METHOD STATEMENT
FOR
xxxxxx
Signature Date
Prepared by:
Signature Date
Reviewed by:
Signature Date
Revisions
Rev. No. Description of Revision Date of Revision
0 First issue xx.xx.2014
Page No. 1
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 2 of 12
TABLE OF CONDENTS
ABBRIVATIONS 3
1 PURPOSE 4
1.1 GENERAL ISSUES 4
1.2 PURPOSE 4
2 SCOPE 4
2.1 REVISION OF MS DOCUMENTS 4
Page No. 2
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 3 of 12
Page No. 3
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 4 of 12
1. PURPOSE
1.1 General issues
1.2 Purpose
2. Scope of Works:
KM Specifications
Project Specifications.
Construction Drawings and Specifications with Fit for Construction
approval.
Page No. 4
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 5 of 12
The Contractor will ensure compliance with all legal requirements with
regards to permits and licenses from the authorities prior to start of any
activities onsite.
CWR Issued by KM
4.3 Supervisor:
The Supervisor shall be responsible for the direct execution of works according
to the plan and shall directly control and give instruction to the working
personnel and operator. He shall also ensure that works are performed with
proper tools and equipment and maintain good housekeeping around the
working area. He shall also act as safety officer in the absence of safety
engineer. Responsible for Quality assurance as per KM Standard.
The QA/QC Engineer shall confirm that all site works commenced as per KM
specification and requirements and to submit all Quality forms requested by KM.
Page No. 5
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 6 of 12
The Safety Engineer shall submit prior to the commencement of work his
safety plan. He will be responsible for the implementation of all safety related
activities including inspection of safety facilities, conduct training of site
personnel and hold safety meetings periodically. He is responsible to do the
safety audit from time to time and to compile reports.
Note:
Page No. 6
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 7 of 12
6. SURVEY CONTROL
Done as per KM Specification.
Surveying to be done KM approved survivor.
8. IMPLEMENTATION
The area of work has been defined and made safe for the workforce and the
public.
Buried services and utilities on or adjacent to the worksite have been located.
Dewatering systems are in place and operational, if required.
All equipment is in sound working order and has the appropriate certificates.
This is checked regularly throughout the project and when new equipment is
brought onto the site.
Provision for daily housekeeping will be provided.
Waste management and disposal systems confirmed to be operational and
effective.
Page No. 7
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 8 of 12
The following shall be done regularly (time intervals as specified for the relevant tasks)
throughout the execution of the works:
All equipment inspections shall be updated in accordance with the regulations,
with emphasis on maintenance records and similar for all mobile plant.
The equipment used will be visually checked and recorded on a daily basis.
Only authorized personnel will be permitted to enter the work site. Upon arrival at site
the following checks will be made and any non-compliance will result in that person
being prevented from entering the work site:
Evidence of receiving site specific safety induction (register of attendance /
helmet sticker)
Appropriate Personal Protective Equipment (see PPE Section).
Page No. 8
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 9 of 12
At the end of each working day, all access to the work site will be secured; where by the
Project or Site Engineer will inspect to ensure that:
There are NO holes in the hoarding.
Proper housekeeping has been implemented.
There are NO Hindrances on Access/Egress Routes.
They will hand over the site to the night patrol, and ensure that the work area is secure
and that safety precautions are in place.
An Emergency Response Plan has been implemented at the work site, addressing, but
not being limited to the following issues:
All accidents and incidents will be reported immediately to site management.
In the event of a serious accident, the area will be segregated off and a full
investigation carried out with initial report submitted to the client.
KAH personnel, when necessary, shall meet the emergency services at the site
entrance and escort them to the scene of the accident.
Emergency contact names and mobile numbers will be displayed in the site
office, entrance gate (security) and rest areas.
Mobile Plant and Equipment will have fire extinguishers located on each
individual piece of plant.
Trained first aiders will be available on site and first aid kits available in the site
offices.
Page No. 9
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 10 of 12
9. HSE Requirements:
9.1 Objective:
M/s Al Khalejia Co. Kahromika main objective in this program is to ensure the
safety of workers and public at all times. To meet this goal we are going to
implement the following:
Page No. 10
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 11 of 12
g. The jobsite will be secured by safety fence with safety warning sign
boards at the perimeter and sufficient lighting facilities at night.
h. A safety access for the launch and reception pits will be available by
providing safety ladders securely bolted to the wall and man basket for
egress.
i. To implement policy that only competent and licensed equipment
operators will be allowed to operate equipment and execute excavation
works.
j. Lifting equipment and gears like cranes, slings and shackle shall comply
with Qatar construction standards.
k. Electrical works shall be handled by a qualified person.
All workers must be responsible for their own safety by using necessary safety
equipment and personal protective equipment (PPE), provided by the company such as
safety helmet, safety shoes, reflectorized traffic vest, safety glass, safety gloves and full
body harness if necessary.
1. All workers must be responsible for their own safety by using necessary
safety equipment and personal protective equipment, (PPE) provided by the
company such as safety helmet, safety shoes, high visibility vest, safety
glass, safety gloves, head lamp and full body harness if necessary.
2. All individual PPE will be monitored by Site Foreman or Safety Officer in
charge of the job site.
1. Provide suitable shelter for shade protection during hot weather condition.
2. An adequate supply of fresh drinking water will be provided.
3. Toilets and hand washing will be provided on site.
Page No. 11
AL KHALEJIA CO. – KAHROMIKA MS- 0067
Rev 00
xxxxxx 12/02/2014
Page 12 of 12
required. In the case of a more serious injury, an ambulance will be used. Any
person injured outside the hoarded area will be immediately transported to
the nearest first aid facility aid.
Page No. 12