1. General Introduction
There are total 4 units to be installed for Zungeru hydroelectric project. The
capacity of every unit is 175MW and the total capacity is 700MW. There are 4
parallel steel penstocks for Zungeru Hydropower Station. Single penstock and
standalone layout is adopted. The steel penstocks are separately arranged in
31#~34# dam sections. The steel penstock stakes are
DV0+616.0~DV0+691.0m, DH0+017.0m~DH0+102.85m and the elevation is
EL130.0m~EL202.75m. The steel penstock inner diameter is 6.733/7.5m and
they are 26/28/30mm thick. There are 65 sections of steel penstock for one
unit, including 12 sections in the top bending section (1#~12#), 36 sections in
the inclined and straight section (13#~48#), 10 sections in the bottom bending
section (49#~58#) and 7 sections in the bottom horizontal section (59#~65#).
The single unit weight is 685.942t. (The number of sections is according to the
drawing D-HS-PE-003~009).
2. Compiling Basis
1) Construction drawings;
No. Drawing number and name
3. Construction Preparation
1) The water and power supply shall have already been connected to the
working areas.
2) The reference points for steel penstock installation and elevation have
been marked correctly;
3) The installation areas have been cleaned and the safety conditions for site
4. Procedure Flow
The installation procedure flow for steel penstock is shown as the chart below:
Install, adjust and reinforce the bottom horizontal sections Circumferential seam welding
Install, adjust and weld the bottom bending sections 100% VT & UT
Accessories installation
5. Construction Procedure
1) The steel penstock segments arrived shall be assembled and welded into
pipe sections. Check the appearance of steel penstock segments. Check
whether the section shapes and sizes meet the design and code
requirements;
2) Before assembling the steel penstocks, ensure to remove the rust and
polish the weld grooves in all sections.
3) Assemble and weld the steel penstock segments into sections according
to the numbering sequence, check and adjust the perimeter and inner
diameter of pipe orifice to meet the design requirements when assembling
the penstocks. Adjust the mismatch and gap with the wedge and
turnbuckle to meet the design requirements.
4) After all meets the requirements, the welds shall be performed.
welding
Overhead/
3.2 110~150 20~23 60~80
vertical welding
Flat/cross
4.0 120~190 20~25 60~80
welding
Overhead/
4.0 120~190 20~25 60~80
vertical welding
technical staff,
Statement of
project quality record
Construction
inspector
Construction in
Design documents,
charge; Construction
GB/T50766-2012
construction record;
Length ±5mm Specification, Method
technical staff, Inspection
Statement of
project quality record
Construction
inspector
Construction in
Design documents,
charge; Construction
GB/T50766-2012
Elevation of construction record;
≤10mm Specification, Method
penstock orifice technical staff, Inspection
Statement of
project quality record
Construction
inspector
Penstock orifice Construction in
Design documents,
center and charge; Construction
GB/T50766-2012
mileage in the construction record;
≤5mm Specification, Method
initial section technical staff, Inspection
Statement of
(Section 1# and project quality record
Construction
Penstock 65#) inspector
installation Construction in
Penstock orifice Design documents,
charge; Construction
center and GB/T50766-2012
construction record;
mileage of ≤12mm Specification, Method
technical staff, Inspection
Sections 17#, Statement of
project quality record
18# and Construction
inspector
Construction in
Design documents,
Penstock orifice charge; Construction
GB/T50766-2012
center and construction record;
≤25mm Specification, Method
mileage in technical staff, Inspection
Statement of
general sections project quality record
Construction
inspector
1. Personnel falling
down; electrical shock; To apply safety belt proper and
scaffold is not firm to tie it to a fixed point;
incline; welding smokes To check the equipment to be
and dust; safety lifted or transported according to
prevention measures is the regulation and take proper Project Safety record
not proper; work prevention measures; safety chief on the regular
protection articles are To check electrical equipment supervisor, meeting
Penstock
not properly checked or and ensure proper insulation; project safety before work
installation
with defects; smoking; To check and reinforce scaffolds man, and
answer a phone during applied for construction; group/team construction
overhead operation; To wear proper protection safety man log
noises; lifting cable with articles;
damage; To arrange firefighting facilities;
2. Equipment lifting, To forbid smoking in the non-
adjustment and smoking area;
installation;
To wear protection articles
properly;
To prepare sunstroke prevention
medicine and ensure the
drinking water is clean;
1. Climate seasonal
To enhance safety prevention Project Safety record
variation;
management at construction site safety chief on the regular
2. Operation at high and
and ensure that access road is supervisor, meeting
Penstock welding;
accessible all the time; project safety before work
welding 3. Calling and answering
To get a shelter in time when man, and
a phone during
being in a heavy rain and stop group/team construction
operation;
work to be avoid of sliding down; safety man log
4. Scaffolds assembly;
To forbid calling or answering a
phone during operation;
Safety man to carry out site
supervision and patrolling
inspection
The equipment for penstock installation shall be allocated following the form
below:
No. Description Type & specification Unit Quantity Remarks
5 Winch 5T set 1
8 Level set 1
16 Acetylene pcs 5
21 Theodolite J2 set 1
2 technician 1 person
5 Erectors 6 persons
6 Welders 8 persons
Total 45 persons
Time of checking:
Elevation: EL125
Construction Map:
Dimension:
Inlet Outlet
Tolerance
No. Theo. Measured(m Differences( Theo. Measured( Differences(
(mm)
(mm) ) mm) (mm) m) mm)
D1 ±12 ±12
D2 ±12 ±12
D3 ±12 ±12
D4 ±12 ±12
Length:±5
1 3
2 4
Remarks:
Witnessed by:
Time of checking:
Elevation: EL125
Construction Map:
Dimension:
Inlet Outlet
Tolerance
No. Theo. Measured(m Differences( Theo. Measured( Differences(
(mm)
(mm) ) mm) (mm) m) mm)
D1 ±12 ±12
D2 ±12 ±12
D3 ±12 ±12
D4 ±12 ±12
Length:±5
1 3
2 4
Remarks:
Witnessed by:
Time of checking:
Elevation: EL125
Page:
Drawing No.: D-HS-PE-003~009 Structure layout of penstock
1/1
Construction Map:
Elevation:±10mm
Distance:±5mm
Remarks:
Witnessed by:
Time of checking:
Elevation: EL125
Page:
Drawing No.: D-HS-PE-003~009 Structure layout of penstock
1/1
Construction Map:
Elevation:±10mm
Distance:±12mm
Remarks:
Witnessed by:
Time of checking:
Elevation: EL125
Page:
Drawing No.: D-HS-PE-003~009 Structure layout of penstock
1/1
Construction Map:
Elevation:±10mm
Distance:±25mm
Remarks:
Witnessed by: