJECT NO.:
PROJECT: Neom desalination plant to gayal transmisssion system.{LD-01) DATE SAMPLED: 24.01.2022
SAMPLE SOURCE: TP NO -01 Depth: 0.60m DATE RECEIVED: 31.01.2022
DAMI'Lt. DESCRIPYION: Brown poorly graded SAND.
DETERMINATION No. 2 3
I
BOTTLE No. A-I B-2
RGF·Ylm-PHY -SOIL-10-04
01.08.2021 Copy Rights Reserved By RGF
-c:.:..-l.:-~(; I~ :: _~ + ~;.;y t-/ I..:?..,J f ~
RIVADH GEOTECHNIQUE & FOUNDATIONS CO.
Neom desalination plant to gayal transmisssion system. (LD-01) DATE SAMPLED: 25.01.2022
TP NO -03 Depth: 0.60m DATE RECEIVED: 31.01.2022
I:>AMi"'L"'- DESCRIPYION: Brown silty SAND.
• CONDo TEMP: 23.6°C HUMIDITY: _ _ _35%
_ _ __ SAMPLE NO.: 8-1
DETERMINATION No. 1 2 3
G T x H'.';
Gs AVERAGE SPECIFIC GRAVITY (G s) : 2.685
w.\.+ W. - W 2
... -.'---.-.-~.----------
RGF ·YNB·PHY·SOIL·10·04
01.08.2021 Copy Rights Reserved By RGF
A i f0..) , ~
f·.t.~
f
Do.x:ilOlt7j,,,
An ERICom"""y
Y'.~nbuAhsin.;lyah,. MVA.,"J; S'1{){)c'). f($A
-c.."L-l.;:.--(JI-' ::
RIYADH GEOTECHNIOUE
T('I~phl';ll\('l1 "~9().G {t<'l) :;\:I'509'!):I' I :l'2sorr.':~3
to +.:7
Foltx! ;!)fi6 (14) :l25l)!)'Hi
;'~OUN~ATIONS CO.
r4'Y\~'H: 'tl''''i;1tnt>ul%9-... r~a'''~'(>n£oe'\,(',.".".
lUfflil\lont Al·N,:,.wantll'~d ~U(ltJl., II~\I A~·MliIOh"l) i)!lot.. kt. R.(;" Y3nbu Al·t.'1f'':'~y4h
PROJECT: Neom desalination plant to gayal transmisssion system.(LD-01) DATE SAMPLED: 27.01.2022
SAMPLE SOURCE: TP NO -05 Depth: 0.50m DATE RECEIVED: 31.01.2022
SAMPLE DESCRIPYION: Brown poorly graded SAND.
ENVT. CONDo TEMP: 23.9°C HUMIDITY: _ _ _36%
_ _ __ SAMPLE NO.: 5-2
NATION No. 1 2 3
W1 358.9 356.7
I
T 25.0 24.0
B-3 A-2
W 53.60 54.30
Gs 2.659 2.668
REMARKS: Method
... ..
~ ..~
B is Used
~- ....-"-.-- ....
~.~~.-- -~.- .... ,,.~-- ..... ~.~--. -~.-~.~ .. ~~.~~. ----.. ........- .... ~-.
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-01) DATE SAMPLED: 24101/2022
-------1
SAMPLE SOURCE: TP: 01 DEPTH: 0.60m DATE RECEIVED: 31/01/2022
-------
SAMPLE DESCRIPTION: Brown poorly graded SAND. SAMPLE NO.:
SAMPLED BY: RGF
-----------------------
ENVT. CONDo TEMP. 24.5°C HUMIDITY: 35%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
4S0
m
Ql
100 /
SO
;/ AT 0.1"
0
1/
0.0 0.1 0.2 0.3 0.4 O.S
Penetration (in)
0.5000 135 I 410
Remarks: C.MDD = 1.92 g/cc CBR @ 90 % Compaction at 0.1" 13
C.OMC = 6.12 % CBR @ 90 % Compaction at 0.2" 15
TESTED BY: M.IRFAN CHECKED BY/REVIEWED BY: Saeed Akhtar
CfJR·2
700
100 ./ AT 0,1"
o V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
CBR@ 95 % 18
6.12 CBR @ 95 % Compaction at 0.2" 21
TESTED BY: M.IRFAN CHECKED BY/REVIEWED BY: Saeed Akhtar
---------------------
RGF· YNB·PHY·SOIL ·05·04
01.08,2021 APPROVED BY: c~~l,(~(1,(je}f1'j,(it6F
f l~m v~~· ~~H~~~~~;NI;;::t:~~~
~~~-
(iD~
~f
Eftl
An Compony .;;.;;;::;;;;.':".;;;'Mb;;;
p~ o. UoQx ]0271. Y.I:mbU NS!ni.\lye-fl..M,A,YAS,SJ,OOO~' NOOI<t. T~. ~. +9~r,.-H-.125Q9'92fJ. Fa=< "l{I, +9"i;-J.4-31SI)'?J-<1~~, s.~~rTl1.'l11: '\:Jf-Ylml:".I-@~IOIXI.I{:I:~-t',fX"J.rorn
.~!Qn: AJ.!'.t~lh~nd S1:r~ l-\nil AI,Milh;:lfl D~trk;t;. UP J\rC'.<1 R,C Yoo.hu Al·~oaly"h K:SA., Ce-rtIDn:te N.o.r jC ~:r.u:4
PROJECT: Neom desalination plant to gayal transmisssion system. (LO-O 1) DATE SAMPLED:
--------1
SAMPLE SOURCE: M-TP: 1 DEPTH: 0.60m DATE RECEIVED: 31/01/2022
SAMPLE DESCRIPTION: Brown poorly graded SAND. SAMPLE NO.: B-1
SAMPLED BY: RGF
ENVT. CONDo TEMP. 24.5°C HUMIDITY: 35%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
Mould No.: K·3 Weight: 6365 gms. Volume: 2109 ee
--------
>
(j)
.2
co 400
/
OJ
c
·c 300
/ 'T no"
co
(j)
/
/
ro 200
100 / AT n "
0 V I
.~ .. ',j-r~/
f v" . "I
---"1ft'Il,.,...'l:-VV ~~~~V\.....-'/I;;J.....--
An~~1 ~~:'Y1~JiJJ RIYADH GEOTECHNIQUe '& ~ OUN';AT10NS CO.
_I< 11 '/
P. Q. Dolt-30271. YMbu p.J ~'ah. MAVAS 51000 S&VdJ NW1i:J, Tet. N». ---g&&·14<;t2smUJ, rex 1;.0., +?/,,A;·14·;.tl.50:9>1t;, E·frulInof·y,t>(;'bI),,?e<1o;t?oStl!!t)~«lrll
.. :Li-..pK~")fl; ,~H~.".voo-d $!to:-t. ~ i.H1il~'i bhttt,1ct:. UP A?('£< ~"c V~J AI·~{I!~ !($A. r;e~Ho.:'fC.a1U
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
CLIENT NEOM . .. PROJECT NO: 21J4037
PROJ ECT: Neom desalination plant to gayal transm;sss;on system. (LD-01) DATE SAMPLED: 24/0112022
SAMPLE SOURCE: TP: 1 DEPTH: 0.60m DATE RECEIVED: 31/01/2022
SAMPLE DESCRIPTION: Brown poorly graded SAND. SAMPLE NO.: 8-1
ENVT. CONDo TEMP. 24.S0C HUMADITY: 35%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
1.90
..
L
1.85
V
/ PENETRATION AT:
24
1.75
/
/ CBR at 90% of MDD: 13
TEST REPORT
..
C.B.R. - DENSITY RELATIONSHIP
CLIENT NEOM . PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gaya{ transmisssion system. (LD-O 1) DATE SAMPLED: 24/0112022
SAMPLE SOURCE: TP: 1 DEPTH: 0.60m DATE RECEIVED: 31/0112022
SAMPLE DESCRIPTION: Brown poorly graded SAND. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 24.5 QC HUMADITY: 35%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
1.90
PENETRATION AT: 0.2"
1.75
RGF· YNB-PHY-SOIL-05-04
01.08.2021 Copy Rights Reserved By RGF
Gl::-l.;./(JI, ~~ ify.)l~
An EBI ~J)iuly RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
,.~o. il~ ~;Z,~,Y"l'lw'At~i1;,h~ M'lAS,$1bOO. io;5J\ 1f:~Ph~; t!)tjfj {-14} :j)2~ll a2~~ ,fjJlI: +-;fi!; (loll :nsrnM6 (ID-311: ret<YiMbu€P'e.16c~tMt:;6,OOIl'l
1(){~lk>\'lo1Al,NaW,l"fJlld :SU~i';t~ tfaIAJ<M.lh;Jft
Pf).ukt" iq;..., Y~Hibt.i N~i';~h
C8R·1
600
tl.IA
Penitration Bearing Bearing
in value Ratio 500 ----'
(lb/in LI ~
(Cor.CBR)
---t ;9 400 /
OJ
:::;
;;;
>
300
V
/
O'l
c:
.;: 200 / liT n 7"
I':l
OJ
CIl /
100 / AT 0.1"
0 V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
0.5000 174 528
Remarks:
RGF· YNB·PHY·SOIL·05·04
01.08.2021 APPROVED BY: C~Qshifflalie}fa~ili,F
~~Gl.::rL:/UI,:.~ ·;:;.0'ifl:?)'~
==-=::.:!:=!...!~~~ RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P~o. 80)4" ::W11.1~ YltllUlJ At~SJn;rVj}h~ MYA~ $1000. J<SA tel~n(!o:. -t96O (lit) 3210'-;92 I 32SO<YJJ (;Jl(: ~966 (14) )2$0946 (man: tllr<y~nbuWeTlseMcte-oc:c:\,wm
loc..;lUnn: At.N.1W.lnarul <f!@'L HOli hJ-.M::&.h~n [)I-!;Irk-~. R.C. Yanlm .1H.S1n..'lwah
C8R-2
PROJECT: Neom desalination plant to !layal transmisssion system. (LD-01) DATE SAMPLED:
--------1
SAMPLE SOURCE: TP: 2 DEPTH: 0.60 m DATE RECEIVED: 31/01/2022
SAMPLE DESCRIPTION: Brown poorly graded SAND with silt SAMPLE NO.: B-1
SAMPLED BY: RGF
-------------------
ENVT. CONDo TEMP. 73_3°C HUMIDITY: 35%
-------- ---
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
Mould No: M-7 Weight: 6385 gms. Volume: 2108 cc
/ AT 0.1"
l/ - -
(ER-J
1000
Peni I Load Bearing Bearing 900
value Ratio
800 /
(lb/inL' (Cor.CBR) N
V
c
:a 700 /
600
/
/
<!)
::J
500
>'" ,.-/
0)
400 /' .T 0"
c
.;:
'"
<!) 300
/
[0 V
200 / AT n 1"
100 /
0 V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
TEST REPORT
C.B.R. M
DENSITY RELATIONSHIP
CLIENT NEOM . .. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-01) DATE SAMPLED: 24/01/2022
SAMPLE SOURCE: TP: 2 DEPTH: 0.60 m DATE RECEIVED: 31/0112022
SAMPLE DESCRIPTION: Brown SAND with silt SAMPLE NO.: B-1
ENVT. CONDo TEMP. 23.3°C HUMADITY: 35%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
1.95
1.85
CBR at 95% of MOD: 21
1.75
RGF- YNB·PHY-SOll-05-04
01.08.2021 Copy Rights Reserved By RGF
(51) mCl:-~{jI, ~~jl:?/.'~
An EBI Oompan)' ~~~~~ RiyADH GEOTECHNIOUE& FOUNDATIONS CO.
P.O. ~ ~()21'. V.ulbu ~ ..:SJftbtyah~ MYM-S'lOOO. K$A Te-lrrpnGt)¢t ·+9QGl~t.t1) $r2S09',)~ 13(:S<>'<~j y~~~ -....$J6t;l (14) 1)lSrnJ4(j t'irun~ "'f.yi;l.:nbu@ut$~OKIt!'n-c'l:r$;.(om
. ,,«~\kttl~ AI·j.4...W"ft\ilOd _-stf~t,tt.. llaiJ'l ,M,tlh,,·o t)~wi~l.Y N.C,. 't~hbtj .N·$.if~ty,o).h
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
PROJECT:
------------------------------------------
Neom desalination plant to !Iayal transmisssion system.(LD-01) DATE SAMPLED: 24/01/2022
SAMPLE SOURCE: TP: 2 DEPTH: 0.60 m DATE RECEIVED: 31/01/2022
SAMPLE DESCRIPTION: Brown poorly graded SAND with silt SAMPLE NO.: 8-1
ENVT. CONDo TEMP. 23.3°C HUMADIl"Y: 35%
----------------
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
----------------
].95
PENETRATION AT: 0.2"
1.90
CBR at 100% of MDD: 30
1.85
CBR at 95% of MDD: 24
1.75
RGF- YNB-PHY-SOll-OS-04
01.08.2021 Copy Rights Reserved By RGF
I - .• ~IC~l;../UI,~~Lfy~l~
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P~O. box ').01.1.1, YMOO AI.$l"';'lyolh. WAS 51000. Yo,SA it'lrphQnt': -1-!l66 (l4) 3~5ro9~ Il~S09$)3 r'))(: ...,66 (14) 31509t.6 tm:,lI: 1·~J<y;;tnbu@'etl6(P1de-o(~,um'
l(){~\lOI'H AJ...tII;)W~Nt1-{I $U\l'trt.. ttillf AI-M~1Ufl OI}.I(k1.1U:;'4 Ytif~l>li
AJ-$ln;)'iy;m
CBR-/
DATE SAMPLED:
--------1
DATE RECEIVED: 31/0112021
I::>AMt'Lt. DESCRIPTION: Brown well graded SAND with silt & gravel. SAMPLE NO.:
SAMPLED BY: RGF
----------~~----------------------
700
/
OJ
t:
.;: AT 0.2"
ra 200
Ql
/
CIl
AT 0.1"
100
0 V
0.0 0.2 0.3
0.1 0.4 0.5
Penetration (in)
0.5000 206 626
Remarks: C.MDD= 2.06 g/cc CBR@90%Compactionat 0.1" 19
C.OMC = 5.35 % CBR @ 90 %Compaction at 0.2" 22
TESTED BY: WISAL KHAN CHECKED BY/REVIEWED BY: Sneed Akhtar
---------------------- ----------------------
RGF· YNB·PHY·SOIL·05·04
01.08.2021 APPROVED BY: c~jB.sN.iJi,alie'tfa~iw,F
[.~
....... . 1.:.A•.:.,A..:..'/U'-, ~r1' t./0.) I ~
~I V - iN· ...
AnERleompany ~,v.~' RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
til}. bow ~:l1l,,_V~nOO-M~SI~i1a-i\ MtAS .$1000, i\$A 'fe~; '+%6 (i4) '3';l~~ I ~lS0$9J fPll! 4iW (ld) :{j:l1'S094~ tmnli; 1Er,y~mbu@f!TI.6ctntle{}CJt"H()fTl
lfK'Atkm! M.N;wr.UUM ;slr8!cl~ ftii AJ..t.,bh;m Oh.bK:t. R_t:". Vanhu At~Jn.~tv..h
CiJR·2
1000
Penitration I Load Bearing Bearing 900
value Ratio
~
800
(Lbs.) (Ib/in') (Cor.CBR) ;:;
c: 700
~ 600
/
Q) v
::::J
m 500
/
>
Ol 400
V
c:
.;:
m 300
7 AT 0.2"
Q)
[!)
/
V
200
100 / AT 0.1"
a V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
c.OMe '"
TESTED BY: WISAL KHAN CHECKED BY/REVIEWED BY: Saeed Akhtar
RGF· YNI3·PHY·SOIL·05·04
01.08.2021 APPROVED BY: c~iisl}(i~g(jelfjJyiQ;F
Gl.:-l:..,/{J I, ~r.1 U'l:?.) I~
AnERlc~mpany RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
I>.(j. "0O)j':)'ol1.l~ Yanbu A1.ssn;iv;)~ "N'fAS 51000, ,",S",- If;'~ptwn(!'~ -+966 (14) lJ'l~.J2J3Zs()<J93 F,)'.(: ~goo (14) '1:i{)g';6 (maa: 'gf,y.)nbu@)mts-c-mdeot.(l1,(om
lCK'..::.Hon~ M.N~w.lnaoo Sirettt Hoii iIJ·M,1.h;Hl Ol~l·l~.ct, R.C, Y.anbu AJ-Struivah
(ER-3
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-01) DATE SAMPLED:
---------/
SAMPLE SOURCE: TP: 3 DEPTH: 1.00 m DATE RECEIVED: 31/01/2021
SAMPLE DESCRIPTION: Brown well graded SAND with silt & gravel. SAMPLE NO.: 8-2
SAMPLED BY: RGF
---------------------------
ENVT. CONDo TEMP. 23.6°C HUMIDITY: 36%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
Mould No.: (-6 Weight: 6345 gms. Volume: 2108 cc
1100
Bearing 1000
value Ratio 900 ........-'
(Lbs) I (lb/inL' (Cor.CBR) N
c: 800 ~
:0
700 ~
Q)
:J 600
/
>
ro
500
/
en ./,// AT 0.2"
.§ 400
ro
Q)
00 300 /
200
;/ AT 0.1"
100 /
0 /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
TEST REPORT
..
C.B.R. - DENSITY RELATIONSHIP
CLIENT NEOM . PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-01) DATE SAMPLED: 25/0112022
SAMPLE SOURCE: TP: 3 DEPTH: 1.00 m DATE RECEIVED: 31/0112021
SAMPLE DESCRIPTION: Brown well graded SAND with silt & gravel. SAMPLE NO.: 8-2
ENVT. CONDo TEMP. 23.6 D
( HUMADITY: 36%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
2.07
2.02
/
/ PENETRATION AT: 0.1"
19
1.87 K
/
TESTED BY: WISAL KHAN
1.82
14 18 22 26 30 34
Axis Title CHECKED BY/REVIEWED BY:
Saeed Akhtar
RGF- YN~-PHY·SOIL·05·04
01.08.2021 Copy Rights Reserved By RGF
•
C~l;;../U Jf) ~d J;'(.?.) f~
AnERI RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
p~o~ BO)( 30271.. Y.at'tOO AI.s~I\;ty~n., MYAS 51000.. KSA T~ph01W't 4~6n ('-') 32;i0992/ 326t)991} F..>J)i,: i-9ti6 {lii~ rll:SOO46 timliili reJ.y..rtb!J(petf~-cM.c~eru::eJr.oot'l'\
l(,)'.)HW'l~ A1·«,)wan~j\d Str{>~t.. Hul At,M~fh"(' Ohtti<t. R.C.~ Y':'nh'U AI,$~ft.;'i1y,ah
TEST REPORT
..
C.B.R. - DENSITY RELATIONSHIP
CLIENT NEOM . PROJECT NO: 21J4037
PROJECT: Neomdesalination plant togayal transmisssion system. (LD-01) DATE SAMPLED: 25/01/2022
SAMPLE SOURCE: TP: 3 DEPTH: 1.00 m DATE RECEIVED: 3110112021
SAMPLE DESCRIPTION: Brown well graded SAND with silt & gravel. SAMPLE NO.: B-2
ENVT. CONDo TEMP. 23.6°C HUMADITY: 36%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
2.07
PENETRATION AT: 0.2"
2.02
CBR at 100% of MDD: 34
1.97
CBR at 95% of MDD: 28
1.87
RGF- YNB-PHY-SOIL-05·04
01.08.2021 Copy Rights Reserveci By RGF
Cl:-l;./VI:J~~J'~~I~
:..::.:..:::=-=-.::.::::.::=:!...!~==~ RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.o.. 8(l)j 302:]1, Y~"bu A1'5.t~i.,~h~ MYM 51000, f<5A It:ltphl,)rrc: ...~6 (14) 3;l5ro9~ I :l:l~J fill(: +?66 (1<'1.) )250946 [m~1t: IBr''f.mhu@t.rrlscmdftDf)I;'<U(ln-l
l.()(itVQfH A!,N.:Jw,;u\l,Ifl41 S\f¢~tj' H.iJ1 A~-M;!h;ifl Oh-lil{1. R(." Y~f\b\.i Al·SlrlAiyah
CBR-I
600
B
c:
400
V
..--'
<Il
:J
L
V
<tI 300
>
OJ
~/
c:
.;: 200 / nn ?"
/
<tI
<Il
ro
100
./ AT 0.1"
IlJ
0
/
0.0 0_1 0.2 0.3 0.4 0.5
19 Penetration (in)
0.5000 158 480
Remarks: C.MDD = 1.93
C.OM( = 6.06
TESTED BY: M.IRFAN Saeed Akhtar
RGF- YNB-PHY-SOIL-OS-04
01.08_2021 APPROVED BY: c~/{silifflalie}f(J)iiro;F
-~ I ~ I ~ Ifq .. i.U .~- --y. ~I ~. 'I::r.::'"/'
·
~1t>
c .•.••
~
.........] ' / ' . .
CBR·2
PROJECT: Neom desalination plant to gayat transmisssion system. (LD-O 1) DATE SAMPLED:
--------1
SAMPLE SOURCE; TP: 4 DEPTH: 0.60 m DATE RECEIVED: 31/0112022
SAMPLE DESCRIPTION: _B_ro_w_n....:.•. _...::.....:=--____________
SAND with silt SAMPLE NO.: B-1
SAMPLED BY: RGF
------------------
ENVT. CONDo TEMP. 23.8°C HUMIDITY: 35%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
Mould No: B-8 Weight: 6395 gms. Volume: 2110 cc
900
Penitration
value
(Ib/in') ''Q Ratio
(Cor.CBR) N
~
c:
800
700
600 ~
~
~
::::.
OJ 500
/
::l
(ij
> 400
Ol Ir'/
c: /
'0:: 300
AT 0.2"
/
OJ
OJ
aJ
200
100
/ AT 0.1"
0 V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
RGF· YNB·PHY·SOIL·05·0~
01.08.2021 APPROVED BY: com{tl,(~~ve~~JYit6F
Cl::A..;/tJl,:~ ·":;~j4?.)I~
I'\fl"""""" ...omp""y I "''''''' ~RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
f.',O~ $~ )Oi11~ «Mbu Al"Sln;tyah. M-yAS !i.1.QQO. ;';SA f(!l(o~~:'%<I. (i4) il;l~2/3:i~J f:;~: 4-90,.0 (14) ~i509J;,6 £m~lj: 19J'V")rlbU~(le~~~,«lm
L6t'4U()81ALN..1w.U'tallti ~tu'!t1It" hid AI,tJj:lh:m ()[\!rkt, Rr.." Y3j~hiJAt~Sltulvah
CBR·3
1000
Peni Load Bearing
value ~"~ Ratio
900
800
~
(Lbs) (Ib/in" (Cor.CBR)
(in) C
~ 700
::::.
Q)
600 V
~
::J
<ii 500 /
>
en
t:
400 ~-.",
.;;:
/
ro'"
300
Q)
V
../ AT 01"
200
100 /'
0 V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
PROJECT:
-----------------------------
Neam desalination plant to gayal transmisssion system. (LO·01) DATE SAMPLED:
--------
26/0112022
SAMPLE SOURCE: TP: 4 DEPTH: 0.60m DATE RECEIVED: 31/0112022
SAMPLE DESCRIPTION: Brown poorly graded SAND with silt SAMPLE NO.: 8-'
ENVT. CONDo TEMP. 23.8°C HUMADITY: 35%
------
DATE STARTED: 04·02·22 DATE COMPLETED: 08-02-22
1.90
PENETRATION AT; 0.1"
1.75 I b"
RGF· YN[l-PHY·SOIL·OS·04
01.08,2021 Copy Rigil ts Reserved By RGF
Cl;..A_::,./V/~;-:~ ·~&J'L.?~f~
A"ERleom.,.... y RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
p~o~ 3i))( ao;rn:~ "f;:$nW .M.$l~i'l;ln., MV)\$: 51.000.. KSA TcJepni)1\«-! ~,960 (14) 3~50992/ 315(')993 f3~1 +f):66{lA) ))250946 E,n;;,H ¥'.et"yM)bU4Pt-tt.s~O\CJt:f'I'~t:~.-c:.om
lo<:.ithmt Ai·NMV,;llY.10d $tt~t.:1,. u..)l AJ,M.;)h~m Pf5.trkt. .fl,¢:"" ¥.anb\t M,Slf\41y.:.h
TEST REPORT
..
C.B.R. - DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. (W-01) DATE SAMPLED: 26/0112022
SAMPLE SOURCE: TP: 4 DEPTH: 0.60 m DATE RECEIVED: 31/0112022
SAMPLE DESCRIPTION: Brown poorly graded SAND with silt SAMPLE NO.: B-1
ENVT. CONDo TEMP. 23.8°C HUMADITY: 35%
DATE STARTED: 04·02-22 DATE COMPLETED: 08-02-22
1.90
PENETRATION AT: 0.2"
1.75
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-01) DATE SAMPLED:
--------/
E SOURCE; TP: 05 DEPTH: 1.00 m DATE RECEIVED: 31/0112021
::-:-:--=-----
SAMPLE DESCRIPTION: Light Brown Silty SAND. SAMPLE NO.:
SAMPLED BY: RGF
ENVT. CONDo TEMP.
-----------------------------------
HUMIDITY: 36%
---------=--,:-.,.
DATE STARTED: 04-02-22 IJATE COMPLETED: 08-02-22
600
Bearing
in value Ratio 500 /"
(Ib/in"' (Cor.CBR)
N'
r: V
:a 400
/'
/
<ll
:::l
ro
>
300
/
/
Cl
r:
<;:: 200 / 'T n?"
C\l
<ll
CO ./
100 / AT 0.1"
0
/
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
RGF- YNB-PHY-SOIl-05·0-l
01.08.2021 APPROVED BY: c~jltshl.it;,alie'tf(J~ilIIJF
~~I.:"".;A..;/(JI,:~ ·J&if~)I~
AnERleornpnn!l RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P,O. box )Qi~'-l. Y.l~bu Al.SI,,;TYi.lh. MYAS 5"1000. ",SA 'Tt!~m-~:'966 (14) :i2:s.o9il2 /:ll~) f~x:.~ (~4) ,zS0946 (maU: tgr'Y·imbu€))crigcoscte-nc.('1...wm
tl'll"A_.~Jl: Al.-N.lw~nand 5ir.i!d~ HItl At.M"h:m {)lJ.ITf.c:t~ n.c
4 , Yanhu Al...~tlUivah
800
Penitration Bearing
700
~
value Ratio
L
(Lbs.) (lb/in )
(Cor.CBR) N' 600
.~
:c 500 /
Q)
::J
i; 400
V
/
>
01
c
.;: 300 /
ca
Q)
10 200 / AT 0.2"
100 ./ AT 0.1"
o V I
CBR-3
1100
B"~~
1000
value Ratio 900
(in) (Lbs) I (Ib/in·' (Cor.CBR) N
t: 800 ~
;g v
700 ~
Q)
/ V
:::l 600
>
ro
500 /
m
t:
.;: 400 / AT 0.2"
ro
Q)
CO
300 /
200
,/ AT 0.1"
100 /
0 V -
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
2.03
1.83
RGF· YNI3-PHY-SOIL-05-04
01.08,2021 Copy Rights Reserved By RGF
Cl:-~()I,~&ifv~f~
An ERI ComPllny RIYADH GEOT€CHNIQUE &. FOUNDATIONS CO~
p.o. fio:lt aO;rll~ Ya:f:I't)1.;i AMit~t'{~:h" MVAS 510<>0.. K$A 1'~tt!'phonC'! 1'96& (:[4) :;J'2:~21 ~2~3 r~3(; ~~ (14) .!\2S(H;>16 fZm~n! x3tJy..nl:n;~e,.t6e:M.t:Jlrnt~I.()it'
lo(oitton: AJ·NOlw~n"ftd.tfl:'<:\. H~~ J\t~h;')fi O~ttkt# R..e·,# V~tl\:(tt At·iln.dY1Jfl
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
CLIENT NEOM. .. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. {LD-O 1) DATE SAMPLED: 27/0112022
SAMPLE SOURCE: TP: 5 DEPTH: 1.00m DATE RECEIVED: 31/01/2021
SAMPLE DESCRIPTION: Light Brown Silty SAND. SAMPLE NO.:
ENVT. CONDo TEMP. 23.6°C HUMADITY: 36%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
2.03
1.98
/' PENETRA TION AT: 0.2"
1.93
/ CBR at 100% of MDD:
/ ..... 24
RGF· YNB·PHY-50IL·OS-04
01.08.2021 Copy Rights Reserveci By RGF
.---:::-:-~t:A.;",l;./U f, ~,0' ifY~ IV'
.:.::.:..::::.::.:.:.~~~==~ RIYADH GEOTECHNIOUE & fOUNDATIONS CO.
P...o . l}Q)f 30111~ Y~olw Al.SJfi~'i'Y;';h.. MYAS 5:l0¢0~ r"SA 1.el!fi:lhon(!o~ :'!k>6 (lfl)3:2!'r099l/1J:~~) fi.'lltt "Sun-(14)3%509.tf) (tO~iJ: IRI·y;aonbtt~~ts:*~dlr~((}nl
t,()(~l~Q1H #-N.J:waNM "$tffti,rt" tim A!'M;.ttt'ft OlMrk:\~ 1(:,(... 'f31ltw Al~S!rt;!i.'tJ'h- CBR-I
PROJECT: Neom desalination plant to !Sayal transmisssion system. (LD-01) DATE SAMPLED: 29/0112022
---------1
SAMPLE SOURCE; TP: 06 DEPTH: 0.60 m DATE RECEIVED: 31/0112021
=---:--:---:-:---
SAMPLE DESCRIPTION: Brown well graded SAND with silt. SAMPLE NO.:
SAMPLED BY: RGF
----------~--------------------
ENVT. CONDo TEMP. HUMIDITY: 35%
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
600
Ratio 500
~ 400
V
<I>
::s
iii 300 /
/
>
OJ
c
',: 200 /
V AT n 2"
/
rt!
<I>
OJ
100 / AT 0.1"
0
0.0
/ 0.1 0.2 0.3 0.4 0.5
Penetration (in)
0.5000 162 492
Remarks: C.MDD" 1.96
6.93
TESTED BY: JAMSHID ALI CHECKED BY/REVIEWED BY: "aeed Akhtar
------~--~~~------
RGF- YNB-PHY-SOIL-05-04
01.08. Z021 APPROVED BY: C~f{sIlI.ffl,alie}fU~iw,F
CA..:",~(j(, ~~j,-:?~I~
AnERt RIYADH GEOTECHNIQUe & FOUNDATIONS CO.
P.O. OO)f ){)~1t" Y;lnbu At.st";iyilif\ M'(AS $UX1O. kSA ·nu.·phtme! <t~ (14) ~l~~' 1\l~1l f'ilX'! *~ (M) }j~!rt?!f40 t:ffi41l: tgt,V~t1bu@eT1S-(i<m:tlN){J"u'tJm
lnc.Aiktn! At.Nawarumd ghr"t~ Hid ~Miih;m Oktrkt. tt.r.. , vanuh AJ,.5ImwIlh
CBR·2
PROJECT: Neom desalination plant to gayal transmisssion system. (LO-01) DATE SAMPLED:
--------1
SAMPLE SOURCE: TP: 6 DEPTH: 0.60 m DATE RECEIVED: 31/0112021
SAMPLE DESCRIPTION: Brown well graded SAND with silt. SAMPLE NO.: B-1
SAMPLED BY: RGF
ENVT. CONDo TEMP.
- - - -71.9°C
- - - - - - - HUMIDITY:
- - - - -35%
--
--------
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
Mould No: M-5 Weight: 6385 Volume: 2104 cc
800
100
/ AT 0.1"
o V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
CBR @ 95 % 19
CBR @ 95 % Compaction at 0.2" n
TESTED BY: JAMSHID ALI CHECKED BY/REVIEWED BY: Saeed Akhtar
RGF· YNB·PHY·SOIL·OS·04
01.08.2021 APPROVED BY: C~ftsf)(~~(ieYl~yit?,F
~~ v '1.:,A.;...-l;;.,/(tf, ~& J' ~) J ~
No Eftl 'tt.~~. -
V.A>
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
~jj.l)Qx ll»):f.t, V.'"mw AI,Sln.1ly;)f1, M'IM-!1.000.. lCSA -lclc-phonel.%(S (u)a~~21;,ll500~i3 u:.:: ..~ (iii) ;l:tSOt1116 tm3li~ fgl.yilnbu4l'tflgf;'!-m.d('"ncAM,oom
lnc'~ifnn: A!.N.:JwJlfi1Jrnl-~tr~t~ Hiil A"'M.dun ().kitlri~ n t;" Y:al1hh Ak~tnawJh
CBR-3
• "U"'~ _~.,~.
1000
Peni Load Bearing Bearing 900
value Ratio
800
.. .. ./
(Ib/in"' (Cor .CBR) N
c::
700
v--
<l)
600 ~
::J
>
~ 500 /
/'
V
OJ
c:: 4QO 1'-0-.""
'i:
~
<l) 300 /
CO V
200 / LlTn 1"
100 /
0
/
0.0 0,1 0.2 0.3 0.4 0.5
Penetration (in)
c('
Remarks: ~-~.. ~.. ~~~~~~~-------;,~~~~~~~~~~--~o_---------
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT . NEOM. PROJECT NO: 21J4037
------------------------------------------ ----
PROJECT: Neom desalination plant to goyal transmisssion system. (LD-01) DATE SAMPLED: 2910112022
SAMPLE SOURCE: TP: 6 DEPTH: 0.60 m DATE RECEIVED: 31/0112021
SAMPLE DESCRIPTION: Brown well graded SAND with silt. SAMPLE NO.:
ENVT. CONDo TEMP. 23_9°C HUMADITY: 35%
---------
DATE STARTED: 04-02-22 DATE COMPLETED: 08-02-22
1.79
RGF- YNB-PHY-SOIL-05-04
01.08_2021 Copy Rights Reserved By RGF
c~~ ~J CL:..-l.;::../UI!J~~t./V.)I~
~M) V" '.""... ....
EO i!! 00"'1>"11),
I "'A$
An· ~.~~. "'_
..•_ RIYADH GEQTECHNIQUE & FOUNDATIONS CO.
').0. !!QX30:t7.1, ViJl'ibO At>$,ln.;lYillh" MVAS 51D()()# KSA 'T~te-phOM'! 'f9()~ (14) 3il?OO92./-3::l-~93 f3li;1 +M6 (14-l :;U~OO46 t;m~IH ,,,f~y;'tt"'bu@etf.seOKit:'nt~,(om
l.fX.",j-tfpn1 Ai·N..l\V;lf\·"~ Stf'ot.et.= H~I AU";')h;):o .t>h.ttkti 'A.,.('t V.)fibu AI-"Slft~Jy,)h
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO; 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-01) DATE SAMPLED: 29/0112022
SAMPLE SOURCE; TP: 6 DEPTH: 0.60m DATE RECEIVED: 31/0112021
SAMPLE DESCRIPTION: Brown well graded SAND with silt. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 23.9"C HUMADITY: 35%
----------------
DATE STARTED: 04·02·22 DATE COMPLETED: 08-02-22
----------------
1.99
PENETRATION AT: 0.2"
1.94
CBR at 100% of MOD: 29
1.89
CBR at 95% of MDD: 22
1.79
RGF· YNB·PHY·SOIL·05·04
01.08.2021 Copy Rights Reservecl By RGF
Moisture Content, Particle Size Distribution,
Atterberg Limits, Proctor Test and CBR Test
LAYDOWN No. 3
SAMPLE NO:
RGF-YNB-PHY-SOIL-1S-02
01082021 Copy Right Resrved by RGF
RIVADH GEOTECHNIClUE & FOUNDATIONS CO_
P.O. DO)c 30....7:1. Ylllnb-u AI,...sh~;lY::'h. MYAS 5::1.000.. KSA TI:~+e'pho.ne-! +9C>6 (:14) 32".5-0992/3250993 f';:).x~ +95(114) 3250946 Ern,,1;:: r.R'-'YahbtJ@I"i!tlB.<e~i.d:-enc::.e •.com
"(.><:.alk>n~. .l'LS-Na.......~'ni<\f\d Stl-.r.O(~t~ H<.ll At-M<lh<l"o fJh:lr-Ic.t:. R,C.• Vo3Inbu A1-Sfn..;lOlV... h
PROJECT
SAMPLE NO:
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
'C..-L:-L::.---U IJ' ~~ if~-' I ~
RIYADH GEOTECHNIClUE & FOUNDATIONS CO.
i">~O. uo~ 30.27:1.~ YtH\'bu At.s'n~lY;;'h~ MYA..."i 51000., tCSA TI;t.:t"'ilht)~;; +-9<66 (:1'1) a;;rS-Q9!):;t /37s.ota93 I"~)(~ +96'& ('5.4) 212509'46 trrf\x.Uc. r-9'..yat1lbu&etig"o~I<ftV)IC:,.t<l:l'.C:()M
l<K1ilItJoo: Al~Nw"",a"i\f'H. St"IW<"t~ U",., Al-Mahlan rJt-lotor-lct. it.C'•• Y>an'b\~ M~Sin.».y.,h
SAMPLE NO:
RGF-YNB-PHY-SOIL-1 5-02
01.08.2021 Copy Right Resrved by RGF
'::::::"=-==-==~=~~!6d RIVADH GEOTECHNIOUE & FDUNDATIDNS CD.
p~o. nOlo$ ,'lO.2:7:1. Yantx.t AJ",,<;b~;'lYll:fh~ MYAS ,5:1000.. KY.A 'l't:I>JephOl'¥e-: +-!>COG (:t~) 32'5Oi)92/ 32S.o!)93 li'h)(: .. 9Ga. (lA) a2S0UJlG En1I:lI1I:: oI'R'''Yanl.-.u@lt':tf9.(!:c..i.Ci~n€.oe»..C:.olY\
.. tJ()rit. At.N=tI.'V;;)I"IIi.)nd
"'()C~ $'l"'''~':'t~ J-bl,1\~ M ..han f.,lht.1G't. R,(.'~,. V""n"tn.t A1"~fn~~1 .......h
NO:
K-7
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
P.O. UO>l.30.2.7:1. Vl:'ldf)bu AJ.SiA';lY:i:ioll. tvJVA...... 5.1000.. KSA T~~~phOr.t!!: +966 (:14) 32s.D"-J92 I 9250"",)93 F;:).x: +9G6 C14) 32$09"6 £n'\nH::.l"d'...y.anbu@efla.<eo:\.Che:r.u::;oe:.... COn'll
Loc..atk>o:. .A)~N.;wWO\I"II~ru. 5u·...,.(I:1". tial A)-" ..",,,h,,,,·n r.)h.I.¥""i:£;"t, R,C. .• ""t.u·.l.,u .A~-Sh ....... l"'iJh
LLE DESCRIPTION : Greyish Brown well graded SAND with clay &. gravel. Sample NO.: B-2
SAMPLE NO:
RGF·YNB·PHY·SOIL -15·02
01.08.2021 Copy Right Resrved by RGF
't.::-L--~(J/!,~~~~-'f~
RiVADH GEOTECHNIOUE & FOUNDATIONS CO.
P.O. UQ>C ~0.27::l.. ~"-&6bu N.Sf",';'ly~h. M¥AS 51000., KSI\ TI::.I.epht:>nel +!9-66 (:14) a:;;l,5U992 I B25Q99:iJ F-'II:l(; ,..966 (14) 9':l;:;':O'O'.II1:\. 'i?~Jt;I,," ·rufyy.",..tH,@I""'tl~~o~h~hC)e ••C:QM
\Q.O;.·OlOljQ";.AlI-N"'\VJiH~iiU·\(f S'lI'~Vt~ .,1; .., 1 At-.-Mllhi>n OtJitri{·.t.. it."";'. "V..-n'bQ A1-!"iln.dv.,h
SAMPLE NO:
RGF-YNB-PHY-S01L-15-02
01.08,2021 Copy Right Resrved by RGF
"C- L:-l..::.--V I., ,:: :: ~
•...:;.; Lf'-:;-'../ f ~
An lEft. Cornp.~an~y..b::=~ RIVADH GEOTECHNIClUe & FOUNDATIONS <::0.
!if r, u ....·.. ",HI ~ J1', ..,,.rtf\l! O,.·.~n."lvwl', ....1Ym,'{ ~ a no!\)" ~fi."\ TJflrl'l~ll.n1ff' t;;.nit-. ~Jj l a:;,f:rQIUII';;J: I ~I:I1 :f'Vlltlf;;' I·;;'}r.~ 4f>U•• , ~ I .11) ,I~~ 1~(H>Aa, if1h41'~ _·to"y,nj'I.:'I.IlJ:ll.t.t+n.~j~'~"'loI~rtiltl"" ,.,UtTI
lo<:.;t'k;>.o!. p,)-No)'YV.ilInand ~ln;;·lI;I.t. tLaI A __M<Jn;;i-H r)lt",Ui(;I', It>(~y. 'V.:)nJ;l\> N-~l","')~\f:!ll"
SAMPLE NO:
B-09
493.65
OF SAMPLE + CAN (DRY) (gms) 470.84
OF WATER (gms) 22.81
OF CAN (gms) 41.24
OF DRY SAMPLE (gms) 429.60
CONTENT (%) 5.31
RGF-YNB-PHY·SOIL·15-02
01.08.2021 Copy Right Resrved by RGF
.... o~ tio)c' 302:1:1. Vn"bu N.Sh:~4tYlll<h~ MYA-s 5:1000,. KSA Tf1.I~phopot'>: .<:I>G6 (:14) a'2,!rtH.l9:! I J,J:lSQ!iH,:a VI:tX: +9t).ol> (1.... ' ::J::!M1!!1.tf. t,l't\:!ilf~ ..AI....y.lloh~tg2~t'!3.,:N:>j..:;l-eI'li!.~A.<:o.m
-..'Ilt"""'Ol'll ;Al·N~·Wi;ln"'I'\(I Sj;a'lIt'o(/"t~ fl"'" A' M~hO)n ~... t'xb'h',l. H.-C,. V.anbu ~'f foll1."ly,~h
NO:
B-09
41.24
OF DRY SAMPLE (gms) 457.51
CONTENT (%) 2.57
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
~"ID ~ c...l..:::-~U I~ ::: :: ~~~ if ,-::?..-J I ~
An ERI Co",,,,,,,,, 1~..J:!:'.t\!l'.' v.~. RIYADH GEOTECHNIClUE & FOUNDATIONS CO.
v~o. au.. Jl027"~ ~"'l"'1bo At..sIO;lY>1-h. t....r'f~~ :s::.otx>.. K.SA Tejc-phone: +966 ('.l4) 3750'1,)92 I ~~i5Q!)1)3 FA)(! +s,oG6 (14) 32SOD<<'tG iim::.lh f'tf'...y,nnbo4Jtetf{\eos."Ch~:t'}1!:>e!:t..c:on'\
t..ot.w.".',nH~>n!. Al~N.;rw";<ln.;rn('ll5t'r."I'Yt. t<tul A~~M .. h~, ot~il,-t(;.-. n.c., 'V<ilAb\) Af-$lnJ)i'r';p,h
LE NO:
K-7
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
P.O. OO)! :10.2:7'~. V6fibti N,$fn;ly~h, "'''VAS 5'!1ooo", KSA Tc.~t<>f$h~t +'966 (14) 325-0992 I :325Q9;9:it F.':W:)(~ +966 (1.,;;1) 32:S09~6 £:rh;;aU! :r(l'''Y;)nbU@f'':tr.e.~o~ten"",e"",ebM
tr,x:",lfoo:. Al-Nit1l'Van:<H'HJ 5't:....:·... t. Hal AJ_M~hiH) f)t\tvk,t. R.<; •• vanhu Al-.$.fl-<lot ... .,h
NO:
AB-1
47.42
OF DRY SAMPLE (gms) 579.60
CONTENT (%) 1.35
RGF·YNB-PHY·SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
~An~E~R~I~~~~~~~;;;;J RIVADH GEOTECHNIClUE & FOUNDATIONS CO.
p~o, JloX :90271, vnrttHJ At~5fn;"tY~h. ""'·"VA.-"J. S:lOOO" KSA Tt>JlI.'phon,1!>! +966.(:1.4) 3:;n'..0!'"l92 /325QQ'!);a 1'1300)(: +966 (14) ;'j:'!509~.(i ~,t)1o)';l;1l~ ...... '·.y;u.bu(fi\>..t:tiiJ-tto~nc.oe"':.c_Qln
\<OoI'''''''fnor. "")·N~w"'rJI",nd ::5tn'l'v.'~ H;A& ,A)··M,lh,ll1i I')hi.,.ic,r. " ..!C., Y;.v\bu Af-Sh'>ll'IV:o;JIh
SAMPLE NO:
RGF-YNB- PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
r---==--_-., c..l.::-~U Ii' ~~ t./'L::?-' I ~
~An~E~R!!!I~~~~~~~;;;) RIVADH GEOTECHNIQUE & FOUNDATIONS CO_
P.O. Uo:>;: 302::7:(. 'Vnnbu AI...sfn;lYiilh. 1\..>IYAS S:::rOOO~ KSA T0hi»phane~ +9-66 (:14) 3:2"SOi!}!'):l1 325(5)9::.,. F~x: *9fi.6. U.4) 3:;t;SC!t4C> 1!i'1"fIo~;1~ #"Rf"YJ.Ulobu®.... tfe.~C>S:<:,,;e~.::eli-,c;bftt'>
"«:w:'•.n fOfH. ,.n.l·Nl);w.... n;1llnd ~-,;,I·'P.~T. H1oIo) AHr.....i:.:r.ho:ln r.lhlr-t<:,t, ftc,CT> \o'er.bu Ai-'Shl.<lly.. h
O
ENVT. COND TEMP 23.5 C HUMIDITY: 38%
Test Started Date 2310112022 Test Completed Date: 2410112022
F-5
RGF·YNB·PHY·SOIL·15·02
01.082021 Copy Right Resrved by RGF
P.O~ OO~ 3027:1., V:.\hbU At-filn;'tyah.1VtYA.,S S;lC)O()", KSA. .~1C'ph~:: +966 (:14) 32.~2 I 325<)9093 FAli: .9~ (:14) g2S0!J'46 Jrit1"\,dh ""8'...y.."t'lb1..'@~~fg.e-CJo.t..<:";l:encoe:f,.c.ptn
t.O<:?.. lfoo! .AJ-N_,;lo"".~nd :St9·~. *Ml Al~M#hl1J) r...bf.. 1i:'1:.~ R.<.. •• Y"'I'"tbU Ai-~"'n.<)f'i.. h
SAMPLE NO:
RGF-YNB-PHY-SOIL-1S-02
01.08.2021 Copy Right Resrved by RGF
-c:...L:-L::.--U I!, ~~ ~~~, ~
:",,,IERlc<>mP""Y RIVADH GEOTECHN10UE & FOUNDATIONS CO.
P.O. OoJot 3002_7:1. Vu.nbi.! N~JnblytJh. MVAS 5:1000.. KSA Te'~ph~: *,966 (:14' a2.s.0'99:,z / »:ZSO!:H):i) F{Iox~ .966 (14) :;12500<160 IF.,.n>>U.~ "'n'''V.anb~..iI!J>''''tlgttO~.ie,...e''''~A'''f>t'n
lo("·,;:nton~ ,I\,\-N;xW'.\oand S-tn~et'~ d-alAl·Milh.." Ohtrk.t, fc(; ... V ...nbu N-Slru\tV.:.h
PROJECT : Neom desalination plant to gayal transmisssion system.(LD·03) DATE SAMPLED: 18-01-2022
SOURCE: TP: 05 Depth: 1. 20m DATE RECEIVED: 22-01-2022
SAMPLLE DESCRIPTION : Greyish Brown poorly graded SAND with silt & gravel. Sample NO.: B-2
SAMPLE NO:
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
P~O. fh:>>( ;;)027:1. 'Y:ln;t;.u N'6fn.:bIY~h. "'''VAS S~H100~ t':SA TeJc-phuJ'l.e: +966 (:1,11.) 21:2:S<W~2 I !?l:::r5(Hi~9:;) 1-':11><: +966 C.14) 32~'!JI46 £'l'n31J;: 1-e:f.yantli.Un>C1rfBoeCo~le"c:.e •• ~OI'n
lQ£.";a,too;. .ni:-Ni'K.......~HUl~tj .5'tnllot>:l:" .MIAi~M .. h~.1'l fJhly'k.l:. \"t.':,. Yl)nu\) ~-:Sh'.;)JIV:oJh
G-3
OF SAMPLE + CAN (WET) (gms) 5
OF SAMPLE + CAN (DRY) (gms) 600.44
OF WATER (gms) 11.91
38.45
OF DRY SAMPLE (gms) 561.99
CONTENT (%) 2.12
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
AnERlc<>rnp,""y
I'!({;f> ~I c..L:-'_::'----U f~ :.:
t'.m.!\W.l£J RIVADH GEOTECHNIClUE & FOUNDATIONS CO.
w - ...:;;~ ~ '-::?---' I ~
P_D. DQJoC 30.2.7:1. 'Vunbu AI •.sh~;'Y;,:)h. MYI'\S 5:1000.. Y.SA Telephone: +966 (:111) 32S09!>12 /S25-O!)9:;) F~)(! +966 (14) 3250946 F.m:ai1:! l"g'...y.IU,bU@.e.l¥.gc,.:::.:«::I"",nc:oelJ..collf1l
L'O(":alk;.n:. ..rr.1.Na...van.and :5it,n:,lft't. Hal .Al-M""h~n D;~tTil;";t. ~,C .......anbu ~--Sh'M'IV+Jh
SAMPLE NO:
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
'C..--L-~Uf.!' ~~ ~y~l~
An ER! Corr>pany RIVADH GEOTECHNIQUE & FOUNDATIONS CO.
T'.O~ uo~ 3~7'1. Yllnt».< AJ.Si",;IYil)h, .f\"fVAS 5'000", Y.:5A 'l'I;tll2'phono! .06"6 ('101) a:orSCl"J92 /32S099!:;) """'>I:: +96«; (1 .... ) 302:50946 E--":aU"!. rR'VYJu"bU«pIi:I,ff""'II'o...el£!nv:oe'fl.cc:.tn
t<\.K.:Hk.. ,,! AJ.N.a-w-Af'q~n<f :5u~";I't~ H~IA1_'Vh:ilh.:ll-T\ I)hlf'kt;. ft.C., Y.anhn AJ·slo<)tV<Jh
SAMPLE NO :
RGF-YN8-PHY-SOIL-15-02
01.082021 Copy Right Resrved by RGF
RIYADH GEOTECHNJClUE & FOUNDATIONS CO.
p~o" Qt)o( 30Af71. YntU>Q Ah$ro';;'rY~h • .,."."VI\S ;53.000.. KSA "rC'101!"pho~! +966 {14} 3:.:./',5.Q992 I ».250!i)93 F""X~ ...gt::;.6 (14) 3:2':509... 6 Etnallt 1f'«,..y,.u·.hu@"'1't3~'::'!i;Cjet'J"".e..,.47('>M
'.o.·.~HI'(>n~. M-N"'W"i,H,~nd :5t·,..r,""'t~ tt~l.At-Mii;h;vn 1')t"U-'.ct.. ft ,C.. .... j,. . .,hu Al_S~naly~h
SAMPLE NO:
CAN NO : E-9
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
f1:»<! .. ~G6 (1.4) 11250946 Etn;31J-:. r8'~yanbU@}"Hfg~o~i:ence:s..«:otn
tJb!lrllCt". R,'C•• Y.;!I;1oUtl ,AI-sr,~ly.,h
SAMPLE NO:
SAMPLE NO:
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
c...L::-L::.---V I., ~~ <../ ~~ I ~
RIYADH GEOTECIINlauc & FDUNDATJOl'-lS CO.
P.O, Do,. 30.z'7'J.~ YtH'libu A'~Sln;lyi)ll. J\1YAS 5"000.. KSA TIfi'J4"phfl~: +-1>(i6 ("4) a::ls.o<'J92 I B2-SQl'....'U'3 vax: .9&6 (14) ::.::lSQ'l>46 £fh31J! 19r..y.l'U"lbU@.-:ttg:oIfC>$dt':"l'>E':lt.eon't
\.o('.</I'k:.o: ,IU-NG.W'l\\"IoAfU'f ::':<;""I')"..-t• • ht.l Al ~\"~h!R," DtJitJlic,t. A ,C•• ,.,...~"t'M,1 AI-:5lo!\lV"h
E NO:
T-6
OF SAMPLE + CAN (WET) (gms) 548.77
OF SAMPLE + CAN (DRY) (gms) 526.33
. OF WATER (gms) 22.44
OF CAN (gms) 45.66
. OF DRY SAMPLE (gms) 480.67
WATER CONTENT (%) 4.67
RGF~ YNB·PHY-SOIL-1S-02
01.08.2021 Copy Right Resrved by RGF
P.o.. ftoJoi 30271~ VanbU AI-Sln;IY~h. ""VAS 5l.000~ KSA TI:l-Je-pho'f\(;O! +~G< (.til' a:;.r,$Q<f")s)2; S::I:!s..o:9'93 V::.X: .9(;.6 (14) 112!'"C941l. J,jI'(u.iJ-1 'i'l\f..ynrd:;uO""Hgc-C'.+~l ....r.c.e:",.cot\')
lO<.aHt)'ol.AATNawa"'ltnd :SU'~(1it~ U,"l Af-M1lh<ln r"h.tJ'h:.t'.fl.<:". V.anbu A:I-"SlOo<lotv~h
SAMPLE NO:
RGF-YNB-PHY-SOIL-1S-02
01.08.2021 Copy Right Resrved by RGF
~~ v "C...-l.:..-l..;:::.--'U I jJ , - '" • ~~ t./ f~ L;:./-'
An ER. Corropany ,~;7!:J' U.A' RIVADH GEOTECHNIClUE ~ ~OUN';ATIONS CO_
P.O. uo)t 30.27:1., YllInbu A"S'~;'l\1;1h. MVA.S S::U}t>O.. KSA TeJ~pho~! +966 (:I."') a7S09!>2 I 3250993 F:lrx: -+96<> (14) 92$0946 IOm'ail::. "·U'...y.lu'lobu@-.etJg.<ep~;:-enc:oe:B-.col'V)
-'1()(".a-H"t"J~ AJ.NallV",n:and 5u·'~"f."t-. H~I AI-M~h;;;n r .. ht.,-i<;;l. R.C., VOJnbu A1-Sln""tVilh
SAMPLE NO:
RGF-YNB·PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
P~O. ,,0)( :;;tUX.7':t.. Ylu'Ibu Af"5f!'\;;lY\)h~ I\.<1VAS S:lODO... Y.SA T~le-phone-! +.966 (14) a.:;l$Q9~:l1 !i):;l50r,)t)~. f.n)(l +966 (:14) a2$09",,6 E,-n:n.1J-:. I"R'-YJlt.I"\l:)UI!P1t!,lg,coMC;ienc:elli.<oom
\-04.:"UI1',>I')::' M·N;.Kyvan:;Hl,(i $t"....oe:'i. HuIAI·M ... hun r'.J'hu'i.::r. 1'11:,,::,. "".anb~~ Af-Sin..lol'r':o;h
SAMPLE NO:
CAN NO: K-11
WT. OF SAMPLE + CAN (WET) (gms) 750.80
WT. OF SAMPLE + CAN (DRY) (gms) 730.25
WT. OF WATER (gms) 20.55
WT. OF CAN (gms) 135.70
WT. OF DRY SAMPLE (gms) 594.55
CONTENT (%) 3.46
RGF·YNB-PHY·SOIL·15-02
01,08.2021 Copy Right Resrved by RGF
RIYADH GEOTECHNIClUE & FOUNDATIONS CO_
P.O. Ue»c 3027:1. YrtnUO AI...sh·~;:'lyal_. MYAS .5-1-000,. Y.SA . TeJ~phon.e--~ +'!\)-G.& U,IJ, 3':Z:>09~:l: ; a:;t!.>tvH3 Vax: "!ii~ (14) a.L!=>VY"'f}. 'i';nhdk 'U'~':r'.l~T.l:<4HW.tlr~,jJ.tH';.U>e)i.""-rtil.e.,fJtln'Y\
t..:,\('.·.'.Hk.~I',It. )1\. NI~' ...Mn!ilr'if ':'iiu,..... l. H-II ~~~h'h.h .... 1".. ,,11",', i't,C" "'(...,.nh~~ A¥-::7hlJ.l.t),.. h
PROJECT : Neom desalination plant to goyal transmisssion system. (LD-03) DATE SAMPLED: 22-01- 2022
SOURCE: TP : 09 Depth: O.30m DATE RECEIVED: 03.02.2022
--------- ------
SAMPLLE DESCRIPTION : Brown Poorly graded SAND with Silt &gravel. Sample NO.: B-1
------------f
SAMPLE NO:
CAN NO: N-06
RGF-YNB-PHY-SOIL-1S-02
01082021 Copy Righi Resrved by RGF
RIVADH GEOTECHNIQUE & FOUNDATIONS CO_
"AX: +966 (:14> 32::>.0946 1Tt'<";aHo::. 1G'..,yar.bu@.e:dgf!"o!r<.:i1!':1,,(;..e:l$.t:o~
Dht,h::l. it,C•• Y.u"tl"u Af-Sh\.<ll)"OIh
SAMPLE NO:
RGF·YNB·PHY·SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
-c:..L:-~U I~ .-:ili ~ ..:;.;~ <./ '-=?~ ,~
An ER. COlnP""''' RIVADH GEOTECHNIQUE & FOUNDATIONS CO.
P.o. no>! 302:7'-. V,:u.,bu N.{5;r.;lynh~ MVA$ $;1000.. KSA TeJ"'phone; +!!>6()' (;Vl) a2S0992 1325(>993 F4:~~ +'9(>6. (1~1') a2~~4'" lirn:;,lh "flf"Y,anl'H.. @""'tllol!:tH..~ll!n-C;>e:"..co"",
Locatfoo:.Ai·NavvAncand :$-tYv.>t't. H~I ""-!Vt:.l'hiW\ Lohulc:.t.. k,C.• Y<lIintlu A1-Sh""""t.,..",h
NO:
M-3
OF SAMPLE + CAN (WET) (gms) 634.53
OF SAMPLE + CAN (DRY) (gms) 613.90
OF WATER (gms) 20.63
WT. OF CAN (gms) 65.30
548.60
CONTENT (%) 3.76
RGF-YN8-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
P.O. Ill.»< 30271, V...nbu Al.51"~i1ah. MVA'$ 5'1()OQ~)(SA "to!1<:<phone; -.-966 (14) 325.c;!J!J~ I :!I2S(}!}:l3 ":')1: ,+9G~ (1t1) 3:J.:501:M6 I!m~lI: tll,f.y,lo"l,h.l@C!:I'",eo"l;.lt'm:c,.(.~l.n
ltl1::::..Uuh: Al,Nawal).,lld ~t"l!i:C U4t Al"v;iilla" OHtfl(.t. n.¢.. Y,tHbU AJ.:$I;H.I!l":,th
Neom desalination plant to gayal transmisssion system. (LD-03) DATE SAMPLED: 15.01.2022
TP: 01 DEPTH: 0.60 m DATE RECEIVED: 22.01.2022
Greyish Brown well graded SAND with silt 8: gravel. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 23.8 0 C HUMIDITY: 39%
DATE STARTED: 23.01.2022 COMPLETED: 25.01.2022
~
720.8 29.5 WT. OF DRY SOIL 2443.80
#4 1006.7 41.2 WATER CONTENT: 0.B2
#10 1540.2 63.0 37.0 REMARKS:
#20 1890.1 77.3 22.7 NON PLASTIC
#40 2094.6 85.7 14.3
#60 2199.9 90.0 10.0
#100
#200 t- 2254.4 ...--..
~~-;~.
2296. 5
-,--~-
92.2
94.0
7.8
6.0
RGF-YNB-PHY-SOIL-Ol-04
01.08.2021 Copy Rights Reserved By RGF
f An ER. Company
1'_0. nOl< ~D271.. Y"'n-t",,, i\'-!Ho;'v..h. MYA.~ 5100Q, t::SA
Cl;;...l.:---'U I, ~~ j',-:?~ r~
RIYADH GEOTECHNIGUE & FOUNDATIONS CO.
"tw:lepll(.)n¢: +9~6 (14) l.:t!HXHi2 I :U!jo;}93 flo ..,.,; ..91$6 (i.1) 'J15()94l1 t"n.:.U: rgf·V3nbu(;j}e.18eos-dC-t>a",.<:on..
lO'(;..tlO(l; Al,N01wa'..... Kf $.ti.;el. H:.l AM..',,\)~., tthWd. ~.<:_ 'I';,~ml;lu Al4Ij,,,,I'I.ah
RGF·YNB·PHY·SOIL·01-04
01.08.2021 Copy Rights Reserved By RGF
f An ERI Company
P.O. 00... .802":7]:, V.n..t,y.AI."":iln;IYAh, MYAS :>'1000. MM
RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
7~I,;.ph<Xl~; ~t) (14) :!-:.t:;~21 ~~~0:!>:93
tue..tfU(~r Al,N';;w.r\:lI~f ~tlo:<t.
'aJI;~ '+9($0 0.4) j'l.50!MO £mlfll: rl;\r.yanbufPt:d8~tn..cle'('!(;e50.t.mh
UbI AI,M.ahllh tJ4ltk,l. A.C., V.",bUAlo$fll.:',toly.ah
~ 2389.30
1 112" 95.9 4.5 95.5 WT.(SOIL+CAN) DRY: gms.
1" 230.5 10.8 89.2 WT.OFWATER 37.50
3/4" 283.1 13.3 I 86.7 WT.OFCAN 263.10 gms.
3/8" 392.8 18.5 81.5 WT. OF DRY SOIL 2126.20 gms.
#4 497.8 23.4 76.6 WATER CONTENT: 1.76 %
RGF·YNB-PHY·SOIL-01-04
01.08.2021 Copy Rights Reserved By RGF
RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
".0. DOl( ~Ol"11. V;>,>VV fti.st,,;JY/:It., MYA'S, 5:1000. '\I;:l.l\, 'f'ehrvh<:me; .,.966 (l~) ~2S()g9l' /3:t:HJ99i!a flax: +9136 (1",) ~:t5(}94G C.,....!t: f1:lr.ya"b\Ja.r:.IR~tH·dt'O()c~.<mn
lbt:MI<.ofl' Al.N"w';II\;:'1I1(i "~f~d. Hal AH..,.,h..n f>h.hl(,,~. ~.( .• Y,iU1IJU Ak$fll..IY4h
PROJECT NO.:
CLIENT:
PROJECT:
NEOM.
------------------------------~-----
Neom desalination plant to gaya! transmisssion system.(LD-03) DATE SAMPLED:
-21J4037
-16.01.2022
---
SAMPLE SOURCE TP: 02 DEPTH: 1.20 m DATE RECEIVED: 22.01.2022
SAMPLE DESCRIPTION: Greyish Brown well graded SAND with clay & gravel. SAMPLE NO.: B-2
ENVT. CONDo TEMP. 24.2 C
o HUMIDITY: 40%
DATE STARTED: 23.01.2022 COMPLETED: 25.01.2022
RGF·YNB·PHY ·SOIL-Ol·04
01.08.2021 Copy Rights Reserved By RGF
An ERI Company RIYADH GEOTECHNIGUE & FOUNDATIONS CO.
f'_O. )lox M271. Ya!>bu A;.!H.)~lyl>f., M'I'A'S 5"10iXJ, 'I<SA 7'CI'Cphone: t!'){).t'j (1111) 32~2 /l250993 t<:Zl!: -.9(',1) (1"') 32::>0946 1;),..,,11: r"'_yanb..,Qlt:/1neClll-del'l<cc".>tmn
L(>.(; .. lk>r,: J\j.Naw,Mwll,' 'tl'e~t~ H.31.'.l"M;J1I~i. ChUf(:i. A.(:_.....1I'.l.iJ At.-;9,ll1bolyah
1~12'
CAN NO. XY
2" 0.0 0.0 100.0 WT.(SOIL+CAN) WET: 2684.90
12" 246.3 10.3 89.7 WT.(SOIL+CAN) DRY: 2639.10
~
" 456.1 80.9 WT.OFWATER 45.80
3/4" 495.2 79.2 WT.OFCAN 253.50 gms.
--~--:-::---
3/8" 639.3 26.8 73.2 WT. 'OF DRY SOIL 2385.60 gms.
----:--
#4 791.7 33.2 66.8 WATER CONTENT: 1.92 %
#10 1213.4 50.9 49.1 REMARKS:
#20 1612.1 67.6 32.4 NON PLASTIC
#40 1914.3 80.2 19.8
#60 1987.5 83.3 16.7
#100 2121.3 88.9 11. 1
#200 2172.1 91.1 8.9
PAN L 1/ .......
~ 650
:: i:L'40
i5 ::<:30
~
1:: 10
20
o
100 10 GRAIN SJZE IN MJLLlMETERS
- - - ---
"
------
0.1
- -- .L
0.01
am 0.001
RGF-YNB-PHY-SOIL-01-04
01.08.2.021 Copy Rights Reserved By RGF
~~ ~ Cl:-~(jI~~~JPl:?..Jf~
f AnERJeomp>nv ....
"_0, Dolt 21,0271, Y'Hl-bu AlxS'n~iY4h. MYA!:l ~1.000.
=·
I<SA
uw RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
1'oeJ~.dU:>fl\!"~"19GO "4) :\2~099"::r I :\1$<W'93 till)!; "i'966 (l-t)tt'l5CJ940 £10,;;11, tRr.yat'>bu@l:!lg<!o)dtt.... o::e!>.'tulT>
1,(O(,uH()(,: Al.N01W..fl:40ll(j $tvt'l!:l. n ..l AI.Mall\,);. DHtfl(.\.l'I_C•• 'fJhl;ou AJ;,$If'J:.tvah
iil 5 30
~ 20
~ 10 -
o
100 10 GRAIN SIZE IN JILLIMETERS 0.1 0.01 0.001
".0. nOM. 80':'-'11, V:I>nb.. AI.S.I.. ~Jy ...h. MVA~ :')JOoO, "SA.
Cl.:-L:-'U l , ~r.tY cYl:?..J I~
RIYADH GEOTECHNIOUE & FOUNDATIONS cO.
1<,h:'.lhoH¢' +9"00 (14) :J':H:~9Z 13%~3 If..,.; ·,.g.66 (14) t\2::>M4tl £>Yo~U; ,."f·Y3nbu~tflg¢o'}<Jton«'AD,"
l(;f('.:.tlo(~~
I\I,N;......"'n:.uHJ !>I1"'¢t!1. it,,1 Al.M,)ll~11 bi,ftld. ".~~ 'I'.:hlN AkSJf}.af1"~h
PROJECT NO.:
CLIENT:
PROJECT:
NEOM.
Neom desalination plant to gayal transmisssion system. (LO-03) DATE SAMPLED:
-21J4037
-16.01.2022
----
SAMPLE SOURCE TP: 03 DEPTH: 1.20 m DATE RECEIVED: 22.01.2022
SAMPLE DESCRIPTION: Greyish Brown well graded SAND with silt. SAMPLE NO.: B-2
ENVT. CONDo TEMP. 23.8 a C HUMIDITY: 39%
-----
DATE STARTED: 23.01.2022 COMPLETED: 25.01.2022
3/8" 25.2
I
iii 30
~ 20
1t: 10
o
100 10 GRAIN SIZE IN MILLIMETERS 0.1 0.01 0.001
p.O. UQ!< ",,0271, Vanbu At<~(';ly ..h. M-'t'AS :,>1,(X)(t, Jo:SA 'l~I~phQoel "i':!iGG U..'I) :J2:$O!i9? / :12~93 YIlJl: ...9156 (14) 3250946 lfm.lll, f~r')'\lnbu.g.I1:.Iu<o~*ntX<!>.{.urtl
ttl(tllltttlo; A!.Nl,h'.rllfi'hl{i St..«t. H",lMt.,l.ah::'h bhttk;:t. It.C.• YAHbti Al'$fm<'yfth
Neom desalination plant to gaya/ transmisssion system. (LD,03) DATE SAMPLED: 17.01.2022
TP: 04 DEPTH: 0.60 m DATE RECEIVED: 22.01.2022
DESCRIPTION: Greyish Brown well graded SAND with silt f:t gravel. SAMPLE NO.: B-1
o
ENVT. CONDo TEMP. 24.2 C HUMIDITY: 39%
DATE STARTED: 23.01.2022 DATE COMPLETED: 25.01.2022
RGF-YNB-PHY·SOIL·Ol-04
01.0B.2021 Copy Rights Reserved By RGF
Cl.:-l.;:/(;I, ~r.?Y J'y~f~
RIVADH GEOTECHNIOUE & FOUNDATIONS cO.
".0. i'.k:lll.itlOl'11. Y.wbu A1.$!n;lVl>.h. MYA=> 5'1000, "'SA T.eI<'11h(>n'l').,~!>(it'i Il.!l) :!llSOt..Hll/ :;12:>.<1993 ttOllIl; ,...966 (1"')~'.t~tH~o;o: £m~l1; ,~r.... ~mbu~l:llB(,"Q"~It'tl(:<:lo"(;Clm
l.i>G.tfil(\: Al.NlIVI;)f):;)n(J $tlotttt. ;UI AI~MJ,h"(f ()t~'rI(:_~ ",C., 'r'4{"'l,Iu Al-!$Ijlafyah
~650
~ !!J40
i5 ~30
;;2 20
1l: 10
o
100 0.1 0,01 0,001
10 GRAIN SIZE IN rJILLIMETERS
RGF-YNB-PHY -SOIL-01·04
01.08.2021 Copy Rights Reserved By RGF
~r4
't:::r_
f V
J -_.
..........., ."'" I - I - ~U I .. '" . . aX AJ, ,,:? H./
t:1,.,,*,
~~M}
~
V "-".......--.....-- ft ~·~i
_ . . . V. . :/' ~
An Eft. Cnmpany '\\\i.i;.."l1.!' v •." RIVADH 0f"OT€ ' rHNIOI IF [(. F OIINDATIONS CO.
P.O. UO)o\ <1017:1, Y.uobu A1-$fn~l" ..h. MYA"; :;:1000. 1($1\ 'f(!leph(.loe: ..!)(l.t} ~)~) 325{)9~Z I :;'5099~ h)<: ...9G6 (,<Ii) 3'250941J ~ln311, J"Qr.y~n4\J@ef!3ec>~lcnc..e5"<am
tuC..Hunt I\hN.lw.,I)Jt!.ii $t"vo:t. Htot AI.M..han DHtdd. ;:t(... -r<lif,bu AI':~I.,..fy;m
Neom desalination plant to gayal transmisssion system. (LD-03) DATE SAMPLED: 17.01.2022
TP: 04 DEPTH: 2.00 m DATE RECEIVED: 22.01.2022
DESCRIPTION: Greyish Brown well graded SAND with day. SAMPLE NO.:
------
23.7 DC HUMIDITY: 38%
DATE STARTED: 23.01.2022 COMPLETED: 25.01.2022
0
100 10 GRAIN SIZE IN JILLIMETERS 0.1 0.01 0.001
RGF-YNB-PHY -SOll-01-04
01.08.2021 Copy Rights Reserved By RGF
f (elf) v [---
-~[Jw I t::"A.•::.-I...;:../V I., ;: -'" •....:;,;.,.4
AnERlcompany "i'.~~' __ ~':: RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
P.O. 00,,30271, Yanbu AI_Sl'n;ly.:oh. MYA'$ ~1000. KSA
- c../U.) I ~ + -
Telephbne .....!')6t) (1.4) ~2:1oOS'J2/31~0993 f!::.,,; ..-96tS (10") :!!J2~094tS t:m411. rl'r·Yilllbu@l:tlseo!l.-c1.e-llc(:,,"C01T'1
luC",U(Jf,: AI~NAwa"4j)d $tf<:'t!t. ";)1 At.M;)'}:;>" Dhhld. A..c., \'di,I"U Akjlll:bllldh
PROJECT: Neom desalination plant to gayal transmisssion system. (LO-OJ) DATE SAMPLED: 18.01.2022
SAMPLE SOURCE TP: 05 DEPTH: 0.60 m DATE RECEIVED: 22.01.2022
SAMPLE DESCRIPTION: Greyish Brown poorly graded SAND with silt ft gravel. SAMPLE NO.: B·1
ENVT. CONDo TEMP. 24.6 DC HUMIDITY: 40%
DATE STARTED: 23.01.2022 DATE COMPLETED: 25.01.2022
SIEVE SPEC. WEIGHT % RETAINED % PASSING
SIZE LIMIT RETAINED WATER CONTENT: (ASTM D 2216-19)
3"
21/2" CAN NO. R-8
2" 0.0 0.0 100.0 WT.(SOIL+CAN) WET: 4065.70 gms.
RGF-YNB-PHY -SOIL-01-04
01.08.2021 Copy Rights Reserved By RGF
RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
".0. no~ :J1)~7'. V.$IrIDli Ah!Un~tyah, MYAS, ~1.OOO. -':$A, idephvnc; 't'!'I'66 (l4) )1::S099~ /3:t5099-:' "",1: ... 966 (14) ":tJ;Og46 l!-.n.:tlh '1\f~y3nbuG'9t:d"('o$rk.'1'!c(:'".<om
L0e..U••ft; AI.N;,wii>.~ml t>t~l,tl. H~l Al.M~h~1l bhttk,). ~.( .• 'I'~i.b ... A,i"lhiJJJlah
ENT:
PROJECT: Neom desalination plant to gayal transmisssion system. (W-03) 18.01.2022
lE SOURCE TP: 05 DEPTH: 1.20 m DATE RECEIVED: 22.01.2022
PLE DESCRIPTION: Greyish Brown poorly graded SAND with gravel. SAMPLE NO.:
• CONDo TEMP. 24.3 0 C HUMIDITY: 40%
DATE STARTED: 23.01.2022 DATE COMPLETED: 25.01.2022
IBoo
v.v II
2893.6 95.8 4.2
PAN 2895.2
TOTAL SOIL WT. 3021.30 gms
RGF ·YNB-PHY·50IL-01·Q4
01.08.2021 Copy Rights Reserved By RGF
1'.0. \1(>~ {t02:r'l. YIIM.>I.JAI,5h·";'V..h, MYA'S ~'l()Q(1, ~$~ T<I<;,phooO!-; 't90(\ (til) 3250!:>!J:l! /3250:9!J3 f<;lI:'-: -+-966 (tol)~2~09"4G f!m.tll, t",r~ya"bU@<ltIIRe-O"dC'm:.e ...<:lnn
Lu~M'{J(n /IF N;'w:~lI):~O(t 1I\1'~;II, lul.,\I·M.?hHII'>T~l(I'.\. R 0';. Y"li.. h,1 M.1fllitfrt",h
PROJECT NO.:
CLIENT: NEOM. - -21J4037
----
PROJECT: Neom desalination plant to gaya/ transmisssion system.(LD-03) DATE SAMPLED: 18.01.2022
SAMPLE SOURCE TP: 05 DEPTH: 2.00 m DATE RECEIVED: 22.01.2022
SAMPLE DESCRIPTION: Greyish Brown poorly graded SAND with gravel. SAMPLE NO.: S-6
ENVT. CONDo TEMP. 23.8 DC HUMIDITY: 39%
------
DATE STARTED: 23.01.2022 DATE COMPLETED: 25.01.2022
gms
RGF ·YNB·PHY-SOIL-Ol-04
01.08.2021 Copy Rights Reserved By RGF
f An ER. CQm.,.ny L';':~!
rQi)..
RGF·YNB·PHY-SOIL-Ol-04
01.08.2021 Copy Rights Reserved By RGF
f An ERI Comp.ny
".0. n(>~ ao.l7~. "bubu At.SJn';ly>l,Jt, MYAS :)'1000. K'SA
CL-l.;../1JJ~ ~~ tfl;?.J'~
RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
T¢I¢p'u:.. n¢; '1";66 (14) It:;(i'Jt)?' /l:t:>O"3 r ..X! "'9~ (,).4) "~!W94~ £',r..:.1I; r(lr~'I'aob\Jj§ledR¢o~dCfiCe,._<C.om
I,.tH.:.atlufI; A1_Naw~(;.nd ,tiC<:'t, Hill AI.h1..hil:il !)h,Ufd.I't.(.• V.Hrt.\> Ah$li''''ft''h
RGF-YNB·PHY ·SOIL-01-04
01.08.2021 Copy Rights Reserved By RGF
An fBI Com.,.ny RIYADH GEOTECHNIQUE 8< FOUNDATIONS CO.
P.O. nul'l. fH12'11. 'tanbu A'~~n~ly;>.to. MYAS ~'ooo. I<SA "fel<t•• ht>f,~; .'96~ (14) 32.501l9Z I '32~993 1'1Ilt: "*91$0 114J 3"1:5&911,6 em~lI; rar~Y3tlb>J€'Pe.l8C'o)c!cm::e~.<um
t(>C .. U()i.~ J\I,NlI'Wtu>JIH(t St:f~Cl, fla\ Af>M.'Iht./'i £>!$ltKl..I\.(. .. "'.tht".. Al4hufy..h
3/8"
0.0
11.5
E i= 0.0
0.7
I 100.0
99.3
WT.OFWATER
WT. OF CAN
WT. OF DRY SOIL
194.20
-----
1718.30
gms.
gms.
-----:--
#4 33.2 1.9 98.1 WATER CONTENT: 2.78 %
#10 185.5 10.8 89.2 REMARKS:
#20 590.0 34.3 65.7 NON
#40 1169.1 6U.O ],1.U
#60 1537.1 89.5 10.5
#100 1626.0 94.6 5.4
#200 1663.9 96.8 3.2
~SOILWT.
1668.1
1718.30 glll~
~I
#40 1087.0 78.1
#60 1246.7 89.5
#100 1308.4 94.0
#200 1344.8 96.6
PAN 1346.2
TOTAL SOIL WT. 1392.20 gms
Neom desalination plant to gayal transmisssion system, (LD-03) DATE SAMPLED: 20.01.2022
SAMPLE SOURCE TP: 08 DEPTH: 0.80 m DATE RECEIVED:
SAMPLE DESCRIPTION: Brown well graded SAND with silt 8: gravel. SAMPLE NO.:
---=--=--
ENVT. CONDo TEMP. 24,2 0 C HUMIDITY: 39%
------
DATE STARTED: 23.01.2022 DATE COMPLETED: 25.01.2022
I
1 1/2" WT.(SOIL+CAN) DRY: 1965.10 gms,
--~-::-:---
~
799.7 45.5 54,5 NON PLASTIC
1138.7 64.7 35.3
#60 1377.5 78.3 21.7
#100 1508.5 85.7 14,3
#200 1618.2 92.0 8.0
PAN 1620.6
TOTAL SOIL WT, 1759.40 gms
~ (§so
::~o
i5 330
;;i 20
Ie 10
o
100 10 GRAIN SIZE TN JILLJMETERS 0,1 0,01 0,001
Neom desalination plant to gayal transmisssion system. (LD·03) DATE SAMPLED: 20.01.2022
TP: 08 DEPTH: 1.20 m DATE RECEIVED: 22.01.2022
Brown well graded SAND with gravel. SAMPLE NO.: B-3
0
ENVT. CONDo TEMP. 23.6 C HUMIDITY: 39%
DATE STARTED: 23.01.2022 DATE COMPLETED: 25.01.2022
SIEVE SPEC. WEIGHT % RETAINED % PASSING
SIZE LIMIT RETAINED WATER CONTENT: (ASTM D 2216-19)
3"
2112" CAN NO. R-2
2" 0.0 0.0 100.0 WT.(SOIL+CAN) WET: 2976.00
1 1/2" 74.9 2.7 97.] WT.(SOIL+CAN) DRY: 2927.90
1" 126.3 4.6 95.4 WT.OFWATER 48.10
3/4" 193.8 7.1 92.9 WT.OFCAN 197.20
3/8" 294.9 10.8 89.2 WT. OF DRY SOIL 2730.70
#4 494.2 18.1 81.9 WATER CONTENT: 1.76 %
~
SPEC. WEIGHT % RETAINED % PASSING
SIZE LIMIT RETAINED WATER CONTENT: (ASTM D 2216-19)
RGF ·YNB·PHY·SOIL-01-04
01.08.2021 Copy Rights Reserved By RGF
AnERI RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
".0, Otnt ~o:'t11. Yanbu JII.!.$lO#lylll., MYA:t: 5'1000, XM "1clr-phoo(': ~66 (14) 32$07:)92' /32!SO!1113 t'alO.: +90:$6 {14) 32"09>11(1, ihn'loit; r6f+...... nl;I1,@~.IS('o~cl~m:oe~.(:mh
l<)(4U;:;...: j\!.NAwa..1U'I(' Stf.:i;t. H ..l AJ.·Mdl>"fI Ofc!ttlet. n.e., 'i~;~bu Aj •.,lw);lyah
Neom desalination plant to gaya/ transmisssion system. (LD-03) DATE SAMPLED: 20.01.2022
SOURCE TP: 09 DEPTH: 1.20 m DATE RECEIVED: 03.02.2022
.:'A....... r DESCRIPTION: SAMPLE NO.: B-3
• CONDo TEMP. 38%
STARTED: 04.02.2022 DATE COMPLETED: 06.02.2022
SIEVE SPEC. WEIGHT % RETAINED % PASSING
SIZE LIMIT RETAINED WATER CONTENT: (ASTM D 2216-19)
3"
2112" CAN NO. N-12
2" 0.0 0.0 100.0 WT.(SOIL+CAN) WET: 2375.00 gms.
-----
1 112" 0.0 0.0 100.0 WT.(SOIL+CAN) DRY: 2305.60 gms.
1"
-------
0.0 0.0 10Q.0 WT. OF WATER 69.40
3/4" 210.2 10.1 8 WT.OFCAN 220.90 gms.
11I~~~~I1I1~~~1
90
in 80
Q 70
100
~;-.60 -
;: ~O
15 3:30
22 20
6: 10
o
100 10 GRAIN SIZE IN MILLIMETERS
0,1 0,01 0.001
RGF-YNB·PHY .SOll-01-04
01.08,2021 Copy Rights Reserved By RGF
CL-L:---'Ul~ ~~ ~y.)l~
An Eftl Company RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
,",.0. noxa02'71. Yat.biJ AhSJn~J.,.d" MYA':J; !hOO(). ~SA. 'foe'C'Jlh(ffl«; ...%6 tl.:!}32~099t 13<Z~09!)3 rax: ..-9156 (14) 3'z509ilG I!m.$lI: q~f.v"u.bu~h:·dR:~oWcnt::c~.(L)m
(i)t'.o.Uoo: A'.N>iwiu\.1lHl Stn:.>i!t. ..I ... AM\'''Olh",n 01$\'1(;1. ft.(; •• va,)h,; Al41Hl>tvah
RGF·YNB-PHY-SOIL·01·04
01.08.2021 Copy Rights Reserved By RGF
An EAI Company RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
P_O. BoX ;30211, Vanbu .Al".sltltllytl.h~ MVAS 51000, KSA 'Telephone: ,t966 (14) 325(»92/3250993 fa)(! +%6 (14) 3250946 Emath rgt"yanbu@t!rlgeo.s:dctH':cs.com
locationt AI·N.3w.3nimd Stfe0.t~ Hal At-M;]h~n otUti(t~ R.C.~ VanbV Al-Slni>\yah
Neom desalination plant to gayal transmisssion system. (LD-03) DATE SAMPLED: 15.01.2022
------------~----~------------~------------------
TP 01 DEPTH: O.60m DATE RECEIVED: 22.01.2022
DESCRIPTION:
----------------------------------------
Greyish Brown well graded SAND with silt ft gravel. SAMPLE NO.: B-1
o
ENVT.COND.TEMP.: 23.8 C HUMIDITY: 39%
STARTED DATE: 23.01.2022 DATE COMPLETED: 25.01.2022
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH
WT DRY SOIL + DISH
NON-PLASTIC
WTWATER
WT DISH
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
LL
NON-PLASTIC
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WT WATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF·YAN-PHY-SOIL-02·04
01·08-2021 Copy Rights Reserved By RGF
P.O. Bo)( 302"1. Yanbu Al.Sln;lyah. MVAS 51000. KSA Td~phonl!': -+966 (14) 3250992/3250993 F.a)(l ·.966 (14) 3250946 Emall!r8t.ya·nbu@~rI8(!.osclenc~s.com
laeatlom Al-Nawannnd Str-eot, Hal AI-Mahan otstrict. R.C.~ Yanbu At-stnntyah
L I QUI D LIM I T
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
~ == ::=,,-~~
LL
:::::~,,::: ~:~.::
... _-
~::~::, ,~=: . PL
. :~~.:.: .=:~.~.=.::: ::==~.
.... ~. ~
- - -~~
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
Cl:-l.;:../U J~ ~~ Lfy.) 1;.(..::/
An Enl Compllny RIYADH GEOTECHNIQUE & f OUNDATJONS CO.
P~O. 80)( 30211, Vanbu AI •.sln3IYllh~ MVAS 51000~ KSA T~tephone: ·t9&5 (14) 3.250992/32S0!J93 f'.all! "'966 (14) 3250946 fmallt tgt"y ..'t)buGP~"lseosdenccs.co.m
locatl~m; AI-Naw~flimd $ttCl.tt, H.i,1II AleMahan DIstrict.. R.C.. Vanbu I\J-S1nafy.ah
L I QUI D LIMIT
RUN NUMBER 1 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL
MOISTURE CONTENT %
NO. OF BLOWS
LL
NON-PLASTIC
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER z 3 4 CONTENT
DISH No.
-=-=------------------~------_+--------_+------~~--------4_--------~
gms
gms
gms
NON-PLASTIC
WTDISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF·YAN-PHY-SQIL-02-04
01-08-2021 Copy Rights Reserved By RGF
AnERt
P,Q. DO)( 30:.al. Yllnbu At..sln~lyahi" MYAS 51000. KSA "Telephone, ·.966 (14) 32!H'}!')92/3250!)93 F;,):.:~ .... 9GG {14} 32!<0946 CmIlU, ra"y~u'\bu@t'rIB(!()J:ch:mce:t.com
LocOltion: AI~Naw3nand Str~~t, H~I Ar~M~ft:n1'l ulbrfla~ B.lo;" Y~nbU Al..,s'niJl'f~h
L I QUI D LIMIT
RUN NUMBER 1 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
gms
NON-PLASTIC
WTWATER
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
LL
.... _........-. .. _.
Number of Blows PI N'P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gm
NON-PLASTIC
WT DISH gm
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF·YAN·PHY·SOIL·02·04
01-08-2021 Copy Rights Reserved By RG F
P.O. 80)( 30271. Yanbu Al-sln~ly:tih. MYAS 51000~}(sA "Telephone: -t966 (:14) 3250'"~92 /32S0993 f.,'])(! +966 (14) 32S0946 Email! rgt~y.:mbu@erlseo.!:cI~nci!$...com
l.oc:titlon: AI-Nawan"nd Strc-~t, Hal AI-M,3h~n otstri<;t. R.C.~ Yanbu AI-Sln:tilyah
L I QUI D LIM IT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WT WATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
..... LL
t:
OJ
.....
t:
o
U
' PL
.2l
C1I
s:
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WT WATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
Neam desalination plant to gaya/ transmisssion system. (LD-03) DATE SAMPLED: 16.01.2022
---------------------------------------------------
TP 03 DEPTH: 1.20m DATE RECEIVED: 22.01.2022
L~"'''Y.r·Lc DESCRIPTION:
---------------------------------------
Greyish Brown well graded SAND with silt. SAMPLE NO.: B-2
o -----------1
ENVT.COND.TEMP.: 23.8 C HUMIDITY: 39%
STARTED DATE: 23.01.2022 DATE COMPLETED: 25.01.2022
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON· PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
LL
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH
WTWATER gms
NON·PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF·YAN·PHY·SOIL·02·04
01-08·2021 Copy Rights Reserved By RGF
P.O. Box 302·'1, Yanbu AI.Sln~IYi1h. MYAS 5:1000. KSA -Tclephon~: -t966 (14) 3250992/3250993 Fa)i! -t966 (14) 32509-46 Email: rs.·yanbu@crIScosc\cnces.com
location: AI-Nawanand Strcat, Hal AI-Mahan Dl&triGt. R.C.~ Ynnou IU-Slnalyah
L I QUI D LIM I T
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
,=
..::.::. . .:·.i··:··:··: . ._-,__=_c,= :.::" ,.:.:.. =::.1:.:.:..:.:..
...... ;
LL
t:
,.-:.:.;:.
2t: '-:':L::.: :::.::: ..:::::
U
o
... ~=l NON-PLASTIC I'·:::,:::::=:
Q)
PL
......
<II
, .. _._.
~ . -- . - .....
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WTDISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY -SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
CL:-l;../UI, ~~ ~,-=?.)I~
An En. Company RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. Box 302:7.1. Vl1/ibU A'~S~n~rYllh)' MYAS SlOOO~ KSA TC!'fephOne! ,,966 (14) 3250992/3250993 Fa)(! +966 (14) 32S0!M6 Email! r6t.y..n\bu@erI8e()sd~nce!u:ot1'\
location! A~-Naw.;tnllml Strnat. Hal Al-Mah;m otstrlct~ R.C.~ YanbU i\t·Slhalya'h
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-03) DATE SAMPLED: 17.01.2022
SAMPLE SOURCE: TP 04 DEPTH: O.60m DATE RECEIVED: 22.01.2022
SAMPLE DESCRIPTION:
----------------------------------------
Greyish Brown well graded SAND with silt. SAMPLE NO.: B-1
-----------1
ENVT.COND.TEMP.: 24.2 DC HUMIDITY: 39%
STARTED DATE: 23.01.2022 DATE COMPLETED: 25.01.2022
L I QUI D LIMIT
RUN NUMBER z 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WT WATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
LL
NON-PLASTIC
PL
.=
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-02 -04
01-08-2021 Copy Rights Reserved By RGF
P.O. Dox 302"11. Yanbu Al~Sln;lv-ah~ MYAS 51000. KSA ·Telephone: ·t966 (l.4) 3250992/3250993 F;))(! ·t9£6 (1.4) 3250946 Email! rB'~yo1nbu@~rl8~oscl~nt~s.tom
I,..QetJotlon: At-Nawo1nand Streat. Ho1l AI~Mah:m Dlstrict~ R.C.~ Vanbu AI·stnalyah
L I QUI D LIM I T
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
E~r~,
....c: LL
~
c:
o
U
... PL
~
ra
~ r:~·:-_-::-:::--:: ..._ . _._.... _~:--.:=======--:::::~-==-_-===:i . . .. -.. _..._. ._... 1 .
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-02-0~
01-08-2021 Copy Rights Reserved By RGF
P.O. Box 30271, Yanbu A1_sln;lyah. MYAS 51000. KSA Tclcphonl!': ,t9G6 (:14) 3250992/3250993 fa,.! "966 (14) 3250946 Em:aU! r8f~yanbu@crls~o~dcnc\!s.com
loeatlon: A'~Nawan .. nd strqet, Hal AI-Mahan Dtstri<;t. R.C.~ Yanbu Ai-Slnalyah
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-03) DATE SAMPLED:
------1
SAMPLE SOURCE: TP 05 DEPTH: 1.20m DATE RECEIVED:
------1
SAMPLE DESCRIPTION: Greyish Brown poorly graded SAND with gravel. SAMPLE NO.: B-2
ENVT.COND.TEMP.: 24.3 DC HUMIDITY: 40%
STARTED DATE: 23.01.2022 DATE COMPLETED: 25.01.2022
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
..... LL
s:::
2s:::
o
U
... PL
.....ra
OJ
:s:
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF·YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
@l
eM
[~] Cl.:.-l.;;...--(JI, ;:::.7A U'L--.) I~ - .. - ..
....c LL
....c
Q)
o NON-PLASTIC
U
L. :~~~J.;.... .c. ... ....• ...............•..•.••..... PL
J!lra
?: C.· .......••••.. .•••....".:::c
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER z 3 4 CONTENT
DISH No.
WT WET SOl L + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY -SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
~~I Cl:,..l:;./U I~ ::;....:..7.& ift,?.) I ~
An ERI Company ~,~, U~A5 i RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. SOl( 30271, Yanbu AI.sln~Iy01h~ MVAS s:tooo~ K5A 'Telcphanl!e +9615 (14) 325tY-J92/3250993 F.a\(~ >}966 (14) 3250946 Eman~ t8t~y;anbtl@C:tI6t:!o5denc:~s.com
loc,atl(')lH AI~NaW3nand Stflll$t, Hal AI-Mah~n DI&tti(.t. R,C'A Y.;'mbu AI·Slnnlyah
L I QUI D LIMIT
RUN NUMBER 1 2 3 4
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
LL
NON-PLASTIC
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN-PHY-SOIL-OZ-04
01-08-2021 Copy Rights Reserved By RGF
P_O. Box 30271. Yanbu AI~SjTl;fV:ah. MVAS 5;'000. KSA 'Telephone: '~966 (14) 32S0992/.3250!J!l3 F.;:.)(! ,.. 966 (14) 32~0946 Em:ali: rgr..ya.1ibu@et1eeo:i:dem::::t':!$.com
loc;)tiom AI~Naw3n .. nd str-cet, H;)t At·Mahan Pt$frr(t~ R.~,.. V.;:.ntru AI.slnaly.ah
L I QUI D LIM I T
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
-::::-~=."
LL
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER z 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
AnERI
P.O. SO)!: 302"11, Yanbu A1.S1n~tY~h" MYAS 5:t000.. KSA 'Telephone! ·.966 (:14) 3250992/3250993 F.ax! .. 9-66 (14) l.l250946 Email: rsf,yanbu@erlgcosdences.c:om
location:: AfwNaW~n;)nd Str(l'et, H.al AtwMafUH1 Dtstrl<;t, R.C.~ Vanbu Al-Slonlvah
LL
NON·PLASTIC
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-02-04
01 -08-2021 Copy Rights Reserved By RGF
P.O~ aox 30271. Yanbu AI~Sfn;ly.m. MYA$ S;lOOO. l<SA Tcl~phon~: '19fl~ ('14) 32e309'92 /3250993 FOlX! ..!to6 (14} 3250946 Em;a,U: rRt..y ...mbu~'i>CrIBCO$dt!nct!.!LCOm
lQCatlon: AI~N",wammd $thH.\t. Bal At~Mi)hOln Ulstl'lct. n,c,~ YtlObu A1-S'naJ'i;ih
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
LL
NON·PLASTIC
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH
WT DRY SOIL + DISH
WTWATER
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
GL-l;./(J/~ ~;;y J'V~I~
An EBI Company RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
P.O. flox 30Z'} 1~ Yanbu AMiln~tyah. MYAS 51000. KSA Tct~phonl!-: -.966 (1.4) 3250992/ 3250993 faX! ..966 {14) 3250946 Emall! t8t~yolnbuQ)ctJs~osdcnc:e$.com
/.oc:tt(on! A!-Nawanand Street,. H~J AI-M,'lhan otstrld~ R.C,~ Vanhu Aj·S1oill'lah
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER
WT DISH
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
....s:: LL
.l!:l
s::
o NON-PLASTIC
U
... PL
.l!:l
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER z 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
Tested By:
-----
M.lrfan Checked By/Reviewed By:
- -Saeed
- - Akhtar
---
Approved by: Awais Nisar Yasin
RGF -YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
P.O_ Box 30211, Vanbu AI-stn;IY;)h~ MVAS 51000.}(SA Telephone: ·t966 (14) 3250992 /3250993 Fax! ·~966 (14) 3250946 Email! rgf_yanbu@'crI8co.!:c1~ce.!=-com
lOcation: I\!-Nawanand Street, Hal AI-Mahcln Dt1.trict. R.C., Vanbu AI-SlnalVah
LL
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WT WATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
p.o_ 80)( 3;0271, Yanbu Al-Sln;IY::lh~ MYAS 51000. KSA 'Tclcphone~ ·,966 (:1.4) 32S0992/32S0993 f~)(! ·t966 (14) 3250946 Em~lI! r8t~yanbu@crI8t!0.!:denc;!'s.com
lOColtlon: AI-Nawanand Street, Hal At-Mahan OTstrict. R.C.~ Yanb-u AI-Slnalvah
Neom desalination plant to gayal transmisssion system. (LO-03) DATE SAMPLED: 20.01.2022
---------------------------------------------------
TP 08 DEPTH: 1.20m DATE RECEIVED: 22.01.2022
----------------------------------------
Brown well graded SAND with gravel. SAMPLE NO.: B-3
ENVT.COND.TEMP.: 23.6 DC HUMIDITY: 39%
STARTED DATE: 23.01.2022 DATE COMPLETED: 25.01.2022
L I QUI D LIM IT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER
NON-PLASTIC
gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
LL
NON-PLASTIC
.....
. . . . ,.tl PL
........... ---
.._ -
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
,eM
,~) ~GL:-l;../(;I,~~t../'U.)f~ - .. + ..
Neom desalination plant to gayal transmisssion system. (LD-03) DATE SAMPLED: 20.01.2022
-------------------------------------------------
SAMPLE SOURCE: TP 09 DEPTH: O.30m DATE RECEIVED: 03.02.2022
SAMPLE DESCRIPTION:
-----------------------------------
Brown Poorly graded SAND with Silt &gravel. SAMPLE NO.: B-1
o
ENVT.COND.TEMP.: 23.6 C HUMIDITY: 39%
STARTED DATE: 04.02.2022 DATE COMPLETED: 06.02.2022
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
LL
NON-PLASTIC
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-02-04
01·08·2021 Copy Rights Reserved By RGF
:..::.An::.::E::::.:"R:..::.:::..I..::.::.:.::~....J....;;~~~ RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. 00)( 302'11. YanbuAt~sJnalY<lh. MVAS SiOOQ. KSA 'Telephone: ·t966 (14) 3250',)92 / 3250993 fa)!": +966 (14J 3,2S0946 Emall~ rgt.yanbu@Nlg(!Osdenc(}s.com
lOCo"ltlon: At~Nawoiln ..nCf Stro4t~ Hal AI-Mahan otstri<;t.. R.C•• Y.aflbu At·Slnaly;ah
Neom desalination plant to gayal transmisssion system. (LO-03) DATE SAMPLED: 20.01.2022
-------------------------------------------------
TP 09 DEPTH: 1.20m DATE RECEIVED: 03.02.2022
DESCRIPTION:
--------------------------------------
Brown Poorly graded SAND with Silt ft gravel. SAMPLE NO.: B-3
--------
ENVT.COND.TEMP.: 23.4 DC HUMIDITY: 38%
STARTED DATE: 04.02.2022 DATE COMPLETED: 06.02.2022
L I QUI D LIMIT
RUN NUMBER 2 3 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON·PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
LL
NON-PLASTIC
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WT WATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
'-=--==Cl:-l.;./U J!} ~r.:1' if~.) I ~
An Eft. Company"" RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
P.O. So;': 302'11, Yanbu A1"slnaly;l.h~ MYAS 51000, KSA 'lcleptionf:!'t 'f966 (14) 32SO"';}!)2 /325U993 f!Hd ~966 (14) ft250946 Emall!rl1t.....anbU@.ctlgel)s(lenc~$.com
lo~attom AI-Na.want')nd S1rc<rt, Hal AI-M~";':In ()I£tti(t~ R.C.~ ¥anbu JU-stnalyah
LL
PL
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WT WATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
M.OISTURE CONTENT %
PLASTIC LIMIT
A YE. PLASTIC LIMIT
RGF-YAN-PHY -SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
r-=-.==r?"91 "GL:.-l..:/U If) ~d j~~ I ~
AnERIc.:<>mp,,"y RIVADI'''' GEOTECI"'NIQUe & fOUNDATIONS CO.
P.O. Box 30271# 't'Anbu J\1~Sinatyldl.< MVAS S:1000~ KSA ·r~lephonel-t966 (:14) 32c!30992/3~.s0993 f'tlxl-t966 (14) 32509116 Er'r"'ii)U~ r8f,y,:u'lbu@CtI8C(.l!I(:lcne~s,cOf'!"
l.n(;;llIQnl Af-N:,w.mi'lod StnH'~t, H<!oJ At·M;lh~n Dh\r!d.. n>c~, Y.;'!ntnl AI-Sln:i\IVilh
L I QUI D LIMIT
RUN NUMBER 3 4 5
DISH No. H-3 F-3
WT WET SOIL + DISH 33.55 37.26
WT DRY SOIL + DISH 30.65 33.85
WTWATER 2.90 3.41
WT DISH 21.55 20.47 21.33
WT DRY SOIL 9.10 11.01 12.52
MOISTURE CONTENT 31.87 29.70 27.24
NO. OF BLOWS 16 23 34
LL 30
PL 21
Numbor of Blow!> PI 9
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No. N-1 N-3
WT WET SOIL + DISH 28.85 29.95
WT DRY SOIL + DISH 26.75 27.45
WTWATER 2.10 2.50
WT DISH 16.52 15.65
WT DRY SOIL gms 10.23 11.80
MOISTURE CONTENT % 20.53 21.19
PLASTIC LIMIT 20.86
AVE. PLASTIC LIMIT 21
L I QUI D LIMIT
RUN NUMBER 1 2 3 4 5
DISH No. A-8 A-10 A-3
WT WET SOIL + DISH gms 34.27 36.55 35.92
WT DRY SOIL + DISH gms 30.52 32.32 32.44
WTWATER gms 3.75 4.23 3.48
WT DISH gms 19.66 18.95 20.70
WT DRY SOIL gms 10.86 13.37 11.74
MOISTURE CONTENT % 34.53 31.64 29.64
NO. OF BLOWS 15 34
.... LL 32
j 36.00
c::
(3 32.00
... PL 22
$ 28.00
III
;:: 24.00
Number of Blows PI 10
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No. T-2 T-3
WT WET SOIL + DISH gms 28.92 30.44
WT DRY SOIL + DISH gms 26.65 27.85
WT WATER gms 2.27
WT DISH gms 15.92
WT DRY SOIL gms 10.73
MOISTURE CONTENT % 21.16 22.48
PLASTIC LIMIT 21.82
AVE. PLASTIC LIMIT 22
L I QU ID LIMIT
RUN NUMBER 2 3 4 5
DISH No. C-3 B-8 K-3
WT WET SOIL + DISH gms 31.70 33.80 31.59
WT DRY SOIL' + DISH gms 28.86 30.55 29.36
WTWATER gms 2.84 3.25 2.23
WT DISH gms 19.66 18.95
WT DRY SOIL gms 9.20 11.60
MOISTURE CONTENT % 30.87 28.02
NO. OF BLOWS 16 24
40.00
..... LL 28
I: 36.00
Q)
.....
I:
0 32.00
u
'
Q) PL 2'1
.....
a:!
28.00
3f: 24.00
Number of Blows PI 7
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No. E-1 F-3
WT WET SOIL + DISH gms 29.68 31.50
WT DRY SOIL + DISH gms 27.33 28.89
WTWATER gms 2.35 2.61
WT DISH gms 16.32 16.50
WT DRY SOIL gms 11.01 12.39
MOISTURE CONTENT % 21.34 21.07
PLASTIC LIMIT 21.20
AVE. PLASTIC LIMIT 21
L I QUI D LIM IT
RUN NUMBER 1 2 3 4 5
DISH No. A-9 F-2 P-5
WT WET SOIL + DISH gms 31.70 33.80 31.59
WT DRY SOIL + DISH· gms 28.86 30.55 29.45
WTWATER gms 2.84 3.25 2.14
WT DISH gms 20.30 19.77 21.56
WT DRY SOIL gms 8.56 10.78 7.89
MOISTURE CONTENT % 33.18 30.15 27.12
NO. OF BLOWS 17 35
.... LL 30
36.00
.sc
t:
8 32.00
.... PL 22
.s 28.00
~ 24.00
Number of Blowl:> PI 8
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No. M-2 M-3
WT WET SOIL + DISH gms 29.70 31.66
WT DRY SOIL + DISH gms 27.33 29.05
WTWATER gms 2.37 2.61
WT DISH gms 16.50 17.25
WT DRY SOIL gms 10.83 11.80
MOISTURE CONTENT % 21.88 22.12
PLASTIC LIMIT 22.00
AVE. PLASTIC LIMIT 22
TEST REPORT
SAMPLE DESCRIPTION: Brown well graded SAND with silt & gravel. SAMPLE NO: B-2
SAMPLED BY: RGF
ENVY. CONDo TElVIP. : 23.9 uC HUMIDITY: 37%
TEST STARTED DATE: 25/1/2022 TFST COMPLETED DATE: 27/1/2022
,
A. Mass of Diy Sample in Ail' (gms) = 107.60
A
(B-O - (B-A}
UNIT wr. (gm/cm 3 ) E D
= 2.755
= 0.65 %
RGF-YNB·PHY-SOIL-17-00
18.08.2021 Copy RighI Reserved By RGF
RGF-YNB-PHY-SOIL-17-00
18_08_2021 Copy Right Reserved By RGF
~7t> .~ f!J ~.··~11v.
(I ~ V.'.':).". J~
" Jc.'.l::.... ,l;;;,7v.
.....:•.. , _- ,.... ,... ff
TEST REPORT
UNIT WEIGHT OF SOIL IN~PLACE BY CORE SAMPLE
AASHTO T 233-02
CLIENT : NEOM. PROJECTNO: 21J4037
PROJECT : !'I~~l1ldesalination pl~ntto gayal transmisssi(Jll:system (LD-03) DATE SAMPLED: - 20/02}2022
SAMPLE SOURCE: TP-08 DEVTH: 1.20m DATE RECEIVED: . 22/~/2!!22_ -
SAMPLE DESCRIPTION: Brown well graded SAND with gravel. SAMPLE NO: 13-2
SAMPLED BY: RGF ......... _
ENVT. COND. TEMP. : 23.9lJC HUMIDITY: 35%
TEST STARTED DATE: 25/1/2022 TEST COMPLETED DATE: 27/1/2022
A. Mass of Dry Sample in Air (gms) 104.50
A
(13-C) - (B-A)
UNIT wr. (gmfcm3 ) E D
2.726
= 0.77 %
REMARKS:
...........
RGF-YNB-PHY-SOIL-17-00
18.08.2021 Copy Righi Reserved By RGF
RGF-YNB-PHY-SOIL-17-00
18.08.2021 Copy Right Reserved By RGF
f An Enl Comp<>ny
~lf)
,\?~,
~
Uk."
., . t --
'--"~........---
t -- ~-'UI ~ ,~- -to .~
RIYADH GEOTECHNIOUE & FOUNDATIONS CO_
•.-1/. ;"0 'r--::.r:."-....--
-~;~ '-" _:/' ~
J·.o. Do.)( :'10271.. V.1Oobu .l\1.Si.n;;.lya ....~ MVA... . "'loot), KSA ·riE"I~,..hlMl.e~
-.966 (;I.") a:.>.S-oc>'!):? J 3::!SO,!)"~::J Faw.: '~)66 (14) 3:;lS()!)4fi l:m'3.iI! '6'·yaont;,.,ll@~r'al!':oI"~~len("t!'ifo.c:om
lll'C"allon: Al·""il\Ni.HlaIH' StrC'~l~ 1"'\ AI·M",han tlbl,.k;I. H..C" Yat"obu AI-!.lI\:'lly"h
DETERMINATION No. 2 3
G-r x W~.
G.\. = . AVERAGE SPECIFIC GRAVITY (G s) : 2.694
w,\ + W. - W 2
PROJECT: Neom desalination plant to gayal transmisssion system.(LD-03) DATE SAMPLED: 16.01.2022
SAMPLE SOURCE: TP NO -02 Depth : 1.20m DATE RECEIVED: 22.01.2022
SAMPLE DESCRIPYION: Greyish Brown well graded SAND with clay & gravel.
ENVT. CONDo TEMP: 24.1°C HUMIDITY: 35% SAMPLE NO.: 8-2
-------
TEST STARTED DATE: 26.01.2022 TEST COMPLETED DATE: 28.01.2022
DETERMINATION No. 1 2 3
B-3 A-2
GT 0.99705 0.99730
RGF ·YNB-PHY-SOIL-10-04
01.08.2021 Copy Rights Reserved By RGF
f An En. Company
DETERMINATION No. 2 3
1<-1 K-2
W1 362.5 363.4
W2 396.1 396.2
5-1 S-3
RGF·YNB·PHY ·SOIL·l0·04
01.0B.2021 Copy Rights Reserved By RGF
CL:-L.:.-U/~~~if~..,J'~
RIYADH GEOTECHNICUE 8< FOUNDATIONS CO.
P.D, no;( 30;17.1:" V4r>b\.t,N~S'''~l>jah. MYAS S'1()QO" KSA. ·rfi"ephOlW:~ .966 (1") 37;S-1l"l:l97, I ;1i'7.~t)tn~ FM'~ .~'bti i-S4l :l;)S()\)4in F"'llo0l1h taf,y;1;nhu~~tlat'!o1.Clf.'n,j;'If'$..("OIn
tuc~dotl~ /!ll-N"_"fUUUJ S1.r('-et.. N<l1 AI-Mah.... bt~tri.::". H.C., Y:IIofibU A1' -5In,"I)'4'''
DETERMINATION No. 1 2 3
T 25.0 24.0
Z-2 Z-4
B 17.9 18.3
RGF·YNB·PHY·SOIL·l0·04
01,08.2021 Copy Rights Reserved By RGF
/U.f I •• ,• •~' .Aj. ~U II~"·.-/
f·,O.
f AnERlcompony
OOX3()271~ V"""bu..l\,.~i""'~lya,h.
~~
< -
"i'~J""J' vx:~
MVAS 5:UlC)O. KSh
~
TIF:J~ptlj:'n.e!
.,. • •
~~~
I·· 1·-
DETERMINATION No. 1 2 3
G
.<;
-
G T x w,<; AVERAGE SPECIFIC GRAVITY (G s) : 2.699
w,<; +~ -W2
RGF-YNB-PHY·SOIL-10·04
01.08.2021 Copy Rights Reserved By RGF
CLA..;./LJI, ~Y1Y j~)f~
All En. Company RIYADH GEOTECHNIOUE & FOUNDATIONS co.
P.O. no:.: 3021l~ V..m bo AhSh)~1'i"h. MVA'S s:t()f)(). ~SA Te-l(ophone: ,..966 (14) :l'SQ9!)'l/ ,3250093 I'rzl<! *966 (14) ~!i09tl6 FrwaiJ! r8t"y:.nhu@NIge(»clen~s.c.nm
l<KaUM: Id~N:;wamU'~d su~t. .~, Al-Mahah O;$bltt. 1\.C., Y",nbv Al-Sinaly,a"
TRIAL NO. 3 4 5
WATER ADDED 6% 8% 10%
WT. SOIL + MOULD (WET) 6142 6148 6125
WEIGHT OF WET SOIL 1980.0 1986.0 1963.0
WET DENSITY 2.122 2.128 2.103
CAN NO. A-7 B-4 B-8
WT. SOIL + CAN (WET) 438.90 435.26 440.39
WT. SOIL + CAN (DRY) gms 411.33 415.88 406.35 403.55
WT.OFWATER gms 8.27 15.22 23.02 28.91 36.84
WT. OF CAN gms 38.74 37.65 38.78 41.40
WT. OF DRY SOIL gms 372.6 379.7 377.1 365.0
WATER CONTENT % 2.22 4.01 6.10 7.92
DRY DENSITY gm/cc 1.90 1.95 2.00 1.97
2.02
I·
. ..
\
u
J2
E
OJ 1.96 / \
Remarks: Method "8" is used
CM.D.D =2.
>
l-
Ui
z
w 1.94 I \
I
0
CO.M.C :=:4.95 % >
0::
0
1.92
\
Tested by: M.IRFAN
J ~
-----
Checked K\IJ'Il<=>V,,,,.\M&;>t1 1.90
Saeed Akhtar
1.88 .......
3 5 7 9 11
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
~f)
~
v Cl:..,i.•:../{J/~~AJ'0)f~
- " -
AnERlcomPl'IlY 'l1i1.t~ u•• ~ RIYADH GEOTECHNJOUE & fOUNDATIONS CO.
P.O. nox 3:0271; 'flH.OO AI~5In~ly;i)h.. MYJ\S 51000, J{SA Tt:Jeoph(l1)e~ +966 (14) 3250992/3250993 fj:)x: ~9f:in (14) a:.tS0946 t::rna!l: t81~yanhu!@!!tlgeru.dtm«:,s,oort\
loc~Uoot AJ·W;)w;an~nd SHe!}!, Hal Al·Manan OMrt~ n.(", Yi}nbu A1,Sln.:dyah
TRIAL NO. 1 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 6015 6095 6195 6205 6178
WEIGHT OF WET SOIL gms 1853.0 1933.0 2033.0 2043.0 2016.0
WET DENSITY gmfcc 1.986 2.071 2.178 2.189 2.160
CAN NO. K-1 5-4 F-7 G-5 J-5
WT. SOIL + CAN (WET) gms 415.33 429.56 446.50 434.27 437.89
WT. SOIL + CAN (DRY) gms 408.33 416.48 422.77 403.28 401.88
WT.OFWATER gms 7.00 13.0 30.99 36.01
WT.OFCAN gms 36.32 37.54 40.55 41.88
WT. OF DRY SOIL gms 372.0 378.9 362.7 360.0
TER CONTENT % 1.88 3.45 6.22 8.54 10.00
RY DENSITY gmfcc 1.95 2.00 2.05 2.02 1.96
2.08
(I
Saeed Akhtar
1.94
o 2 4 6 8 10 12
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
~1f). ~ 'c.,Ll,::./(jI~~~~~)j~
AnER.company ~J'i'')"~' ~ •• ~ RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
P.O. HOl( 302:71.. YlU)bti AJ.S!n;'Y-lh, MYI\S 51000, KSI' Tl:!le-phone: -t966 (14) 32S0992/32S(}l)93 FalC: -1-966 (14) 3250946 Em'alJ! '81"'Y"'l'lbU@r!f~.a.e()!.dl!nft!l!i,ct}m
lo(·~\lj)fI; AI·NilW,ijnand Stfccf-l H-iJl.A~-MO:lhan Dj~\,kl. n.(,~ Yanbu A1-S1"aly~h
TRIAL NO. 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 5932 5995 6095 6098 6075
WEIGHT OF WET SOIL gms 1770.0 1833.0 1933.0 1936.0 1913.0
WET DENSITY gm/cc 1.897 1.964 2.071 2.074 2.050
1.96
II
Li
>
t:: 1.90 \
I/
(f)
z
w
0
>a: 1.88 \
Tested by:
------
M.IRFAN
0
1.86
\ 'W
Checked By/Reviewed By:
Saeed Akhtar
I
1.84
2 3 4 5 6 7 8 9 10 11 12
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
F· YNB-PHY-SOIL-03·04
~~~C~l;/Ul.:.; :;;;&J-'t;:')I~
:::An:.:::E=R=I:"'::'::::':~~===~;;d RIYADH GEOTECHNIOUe & FOUNDATIONS CO.
P.O. B()~ 30211.0 V,afiW AI,sh,;tY.1lh, MYAS 51000, KSA rt!l~phol'W~ ,,956 (1.,) .3.25099',l /32S0093 fn~! +966 (14) 3250946 k:math t8t"'Y.lHjb-U@~,lgeMt:lt!nc~s,com
lut'aUun; A)·N\Jwilnaod Stn:!ct,. Hill AJ...Mana-n {)h\\'kt~ f\,C"1 YfJnuu At~$JNIy~h
TRIAL NO. 1 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 10455 10657 10855 10862 10785
WEIGHT OF WET SOIL gms 4224.0 4426.0 4624.0 4631.0
WET DENSITY gm/cc 2.002 2.098 2.191 2.195
2.08
'1 2 3 4 5
D % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) 10S68 10762 10963 10978 10926
WEIGHT OF WET SOIL 4531.0 4732.0 4747.0 4695.0
WET DENSITY 2.147 2.243 2.250 2.225
2.14 ,
...
V ~
11
g, 2.08 I \
Remarks: Method"C' is used
CM.D.D =2.20glcc
>
!:::
(f)
z 2.06
w
I \\
Co.M.C =5.10 %
0
>
tr:
0
2.04
! 1\
Saeed Akhtar
2.00
2 3 45678 9 10 11
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
F-YNB-PHY-SOIL-03-04
:..::.An:..::.E=R=B::.=::.:.::.:.:!...J=;====~ RIYADH GEOTECHNJQUE & FOUNDATIONS CO.
P.O. Box 302"11, V,anbu AV~ln;ty.)h.. MVA'1 51000# !\~A lehtpttotll!'r -l966 (14) 9250992!32,SO<J9;3 F:u! ·,.966 (14) 3250946 [rnJill: l'a'''yl'lnhu«pet;8eo1d(':J)~J,rom
Loc"Hon.A)·N\lWanand Sb'~e-~ Hill AHI'Jl)nilt'+ OfstfKl.t A.(:,. Y~nbu At-$lfl.>:lty~h
TRIAL NO. 1 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 10572 10766 10972 10978 10926
WET SOIL gms 4341.0 4535.0 4741.0 4747.0 4695.0
WET DENSITY gm/cc 2.057 2.250 2.2.25
CAN NO. M-10 K-11 K-15
WT. SOIL + CAN (WET) gms 416.58 436.55 437.65
WT. SOIL + CAN (DRY) gms 409.52 406.35 403.28
WT.OFWATER gms 7.06 30.20 4.37
WT.OFCAN gms 39.20 41.22 41.15
WT. OF DRY SOIL gms 370.3 365.1 362.1
TER CONTENT % 1. 91 8.27 9.49
DENSITY gm/cc 2.02 2.08 2.03
2.14 ,---r---r-:--
~
!5, 2.08 +---I---+---fl'---f----I---+--t-:E--+---+---j
Remarks: Method HC' is used >
!:::
if)
TRIAL NO. 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 5975 6055 6142 6148 6135
WEIGHT OF WET SOIL gms 1813.0 1893.0 1980.0 1986.0 1973.0
WET DENSITY 1.943 2.028 2.122 2.128 2.114
(AN NO. P-10 P-10 B·2
WT. SOIL + CAN (WET) 444.60 435.26 438.99
WT. SOIL + CAN (DRY) gms 416.57 418.36 402.55 398.90
WT.OFWATER gms 11.21 17.05 26.24 32.71 40.09
WT. OF (AN gms 41.55 41.30 39.55 4 43.25
WT. OF DRY SOIL gms 369.2 375.3 378.8 3 355.7
WATER CONTENT % 3.04 4.54 6.93 9.09 11.27
DRY DENSITY gm/cc 1.89 1.94 1.98 1.95 1.90
2.00
/'
- .... - ~ ~
MAX. DRY DENSITY gm/cc: 1.98 1.98 .
OPT. MOISTURE CONTENT % : 6.93
1.96 I "'\
\ ----
~
0
E 1.94
OJ
j r\
Remarks: Method "A" is used >
I
17)
z
w 1.92
! \
0
>
IY
0
1.90 I \
Tested by:
Checked By/Reviewed By:
M.IRFAN
1.88
V
Saeed Akhtar
1.86
2 3 4 5 6 7 8 9 10 11 12
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
YNB-PHY -SOIL-03-04
,l.O( Pox 30271. VAJthu AS~Sifl~iY~ih) MYA~ ~:1()OOJ )(SA l~h·phoof.': ·~9GCl (14) "3~'sn<j"')21 ))250903 fMeI HHi6 (:1.4) 3:l!iO!Jt1fj f:.'fY1:i:tih r"f~yi),nhuq;rff.Jlet:u.cl(,1'1cc~.Cortl
Luro!1tlr>lH A!·n~p'l'Y.M'''iH'\d f;t/~d.lIlAI AI MlIhnn Ob\rlelJ n,c;'-I- Yunbu AI iHfli.lIVilh
1 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 5962 6035 6115 6120 6115
WEIGHT OF WET SOIL gms 1800.0 1873.0 1953.0 1958.0 1953.0
WET DENSITY gm/cc 1.929 2.007 2.093 2.098 2.093
CAN NO. P-10 B-10 B-9 K-5 B-8
WT. SOIL + CAN (WET) gms 423.56 433.65 435.68
WT. SOIL + CAN (DRY) gms 411.26 415.68 401.29 395.68
WT.OFWATER gms 12.30 27.57 32.36 40.00
WT.OFCAN gms 40.33 37.85 40.32 43.25
WT. OF DRY SOIL gms 370.9 377.8 361.0 35
WATER CONTENT % 3.32 5.03 7.30 8.96 11.
DRY DENSITY gm!cc 1.87 1.91 1.95 1.93
o
.!2
~ 1.92 -f--t----lc----r+--t---t---t---rr-t-----j-_;
>f
Remarks: Method "A" is used U)
CM.D.D t5 1.90 +--1----1--1-+-
o
C.O.M.C=6.25% >
0::
o
1.88
TRIAL NO. 1 2 3 5
WATER ADDED % 4% 6% 10%
WT. SOIL + MOULD (WET) gms 6195 6178
ET SOIL gms 2033.0 2016.0
gmlcc .071 2.178 2.160
CAN NO. K-1 $-4 F-7 J-5
WT. SOIL + CAN (WET) gms 415.33 429.56 446.50 434.27 437.89
WT. SOIL + CAN (DRY) gms 408.33 416.48 422.77 403.28 401.88
WT.OFWATER gms 7.00 13.08 23.73 30.99 36.01
WT.OFCAN gms 36.32 37.54 41.20 40.55 41.88
WT. OF DRY SOIL gms 372.0 381.6 362.7 360.0
WATER CONTENT % 1.88 6.22 8.54 10.00
DRY DENSITY gm/cc 1.95 2.05 2.02 1.96
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-3) DATE SAMPLED: 15/01/2022
--------1
SAMPLE SOURCE: TP: 01 DEPTH: 0.60 m DATE RECEIVED:
~~~~~--~--- --------1
SAMPLE DESCRIPTION: Grayiesh Brown Well graded SAND with silt & gravel. SAMPLE NO.:
SAMPLED BY: RGF
----------~~~--------------------------
ENVT. CONDo TEMP. 24.8°C HUMIDITY: 38%
----------~~~~
DATE STARTED: 26-01-22 DATE COMPLETED: 30/01/2022
900
.:
Penitration Bearing .. .--'
800
.....--' ~
in value Ratio
(in) (Ibs) (lb/inL' (Cor.CBR) N 700
.:: V
~ 600
Ql
:::l 500
/
>
ra
400 / AT 0.2"
OJ
c:
·c
ra
300
/'
Ql
Ol
200
,,/ AT 0.1"
100 /
0 /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
0.5000 271 823
2.14 glee CBR @ 90 % Compaction at 0.1" 27
C.OMC = 4.95 % CBR @ 90 % Compaction at 0.2" 32
TESTED BY: M.ARFAN CHECKED BY/REVIEWED BY: Saeed Akhtar
----------~~~-------- --------------------
RGF· YNB·PHY·SOIL·05-04
01.08.2021
Cl;.A.;/(JI,;~ ·;;;~ifL;?~I~
P.O. _
f "'ERI""....
lUDdnn~
.RjYADH GEOTECHNIQUE & FOUNDATIONS CO.
3(j)1>., l'>nbu AI.SIt••ly.h" ",VAS S1000. j(!;N. ltI,\pho",,; c.~ Ii"} l~5®92 / l2sOO;,,· fiOO >1)G.G (14) 31S01l46 em.lI, l1It,y.llbl.I!>..llI"""*imcoHum
t\.l..H.1W;UUrul !1.Jr~i!L UM At.Mab.'m nlli1rkt.. nC.;Votllno A'",~tt;:tlvlih .
CfJn2
---
1200
Bearing 11UU
value Ratio 1000
(in) (lb/in L
)
(Cor.CBR) ~
900 ~
'"c ~
g 800
/'
(II
700
:J
;;; 600
V
>
0) 500
./
t::
';:
<tI
400 1/ AT 0.2"
(II /v
aJ 300
200 /" AT 0.1"
100 /
o /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
CBR @ 95 % at 0.1" = 36
CBR @ 95 % at 0.2" =
CBR"]
1400
.....
Bcaring
..---'
RatIo 1200
~'.
(Cor.CBR) N-
c
~
1000
~
/
Q) 800
/
~
iii
......
V
>
OJ 600 / AT 0,2"
c
.;:
(IS
Q) 400
/
/
OJ AT 0.1"
200
0 V
0.0 0.1 0.2 0,3 0.4 0.5
Penetration (in)
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
PROJECT:
------------------------------------------
Neom desalination plant to gayal transmisssion system.(LD-3) DATE SAMPLED: 1 5/01/2022
SAMPLE SOURCE: TP: DEPTH: 0.60m DATE RECEIVED: 22/01/2022
=-:-:-:
SAMPLE DESCRIPTION: Grayiesh Brown Well graded SAND with silt 8: gravel. SAMPLE NO.: B·1
ENVT. CONDo TEMP. 24.8°C HUMADITY: 38%
---------------
DATE STARTED: 26-01-22 DATE COMPLETED: 30/0112022
2.10
PENETRATION AT: 0.1"
1.95 t-~---+--~"--+----'--,-_+---'---,--+_----_t---'-'--_t
RGF- YNB-PHY-SOIL-05·04
01.08.2021 Copy Rights Reserved By RG F
t::A•.:_l.:....--{1I~ ~~ J' ,-:?.-J I ~
RIYADH EiEOTECHNIQUE& FOUNDATIONS co.
P.O. Dux 3()2"'1~.v<lf\t;ru N'Sll\;tY"~ MY,I\S Sl000~ K~ _1:~~~P!1~~! .. ~~ (11t)·3~~0992:i32Mm93 r-a)t~ WU6 (i4) ;l~5()l.)46 EiMU;: f3f·Y.)'f'lbu~~'t$c~ie-fiCe""~Orn
L<KMk>m AH._Mt)M,$\,,,i;\, Hlil Al'M~"'" Ol>l<kt, 11,(" nhb" ;l.HiIn.lVah
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system.(W-3) DATE SAMPLED: 15/0112022
SAMPLE SOURCE: TP: 1 DEPTH: 0.60m DATE RECEIVED: 22/0112022
SAMPLE DESCRIPTION: Grayiesh Brown Well graded SAND with silt & gravel. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 24.8°( HUMADlTY: 38%
DATE STARTED: 26-01-22 DATE COMPLETED: 3010112022
-----------------
2.10
PENETRATION AT: 0.2"
1.95
RGF· YNB·PHY-SOIL·05·04
01,08,2021 Copy Rights Reserved By RGF
Cl;,l.;../uJ,~:0' J"~.)I~
An ERI Company RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
p,1'>. no;.< :wnl, Y.II"" Al,1il<~I~.h, MvM ;,;,OO<),,~ l~"'f'!"m'l'~ (14) 8~:k)99' I )~""'9ill' ....,+%(0 .!I.~) )~~OO4« f:mlll: r~'."I';"l>u@>CII~.",<I.M.""H"
\«.;t.f!)iii AH'u:~~~'~t'tc-t, tf~J Ai.:M·~b1irtJJt)V'Rt. ~A ",,,,I\t,1ij N·~.J(\MY~h
C8R,/
1000 .........
in Ratio
900 I~-~ .....
...
.----'
800
N I.·:·.:····.· V
(Cor.CBR) c
:a 700
. I .
~
- 600
'-'/-"
~
~,
Q)
::J
C\i 500 "
>
OJ 400 /
c
.;:
'" 300 /
/ ATO.1"
Q)
III
200
100 /
0
V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
Remarks:
~~~-~~-~----~~~~~~---~~----77-------------
CBR-2
1400
Bearing 1300
value Ratio 1200 ;
.--'
(lb/inL) 1100
(in) (Lbs.) (Cor.CBR) N
1000 ~
.!:
::a 900
~
Q) 800 ..-'
::l
'itj 700 /
> 600 /'
OJ
t:
.;: 500 / AT 0.2"
'"
Q) 400 /'
!O
300 ./ 'T n ....
200 ./
100
,/
0 /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
DATE SAMPLED:
---------1
0.60 m DATE RECEIVED:
--------------~
SAMPLE NO.:
HUMIDITY: 43%
----
26-01-22 DATE COMPLETED: 30/0112022
Mould No.: A-8 6363 ---------------- Volume: 2115 cc
1600
Bearing
1400
value Ratio
(in) (Lbs) (Ib/in" (Cor.CBR) 1200
1000
OJ
.aro 800 '
>
0)
c:
.;:: 600
ro
()J
III 400
200
0
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
Remarks:
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
------
--------------------------------------------
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-3) DATE SAMPLED: 16/0112022
SAMPLE SOURCE: TP: 2 DEPTH: 0.60m DATE RECEIVED: 22/0112022
-,----,...,--,
SAMPLE DESCRIPTION: Greyish Brown Well graded SAND with clay a: gravel. SAMPLE NO.:
ENVT. CONDo TEMP. 24.2°C HUMADITY: 36%
------
-------------
DATE STARTED: 26-01·22 DATE COMPLETED: 3010112022
2.15
1.95
RGF-YNB-PHY·SOIL·05-04
01.08.2021 Copy Rights Reserved By RGF
RIYADH (iiEOTECHNIQUE & FOUNDATIONS CO.
P.O. UO)( 30'l71, VaftbO N:>sll'l~fy~h,.. MYAS 51000, KSA Tc1epOOnC! 4!'~~~ (~<1) 3?~2.i-32~3- f-;!lt-; '*:~ (1~) ::U:'5C!l~6 ftm~U! f'$t·V>lnbuQ)e-tt~MdeMe:~,f:-'0f'1'\
lOUI!!>'" AtN'lW"".nd.1>I....I. H~I A1cM.>n.n 1:>1,,,kt; lI.e" y .... b .. "'~SlMIV.h
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. (LO-3) DATE SAMPLED: 16/01/2022
SAMPLE SOURCE: TP: 2 DEPTH: 0.60m DATE RECEIVED: 22/01/2022
SAMPLE DESCRIPTION: Greyish Brown Well graded SAND with clay 8: gravel. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 24.2 QC HUMADITY: 36%
DATE STARTED: 26-01-22 DATE COMPLETED: 30/01/2022
-----------------
2.15
PENETRATION AT: 0.2"
2.10
CBR at 100% of MOD: 55
2.05
CBR at 95% of MOD: 44
1.95
RGF-YNB·PHY-SOIL·05-04
01.08.2021 Copy Rights Reserved By RGF
f An Eft. Compony
. . t:':..1••:--l.;./V I, ~A l/l:?~ I~
RIYADH G€OT€:CHNiaUE & FOUNDATIONS CO.
~ :.
CBR-'
450
....
Penitration ng 400
~
....c......
in value Ratio
(lb/in L N 350
(in) (Ibs) (Cor.CBR)
/
'
.5
~ 300
Q)
/v
250
.=!
>
co
200
V
Cl
t:
·c 150 / AT 0.2"
co
Q)
OJ
100
V
50
/ AT 0.1"
0 /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
0.5000 132 401
Remarks: C.MDD = 1. 96 g/ee on at 12
------~~-~----------~----------------------
C.OMC = 6.24 % CBR @ 90 % Compaction at 0.2" 14
TESTED BY: M.IRFAN CHECKED BY/REVIEWED BY: Saeed Akhtar
-------------- ---------------
RGF- YNB-PHY-SOIL-05-04
01.08.2021 APPROVED BY: c~shtiJiQ1ie)j'6'fRtF
----~~~------~--------
CI..:-l;;./V l ,=.::
RI'fADHGEOTECHNIQUe & FOUNDATJONS CO.
'A~~4?~I~
-An ERI ComJ>ilhy-
P. 0. t'Qx3Q271. n,...bU N SIMf)'e-h.. HAY.~,SlO~.~'ArtW~ ru. No. -"'%-f;.,-l"'-J~!>09'!):\!I3, r{t.'\{~. +'!1(ithtiH~2SQ$<iI.~~ C",:lnblH tQr",:'$nlJu~,a*'l-oo.~~,mm
~kin: ~'~~~d~r~,.-klld !'l'Mifo~:~~,!~" .UP.~~ ~;<; :tjil):..u~~~~~ f.<:~
CBR-2
700
i i
Penitration Bearing
600
Ratio
(in) (Cor.CBR)
500
.....-' ~
Q) 400
V
>
::l
'iii
Cl
300
/
c:
.;:
III
Q)
OJ
200 / AT 0.2"
100 / AT 0.1"
V 0,4
0.1 0.2 0,3 0.5
Penetration (in)
CBR@ 95% 18
CBR@ 95% 21
TESTED BY: M.IRFAN CHECKED BY/REVIEWED BY: Saeed Akhta r
----------~~---------- -----------------------
RGF- YNB-PHY·SOIL·05·04
01.08.2021
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-03) DATE SAMPLED:
----------------~
SAMPLE SOURCE: M-TP: 3 DEPTH: 1.20m DATE RECEIVED:
----------------~
SAMPLE DESCRIPTION: Greyish Brown well graded SAND with silt. SAMPLE NO.:
----------\
SAMPLED BY: RGF
ENVT.COND. TEMP.--------24-.-8°-C-----------H~U~M~ID~I=TY-:---3-8%-0--
DATE STARTED: 26-01-22 DATE COMPLETED: 30-01-22
Mould No.: E-4 Weight: 6365 gms. Volume: 2109 ee
800
Peni Bearing
700
I·· .. /
value Ratio ~
(lb/in LI (Cor.CBR) ;:;
c 600
...... ......
/"
'<::
@. .. ........
.....
,/
V
500
Q)
3(1:l
400
...... ...... /'
>
C'I
c
.;:: 300
..
100 / AT n 1"
0 V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
TESTED BY: M.IRFAN CHECKED BY/REVIEWED BY: _ _ _. .:S:.,: a:. ; .e. :. ,e. :. ,d. .:A:. ; .k. :. ,ht. .:a. :. ,r_ __
RGF· YNB·PHY·Sut'!1Irr:[·",05""·om4r------------------
01.08.2021 APPROVED BY: _--,-rJ.ll.l~ljL.111!lW·-'U,*=L~""ru:,-",e=h..u;SiV"",,jn,"-lJF,--_
Cl:-l;../{jl,.~
~ ~t.fU)I~
JZ.. .,.
RlYADHGEOTECHNIOUE & fOUNDATIONS CO.
0.00;< 30271. YMbu N SlnaMlh,~YAS Sl~O?~1 ~~ It'f. Ho. 't~tG-14-,)259992{3, f_&X ~' __f:~-~4>~~(;. E-m~:-f~t~'OO~~~,QYTl
LqaJlbn; IH/aI~~:u.nu Str~ t~_A1'~ Dkrtt{di UP Af~,R~ ~bu AI:'~~~ ~
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT • NEOM. PROJECT NO: 21J4037
PROJECT: Neom desalination ptant to gayat transmisssion system.(LD-~TE SAMPLED: 16/0112022
SAMPLE SOURCE: TP: 3 DEPTH: 1.20m DATE RECEIVED: 22/01/2022
SAMPLE DESCRIPTION: Greyish Brown well graded SAND with silt. SAMPLE NO.: B-2
ENVT. CONDo TEMP. 24.8°( HUMADlTY: 38%
-------
DATE STARTED: 26-01·22 DATE COMPLETED: 30-01-22
1.95
1.80 +-----+-----+-----+--'---"'---1
RGF·YNB·PHY·50IL·05·04
01.08.2021 Copy Rights Reserved By RGF
1• •,,:.,.... _CL.l...:;.,/rf/J~~v'i')J~
RIYADH GEOTECHNIQUE & f·QUNOATlONS CO.
P. o. D-»:~0271, y~ N S~iMAYM ~l.QW-$1l'IJ(ll AlWI~t :r~. ~,..4-?(>6"H'32~Q99;Ul. fW(:NQ. +~·U·l2~,~'fl;E·P\aH: m1·~~,<<>m
~~n~.AI"~~.~~~~:I-~ AJ'~~ ~~~,~~'.~Wk,~;~.~,YlVtW~~~·~., ..
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to !layal transmisssion system. (LD-03) DATE SAMPLED: 16/01/2022
SAMPLE SOURCE: TP: 3 DEPTH: 1.20m DATE RECEIVED: 22/01/2022
SAMPLE DESCRIPTION: Greyish Brown well graded SAND with silt • SAMPLE NO.: B-2
ENVT. CONDo TEMP. 24.S0C HUMADITY: 38%
DATE STARTED:
----------------
26·01·22 DATE COMPLETED: 30-01-22
----------------
1.95 +---------t---------t----i------\-~---:-
PENETRATION AT: 0.2"
1.80 +-----t---/----t-----,.-----+------,.---l
RGF· YNB-PHY-SOIL-05-04
01.08.2021 Copy Rights Reserved By RGF
-c:.,L:-t..;;:./{j I!J ~~ ~i..;?./ J~
An ERlcQm"",ny RIYADH GEOTECHNIOUe& FOUNDATIONS CO.
p,o, ac;..,.; 00271,-y~"bU N-z.lt\i:i1~h. MVA$ ~;\OO()~ KSA 1'¢1c>P:h~o-1.1J66 (1A) a:2~2j32~3 " ..lIe: ... 966 ·~1-'iJ.a-2"!00'9"'6 £~m t$,.y,;!4'11xI~tlM101,dc;I\UllJd:t)m
t.~<.l\l9!'H Al-<N.)Cwpl1",nd ~~n::.. ~ n4i: Ai·M~h~ oo,-t)'k't# 1t.~.. fin~ N~~t'la¥... h CDR.1
T-1
a 600
': .... .
<1l
.= 500
/
>
(1J
400 /
en
1::
.;:
(1J
300
V
/ AT 0.2"
<1l
OJ
200 / .... " ..
100 /"
o /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
0.5000 268 814
Remarks: C.MDD 2.18 g/cc CBR @90 % Compaction at 0.1 26
~C~.O~M~C~--~5~.~15~-7%~------~C~B~R-@~9~0~%~C~o-m~p-a-c~ti-on--at~O~.2~"~----~3~2-------------------------
TESTED BY: _ _ _ _T_V_F_A_IL_K_H_A_N____ CHECKED BY/REVIEWED BY: _____S_Q_e_ed_Ak_h_t_ar_ _ __
Awais Nisar Yasin
RGf· YNB· PHY·SOIL·05·04
01,08.2021 Copy Rights Reserved By RGF
'c:L:-l.;:./U I~ ~.0.t../ 4?..,J' ~
RIYADH GEQTECHNIOUE& FOUNDATIONS co.
P.Q. BI)It 3O:l:7,i,. YanOO l>J~'$h~lyah. MYAS_SlOOO.. JC$A. l'(;:lC\"phon&~ -J.~6"" (1:4) :;t;U>~2-'3:;,o$C~.1 .f>ttrIJ .. ?W (14) ~1!iM4(i. F.m;:),H~ T8vv,arlbU~lI'tfr~~leJ1.f_~,;.Ulm
• _ _.......:..._ . . . . " .... ~ •• "'M_~-_d .... ~~'"'. ~ .. _.- ... i·... ~ ••• ~M &,",h4~" n "'" ;'h._~.~~'~ ",J_ ••_. __ ~,
CBR-2
1600 , ,
1000 ~
V
<I>
.aro 800 /
>
Ol
t:: 600 /' V
.;;: ATO.:!"
ro
<I>
III 400 ~
200 / AT 0.1"
o V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
CBR@ 95 %
CBR @ 95 % Compaction at 0.2"
TESTED BY: TUFAIL KHAN CHECKED BY/REVIEWED BY: Saeed Akhtar
----------------------- ---------
RGF- YNB·PHY-SOll-05-04
APPROVED BY: _____..:....:...______-:-::-...;,.-,-::--_
01.08.2021
An IEBI Coml>"ny RIYADH GEOTECHNIOOE& FOUNDATIONS CO.
CBR-J
1800 , .:"':'"
I·······:··
Bearing
'1600
Ratio
(Cor.CBR) N 1400
...
.. ..... ~
.5
£1 1200
......... :.......
...............
~
<ll
::l 1000
.... ;/
V
>'" 800
..
./ ,T n?"
01
r::
'i:: 600
;/
'"
m
<ll
./ ATO.1"
400
200
/
0 /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT PROJECT NO:
NEOM.
- -21J4037
----
PROJECT: Neom desalination plant to PlayaI transmisssion system.(LD-~TE SAMPLED: 17/1/2022
SAMPLE SOURCE: TP: 4 DEPTH: 1.20 m DATE RECEIVED: 22/1/2022
SAMPLE DESCRIPTION: Greyish Brown well graded SAND with clay ft gravel. SAMPLE NO.: B-2
ENVT. CONDo TEMP. 24.1°C HUMADITY: 36%
--------
DATE STARTED: 26/01/2022 DATE COMPLETED: 30-01-22
2.15
2.00 +----+--;4---+----+--+--+---'---+....,.--:--1
RGf. YNB-PHY-SOIL-05-04
01,08,2021 Copy Rights Reserved By RGF
Cl;...~fJ 1.1 ~r.:1' c/L;?.,) I·~
RIYADH G.EOTECHNIOUE& FOUNDATIONS CO.
PA Oox tJO~7j~ Y.antru AMHn;lyi}-h. MYAs.S1000.~!.A 't.4'tlcph~:~.oj6~ i1.4)3~t.!(l9.~).1 ).l',~3-.. *-,u~ '*~~ (i'" ~:i~M46 ,t~!H J"8'.y,)ubuOCf~JJf:0'1_th~fttf'!u::.om
f.~('.. \~l"tl At.n~~~M St,.~ ~1 AU<.4...Nn Obtfkt. A~ YOtn\>\i AJ,$hl4'Wh
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
------1
PROJECT: Neom desalination plant to !Sayal transmisssion system.(W-03) DATE SAMPLED: 17/1/2022
SAMPLE SOURCE: TP: 4 DEPTH: 1.20 m DATE RECEIVED: 10-10-21
SAMPLE DESCRIPTION: Greyish Brown well graded SAND with clay a: gravel. SAMPLE NO.: -------=B-_2=----f
~--
l.UIl +--+_-f--+--'-}----jI---+-_4_--+_-,--.,_I
RGF· YNB·PHY·SOll·05·04
01.08.2021 Copy Rights Reserved By RGF
CL::-I....;:./V I-,~~ t../'-;?~ I ~
r--=::--'-"""I:l;i"'"
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-03) DATE SAMPLED: 18/1/2022
--------------~
SAMPLE SOURCE: TP: 05 DEPTH: 0.60 m DATE RECEIVED:
------~------~
SAMPLE DESCRIPTION: Greyish Brown poorly graded SAND with silt & gravel. SAMPLE NO.:
--------"'-~----~
SAMPLED BY: RGF
ENVT. CONDo TEMP. HUMIDITY: 36%
-------
DATE STARTED: 26101/2022 DATE COMPLETED: 30-01-22
Mould No: M-1 Weight: 6387 gms Volume: 2110 cc
./"
,,;/
~
600
Q)
500
..... ,"
y
:l
iii
> 400
/
0')
c
.;:
!V
300
....
/.. ATO,Z"
Q)
III
200
,/ AT n "
100 /
0 V
0,0 0.1 0,2 0,3 0.4 0,5
Penetration (in)
Remarks: C.MDD =
~C~.O~M:C==..--~~--~------~~~~~~--~~~~----..·--~----------------------
1600
Bearing
1400
value
~
Ratio
(in) (Lbs.) (Ib/in') (Cor.CBR) ;:; 1200
~
r::
£1 1000
i
(l)
;:J
iij
>
800 /
OJ
r::
.;:: 600 / AT 0.2"
<II
(l)
CO 400
/
200 / AT 0.1"
0 /
0.1 0.2 0.3 0.4 0.5
Penetration (in)
CBR@ 95 % at 0.1" = 43
CBR @ 95 % at 0.2" =
TESTED BY: TUFAIL KHAN CHECKED BYIREVIEWED BY: Saeed Akhtar
------------------------ --------------~--------
RGF· YNB· PHY·SOIL-05-04
01.08.2021
P.O', f)';:>x W::i;:J. Yll~\tm AI.sl~ijv.ah,. MY-AS. $:U>OQ.. ";$A 'fcM~()M! ~%6 (1-l) ):t~:iI ,f;J2~iJ S~t~" ,(4) ~j:S(f!M6 t:(ru\H: ,~:.v:;(;bu~Nl£~co«hm<~$ ~()m
. 1,<$C'.Mloru AI,N::wx.anand .".t~:t. H.:t5A'-M.::ttloOln Oh.fkl~ f\,t":",~ V::lAhOAh1:tu.-h,.h
PROJECT: Neom desalination plant to gayal transmisssion system. (LO-D3) DATE SAMPLED:
---------\
SAMPLE SOURCE: M-TP: 5 DEPTH: 0.60 m DATE RECEIVED:
---------\
SAMPLE DESCRIPTION: Greyish Brown poorly graded SAND with silt 8: gravel. SAMPLE NO.:
---------\
SAMPLED BY: RGF
ENVT. CONDo TEMP. 24.7°e HUMIDITY: 36%
DATE STARTED: 26/0112022 DATE COMPLETED: 30-01-22
Mould No.: M-3 Weight: 6245 gms. Volume: 2106 cc
1800
Bearing
1600
value Ratio
(lb/inL' (Cor.CBR) N 1400
.!:
;e 1200
Cl>
::l 1000
til
> 800
OJ
t:
.;::
til
600
Cl>
III
400
200
0
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
Remarks:
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
PROJECT:
---------------------------------------
Neom desalination plant to sayal transmisssion system.(LD-~TE SAMPLED: 18/112022
SAMPLE SOURCE: TP: 5 DEPTH: 0.60 m DATE RECEIVED: 221112022
SAMPLE DESCRIPTION: Greyish Brown graded SAND with silt & gravel. SAMPLE NO.:
-----------
ENVT. CONDo TEMP. 24.7°C HUMADITY: 36%
-------------
DATE STARTED: 26/0112022 DATE COMPLETED: 30-01-22
2.15
2.00 +-----+-:_--+---~f----___l----__+--,___+----_l
RGF- YNB-PHY-SOIL-05-04
01.08.2021 Copy Rights Reserved By RGF
Q1t> V 'CL:-L.;....--tJ/~ ~&ify-"'j.~
AnERlcomvany ~~, v... RIYADH GEOTECHNIOUE & FOUNDATIONS CO_
'>,O.-IMlM 3{)27.1~ Vilnbo At.-!.I~ly':'h. MYAS-:'!;j.OOO, }o;SA 'fe~ephb"(Ol: ~'966 (1t1.}a:7l.50992/<U~9':)3 f'~lo +966 (.1.., 32~~6 Ilm-all: Jfl"y,.,nblJ@'e,.lg(ODKfl."",c:e",I:'O~
l,~Ol'to.r.: AI.N;;aw;;ah:ahd:5h_t. H,3,~ At-MotH;." okVI~1~ R..c;,... Y.anl,l~ Aj·$inzr,ly.Nl
TEST REPORT
.
C.B.R. - DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-03) DATE SAMPLED: 18/1/2022
SAMPLE SOURCE: TP: 5 DEPTH: 0.60 m DATE RECEIVED: 10-10-21
SAMPLE DESCRIPTION: Greyish Brown poorly graded SAND with silt & gravel. SAMPLE NO.: B-1
.
,."~ ..-~~.~.~.~.~--,~~,,~-~~.-,,-~",,-~-,--~~~-,~~~.~~-.---~~~
' / ~ .....
. i I
I
2.15
, ...
/' PENETRATION AT: 0.2"
2.10
...•
./
/ .•.........
/
.
2.00
V
/
1.95 . ~- -~---,
- ~- .. ~-
---" "-_ .. ~ . ~--. .S.~--T ~~~~~
RGF-YNB-PHY-SOIL-05'04
01.08.2021 Copy Rights Reserved By RGF
Gl:A_::./UI,~~c.J'l?)I~
An ERlcompony RIYADH GEOTECHNIQUe & FOUNDATIONS CO.
~.o, n<»< Jon!, YonbIJ ru'51.;ly.i~ MYAS.SlllOO,~SA Tv-I.pllOt,,,, ~ 114) J1"W!1~ 13l~;) f~'" .'t>lI!idI1l1m.6 ,molll 'eI"I'""bIJ~"I~""IC/l<...tO!l\
l<K~lJQ/I'A~N_....n<l $"'"", Hal AIM,b... ()Iud(\, M';Yonoo Al·Slt\.ltm . CBR·/
Bearing 900
-
..
----
in value Ratio .....
800 ........
(lb/in'J
(in) (Ibs) (Cor.CBR) '"'c
~
a 700
V
600
.. ........ /
~
Q)
co 500
/
>
Cl 400 /'
c
·c
co
Q)
300 /' . AT 0:2"
III
200
;/'
100 / '" u.
0
/'
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
0.5000 286 868
Remarks:
ctJR·2
1600
Penitration Bearing Bearing 1500
1400
.
value Ratio ----'
1300
(in) (Lbs.) (lb/inL) (Cor.CBR) ~
'"t: 1200
~
1100
~ 1000 7/~
(]j 900
:::l
"iii 800
> 700 /' AT 0.2"
Cl
t: 600 ?If
"
<1l 500 / u.
(]j
CO 400 /
300 /'
200 Ji
100 III
a /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
CBR @ 95 % 48
C.OMC = CBR @ 95 %Compaction at 0.2" =
CilR-3
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-3) DATE SAMPLED:
--------------~
SAMPLE SOURCE: M-TP: 6 DEPTH: 0.60 m DATE RECEIVED:
--------------~
SAMPLE DESCRIPTION: Greyish Brown poorly graded SAND with silt a: gravel. SAMPLE NO.:
-~---~-~~-----------~------- --------i
SAMPLED BY: RGF
ENVT. CONDo TEMP.
-------------------------------------------
24.6°( HUMIDITY: 38%
DATE STARTED: 26-01-22 DATE COMPLETED: 3010112022
Mould No.: A-6
-----------------
Weight: 6429 Volume: 2114 cc
~
(Cor.CBR) N'
c
;a 1400
1200
..
~
Q)
::l
..
V
(1) 1000 /"
> ATO.2" ...
OJ
c 800 /
.;: ,/'
til
Q) 600
/
...
CO AT 0.1"
400
/
..
200
0
V
0,0 0.1 0.2 0,3 0,4 0.5
Penetration (in)
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
-----------
-------------------------------------------
PROJECT: Neom desalination plant to !layal transmisssion system. (LD-3) DATE SAMPLED: 19/0112022
SAMPLE SOURCE: TP: 6 DEPTH: 0.60 m DATE RECEIVED: 22/0112022
SAMPLE DESCRIPTIOr-. Greyish Brown poorly graded SAND with silt & gravel. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 24.6°( HUMADITY: 38%
DATE STARTED: 26-01-22 DATE COMPLETED: 30/01/2022
2.20 -t----+----+----t-----t----I-'----'--f--'----'--t-'-----t-:,4--+'-,-'--,--j
2.00
RGF- YNB-PHY-SOIL-05·04
01.08.2021 Copy Rights Reserved By RGF
Cl;..A•.,;;~/U/~ ~~ if~.) I~
RIYADH eEOTECHNIQUe& FOUNDATIONS CO.
P';'Q" (l.())I' 3(')2'1~-".. ,.,bll At~S.Il\i;i'i","h~ MYM StJXID, ':-$1\ T~f~h()fi.jJ! 4-~6 fIJi) 3~rHl9!)21 a:l,~0093. ra~~ ~56 (1~} _'250tMtJ:. E:~th t~(~y,A"'bH(@~'l&~'I'm«$~~)i'n
t.t~K:,3t~j"1 A'J'NMY';M"''»lh11}U't;''.cl.. H~j At"M,»h~.fi ()h.t.ft(,;t~ n~("... vanbu J\j4tJMlY:~h
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to $layal transmisssion system. (LD-3) DATE SAMPLED: 19/0112022
SAMPLE SOURCE: TP: 6 DEPTH: 0.60 m DATE RECEIVED: 22/01/2022
SAMPLE DESCRIPTION: Greyish Brown poorly graded SAND with silt & gravel. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 24.6"C HUMADITY: 38%
DATE STARTED: 26·01-22 DATE COMPLETED: 30/01/2022
------------------
2.1 0 +-'-----+----,-+----!----!--.,...,.7f"----!----!--'--!-.,---!--'-'-'_1
CBR at 95% of MDO: 54
2.00 +----b"'-----!-.,---,-!----!-.,..---!----!----!----!-~-!--,--'_1
RGF-YNB-PHY-SOll-05-04
01.08.2021 Copy Rights Reserved By RGF
~~GL-L;./Uf, ~.0',yY)'~
An ERICoI1'lJ)liYlY RIYADH GEOTECHN IQUE & FOUNDATIONS CO.
PA:bc, :ron1, v.1\l)"Al~l"'I~ MYM51(l(l(l, l(,$A 1.I.jlh<>",n.!lfi6{l>1) $1~~ 13l~3 fa" *,,<;6 (14) 31509<6 ("""" 'Sr·y"nbtllJ>ll'Ils• ."tl.,,,,",,,,,,n,
1<><41\""" N·Naw....r><l Sl,m,lnl AIM'~'~ 'P!>I'",l.1\,G... roob~AI.sJ"'ly.h
CBR-l
Bearing
in value Ratio 500
(Ib/inkl (Cor.CBR)
N
.5
~ 400
Q)
-=>ro 300
Ol
t:
'1: 200
ro
Q)
III
100
0
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
Remarks:
~~~~~--~~~~~~r---17------------
TESTED BY: CHECKED BY/REVIEWED BY: _ _ _-=5::. .:Q.:. .:e. . :.e. . :.d. :.A. :.k. . :.h: . .:ta.:. .:r_ __
------------
RGF· YNS·PHY·SOIL-05-04
01.08.2021
~t> ~.t:A..;A..;:../(JI!J ~&t./~)I~
Ar>EHlcQmPllDY ~. . v ... RIYADH GEOTECHNIQ\.JE& FOUNDATJONSCO.
(;BR·2
900
' .
• •
Bearing 800 •
value Ratio
(Ib/in<) (Cor.CBR) 700
~
N'
t: ,
§, 600
(\)
~,
:::l
500
ro
> 400 /
Ol
t:
~
.;:
300 /'
ro AT 0.2"
(\)
III
200
/
100 / AT 0.1"
a V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
CBR-3
1000
Bearing 900
Ratio
800
(Cor.CBR) N
t:
700
f!
(l)
600
.:::ro 500
>
OJ 400
c:
.;:
ro 300
(l)
CO
200
100
0
0,0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
Remarks:
rON~~~~-------n~~~~~~--~--------
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
---------------------------------------- ----------
PROJECT: Neom desalination plant to !Jayal transmisssion system.(LD-~TE SAMPLED: 20/0112022
SAMPLE SOURCE: TP: 7 DEPTH: 0.60 m DATE RECEIVED: 22/01/2022
SAMPLE DESCRIPTION: Brown poorly graded SAND. SAMPLE NO.:
ENVT. CONDo TEMP. 24.3°C HUMADITY: 37%
--------------
DATE STARTED: 26-01-22 DATE COMPLETED: 30-01-22
1.95
PENETRATION AT: 0.1"
LBO +-'------f~
RGF· YNB·PHY-SOIL·05·04
01.08.2021 Copy Rjghts Reserved By RGF
~f) , CG~(J/~~~ify.)l~
An ERlcomP""Y ~~:s "..... RIYADH G.EOTeCHNIQUE & FOUNDATIONS CO.
P¥O~ Box 30271, 'f.umu lU4il~~~hi MVAS 51000. KSA 'T~1~ph(jtnc!: ,t-?66 {:101)'3':1'SO<I:j92,(3:l.51)99;) r-¥'i~1.f1)~ tlll} ::J250!;~G l"-'n-aUHgt~YM'!'buOt'fI~t;t:6W:.kol!e"',(,(')m
10<:;:;tft»U ..·~J·Naw;lr\aM $tt~~«Ji ~J. ArM,)h~h b~~1:tkt£ ft.(v:Y.3nbu AIN$thilJy-iloh .
TEST REPORT
C.S.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
PROJECT:
------------------------------------------
Neom desalination plant to gayal transmisssion system. (LD-03) DATE SAMPLED: 20/01/2022
SAMPLE SOURCE: TP: 7 DEPTH: 0.60 m DATE RECEIVED: 22/0112022
SAMPLE DESCRIPTION: Brown poorly graded SAND. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 24.3°( HUMADlTY: 37%
DATE STARTED: 26"01-22 DATE COMPLETED:
-----------------
30-01-22
1.95 +--'------t-'----:---i-------+--;£--.---+----:-"--i
PENETRATION AT: 0.2"
1.80 +---___---;1'--___----1-------+-------+--------\
RGF-YNB-PHY-SOIL-OS-04
01.08.2021 Copy Rights Reserved By RGF
Gl.::.-VUi, ~~ di..:?)I~
An ERI Cfl!np.iny RIYADH GEOTECHNIQUE & fOUNDATIONS CO.
P,O. ~•• !mH.$. v."w AI.$li,;'ry'n.MYJ.$ SlOOO. ~ Telo""""", .~ll (14) 315ilil!>2/l25ili1!» , ...., .gllG 1~')"l~Q~'(; tmMI' r~f"f'''bu~'''l(I;i _ _''',t<l1l1
1.()('"tfQ:t'l~ ~.N~V1.f\3ruJ ~ttCt't.lfa1 Al·M_fl~n ~tf~ R'(~I 'f;fnfxl4!·$H~flh .
COR·'
PROJECT: Neom desalination plant to gaya/ transmisssion system.(LD-03) DATE SAMPLED: 2010112022
-------------~
SAMPLE SOURCE; TP: 08 DEPTH: 0.80 m DATE RECEIVED:
---=-----:---- ------------~
SAMPLE DESCRIPTION: Brown well graded SAND with silt & gravel. SAMPLE NO.:
SAMPLED BY: RGF
-----~~~-------------
ENVT. CONDo TEMP. HUMIDITY: 36%
DATE STARTED: 26-01-22 30-01-22
Mould No: Weight: 6441 gms Volume: 2102 cc
700 ...
.........
600 ....
(Cor.CBR)
N
c
......
/
7"
g 500
.....
/
Q) 400
/ ..
:J
<tI
> 300
/'
/
/
OJ
c
·c AT 0.2"
....
<tI
Q) 200
m
100 / AT 0.1"
0 / ..
CBR-2
1000 i .
Penitration Bearing 900
value Ratio I /"
800
(Ib/in') ;::;
c: 700 /
~
600 /
1:1>
.2
<1l 500 /
>
OJ
c:
400
/
'':
<1l
1:1> 300
/ AT 0.2"
aJ
200 /' V
100
/ AT 0.1"
0 /'
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
CBR @ 95 %
CBR @ 95 % at 0.1" =
TESTED BY: WISAL KHAN CHECKED BY/REVIEWED BY:
------------------------ ------------------------
RGF-YNB-PHY-SOll-05-04
01.08.2021 APPROVEDBY: __~c~~~~'~s~=~=~~e~~~~t~~~F_____
Cl:.-l.:;../V 1, ~r.:YJ't?~ J~
An ERI Company RIYADH GEOTECHNIQUE & FOUNOATJONSCO.
I',~, ""'. \\O'.n, 'f".""A\.Slnt.ly.li,. MVAS SfOO(" X<A r_Ioj>ht»w' +'>6<)('4) ~,~, I al~j f.x: .~\'i(il!.) ;)lS(J94/i ~m.U, Ig(,y.nbulV"IG<t»tlen"'Hom
. uM Sb~tID Ulil M.-M;ilull ()lstrkt~lt('"" Y:iinl>ltAi..stnalv"h
ttICAUOQt A\..Nltw.u
caR-J
1100
Bearing 1000
value Ratio 900
(Lbs) (lb/in LI (Cor.CBR) N
c: 800
~
100
(l)
::J 600
to
> 500
OJ
c: 400
';::
to
(l)
aJ
300
200
100
0
0.0 0,1 0.2 0.3 0.4 0.5
Penetration (in)
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-mTE SAMPLED: 20101/2022
SAMPLE SOURCE: TP: 8 DEPTH: 0.80 m DATE RECEIVED: 22/01/2021
SAMPLE DESCRIPTION: Brown well graded SAND with silt £i: gravel. SAMPLE NO.: B-2
ENVT. CONDo TEMP. 23.3°( HUMADITY: 36%
--------
DATE STARTED: 26·01-22 DATE COMPLETED: 30-01-22
2.00
1.85 +_----+------,'~_+---_I----+_---_1
RGF· YNB·PHY·SOIL·05·04
01.08.2021 Copy Rights Reserved By RGF
~---"""" Cl::-(..;../V I!J ~& c./~.) f~
.:.2:.-=::"~=:::!:::::!...!=:ii~==~ RIYADH GEOTECHf\UaUE & FOUNDATIONS CO..
p~o~ U~)( 3027.1. V,'u\bU Ai,Slnc-;IV.l-h, MYA$ Sl(:)()O. KSA T¢t-tl<f"h"fi~! ·-.966 (1") 3~S099'?, /3:250993 F;'iIII! +9G.6 (14j :t2:~()!)"6 £~Urfl:l;f·vW\bt'(getf,s~l»C.l~",«lM
lO<ii-Hom AJ.t4a-w~n~j\d Sltec\.- '~~I J\1,M~h'"lfl J)f1-ltkl, A.C•• V.t)f1bti ~-Sjfl~Jv~n
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. (LO-03) DATE SAMPLED: 2010112022
SAMPLE SOURCE: TP: 8 DEPTH: 0.80 m DATE RECEIVED: 22/0112021
SAMPLE DESCRIPTION: Brown well graded SAND with silt a gravel. SAMPLE NO.: B-2
"_~A~~,~~_~v~~~" •• ~_,~~_~~~"w~<.~._"q~'_'_"'~d""'''_="~V _'''~"_"'_
1.85+-------:---7"+------11------+---------1
RGF·YNB·PHY-SOIL-05-04
01.08.2021 Copy Rights Reserved By RGF
r--=~.~-'''c.,L:-l.;../(jI~~~~~~I~
P~O. Q(>II'
f . _EOlcompony
:"O:t1i f Y,J,hlW iU-Slt..;"Y.lh. MYA5 Sl-.ooQ.. t<SA
RIYADH GEOTECHNIOUE& FOUNDATIONS CO.
.... ~l90f)b(>f.);):i ...9.6"6(1"')32SOW2/:l:l'W993 "~.9" (14,32:50046 cl\,~m fO'-'Y.$ot'\l",,*~fa~~J¥:'H;.~.. ,t«:u·~
s."O<.,~li>lll "'\>.N"'W~T.~'H. ~~n:rio:l .. UiH 1\'·M~h;w, 't»*k1~ «.C'" V;:in~ hf'S¥l~I't,)h CBR-l
--.~----------~
SAMPLED BY: RGF
-----------------------------------------
HUMIDITY: 35%
07-02-22 DATE COMPLETED: 11-02-22
Mould No: B-10
Bearing 800
in value Ratio
(lb/in LI 700
(in) (Ibs) (Cor.CBR) C:
8 600
<l)
::s 500
iii
> 400
O'l
s:::
...
til
300
<l)
m 200
Remarks:
~~~-- ..~~--~--------~~~~~~------~~------~-----------------------
CBR-2
PROJECT: Neom desalination plant to gaya/ transmisssion system. (LD-3) DATE SAMPLED:
---------------4
SAMPLE SOURCE: TP: 9 DEPTH: 0.30 m DATE RECEIVED:
---------------;
SAMPLE DESCRIPTION: Brown Poorly graded SAND with Silt & gravel. SAMPLE NO.:
SAMPLED BY: RGF
ENVT. CONDo TEMP. HUMIDITY: 35%
DATE STARTED: -0-7--0-2--2-2--D-A--T=-E-C--O-MPLETED: 11-02-22
Mould No: B-11 Weight: 6320 gms. Volume: 2109 cc
1600
C1!
Q)
OJ 400 /
200 / AT 0.1"
o V
0.0 0.1 0.2 0,3 0.4 0.5
Penetration (in)
CBR @ 95 %
4. CBR @ 95 % at 0.2"
TESTED BY: TUFAIL KHAN CHECKED BY/REVIEWED BY: Saeed Akhtar
------------------------ -----------------------
RGF- YNB-PHY·SOIL-05-04
01.08,2021
c...l::-l.;./vl~~&ifv~'~
RIVADH GEOTECHNIOUE 8< FOUNDATIONS CO.
CBR';]
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-3) DATE SAMPLED:
----------------~
SOURCE: M-TP: 9 DEPTH: 0.30 m DATE RECEIVED:
-----------1
SAMPLE DESCRIPTION: Brown Poorly graded SAND with Silt 6: gravel. SAMPLE NO.:
----------1
SAMPLED BY: RGF
------------------------
ENVT. CONDo TEMP. 24. 5°C HUMIDITY: 35%
DATE STARTED: 07-02-22 DATE COMPLETED: 11-02-22
----------
Mould No.: B-12 Weight: 6368 gms. Volume: 2106 cc
1800
Peni Bearing Bearing 1600
value Ratio
(in) (Lbs) (Ib/in" 1400
(Cor.CBR) '"c:
:a 1200
(lJ
::l 1000
<ii
> 800
C!
c:
.;:
<tI
600
(lJ
OJ
400
200
0
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. {LD-VATE SAMPLED: 22/112022
SAMPLE SOURCE: TP: 9 DEPTH: 0.30 m DATE RECEIVED: 02-03-22
SAMPLE DESCRIPTION: Brown Poorly graded SAND with Silt ft gravel. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 24.5 DC HUMADITY: 35%
------
-------
DATE STARTED: 07·02-22 DATE COMPLETED: 11·02-22
1.95 +-----':~--'--I------I---+---I----l--'---I--'-----",
RGF·YNB·PHY· SOIL-05-04
01.08.2021 Copy Rights Reserved By RGF
P.o. tlmt~O~'1i~ Ym\WA],SIrn.IV"-th., MYAS_5:t,()OO~ l(,SA Y~l¢phonez"'9(\.~{14!a'~):l1 !I_~5-I)o&;j. t:'lot,/sX ~.,U (14) :l2SW.l4a (ttU!I~ T6r,Y.l_T'ltru~cr1u-c~ec".(¢m
'- ~...lfQ.l"!i AhN,*~~)fi4 $t,{t~. »:,.i MM,,'~t) Qht,kt,. ~,~~ Vht.b-V AI~St;\4t';''*t;
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
------f
PROJECT: Neom desalination plant to sayal transmisssion system. (LD-3) DATE SAMPLED: 22/112022
SAMPLE SOURCE: TP: 9 DEPTH: 0.30 m DATE RECEIVED: 10-10-21
--::-:---1
SAMPLE DESCRIPTION: Brown Poorly graded SAND with Silt & gravel. SAMPLE NO.: B-1
--~~-'-"-'---'-'~~"-"--"'---~~~" ------I
ENVT. CONDo TEMP. 24.5°C HUMADITY: 35%
DATE STARTED: 07-02-22 DATE COMPLETED:
----------
11-02-22
2.05 ~--'-t-"...---+---:Io''-'---,-f----li-----'--+--+---I---I
CBR at 95% of MDD: 42
2.00 ~-+--'--',4--'---+-'---,-f---c------If---+--+---I---I
CBR at 90% of MDD: 28
1.95 ~--Jf-,-t--+--+---,-f----li--+--+---t---I
RGF- YNB-PHY-SOIL-05-04
01,08,2021 Copy Rights Reservecl By RGF
Moisture Content, Particle Size Distribution,
Atterberg Limits, Proctor Test and CBR Test
LAYDOWN No. 5
RGF-YNB-PHY·SOIL-15-02
01.082021 Copy Right Resrved by RGF
-c:.-L:-~U I ~ ~~
- -' J:' L::->-'
I
RIVADH GEOTECHNIOUE & FOUNDATIONS CO •
....."0. UO)f :JO.;!';7:t., "rUt'.lbH AJ,Sfh;ly:\')h. ""'I'YI\$ .s::u)()O" Y.SA "f"ti"h~'phon~~ .. 9C.6 (:1«\) a"2~\92;1 325099:., I'';:'>:! .. ?6G (:14) :l2!!.0946 L,nall, t6hynnbH(n}<t'r/;S).t:!'<>"dcn~<l~,f:o"",
..... 'I<;..rH A~·:N.uv"'l"1!~r~d
1.~....,,· ~U->r.-~t .. tt~l A}_N'l .. n~)(\ [~'''f1''>t·t. f,L<. .• y.a ... ~"".". AI-$1n~\V~h
RGF-YNB-PHY-SOIL-15-02
01082021 Copy Right Resrved by RGF
'c~)
;;,,~ ---:-~-- or - t .' I --
V ............ "'---- ----
J U-' J
.,
'
'-'
;,:.- ~ I f
_:/'"
;:r::
~
.. ~
"
An Eft. Com.",ny I "f.'W.:cm'[Zj""""""""""""""""""""""" -----------------------
RIVADH GEOTECHNIOUE & FOUNDATIONS CO.
I"'.O~ no)t .1,0;,.."'. Yrud:rU A¥~Slt'\;.IY .. h. ¥\1YAS 5:'1000" KSA T~flZ-phone: +--9<iG 4:11').} 32S0-t'D2 I 32:s.o-o-9>:a «(l'f-yanbu@>E!'h3.*Q'\-c·Cr.c..:;".con')
,~><a'~nn! .A1-Naw-nnand .$l1"t:f(':t". J-Hd "'l:~tvI:':'I\';'1' AI.'$·ln....ly ..h
RGF-YNB-PHY -SOIL·15,02
01.08.2021 Copy Right Resrved by RGF
.. ~c..-L:.-L.::.---UJ~~;;Y j f~
AnLIi!ll!l1Company l·~·=,?:J~ ~I RIYADH GEOTECHNIClUE & FOUNDATIONS CO.
P.O. nO>l :;)0:;<'7:1. V;:;tobU IM,~'J'\al"''''h. ",1Y.....S S:lVOO", K.l!'A )'''')ocl-,"'OhOnb: .!1)6-06 (::t4} a25Q>:.}92" 326-0990 .....>:: +966 (:t4) ~:'?!~OY'''''' Lr",..1li,·: fUt~Y};H\b'YIK9'''''10!e'O:•.;;:JC:i'. .:::<-'LCOrr;
L ...... ~tfoot AJ·Nd.....,)lO.<1ond S1:£~ ... I. H~\l At_~ .. h.,.t\ Oht.. k,l. ft><:-,~ V"'H~.. q nd.$ln.......... h
S-4
A-6
RGF·YNB·PHY·SOIL·15·02
01.08.2021 Copy Right Resrved by RGF
r-=:~___" 1...::...-L::-~() I.!' :: ,. • .-:;~ t-? l::?-' I ~
AnERD RIVADH GEOTECHNIOUE & FOUNDATIONS CO_
p"Q~ UO)O( :AU27'1.. Y"nbH 1·\J.S'n;'ly~h. MYA:!: S;t.OOO~ )(SA l"4<l"lC'otH)ne: .966 (:14' a~s.o99:t /30?:S<>!>!l'3 '-at_y4)nbu!jJ><bI'J.~~c.:t.eiet'>coe:s_<ol'Vll
"\()'i:'.;o.Hnrnt A'~Nllvv.anand 5U·~tH. 1-~~; A)~M,lh~n AJ.!:.-ln.<H\"ah
0
ENVT. COND TEMP 23.8 C HUMIDITY: 35%
Test Started Date 09.01.2022 Test Completed Date: 11.01.2022
--------
NO: S-5
D-8
185.45
587.15
R CONTENT (%) 4.75
RGF- YNB-PHY-SOIL-15-02
01082021 Copy Right Resrved by RGF
.......-=~-~"-c::...L:::...-~U I~ ~~ t.../~./
... I - --
~"_wm~~~... .-ny I .~.~~.~.~......~I RIYADH GECYTECHNIClUE & FOUNDATIONS CO.
1".0. lh:;J)o( 30~7;1,. 'V~~t»J N'!Ht\';'lV~h. l'...t'Vh~' S:1(.)()O", y..5A Tcle-phone-: t-l!>G-i& (:14) a2".so,"-~!:):a /325.0993 r:'X; .... 9(;.6 (:14) .<J:Z::'0!.146 l'.'i'V'<ai':: r~'~yahbuWoet'l:€'io¢"o-~!(\lt)C;~$.<::UtV1o
i.()o(',.'Hfon, A]·Nil........-an.;arH1 5u'''''l''t~ "tal A'-~<'lh.-.n Ohhi:ct. it.C.• Y~nbu AI.5t,~"' ....ah
RGF-YNB-PHY·SOIL·15-02
01082021 Copy Right Resrved by RGF
P.O_ no)ol 30~7:1. Y:.robu Al,S;:,...;ly;th. MVAS S3.000~ KSft -reJcphon-e::;. .966 (:1~) 3;;[$0992 /325-0!)93 f.';;a)(; +966 (:14) 32~!»16 ~:.I'n:loi'~ "O'vY.i>r.bU((poC~'ge<!o~'-e_'.<:.-e:~.CO.-n
• 1.~,.""tk>o~ftl-N~l\IV.i.ln.."nd
$.tr.".ot>t. H",I.At-Miih"'1\ I),~);t,k.t. 1~,oC .• v-",ihu 1\1-$.ch.....llV .. h
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
r:~IV'-
V
~ID ~ "'--'-----
I .., I .. ~u-' /a - W -~.
../ .- -11,'-"~L:;/
- ~;~ _::.r"Ij
An Eft. Company ~'. U"." ... RIVADH GEOTECHNIClUE & FOUNDATIONS co.
f'~O, 110>0 ::J.o;r71.. Yllo.'!obu AJ,Sinaly-::.h, r-.>lVAS s.-;1000~ KSA Tcl;;>phonct j ;;l.~~:::J J':l<>I; 4:',).66 (1-1) 37:.09"'6 r,.n~5:lIl1! t'n'..y:<ulbu@«!'}B<V'<>.\Ci~'''<:'I!:'',iCOJ'Vo
ft;·N;\W';;,¥n~",.~(J t""" ,AI-M..h ...n Dhhk.\, ,,,,<:'.. V ...nbu Ai-S,Jn...,l:y."h
S-2
CAN NO: B-2
WT. OF SAMPLE + CAN (WET) (gms) 815.35
WT. OF SAMPLE + CAN (DRY) (gms) 797.60
OF WATER (gms) 17.75
180.55
. OF DRY SAMPLE (gms) 617.05
R CONTENT (%) 2.88
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
•
RGF-YNB-PHY-SOIL-15·02
01.08.2021 Copy Right Resrved by RGF
1"_0. uo~ :',JO~71. Yal!')bti .AJ".sir'\;lY~h. ·r",'JYAS 5:1000", Y.SA T~J.e-f.hone~ .966 (.1 .... ) ::J.2S0992 I ~~2sor~93 I;~)(~ .91:'".61.14) :l.:1'509.'1u £,,rn~iJ: ..n ....yar'\b\J@.!fi.B'I'!'o~c;en"'e".(.·ol'n
l.tH: ..Hfon;..A..I-No:t..,..,HU.<lod $.U·~""f. H;~I Al-M;;Jh.'H rJOi\fl't;.I. f·C("•.• "Y;~nb .. A.1-$:;n..\.V",h
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
An ERB Company
4<"''?>-
~M-J
-r::t.l t.:::...- L:...- ~ U
'l!'.!;o.!'!:J'
"
u'.~' RIVADH GEOTECHNIClUE & F OUNDAT10NS CO •
I!, j L.;:./...,)
••
f~
.... o~ Oo~ ;lO.~7:l.. Y.anb-u At>~Hr.;,y;;oh. f...'YAS :;;;tOOO~ .K5A T«:!o2" •."ho.r.-e; ... -;66 (:ttl} a2.~)U:l 132~.J93 F"'x~ -f-V(>6 (:t4} 3l:::'09<46 f.',,-....,a.t: l'Jat"""ln.. bulYYe.d~~.::.:s,c'.cn<-..,;.eQm
1.. .....c~ •• k;.n:.A.I-N>k ......~n~at~d Sb·~AAi;. Hi,... Al-M<'lh~n ol".ftct:, R.C.~ 'Yllnb\~ AJ~~Ht\AffY' ... I~
NO: 5-5
M-2
RGF-YNB-PHY-SOIL-15-02
01,08,2021 Copy Right Resrved by RGF
Ii!1
, -i~·"'-c.....L-L::...-VI~~~J-"l?~I~
AnERlcomp~ny I '''''''''';WJ' ~I RIVADH GEOTECHNIClUE & FOUNDATIONS CO.
P,G. ~1Q.l<I ;';\10;0"7;1" Y"''''h1''I\J~!:;rn.;i')lah. :-'!)Y"""", !.>:l.OOO~ KSA TiH<!ophon~: .. 966 {::1"}3:2'S-O:,-t92 / 32SO~1)a. I'll-X:: 4>966 {:t4} llJ~~)4'4:> l<:w.,.,H: rHf~y#nlb1..uXft"Hh'J*o~lc;~<.:.,,:t,COI'n
L'O<..atioo~ Al-N,;.t"""Hu~nd $l£"I'c,(t. t-...,.1 AJ~I!V1·..h""n 01",1,-1('1", fcc,. Y>lHUU AI· ")1e>-:'l.y","h
LE NO: S·6
M-7
OF SAMPLE + CAN (WET) (gms) 750.45
OF SAMPLE + CAN (DRY) (gms) 722.55
OF WATER (gms) 27.90
. OF CAN (gms) 188.45
WT. OF DRY SAMPLE (gms) 534.10
WATER CONTENT (%) 5.22
0
ENVT. COND TEMP 23.8 C HUMIDITY: 35%
Test Started Date 09.01.2022 Test Completed Date: 11.01.2022
-------
RGF -YNB·PHY·SOIL·15·02
01.08.2021 Copy Right Resrved by RGF
1..:- L:::-l..:::...--U J" ~~
..... ... -' I ~
_.. t../-" c..:;..,
RIVADH GEOTECHNIClUE & FOUNDATIONS CO.
f.'A':':>. OQ,>f. 30~7:t.. v""..,bu AlA~;n;'Yi:lh. ,VI'VAS 5.1000" Y.;5A F~x! ."356 ~.:l.4' 3:t!,~OY.J\C. l,h'oa'!: l"f..yiU'b'Jtrtt.:t'.:l.>il"(';.'\.,;\e.~i:'¢~.<:o""",
...
r.lh.'~·~t;"l. f-t~<" yit .... h~~ Aj·&~n.<.tv~h
NO: S-l
K-9
OF SAMPLE + CAN (WET) (gms) 827.10
OF SAMPLE + CAN (DRY) (gms) 808.70
OF WATER (gms) 18.40
. OF CAN (gms) 180.50
628.20
R CONTENT (%) 2.93
RGF·YNB·PHY·SOIL·15-02
01.08.2021 Copy Right Resrved by RGF
~
AnES. Company
" r~~'"
(,g'ID
,~~~,},
-
v ..........
U","
L:- L:::--- UI ~ ---
RIVADH GEOTECHNIGUE & FOUNDATIONS CO_
Go • ~~~ ~ ~
'-:;;"--y ,. ~ j ::.e..::---
P.o. 00)01 30.2:7:1, '(.:lnbu M.s,r.;.y.,h. -ll,I)YI\S !'>.l.OOO... YOS"'" TeJe-phon-e: +966 (:l<1) ;)..25-0992 / 32:5-01"",)93 f;-.)(! +9i"~b (:14) ~2:;,-o9.-\b Lr,",,:..il~ "n'vyat'>b'l."(V!Ct'g~c>~i-e,_'• ..:el.cc..;·y.
t. •.x-:.<,tfon:.
A.I'-NiWW"~_n.i\"d 5u-"~oI:"t •.H~i .A)-M ... h .. ~, l)tI;U~~;l. R.C.• V.anbu A-l-Slor""t..... h
CAN NO : M-18
RGF- YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
"c-L::--L::.---U I~ ~~ J:'~~ f ~
An EB! Com.,..ny " ~F-ll RIVADH GEOTECHNIClUE & FOUNDATIONS CO.
P.o.. no).4 :J0;'';'71, .... :.~bo N,-Sr,...,::'I'Y;,h. MYA~; !:>1;::xx::t~tL"iA 'I:'I-.!:-phOf">f!ol to~G.& (.,.4) ;:t;;1,$0092 /32509'93 f'~x: 491SoG (.\4) Sl-=tS0946 E,r.... ;1I.iJ: 'n'-y~t'ob'UI1':t't::t4\~t..$~i~hO(~~.C:O>'1l'.
l..oc.·"H'c.. n!.~~-N>kw""H\J1>~H~ $t:n:;lI.J't. Hi~i ft\~h>1+<h;;on. otlott'k,lt. f(,C•• v..,nbu AI·Si.\..\l>fV~h
,...o~ uo~ 30~.7:1. 'i~~bH AJ'S'r.;lY~h. MYAS ~::lU-OO~ KSA ,.-:-~::I~:}·l~~;-~~~~~~~~~~~~~~:;~~~~~~a~!n iJ~::t.::,:~~,~~:~~,:\~.~t~~!~~.~:.~i~:~~l: "nf·,y:u'bu«P"'~6p'.~c,.~.:.i"'''-,(;.¢"c<:)rf...
RGF-YNB-PHY-SOIL-1S-02
01.08.2021 Copy Right Resrved by RGF
-c.:...- L.:::.-l..:::.--- UI.i' ~ j~~l~
RIVADH GEOTECHNICtUE & FOUNDATIONS CO.
(1."0. n6>t ;:.)02:7:1. YIH"lbu Af'!'iin~l'Y;i'h. ""VA-"> :0.;1.000" $':5;\ -n""ephonc-::: +966> (1'1) 37"""0'992" :'J.25U993 r~t~·ar.bu«t>~~tg~~I~H'i<:'¢=!.f:O.Nl!
t.<r><~.fQn:. Al_N;,k .......\I·},..nd ~U,<,;,,~f .....lnl Al~fYlaha-;n Ai .. ~'n-.'lyah
SAMPLE NO : $-6
CAN NO: D-30
WT. OF SAMPLE + CAN (WET) (gms) 785.40
WT. OF SAMPLE + CAN (DRY) (gms) 755.80
WT. OF WATER (gms) 29.60
WT. OF CAN (gms) 175.45
WT. OF DRY SAMPLE (gms) 580.35
WATER CONTENT (%) 5.10
RGF-YNB-PHY-SOI1.-15-02
01.08.2021 Copy Right Resrved by RGF
~~--r_ _-n "'" -
~'---'~.
I.· I -- ~U.f I ..
".;.><. ~-..... ~ L/l2-'I~
An " .... " "",,,,,,,, ...y L.""_w",. =. RIYADH GEOTECHNIOUE & FOUNDATIONS C<:>_
P.(.,). Ho>c ;')001'7;1. V:'l"Ibti AkSit.;'lY~h. MYA:';'; ::'1A:.tOC>, KSA Tel",phon..,.: ~S\66 (;1,0) 3"2SO'<_"92 1325O""'~)<3 '€nt~Y"'l'\l..UllV*">e eo;\.;i,:;~.,>c::-e:s .cort"',o
,(x"Hk>f'l1 ,A).N;k......~'n ..\rHt 51T~o(Io"t~ cHat .AI· M<th;1,H Af--Mt>-..tYdf.
RGF-YNB-PHY-SOIL-15-02
01082021 Copy Right Resrved by RGF
~~---""..- I I -- ~u-' I:J _- Go • ~. "~,~~ ~ :/"I j ::r: .~------
>;1'.~""'J' Q',A>
>,"' - ,>
L'>wf!'.
~M) ~
_ "'---' -.......--.-- - - ~~-,;
_ - ~
0
ENVT. COND TEMP 23.8 C HUMIDITY: 35%
Test Started Date 09.01.2022 Test Completed Date: 11.01.2022
-------
RGF-YNB-PHY-SOIL-15-02
01082021 Copy Right Resrved by RGF
\" :."
~+.
(;if> [:;r'-L-~UI , , _ +~ _+_~~-'I::.r~
" ++ + -.---- +
v ~ -,-»
}!J _" ++
NO: S-3
XP-9
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy Right Resrved by RGF
~=~~1 "f - ~l...:::..-I
-- ~
-- ~U-' J..
,., -"'AA
____
~~ ~l:?~I~
ERI RIVADH GEOTECHNIClUE & FOUNDATIONS CO_
1".0.001'1' 30;t7"1.. 'Y:.,."lH" A*~-5Ir>;1')'''h. l\.'lVA.."<;' 5'10<)0. KSA TbJQ~hVfWi>i. +96t> '::11) l1ZSQ'!J9:t I 325-0:993 ... {I'~-yanh'.H!p e~ 'o:Jot.,;:.",.:;'e.~<:-""" ,COt\")
,,",.,<,;),k>n! N-Nn""""..Hl,aod StJ"\'!... t. t'k>l A}.M.. h·...\ A'~Sif\..\~IV ... h
0
ENVT. COND TEMP 23.8 C HUMIDITY: 35%
Test Started Date 09.01.2022 Test Completed Date: 11.01.2022
-------
LE NO: S-4
M-33
OF SAMPLE + CAN (WET) (gms) 805.40
WT. OF SAMPLE + CAN (DRY) (gms) 791.00
WT. OF WATER (gms) 14.40
WT. OF CAN (gms) 210.45
WT. OF DRY SAMPLE (gms) 580.55
WATER CONTENT (%) 2.48
RGF -YNB-PHY-SOll-15-02
01082021 Copy Right Resrved by RGF
L~"""D~:I
~M' ~ "c:--L::-l..::----'U J~ ~~
- _- t../" c:-~
I~
An Eftl C<.>mF><'ny "f.~~J' u~.~> RIVADH GEOTECHNIGUE & FOUNDATIONS CO_
HO>l 30:,r},:1, Ylllnbi.~ N_S'r-;'1,,>,3h. !\.>'!YAS !:.:1OOO. Y.5A Tt2'Je-phon-e~ +966 (:l"1) 32"::>"09921 ;g,2S-tY~931 "'.3,X~ +966 (:14) :'j~::-;.o9.tl6. E:t'~ .... iI; 'O'vYZll"lb'-I@,o:ntf.to!':'c.~Ctel''';::.~$,(:(>Fr''''
"Ot:~ufo~nA'_Na......-;:>n .. nd $U·...,.~H. H;.,I.I\,J-tvl;:oh<'lH rJi:;I;.t:rk.l. R,.c., Y.:anbu At-S~n.">.v .. h
RGF-YNB-PHY-SOIL-1S-02
01.08.2021 Copy Right Resrved by RGF
r-=CT-:7~ c..,l..::-t...:::.-U 1.1' ~~ i f ~-' j - -+ .......
RGF- YNB-PHY-SOll-15-02
01_08_2021 Copy Right Resrved by RGF
I ~".• ,~~:c;:- "1 ~ L:.- L::.----- UIi' :: G. • .-:.:,,;~ t.../' '-::?-' I ~
An !!COl\! C<>mp."y I '~.!:!I'':'Il'';' l.::;;lj!!E='1 RiYADH GEOTECHNIOUE & F DUNDATIONS CO.
I :;l250!)93 F;t>o:: +966 1.1.4) 32:!>0t7Ac;. Eih\aH,~ w-·(,hy~htJi..l@c'inco~d-c-'-'~'¢:$,.t'<'>f'I')
t.4\1 AI-~ •• h""in t)tliH I.::\,. il.C.• Ylt'u"\bu FU~S-fn.:,~iV:;Jh
0
ENVT. COND TEMP 24.3 C HUMIDITY: 40%
Test Started Date 23.01.2022 Test Completed Date: 25.01.2022
-------
SAMPLE NO:
RGF- YNB-PHY-SOIL-1S-02
01.082021 Copy Right Resrved by RGF
~if)
'~ ~~
v ....'---""
-
""---".......--
I -' I -' ~u-' I...
" ' ;:,~
_ Y'Ij::r::::""'~
1..../ ~
An ER! company~' UO_A' RIVADH GEOTECHNIOUE & FOUNDATIONS CO.
P.O. Oo)t :»0;;'7:1., .... )1,..,bi.~ AI •.!*.n.~lYUh. MYAS .5:1000. KSA TE"J.ephoHt"': ..966 (::t4}a2:>09s);Z / n:ZS0993 fnt~y1>nb>Jtf;><4:l"'~~c.;),~;~<')t..c" .com
L ......··•• t~un~ N_N.a_~u~ .. nd $~r<o';"",~r, .ti>;\1 A\·rvtah..n AI-">fn';'lly,a'.
SAMPLE NO :
SAMPLE NO :
CAN NO : B-10
WT. OF SAMPLE + CAN (WET) (gms) 388.40
WT. OF SAMPLE + CAN (DRY) (gms) 382.70
OF WATER (gms) 5.70
46.52
WT. OF DRY SAMPLE (gms) 336.18
CONTENT (%) 1.70
0
ENVT. COND TEMP 24.3 C HUMIDITY: 40%
SAMPLE NO:
CAN NO : 8-9
Wf. OF SAMPLE + CAN (WET) (gms) 403.50
4.40
58.04
341.06
RGF- YNB-PHY-SOll-15-02
01.08.2021 Copy Right Resrved by RGF
~-~...~
~?~I v "'--' -.....-..-------- ~ .!'J ~
",- I - w • -~-
•.• .,y
I
.; ~~ 1....--'__
_.-- ~Ul 'I:::J_ ••'"
::...- ,PI --, ----- ~
SAMPLE NO:
RGF-YNB-PHY-SOIL-15-02
01.08.2021 Copy RighI Resrved by RGF
i~---'.'-~...,.
C:,'0"'-
~~I
~ I......--' I____
-
... I - - -t)
............-
.I
I -' _...
_ .~.
-~...
r ,&"1
_-
- .'
'-" '--'"
.',
...,...,
_r-".
'1'::::1_-""-/
::.....--
0
ENVT. COt-.1D TEMP 24.3 C HUMIDITY: 40%
Test Sta rted Date 23.01.2022 Test Completed Date: 25.01.2022
-------
SAMPLE NO:
RGf- YNB-PHY·SOIL-15·02
01082021 Copy RighI Resrved by RGF
\
rq f ~
EnI
r_'·';;:;""""··""'····"I"',·::;A.;.A_;•._CIIJ' ,";::
I ~:.
, ".,"~_1
C~
~ CR 11l10tM~8(~
I.""""W C"""","y' c..,,,", '.000,000
lim....
CD",~n_~__ !..~~;;;;;;;,.~,o,,~~;:~.e RIYADH GEOTECHNIOUe 8< F OUNOATIONS CO.
"p.. , J'" .r' > i .. P'-- .... ,)-. ....' "
:...:;v~ ~ ,-:?..,),~
s.~ ~", ~"
'"l"'\"".A~ ~~ <J-
P.O. Box 9182. jedd,'h 21413, KSA Telephone: +966 (12) 6715621 / 6176860 fax: +966 (12) 6715426 Em,1il: rgf,wp@erigeosciences.com
Loccltion: Gclrn~lthcl St. nedl' Arbcleen St. intersection, ivlllsilre(clh District, Jeddah
TEST REPORT
PARTICLE SIZE DISTRIBUTION (GRADATION) OF SOILSUSING SlEVEANALYSIS
ASTM -D69131D6913M-17
CLIENT : ~!~0IY!_<;:ompany -----~-
PROJECT NO, :
-~---------------
21J4037
PROJECT : NEOM Desalination Plant to Gayal Transntission System
SAMPLE SOURCE: LD-5( TP-01 REPORT DATE : 29.01.2022
SAMPLING DATE: - TEST START DATE : 18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE : 20.11.2022
o
SAMPLED BY: - ENV. CONDITION TEMP. : 24.0 C HUMIDITY : 47%
BOREHOLE NO. : LD-S / Tl'- 0] DEPTH (m): 0.60 SAMPLE NO. : B-1
SAMPLE DESCRIPTION: Brown, well-greded SAND with silt & gravel.
3" CanNa. : SM
2112" 00.0 0.0 100 wt. (Soil + Call) Wet (gm.) : 3772.0
2" 00.0 0.0 100 Wt. (Soil + Call) DIy (gm) 3638.7
-----
I1h" 00.0 0.0 100 Wl. Water (gm.) : 133.3
3/4" 324.2 9.8 90 Wt.Can(gll1.) 314.2
--_._-- _ .
# 20 -_.
2434.3 73.2 27 (ASTM D3282-09fD2487-10)
--. ._-----------
# 40 2824.2 85.0 15 A-I-a/SW-SM
# 60 2967.7 89.3 11 Dry WI. of soil before washing
----
# 100 3054.0 91.9 8
--_.._.._------
= 3324.5
------
100
90
~. .. .cc' ."., -
J: .~ .
Ol
'a;
80 .... .• ,' ,.'<".:~':~'. - " .,: --.
" ." . .
~
"
70 . , :··· ... i,:~ ... . , : : .
.D 60 ~., .
..·C.· ,:
c
Ol -
50 --.
'iii
Ul
'"
40
..
"
n.
C 30 ~'"
,~
'"
I! 20
--. ,~
'"
n. 10 -.
o 1 I' F 1 1
100.00 10.00 1,00 0.10 0.01
Grain-size in Millimeters
REMARKS:
---- .---------------~----- --_._- .. " - - - - - - -- - ------------- - - - - - - ------------------.- .... _._ -.
--- --- -- - ---_._-_._-- ---._. ---_. __. --_.-- ._- _......... - --_._-- ... - . -- .. ----_. __ .._- .
APPROVED BY:
............... ------ --- ---- -'
(I.ab.lncharge)
Cop.\'right of this d(ll'unH'nl is owned by HCr, itlllclY not be reprlltitll"pd e\n'pt with prim writtell 111'rrnissioll from tilt' cOIllIMIlY,
HGI'-jEj)·I'IIY·SOIL·01·03
20.01.2020
\
tq f ~_
ERR
Cnm....ny
r~"~':'-'~'~"""-']
,
A
•
-(;L'<..
1:;A_:..-L.:---- til" ,::: .-:;.~;~ c./~.",J I ~
o;;f,;;?
.
I§~~ ~1., Lmood.l3abiJilyConl,umyJCnpil.nI6.000.000S.J~
CR)-010160-200
co.
P.O. Box 9182, Jedd<lh 21413,](sA Telephone: +966 Cl2) 671562'1 / 6'176860 Fax: +966 Cl2) 6715426 E"1<1il: rgf-wp@erigeoS<.-iences.col11
Location: Gr1rnnthrl St. neclT Arbaeell St. intersection, Mushrefah District, Jeddclh
TEST REPORT
PARTI CLE SIZE DISTRI BUTION (GRADATION) OF SOl LSUSING SIEVE ANALYSIS
ASTM -D69131D6913M-17
CLIENT .NEOM Company.. PROJECT N O ' _ .. ~~I~()3!__ .~
PROJECT NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5/ TP - 01 REPORT DATE 29.01.2022
SAMPLING DATE: TEST START DATE 18.01.2022
SAMPLE RECEIVING DATE: TEST FINISH DATE 20.11.2022
SAMPLED BY : ENV. CONDITION TEMP. : 24.0 °c HUMIDITY 47%
BOREHOLE NO. : LD-5/ TP - 01 DEPTH (m) : 2.00 SAMPLE NO. S-5
SAMPLE DESCRIPTION: Brown, well-greded GRAVEL with sand .
# 100
---_._--_._- ---~------
2281.1 96.9 3 2353.0
# 200 2295.7 97.6 2 DIy WI. of soil Aflerwashing
- - - - - - - --
(I)
0.. 10
3=:' ::- ....... .
••..... .- '.. . .•
01" .~.:~ . .- j'"
REMARKS:
---.- ... --------~-.--- ------------ - - .- .---- .. ---~-- ...---.-------
RIYADH GEOTECHNJaUE
,,*" •...,.:;;
"'-:.,:.
s=... L0~JI ~imi"'d.L""''''''C"""",",J'''''fi''''''.00\).''''''5.n
c~''' ~!J~"HH=''~~~;~;;J
; ';'1) CR l01(.1100~M
-<~;:
p.o. Box 9182, jedd,)h 21413, KSA Telephone: +966 (12) 6715621 j 6176860 !"),, +966 (12) 671Sn6 Email: rgf-wp®erigeosciences.com
.A!J'V..,JI~
_
"""'......
a FOUNDATIONS co.
~~-..~_,,-"n .... ;},>':. ..........
-J"....-',u.,... "',J-",,...........
TEST REPORT
PARTICLE SIZE DISTRI BUTION (GRADATION) OF SOILsUSlNG SIEVE ANALYSIS
ASTiVI-D6913/D6913M-J7
CLIENT NEOM Lom.!:"". : PROJECT NO. :
----_. 21}4037 ...• -~
~
3" Can No. RG
ih" Wt. (Soil + Can) Wet (gm.) : 4216.0
2" 00.0 0.0 100 Wt. (Soil + Can) Diy (gm.) : 4113.8
~
11h" 181.9
.......- .........- ..
4.7 95 Wt. Water (gm.) ; 102.2 --~~
100
... ~, ... ....:::::: .: ....... "-,. . .. ., .. ; . , .
.... .
. .
90 " 'c ;=,,'.
1" . ,' ~".;; ...; .; ....
·.CC
. ..
;;
0>
80 , •.• ".;~. ":.;,. •••• :;;,:: .•.• : .".:' :"".",:;;;, :
~
.
70 .• ;, ,. ;'." •• :."';:;":::.;:.~:;: ..:,:;:: '.::::;';;.' '.' ,c: :.:.' .... : ,·.c ..... .... C"
........ '
,
'"
.0
0> ~~; : ';:"':'~:':."., .. ..
'
•
.
'.'
i:!
ID
0
~~ '. " ..·.c.·· •.•·.··: •..•.•.. C'~: • • • .:
o ' . .
. _._.
TESTEDIlY; I'aiyaz CHECKED BY / REVIEWED BY : I\sad 1\ bbas
APPROVED BY:
(I.llb. Incharge)
Copyright of this dnt'umi!ll! is nWHP{i hy' RGF, illnllY not h(> rt'f·wodu~\·d ('\n'pl with pI ior wrillcn IWrlllission from tIll' rOI1lI1,\I1~'.
p.o. Box 9182, Jeddah 21413, KSA TelephQne: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf-lVp@erigeoociellco5.COI11
Location: Garntltha SI. ne.u Arbaeen st. intersection ivlllshrefah District, Jeddah
f
TEST REPORT
PARTICLE SIZE DISTRIBUTION (GRADATION) OF SOl LS U5I NG 51 EVE ANALYSIS
ASTM -D69131D6913M-17
CLIENT : NEOM Company . . PROJECT N o ' : 21J4037
IJROJECI : NEOM Desalin~tio~1-~~~ttoG~-;iT;;;~;~-:;;SsiMSy~t~;;-;--
SAMPLE SOURCE: LD-5/ TP - 02 REPORT DATE : 29.m.2022
SAMPLING DATE: - TEST START DATE : 18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE : 20.11.2022
o
SAMPLED BY : - ENV. CONDITION TEMP. : 24.0 C HUMIDITY: 47%
BOREI-IOLENO.: LD-5/TP-02 DEPTH (m): 1.50 SAMPl,ENO.: S '1
SAMPLE DESCRIPTION: Brown, well-graded SAND with gravel. _
-
#4
..
964.1 40.6 59 WaterContent(%) : 3.36
# 10 1518.9 64.0 36 CLASSIrICATION
•.........
# 100 2250.3 94.7 5
---
" 2 3 7 5 . 0 _.... _.. _... . _ -
# 200 .... _ .. _-
2267.9 95.5 5 Dry WI. of soil Aflerwashing
....
100
90~--c ;·::::c·c.-~.:::_::ccc ::. c :' .. : ' ... c" ......
:§, 80 "'K .. ;::.::,.;.; - : : ..;, .
'0; 70 .',:";, c.,_. :,---,~.:cc:c:
,'c':' ........: : : : . . . . : :::
:;, 60 .:.; :<-:: .;: """",
· , . : · c c . . . " . : ; ' . : ' : :-: C·c· :c
i 50:' ,. • .: ,··.c:c...::::::::;~:: '.'; . :' · · · ; c ; : : ., .• :c . . - : ...
~ 40 ;c'~ c
':: 30 ... :- .., ., .. , ., ,
&; :: .. :... .. ~ ..
~ 20.. :: .. ," .',: .. ,. = ~ ; •• • ..' :..:
CL 10
o c· ...
REMARKS:
---- - - -- ~-------- --
APPROVED BY:
.... ...---
(L'10. Inchargc)
Copnighl ur I his tlonltn(~nl is o\\,l1t'tl hy }{C F, if ma~' nol Ix~ H.'produn>d (>xc\.'pt with prior wriUt'1l pt'rmis.o;;inn (rom Ihf' ,,'omIMHY.
I{GF-jFD-I'IIY-SOIL·OI·03
20,01.2020
.... • ;;.JA - I~
tq f~ERI~.~~ CA.;;...L:.--(JlfJ ;:."
CR'U'Ul~
_. if0..,.J
lmtoo ~("~y I~j<;w 6.000,00Q fU~
RiYADH GeOTeCHNIOUE 8< FOUNDATIONs CO.
-~,;t ~~ "\ .J1.\.......1~:: ~4~
h\.\"\"1 .. .., ...
a..>..:,r.- ~I'"
p.o. Box 9182-jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 FHX: +966 ( 12) 6715426 Email: rgf-wpfEerigeosciel1fes.col11
Location: Gllrnath.l SL nt2'.af Arlhleen S1. intersection, Mushrefclh District, Jeddclh
TEST REPORT
PARTICLE SIZE DISTRIBUTION (GRADATION) OF 50ILSUSING SIEVE ANALYSIS
ASTM -D6913/D6913M-17
CLIENT : NEOM Company PROJECT NO.
PROJECT : NEOM Desalination Plant to Transmission
SAMPLE SOURCE: LD-5 TP-03 REPORT DATE 29.01.2022
SAMPLING DATE: TEST START DATE 18.01.2022
SAMPLE RECEIVING DATE: TEST FINISH DATE 20.11.2022
o
SAMPLED BY: ENV. CONDTI'ION TEMP. : 24.0 C HUMIDITY 47%
BOREHOLE NO. : LD.5/'I1'·03 DEPTH (m): 0.60 SAMPLE NO. B 1
SAMPLE DESCRIPTION: SAND with silt &
3" - -... -~
Can No. CR-12
1
2 h" Wt. (Soil + Can) Wet (gm.) 3946.0
2" wt. (Soil + Can) Diy (gm.) 3798.4
00.0 0.0 100...
-_ Wt. Water (gl11.) 147.6
288.0 8.1 92 wt. Can (gm) 258.4
614.5 17.4 83 Wt. (Soil) Dly (gll1.) 3540.0
#4 1149.6 32.5 _. - - 68 Water Content (%) 4.17
--
# 10 2071.9 58,S
41 CLASSIFICATlON
--- ... -~
# 60 3151.9 89.0 11
- - -...........
Dry Wt. of soil before waShing
~-
----------~---
# 100 ~~-~----~~---------
3217.6 90.9 9 3540.0
# 200 3240.3 91.5 8 Dry WI. of soil After washing
PAN 3241.6
....
3241.6
._------------_ ...... _.... _-- . _. '
-~-------
-~ ~-.
100
90
1:OJ 80
'0;
3: 70
",
.0 60
OJ
<:
'~
50
'"'"
0
40
30
.,
;:
!: 20
'"
0 10
0
100.00 10.00 1.00 010 0.01
Grajn~sizo in Millimeters
REMARKS:
APPROVED BY:
(L.ab.
Cop~Tighl of Ihis d()~'unwnl IS OWIWi! by HGE il H1fl)' nol Ill' n.' pnllh,(cd l>);t't'pl wilh prior wrillptl pC'rmission fHim Ihe ,,'omrldnr.
HGF-JED-I'IIY-SOIL-OI-03
20.01.2020
rq f_EftI_" ·c...-4••;:•...I....:--0 J:t :: u
CR lU'U.l1007.oo
•
p.o. !lox 9182, Jedddh 214'13, KSA Telephone: +966 ('12) 6715621/ 617686() Fax: +966 (12) 6715.126 En",il: rgf-wp@erigeoscienccs.com
..:;;~ i f ,-::?..)I~
.)N~ ,",,~ ... ,Jt\.,...J;; 1 u,,~ ~,$>-~
Loc,)tion: GM1Mthn SL near f\rbaeell St. intersection, -ro.. lushre(,lh I:J'istrict, Jeddnh
TEST REPORT
PARTICLE SIZE DISTRIBUTION (GRADATION) OF SOILS USING SlEVEANALYSIS
ASTM -D6913/06913M-17
CLIENT : NEOM I'ROJECT NO.
PROJECT : NEOM Desalination Plant to Transmission -
SAMPLE SOURCE: LD-5 TP REPORT DATE 29.01.2022
SAMPLING DATE: TEST START DATE 18.01.2022
SAMPLE RECEIVING DATE: TEST FINISH DATE 20.11.2022
-E-NV-.-C-'O-N-D-n··'··I··..O
......N
..........T......E....M
.... P.-: 24.0 °c HUMIDITY
SAMPLED BY: 47%
----
BOREHOLE NO. : - - - ' - 11'-03
_ .............
DEPTH (m): 2.00 SAMPLE NO. S 5
GRAVEL with silt & sand.
CanNa. B.B
Wt. (Soil I- Can) Wet (gm.) 3040.0
00.0 0.0 100 wt. (Soil + Can) DIy (g1l1.) 2979.0
78.2 2.9 97 wt. Watel' (gm) 61.0
316.6 11.9 88 Wt. Can (gm.) 308.0
._.._ - -------
823.3 30.8 69 Wt. (Soil) DIy (gm.) 2671.0
#4 1360.5 50.9 49 Water Content (%) 2.28
# 10 • 1848.2 69.2 31 CLASSIFICATION
90
1:
.,
.9' 80
s: 70
E 60
0>
c:
'iii
50
i:l
a..
40
C :30
e'" 20
'"
a.. 10
0
100.00 10.00 1.00 0.10 0.01
Grajn~size in MiHimotors
REMARKS:
APPROVED BY:
(Lj.1b.
Copyright of Ihis donlllwnt is mVlwd In' H.GI'~ il 111,1,\' nollx' 1('prodtlC(ld P:\C('l't with priOi \VI illt'll pPlInission from 1hI.' fOlllpclny.
HGF-JED-PIIY-5011.-01-03
20.01.2020
t:..-l.::-l..:.-'Vl!:f ,:-:, ..
CR.lO:,}U1~:::{)S
':;;.0 if~..) I ~
l..~tJB\)'iJi\y~1:p(I<n>,I.CiUp"~$,OQ(U,}QO$,R ~~.J~~'\ .}ll~.~",i~",,~
fAnERI RIYAD'" GeOTECHNIQUe &. FOUNDATIONS CO.
p.o. !lox 9'182, Jeddah 21413, KSA Telephone; +966 (12) 671562"1 /6'176860 Fax: +966 (12) 6715426 Em,lil: rgf-wl'@erigeosLiell",,,.({)1l1
Locolion: Garnntlm S1. near Arbaeen St. intersectionr j\JushJ'cfah District" Jedd;:lh
TEST REPORT
PART I CLE SIZE 01 ST RI BUTI ON (GRAOATI ON) OF SOl LS USI NG SI EVE ANAL YSI S
ASTM -D6913/D69131\J-17
CLIENT : NEOM rOm"""" PROJECT N O . : 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5/TP - 04 REPORT DATE : 29.m .2022
SAMPLING DATE: - TEST START DATE : 18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE : 20.11.2022
SAMPLED BY: ENV. CONDITION TEMP. : 2"1.0 °c HUMIDITY: -47% . . . . -~
BOREHOLE NO. : LD-5 /11' - 04 DEIYfH (m) : 0.60 SAMPLE NO.: B 1
SAMPLE DESCRIPTION: Brown, weli-greded GRAVEL with sand.
.._..
# 100 --------------~~-~
3666.7 96.2 4
---- = 3811.7
- - ...•
# 200 3683.2 96.6 3 Dry WI. of soil After washing
1- . . .
PAN 3685.0 = 3685.0
._- ,------------ .... _-----------,
Tol"l Soil WI. (gill.) 3811.7
1~~: ~"-..:: ••. ."~ .~.T:·.:: ,::.:c:-::,,::,: •. ''''. _~ ... ~ ~. c'.: >: • :._~ •. '. :>~~'. ·:-·..c·.: . ..,
~ 80 :.::..~:c .~~c . .·. _.·... ~c.... . c. . -.': .:,....
'iii 70 :.~.. :~:. ~:::::.:::.: ••:.:::..~:•.: : '.' •• : : :.: ., ,'.': :. '.::: :.:. :.:: .:. .' . '.' .
~ 60: ':'. :': : '.: .. :'. ::·~:~:co...~.·: .:.:.:."::~::c~:::: ....-'... :···~::c··:..: .'::... ..: .• :..:::
.1r 50 ....•... • ::::~:::::·::.·::·:L:::·::::·.·::· - :...<.:.:·.::'c:>:::·::': : •
::I 40 .• ~ .••. .=: .:' :.
~ 30 • .• ..•.•• ~ ...•.... =: : ....•.
REMARKS:
~~~~".,,~" .."-" .. "'-"-.,~.-- .. --~. .............. ------_ .._. -.-.--.. --.---.--------~- ............. -----_.". -- - - ------_.. __ .. - ........ _--
APPROVED BY:
- ~ ..- ...---,,--,,--------- .... -.~------
(Lab. lncharge)
Copyright of this d()(lImt.~nt is owned by HGF, iilllcl.\' nol Lx' t"l'prodlKed t'xn'pl wUIl prior wrillpf1 lwrmission from the (ompany.
RGF·JED-PIIY-SOIJ.·OI-lH
20.01.2020
f· An ERI
~
Compeol(
1""·'
~) ' ' "'
i::::~4-
~~~."""''''''--''''
Cl.:-I....:.-'V 1J1 ~~ t-i',-:?..,J I ~
"f'l ~fi1(l'OOli!~
tJmikldlWbil.ly Compn.n,JC«tt~f)j15.000,(;(U) s.n
p,o. !lox 9182., Jedd"h 214 13, !<SA Telephone; +966 (12) 671562'1 / 6176860 Fa" +966 (12) 6715426 En1<1il; rgf,wp@erigeosciences,cOl]l
Locdlion: G)(;).'ull<l. st ned.!' Arbi1een Sf. interSL'CtJon. Mushrefclh District, Jedd,\h
TEST REPORT
PARTICLE SIZE DISTRIBUTION (GRADATION) OF SOl LSUSI NG SIEVE ANALYSIS
ASTM -D69J3fD69J3M-17
CUENf : NEOMr. 'Y PROJECT NO. : 21J4037
- , ..----------
PROJECT : NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5/ TP- 04 REPORT DATE : 29.01.2022
SAMl'UNG DATE: ..
TEST START DATE " : 18.01.2022
- _---
3" CanNa, : AM
1
2 /z' ~
wt. (Soil + Can) Wet (gm.) : 3481.0
-
2" Wt. (Soil + Can) Dry (gll1.) : 3377.8
11h' 00.0 0.0 100 Wt. Water (gm) : 103.2
3/4" 683.2 22.3 78 wt. Can (gm) 314.0
- 3/8' 1204.8 39.3 61 Wt. (Soil) DIy (gl11.) 3063.8
---._--_..
#4 1828.6 59.7 40 Water Content (%) : 3.37
2059.2 67.2 33 CLASSIFICATION
-_._ #10
# 20 2318.0 75.7 24 (ASTM D3282-09jD2487-10)
----
# 40 2476.8 80.8 19 A-2-4/GW-GM
# 60 2546.5 83.1 17 Dry WI. of soil before w<lsbing
~----.--
100
...... ~ :'
.. . .. .
';: ~
.... '.' ..
",
.
.. ..... .•.............
.
.
'
90 :
.crn 80 . ' ...
•
; - . •
;
'w
s
'"rn
.a
70
60 ~ .....
...•.•. ~...
, ........ .... ' , ~...... ' :
i.. : ........
.
••
............ ..
c:
'Vi
50 •••••••
:
.
~
...c
..'
.•....••...
:;; :.' . •
'"
ro
Q..
40
. ~ ." ... ,
c: 30 .~
Q)
~ 20 ; :'.;.. . .. :;; ~ : : .
'"
Q..
10 . .•...... ···i •..•. .
..
0
: •• : :
REMARKS:
------------
- --.-------.. -------
APPROVED BY:
(Lab. Inch~i:g;;f
Copyright of this do..: ullwnt is oWI1('d h.\' HGE it liMy not l)(' rppmtiun'tll'sn'pl with Iwior wrill{,11 Iwrmissioll fmmille (omp<ll1:'.
RGF-JED- PI IY·SOIl.-OI-03
2001.2020
f"-,,,:,;"~'=="'I 't;:'A•.~_L;.-O'" .: .: ....:;.;-~ i f y..,) ,~
rqf_ERI_, I~
,h,,~)
[us?,]
~ CR '0101~OO
L""''''''.U"",,,,y
;,:,::.:~~~;;~;:;" RIYADH GEOTeCHNIOUE & FOUNDATIONS CO.
Com,,>n,' ".",\," •.000.000 S." .J., or>- , J~' ,.,..', I "'~' "">>-~" U'r'
~,"'.'"\"1.",..It'.;:,....--
P.O. Box 9'182, Jedd.lh 21413,!<SA Telephone: +966 (12) 6715621 / 6176860 FdX: +966 (12) 6715426 Email: rpf-wp@erigeosciences.com
Location: Gafllatha St. near Arbaeen St. intersection, jvlllshrefah District Jeddclh
TEST REPORT
PARTI CLE SIZE DISTRIBUTION (GRADATION) OF SOl LSU5I NG 51 EVE ANALYSIS
ASTM -D69131D6913M-17
CLIENT : NEOM CompanL ____ PROJECT NO. :
.---_..
21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-S / TP-OS REPORT DATE : 29.01.2022
SAMPLING DATE: - TEST START DATE : 18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE : 20.11.2022
o
SAMPLED BY: - ENV. CONDITION TEMP. : 24.0 C HUMIDITY : 47%
BOREHOLE NO. : LD-5/TP-05 DEPTH (m): 1.20 SAMPLE NO. : B-2
SAMPLE DESCRIPTION: Brown, silty SAND with gravel.
-_._-
3/8" 599.2 19.7 80 ..
Wt. (Soil) Dly (gm.) : 3038.8
---._-
#4 1044.3 34.4 66 Water Content (%) : 7.08
--
# 10 1646.4 54.2 46 CLASSIFICATION
------~---- -----~ .. ... _---" - .-.-~-~~ --- ----~~-.
# 100 .. ~.---- ..
2578.5 84.9 15 =
-------_.
3038.8
# 200 2637.7 86.8 13 Dry WI. of soil Afler washing
.-----
----------_._. -
'1'01.11 Soil WI. (gill.) 3038.8
100 :
:-----.:... c,: _:"',.: ,~
E
90
80 :,: . ~':' :...:.":
..
..c - ,.. : : , ...': .:
01
.;:; ::~, ..:"".:,... "-,,., , .
3: 70 ... - .....
.. : ::: .:ec.'.· .-.
~ ..
.-'::
, : ..
'"
.c
01
c: ~~ .... ..' :'~:. ,
~, ....
.. ' ..
cc· .
: ..
.. '
,
'iii
\Jl
ro 40
::: ,
,
" , .. ,.
0. : .. . :. ~ :
C' 30
~
'~" 20
'"
0. 10 --_.
o I' I' T I I
100.00 10.00 1.00 0.10 0.01
Grain-sizo in Millimotors
REMARKS:
------ ---- -------~. ---------------_. ----------------- - --------- - - - - - - - - - - - - - - - - - .. _------------
__________ • • _ _ _ _ _ _ _ _ _ . . _. _ _ _ M _ _ . _ . _ •• _ . _ . . . . .•.__ ..._.. _.. _-- _____.0.____.0_.."_ _ -" .. --_. __ ._.. __.._-
(Lab.lncharge)
Cop~'J"ighl o( Ihis donmwlll is mVIll'd b~' HGr, il 1Il<\~' nol Ix~ rl'plOdlKL'd l'x(l'pl with prior writtl'll pl'rmissioll (rom Iht, (Olllp(lIl~·.
RGr·JEI)-I'IIY-SOII.·O 1-03
21l.01.2020
"C..-l;;;.....(...;...--V I., ~~ i f0..) I
tq f •
An
IERI
,
i~~ ~J L1m'""'l_ll\y~fi'I(_
r"·.w¥··""'.. ··"'·"~··· ..~""··"'
1 ~\'<1' ~ tR.
.
Hl'O'ao.~60
...'''.OOO,''''''''."
.....
]'.0. Box 9'182, Jeddah 214'13, 1<5;\ Telephone: +966 (12) 671562'1 /6176860 j',,,: +966 (12) 6715426 Email: rgr·wpfterigeosdences.com
Location: Garnatha St. near Arbaeell St. interSfflion, Mushrefl:lh District~ Jeddah
TEST REPORT
PARTICLE SIZE DISTRIBUTION (GRADATION) OF SOILSUSING SlEVEANALYSIS
ASTl\1-D69131D6913M-17
CUENT NEOM Company ..............................................._---
PROJECT NO.
PROJECT NEOM Desalination Plant to Transmission
SAMPLE SOURCE: LD-5/ TP-05 REPORT DATE 29.01.2022
SAMPLING DATE: TEST START DATE 18.01.2022
SAMPLE RECEIVING DATE: TEST FINISH DATE 20,11.2022
SAMPLED 13Y : ENV. CONDITION TEMP. : 24.0 °c HUMIDITY 47%
BOREHOLE NO. : DEPTH (m): 2.00 SAMPLE NO. S 5
SAMPLE DESCRIPTION: Brown, well-graded GRAVEL with sand.
100
90
EOl 80
'iii
S; 70
E 60
01
c: 50
'iii
III
40
'"
0..
c: 30
'"~ 20
'"
0.. 10
0
100.00 10.00 1.00 0,10 0.Q1
Grain~size in Millimeters
REMARKS:
_.. ,--_. ~ ",.~-~----~--~-- .. -. _... ... ... . ~---
APPROVED BY:
Copyrighl of this donmwlll is O\\'llpd by HGE tI rnd~: not bi." feprodu(l'd l'XtT'pl "'illl prtor wrillpil pl'nnls5fon rrlllH Ill(' ,"omp.my.
"GF~JED~I'IIY~SOII.~0I~03
20.01.2020
~~-"Cl:-~O/~ ~~if~~I~
,-,,-,--,-,-,,-,-,-,-.c:.:.::...-'-=---'====~ RIVADH GEOTECHNICUE & FOUNDATIONS CO•
.. .0. D(lx tll'):tIl., V"'nb... Al·5".;ly;:,h. MYA$ ~:tOOO. to:SA ''Telephone; ...')(or} (l.ll~ 32:;'~2/32~-l t'ax: 1"966 (1)\) ~1:!\'O~)II6 £ .... ~lL q~f~yt>l'lt""We.lgeo~cltor5t;<:c~.tQWj
lo(;aUut>: /I.!.Naw<u"L;$nd $tfw.!f:l. H.:)l A)..M .. h:Olil DHt(k•• n.c•. YJohl,l';J AI;_$ijliil:f.;lh
~ 30
~ 20
g: 10
o
100 10 GRAIN SIZE IN MIIJ.IMETERS 0.1 0.01 0.001
RGF·YNB·PHY -SOIL-Ol·04
01.08.2021 Copy Rights Reserved By RGF
f An flU Compony
'i.:..A•.:..-l;:../LJ/ ~ :: '" ·....:7A ~L;..;..) I ~
RIYADH GEOTEC':;NIOUE ; : OUN~ATIONS CO.
1-'.0. IlQX ::102"71, v ....bu AI.5Jn~l)1 .. h. MYA~ ~.1(}(){), KSA "'·d~phooe; ..-!:H:)t:) (10'1) :t:t~09~2 I :U:.:>tl993 t: ..,,; -..9(,6 (101) :3'1:':>0946 f.!m,3l1; ~~I.y .. nbu@".rReO~dt-nce'.(:D,n
l(1c.. th)(.~ Aj,N;Jwa.\;:iJI(f $h'.;o;[, H"I ,'\I.M.ll):;:.~. Dl$tdo;.i. A,C .• Y,tl,,->u A1.::5II,;)I)I.)h
RGF-YNB-PHY ·SOIL·01-04
01.08.2021 Copy Rights Reserved By RGF
f An Eftl Comp3ny
f",o. no.. 30Z71. Y.;u>bu- Aj.SI"~:;Y";', MYAS ~'1QO(). K!SA
l¢("'HtJn~
c...-L:-L---'Ul~ ~~ ifl:?.-J f ~
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
1'¢1l!phe>n<l': ....1>06 (:1.04) 3250'}92/32~3
Al.Nili!W<'J<Ui)-d Sl~;:t. H:ol At.tlo'ldmt.h
I';u:: ~966 (14) 3"l!l0946
Cl!$\tkt."~ .. Y.iflht!
ewul1: I'6f.'1anbU@r<l.Hco~·d!:",.c..,,.,,,om
Aklh')~.t)l'ah
PROJECT: Ne'om desalination plant to Slaya/ transmisssion system.(LD-05) DATE SAMPLED: 30/1212021
SAMPLE SOURCE TP: 07 DEPTH: 1.20 m DATE RECEIVED: 06.01.2022
SAMPLE DESCRIPTION: Brown well graded SAND with siltft gravel. SAMPLE NO.: B-2
0
ENVT. CONDo TEMP. 23.9 C HUMIDITY: 39%
DATE STARTED: 19/01/2022 DATE COMPLETED: 21/01/2022
RGF·YNB·PHY·SOIL·01·04
01.08.2021 Copy Rlghts Reserved By RGF
1'.0.
f An ERI company
Neom desalination plant to gayal transmisssion system. (LD-05) DATE SAMPLED: 30.12.2022
TP: 07 DEPTH: 2.50 m DATE RECEIVED: 06.01.2022
DESCRIPTION: Greyish Brown poorly graded SAND with silt & gravel. SAMPLE NO.:
ENVT. CONDo TEMP. 23.7 o C HUMIDITY: 38%
DATE STARTED: 19.01.2022 COMPLETED: 21.01.2022
RGF -YNB·PHY·SOIL-01·04
01.08.2021 Copy Rights Reserved By RGF
Cl:::.-l.;/U/~ ~A.... i./0.,)f~
RIYADH GEDTECHNIQUE & FOUNDATIONS CO.
- ..
P.O. no... 302':'1'1:, 'V.mt;u Ah~";lYi:>h< l!.itYA.S !\lOOO, "SA Tc:l~.dl(.>(\.e~ ">'900 (14) :n:50992: I )l:!KI9!)3 jlj:>)\: ... 9~O (14) ::1:0/::>094/1 tm"J1: ~t-V.;.... bu@l:"jlgeo,d~fl«",.<:om
l,;,e~U(>f': J'\t,NltW':H'\,Uld :$l~et. tt;;ol A"M~IY"'l OI,.ttld. R.<': •• V.H.bu Al.'!ln",flfoSh
RGF ·YNB-PHY·SOIL·01·04
01.08.2021 Copy Rights Reserved By RGF
t:--L-L/V l:t ~r.:f ~,-:?.,J I ~
RIYADH GEOTECHNIGUE & FOUNDATIONS cO.
f.<,Q. nOlO; ao~·r:). V"rU:>u AMI");'l'.oh, M'fA':S :;'].000. t-:5A. Tdcph&ne~ ....~G (34) 3250992 /32'SO!n.) t'.lOll: +!I66("14) "':t.5b940 tm..tlh t$f.y"nuufPcilg<!'Ulr,lC'f<¢(:!> <-um
(6(:;:.Uon: Aj,N..w.'}.<")aH(t $tn~f. H~t AJoM..hM, bliVk.t" A. .c", Y;;t.i:bu Ah$jiH.ly.."
Neom desalination plant to gayal transmisssion system. (LO-05) DATE SAMPLED: 01.01.2022
TP: 08 DEPTH: 1.50 m DATE RECEIVED: 06.01.2022
;)AMI"'Lt:. DESCRIPTION: Brown well graded SAND with Silt ft gravel. SAMPLE NO.: S-4
0
ENVT. CONDo TEMP. 24.9 C HUMIDITY: 41%
DATE STARTED: 1910112022 COMPLETED: 21/01/2022
~
w
k! 20
it: 10
o
100 10 GRAIN SIZE IN JIIJJMETERS 0.1 0.01 0.001
RGF-YNB-PHY ·SOIL-01·04
01.08.2021 Copy Rights Reserved By RGF
"C.A..:_L::.--V I, :;..~ .~& Jr~..-J I ~
fAn ERIc"",,,. .,,y
Crt 10101GO?b!'J.
U'l~l~ I.~)' ~y I~
P.O Box 9182. jedd<1h2H]3, KSA Telephone: +966 fl2) 6715621/6176<%0 Fax: +966(12)6715426 Email: rgf-wp@erigeosciences,coll1
TEST REPORT
AITERBERG LIMIT DETERMINATION
ASTM D 4318-17el
CLIENT : NEOM Company PROJECT NO. : 21JLI037
PROJECT: NEOM DesaE1.1atio~~Plant to Gayal Transmission Syst~
SAMPLE SOURCE: LD-51 TP-01 REPORT DATE: 29.01.2022
SAMPLING DATE: - TEST START DATE: ~---~
18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE: 20.01.2022
SAMPLED BY: - ENV. CONDITION TEMP. : 2'1.0 Uc HUMIDITY: ~ _'M'._'_" ~~_
47%
BOREHOLE NO. : LD-51 TP 01 DEPTH (m): 2,00 SAMPLENo.: B 1
Descri ption of sample: Brown, .~. "'..~~~ SAND with silt & gravel. Preparation method: Dry
LIQUID LIMn'
RUN No. 1 2 3 4 5
D1SJ-JNo,
WT. OF WET SOIL + CAN gm5,
WT. or DRY SOIL + CAN gms,
\VT. OF MOISTURE gm5.
WT,OFCAN gUl(),
. ._=
LL: -
t==
C
2c::
r
0
I
I
Plastic limit cannot be PL: NP
u I
2
0.
I determined/NON PLASTIC
I
s:'" I PI : -
Numberof Blows
APPROVED BY:
(Lab,lnchmge)
Cop~-ri~~hl of Ihis dOfunw-llt is OWIl()d hy ItGF, ilIlM~' noll)(~ rf'prodllfcd (,Xff'pt with prior writl!m pl~rmission fl'Otn tii(' (oIllIMny,
RGF·JEI)·PIIY-SOII.-Ol-m
20.012020
t.:.A...;:... c.....::---U ',·~A t.f~J I~
q
(C f . AAERlc_pa,w i~ I./ii/.," I
~_ _'"<_.
1010't6bZb~ r~'~~'7r-·-"·-·';;;;~;::;;;"-j
J"• ...,.JJ •• .
\"'\''''!A40':;'<.Jr-'
r.o. Box 9182, jeddah 21<113, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715'l26 Email: rgf,wp@erigeosciences.com
Ux:cltion: Garnatlltl 51. near Arbdeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
ATTERBERG LIMIT DETERMINATION
ASTM D4318-17e1
CUENT : NEOM Company PROJECT NO. : 2lJ4037
PROJECT: NEOM Desalination Plant to Gayal Transm.ission System
SAMPLE SOURCE: LD·5 / TP- 01 REPORT DATE: 29.01.2022
SAMPUNGDATE: - TEST START DATE: 18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE: 20.01.2022
SAMPLED BY: - ENV. CONDITION TEMP. : 24.0 U c HUMIDITY : 47%
BOREHOLE NO. : LD-5/ TP- 01 DEPTH (m): 2.00 SAMPLENo.: 5-5
Description of sample: Brown, well-greded GRAVEL with sand. Preparation method: Dry
LIQUID UMIT
RUN No. I 2 3 'I 5
DISH No. --_. ....... ---.-----.-.--~~-.
-_.. _... _ -.~- ..-----.-. --.~~~------
WLOFCAN fllns.
Wf. OF DRY SOIL gms.
MOISTURE CONTENT I'lil
NO. Of BLOWS
I LL:
C I
2<: I
- Plastic limit cannot be
u
0 =
=
PL: NP
2
~
=
=
determined/NON PLASTIC
~'" = PI :
Number of Blows
-----" ..... _._.-----_ .. _._. ---------~ .... -.-.-.~-------- --------------_._ .. _-- - -- ---- - - ---- ---- -------- - ---- - - - - - - - - - - - - - - - - - - ------- .. -~------------------
APPROVED BY:
---------~---.-.----------- .------~
(I.nb.lnchnrge)
Copyright oflhis dorulllPnt is oWlwd hy HCF, it I1My not lv IvproduCl'd PXfPpt with prior wriltl'IlIWflllission from thpcomp,lllY"
RGF·jED-PIIY·SOII.·02·o:l
20.01.2020
·.En'.. . C.A_;;..A_;_/(j'~·~At./0.,J'~
f . An. Co"'''''",,
"-~-:si~--,~::"-:,~,:;z;-1
f§:d. [-~f:r-II U".""'I."""';ly~"tCe,_6.000.<X><>3." .J"~""" ~ ·.r;i]·.)~· "'J_~'''''' r
Cl't "11:Jl0100ZD\l
.j..
- \.,,,",~....:O..!.<....>'"
p.o. !lox 9'182, jeddah 21413, KSA Telephono: +966 (12) 6715621 /6176860 Fax: +966 (12) 6715426 Email: rgf-wp!Yerigeosciences.colll
Location: GiHnatha St. lledT Arhaeell St. intersectioll, rvlushrefclh District, Jedclc1h
TEST REPORT
ATTERBERG LIMIT DETERMINATION
AsTM D 4318-17el
CLIENT : NEOM Company PROJECT NO. : 21J4037
PROJECf: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5/ 1P- 02 REPORT DATE: 29.01.2022
SAMPLING DATE: - TEST START DATE: 18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE: 20.01.2022
SAMPLED BY: - ENV. CONDITION TEMP. : 24.0 Uc HUMIDITY: 47%
BOREHOLE NO. : LD-5/ TP-02 DEPTH (m): 0.60 SAMPLENo.: B-1
Description of sample: Brown, well-greded SAND with gravel. Preparation method: Dry
LIQUID LIMIT
RUN No. 1 2 3 4 5
DIS]-] No.
WI'. 01' WET SOIL + CAN gnls.
WI. OF DRY SOIL + CAN gills.
wr. OF MOISTURE gillS.
WI'.OI'CAN gnLc).
W 1'. OF DRY SOIL gnlS.
MOISTURE CONTENT uII)
NO. OF BLOWS
..... =
=
LL:
c
.....
Cl.I
c
0
=
-,---
I
Plastic limit cannot be PL: NP
u
....
.2!
I
I determined/NON PLASTIC
I
'" PI :
$: I
Number of Blows
WLOFC,\N gins.
WT. OF DRY SOIL gills.
MOISTURE CONlloNT I~J
PLASTIC I.IMIT
AVE PLASTIC LIMIT
-------------- ...... ~-.... --- -----------------_._----_._._._._---------- ------------------------- - -,---._'--. __ .. _-_ ...... _------_ .._ . _ - - - - - - - - - - - - - - - - - _ . _ - _ ..
APPROVED BY:
-----_._------------------ __
.. .. .. _---- -
(L~b. Inch~rge)
Copyright of this docullH'nl is O\\'Ill'd by HGF, it IJM~' noll1\.' J'l'prOdU(ctll'xCl'pl with prior writtell permission frolll Ih(' romjlclny.
I{CF-jFD-I'IIY-SOII.-02·03
20.01.2020
rq f..ERlc__ __==,~
~] ~
-..,... I
t.::A_:,A.,.;:.-(J,,·~~t../t;?J/~
ct\ HH01002~ . .
U.tt~dt:~.COmpBnylc:::;.up~B,t'Kltl.t$)$.t~
..1 RIYADH GeOTECHNlaUE & FOUNDATtoNS co.
,.,.~~'\~ ...'.~ ........
Jl,t... J,~'~ J~~~,fJ~"~~.J~,,"",.I)I$'r'"
p.o, Box 9182, jeddoh 21413,!<SA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (2) 6715426 Email: rgf-lVliiiJerigeoscienres,corn
TEST REPORT
AITERBERG LIMIT DETERMINATION
ASTM D 4318-17el
CLIENT : NEOM Company PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5/TP- 02 REPORT DATE: 29.01.2022
SAMPLING DATE: - TEST START DATE: 18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE: 20.01.2022
SAMPLED BY: - ENV. CONDITION TEMP. : 24.0 Uc HUMIDITY: 47%
BOREHOLE NO. : LD-5/ TP- 02 DEPTH(m): 1.50 SAMPLENo.: 5-4
Description of sample: Brown, well-graded SAND with grevel. Preparation method: Dry
LIQUID LIMIT
RUN No, 1 2 3 4 5
Dl:'aINo.
WI. OF WET SOIL + CAN gms.
Wf, OF DRY SOIL + CAN gms,
wr. OF MOISTURE gms.
WI. OF CAN gms,
WT. OF DRY SOIL gn,;.
M01STURE CONTENT I'll)
NO, OF BtOWS
....c: I LL: -
I
1
~
c:
0 =
=
Plastic limit cannot be PL: NP
(.)
~
.... =
= determined/NON PLASTIC
~
n:I
PI :
s:
Number of Blows
APPROVED BY:
--------------- - ------.---.-~-------
(Lab, Incharge)
Copyright of! 11[5 donrnwnl is oWlwd by HGF, it II"'), not h,' n,'pt olitlty'd pxCtlpt with prior wfiH('n !'xymission from til(' rompllfiy.
I(CF·)F1)'I'IW·5ClIL 02,03
20.0L2020
rq f [__ _ ~
I
'.""~"=__ 'C-L:..-t....;:,..-UIJJ~~v0~'-~
If
Q~) ~-I.It(A'II ~ 1 C"''''016''''''~
/. --. -
-.::.r-::..
"""HA''''~
ERI. . .!041~'" LioJ/lndtWbU"JyCQrrpOl"1y/CaplbdO,(}()O,QO()S.I"t J"'.)~~'" .JU\....r'-.)J~l"~..".1..,.)l~...z...uu:-~
. . ~An..;,.;;,==.:c:.:"::.:"'::""=n\r::....J=.. w=. ._=....=....=....=..,..'-~~~,~J RlVA.DH GEOTECHNIOUe &. FOUNDATIONS CO ..
r.o. Box 9]82, Jeddoh 21413,!<SA Telephone: +966 (12) 6715621 / 6176860 Fox: +966 (12) 6715426 Elllail: rgf-wp@erigeosciences.colll
Loccltion: GarnathC'l St. near Arbaeen St. interseclion, Mushrefclh District, Jecldah
TEST REPORT
ATIERBERG LIMIT DETERMINATION
ASTM D 4318-17e1
CLIENT : NEOM Company PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5 / TP- 03 REPORT DATE: 29.01.2022
SAMPLING DATE: - TEST START DATE: 18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE: 20.01.2022
SAMPLED BY: - ENV. CONDITION TEMP. : 24.0 Uc HUMIDITY: 47%
BOREHOLE NO. : LD-5/ TP- 03 DEPTH (m): 0.60 SAMPLENo.: B-1
Description of sample: Brown, well-greded SAND with silt & gravel. Preparation method: Dry
LIQUID LIMIT
RUN No. 1 2 3 4 5
UISHNo.
WI'. OF WET SOIL + CAN gnls.
WI. OF DRY SOIL + CAN gills.
WI'. OF MOISTURE gms.
Wr.OFCAN gUlS.
NO. OF BLOWS
..... =
=
LL: -
c:
.2l
c: =
= Plastic limit cannot be
u
0
....
=
= determined/NON PLASTIC
PL: NP
.2l = -
=====
III
PI :
s:
Number of Blows
APPROVED BY:
-_.--_.._--_.._--_._------------_.._-
(Lab.lllcharge)
Cop~'righl of this dOl"ullwnt is oWIlPd by HCF, it m.1Y nol bt' l'l'J11 oduced p:'\l"l'pl wilh pJior wrilll'll l1l'rmissioll from IIw rOlllp,lll,\'.
RGF-JED·PIIY-50IL-02-03
20.01.2020
~~-~--~==.'-." 1.::...(..;;•...1.....=.,-0 IjI'.:.~
·2.d ~ 4:?~ I ~
tqf~m,~ f ~'" 1.:'
. :iZ)
1,1<Ji ~ C;\ '\::n.Olae2n~
""""""._"""",=,1""""",&.000.00(>9."
i
.:==;';~:;;,J RIYADH GEOTECHNlaUE & FOUNDATIONS CO.
",......~ ..-'i' h,~ 4,;-~" =,.
.
J,,> J'"
,.\.~""!'\.,!A.,:,, V"
P.o. Box 9182, Jeddilh 21413, KSA Telephone: +966 (12) 6715621 /6176860 fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Lociltion: Garn(lthil St. near Arbaeen St. intersectioJ1~ ivlushrefah District Jedd<lh
TEST REPORT
ATIERBERG LIMIT DETERMINATION
ASTM D 4318-17el
CLIENT : NEOM Company PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5 / lP-03 REPORT DATE: 29.01.2022
SAMPLING DATE: - TEST START DATE: 18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE : 20.01.2022
SAMPLED BY: - ENV. CONDITION TEMP. : 24.0 Uc HUMIDITY: 47%
BOREHOLE NO. : LD-5/ TP- 03 DEPTH (m): 2.00 SAMPLENo.: 5-5
Description of sample: Brown, well-graded SAND with silt & grevel. Preparation method: DIy
LIQUID LIMIT
RUN No. 1 2 3 4 5
DISH No.
VIT. OF WET SOIL + CAN g111S.
....C =
=
LL: -
....c
Q)
0
=
= Plastic limit cannot be PL: NP
u ~
...
....
Q) =
r- determined/NON PLASTIC
PI :
5:'"
I -
f--
Number of Blows
---_.. -----~----.-.---~-------.-- ~ .... ----------.-.-.-~.-.-------.-.----- ... -- .. --...-- .. __ .. __.... _----_ .... _... _... --------_ ..._---------._.---_.. ,---" .. _.._----------- ---
(Lab. Illcharge)
Copyright of this dOClIlllt'1l1 is oWllPd b.v RCF, illlld~' not lx' I"q1t"()dUn'til'Xl"('pl with prior wriltell Iwnnissioll frolllihe (Olllpllily.
!(GF-JI·D-PIIY-5011.-01-o:l
10.01.2020
V I" ~ -Y if0..) t~ A.../
f ~I;III~"".~ [~
t:.A....: ..-l......::....""(j _.... __ _ -~i,= ~.
tr\ lOllYHlU2tl~ "\<~~"'>;'t"' • .:!..V""
t.i...~tudt.~'ty~;I'l)'/c.upnmG.uoo.oo()~J.I{ Jl,iJ":".w-" jU-~,J! b.~ :Y.1,r-:.< ~U U':~
P,O, !lox 9182, Jeddah 2"1413, K5A Telephone: +966 (12) 67156'21 I 6"176860 Fax: +966 (12) 6715126 Email: rgf-Ivp@erigeosciences,COI11
Location; Garniith.:lSt. HPar Arh:lecnSL intersection.. ivlushrefah District Jeddl:lh
TEST REPORT
AITERBERG LIMIT DETERMINATION
AS1M D 4318-17el
CLIENT : NEOM Company PROJECT NO. : 21J'J037
PROJECT: NEOM Desalination Plant to Guyed Transmission System
SAMPLE SOURCE: LD-S./TP - 04 REPORT DATE: 29,01.2022
SAMPUNG DATE: TEST START DATE: 18.01.2022
SAMPLE RECEIVING DATE: _ ..... - TEST FINISH DATE: 20.01.2022
SAMPLED BY: - ENV. CONDITION TEMP. : 24.0 U c HUMIDITY: 47%
BOREHOLE NO. : LD-5/ TP- 04 DEPTH (m): 0.60
........
SAMPLENo.: B-1
Description of sample: Brown, iVeU-!;!,CuCU GRAVEL with sand. Preparation method: Dry
LIQUID LIMIT
RUN No, 1 2 3 4 5
DISH No,
WI'. OF WET SOIL + CAN gIns,
WI'. OF DRY SOIL + CAN gillS.
i wr.OFCAN gms,
I Wr,OFDRYSOIL gIns,
II MOISTURE CONTIO~ 'Vi)
NO. OF BLOWS
...c: I LL: -
I--
sc: -~ Plastic limit cannot be
0
() =
= PL: NP
'
s =
=
determined/NON PLASTIC
-
<II
:;: = ..
PI :
Number of Blows
TESTEDny: Ahmed CHECKED BY/ HEVIEWED ny; .._.__ ,~(~d_ Asnd Abbas_ _. __
APl'nOVEDBY:
(Lab.lllcha,w:)
Copyright or this d(KUmrllt is 0\\'11('(1 hy RGL H 11M;' not lx- rt'pmducpd (>xn~p' with prior wriU('1l I'l(>nnis.<;ioll (rom lh('fOmprlIlY.
I,Cl'-jED-1'1IY-SOIlA)2-03
2{),01.2020
tC f ~ .
. An
ERI . ...
. ="'",",,, L=__
r------'"""~"'"~, t.:A..;;-l.;...----U/~·.~~ t./~~I~
; [, 'Cb
I:
l§~~ L\~ UmJ'"dlJa"'I.1yC<>m""ny":"p"",~,?",,,IlOO$." J,,~p.'J"'''"''''~_'hP';'''h'';>
~ Ch'1010~6aWe;
p,o. Box 9182, jeddah 214]3, KSA Telephone: +966 (12) 67]562] / 6·176860 Fax: +966 (12) 6715426 Email: rgf-IVp@€rigeosciences.com
Location: Garnalha St. near Arbaeen St. intersection, lvlushrefah District, Jeddah
TEST REPORT
ATIERBERG LIMIT DETERMINATION
ASTM D 4318-17el
CLIENT : NEOM Company PRO}ECf NO. : 21J4037
PRO}ECf: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5/ TP- 04 REPORT DATE: 29,01.2022
SAMPUNG DATE: - TEST START DATE: 18.01.2022
SAMPLE RECEIVING DATE: - TEST FINISH DATE: 20.12.2021
SAMPLED BY: - ENV. CONDITION TEMP. : 24 Uc HUMIDITY: 47%
_._--_. __ ._...__..------- -- ._-_._--
BOREHOLE NO. : LD-5/ TP- 04 DEPTH (m): 150 SAMPLENo.: S-4
Description of sample: Brown, well-graded GRAVEL with silt & sand. Preparation method: Dry
UQUID UMIT
RUN No. 1 2 3 4 5
DISI-INo. ULP M,02 LVL
WI'. OF WET SOIL + CAN gnlS. 30,22 30.00 29,97
WT, OF DRY SOIL + CAN gms. 76.90 26.36 26.33
WT, OF MOISTURE gills. 3,32 3.64 3,64
wr,OFCAN gillS. 14,33 13.45 14,20
WT. OF DRY SOIL gills. 12.57 12.91 12,13
MOISTURE CONTENT l'li, 26.41 28.20 30.01
NO. OF BLOWS j4 L4 I::>
31
30 LL: 28
....c:
~ 29
0 PL: 21
u •
... 28
*5: 27
PI : 7
26
10 Number of Blows 100
(Lnb, Incharge)
Copyright of this dOClIll1l'nt is OWIll'd hy Rcr, illll.l~' not lX' rt'produC{'d (';'\.Cl'pl with prior wriUPIl ppnnission from Ill(' (OlllllclIlY.
r~GF-JI:D-PIW-50fl,-D2-03
20.01.2020
CL:-L:-'(I.'J).~-dif~."JI~
f'qf~."""" 'Cf\ lO1'01aam'a _ __
tJ.mfMdL~~JCiQ:)lU.da.ot.)(j.>ooos"t::t
P.O. Bo, 9182, jeddah 21413, KSA Telephone: +966 (12) 6715621/6176860 P.lX: +966 (12) 671&126 Email: rgf-wP'ID'rigeoscien.:es.rom
Location: Gam a thil St, n(;'(1r Arbaeen St intersection, rvlushre(ah District, ]eddah
TEST REPORT
ATTERBERC LIMIT DETERMINATION
AS'IM D 4318-17el
CLIENT : NEOM Company ........
PRO]ECI NO. ; 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission Syst~
SAMPLE SOURCE: LD-S/ TP-OS REPORT DATE: 29.01.2022
SAMPLING DATE; TEST 8TART DATE: 18.01.2022
SAMPLE RECEIVING DATE: TESTFINl8H DATE: 20.01.2022
SAMPLED BY: - ENV. CONDITION TEMP. : 24.0 tiC HUMIDITY: 47%
BOREHOLE NO. : LD-S/TP- OS DEPTH (m): 1.20 SAMI'LE No. ; B-2
Description of sample: Brown, silty SAND with gravel. Preparation method: Dry
LIOUID LIMIT
Rill," Nu. 1 2 J 4 G
DISH No.
• WT. OF WET SOIL + CAN gms. ----- ....... ~
wr.OFCAN gUl.4).
LL:
....s:: t======
'======.
J!ls:: =
= Plastic limit cannot be PL: NP
0
0
.... =
= determined/NON PLASTIC
~ r- PI : -
s: I
Number of Blows
APPROVED BY:
----_._
(Lab. Jllchmge)
Copyrighl of this donmwnt is owned hy HGF, it Illll;" nol ("l\' frprodtKt'd ('xn'pl with prior written pf'rmis.<;ion from tilt' romp.lIlY.
RGF-JED·PI·IY·S(111.·1)2·I).j
2().OI.2020
" f 1.:..A...; ..,A_;;;...,..... OI,~- --1! ~0,..JI~A---
- -
(C
~ ...... ERI
~
en ~010~(l6Z~\J.
~~ ~-
J~/"""" <h".r',t"'~""'J-.~ ""~"
t...,."""t.."""'yC--,yl ""'"...." •. OOO,OO<.l S.ll
AtYADH GEOTECHNlaUe .& FOUNDATIONS CO.
\""',,\'A"~~-<"y
r.o. Box 9'182, Jeddah 21413, KSA Telephone: +966 fl2) 6715621 / 6176860 Fa" +966 ('12) 6715426 Email: rgf·wpIDerigeoscienccs.com
Locution: Ganmtha SI. near Arb.:leen 51. intersection~ ~vlushrefah District, Jeddah
TEST REPORT
ATTERBERG LIMIT DETERMINATION
ASTM D4318-17el
CLIENT NEOM PROJECl NO. : 21}4037
PROJECT : NEOM Transmission
SAMPLE SOURCE: REPORT DATE: 29.01.2022
SAMPLING DATE: TEST START DATE: 18,01.2022
SAMPLE RECEIVING DATE: TEST FINISH DATE: 20.01.2022
SAMPLED BY: ENV. CONDITION TEMP. : 24.0 Uc HUMIDITY: 47%
BOREHOLE NO. : LD-5 TP - 05 DEPTH (m) : 2.00 SAMPLE No. : 5 -5
Description of sample: Brown, well-graded GRAVEL with sand. Preparation method: Dry
LIQUID LIMIT
2 3 <1 5
LL:
1:
~o Plastic limit cannot be PL: NP
u
determined/NON PLASTIC
I PI :
Number of Blows
PLASTIC LIMIT
RUN No. 2 :l
DISH No.
wr. DF WET SOIL .. CAN :1111.<;.
gIll,).
gms.
gm.'. i.
gnl<).
{lA,
AI'I'HOVED BY:
(Lab. Incharge)
CopYfi~~ht of this donll1lt'lll is oWlwd hy HGF, H may nollx" ff·prothKf·tI (·x.((·pt with prior wriHt'n Ix-"nnission from tlll-'(omp(m~.'_
RGF·)ElH'IIY·50IlA)2·03
20012020
AnERt
P.O. Box 302"11r Y~nbu AlwSlnalY;'Jt'i. MY,AS 51.000. KSA Ttl:lt:phone! ,t966 t:t4) 32SO£.l92 J 3250993 fax:- -t966 {14} 3250946 Email: rgf.yanbu<iPct!gcoKlenccs.com
LOCidtlotU J\I-Naw.:lmmd Stt~e~ Hai A'-M~han ()lstrid~ R.C.~ Yanbu At-Slnatyah
NON-PLASTIC
WT DISH
gms
%
..... LL
r::
.er::
o
U
.... PL
.e
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
M.lrfan
Tested By: _ _ _ _ _ __ Checked By/Reviewed By: Saeed Akhtar
-------
Approved by: Awais Nisar Yasin
L I QUI D LIMIT
RUN NUMBER 1 2 3 4 5
DISH No.
WT WIT SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
....I:: LL
.lBI::
o
U
... PL
.lBtil
~
Number of Blows
PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER z 3 CONTENT
DISH No.
WT WIT SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
A VE. PLASTIC LIMIT
RGF-YAN-PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
·CA•.;_l..;../U I~ =;: ~& t/ V.) I ~
An Eftl Company RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. Box :302-11. ¥anhu AJ_slnaiY3h. MVAS 5:1000~ KSA "Tcl~phone~ ·t956 (14) 325099-2/3250993 Email! tBt~yahbu@~tl6(:'osdenc:e!i:.(OJTl
l(>CJt1on; "'t-NaWtli:und st:r-'Get~ H",; Al·M;,h:an Olstrlct~ AI-SlnoJ'Iah
PROJECT: Neom desalination plant to sayal transmisssion system.(LD-5) DATE SAMPLED: 30/12/2022
SAMPLE SOURCE: TP 07 DEPTH: 1.20m DATE RECEIVED: 01.06.2022
SAMPLE DESCRIPTION: Grayiesh Brown Well graded SAND with silt ft gravel. SAMPLE NO.: B-2
ENVT.COND.TEMP.: 23.9 DC HUMIDITY: 42% ----
STARTED DATE: 19/0112022 DATE COMPLETED: 21/0112022
L I QUI D LIMIT
RUN NUMBER 1 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
gms
SOIL gms
%
NO. OF BLOWS
..... LL
c:
.e
c:
o
<.J
... PL
.e
I'll
~
Number of Blows
PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN-PHY-SOll-OZ-04
01-08-2021 Copy Rights Reserved By RGF
CL:-L;../ul,~Ajv.)l~
.. .,... ..
An
----~
EAI Company
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. Hox 30211, Y:lntn; Ak<;lnaly,:Ifl. MYAS 51000~ KSA Tclcphone~ ,.. 966 {l4} 3250'J92 J 3250993 r.<:lX! "t966 (14) 3.2!:.O9.46 Ern:tl~: rSf~ynnbu@crlscosdencc:s.com
loc.<:Itforu ",t-N3W3nimd Str~t. H:li AI-Mnh~n 01strlct.. H.C... Y.<:Iobu A.I·.sfnalyah
PROJECT: Neoro desalination plant to gayal transroisssion system. (LD-5) DATE SAMPLED:
-----1
SAMPLE SOURCE: TP 07 DEPTH: 2.50m DATE RECEIVED: 01.06.2022
SAMPLE DESCRIPTION: Greyish Brown poorly graded SAND with silt a gravel. SAMPLE NO.: S-6
0
ENYT.COND.TEMP.: 23.9 C HUMIDITY: 42%
STARTED DATE: 19/01/2022 DATE COMPLETED: 21/01/2022
L I QUID LIM I T
RUN NUMBER 2 3 4 5
DISH
WT WET SOil + DISH gms
WT DRY SOIL + DISH gms
gms
NON-PLASTIC
WT WATER
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
..... Ll
!:
.f!:!
c
o
u
... PL
.....
<ll
ro
:l:
Number of Blows N-P
PI
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WT WATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN -PHY-SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
P.O. flox 30271, Yanbu AI.SlnaIY~h.. MYAS 51000~ KSA T~I~phot1~= ·t966 (14) 32~tYJo92/32509!}3 fax: ·.9&6 (14J 325091\6 EmOlU! rB"r-yat1bu@~rlB"~o5d~nces.coM
location: AI-Nawanand Strcot, Hai At-Mahan District. H.C.• Y.mbu AI·Slndlyah
PROJECT: Neom desalination plant to gayal transmisssion system.(LD-5) DATE SAMPLED: 02.01.2022
SAMPLE SOURCE: TP 08 DEPTH: O.60m DATE RECEIVED: 06.01.2022
SAMPLE DESCRIPTION: Brown Silty SAND with gravel. SAMPLE NO.: B-1
ENVT.COND.TEMP.: 24.6 DC HUMIDITY: 42%
STARTED DATE: 19.01.2022 DATE COMPLETED: 21.01.2022
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WT WATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
....c LL
.l!l
c
o
U
" PL
....OJC1I
5:
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOl L gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
M.lrfan
Tested By: _ _ _ _ _ __ Checked By/Reviewed By: Saeed Akhtar
----------
Approved by: Awais Nisar Yasin
RGF·YAN·PHY ·SOIL·02-0~
01·08·2021 Copy Rights Reserved By RGF
l.:,L:-l.:,./U I!J ~~ if L:?~ I~
AnERI RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. Box 302'1l~ Y.;mbu Al~stn..ly:ih,. M'IAS 51000, KSA Telephone: ·t966 (.1.4) 3250'''>92/32!)09~3 fa:l«:: '~9S6 (14) 3250946 Email! r6t~y.3t'lbu@etlBcosdeJ:H;4"!!f..r;()",
loc.l.tlon: AI-Nawanand Strcat, Hai AI~Mahan OJstrlct~ B,CA Yanbu At·Slo;)'I'Iah
L I QUI D LIMIT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH
WT DRY SOIL + DISH
NON-PLASTIC
WTWATER
gms
%
NO. OF BLOWS
.....I: LL
$
I:
o
U
... PL
J!l
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN-PHY-50IL-OZ-04
01-08-2021 Copy Rights Reserved By RGF
GL:A...:../LJI,:.;: ..A7~ ~~.) I ~
An ERI Company RIYADH GEOTECHNIQUE & FOUNDATIONS CD.
p.o. Box 302·,1. Y.1obu At-stnalyah. MVAS &1000, KSA Telephoru:~~ ,t966 (l.4) 3250"):92/3:250993 Fa)l~ '.%6 (14) 325.09.0.16 Em.. n! tgf-y.1Xtbu@erlgco!ic}ences.com
loeatlOrl\ Ar~Nd.w~mmd Stteat~ Hal AI~Mahan Dlstri<l. R.C•• Yanbu AI-Slnaly,:ah
L I QUI D LIM I T
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
MO. OF BLOWS
..., LL
c
.ac
o
U
.... PL
.a
~
Number of Blows PI N-P
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH
WT DRY SOIL + DISH gms
WTWAT£R gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF -YAN-PHY·SOIL-OZ-04
01-08-2021 Copy Rights Reserved By RGF
"""--"---==Cl:.-L;../ UI, ~~ J:' '-:?.) I ~
AnEIU RIYADH GEOTECHNIQUE & fOUNDATIONS CO.
P.O. Box 302', I, Vanbu AI~S!n~Il';.'Ih~ MYAS 5.1000. KSA relephon.e: -t!)&6 {-'iil) 3250992 /3250993 fd"'! l-9S6 (14) 3250946 Emalll rgt~y ..mbtJ@ede~05dent:t'~_com
I,,('tc()tiom AI·N~wannnd Str-e~t~ H~l )\1~Milhtm DT£ttict~ R.C.~ )'anbu AI-Sioalyah
L I QUI D LIM IT
RUN NUMBER 2 3 4 5
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
NON-PLASTIC
WTWATER gms
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
NO. OF BLOWS
..... LL
t:
.....Q)
t:
o
U
!o PL
.....
Q)
I'll
~
Number of Blows N-P
PI
NATURAL
PLASTIC LIMIT
WATER
RUN NUMBER 2 3 4 CONTENT
DISH No.
WT WET SOIL + DISH gms
WT DRY SOIL + DISH gms
WTWATER gms
NON-PLASTIC
WT DISH gms
WT DRY SOIL gms
MOISTURE CONTENT %
PLASTIC LIMIT
AVE. PLASTIC LIMIT
RGF-YAN-PHY -SOIL-02-04
01-08-2021 Copy Rights Reserved By RGF
rqf~~ CR 'O_1£n("~
~ rJ" 0..) r::J::'.,.~
t.:...-l.:.A..,.;....... (J I, ;:,:it •;:;;
Um\'!Xl&i(>I)J!.ily_CQf·fl;~JC~~!~H>W.OOi)SJt
- -
.)\f,;;;~" ,)\1.."...,.",)J 4.1)# lJ:J,....,....~J
~
l'\'\"''\.''A~~ .....__
lS'" ~
RiYADH GEOTecHNIQUe &. FOUNDATIONS CO.
p.o. \lox 9182, jeddah 21413, KSA Telephone: +966 (12) 6715621/6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
TEST REPORT
MODIFIED PROCTOR TEST
ASTM 0 1557-12 (METHOD-C)
CLIENT : NEOM Company PROJECT NO. :
-21J4037
-....-
PROJECT: NEOM Desaii~ation pi;;;:~t to Gayal Transmission System
SAMPLE SOURCE: LD-5 / TP - 01 REPORT DATE : 29.01.2022
SAMPLING DATE: ..................-
-
-....
TEST START DATE: 20.01.2022
SAMPLED BY : R.G.F TEST FINISH DATE: _.. ~~·V··.
21.01.2022
BH/TPNo. : LD-5 I T1' - 01 SAMPLE No. : B 1 DEPTH(m): 0.60
MOULD No. : IH-03 Wt. of Mould (gIll) : 5112 Voluille of Mould (ee) : 2123
TRIAL No. 1 2 3 4 5 ~
WATER ADDED % 2 4 6 8 10
'NT WET SOIL + MOULD (WET) gms 9666 9863 10101 10076 10069
'NT WET SOIL gms 4554 4751......
-_ 4989 4964 4957
WETDENSIlY g/cm' 2.145 2.238 2.350 2.338 2.335
DRY DENSITY
----~-~ ............. _ %
J
2.13
2.10
4.10
2.15
6.23
2,21
8.26
2:16
10.12
......•... _._----- - - _......_......
2.'12
!l;/cm
~ lil;;
;
BroW'}Ll.Ne1t9@9':9 SAf\J!?\f\Iith:;i!t & gravel. ._- ~~----""'----~ 2.20
! " ::: .. I .....
V N
:
t . I" ~: .
2.16 .. ... .
REMAR1<S: ~
rJ')
iii 2.14
...
.... 1\ I·······
l····
::.
......
TESrEDBY: Faiy<lz/Narejo
0
2.12 ..
! . ..
1\
CHECKED BY / HEVIEWED BY : Syed Asa:~!~~I:'a.<;_.__. 2.10 /:
. .
. ..
APPROVED BY : 2.08
.... ~-~-~--.-.----------------
(LAB.INCHARGE) 1 2 3 4 5 6 7 8 9 10 11
Moisture Content (%)
Cop~Tight of this document is OVVJ1l'd b~' RGP, it l1ldY not btl n>proLhKl.)d l'XH'pt will! I,rinr wri!tpn pennission (rom tht, fompany.
RGF-Jl:D-H1Y-SOIIA1Hl·1
20.01.2020
-..--~ ./ -:; --AI"
~
if c;.....) I ::f
"t.::'A...;..-f...::--rfJ J-' ::-v. :-.:!"',...,....;
f An
ERI
~pnny
I·~
..•._.. h-h ....
-=_.G~~.11
-;;J
..
W'
""""'~ ~i'bl"ty G€OTECHN,QUE
. ·;':L_ RIYADH C.""'•. ..I',~"",
m_Uu.'~".:;::,=''':...
OR
J~'
'~1-o1r;f\29-!;,
OO<l.OOO S.R
_
,
..,..
~_\.\\'\ .... .3~_.....
",', J ••, .... ··h)-- P<
P.O. !lox 9182, jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf,wp@erigeosciences.com
Location: Garnatha St. near Arbaeen St. intersection, Mushrefah District, jeddClh
TEST REPORT
MODIFIED PROCTOR TEST
ASTM D 1557-12 (METHOD-C)
CLIENT : NEOM Company PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LO-S / TP - 02 REPORT DATE: 29.01.2022
SAMPLING DATE: - TEST START DATE : 20.01.2022
SAMPLED BY : - -"- .--"-.. --~
R.G.F
..---.----------.--.-----.-- .. ------
TEST FINISH DATE: 21.01.2022
-_._--
BH/TP No.: LD-5 / TP - 02 SAMPLE No. : B-1 DEPTH (m) : 0.60
MOULD No. : IH-03 Wt. of Mould (gm) : 5112 Volume of Mould (cc) : 2123
1RIALNo. 1 2 3 4 5
WATER ADDED % 3 5 7 9 11
WT WET SOIL + MOULD (WID) gills 9615 9812 10020 10018 10010
WTWETSOIL gills 4503 4700 4908 4906 4898
WET DENSITY g/cm3 2.121 2.214 2.312 2.311 2.307
, ..
'C'
:i J
f: ."\
.... ..
.. ..
MAXIMUM DRY DENSITY (glcm3) : 2.16
iO 2.14 ..
II 1\
..
7.0% E ...
...
OPTIMUM MOISTURE CONfENT : ~ . ..... . ....
.9 2.12 ..... . ....
II
HEMARKS: ~
'iii
e 2.10
.... . . ..
1/
._ ...
r\
.....
.. '
'
.
. . .....
I'
0
Q)
V \
TESTED BY: FaiyazjNarejo '5 2 .08 I
2.06
/ ...
.. .
Cop~Tighl of Ihis d(Kllllll'1l1 is mVlll'd h~' RGF, il nM~' I1nllw rt'prodllCl'd l'xcl'pl \vilh prIor \\'nllpll )lL'rmissioll from IllP compall~·.
I~GF· /l:U·PHY·SOll.·O-Hll
20.01.2020
./ -7.AJ· ,I-"-~
l.:.A_;__ ~t)',::_tio ~Jl""""..'" if0./1::J~
~.
f ~_••••
Eftl I~-, [,~-ll "'h,":::'~)h"""'~~='"
_~p"ny I=- _. , ; :. _
eR l0101('.n?-Br.. -
Un'lqdV.",'ilyC"""""."IC",,•• 'C.\)O(>.OOOS.H
RIYADH G<EoreCHNIQUe & FOUNDATIONS CO.
..l'J~yJ..'.J"·jJi»''''''·h_'''''''''''
_. ~ ~.\.\''''l''''''''';:;' ........
P.o. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf,wp@erigeosciences.colll
Location: Garnatha S1. near Arbaeen St. intersection, Mushrefah Distrkt, Jeddah
TEST REPORT
MODIFIED PROCTOR TEST
ASTM D 1557-12 (METHOD-C)
CLIENT NEOM Company
: PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5 / TP - 03 REPORT DATE: 29.01.2022
SAMPLING DATE: - TEST START DATE: 20.01.2022
SAMPLED BY : R.G.F
-~-----------.---.----.-----.-----
TEST FINISH DATE: _. ----
21.01.2022..__... _"_ .. __..
BH ITP No.: LD-51 TP - 03 SAMPLE No. : B-1 DEPTH(m) : 0.60
MOULD No. : IH-03 wt. of Mould (gm) : 5112 Volume of Mould (cc) : 2123
TRIAL No. 1 2 3 4 5
WATER ADDED % 2 4 6 8 10
WT WET SOIL + MOULD (WET) gms 9681 9899 10131 10116 10095
WTWETSOIL gms 4569 4787 5019 5004 4983
3
WET DENSITY f'/cm 2.152 2.255 2.364 2.357 2.347
CAN No. .
ZPL CR-I0 VLV MNS ZAL
.
WT. SOIL + CAN (WET) gms 2948.0 2971.0 2980.0 3000.0 2986.8
WT. SOIL + CAN (DRY) gills 2894.2 2867.0 2825.0 2792.5 2733.0
WT.OFWATER gms 53.8 104.0 155.0 207.5 253.8
-----
WT.OFCAN gms 205.0 230.0 255.0 240.0 248.0
WT. OF DRY SOIL gms 2689.2 2637.0 2570.0 2552.5 2485.0
WATER CONTENT % 2.00 3.94 6.03 8.13 10.21
---- ------ ------
3 2.13
DRY DENSITY g/C111 2.11 2.17 2.23 2.18
I ~: .:'
2.22
MAXIMUM DRY DENSITY (glcm 3
2.23 I
) :
- .. ~--.------- .. ----
;::; 2.20 ...
.... j ...•
.. -.. . .. ....
\ ..
»1/
...
REMARKS: -----_.. ---~----.------ .. ~-.----.-----.--.-
.e
~ 2.16 ...
\ ....
......
&' 2.14 I \
CHECKED BY 1 REVIEWED BY : Sycd Asad Abbas
-_._---_._--------_._- 2.12
I
/.. ~
. ~ .
APPROVED BY : 2.10
----------.-----------~----------
(LAB. INCHARGE) 1 2 3 4 5 6 7 8 9 10 11
Moisture Content (%)
Copyright of this lhKlIllll'nl is o\vncd b~' RGE ilml1Y not bt, J'l'proLiuced pxcl'pl ,,,,,ilh prior wrilll'1l pprmission fromllw company.
EGF·1E])·I'IIY·SOIIA1Hl'i
20.01.2020
rq f Eftl
. 1.:.
[~ Lv~! un"t<~·k'."'fi!yC<)m, "!\ylC
"V'::;-'~'.---
'*'
....-.-.---.--'---C"<-1
t,;,h- _ I
I.
_
en 10Hl100~~
./
.A...::•.A...::.../t) J-' ; ..Gi _ -
••,..IO.OOO.OOll$J'l
_
-;-..A.J.,
~,.-.;'" V u/I f::l~
_I""' ...
P.O. Box 9182, jeddah 21413, KSA Tel0phone: +966 (12} 6715621 / 6176860 Fax: +966 (12) 6715426 Email: rgf,wp@erigeosciences.com
Location: Garnatha 51. near Al'baeen St. intersection, Mushrefah District, Jeddah
TEST REPORT
MODIFIED PROCTOR TEST
ASTM D 1557-12 (METHOD-C)
CLIENT : NEOM
---~---~--~--~--
............. -~-~--~------
PROJECT NO.: 21J4037
PROJECT: Transmission
SAMPLE SOURCE:
SAMPLING DATE:
REPORT DATE:
TEST START DATE:
29.01.2022 ......
21.01.2022
_
SAMPLED BY : R.G.F TEST FINISH DATE: 22.01.2022
BH/TP No.: LD-5/ 1P - 04 SAMPLE No. : B-1 DEPTH (m) : 0.60
-------
MOULD No. : I1-I-03 Wt. of Mould (gm): 5112 Volume of Mould (cc): 2123
--------- -----
1RIALNo. 1 2 3 4 5
WATHRAUUED % 2.5 4.5 6.5 8.5 10.5
WT WET SOIL + MOULD (WEI) gIllS 9621 9842 10073 10056 10050
WTWETSOIL gm..'> 4509
.-......
4730 4961 4944 4938
WETDENSTIY r;/cnl' 2.124 2.228 2.337 2.329 2.326
~:6~---1---~:~:"I---~i.~~ ~-.
WATER CONTENT % 8.82
DRY DENSITY glen? 2.14 2.10
··'····I········I······I·······~·I
~ ................
I.::: .......1'....
TI~STED BY: c5 2.10
.... ...... . --- . -. -_._.
CHECKED BY / REVIEWED BY : Asad Abbas
2.08 1--,1----/
APPROVED BY : 206
(LAB. INCI-IARGE) 2 3 4 5 6 7 8 9 10 11 12
Moisture Content ("!o)
Cop~Tighl of this docUlnenl is oWf\(·d by RGE it mny not be n,"producl'd l'X(Ppl \\'ith prior \-\'littei1 Jwnnission from till,' company.
RG1·JED·PIIY-50IL-O·I-OI
2ll.O1,2020
rg f
. An
ED I
1.::.A.;__ ~(J/~=';: ~~V'l?.)t~
!,.1~~MJ!"~W'jtyConWfiY/CUp~eJ)'JO,OO~$,R. ~J.J~''\ ~*..rl.jl"'.l~ 4J~;'-~.'}U'";rJt
Cn. lOHUN.l2'65
P.o. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 / 6176860 fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.colll
TEST REPORT
MODIFIED PROCTOR TEST
ASTM D 1557-12 (METHOD-C)
CLIENT : NEOMn PROJECT NO. : ------~~
21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5 /TP - 05 REPORT DATE: -_. 29.01.2022
SAMPLING DATE: - TEST START DATE: 21.01.2022
SAMPLED BY : R.G.F TEST FINISH DATE: 22.01.2022
BH/TPNo. : LD-5 / TP 05 SAMPLE No. : B 2 DEPTH(m): 1.20
MOULD No. : IH-03 wt. of Mould (gl11) : 5112 Volume of Mould (ee) : 2123
TRIAL No. -
1 2 3 4 5
WATER ADDED %
.,,-"~~--
:1 .'i 7 9 n
\NT WET SOIL + Moui:i5 J~IrI) gms 9640 9838 10069 10048 10039
WT WEr SOIL gms 4528 4726 4957 4936 4927
.--~--"-".-
~-.-~-
~
~.
212 . 1 / 'K
Faiyaz/Narejo
..~~'
TESrEDUY:
o 2.10 ) .
CHECKED BY / REVIEWED BY : Syed Asad Abbas
-------~-------------~--
208 . iJ .
. I··
APPROVED BY : 206
(LAB. lNG-lARGE) 2 3 4 5 6 7 8 9 10 11 12
Moisture Content (%)
~
Cop~Tighl of Ihis d(KUllwnt is ()'~vn('d by RGF, it B)HY nOIl'w n'produl'l'd pxcl'pl with pri(1r\~TiHen pt'n1lissjQIl from Ow company,
RGF-JICl)·P1IY-SOIL-OI-O,1
2{Ull.20211
~~ t:.A..:.A...:../U I,:;: :;;;~ J ,-:?) I~
AnERlcompany RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. !lox 30271... Vanbu AI~SI~ly;'th. M'IAS 51000; KSA Te1~phon~! ·~9fi6 (111) 3250992 /3250993 hl)(~ .,.966 (14) 32.!.0946 ErnOllJ! r8l.Y~I~bu@Nrg.eos.denc.e!l.com
L<KiJlIon; A1-Nawanand St.r~C't~ Bu) AI·Mtloh.m Dbtrkl, R.C,# ';'ianbu Af~Slnaly.ah
pz~• •~'~.
TRIAL NO. 1 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 6021 6095 6195 6208 6170
WEIGHT OF WET SOIL gms 1859.0 1933.0 2033.0 2046.0 2008.0
WET DENSITY gm/cc 1.992 2.071 2.178 2.192 2.152
2.08
2.06
MAX. DRY DENSITY gm/cc: 2.05
OPT. MOISTURE CONTENT % : 6.4 7 2.04 ./ "-
0
-!2 2.02 /
/
'" ~
E
en
>f-
/ \
Remarks: Method "A" is used 2.00
I \
U)
Z
e.M.D.D =2. 16glcc W
0
1.98
e.O.M.e =5.25 % > /
cc:
0
1.96
1
\
I~
Tested by:
Checked By/Reviewed By:
Tufail Khan
1.94
I
Saeed Akhtar
1.92
2 3 4 5 6 7 8 9 10 11 12
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
RGF- YNB- PHY -SOIL -03-04
·Cl;...l.;./UJ,:.. '" :;;AJ'L;,t,)1;;:4/
.....,. ~
1 2 3 4 5
% 2% 4% 6% 8% 10%
OIL + MOULD (WET) gms 10589 10785 10978 10970 10945
WEIGHT OF WET SOIL gms 4358.0 4554.0 4747.0 4739.0 4714.0
WET DENSITY gm/cc 2.065 2.158 2.250 2.246 2.234
T-2 S-4 A-9 K-3 F-3
gms 419.60 432.58 446.35 435.26 440.39
gms 413.25 419.35 425.36 406.58 406.35
WT. OF WATER gms 6.35 13.23 20.99 28.68 34.04
WT. OF CAN gms 40.22 41.30 40.55 42.88 43.25
WT. OF DRY SOIL gms 373.0 378.1 384.8 363.7 363.1
WATER CONTENT % 1.70 3.50 9.37
DRY DENSITY gm/cc 2.03 2.09 2.04
2.16
o
Uj
iE 2.08
/
I \
CO.M.e =5.40 % >
0::
o 2.06 \
\
Tested by:
-----
Checked By/Reviewed By:
M.IRFAN
2.04
¥
/ I~
Saeed Akhtar
2.02
2 3 4 567 8 9 10 11
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
·~1J. mC~~Ul'~~~l?)I~
AnEIUcompany I~J'I'J'f,;t ~ RIYADH GEOTECHNIQUE & FOUNDATIONS co.
P.O~ 80x a011J.I 'fO\lllH;,AhSrt)~iyah. MYAS 51000~ KSA 'rr1cphomt +966 (14) 31S09t)2/.!f:2'SOO9:3 f-lll(! ~9b6 (14) 3250946 E:tna;1Jr tQt"y~nhu@~tlSt!~ti!~'$.t.t>m
lo~tjOfi: AJ-N~w.;m.md StN:cL H>fi A~Mli\hafJ Ob-h-Jr,;t_, n.c" Vvnbu Al-5in3ty..h
TRIAL NO. 1 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 6055 6135 6215 6228 6210
WEIGHT OF WET SOIL gms 1893.0 1973.0 2053.0 2066.0 2048.0
WET DENSrry gm/cc 2.028 2.114 2.200 1.214 2.195
Z-1 6-8 K-4 M-8
gms 425.30 421.58 422.50 437.56
gms 416.57 40 •. 398.25 392.70 401.32
WT. OF WATER gms 8.73 14.56 23.33 29.80 36.24
WT. OF CAN gms 39.60 38.25 37.55 41.28 41.90
WT. OF DRY SOIL gms 377.0 362.9 360.7 351.4 359.4
WATER CONTENT % 2.32 4.01 6.47 8.48 10.08
DRY DENSITY gm/cc 1.98 2.03 2.07 2.04 1.99
2.08 . ...
2.07
MAX. DRY DENSITY gmlcc: 2.07 /'
OPT. MOISTURE CONTENT % : 6.47
2.06
2.05
1/ "\
~ 2.04
/ 1\
E
OJ 2.03
F \
Remarks: Method "An is used
>
I-
Ui 2.02
z
/ \
C.M.D.D =2.
c.O.M.e =5.55 %
w
0
> 2.01 II
/ \
DC
0
2.00 \
Tested by: M.IRFAN 1.99 ! ~
TRIAL NO. 2 3 4 5
WATER ADDED % 2% 4% 6% 8% 10%
WT. SOIL + MOULD (WET) gms 10589 10785 10978 10970 10945
WEIGHT OF WET SOIL gms 4358.0 4554.0 4747.0 4739.0 4714.0
WET DENSITY gm/cc 2.065 2.158 2.250 2.246 2.234
2.16
\
Tested by:
------
Checked By/Reviewed By:
M.IRFAN
2.04
¢If
/ bt.
Saeed Akhtar
2.02
2 3 4 5 6 7 8 9 10 11
MOISTURE CONTENT %
Approved By:
Awais Nisar Yasin
F- YNB-PHY-SOIL·03-04
rg f ,,-~RI __,
l..:..-L:-t...::.-u 1]1 ~.& d y..),~
CR HnOH:m2~
lJm!bH:iL~ily (;.omPfl.«yli;ll~bii~.jJ#)Q,fJOOncn.
P.o. 130x 9182, jedd,1l121413, KSl\ Telephone: +%6 (12) 6715621 /6"176860 Fax: +966 (12) 67"15426 EIM;I: rgf-wP'i~rigrosciena:s.com
TEST REPORT
CALIFORNIA BEARING RATIO
ASTM D 1883-16
ICONSUl,TANT NEOM Company PROJECT NO. : 21J4037
ipROJECT NEOM Desalination Plant to G IT system ~------
0.0000 300 /
0.0125 V
;/
0.0250 101 34 f£ I·· i .....
g
0.0375 ~
'l 200
238 79
0.0500
/
1\l
>
0.0750 362 121 .§ ........ ... ....
0.1000
0.1500
486
652
162
217
16 ~ '"
100 I
/
0.2000 818
................ ...... 27:" 18 .........
O.25DO 899 :"00
0.3000 967 322
0
(J.3500 1017 :n9
0.0 0.1 0.2 0.3 0.4 05
OAOOO 1041 347 Penetration in (ins)
0.5000
APPROVED BY:
(Lab.lncharge)
Copyright of this document is owned by RGF, it I1lny not be reproduced except with prior written permis.';iol1 from the compnl1Y.
RGF·jF.Il·I'IIY·SOIl.·OR·03
2().OI.202()
CL.-t...:---v I~ ,:.;: *2.d J',-:?..) f~
tqf_ER'.~' en t010'lOi):l~
l.~l~y".€Jtnpai'l:Y/~p1ht1l;,~,~n.. n
RIYAOH GEOJ'ECHNIOue & FOUNDATIONS CO.
~~,f~J¥)"."" ~"U.i~~
P.O. Box 9182, jeddah 21413,!<SA Telephone: +966 (12) 6715621 /6176860 F,1X: +966 02) 67 J5426 Email: rgf·wp@:'€rigeosciences,colll
Loc~ltion: G.1rnatha St. near AJIA1('E'J1 S1. inlers(."Ction.. tvlushrefah District, Jccl(!i:lh
TEST REPORT
CALIFORNIA BEARING RATIO
ASTM D1883-16
ICONSULTANT : NEOM Company 1'1( IF(TNO.: 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5/ TP 01 REPORT DATE: 29.01.2022
SAMPLING DATE: TEST START DATE: 21.01.2022
SAMPLE REe. DATE: TEST FINISH DATE: 25.01.2022
SAMPLED BY _ .....
RG.F. ENV.CON: T: 24.1oC H: 46%
-
BH/TPNo.: LD·5/ TP-01 DEPTH (m): 0,6 SAMPLE No.: B 1
Mould No.: M-2 Weight: 6238 gms. Volume: 2143 em
0.0000 700
... V - --------- ..--". ~ ...
0.0125
600
/
0.0250
0.0375
270 90 2
g
c: 500
I -" ··,,1· .....
00500
0.0750
589
901
196
300
'!l
~
'"c: 400
II " I·· . .. , , "
APPHOVED BY:
(L'lb. Inch<ll'ge)
'''
Copyright of Ihis doclllllent is owned by RGF, it mey not be reproduced excepl with prior wl'itlcn permission fJ'Ol11lhc company.
RGF~JED'PI·IY,SOJI."[)g·05
7OJ)L2020
CL:-~tJl,~~~~..)I~
tq f _ERI-=" ,
eft ' O l Q 1 Q ; f . 1 2 J : m .
\"~U;oohilityComplm)"Ct:tp1tru{\,o(x'}"OOQi~U\,
1'.0. !lox 9182, jcddi1h 214]3, KSA Telephone: +966 (12) 6715621/6]76860 Fax: +966 (12) 6715426 Email: rgf-wplilerigeosciences.com
TEST REPORT
CALIFORNIA BEARING RATIO
ASlM D 1883-16
CONSULTANT : NEOM Company l'J{U)I:lCt' NO, : 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5/ TP - 01 REPORT DATE: 29.01.2022
SAMPUNG DATE: -_ .....
TEST START DATE: 21.01.2022
SAMPLEREC. DATE: TEST FINISH DATE: 25.01.2022
SAMPLED BY R.G.F. ENV.CON: T: 24.1oC H: 46%
BH/TPNo.: LD-5/IT-01 DEPTH (m): 0.6 SAMPLE No.: B-1
Mould No.: C-7 Weight: 7763 gtllS. Volume: 2083 em'
,./
0.0125
0.0250
0.0375
528 176
i
1200
1000
.... _.
v- ------- - ._. __..
RGF-)ED-PIIY-SOII.-OS·1l5
20.01.2020
rg
I '-
f
No
EAI CoMpany
---··~-------n 1..:..rL:,...,t....:;...;(Ji;!t:~ y~iff..:?...J/~
i
f 1.li~JI.i'u~""''''
,9ili) .~
- RIYADH GEOTECHNIOUe &. FOUNDATIONS. CO.
.J<l,..-',: ........ ~~;::;~;.;;
P.o. Box 9182. Jedd.11121413, KSA Telephone: ~%6 (12) 671562J /6176860 Fax: +%6 (12) 6715426 Email: rgf-wp@erigeosciences.com
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
ASThl D 1883-16
CLIENT : NEOM PROJEcr NO. : 21J4037
PROJEcr: NEOM Desalination Plant to Transmissi REPORT DATE : 29.01.2022
SAMPLE SOURCE: LD-S I TP 01 TEST START DATE: 21.01.2022
SAMPLING DATE: _ _ _ _ _ _ _ _ _ TEST FINISH DATE: 25.01.2022
SAMPLE REC. DATE: H: 46%
------------------------------ ENv.cm- - - -
24.1oC
BH/TPNo.: LD-3 / TP - 01 DEPTH 1m) : 0.6 SAMPLE No.: B-1
2.18 +1----+----f----f-----+---I
~
0 TESTED BY:
2.02 I I / I
CHECKED BYjREVIEWED BY: AsadAbbas
Copyright of this document is ovmed by RGF, if may not be reproduced except with prior written permission from the company.
RCf-jED.PHY·SO'I.·Og·05
20.01.2020
C(";.A...:...---V t, ~~..l"',-:?..Jf~
,,;
I q =~=~/~"~"~' .,J~.ir~.'~~\~;.!"'~.~~~:~~;':
.:..=:..=~=:=~==~~J RIYADH GEOTECHNIQUE & FOUNDATiONS, CO.
p,o. Box 9'1 82. Jeddah 2I,<1:'.,!<SA Telephone: +966 (12) 6715621/6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences,com
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
ASTM D 1883-16
CLIENT : NEOM Company PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Transmissio REPORT DATE: 29,01.2022
SAMPLE SOURCE: LD-5/ TP - 01 TEST START DAT 21.01.2022
SAMPLING DATE: _ _ _ _ _ _ _ _ _ _ TEST FINISH DAl 25,01.2022
SAMPLE REC DATE: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ENV. cm 24.1oC H: 46%
BH/TPNo.: LD-;; / TP- 01 DEPTH (rn): 0.6 SAMPLE No. : B-1
2.18 1 1 /1
PENETRATION AT: 0.2"
J2.14 t--+--I-~
CBR at 100%, of MDD: Z1
.!=2 CBR at 95'X, of MDD:
E 12:
T-I-:-t-:--t-+-~-1L+--l-J~
OJ
t::
>-2.10 be 1 CBR at 90% of MDD: 18
en
z
w
e2.06 1/ 1
0:: TESTED BY: Paiyazi\luned{Usma
Cl
2.02 1 1/ 1 ,I
CHECKED BYjREVIEWED BY : S)'e<if,s~~!,bbas
APPROVED BY:
1.98
15 20 25 30 35
~.8~~. ~ 55
60 65 70 75
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PI-lY-SOIL-OS-OS
20,01.1020
'C-L::-~(jl" ~~t/b;)l~
tq.f_m,--, Il CR IOltfHlfH?M
L~todt~)'~yl-C;.<:1-pftt~:Hl:~,QO()~,R,
RIYADH GEOTEC:HNIOUE:&FOUNDATiONSCO.
- -- -
.Jv~,~~\.o·~ ,J\lI~J' ~!,>~1.;lJj-~~
\~r.'t'1'V".,;:"""""
u"p
P.O. Box 9182, Jeddah 21413,](sA Telephone: +966 (12) 671562'1 I 6176860 Fax: +966 (12) 67J5426 El11ail: rgf-wp@erigeosciellces.com
TEST REPORT
CAUFORNIA BEARING RATIO
ASTM D 1883-16
CONSULTANT : NEOM Company .... ._-
PROJECT NO. : 21J4037
PROJECT: NEOM Desalinatio!1 Plant to Gayal TraJ1Smissj()~.System
SAMPLE SOURCE: LD-5/ TP- 02 REPORTDATE: 29.01.2022
SAMPLING DATE: - TEST START DATE: 21.01.2022
SAMPLE REC. DATE: TFST FINISH DATE: 25.01.2022 i
-
!
in Lbs value Ratio
300
./' r--
Inch Ib/iJ'> Cor.CBR
, .. .... [ .... ". __ .
0.0000 ;7
250
0.0125
,....
V
~
0.0250
0.0375
90 30
~ 200
7
0.0500
0.0750
207
315
69
105
~
·e
~
OJ 150
,
/ .... I .... "
!
:ll ... - ." ... .. _.-,
I
0.1500 189
.... ' .... " . ... "
I
0.2500 810 270
I····· .....
0.5000
TESTED BY: Fail'az Ahmed/Usman CHECKED BY/REVIEWED BY: Syed /\sad Abbas
APPROVED BY :
(Lab. Incha!'g")
RGF-]ED-PHY·SOII.·08·05
20.01.2020
~L-~tJl,=_" +2A~v..)l~
tq f AAERL.___ . ' ..
on 10'tiJ't~~%..
~~>"~'fJ~l$.(;Qtl,~;:tUl
.)l(~':'#~'"', ...~~,;rJ.lt
p,o. llox 9182, )ectdah 21413, KSA Telephone: +966 (12)6715621/6176860 Fax: +966 (12) 6715426 Email: rgf'lVv~rigeo5CiellCes,com
Location: Garnatha St. l1e.lr Arhaeen St. intersection. :rvfushrcfah District} Jeddah
TEST REPORT
CALIFORNIA BEARING RATIO
ASTM 0 1883-16
CONSULTANT NEOM Company PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to
SAMPLESOURCE: LD-5! TP -02 REPORT DATE: 29,01.2022
SAMPLING DATE: TE..ST START DATE: 21,01,2022
SAMPLEREC DATE: TEST FINISH DATE: 25.01,2022
SAMPLED BY R.G.F, ENV.CON: T: 24,loC H: 46%
BH!TPNo.: LO·5!TP-02 DEPTH (m): 0,6 SAMPLENo,: B 1
0,0000 700
0,0125
I .. --------- ~ ..... ...... ...
~ . .., . ,
0,0250
0,0375
259 86 N
c
lic
,S
600
500
.7 I~ .. I·······~~~ ....
(J,0500
0,0750
562
854
187
285
~
~
0>
c
'C
400 I ...
... ~
... j .
..
.
~
...
. . . . . . . . . . ..
~ ~
~ /
~ ~
TESTED BY: . . l:ai}'ilz~~ll~l(=',J /Ufil~J~ ... CI-IKKED BY /REVlEWEO BY: Syed Asad Abbas
APPROVED BY:
(l.ab,lncharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company,
RGI··)E1.J..PI'IY·SOII.·Og·05
20,01.2020
\;:"A.~..A•••.;:.../U I~ :;:: .;-dJul::?.) t~
tqf_ERI~f~T
=
OR tOH)H~~:/'1lh . . ' "~""",;,,,,,,,,,,;:,-, ...Wi
Wrntt.ud l.~lty~)' ICn:pLMt'&.()qO.OOO 6U't,. .J~,} ...~ .,,' ....<ul..V'"\1 {h?4.;tt~JJ-- ..tI>,.\-.lS' J>A
P.O. Box 9182, jeddnh 214B, KSA Telephone: +966 (12) 6715621 /6]76860 Fax: +966 (12) 6715'l26 Email: rgf-wp®>rigeosdences.com
TEST REPORT
CALIFORNIA BEARING RATIO
ASTMD1883-16
CONSULTANT: NEOM Company PRO]ECTNO.: 21J4037
PROJECT ; NEOM Desalinatio~J=lI~nt to Gayal!ransmission System
SAMPLE SOURCE: LO-5/TP 02 REPORT DATE: 29.01.2022
SAMPLING DATE: - TESTSTARTDATE: 21.01.2022
SAMPLE REe. DATE; TE'IT FINISH DATE: 25.01.2022
SAMPLED BY R.G.F. ENV. CON: T: 2tU DC H: 46%
BH/TPNo.; LD-5/TP-02 DEPTH (m): 0.6 SAMPLE No.: 13-1
Mould No.: M-10 Weight: 6073 gInS. Volume: 2115 en1
0.0000 1100 / .
0.0125 1000 /'
0.0250 472 157 ,,," 900 +----+---/--:7+----+----+-----1
o0375 .§ 800 /
0:0500 855 285 ; 700 r----+--,~--t----+---_+-----I
0.0750 1290 430 ~ 600 r----+Vr/'-----I-----+----I-----I
0.1000 1720 573 57 .~ 500 /
0.1500 2248 749 &l 400 I-----;r-+----j----+----~---__I
0.2000 2788 929 62 300 1 - - - / , f - - / - t - - - - t - - - - t - - - - t - - - - - I
0.2500 3057 1019 200 ---..--,-+---+----1
0.3000 3273 1091 100 I-cf-I---+----+----+----+----I
0.3500 3345 1115 0 I-V___-'-__-.J_ _ _- L_ _ _- ' -_ _-.J
OAOOO 3395 1132 0,0 0.1 0.2 0.3 0.4 0.5
0.5000 Penetration In (ins)
TESTED BY: Faiyaz Ahmed/Usmal1 CHECKED BY/REVIEWED I3Y: Syed A5<1<1 Abbas
APPROVED BY:
I
(Lab.lncharge)
Copyright of this doclIment is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-jEIH'IIY-SOll.OS·05
2(),OL20lO
rcq f An,EftI
cl..=.-~6t!J~:dtY42..)f~
~A;""Cf'l¢l~
('~~~"YI_~d,.OI.1O.voo
':"':':"':==-=-=:::!"-'===,~~ RIYADH GEOTECHNIQUe' 8.
_,
.. ,5:~
. ' . ",' '_"'~';\!":\.Y,;';;..;:':::'-.;-w
_..J~~"'."';"'~';Q.t.~J.t~~-~,;I~_~':I$"~,
FOuNDATIoNs CO.
1'.0. Box 9182. Jedd,\h 21413, KSA Telephone: +966 (12) 6715621/6176860 Fax: +966 (12) 6715426 Email: rgf.wp@erigeosdences.com
Location: Cilrnalh" St. near Arb"".n St. intersection, Mushrefah District, Jeddah
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
ASlM 0 1883-16
CLIENT : NEOM PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Transrnissi REPORT DATE : 29.01.20??
SAMPLE SOURCE: LO-5 TP 02 TEST START DATE: 21.01.2022
SAMPLING DATE: TEST FINISH DATE: 25.01.2022
------------------------------
SAMPLE REC DATE: ________________________________ El'·N. COl' 24.1 oC H: 46%
BH/TPNo.: LD·S TP - 02 DEPTII (m) : 0.6 SAMPLE No. : B-1
2.14
PENETRATION AT: 0.1"
1.94
APPROVED BY:
10 15 20 25 30 35 40 45 50 55 60
C. B. R. % (Lab Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-Pl-lY·SOlL·OS-05
20.0'1.2020
C--L:A....::...,(jI,:;: :"::;;~if:l:?..)f~
rqf_ERl~' c..R 1(.l1Q"tGG;z6fi.
t,.~~y~lC.u)*l'aHi,~COOS,~,
r.o. Box 9182. Jedd"i1 21413, KSA Telephone: +966 (12) 6715621/6176860 Fax: +966 (12) 6715426 Email: rgf-wp11)erigeosciences.com
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
ASTM D 1883-16
CLIENT : NEOM PROJECT NO. : 21J4037
PROJECT: Transmissio REPORT DATE; 29.01.2022
SAMPLE SOURCE: TEST START DAT 21.01.2022
SAMPLING DATE: TEST FINISH DAl 25.01.2022
SAMPLE REC. DATE: ENV.cm 24.1oC H: 46%
BH/TPNo. : LD-5 11"- 02 DEPTH(m): 0.6 SAMPLE No.: B-1
2.18 --
MAXIMUM DRY DENSITY: 2.16 glee
OPT. MOISTURE CONTENT: 7.00 tVtl
/'
/.
2.14
/ PENETRATION AT: 0.2"
-2.10
(,)
/ CBR at 100'Yi, of MOD: 62
.!:2
E
OJ
/
/ , CBR at 95'Y" of MOD:
f:2.06
/ .... .. -16
//
(J') ,
z ,
~2.02 ..
/ ., ;
f20 /"/ TESTED BY:
1.98 /"
/" . '. CHECKED BYjREVIEWED AsadAbbas
-------
/ • ••
APPROVED BY:
1.94 • ••• •
(Lab Inerer e)
10 15 20 25 30 213. It.O % 45 50 55 60 65
Copylight of this document is owned by RGF, it may not be reproduced except with prior written perm.ission from the company.
RGF-JED-PHY-SOIL-OS·05
20.01.2020
'CL:-L;.../VJ,~~r../y..)l~
. nERI~
tqf= CR"'Q10'~'\')
t.~l~li'~/~G,OQO,~(l:.,R:.
p.o. Box 9182, Jeddah 21413, KSA Telephone; +966 (12) 6715621/6176860 F"x: +966 (12) 671';126 Email: rgf-w,,®erigeosdences.com
Location: Gclrnatha st. nefU Arb.leen Sl. intersection, iVlushrefah Di5lrict~ Jeddl1h
TEST REPORT
CALIFORNIA BEARING RATIO
ASTM D1883-16
CONSULTANT NEOM Company PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5 TP-03 REPORT DATE: 29.01.2022
SAMPLING DATE: TEST START DATE: 22.01.2022
SAMPLE REC. DATE: TEST FINISH DATE: 26.01.2022
SAMPLED BY: R.G.F. ENV.CON: T: 24.1 "c H: 46%
......................... ~
/
0.0375
'l ~~ ~ . .~ ~~ ..
0.0500 270 90 ~
0.0750 405 135 !l' 200
0.1000 537 179 18 til'" V
- -- ------
1
0.1500 725 2'12
100 ' /
0.2000 913 304 20
D.2500
0.3000
0.3500
990
1074
1112
1124
330
358
371
375
0110.0 0.1 0.2 0.3 0.4 0.5
0.4000 Penetration in (ins)
0.5000
TESTED BY: Fai)'a~. i\hlJlcd/Usl11an CHECKED BY / REVIEWED BY: Syed i\sild i\bbas
AI'I'HOYED BY :
---"-------
(Lab. Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
I<GF-jED-PIIY·SOIL-08·05
20.0'1.2020
t::..A••;_~tJl~ ;: ..'" .,2 -11 ifv~ f..:r:.
tq fM_Eft,o",=, CA j(»)(l'1M~.
i.~t!.~y CoJT)~/a.apu.il;:16:.OQ(I,~$.R.
1'.0. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621 I 6176860 Fax: +966 (12) 671&126 Email: rgf-wp@erigeosciel1ces.com
TEST REPORT
CALIFORNIA BEARING RATIO
ASTM D 1883-16
CONSULTANT: NEOM '"'''"",''''y ~: 21J4037
PRO}; NEOM Desalination Plant to Gayal I [ClII::iHII:;!SIUIi System
·SAMPLF SOURCE; LD-5/ TP - 03 REPORT DATE: 29.01.2022
SAMPLING DATE: TEST START DATE: 22.01.2022
SAMPLEREC. DATE: TEST FINISH DATE: 26.01.2022
SAMPLED BY R.G.F. ENV. CON: T: 24.1oC H: 46%
BH/TPNo.: LD-5/TP-03 DEPTH (m): 0.6 SAMPLENo.: B 1
Mould No.: M-1 Weight: 6466 gms. Volume: 2126 em
TESTED BY: FaiY(lz Ahmed/Usmill1 CHECKED BY/REVIEWED BY: Sycd Asad Abb"s
APPROVED BY:
(Lab.lllchargc)
Copyright of this document is owned by RGf, it may not be reproduced except with prior written penni~sion from the company.
ECf-JED-Pl"lY-SOll.-OS-05
20.01.2020
rq
. f -=-_
_IJ:HIII c""'""'''Y
~,,,,.,~._*,~=,,,,C..l•..:-~(J/~:::: ·~~Jy~l~
..=r
\~ .,.-,.fJ.
. ;b,
[j?J. .Jl!~.
.d:J
";;" ,
,. "~.-ity~.nYJCIWIItri.",OO6,OOQ~f\ -Ji.o";'~'\·':I1!
ell 101t)1c:a)~~_
P.o. Box 9182, Jeddah 214'13.!<SA Telephone: +966 (12) 6715621/6176860 Fax: +966 (12) 671:Yl26 Email: rgf-wp@;erigeosciences.colll
Location: Garnatha Sl. near Arbat,"'en SL intersectiofl~ i\lushrerah District, Jedd!i.h
TEST REPORT
CALIFORNIA BEARING RATIO
ASTM D 1883-16
CONSULTANT: NEOM \"UII'IJ''''Y PROJECT NO.: 21J4037
PROJECT : NEOM Desalination Plant to Gaya Transmission System
SAMPl£ SOURCE: LO-S/ TP - 03 REPORT DATE: 29.01.2022
SAMPl.ING DATE: - TESTSTARTDATE: 22.01.2022
SAMPLE REe. DATE : - TEST FINISH DATE: 26.01.2022
--- -
SAMPLEDBY _ _ _ _ _ _ ..._~R~.G_:F. ENV.CON: T: 24.1oC H: 46%
BH/TPNo.: LD-5/1P-03 DEPTH(m): 0.6 SAMPLE No.: B 1
Mould No.: C-8 Weight: 7644 gms. Volume: 2137 em'
~)~75 i 1000 /
0.0500 1055 352 .£
" 800 I----+I--r
/--+----jL....-.--.f---
lJ.U:I!.llJ 1595 5.U ~ ~/ ..... ....._J .....
0.1000
0.1500
2130
2755
710
918
71
! / .....~. ~ -~ -~~ .-~-
.§ 600
I ~ ..
0.2000 3390 1130 75 400 /
0.2500 3694 1Lj 1
0.3000
0.3500
3943
4078
13"14
1359
200
0
V
f-~--4----+----+----4f---_
.. 1 - ·....
TESTED BY: Faiya;; Ahmed/Usman CHECKED BY / REVIEWED BY: Sycd Asad Abbas
APPROVED BY:
~~~.~.----~~~.-~~~ ........... ..
~ ~--~.-~ .....
(I.nb. 111rhmg<')
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF·JED·I'IIY~S()II.~08·03
20,01.2020
(('q f An
Enl ~!.
.
~----- -c..-L:-l:;./{JI,::~ -.....:;;~t/'-:?..)f~
!~ Iv~l RIYADH
~
> '~~'/
~~"'/ea.-1M'OO."""sll'<
~
~~:
OR;
P.O. Box 9182. J",ld.,h 2'1413. KSA Telephone: +966 (12) 6715621 /6176860 Fax: +966 (12) 6715426 Email: rgf-wp@?rigrosciences.com
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
ASTM D 1883-16
CLIEI\'T : NEOM PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Transmissi REPORT DATE : 29.01.2022
SAMPLE SOURCE: LD-5/ TP - 03 TEST START DATE: 22.01.2022
SAMPLING DATE: TEST FINISH DATE: 26.01.2022
-----------------------------
SAMPLE REC DATE: ENV. CO~ 24.1oC H: 46%
---------------------------
BH/TPNo.: LD-5/TP-03 DEPTH(m): 0'; SAMPLE No.: 8-1
-----------
2.20 I 7'
PENETRATION AT: 0.1"
TESTED BY:
2.04 I i/ I
CHECKED BY/REVIEWED BY: Asad Abbas
,j{
2.00 +1--+--+--+--+---1--+---:'-1 APPROVED BY:
15 20 25 30 35 40 45 50 55 60 65 70 75
C. B. R. % (Lab Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY·SOIL·08-OS
20.Q1.2020
rg f
I '- An
fR.1
r?si)-r<.bl~ ~~;-:--iJf-,.-.: ·":;;-~r./,-?..-Jf,~
I~-"- _¥~. Lwr~ft.~.y~/~6.000,OQQ~,.~. ~\(:}~~'~''''~l.~JJ~~.~.tj-O.~~ ~
ComPM'Y L ...-:-:::::........ ~;~;-=,,_ RIYADH GEOTECHNIOUe & FOUNDATlONSCO.
..
P.o. Box 9182, J,,,ldah 21413, KSA Telephone: +966 (12) 6715621 ! 6176S60 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Location: Garn(1thil St. near Arbaeen St. intersection, Mushrefah District Jeddah
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
ASTM D 1883-16
CLIENT : NEOM Company PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmissio REPORT DATE: 29.01.2022
SAMPLE SOURCE: LD-5 TP- 03 •••• < ~ • • • • • •- - - - - - - - _ . _ ••••
TEST START DA1 22.01.2022
SAMPLING DATE: - TEST FINISH DAl 26,01.2022
SAMPLE REC. DATE: - ENV.Cm 24.1oC H: 46%
BH/TPNo, : LD-5/ TP- 03 DEPTH (m): 0.6 SAMPLE No.: 8-1
---
2.20
V
/ PENETRATION AT: 0.2"
u
·2.16 / CBR at 100'}-(, of MDD: .Q
~
E
OJ
>-2.12 /
/ CBR at 95'1., of MDD: ~
2.00
/ APPROVED BY:
(Lab Incharge)
15 20 25 30 35
40 C~B. R~ 010 5 60 65 70 75 80
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
P.o. Box 9182, Jeddah 21413, KS;\ Telephone: +966 (12) 6715621 /6F6S60 Fax: +966 (12) 6715426 Email: rgf-wp<illerigeosciences.com
LOCiltion: Garnatha st. near Arb<leen St. illtersection~ fVlushrefah District, Jeddah
TEST REPORT
CALIFORNIA BEARING RATIO
ASTM D 1883-16
CONSULTANT NEOM Company PROJECT NO. : 21J4037
-----------i
PROJECT : NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5 / TP - 04 REPORT DATE: 29.01.2022
SAMPLING DATE: TEST START DATE: 22.01.2022
SAMPLE REC. DATE: TEST FINISH DATE: 26.01.2022
SAMPLED BY: R.G.F. ENV. CON: T: 24.1 "C H: 46%
BH/TPNo.: LD-5/ TP - 04 DEPTH (m) : 0.60 SAMPLE No.: B-1
.~--,
'"'.,--20itij~
Inch Ib/in' Cor.CBR -----_.__.. _. .. -.- ..--.---
.... _.
_. -~- - - - - - - - - - _.
0.0000
0.0125
wei I
fj;
0.0250 104 I 35 g I
0.0375
0.0500 204 68
c
~
~
200
/1
0.0750
0.1000
310
414
103
138 14
rn
.§
~
m
150
100
If:
!
0.1500 569 190
. ,...
0.2000 719 240 I
16
0.2500 809 270 50 ~
0.3000 865 288
o
0.3500 899 300
0.0 0.1 0.2 0.3 OA 0.5
0.4000 933 311 Penetration in (ins)
0.5000
TESTED BY :_~ Faiyaz Alllll['~l1l}...:~I~~~ ______ CHECKED BY / REVIEWED BY: Syed Asad Abbas
APPROVED BY :
(Lab. Jncharge)
Copyright of this document is owned by RGf, it may not be reproduced except with prior written permission from the company.
I,GF-JED-PI·IY-SOII.-OS-[)"
20.01.2020
c.,..L--~{jI;J ~~·~l.:?..)I~
tqf_ER'o_~ '<OR. "Q'I-o:t(l{i2B~.
~1..~nyCOf~lYj~6.'OQQ1~)f),.n .,,'!:,.,q~ ... "''U.w4)!.~~.r~.l.,l.;~~~...JI'"
P.O. Eox 9184 )eddah 214J3,!<SA Telephone: +966 (12) 671562J /6176860 Fax: +966 (12) 67J5426 Email: rgJ·'VJ1i"erigeosciences.com
TEST REPORT
CALIfORNIA BEARING RATIO
ASTM D 1883-16
ICONSULTANT: NEOM Company I'ROJELT NO.; 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5ITP - 04 REPORT DATE: 29.01.2022
SAMPUNGDATE: TEST START DATE: 22.01.2022
SAMPLE REC. DATE: TEST FINISH DATE: 26.01.2022
SAMPLED BY RG.F. ENV. CON: T: 24.1 oC H: 46%
BH jTP No. : LD-5/ TP - 04 DEPTH (m) : 0.6 SAMPLE No. : 13 - 1
llEARlNGRATIODATA 900
IJeni Load Dearing Dearing ~"""_ .. ~~~". .... ___ ~. _____.._... _ ._._._________ ~ _____ ....
V
0.1000 1144 381 38 300 / --1-.. ...... . .....
i TESTED BY: Fail'a;>; A/uncd/Uslllill1 CHECKED BY / REV1EWED BY: Syed Asatl Abbas
I API'ROVED BY: .. ~.~.."......."."..........
I (Lilb.lnch<1rg0)··-·-·
Copyril~ht of this document is owned by RGF, it nMy not be reproduc<'d except with prior written permission from the C0111I'«l1y.
RGF·JED-PHY·SOII.·U~·05
20.01.2020
~f
rc
.. A1iERI
__~_..-:.--'~
com~-,,~
m""'''':'_....
c:':~~~o
~~~'II\CL:-l.;...--'UI!t~~jl:?Ji~
:-J
..
Cfl H)1Q'":tB!1I
[ ~:.. -v~L Umiimji.1nW.Il)'_~.,.:n~/C~llnI~900~OO)$,~
H'''''~
- _ .
j\o;;,~, ~ru.' .......i)!a_~,1'-':U:J;"-':'>.u.
RIYADH GEOTeCHN10lJE & FOUNDA"TlONS CO.
p,O, Box 9J82, Jeddah 21413, KSA Telephone: +966 (12) 6715621 /6'176860 E,,: +966 (12) 6715'126 Email: rgr,wp<rerigeosciences,com
Location: Gtlrl1flth,l SI. neill' Arbacen St. inrerscction, Mushrefah District, Jeddah
TEST REPORT
CALIFORNIA BEARING RATIO
AS1M D1883-16
CONSULTANT: NEOM vOflltJ"UlY PROJECfNO.: 21J4037
PROJECT: NEOM U",::.aIlIlCH,u,1 Plant to Gayal Transmission System .
SAMPLE SOURCE: LO-S/ TP 04 REPORT DATE: 29,01,2022
SAMPLING DATE: .. TEST START DATE: 22.01,2022
----------------
SAMPLEREC. DATE:_____________ ....._ _..... TEST FINISH DATE: 26.01,202~ __
SAMPLED BY KG,F, ENV. CON: T: 24.1oC H: 46%
BH/TP No. : LD-5/ TP - 04 DEPTH (m): 0.6 SAMPLE No. : B-1
Mould No.: M-16 Weight: 6213 gms. Volume: 2141 em
~::: 1200 l/ . . . ._ . _. .
0,0250 478 159 1000 /
'E 1 .... 1 - 1..- ... -.- ...
Q.0375
0,0500
0,0750
944
1401
315"
467
!lj
J§
'"
~
800
II
I-----+-+----+----l------l----~
/-¥-----+----l-------l----~
600 \--____
1-..
RGI:·)ED-PIIY·SOII.·08·03
20.01.2020
l.::;A•.:.--,_:/l! I, ::~ •.;:;v~ iff..:?..,J I ~
fqf_BU__ ~. eft 1i>10'J~
U".,.'IE.~~oy'~MQU.O\J(>~~
RIYADH GEOTECHNlOUe&.f'OUNOATIONS CO~
.i'<l"'........
" .• 'I:;:"......."Y.;..~.."..-
w"'"' .....': .._ViJ-.""" ...'"
P.O. Box 9182. Jed,idh 21413, KSA Telephone: +966 (12) 6715621/6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeosciences.rom
2.16
PENETRATION AT: 0.1"
-
<.>
E
O'l
CBR at 95'}j, of MDD: ~
~ 2.08
CBR at 90'lIc, of MDD: II
enZ
~ 2.04
~
Cl TESTED BY: ~aiyaz Ahmed/Usma
2.00 I Y -I
CHECKED BYjREVIEWED BY: Asad Abbas
1.96 +I---+---I----+----l---I--+--+--t----'---jl---'-I-
APPROVED BY:
10 15 20 25 30 35 40 45 50 55 60 65
C.B.R. % (Lab lncharge)
Copyright of tl-us document is owned by RGF, it may not be reproduced except "ith prior written pen:nission from the company.
RGF-]El).PHY·SClHAlS-DS
20,01.2020
Cl:.A....:.,.-,fll,:-:: ·2~t./!..:?~'~
rgf_ER,_ ; CR10\01;CKi:2N
, ~l.ilIl)ility~ICmm!6,QOO;llOOS,,!,J"J';'''''''
Rl'YADH GEOTECHNJOUE! 8<
',,:~"~"'''Il' .... #-...:.:...,..
"'''"·"hl .>:t,...)I.1J..... -,.:;,l'''
FOUNOATlONSC:O~
roO Box 9182 jetldah 21413, KSA Telephone: +966 (12) 6715621 /6176860 Fax: +966 (12) 6715426 Email: rgf-wp@I?rlgeosdences.com
I.ocation: Glrnatha St. near Arbaeen St. intersection. Mushrefah District Jeddah
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
ASTM D 1883-16
CLIENT : NEOM PROJECT NO. : 21J4037
PROJECT; Transmissio REPORT DATE : 29.01.2022
SAMPLE SOURCE: TESTSTARTDAl 22.01.2022
SAMPLING DATE: TEST FINISH DAl 26.01.2022
SAMPLE REC DATE: ENV.Cm 24.1oC H: 46%
BH/TPNo.: LD-5/ TP-04 DEPTH (m): 0.6 SAMPLE No.; 5-1
2.16 1/
/ ..
PENETRATION AT: 0.2"
0 2.12
/ ·
CBR at IOO')!" of MDD: .@
..!2
E / · CBR at 95% of MDD: :g
01
>-2.08
/ CBR at 90'\\, of :MDD: :ill
!:: ·
(f)
z
W /
/ ·
02.04
>
/ ..
ex:
0
2.00
// TESTED BY: Faiyaz Aluned/Us
1.96
/ ; . .
APPROVED BY:
·
15 20 (Lab Incharcre)
25 30 35
c~'B. 11.5 % 50 55 60 65 70
Copyright of this document is owned by RGF. it may not be reproduced except with prior written permission from the company.
RGF-JED-PHY-SOIlAS.Q5
20.0'1.2020
-~. -;J:.A
'W""=~~" t.:..-L..-~U/~ :::: .~_; r..,/y.,.)f-~
J
f An Enl Compony [
r~t"'') I ~ 1i 'ow,.,,,,,,,..
................................._•........!
CR
~.~ .-,,.~~~ f t~t~rCc"n~'C~plt"il'lI3.,OQO<OQO_RR. .,J~_
,.,-""""" '"
.:\J.........1Jf"~.p.V!1.,))~.:.,..~J>U"'~
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
... .;,."...... "
P.O llox 9"182, jeddah 214"13, KSA Telephone: +966 (12) 6715621 /6176860 Fax: +966 (12) 6715426 Email: rgf-wp@.'erigeosciences.com
Localion: Gal'natha St. near Arhaeen St. intersection, tvlushrefah District, Jeddah
TEST REPORT
CALIFORNIA BEARING RATIO
ASTM 01883-16
CONSULTANT NEOM Company PROJECT NO. : 21J4037
------
PROJECT : NEOM Desalination Plant to Gayal Transmission System
SAMPLE SOURCE: LD-5/ TP - 05 REPORT DATE: 29.01.2022
SAMPLING DATE: TEST START DATE: 24.01.2022
SAMPLE REC. DATE: TEST FINISH DATE: 28.01.2022
SAMPLED BY: RG.F. ENV. CON: T: 24.1 "c H: 46%
BH/TPNo.: LD-5/ TP - 05 DEPTH (m) : 1.20 SAMPLENo.: 13-2
I
-···················~·
... -. . . .. .. - .........
, '" ...._-""-_._-------_._- - - - - - - - - - ------.
0.0125
~.-.-"
-.-= --""-"'0.'- " _ ' __ ' _ 0 ' ____ •• _ •• ___ ••• _ •••••• _ • • • • _._". _ _ _ _ _ .~ _ _ • _ _ _ _ _ _ _ _ •• ~ __ ••
'i; 250
b
./1 ··T········I··r-r
0.0250 123 41
'g - - - - -. - ,-- - - . - ._-.-. . - .. - - - _
0.0375 s ,. . -..... ~. - _. --- - - - - - -- - _.
- - --- - - - - -- - - - - ----- - -- ~-- - ----.- - ... _---_.
........._--._---- ---- -
~
"l 200
0.0500 225 75 ~
0.0750 337 112 ,~ 150 - - .- . . . . "::.1:
Jl
0.1000 456 152 I 15
I I
0.1500 629 210 100
0.2000 814 271 I 18
! I
0.2500
0.3000
0.3500
900
960
991
1018
300
320
330
339
50
0
v
0.0 0.1 0.2 0.3 0.4
I
0.5
OAOOO Penetration in (ins)
0.5000
TESTED 13Y: ____ Faiya".l\hl2.1ed/Us.'.1~".~~ ___ CHECKED BY/REVIEWED 13Y: Syed I\sad Abb".s
APPROVED 13Y :
(Lab. Incharge)
Copyright of this document is owned by RGF, it m<ly not be reproduced except with prior written permission from the company.
I(GF-JED- PlIY-SOIL-OS-03
20.01.2020
t::..-l.;....l....::,./u I, ~~ ~y..) f~
f AllIERI Compony
~m:H}l-Q'1ti;i~_.
l..~U;~1-~1 c:~nyl~~6}4Qni)(lQj) R
1'.0. Box 9182, Jeddah 2'14"13, KSA Telephone: +966 (12) 6715621/6"176860 Fax: +966 (12) 6715"126 Email: rgf-wp@erigeoscienl-es.com
Loc{)tion: Garnatha St. n(>cu Arbaeen St. intersectlon, 1vlushrefah District, ]eddah
TEST REPORT
CALIFORNIA BEARING RATIO
AS1M D 1883-16
CONSULTANT: NEOM Company PRO}Ecr NO.: 21J4037
PRO}ECr: NEOM Desalination Plant to Gayal Transmission System
SAMPI.E SOURCE: LD-5 I TP - 05 REPORT DATE: 29.01.2022
SAMPLING DATE: TEST START DATE: 24.01.2022
SAMPLEREC. DATE: TEST FINISH DATE: 28.01.2022
SAMI'LED BY R.G.F. ENV. CON: T: 24.1oC H: - - -46%
·--1
BH!TPNo.: LD-5/ "IP - 05 DEPTH (m) : 1.2 SAMPLENo.: B 2
Mould No.: M-4 Weight: 6354 gms. Volume: 2153 em
EGF·jED·PllY·SOHAi8·03
20.01.2020
_~~~==~ t'::'..l_;-~tJ J, ~~jI t../'l::?~ I~
tqf_ERI_ Cl'l10'Q'tf)Un~
~1.u.:mtl4i\ly~:n)'.te1l$14Ma.¢(l(J,()O()Sll.
RIYADH GEOTECHNlaue &. FDUNOAIlONS CO.
l,-.Y.""'l"A"'';;!>~
J';'.>v.~'-~·1U ......V. ?,".).'y4~-,/~~}~lS~
P.o. Box 9182, Jeddah 21413, KS/\ Telephone: +966 (12) 67"1562] /6176860 Fax: +966 (12) 671!Y126 Email: rgf-wp<1J.'e'igeosciences.com
l...oc.1tion: Garnath,) St. 1lE'(\f Arbaeen St intersection, l'vlushrefi\h Dislrict, Jeddah
TEST REPORT
CALIFORNIA BEARING RATIO
ASTM D 1883-16
CONSULTANT NEOM Company PROJECTNO,: 21J4037
PROJECT : NEOM Desalination Plant to Gayal Transmis~i(m System
SAMPLE SOURCE: LD-5/ TP - 05 REPORT DATE: 29.01.2022
SAMPLING DATE: -----~... --~.--~
TEST START DATE: 24.01.2022
SAMPLEREC DATE: TEST FINISH DATE: 28.01.2022
-------.
SAMPLED BY R.GF ENV. CON: T: _24.1oC
...... _ -
H: 46%
! BHjTP No.: LD-5 j TP - 05 DEJYfH (Ill) : 1.2 SAMPLE No.: B 2
Mould No.: C-9 Weight: 7747 gms. Volume: 2050 em
~ 1~ ~p.
0.0125 .--7---------~---
~ 600 + - - - 4 f - - - - 1 - - - - - 1 - - - - - + - - - - - - i
0.0750
0.1000
1350
1794
450
598 60.~ I ..... ~....._I__
0.1500
0.2000
2347
2911
782
970 65
&l 400
I ..
O.2S00
0.3000
0.3500
3192
3406
3540
1064
1135
1180
II.
200 I--+---t----~-·-I-----I-----+-----
RCF-JED-I'IIY-SOIL-OS-05
20.01.202()
-c.,L::...(_:./(jI~ .:;' •..:;;~ ifL:?~ I~
tqf~ERI~~~ CR10101~
tinlfib$fj~Con-tp.uny(~".OOO.()(,J(}$;.~
P.o. Box 9182, j('dddil 21413, KSA Telephone: +966 (12) 6715621 / 6176860 Fox: +966 (12) 6715426 Email: rgf-wp@erigeosciences.com
Loc,1tion: Garnati'M St near Arbaeen St. intersection, Mushrefah District;. Jeddah
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
ASTM D 1883-16
CLIENT : NEOM PROJECT NO. : 21J4037
PROJECT: NEOM Desalination Plant to Gayal Transmissi REPORT DATE: 29.01.2022
SAMPLE SOURCE: LD-S IF-OS
---~--.
TEST START DATE: 24.01.2022
SA MPLING DATE: - TEST FINISH DATE: 28.01.2022
SA MPLE REC DATE: - ENV.COl' 24.1oC H: 46%
BH/TPNo.: LD-51 TP-05 DEPTH (m): 1.2 SAMPLE No.: B-2
QQ
~
E I
i / CBR at 950ft, of MDD:
Cl I / :ill
> 2.08 . CBR at 90'Y<, of MDD: 12
!::
(J)
Z
;/
/ .
~ 2.04 ,/ :
~ // i
Cl
,/ TESTED BY: .'aiyaz Aluned/Usrna
2.00
;/
1.96
/ ...
CHECKED BYjREVIEWED BY: Sl~ci!'SadAbbas
• •
APPROVED BY:
10 15 20 25 30 35 40 45 50 55 60 65
C. B. R. % (Lab Incharge)
Copyright of this document is owned by RGF, it may not be reproduced except with prior written permission from the company.
RCF-JED-PHY-SOIL-QS.05
20.01.2020
t:.-l:A..:./Uf}1 -:: ·A~ V',-:?..J I~
rqf_ER'~' CR 10'tO"lGG265
L__ ~_y~!~",_SA . ,' ..."""':u,;-.""" ...""
RI'VADH GEOTE2CHNIOue & FOUNOA-noNSCO_
,J,,",....~,,"',.,..,
'1 ... \~\"t."lTA1iI'''::'-"",
P.o. Box 9'182, J,,,ili,1i1 2'1413, KSA Telepl10ne: +966 (12) 6715621 /6176860 Fax: +966 (12) 6715426 Email: rgf-wp@erigeoscienC€s,com
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
ASTM D 1883-16
CLIENT : NEOM PROJECT NO, : 21J4037
PROJECT: Transmissio REPORT DATE: 29.01.2022
SAMPLE SOURCE: TEST START DA1 24,01.2022
SAMPLING DATE: TEST FINISH DAl 28.01.2022
SAMPLE REC. DATE: ENV.Cm 24.1oC H: 46%
BH/TPNo.: LD-5 JP-05 DEPTH(m) : 1,2 SAMPLE No.: B-2
2.16 / ,
/ .,
. ;
PENETRATION AT:
~
<.,)2.12
E
17 CBR at 95'1<, of MDD: i!2
.
Cl
>-2.08
/ CBR at 90"J., of MDD: -18
!::
(f)
z
w /
/ , .. . ,
02.04
,
~ /// TESTED BY: Ahmed/Usma
0
/'
2.00
: .. CHECKED BY/REVIEWED BY: Syed Asad Abbas
./
/' .. :
1.96
' . 'I: APPROVED BY:
(Lab Incharg.e)
15 20 25 30 35 <1.%. Ft.5 % 50 55 60 65 70
Copyright of this document is owned by RGF, not be reDroduced except with permission from the company.
RGF·jED-PHY-501L·OS·05
20.01.2020
C~~(II, ~J:!f J:',-:?)l~
"",~" .. ,,"ml"'nl w:::' ~ RIYADHGEOTECHNIQUE & FOUNDA'TIONSCO.
r'..o. IJpX ;m211~ YanbU Al.Sln~lyj}·h4· MYAS 51000. K:5A tcl'CphQt~t 4f)66 (l~.)J~~l j ;S"fS¢!$3 f.a'~ +sl}.6 {14} 31S(.t9~O tflvl); r$t·~)bu.tt~{tac~kii1(.~i:~(.t)m
l,«:~.\l~l Al'Nl)jN;ml!)~ $(f~~t. Ui;!Il.I'J-M.;ihM'i ~i(t~ ,R,C,,. 'faflbV -N...$1n~Jy;m
aJR-1
PROJECT: Neom desalination plant to )Jayal transmisssion system. (LD-5) DATE SAMPLED: 1/112022
SAMPLE SOURCE: TP: 06 DEPTH: 0.60 m DATE RECEIVED: --6-/1-12--0--2--2---1
SAMPLE DESCRIPTION:
------------------
Grayiesh Brown Well graded SAND with silt & gravel. SAMPLE NO.:
SAMPLED BY: RGF
ENVT. CONDo TEMP.
-------------------------------------------
HUMIDITY: 39%
DATE STARTED: -2-3-/0-1--/2-2-~~~~
DATE COMPLETED: 27/0112022
Mould No: A·4 Weight: 6455 gms Volume: 2113 cc
900 ....
. .
Bearing 800
in value Ratio
. ~ ~
(Ib/in" (Cor.CBR)
N 700
(Ibs) c:
(in)
.~
:0 600
<1l
::; 500
I :/
ro /,/
> 400
0)
c:
....
C1I
300 V
/ ATII ?"
<1l
en 200 /
100 / AT 0.1"
0 /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
Remarks: 27
,... ..... ,... ~ ......... n.~ __
1400
Penitration I Load Bearing Bearing 1300
(in)
value
(lb/inL)
Ratio
(Cor.CBR) N
c
:0
a;
1200
1100
1000
900
800
.--/
~
~
v
---
::J
rn 700 /
> 600 ./
01
c:
.;: 500 /' AT 0.2"
rn
a; 400 V
OJ
300 ./" AT 0.1"
200 /
100 /
0 V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
RGF· YNI3·PHY·SOIL·OS·04
01.08.2021 APPROVED BY: copy1\I~.mi*,NJm1i r):{cw,in
Cl:-l;./VJ-,:~~ .;;;& J'l:?~f~
RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
p,.{), iK>x :w:.tH, "(;',,00 Al.sl";fv~h! M;vA5 Sj~ K'~ 'lit~~J}hM~! ""!,;G6 (1~)3l_~,t ~ l).:')009~ ~;oX! ~1it\6 (14) $l~O'j46 tlfl..lli: fuf,.yMtbU~l1i'iltwoot.f#Jlt:(!t.l;om
tru;,,-l:lL:UH AUil)w~t\:2n.d!\tt'~~ Hi'I:\ Al.M;lh;m rnu(kl.l\.C,~ Y;m.,.l M.•:~ltuiv.m '
alR,1
1800
. ,"
Bearing
1600 •
~---"
value Ratio ' ,
1200
~, , :"
Q)
::l 1000 / ..
>
iii
800 / AT 0.2"
01
c:
.;:
600
,/
'"
Q)
CD ;/ AT 0.1"
400
200 /
0
V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
56
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT :~N=EO=M~.____________________________ PROJECT NO: 21J4037
PROJ ECT: Neom desalination plant to sayal transmisssion system. (W-S) DATE SAMPLED: 1/112022
SAMPLE SOURCE: TP: 6 DEPTH: 0.60m DATE RECEIVED: 6/112022
SAMPLE DESCRIPTIOI\ Grayiesh Brown Well graded SAND with silt 6: gravel. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 24.4°C HUMADITY: 39%
---------------
DATE STARTED: 23/01122 DATE COMPLETED: 2710112022
2.15 I I. /'1
1.95 I ;/
RGF· YNB·PHY·SOIL·05·04
01.08.2021 Copy Rights Reserved By RGF
'Cl.::..A...;;...,..(j1-' ~~ J'Y...J I ~
An ERI Company RIYADH GEOTECHNIQUe & FOUNDATIONS CO•
.P,,()~ Do)( 302:7:t... Vanbo I\hSlt~ty~h.. MYJ\'S 51000, K-'>,A 'Tt"l~phoM! 4~6a t~4) 3?Sf:W92/ a2S0!>93 Fa,,""! ~9uo (14) ;125(1"'>46 ~m.1IH l~f-'tanbu~cf:S~jtm(:~~,~
t~Vt)nl MN~ooand St(>J:'iCl"," H~a N~Mt1h;tn O$\tkt.. ft.,., Y~flW N~'h~iy~n .
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT NEOM. PROJECT NO: 21J4037
--------------------------------------------
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-5) DATE SAMPLED: 1/1/2022
SAMPLE SOURCE: TP: 6 DEPTH: 0.60m DATE RECEIVED: 6/1/2022
SAMPLE DESCRIPTION: Grayiesh Brown Well graded SAND with silt a gravel. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 24.4°C HUMADITY: 39%
DATE STARTED: 23/01/22 DATE COMPLETED: 27/01/2022
------------------
------------------
2.00 ! /
CBR at 90% of MDD: 31
1.95
RGF: YNB-PHY:$OIL:05-04
01:08:2021 Copy Rights Reserved By RGF
Cl;.,l.:/V l, ~~.~y)l~
An ERI Comp,;,rl! RIYADH GEOTECI-INIQUE & FOUNDATIONS CO.
P~O. no. )()~11" Yanbo-Al~SWlf"'h~ MYA5 !'.1:1OOO. k$A ft:l~~ --1'%6 (Id) tll~09P21 ,):(~:) ';');1 +9()G (Iii) 3250946 t:tnAU; Tgf"Y~buO'er~~tIMKei,{(Hn
tQ(~)Jqm #'k-iJ:W~t\3n(i SHetrt~ Hal JU M;}h$tll 04i.rlt;(. H.(,,,. Y~hi;n.j Al~smal)'.lh
600
<1>
.2
500
/'
>'"
Cl 400 / -
c:
.;::
300
/' AT 0.2"
'"
Ql
CO
e/
200
7
Po U.·I
100
0
V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
0.5000 286 868
RGF· YNB·PHY·SOIL·05·04
01.08.2021 APPROVED BY: cop/lR\Wlli!ifNi5Il1lid'&;lf~irr
Cl;.,l;../(II, ~~ jl:?)I~
AnERICQl'I'l))llI'lY RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P,o. Bow J.Dl1;i~ YoH\W At..sm;yt;;h. M'lAS S1,j;')Oi). J($A -fell?phtme! ~96() (14) ~a~!ll a~~3 fax! +tJ6fi (lfi):32!tQ';l46 J;ffi~tI~ .t$f<v,:mbufY'ert~<»dern:¢$,(.qm
to('.a\Ion~AU;laWArumtl ~'1?£>L H:.31 A.t.MaJufl bidrkt.- R.t!... VanhuAMtnaivah - .
CBR-2
1400
1300
.--
Bearing
1200 ...-'
Ratio
1100
(Cor.CBR) N
~
.:: 1000
---,V
;§ 900
Q) 800 /
:::l
ro 700 V
>
en 600 /
.§ 500 /'" AT 0.2"
ro
Q) 400
V
r::o
300 / AT 0.1"
200
]I'
100
,/
o V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
RGF- YNB·PHY-SOIL·05·04
01.08.2021 APPROVED BY: copfl<l'gp,i§dlIl~A&dYJ9R&
'C~L;./ul!J~difl:?.)'~
An EBI Company RIYADH GEOTECHNIQUE& FOUNDATIONS CO.
p...o. BOlt 30:1'1" v';,mbtrA'.$I~lY,)l\. M\"AS ~1i:)()O~ x5.A lttk1!pr;toM!'! ~ij (lA) 'l~$099~1 )1~3 Ji.a)!~ .966 ('1,iJ) 3flS()~46 (man! fEi.y~but11ef(gC\)t:tl~t)(@'1..(fim
i.OOIlk¥l:: AhN~w;"'JH'td Stt.t't't. *iM .M.M;i.h:n~ O'l).lfict. R (;" vanhll AI.~~h
caR·3
1800 ..
. ... . ......
:
'''~D
.....
(Lbs)
value
(lb/in L'
Ratio
(Cor.CBR) N 1400 ~ t-'.---
oS V
:c 1200 /
Q)
:::l 1000
/' .....
iii
> 800 / AT 0.2"
01
t:
.;::
ns 600
/
ro
<IJ
400 / AT 0.1"
200 /
0 /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
Remarks:
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT :..:..:N:.=.EO=-:M:.:.;.._ _ _ _ _ _ _ _ _ _ _ _ __ PROJECT NO: 21J4037
-----
PROJ ECT: Neom desalination plant to '!layal transmisssion system. (LO-5) DATE SAMPLED: 30/1212021
SAMPLE SOURCE: TP: 7 DEPTH: 1.20 m DATE RECEIVED: 6/1/2022
SAMPLE DESCRIPTIO" Grayiesh Brown Well graded SAND with silt fr gravel. SAMPLE NO.: B·2
ENVT. CONDo TEMP. 24.4°C HUMADITY: 39%
---------------
DATE STARTED: 23/01/22 DATE COMPLETED: 2710112022
1.95 I - I
RGF·YNB·PHY·SOIL·05·04
01.08.2021 Copy Rights Reserved By RGF
CL:-l;../~/JJ ~~ if9.)f~
RrVADH (,EjEOTECHNIQUE& FOUNDATIONS CO..
'P~O. no" iO:l7'1, V.;t.nbU JL!.s';t\~~"'·h" MVAS 51.0()0~ KSA 'TcJ.epht:>nth +96& t:t4) :;lil~0992 I a2~3 f'~t);;: ~>66 (14l. 'l2SO!J46 'E~il! f"$f~ya",uu4'Weflg~tad6nc~$.:.(-()m
t1)(:)l~f)t\~_ Al·N~·'~~tXJ Slt~_~1 .. H~j N-M.;),h."n Off.trtct" ft,(:? V~II00 At·~(\~~ft
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
LlENT NfOM. PROJECT NO: 21J4037
PROJECT:
------------------------------------------
Neom desalination plant to !!Jayal transmisssion system.(LD-5) DATE SAMPLED: 30/1212021
SAMPLE SOURCE: TP: DEPTH: 1.20 m DATE RECEIVED: 6/112022
SAMPLE DESCRIPTION: Grayiesh Brown Well graded SAND with silt & gravel. SAMPLE NO.: B-2
ENVT. CONDo TEMP. 24.4°C HUMADITY: 39%
DATE STARTED: 23/01/22 DATE COMPLETED: 27/0112022
-------------------
-------------------
2.0S I AI'
CBR at 95% of MOD: 48
1.95 I I - .I
RGF- YNB-PHY-SOll-OS-04
01.08.2021 Copy Rights Reserved By RGF
r--::----~ Ct.::A..::,.-rV I, ~~J'l:?) I~
:::.:...::::.:::.=.:.::.:;:=:!....!~==dl!=! RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.O. fWlt. 30:211. 'Y.<itlbu AhSInt.Jy~h. M'(AS Sl@. KSA T('J~nm "!)uS (l-d) a1~('Y,r;)1 / a'S0993. fa..! -f~1S6 "h<1' ;,;t:'>0946 f.~:afi: r$"YMlbu@e*l$eokle-tKcu:om
.ltx:;)titm: N:·.u~\Y':,tmll)d S,tft~l.) tIJt Al.MJh~ Dhttkl... R,C.~ v:,tnb\J A1-$if'i~Iy~h
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-5) DATE SAMPLED: 2/1/Z(J2.2
------------1
SAMPLE SOURCE: TP: 08 DEPTH: 0.60 m DATE RECEIVED: 6/1/2(J2.2
SAMPLE DESCRIPTION: Brown Silty SAND w-I'-:-'t'h-g-ra-Y-e'I.------- SAMPLE NO.:
SAMPLED BY: RGF
----------~~--------------------------
ENVT. CONDo TEMP. 24.7°C HUMIDITY: 41%
DATE STARTED: 23101/22 DATE COMPLETED: 2710112022
900
in value
Beoc~
Ratio
800
~
(Ib/in" N 700
(in) (Ibs) (Cor.CBR) c:
::0
600 /
.2
Ql
500
,/
/
ru
> 400 /'
en
c:
.;:
ru
Ql
300
./
/ AT n 7"
m 200 /
100
;/ ATO.1"
0 V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
0.5000 258 783
Remarks: C.MDD = 2.16 glcc CBR @ 90 % Compaction at 0.1" 26
C.OMC = 5.55 % CBR @ 90 % Compaction at 0.2" 31
TESTED BY: M.ARFAN CHECKED BY/REVIEWED BY: C;QPpd Akhtar
---------------------- ---------------------
RGF· YNB·PHY·SOIL·OS·04
01.08.2021 APPROVED BY: CopyA'tl!l1aiS\cN&511-11 i}yCRrin
~t!) v ·~~if0~1~
f AnERlcornpaoy ,,!~J~' v';''!.
~
CL:,l.:;../U I,:.:·
- " "
RIYADH GEOTECHN1QUE & FOUNDATIONS CO.
·P.O, Box j0211~ Y~nbu Al"Si~ly:;J;h.. MY"$. Sl000 f{~A 't(!"Jt.pbon~: ·.,,)6.6 (Id) )'5(')9+)l.I3i~j
A r3){~ ..:!)6.6 t14) :U5b'j)4G fmJU: fS',Y.Jfli>u«pertgeosctM)(cs,c-Om
hJoC~t't):n: .Al.J.J3w::m::md Slrot't. Hal Ai· Mahan Ohtrkl. A"C.. V..nbu ht.5'n31v:..h
1400
Penitration I Load Bearing Bearing 1300
1200 ...
value Ratio
(lb/inL) (Cor.CBR) N'
c
:a
1100
1000
900 V
~ ----
(1) 800 /
:::l
iii 700 ./
> 600 ./
01
C
·c 500 / AT 0.2"
<II
(1) 400
./'
CIl
300 / AT 0.1"
200
,/
100
,/
0 /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
RGF· YNI3-PHY·SOIL-05-04
01.08.2021 APPROVED BY: eopy1\Wqi*.N.imG rYB@fl
Cl:.-L:./UJ,~~J't?.),~
AnERI RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
P.()~ Box 3o:~ra., Y;;Jnbu Af..s!~f~ah, MYM S1()¢(}, ';51\ '1'(!~n«!'; ..966- {It})2~:lI3::f~) t;Vi~ t!lM ,(iit} :jl'!H>i>46 £t»llfl: rg1.y.muu&effgt>Oittenuu:flm
tm:~dflm AJ..}.!;lv.ran:aruJ Sf,"l. Hal JJd~Mah.tt Uidrld. tLC,,~ Vaotw Al.SIf)."dVah
CBR"
1BOO
(Lbs) I
value
(Ib/in"'
Bearing
Ratio
(Cor.CBR) N
1600
1400 ~
..---
L'V
t:
~ 1200
(1)
::l
iii
1000 L
> BOO / ATO.Z"
OJ
t:
.;:
<U
600 /
(1)
OJ
400
;/ AT 0.1"
200
;'
a V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT :~N~EO~M~.___________________________ PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-5) DATE SAMPLED: 2/112022
SAMPLE SOURCE: TP: 8 DEPTH: O.60m DATE RECEIVED: 6/1/2022
SAMPLE DESCRIPTIO" Brown Silty SAND with gravel. SAMPLE NO.:
ENVT. CONDo TEMP. 24.7°C HUMADITY: 41%
---------------
DATE STARTED: 23/01/22 DATE COMPLETED: 27/0112022
1.95
RGF- YN B-PHY-SOIL-OS·04
01.08.2021 Copy Rights Reserved By RGF
CL:-~UI~~&ifL:?.)I.~
AnERlcol1lp;ll1)' RIYADH GEOTECHN1QUE & FOUNDATIONS CO..
Il~O" flO~--1027:l.l' Ya.n:bU AI..Sl~;Yil-h.. M'lAS 51000, K5A T(:l,phOf\e-~ --tgf>G- (34) U2!?,O!>?'l/ :l~S0993 F~)(: ~~'6 (14) 32509illi trm~U: f.gf'y~f'ibtJ~~t"i8'l}hS·dl!'Il-{'e5...eom
lO(',,;l\k)n: At·N~m.h,)nd SUt'trl.. H-iil AI·M,)P01Ifi O;;i.tt'i(\.: *,.C., V,*l\b\.I AlvSffl.utyah
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT : NEOM. PROJECT NO: 21J4037
------------------------------------------
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-5) DATE SAMPLED: 2/1/2022
SAMPLE SOURCE: TP: 8 DEPTH: 0.60 m DATE RECEIVED: 6/1/2022
SAMPLE DESCRIPTION: Brown Silty SAND with gravel. SAMPLE NO.: 1
ENVT. CONDo TEMP. 24.7°C HUMADITY: 41%
DATE STARTED: 23/01122 DATE COMPLETED: 27/01/2022
-----------------
------------------
2.15 11~-+--+-~+--f-~-.....-t-.....-j:;17:r'c:.c..·II~____
PENETRATION AT: 0.2"
2.10 I /1
CBR at 100% of MDD: 64
2.05 I j""
CBR at 95% of MDD: 46
1.95 1 ',M"
RGF- YNB·PHY-50Il-05-04
01,08,2021 Copy Rights Reserved By RGF
./ . . . -~. AI" _r"
, - , "CA..;... l.;./U I" ~>::f vl?.)I:r~
RIYADH GEOTECHNIQUe & FOUNDATIONS CO.
P.(')~ »ox ;J()2n.. Y,i)",ooMe$Ir~;;Y~h. MYAS 5lt;;lXi. t(-;sh \1rl~ph"~J 1'966 (14) !il~~2-/.):l~j. fa'JI_~ +?OO (14) 3i5i)~fI() rimall! t"'-'YMtnJePt!(I$~tie:ntC!).tOOl
to{~~~m Al·N~~_wn4_'ttW. l1~1 AJ.·Ml;I.h;)t1 1)h:1ti{t.,. R,C... YiIliJ\l Al~$ln;jl... ~h
CtJR-/
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-5) DATE SAMPLED: _. ___ _
SAMPLE SOURCE: TP: 09 DEPTH: 0.60 m DATE RECEIVED: -_.- - .
--~---------------
SAMPLE DESCRIPTION: Grayiesh Brown Well graded Gravel with silt & sand. SAMPLE NO,:
SAMPLED BY: RGF
, CONDo TEMP. HUMIDITY: 40%
26101122 3010112022
1000
Bearing 900
Ratio
800 ~
~
N
(Cor.CBR) .E
a 700
/
..
600
<lJ
.a ./
V
500
>'"
C) 400 / -.
I:
.;:: / ATO.2"
'"
<lJ
300
m
200 / A, U.·'
100 /
0 /
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
2.22 glee 32
5.35% 36
TESTED BY: W/SAL KHAN BY: Saeed Akhtar
RGF· YNB·PHY·SOIL·05-04
01.08.2021 APPROVED BY: copyPli~Il~(;}ff3Va(iin
f .. E RI,-"
Gl:A..:../YI., ~~ ifl.:?..J'~
RIYADH GEOTECHNIQUE &. fOUNDATIONS CO.
V~OA Do~: lOth, "1',)noo Ai,Si~""~hf M'fM :SiOOO, "SA It':'~hf)11<< ..$66 {:t4) ~nS0992'J ~'S<»ll r")j( ~96;6 t14}Z}~~946 fmilU: f8'·y~nb\JVer~~!cnc:oeu;orn
tM.J»mm "'''NaWA1\dlld$.lTi'i''t. W.." M-M.>ium Dhhlrt. R.l:,. 'Yanhu .lU...."i1n,.;1h..ah '
CBR·2
1600
Bearing 1500
1400
value Ratio ~
.......- .-----
L
1300
(lb/lo )
(Cor.CBR) N'" 1200
c
1100
~ 1000 .-----'
III 900 L
::l V
(ii 800
> 700 / AT 0.2"
en /
c 600
'C
<'Q 500
-/' v.
III
CO 400 sf
300 /
200 /'
100 ?
o V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
CBR@ 95 % 52
CBR @ 95 % Comoaction at 0.2" 56
TESTED BY: WISAI. KHAN CHECKED BY/REVIEWED BY: Snppr/ Akhtar
---------------------- -------------------
RGF· YNB·PHY·SOIL·05·04
01.0B.2021 APPROVED BY: copy~lifAYf{~~f1l8yoft8in
Cl.;:...l;../{J I~ ~~ J'l;-'.)';.(.::/
An IERI COl1\p.'Iny 'RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
F,O.. nOI( 1<)111 t 'fMlUu AJ~n.;Jy"h~ M'fAs ~100Q~ xSA 'felt<Pb~: "'966 {1.1) !"i~91'/ ~'$(}19)' h)l! .t;t)6 fi4) :li~946 trn-aHt flJf,y~rllm@efl8~1»'I(!oC~1,torn
t()('J)llnm Al,HAw.an:arHl '8tTf"l't Hal M-Mah.m {)khk.. R.C.. Y:mhu AJ.~lntiiv,,)h
CBH.,J
2000
Bearing Bearing 1800
value
(lb/in<1
Ratio
1600 ~
I ~
N
(in) (Lbs) (Cor.CBR) t:: ..
:c 1400
1200 ~
(J) V
2
ro 1000 /
>
OJ
t::
800
/ AT 0.2"
.;:: //
ro 600
(J)
ro
400 / ATO.1"
200 /
0 V
0.0 0.1 0.2 0.3 0.4 0.5
Penetration (in)
Remarks: 69
TEST REPORT
C.B.R. DENSITY RELATIONSHIP
CLIENT :.:.:N=.:EO::.::M~. _ _ _ _ _ _ _ _ _ _ _ _ __ PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gaya/ transmisssion system.(LO-5)
-- --
DATE SAMPLED: 22/01/2022
SAMPLE SOURCE: TP: 9 DEPTH: 0.60 m DATE RECEIVED: 22/01/2022
SAMPLE DESCRIPTIO" Grayiesh Brown Well graded Gravel with silt Ii sand. SAMPLE NO.: B-1
ENVT. CONDo TEMP. 24.3 DC HUMADITY: 40%
DATE STARTED: 26/01/22 DATE COMPLETED: 3010112022
-----------------
2.20 I "V
2.00 1 1 - I
RGF· YNB-PHY·SOll-05-04
01.08.2021 Copy Rights Reserved By RGF
-';..Ai · _ r ·
.I
~1f)
,ti1l>
vr;Iit~Gl::..-l.;;:./UI!) ~~i
- _.. c./0~,;J~
..
AnEo.company "t_~. UOAj RIYADH GEOTECHNIOUE& FOUNDATIONS CO.
p~o_ nox 302711' Y;.\n'bU Al"'SI~'iy~h" MYA$ 51000.. )!SA- T."j~pho.nc! +966 {lA) 3~S0992' J a2~3 Fu! ..1)66 (14. 3;;t50;',)46 lim"n: t$'~y.illt'lb\J~~tt6~o$dcn<·~'S-,(OM
\'<.K:~U"Jl~ At.NJW3Mn(;f :'ittlC'tt~ H.Jl Aj~M;,h4Jn Ot>ltict, n.c" Y.afl\>v N.slf,a,:Jyat.
TEST REPORT
C.B.R. - DENSITY RELATIONSHIP
CLIENT .. NEOM . PROJECT NO: 21J4037
PROJECT: Neom desalination plant to gayal transmisssion system. (LD-5) DATE SAMPLED: 22/01/2022
SAMPLE SOURCE: TP: 9 DEPTH: 0.60m DATE RECEIVED: 2210112022
SAMPLE DESCRIPTION: Grayiesh Brown Well graded Gravel with silt ft sand. SAMPLE NO.:
ENVT. CONDo TEMP. 24.3°C HUMADlTY: 40%
DATE STARTED: 26/01122 DATE COMPLETED: 3010112022
;/
/' PENETRATION AT: 0.2"
2.15 .. V ..
2.10
..
/'
V CBR at 100% of MDD: 76
2.05
--
V ' .
RGF- YNB-PHY·SOIL-05-04
01.08.2021 Copy Rights Reserved By RGF
CHEMICAL TESTS ON SOIL
LAYDOWN No. 1
TEST REPORT
CHEMICAL ANALYSIS OF SOIL
CLIENT: NEOM Comp<luy
PROJECT: NEOM Desalination Plant to Gayal Transmission S)'I:iU:!Hl (LD-01)
SOURCE:
-~
Trial Pits RECEIVING DATE; 27.03.2022
LOCATION: - i PRO) hLT NO.: 21J4037
SAMPLING
- iREPORl DATE: 29.03.2022
DATE:
SAMPLEDBY: iRGF IENV. CON: T : 22.7 oC H: 45%
~ERSTESTED
LAB. REF. No. :
O.
UNIT METHOD RESULTS
DEPTH
pH - BS-1377-3 8.74
LD-1 TP-Ol Chloride (Cl) (H20 Ext) % " 0.0565
II
B-1 Sulphate (SOg) (H20 Ext) % 0.1165
0.60 Carbonate as CaCOg % ASTM D-4373-14 8
Organic Content % AASHTO-T-267 -
pH - BS-1377-3 8.76
LD-1 TP-02 Chloride (Cl) (H20 Ext) % II
0.0495
II
Sc3 Sulphate (S03) (H20 Ext) % 0.0665
1.00 Carbonate as CaC03 % ASTM D-4373-14 6
Organic Content % AASHTO-T-267 -
pH - BS-1377-3 8.78
II
LD-1 TP-03 Chloride (CI) (H20 Ext) % 0.0055
II
B-1 Sulphate (S03) (H20 Ext) % 0.0035
0.60 Carbonate as CaC03 % ASTM D-4373-14 9
Organic Content % AASHTO-T-267 -
pH - BS-1377-3 8.84
II
LD-1 TP-04 Chloride (CI) (H20 Ext) % 0.0045
II
B-1 ) % 0.0012
0.60 Carbonate as CaC03 % ASTM D-4373-14 4
Organic Content % AASHTO-T-267 -
pH - BS-1377-3 8.72
II
LD-1 TP-05 Chloride (Cl) (H20 Ext) % 0.0285
II
S-2 Sulphate (S03) (H20 Ext) % 0.2415
0.50 Carbonate as CaC03 % ASTM D-4373-14 5
Organic Content % AASHTO-T -267 -
(CHEMIST INCHARGE)
RFG-J ED-CHE-SOIL-02-01
01.01.2015
RIYADH GEOTECHNIOUE & FOUNDATIONS CO.
P.O, SO)( 9182, Jcddah 21413, KSA Telepnone: +%6 (12) 6715621/6176860 Fax: .a.96G (12) 6715426 Email: r8f~wp@erI6€lOsdcnces,com
Location: Garnatha St. near Arbaeen Sf. Intersec.tlon, Moshrerah District. Jeddah
TEST REPORT
CHEMICAL ANALYSIS OF SOIL
CLIENT: NEOM CtCOlnt>llnV
TP.NO.
PARAMETERS TESTED UNIT METHOD RESULTS
DEPTH (m)
pH - BS-1377-3 8.82
LD-1 TP-06 Chloride (Cl) (H20 Ext) I % " 0.0115
B-2
1.10 Carbonate as CaC03
q=t ASTM 0-4373-14
11
0.0065
8
Organic Content % AASHTO-T-267 -
pH - BS-1377-3
II
Chloride (CI) (H20 Ext) %
II
%
Carbonate as CaC03 % ASTM 0-4373-14
Organic Content % AASHTO-T-267
pH - BS-1377-3
Chloride (CI) (H20 Ext) % "
II
%
Carbonate as CaC03 % ASTM D-4373-14
Organic Content % AASHTO-T-267
pH - BS-1377-3
II
Chloride (Cl) (H20 Ext) %
II
%
Carbonate as CaC03 % ASTM 0-4373-14
Organic Content % AASHTO-T-267
pH - BS-1377-3
II
Chloride (CI) (H20 Ext) %
II
%
Carbonate as CaC03 % ASTM 0-4373-14
Organic Content % AASHTO-T -267
RFG-JEO-CHE-SOIL-02-01
01.01.2015
CHEMICAL TESTS ON SOIL
LAYDOWN No. 3
TEST REPORT
U.
II
B-1 Sulphate (SOg) (H20 Ext) 0.0735
0.60 Carbonate as CaC03 ASTM D-4373-14 4
Organic Content AASHTO-T -267 -
pH - BS-1377-3 8.86
II
LD-3TP-04 Chloride (Cl) (H20 Ext) % 0.0425
II
B-3 Sulphate (S03) (H 20 Ext) % 0.0700
1.00 Carbonate as CaC03 % ASTM D-4373-14 5
Organic Content % AASHTO-T-267 -
pH - BS-1377-3 8.89
LD-3TP-05 Chloride (Cl) (H20 Ext) % II
0.0850
II
B-1 Sulphate (S03) (H20 Ext) % 0.0200
0.60 Carbonate as CaCOg % ASTM D-4373-14 5
Organic Content % AASHTO-T-267 -
APPROVED BY:
--~~~~-----"'~-
(CH
RFG-JED-CHE-SOIL-02-01
01.01.2015
rc.q f lCal
C),~
~M}
-: ;.-I..,:- -. I'"",--'\""..--'--'""'u'./....
v
VKA'
I ..- I -
j ....- .
.. .
w ~-.Ai, ,;7/ -, If:;! _"'/
- .--:,.,:>''/
... U'. 1"""...-'/
_~n~_lillillilCOmpany Il.'.~lm~ __ ~-=-- RIYADH GEOTECHNIQUE & FOUNDATIONS CO.
.
.~r"
::r
P.o. Box 9182, Jeddah 21413, KSA Telephone: +966 (12) 6715621/6176860 Fax: .. 966 (12) 6715426 Email: rBf~wp@erlBeosciences.com
location: Garnatha Sf. near Arbaeen 51. intersection, Mushrefah District, JeddOlh
TEST REPORT
CHEMICAL ANALYSIS OF SOIL
CLIENT: NEOM Company _.
PROJECT: NEOM Desalination Plant to Gayal Transmission System (LD-03)
SOURCE: Trial Pits RECEIVING DATE: 30.01.2022
LOCATION: - PROJECT NO.: 21J4037
SAMPLING
- REPORT DATE: 23.03.2022
DATE:
SAMPLED BY: RGF ENV.CON:T: 23,6 DC H: 44%
__' 0
APPROVED BY:
~(C~H~E~r~~~~~--
LAYDOWN No. 5
TEST REPORT
TP. NO.
PARAMETERS TESTED UNIT METHOD RESULTS
DEPTH(m)
pH - BS-1377-3 8.92
II
LD-5TP-01 Chloride (Cl) (H20 Ext) % 0.0055
II
B-1 Sulphate (S03) (H20 Ext) % 0.0030
0.00~0.60 Carbonate as CaC03 % ASTM D-4373-14 4.00
Organic Content % AASHTO-T-267 -
pH - BS-1377-3 8.79
II
LD-5 TP-05 Chloride (Cl) (H20 Ext) % 0.2480
11
S-3 I Sulphate (S03) (H20 Ext) % 0.0835
0.00~1.00 Carbonate as CaC03 % ASTM D-4373-14 5.00
Organic Content % AASHTO-T-267 -
pH - BS-1377-3
II
8.76
LD-5TP-OH Chloride (Cl) (H:,<U Ext) % 0.1275
II
S-2 Sulphate (S03) (H20 Ext) % 0.1035
0.50 Carbonate as CaC03 % ASTM D-4373-14 6.00
Organic Content % AASHTO-T-267 -
pH - BS-1377-3 8.78
II
LD-5TP-09 Chloride (CI) (H20 Ext) % 0.2695
II
B-2 Sulphate (S03) (H20 Ext) % 0.1960
0.60 Carbonate as CaC03 % ASTM D-4373-14 8.00
Organic Content % AASHTO-T-267 -
TESTED BY: Ibrahim/ REVIEWED BY / CHECKED BY: ~~~bdUl~ajid ._~
APPROVED BY: ~~
~T INCHARGE)
RFG-JED-CHE-SOIL-02-01
01.01.2015
APPENDIX-C
PHOTOGRAPHS