1. SCOPE OF SUPPLY
ENCLOSED
The documents listed below are applicable in their entirety unless agreed deviations are listed
in clause 5.9. Documents referenced within the documents listed below will also apply.
3. SPECIFICATIONS
The documents listed below are applicable in their entirety unless agreed deviations are listed
in clause 5.9. Documents referenced within the documents listed below will also apply.
3.1. LOCAL AUTHORITY REGULATIONS / REQUIREMENTS
3.5. OTHERS
NOTE: All documents included in chapters 6 and 7 part of this PURCHASE ORDER. Detail list of
these documents included in PURCHASE ORDER Cover Sheet.
TECNICAS REUNIDAS
R-1910-0318 Rev.: 00 Page 7 of 26
The documents listed below are applicable in their entirety unless agreed deviations are listed
in clause 5.9. Documents referenced within the documents listed below will also apply.
5.1. OBJECTIVE
The objective of this PURCHASE ORDER is to obtain bids for the items listed in Scope of
Supply which are to be furnished and installed for the new Saudi Kayan Petrochemical
Complex-Phenolics facilities Project of Saudi Kayan.
This PURCHASE ORDER defines the minimum technical data and requirements for design,
materials, fabrication, testing, inspection, and surface treatment, painting, and packing,
preparation for shipment, supply, and documentation for the above mentioned equipment and
delivery ex-works.
5.2. DEFINITIONS
The following words and expressions used in the PURCHASE ORDER have the following
meanings:
SELLER or Any person, firm, partnership, company, corporation or combination thereof with whom
(VENDOR) the BUYER has sent the QUOTATION REQUEST or placed the PURCHASE ORDER.
Any person, firm, partnership, company, corporation or combination thereof other than
SUB-SUPPLIER
BUYER supplying to SELLER parts thereof in connection with the PURCHASE ORDER.
PURCHASE ORDER placed on the SELLER by the BUYER, which shall incorporate
PURCHASE Terms and Conditions of Purchase, the Material PURCHASE ORDER, drawings,
ORDER specifications and other documents referred to in the PURCHASE ORDER, and any
written amendments thereto.
5.3. REQUIREMENTS
5.3.1. GENERAL
5.3.1.1. SELLER shall provide all services, documentation, equipment and materials
as required to comply with this PURCHASE ORDER, and with all the referenced
documents attached herewith.
5.3.1.3. This PURCHASE ORDER in no way releases the SELLER from the final
guarantees as regard the materials, equipment, workmanship and performance
of the equipment to be supplied.
5.3.1.6. If any inconsistency or conflict exists between these documents and other
OWNER documents, Industry Standards, Codes or Drawings it shall be the
responsibility of the SELLER to bring it to the attention of the BUYER in writing.
BUYER with OWNER shall resolve the inconsistency or conflict. SELLER shall not go
along, where a conflict with the referenced Standards, Specifications, Drawings, Forms
and Codes has been detected, unless accompanied by an OWNER/BUYER pre-agreed
written waiver.
5.3.1.7. The Specification, Standards and procedures contain language that could
imply that certain standards, specifications and practices that are discretionary.
Where the words such as ’will’, ’may’ or ’should’ appear in OWNER standards,
procedures or OWNER-provided Preliminary Design, these will be interpreted as
’shall’ by SELLER.
5.3.1.10. Confidentiality
Any information related to the Saudi Kayan Petrochemical Complex Project – Phenolics
Facilities must be held in strict confidentiality. SELLER obliged to maintain all the
information and documentation related to this PURCHASE ORDER and subsequent
Purchase Order as Confidential. Therefore, no information or documentation shall be
disclosed to any third party or used with different purposes than the ones stated herein,
and not to use it except as authorized by BUYER.
SELLER may be obliged to follow specific Project Procedure for receipt, handling,
control, distribution, storing, reproduction, transmission, destruction or other handling
operations in relations to technical information that BUYER / OWNER may consider
necessary. SELLER is requested to confirm in his quotation that these requirements will
be met.
This part complements the general scope of work listed on Part nº1 of this
PURCHASE ORDER and defines a detailed scope of supply.
The Scope of Supply shall comply with all the requirements specified on the
Equipment Data Sheets referenced and attached with this PURCHASE ORDER.
All components, shall comply fully with all the referenced specifications,
standards, forms, drawings and codes listed in Clauses 2, 3, 4 and 5 of this
PURCHASE ORDER.
The SELLER, and its selected SUB-SUPPLIERS, shall comply with the
qualification requirements as covered in the individual equipment referenced
Standards and Specifications listed this PURCHASE ORDER.
SELLER shall be responsible for providing / co-ordinating detail design of all
equipment and components within the scope of supply. They include but are not
limited to providing expediting services, progress reports, organizing SELLER
and SUB-SUPPLIER coordination / kick-off / design review meetings, resolving
engineering questions relating to equipment within the scope of supply.
The SELLER’S scope of supply shall include, but is not limited to, the following
items / services detailed herein:
OTHER SUPPLIES
Engineering Services:
Performing / coordinating all calculations, analysis etc., and providing documents / drawings / mechanical
calculations as specified in this PURCHASE ORDER and referenced specifications and standards.
The vessels shall be designed to be erected in full-dressed condition (including insulation, fireproofing,
platforms, ladders and piping)…If this condition controls the thickness required for the vessel, the
SELLER shall clearly state on the quotation.
For the equipment V-52-273 The SELLER shall supply and install in the nozzle C, the Emergency
Quench Eductors. For Eductors information see Special Piping Material Data Sheet Nº SP-2126.
The SELLER shall design, supply all the materials, fabricate and install all support clips required for the
installation of ladders, platforms, piping over the equipment included in the scope of supply of this
PURCHASE ORDER.
The following estimated weights of support clips shall be assumed by the manufacturer in his supply
V-51002 45 Kgs
V-51021 55 Kgs
V-51031 55 Kgs
V-51041 35 Kgs
V-51042 15 Kgs
V-51051 30 Kgs
V-51701 35 Kgs
V-52701 40 Kgs
V-52273 45 Kgs
V-52401 30 Kgs
V-52432 30 Kgs
V-52441 55 Kgs
V-52443 10 Kgs
V-51750 55 Kgs
V-51751 55 Kgs
V-53101 10 Kgs
TECNICAS REUNIDAS
R-1910-0318 Rev.: 00 Page 13 of 26
V-53107 10 Kgs
V-53300 15 Kgs
V-53804 55 Kgs
V-53808 5 Kgs
V-53809 5 Kgs
V-56701 55 Kgs
V-56703 55 Kgs
V-56704 55 Kgs
TOTAL WEIGHT
NOTE:
The Total Weight indicated (855 Kgs) is referential and may be taken into account with a variation of ± 5
% without any cost adjustment, nevertheless if the variation exceeds the ± 5 % , an adjustment in price
will be made in favour of the Vendor or TR, according with the price in € / Kg given by the Vendor in his
offer.
The vessels shall be Hydrostatically Tested in accordance with the design code and
specifications.
Vertical vessels which are shop tested in the horizontal position shall be checked
considering future site tests in the erected position, i.e. shop hydro test shall include
the static head in vertical position.
For site hydro test, 50% wind load shall be considered in calculation.
Seismic Zone 1
Z= 0.075
TECNICAS REUNIDAS
R-1910-0318 Rev.: 00 Page 14 of 26
Dead load is the weight of the vessel, its internals, ladders, platforms, pip -
ing, refractory lining, fireproofing, insulation, supports, and other perma -
nent attachments.
When the values from the graphs of WRC 107 are exceeded no extrapo-
lation shall be made. In this case, the SELLER shall perform a Finite Ele -
ment Analysis for the stress evaluation. The SELLER shall state sepa -
rately his price for a single Finite Element Analysis.
5.3.4. EXCLUSIONS
Anchor Bolts
Fireproofing
Insulation
Platform and Ladders
The information contained in each WPS and PQR shall include, but not be
limited to, the information contained in ASME Code Section IX therefore,
any additional requirements that may be contained in scope of work,
drawings, or other instructions/ specifications pertaining to specific item of
work shall also be included.
TECNICAS REUNIDAS
R-1910-0318 Rev.: 00 Page 16 of 26
Weld Map shall not be reviewed without applicable WPSs and PQRs or
vice versa.
Welding shall not begin until Welding Dossier has been approved by
Contractor and returned to the manufacturer.
5.3.6.1. All equipment and materials shall be supplied suitably protected from
corrosion during transit, storage, after installation and during operation.
5.3.6.2. The procedures, preparation, precautions and quality control requirements
shall be as per ¨Surface preparation and external painting of Equipment and
Piping systems, 000-50S-0042 ¨, Sabic Coatings Standards (Paints, Coatings,
Linings)T01-S01, and SK-T01-S01.
5.3.6.3. Vendor’s (Painting subcontractor) quality control program shall be submitted
for review and approval prior to commencement of work.
5.3.6.4. BUYER will review and comment on Vendor/Insulation Subcontractor’s data,
documentation and QC program for painting to ensure compliance with Project
Specifications.
5.3.6.5. Any material and intended work practices which differ from Project
Specification procedures shall be submitted to BUYER for approval.
5.3.6.6. SELLER shall advise any requirements for preservation of equipment and
materials: should they require long-term storage after delivery. SELLER shall
provide all materials required for preservation and protection required for
shipment and storage on site prior to installation.
* Bulk commodities such as small bore pipe fittings, piping bolts and
gaskets are also included in this definition.
5.3.7.3. SELLER shall be required to list all the required spare parts including those
identified by OWNER, if any, and all other potential spare parts of the
equipment/equipments within their scope of supply, with their respective unit
prices, on the Spare Parts Interchange ability Record form or approved
alternative when submitting the quotations for the main equipment and materials.
SELLER shall, based on their experience, indicate in the appropriate column the
quantities of those spare parts requested by OWNER and recommended by
them for two (2) years operation.
SELLER shall ensure that, for all equipment supplied for the Facility, spare parts
will be available for at least ten (10) years from purchasing.
SELLER shall include the sample of Bill of Materials.
5.3.7.4. Successful SELLER selected to furnish the main equipment and materials
shall finalize the agreed spare parts list complete with price, interchange ability,
delivery terms and other information required, reflecting actual detail design, in
TECNICAS REUNIDAS
R-1910-0318 Rev.: 00 Page 18 of 26
accordance with OWNER’s proposed format and instructions within sixty (60)
calendar days after the date of the letter agreement for the main equipment and
materials. This spare parts list shall be completed in accordance with the Spare
Parts Interchange ability Record Instructions (SPIR), included in procedure 500-
00Z-0009.
5.3.7.5. The spare parts shall be identical and interchangeable with the respective
parts of the main equipment and materials. Successful SELLER shall also be
required to furnish identification of parts manufactured by others, including spare
parts required for auxiliary units. If any additions or changes are made to the
main equipment design after the submission of recommended spare parts list,
successful SELLER shall add or change the respective spare parts accordingly
with price and supply conditions immediately.
5.3.7.6. OWNER may provide, at their discretion, additional proposed parts for
further consideration and inclusion in the spare parts proposal by SELLER.
5.3.7.7. The selected two (2) years operation spare parts generally will be ordered in
a separate Purchase Order from the main order. OWNER reserves the right to
adjust the quantities proposed by SELLER and place the Order directly with the
SELLER for all or partial items from among the total spare parts list at the fixed
unit rates as offered by the SELLER.
5.3.7.8. SELLER will comply with PEMTO (Plan Expansion Materials Take On) and
will provide the necessary human resources manage and achieve the correct
interchange ability of Spare parts.
5.3.8.1. SELLER shall include any special tool required for installation, field-testing,
commissioning, operation or maintenance of the SUPPLY (such as bolt
tensioner, site testing equipment, instrument calibration equipment …).
5.3.9.1. SELLER shall include any lifting device (lifting lugs, trunnions, slings, jigs,
spreader beams,…) required to lift the SUPPLY during transport to site, for
installation and for maintenance.
5.3.9.2. In order to guarantee the mechanical integrity of the vessels during lifting, the
Vendor shall verify in his calculations that the wall thicknesses of the vessels are
adequate.
TECNICAS REUNIDAS
R-1910-0318 Rev.: 00 Page 19 of 26
5.4.1. GENERAL
SELLER shall provide all the necessary services for the design, fabrication,
inspection and testing of the equipment, including the provision of
information to enable BUYER to design the installation and verify the design
of the equipment supplied.
Act as a single point contact for all communication between BUYER and
SELLER.
5.4.3.3. Equipment inspection level required is LEVEL 2, for all ITEMS of the
scope of supply.
TECNICAS REUNIDAS
R-1910-0318 Rev.: 00 Page 20 of 26
5.4.3.6. SELLER shall notify the fabrication places and contact details for all
components.
NOT APPLICABLE
5.4.5. TRAINING
NOT APPLICABLE
5.5. SUB-SUPPLIERS
5.5.1. SELLER shall control, co-ordinate, expedite and resolve all problems with any
SUB-SUPPLIER in order to meet the requirements of this PURCHASE ORDER.
5.5.2. SELLER shall guarantee and be responsible for the design and performance of
all sub-supplied items. SELLER shall ensure that relevant information, reference
documents and documentation requirements are passed on to any SUB-SUPPLIER,
including confidentiality requirements indicated in chapter 5.3.1.10.
5.5.3. SELLER shall select SUB-Supplier’s from the Owner’s Approved Suppliers List
for the following equipment/ material:
Plates
Forgings
Flanges
TECNICAS REUNIDAS
R-1910-0318 Rev.: 00 Page 21 of 26
Pipe
Fittings
Mixers
Any deviation to this list shall be submitted for BUYER / OWNER approval, prior to
sub-order placement.
5.5.4. SELLER shall include in the quotation a list of all SUB-SUPPLIER proposed for
the supply of equipment and materials.
5.5.5. SELLER shall, as part of the detail design documentation, provide for BUYER
information, in case of Purchase Order, a copy of all SUB-SUPPLIER un-priced
Purchase Orders.
5.7.1. SELLER and SUB-SUPPLIERS shall support and comply with all HSE
requirements. SELLER shall submit a letter confirming its compliance with HSE
requirements.
The compliance with HSE requirements will also be evaluated along with other
technical requirements and taken into account for SELLER selection.
5.7.3. The following materials or substances shall not be used within the package, as
they are strictly prohibited:
- The project shall comply with the Montreal Protocol and no equipment
provided by Vendor shall contain any banned Chlorofluorocarbons (CFCs) or
Halons.
TECNICAS REUNIDAS
R-1910-0318 Rev.: 00 Page 22 of 26
SELLER shall clearly indicate in his proposal that his equipment does not contain any
of the prohibited substances.
5.7.4. SELLER must include in his technical quotations, one specific clause dedicated
to the HSE topics. SELLER shall address there following issues:
B) Commitment or comments, if any, to each and every clause included under HSE
Instructions to Vendors and Subcontractors Doc. No. 500-30Z-0005 Rev. 0, as
applicable to the quoted scope, and also fill its attachments.
C) Not applicable.
E) Confirmation that parts or pieces exceeding 25 Kg. weight, that need some sort of
handling during normal operations, are identified in the drawings and fitted with
lifting aids.
F) Not applicable
G) Not applicable
represents an format that conforms to the ISO 14001 and ISO 9000 Management Sy
5.7.5. Additionally, if available, Vendor will provide a copy in his proposal of the
following:
- ISO 14001/OHSAS 18001/ISO 9000 Certification
- HSE Manual
- HSE Policy
5.8.1. GENERAL
5.8.1.5. SELLER shall fulfil / confirm the VDDR´s included in the PURCHASE ORDER,
including the specified submission time schedule to issue the applicable documents and
send them in the Quotation.
5.8.1.6. SELLER shall follow the security and confidentiality requirements indicated in
clause 5.3.1.10.
5.8.1.7. SELLER shall ensure that all the VDDR´s included in the PURCHASE ORDER are
incorporated into the SELLER Document Index.
5.8.1.8. In addition to the required number of Paper Copies, all documents including the
Equipment Operation and Maintenance Manuals are required in an Electronic format. Any
Electronic format supplied shall not be Copyright Protected and shall be able to be
reproduced by the OWNER / BUYER in either Electronic or Paper form. SELLER to
confirm compliance with this requirement in his quotation.
5.8.1.9. SELLER operation and Maintenance Manuals shall be indexed and organized in-line
with OWNER´s operation and maintenance requirements.
5.8.1.11. SELLER Documents and Drawings shall include OWNER´s project number,
BUYER´s project number, purchase order number, SELLER´s drawing number and
equipment item number.
5.8.2.5. SELLER may have to send at any moment any native file upon BUYER
requirement.
5.9.1. The complete SUPPLY shall be in accordance with this PURCHASE ORDER
and the documents attached herewith. Any deviation and / or exception to this
PURCHASE ORDER and its applicable specifications, Data Sheets or any other
document included herewith must be declared by SELLER in the form “Deviation List”
to be attached to the quotation, using the format as specified in clause 2.3 (“Others”)
of this PURCHASE ORDER. In case of no exception, SELLER shall indicate “No
Deviation” in this list.
5.10.6. SELLER to fulfil / confirm all VDDR´s included in the PURCHASE ORDER,
including the specified submission time schedule to issue the applicable documents
and send them along with the quotation.
5.10.7. SELLER to confirm that final SELLER Documents and Drawings to be handed
over to BUYER will be in the electronic formats indicated in clause 3 of Project
TECNICAS REUNIDAS
R-1910-0318 Rev.: 00 Page 26 of 26
5.10.8. SELLER to confirm in the quotation that all SELLER Documents and Drawings
including when apply the Equipment Operation and Maintenance Manuals will be
handed over in the required Electronic format that shall not be Copyright Protected
and shall be able to be reproduced by the OWNER / BUYER in either Electronic or
Paper form.
5.10.10. In relation to QA/QC documentation required with the quotation, Suppliers shall
comply with requirements detailed in Project Procedure 500-00Z-0024, making use of
applicable formats included as attachments within such procedure.
d) Commitment or comments, if any, to each and every clause included under HSE
Instructions to Vendors and Subcontractors Doc. No. 500-30Z-0005 Rev. 0, as
applicable to the quoted scope, and also fill its attachments.
5.10.13. SELLER to provide with quotation Work Schedule, including key items (sub-
order placement, material / main components arrival at shop, fabrication period,
delivery, key drawing issue dates,…).
5.10.14. In relation to Spare Parts SELLER to provide with quotation the following
information: