IIS - Online Herbs Shopping PHP - Product and Sprint Backlog Jsa
IIS - Online Herbs Shopping PHP - Product and Sprint Backlog Jsa
Create an account
login to my account
manage products
manage orders
delete products
change order status
view order details
manage users
manage site content
so that ..
1
3
1
1
1
1
3
Estimate
(Hours) Remarks/Comments/Additional info
15
10 Uses secure password encryption
16
12
40
Estimate
Sprint Id Backlog Id Description Owner Status (Hours)
1.1 PB01 Design UI Mock Up member 1 Done 3
1.2 PB01 Write online help test Not started 8
1.3 PB01 Develop CSS/HTML member 3 + 4 Ongoing 40
1.4 PB01 Develop validation criteria member 2 Done 10
1.5 PB03 Create database tables member 1 Done 16
1.6 PB08 Code test fixtures member 2 Ongoing 10
1.7 PB08 Code & test member 1+2+3 Done 25
Total 112
Burn down
Burn up
After
completed
always = Remaining Only update one time. When task is done.
Estimate work to be You update with the estimate hours, NOT the
hours done. hours you actually worked to finish the task.
Day 10
Day 11
Day 12
Day 13
Day 14
Day 15
Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
Day 8
Day 9
Completed Pending
3 0 3
0 8
0 40
10 0 10
16 0 16
0 10
25 0 25
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
54 58 0 0 0 0 10 0 19 0 0 25 0 0 0 0 0
112 112 112 112 102 102 83 83 83 58 58 58 58 58 58
0 0 0 0 10 10 29 29 29 54 54 54 54 54 54
Worked hours 1 2 3 4 5 6 7 8 9
10 11 12 13 14 15 Total hours
Team member 1 0
Team member 2 0
Team member 3 0
Team member 4 0
Team member 5 0
0
Above you can update actual worked hours every day for each team member to get a total number of hours in the sprint
rs in the sprint
Reports & Dashboards This page is updated automatically when you update the numbers when a ta
83 83 83
80
60 58 58 58 58 58 58
40
20
0
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day Day Day Day Day Day
10 11 12 13 14 15
you update the numbers when a task is done in the Sprint 1 backlog sheet