Professional Documents
Culture Documents
An Overview of Horizontal Well Completion Technology
An Overview of Horizontal Well Completion Technology
An Overview of Horizontal Well Completion Technology
SPE 17582
This paper was prepared for presentation at the SPE International Meeting on Petroleum Engineering, held in Tianjin, China, November 1-4, 1988.
This paper was selected for presentation by an SPE Program Committee following review of information contained in an abstract submitted by the
author(s). Contents of the paper, as presented, have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the
author(s). The material, as presented, does not necessarily reflect any position of the Society of Petroleum Engineers, its officers, or members. Papers
presented at SPE meetings are subject to publication review by Editorial Committees of the Society of Petroleum Engineers. Permission to copy is
restricted to an abstract of not more than 300 words. Illustrations may not be copied. The abstract should contain conspicuous acknowledgment of
where and by whom the paper is presented. Write Publications Manager, SPE, P.O. Box 833836, Richardson, TX 75083-3836. Telex, 730989 SPEDAL.
ABSTRACT INTRODUCTION
Highly deviated or horizontal wells have Since the usual purpose to drill and
led to new thinking in the application of well complete horizontal wells is to enhance
completion and stimulation technology. production, the completion program must match the
Hori zonta 1 drilling technology has advanced production objectives.
rapidly over the past few years. It is now There are many circumstances which lead
common to be able to drill and control horizontal to the decision to drill horizontal wells and
holes of greater than 1,000 ft. displacement. these must also be considered in the final
However, horizontal completion technology is completion design.
still on a steep learning curve and many
completion practices need to be refined to These circumstances, almost all reservoir
contribute to the economic success of a related, include :
horizontal project. In addition, a better
understanding of reservoir performance with Thin Reservoirs.
horizontal completions will be needed.
The Productivity Index (PI) for a
Proven completion techniques used in less horizontal well reflects the increased area
deviated wells have not proved to be cost of contact of the we 11 with the reservoir.
effective or efficient in this new application. Typically the PI for a horizontal well may
This paper addresses severa 1 of these prob 1em be increased by a factor of 4 compared to a
areas by discussing the shortcomings of vertical vertical well penetrating the same
well completion technology and offers solutions reservoir, a1though enhancement by a factor
to horizontal applications. of 10 or mor1. ~ay be achievable in certain
Specific completion areas discussed include circumstances - (Fig.1).
production string isolation, influence of
horizontal wellbore deviation, stimulation Vertical Permeability.
considerations, sand control and downhole
production equipment. Case histories of three The productivity obtained by drilling a
Bima Field wells, offshore Indonesia, are horizontal well partially depends on the
presented to illustrate various completion magnitude of the vertical permeability and
practices. the length of the drainhole. Where the
335
2 AN OVERVIEW OF HORIZONTAL' WELL COMPLETION TECHNOLOGY SPE17582
336
SPE1~582 R.E. COOPER and J.C. TRONCOSO 3
Adequate zone isolation over long horizontal The key to such cost effective cementing is the
sections and subsequent perforating can add proper design and execution of the job from
significant cost to horizontal completions. pre-drilling planning to final displacement.
Atlantic Richfield Indonesia Inc. (ARII) This planning could include the following
reported a cost comparison of an uncemented, variables:
predrilled liner and a standard cemented liner
which indicated that the former could be Borehole eccentricity (ovality)
installed for approximately 10% of the cemented Mud and cuttings removal
1i ner cost 6when tubing-conveyed perforating was Pipe centralization
considered. Float equipment selection
Slurry properties .
However, production hi story from early and Alternative zone isolation techniques
recent horizontal completion projects indicates including ECP usage
partial or total zone isolation may be required Ability to do future remedial work such
in more cases than previously estimated. One of as squeezing.
the primary reasons for this is the early
breakthrough of gas or water into oil producers.
This may be particularly evident in thin Hole Cleaning
reservoirs where fractures or streaks of varying
verti ca 1 permeabi 1i ty are encountered or where The most important aspect of any primary
vertical control of the horizontal wellbore path cement job is adequate mud displacement and hole
is poor. Improvements in vertical control have cleaning. In horizontal completions the
almost eliminated this latter problem. additional problem of mud solids and cuttings
settlement on the low sf~e of the hole
In such cases, a totally isolated liner or complicates hole cleaning. 12 '
production casing and selective perforation. may
be required. This can be accomplished by several Several studies 13 - 15 have been performed to
methods. define optimum mud properties to remove cuttings
in highly deviated or horizontal drilling. These
A totally cemented liner and selected properties include mud density, thixotropy,
perforated intervals. rheology and velocity.
Multizone isolation using ECPs and
selectively placed sections of slotted Crook et a1 16 reported that cuttings
liners or subsequent selective perforations. transport in highly deviated wells is improved by
Uncemented predrill ed 1i ners with se 1ected reducing thixotropy, apparent viscosity and the
blank sections. This method assumes that ratio of yield to plastic viscosity, Ty/PV. Also
the formation will collapse around the blank important is using high mud densities and
sections with time and depletion. This turbulent flow. Conversely, it was shown that
technique is argumentative and needs to be settling of weighting material in static mud was
proven. minimized with a high-threshold, yield-point
value.
Elf Aquitaine and Institut Francais du
Petrole are continuing a broad research project Therefore, a proper mud system is important
into ~he selective completion of horizontal to optimize hole cleaning and should be designed
wells. Included in the project are cementing prior to drilling.
procedures, horizontal coning, borehole geometry
and downhole production ~arameters.
Centralization and Liner/hole Sizes
One of the current problems in designing a
selective multizone horizontal completion is Maintaining adequate casing standoff on the
identifying the location of vertical permeability low side of a horizontal hole is critical to
streaks and potential zones of early gas or water prevent cement s 1urri es from bypassing the 1ow
breakthrough. Since the positive identification side and flowing only along the top portiqr of
of such zones is often difficult some operators the annulus. In some high buildup wells , a
are· considering using totally cemented liners smaller than normal liner has been run in a
with selective perforations. If early gas or standard hole size, i.e., 5-1/2-in. in 8-1/2-in.
water production is encountered these zones may hole, for flexibility reasons. This also has the
then be squeezed off as in conventional vertical benefit of 1eavi ng a higher annular area on the
completions. Large diameter coiled tubing, i.e. low side which hf£tPS facilitate mud removal and
1-1/2-in. diameter, wi 11 be used more and more cement placement.
for this purpose.
Centralization in horizontal completions
Current cementing technology should be able during cementing can be optimized by reducing the
to provide cost effective cementing of many of ratio of fluid densities inside and outside the
the highly deviated or horizontal completions now pipe. This reduces the weight which the
being planned. centralizers must support.
337
4 AN OVERVIEW OF HORIZONTAL WELL COMPLETION TECHNOLOGY SPE17582
338
SPE17582 R.E. COOPER and J.C. TRONCOSO 5
Two examples of a properly designed, acid wash used a hydraulically set tool run on
executed and evaluated horizontal-liner cementing tubing. This tool allowed the washing to be done
pr~gram was reported by Hardman for Becki ngham at preselected 1-ft. and 10-ft. intervals to
36 and Simorangkir for Rama I-7. 7 In both maximize exposure of all of the wellbore face to
cases, free water and fluid loss were held to the surfactant and 5% HCl respectively. This
minimum values, batch mixing was employed and prepared the well for a subsequent 15% HCl matrix
bond evaluation was performed. treatment to be performed after the completion
assembly was run. In some cases, where excessive
In Beckingham 36, 1,825-ft. (557m) of losses were encountered during the surfactant
5-1/2-in. liner was run in 8-1/2-in. hole wash, the following acid wash and/or acid matrix
including 940-ft. (286m) of horizontal section treatment were eliminated.
and after cementing, the CET lo§ showed an almost
perfect bond over this section. The centralizer The 15% HCl acid treatment was performed
program, designed for 80% standoff with a cement using coiled tubing to selectively place the acid
slurry to mud density ratio of 0.57, included along the well bore. A low acid volume, i.e., 15
three alternating left and right spiral spring gals/ft. of perforated interval, was used to
centralizers and one hydro-bonder every two minimize the risk of accelerating early gas/water
joints. One positive centralizer per joint was brea-kthrough.
run in the liner lap.
This technique was developed over several
In Rama 1-7, a 7-in. liner was run into completions and was found to be effective in
1,290-ft. (393m) of essentially horizontal stimulating long hole section (over 2,000-ft.)
8-1/2-in. hole. Two alternating spiral where diverting systems and large volumes could
centralizers per joint were installed to give a not be used.
minimum of 80% standoff. After cementing, a CET
1og run over the upper 500-ft. (152m) of th7 Removal of deeper matrix damage can require
liner indicated good bonding above the pay zone. large quantities of acid because of the long
Subsequent selective perforating also indicated sections usually associ ated with hori zonta 1
good zone isolation within the pay zone. wells. Treatment volumes in excess of 100
gal/ft. of interval are often required to remove
such damage and in long sections the total
STIMULATION treatment val ume can exceed 100,000 ga 1s. Such
treatment may be prohibitive because of cost and
Matrix pumping time factors, i.e., low pump rates when
using coiled tubing. Selective stimulation of
Stimulation of horizontal wells has not been those intervals with low fluid contribution
widely applied for a variety of reasons: lack of appears to be an alternative at this time.
zone isolation, little or unreliable skin
information or a lack of a mechanical means to do In addition to economic and time
the treatment. considerations, special attention must be given
to the placement of large volumes of acid in
Several papers 1' 5' 21 , 22 have addressed the extended horizontal and highly deviated sections.
problem of determining skin factors in horizontal Large volumes of acid pumped in areas of vertical
wells. In several cases, high pseudo skins, fractures and permeability could stimulate these
indicating possible formation damage, have been zones creating communication to gas and water,
determined. In most of these cases, subsequent thereby accelerating coning and channelling.
stimulation has not been applied, primarily due
to lack of zone isolation or due to concern of Optimized treatment results and reduced
accelerating early breakthrough of gas or water. treatment volumes can only be obtained by uniform
coverage of the entire i nterva 1 ( s). This wi 11
In the Java Sea Bima Field, initial require continuous diversion during treatment
horizontal skin values were not available, but injection.
based on earlier vertical well performance, some
degree of drilling and completion damage was Formation integrity must be considered when
assumed to exist. Therefore, an engineered aci di zing hori zonta 1 sections. Subsequent draw-
approach to stimulation (damage removal) was down caz1Pi ti ons may cause boreho 1e compressive
applied as part of the initial completion program fa i 1ure . However, if proper fluid design and
of these we 11 s. adequate diversion are used, drawdown pressures
should not be a problem, particularly when long
After the 7-in. predrilled production liner treatment intervals are considered.
was run, a two stage perforation wash, using sea
water with 2% surfactant and 5% HCl, was To remove skin damage over potentially
performed to remove the mud a·nd mud cake from incompetent horizontal intervals special acid
behind the liner. The 11 perforation wash 11 and formulations can be developed. An example of
such a system is an emulsified acid system
developed for the Batu Raja formation in the Bima
Field in Indonesia.
339
\
6 AN OVERVIEW OF HORIZONTAL WELL COMPLETION TECHNOLOGY SPE17582
This formation, which has been the primary This leads one to consider the best of both
horizontal well target, exhibits a high worlds for maximum reservoir production and
hydrochloric acid solubility but can ·maintain recovery. The mast effective drainage network
formation integrity when exposed to small volumes could be a horizontal wellbore perpendicular to a
of low concentration acid. Some skin damage was series of vertical hydraulic fractures (Fig. 4).
suspected from asphaltine based drilling mud
fluid loss additives and asphaltine oil deposits Yost et a1 26 investigated optimized
as well as migrating fines. Based on these horizontal borehole length when combined with the
conditions an acid inside phase emulsion using a addition of multiple hydraulic fractures
90:10 volume ratio of 7.5% HCl and Xylene was perpendicular to the wellbore. Assuming a given
developed. The viscosity of the emulsion aided gas price, a 2,000-ft. (610m) wellbore with three
in diversion and acid retardation. As a result 150-ft. (46m) hydraulic fractures were required
only small volumes, i.e., 7-12 gals. per foot, to provide a predicted economic performance.
were required for effective damage removal while
still avoiding potential formation compressive It is doubtful that a horizontal wellbore
failure. will be in the same plane as an iriduced hydraulic
fracture and such fractures wi 11 probably
An initial test treatment on a vertical Batu intersect the wellbore at an angle. In-situ
Raja well proved the effectiveness of the acid stress profiles of a horizontal wellbore may
solution. A larger volume treatment is now indicate the probable point(s) of fracture
planned for a horizontal well in the near future. initiation.
This treatment will use coiled tubing as a
placement medium. Research continues on the problems
associated with hydraulic fracturing of
horizontal boreholes and the associated fracture
Fracturing geometry. Two extreme cases of geomet~ and
resultant performance can be postulated. In
There has been very little experience in the first case, a longitudinal fracture has
fracture stimulation of horizontal wells. One of been initiated along the wellbore axis. A large
the primary reasons to drill horizontal wells is number of perforations are involved in the
to enhance productivity in thin, low-permeability fracturing treatment and in the subsequent
zones, i.e., less than 100-ft. thick and 5 md. production phase. This fracture, as it
Such low-permeability zones are often ideal propagates away from the wellbore, will re-orient
fracturing candidates. itself to become perpendicular to the least
in-situ stress component. Such a rotation may
Sung and Ertekin 24 presented a series of not affect the treatment or performance provided
numerical simulations which indicated that for fracture fluid shear is minimal and there is
equal surface areas the production from adequate fracture width.
hori zonta 1 wells is expected to be greater than
that of hydraulic horizontal and vertical Another case is an inc 1i ned fracture whose
fractures. Furthermore, it is usually plane passes abruptly through the wellbore axis.
technically easier to extend a horizontal Only a minimal number of perforations will
wellbore in a thin zone than to extend a participate in the treatment and subsequent
hydraulic fracture. production. This 1imi ted fracture contact with
the well bore forms a choke for 1inear fracture
Cl ants and Ramey 22 deve 1oped a pseudo-skin flow. In such cases, there is a maximum size for
factor to compare horizontal borehole the fracturing treatment, beyond which the
productivity with that of vertical wells and production capability cannot be exceeded. Once
vertical fractures. They concluded that the this optimum size is reached increased production
horizontal drainhole pseudo-skin factor for a capacity can only be reached through additional
dimensionless drainhole length greater than 10 is parallel fractures.
identical to that of a uniform flux vertical
fracture. In practice, however, horizontal However, to provide the most effective
drainholes may have higher ff~ctivities than drainage network for a reservoir, i.e., wellbore
vertical hydraulic fractures. ' and fractures, the means must be ava i 1ab 1e to
initiate fractures at several predetermined
In the case of anisotropic reservoirs it has points along the wellbore. This can be done by
been suggested that horizontal wells should be the use of numerous port collars installed in the
drilled perpendicular to the larg2s4 ~5rmeability casing string or by selective stages of
direction for _optimum production. ' ' perforating and fracturing. Once the fracturing
treatments are completed and evaluated,
additional perforating may be done in
nonfractured areas.
340
SPE17582 R.E. COOPER and J.C. TRONCOSO 7
341
8 AN OVERVIEW OF HORIZONTAL WELL COMPLETION TECHNOLOGY SPE17582
Howev~r, differences in mobility ratios and section between the tubing tailpipe at
formation heterogeneity have made gas and water approximately 50-deg. deviation and the
coning a production problem in highly deviated horizontal section creates areas of fluid
sections. The ability to successfully isolate fallback and gas segregation. This fluid
those invaded areas by mechanical means or cement separation has caused production problems in
squeezing would have to be field tested before flowing and pumping wells. ZUG-1 is a typical
high angle and horizontal wells can be example which presented unexpected production
successfully adopted in the development of problems (Fig. 7).
oilfields with close contacts.
ZUG-1 is a horizontal well completed in
approximately 1,200-ft. of horizontal section
Production Operations (Fig. 8). This well tested upon completion at a
rate of 250 BOPD and 16,000 SCF/STB GOR. Due to
After approximately a year of production, this high GOR, an electric submersible pump was
most of the Bima Field high-angle (85 deg.) and not run in the initial completion. The well
horizontal wells (90 deg.) have shown improved produced on natural flow for approximately 2
production performance when compared to months at 600 BOPD and GOR in the 500 to 3, 500
conventionally deviated wells. Measured SCF/STB range.
productivity iDdices in these high-angle and
horizontal wells are approximately four times or Following an enforced shut down, an electric
greater than those measured in conventionally submersible pump was installed in order to kick
deviated wells. Higher production rates (Fig. 6) off the well. The well produced at higher liquid
in the majority of the high-angle wells with production rates of approximately 800 BOPD and
lower drawdown pressures also have been attained. lower GORs (100-1,500 SCF/STB), however, these
In many cases, these lower drawdown pressures rates were regularly interrupted by short periods
also have permitted control of gas and water when the well would flow through the vent valve
influxes. (Fig. 5) at very low fluid rates and unusually
high GOR. These rate variations are not
However, as operating experience is gained reflected on the well production history plot.
in these wells some production prob 1ems can be This production pattern would cause the electric
associated to the particular geometry of these submersible pump to switch off on underload.
we 11bores. The 1arge vo 1ume of the we 11bore in
the high-angle and horizontal sections (below the To control the well under these conditions, the
electric submersible pump setting depth) of more top sliding sleeve would be opened to divert
than 100-BBL, in combination with the fluid flowing production to the tubing; after the well
properties in this reservoir, have created died, the top sleeve would be closed and the well
unexpected problems which have necessitated put on pump again. This operation was repeatedly
creative solutions. The presence of an overlying performed to maintain production. This 11 gas and
gas cap in some of the wells drainage areas and 1iquid slugging 11 caused several electric
water drive in others have also caused unexpected submersible pump failures during this time
early gas and water breakthrough which have period.
necessitated reservoir management techniques to
stabilize oil rates. This 11
S 1uggi ng
11
production mode was
suspected to be caused by the volume of the
Modifications to the original 11 Y11 block horizontal section of approximately 45-BBL, and
completion in some problems wells have been by the large casing volume of approximately
necessary to increase production, electric 70-BBL in the tubingless section between the
submersible pump life, and operating efficiency. production packer and the straddle packers run to
protect the 7-in. liner top. Since lowering the
Examples of typical problems observed in the pump to reduce the tubingless· section was not
Bima Field highly deviated wells are presented recommended due to the 85 deg. deviation of the
below. It should be mentioned that Atlantic well at the top of the 7-in. liner, a tailpipe
Richfield Indonesia Inc., is presently devoting was run to the on-off attachment in the top
major efforts to the solution of these straddle packer (Fig. 9). The elimination of the
shortcomings as some of these wells start showing casing flow resulted in a more sustained and
indications of depletion and necessity for stable production rate.
remedial workovers.
This reduction of the volume in the highly
deviated section (less than 85 deg. deviation)
Case History No. 1 helped to reduce the gas and liquid slugging and
has improved the operating efficiency of the
The relative large volume of the horizontal electric submersible pump. Although this
and highly deviated section in a high-angle well reduction did not completely eliminate the phase
has been found to act 1ike a 11 sepa rator 11 where segregation in the horizontal section as
phase segregation of oil, gas and water can evidenced by the pump ampere charts, pump
occur. In addition, the extended tubingless failures have not occurred since the installation
was modified.
342
SPE17582 R.E. COOPER and J.C. TRONCOSO 9
This phase segregation has also been Temperature, pressure and flowmeter data are
observed in other highly deviated and horizontal expected to help determine fluid entries and the
wells where similar pump operating pump problems extent of the gas invasion. Coiled tubing
and production modes have resulted in pump electric logging has already been successfully
failures. tested in Europe and ~lffka to survey horizontal
and high-angle wells. '
Case History No. 2 After this data is obtained, plans are to
isolate gas invaded zones by either plugging off
The production performance of ZUA-9 the furthest end of the wellbore or straddle
exhibited a similar production pattern to ZUG-1 packing intermediate zones to isolate the gas
(Fig. 10}. ZUA-9, a horizontal well with entries. ARII is presently also investigating
approximately 1,600-ft. of flow in a tubingless the use of conve.ntional packers and plugs for
section, also experienced recurring pump application in these highly deviated sections.
failures. The well tested upon completion at a
rate of 2,000 BOPD and 50 SCF/STB GOR.
CONCLUSIONS
Figure 11 shows the original completion and
the completion modifications performed to Drilling and completion of highly deviated
minimize the gas and liquid slugging effect. In and horizontal wells have been documented in
the modified completion, the nyn block was numerous technical publications. However,. as
removed and the electrical submersible pump production stabilizes and reservoirs start
lowered approximately 1,250-ft. closer to the showing indications of pressure depletion
open perforations. Although this reduction of attention should now also be focused on the
the volume in the tubingless section has improved production problems associated with the
the initial production performance, it has not particular geometries of these wellbores. With a
completely eliminated the unstable production better understaDding of the production
mode. performance of these extended wellbore sections
and direct measurement of downhole data,
The ampere charts from ZUA-9 are still applicable modifications to the present
somewhat erratic indicating viscosity differences completion installations and future completion
and gas effects, however, a more stable programs should occur. Many areas of required
production mode was established. Present research and development appear at this· time to
production level in this well is 700 BOPD and 70 be important to the deve 1opment of oi 1fie 1ds by
SCF/STB GOR. these highly deviated and horizontal completions.
1. The full production potential of many
Case History No. 3 horizontal wells is not being achieved due
to unsatisfactory completion procedures or
ZUG-2 is a horizontal well which tested upon completion problems. One of the primary
completion at a rate of approximately 2,000 BOPD problems is zone isolation and the ability
and solution GOR of 100 SCF/STB. This rate was to control fluid flow during a we11•s later
sustained for approximately one month, with a life. Such problems should be anticipated
steady increase in GOR to 300 SCF/STB. and considered in the initia·l completion
Subsequently, the GOR increased to 3,000 SCF/STB design.
with a fluid rate drop to 600 BOPD. Choke
control helped to obtain a stabilized rate of 600 2. Most of the problems encountered in
BOPD and 2,000 SCF/STB for the second month, but cementing horizontal wells have been defined
increasing gas eventually reduced the fluid rate and current cementing technology is able to
to approximately 100 BOPD and 7,000 SCF/STB GOR. provide solutions to these problems.
Successful cementing wi 11 require deta i 1ed
This dramatic fluid production decline and attention given to mud removal, pipe
gas increase is explained by gas coning from the centralization and slurry properties.
Batu Raja gas cap into the furthest end of the However, actual field practice may prove
wellbore•s horizontal section. Figure 12 shows additional research and developement work is
the ZUG-2 wellbore path in relation to the Batu requie~ed.
Raja gas cap. Note that there is only 15-ft. TVD
between the gas-oil contact at 2,512-ft. s.s. and 3. The large volumes in horizontal wellbore
the closest high-angle predrilled section in well camp 1et ions can 1ead to the separation of
ZUG-2. oi 1, gas and water under downho 1e pressure
and temperature conditions in some
To precisely determine the gas entry or reservoirs. This downhole phase segregation
entries into the ZUG-2 wellbore, the use of has caused production problems directly
coiled tubing conveyed production logging tools associated to the slugging of fluids.
using memory gauges is p1an ned for this we 11 to
survey the highly deviated sections of the well.
343
10 AN OVERVIEW OF HORIZONTAL WELL COMPLETION TECHNOLOGY SPE17582
4. Data aquisition during production in 5. Sherrard, D.W., Brice, B.W., and Mac Donald,
hori zonta 1 sections requires deve 1opment of D.G.: 11 Application of Horizontal Wells at
downhole instruments capable of detecting, Prudhoe Bay, 11 paper SPE 15376, presented at
accounting for and/or eliminating phase the 1986 Annua 1 Techni ca 1 Conference, New
segregation effects. Interpretation of such Orleans, LA, Oct. 5-8.
data will be necessary to determine
selective zone completion and stimulation 6. Isvan, A., Wheatley, L.D., and Barry, P.M.:
requirements. High Angle Deve 1opment Wells 1 n The
11
344
SPE 17582 R.E. COOPER arid J.C. 7 lRONCOSO
15. Gavignet, ·A.A. and Sabey, I.J.: 11 A Model for 25. Sal amy, S. P., Saradji, B.S., Okoye, C.O.,
the Transport Of Cuttings In Highly Deviated Mercer, J.C. and Yost II, A.B.: Recovery
Wells, 11 paper SPE 15417, Presented at the Efficiency Aspects of Horizontal Well
Annua 1 SPE Techni ca 1 Conference, New Drilling in Devonian Shale, 11 paper SPE/DOE
Orleans, LA, Oct. 5-8, 1986. 16411. Presentation reference not known.
16. Crook, .R.J., Keller, S.R. and Wilson, M.A.: 26. Yost II, A.B., Overbey, W.K., Salamy, S.P.,
11
Solutions to Problems Associated With Okoye, C.O. and Saradji, B.S.: 11 Devonian
Deviated Wellbore Cementing,.. paper Shale Horizontal Well : Rationale for
SPE 14198, presented at the Annual Technical Wellsite Selection and Well Design, 11 paper
Conference, Las Vegas, NV, Sept. 22-25, SPE/DOE 16410. Presentation reference not
1985. known.
17. Wilson, M.A. and Sabins, F.L.: 11 A Laboratory 27. Roegiers, J.C. and Bruce, S.: 11 Fracture
Investigation of Cementing Horizontal Initiation and Propagation From Inclined
We 11 s, 11 paper SPE 16928, presented at the Boreholes in a Homogeneous, Isotropic,
Annual Technical Conference, Dallas, TX, Elastic Medium, Subjected to a Triaxial
Sept. 27-30, 1987. State of Stress, 11 Oct. 7, 1987, Schlumberger
Cambridge Research, not presented.
18. Cooper, R.E., Purinton, R.J.: 11 Gel-Plug
Technology In Pipelines, .. paper OSEA 88150 28. Hsiao, C. : 11 A Study of Hori zonta 1 Well bore
presented at the 7th Offshore South East Fa i 1ure, 11 paper SPE 16927 presented at the
Asia C6nference, Singapore, Feb. 2-5, 1988. 62nd Annual Technical Conference, Dallas,
TX, Sept. 27-30, 1987.
19. Zurdo, C., Georges, C. and Martin, M.: 11 Mud
and Cement for Hori zonta 1 We 11 s, 11 paper SPE 29. Dickinson, W., Anderson, R.R., Dickinson, W.
11
15464 presented at the Annual Technical and Dykstra, H.: Gravel Packing of
Conference, New Orleans, LA, Oct. 5-8, 1986. Horizontal Wells, 11 paper SPE 16931 presented
at the 62nd Annual Technical Conference,
20. Orban, J.A. Parcevaux, P.A. and Guillot, Dallas, TX, Sept. 27-30, 1987.
D.J.: 11 Specific Mixing Energy: A Key Factor 11
for Cement Slurry Quality, 11 paper SPE 15578 30. Nehmer, W.L.: Viscoelastic Gravel-Pack
presented at Annual Technical Conference, Carrier Fluid, 11 paper SPE 17168 presented at
New Orleans, LA, Oct. 5-8, 1986. the SPE Formation Damage Control Symposium,
Bakersfield, CA, Feb. 8-9, 1988.
21. Goode, P. A. and Thambynayagam, R. K. M.:
11
Pressure Drawdown and Buildup Analysis of 31. Hudson, T.E. and Martin, J.W.: 11 Use of
Horizontal Wells in Anisotropic Media., 11 Low-Density, Gravel-Pack Material Improves
paper SPE 14250 presented at the 60th Annual Placement Efficiency,.. paper SPE 17169
Techni ca 1 Conference, Las Vegas, NV, Sept. presented at the SPE formation Damage
22-25, 1985. Control Symposium, Bakersfield, CA, Feb.
8-9, 1988.
22. Clonts, M.D. and Ramey JR., H.J.: 11 Pressure
Transient Analysis for Wells With Horizontal 32. Joly, E.L., Dormigny, A.M., Catala, G.N. and
Drainholes, 11 paper SPE 15116 presented at Pincon, F.P.: 11
New Production Logging
the 56th California Regional Meeting, Technique for a Horizontal Well, 11 paper SPE
Oakland, CA Apr. 2-4, 1986. 14463 presented at the 60th Annual Technical
Conference, Las Vegas, NV, Sept. 22-25,
23. Ozkan, E., Raghavan, R. and Joshi, S.D.: 1985.
11
Horizontal Well Pressure Analysis, .. paper
SPE 16378 presented at SPE California 33. Wahlmeier, M.A. and Andrews, P.W.:
Regional Meeting, Ventura, CA, Apr. 8-10,
11
Mechanics of Gravel Placement and Packing :
1987. A Design and Evaluation Approach, 11 SPE
Production Engineering, (69-82) Feb. 1988-.-
24. Sung, W. and Erteki n, T.: 11 Performance
Comparison of Vertical and Horizontal
Hydraulic Fractures and Horizontal Boreholes
in Low Permeability Reservoirs: A Numeri ca 1
Study, 11 paper SPE/DOE 16407 presented at the
SPE/DOE Low Permeability Reservoirs
Symposium, Denver, CO May 18-19, 1987.
345
10~--------------------~--------------------~--------------------~
~~-·f
0
-~0
.r:
0
Ql
>
a:: a::
Fig. 1-A comparison of the productivity index (PI) for horizontal drainholes of varying lengths with the PI for a
vertical well through the same reservoir.
Co)
.co. Fig. 3-Cuttings pickup gelled spacer•
=
"'1""tal holo ""'lh room
fracture planes
13]
E! 0
~ ~ 5;-------------t----------1~--------~~------+---~~~
a. a.
20 40 60 80 '00
Fracture length • m
Fig. 2-A comparison of productivity index for fractured horizontal drainholes with the nonfractured case.
Fig. 4-Alternative fract11re geometries for a horizontal well.
VENT VALVE
~---.-----PACKER
~--1------ 11 y II SL oc K
ELECTRIC -------t::iJt
SUBMERSIBLE PUMP
AT 2100' +/-
IN !50° +/_ HOLE
~-~~ON/OFF ATTACHMENT
HOLE ANGLE@ PACKER~---. ~-==:::::::::a.~~;---......._-- PACKER
50° +/-
~:..:.lllii<E:---+-SELECTIVE NIPPLE
I AT 2200' +/..
I
IN !54° +/_ HOLE
)\
TOP 7 II LINER--~
s ~e " SHOE----,-·-
347
1000
~NNW---
-
~ HORIZONTAL DISPLACEMENT - - - SS E-P=--
'\
900 \ usoo' zooo' uod :sooo' :s&OO'
''~VERTICAL
700
600
_,.....
..-------···' :',,
···········------...
WELLS
~_;:..-~ '~-::::..-====--=--=::::::::::-.::::~::::-::::::::
0
a.. 500
IJ..
----
III
400 ZU-2.4 GAS SAND
200 N2.5'
-uoo'-1 ~ _ SUBS~
100
0,_--~~---r----~---.-----r----r----.----.-----r----.----,
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC I FIELD OWC - 2 8 4 8 ' - - - - - - - - - - - - - - - - -
YEAR 1987
oo·L
SCALE
NOTE • 1202' MD (19' TVD ) OIL
100 1
Fig. 7-Zug-1 wellbore path.
w
=
ol:ao
1125
~
4500
~ ::> ~
t;"n. ......
~~~
~g
j ~ 0: l-4000
~ ti~
~5
:~~ ~
a.,_
~~ 8g
Iii ~
n
cO
11 0:
750 :;~~ ~ :E...J 3000
:~ -
lh
II' iii
1-
0
•''Jl',,I (/)
iJ::
a. ul
nl 0
g 500 I
2000 ~
\I 0::
0
(!)
I
I
\f\1
n
1
250
l:l
\ I
I III :
~ :!\, 1000
I
I I
~IJIJ \
t , .
\ :
\: \.....,i i\i\ .rj'-'"'\./!
\: 1:1 I; I ~,t_r... f "''.,/-.--- - - -
~;E~C:-8:6~-,--L---r---L-~----_,--JL_ir-l_--,-l_---,------~====jlo
JUN -87
1.1
DEC-87
'
DEVIATION
33°
34°
37°
71 °
11
9-5/8
45 goo
bbls
7"
5326' MD. (-2589')
2000 500
0 Ul
z w
<t !:(
~~
ll:
z
~~~ Q
w ...
g
w
~~~ 0 400
1500
3 ow
g~~
0
ll:
a.
~ W.JO w
~~ffi
a. .J
m
~ ~i[>- ~
m
1-
U)
0 1000 L&:
a. 0
0 ~
co a::
0
,,
(!)
' I ,,.v
II'' I l, '
\
\
./,J'
\
\I r J I '\ \
I I
I
I
\
I
\ .,~"",\_,,-"\oo"'""""'- ...... . . . . . . ....,,._,jl
'\..... ,..,...., ....
"" I
I
\
'---"""""'""'""---;._1
0 0
JUN-87. OCT-87 FEB-88
349
ORIGINAL COMPLETION MODIFIED COMPLETION
DEVIATION
41°
ESP----I
1 12501MD.(700'TVD) P=
t-
j_ESP ~
I...-
8 18 85°
9·5/8
11 ~ ...
711
1
5591 1MD. (-2600 )
70
DO
90
<40
50
-------- ------
1 - - - - - - - - - - - - - - - - - - - F I E L D OWC
.
-2645'--------------------
------
------
UPPER GOOD RESERVOIR "V31' NEO
740' MD OIL SCALE
"l.~~,
Fig. 12-Zua-2 wellbore path.
350