Facilities

Central Norm

at Messla Oil Field


Timeline plan

month1

month2

month3

month4

month5

month6

month7

month8

month9

month10

month11

month12

month13

month14

month15

month16

month17

month18

month19
Mobilization
Civil Activity
B01 (Material /Equi storage)

B02 (Main Waste Treatment) MEP Activity


B03 & B4 (office & security)

B05 ( Contaminated Equipment


Recievinhg)

B06 ( Pipe storage)

B07 (Scrap Metal)

B08 ( Drum storage)

B09 ( Geomembrane Lined Pit)

B10 ( Geomembrane Lined


Evaporation pond)

B11 (Elevated water Tank)

chain link fence

Main Electricity

Testing & Commissioning

0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450 480 510 540 570
Days of the Month