CONCRETE LABORATORIUM

PT BORNEO MANUNGGAL PRATAMA


PLANT KM 13 BALIKPAPAN

TRAIL MIX REPORT

Customer : PT NINDYA KARYA Date : 21/10/2023


Project : RUMAH SAKIT PERTAMINA KELAS C Time :
Grade : K-350 Act Slump :
Requirement slump : 10-12 cm Speciment mark :
Volume Trail : 0,078 m3

Material Source Weigth of 1 m3 Absorbsi M/C (%) Weigth Correction Vol Trial 0,078
Cement Tonasa 400 kg / m3 400 kg / m3 31,20 kg / m3
Sand 1 Lariang 798 kg / m3 0% 0% 798 kg / m3 62,28 kg / m3
Split 10-20mm Palu 1005 kg / m3 0% 0% 1005 kg / m3 78,36 kg / m3
Air Sumur 180 kg / m3 180 kg / m3 14,04 kg / m3
- Type D 0,35% Sika Plastiment VZ 1,40 kg / m3 1,40 kg / m3 109,20 gr / m3
Density 2384 kg / m3 2384 kg / m3

Slump loss
After ( minutest ) 15 " 30 " 45 " 60 " 90 " 120 " 150 "
Slump Awal 13 10

Sand/Aggregates 44%
W/C Rencana 0,45
Pengurangan Air 1,78 Liter
Air Realisasi 157,18 Liter
TEST RESULT
W/C Actual 0,39 Age Load
Date of test Weigth Stregth %
Temperatur concrete days ( Kn )
Workability 24/10/2023 3 12,67 375 260,79 75%
24/10/2023 3 12,76 375 260,79 75%
Note : 24/10/2023 3 12,66 375 260,79 75%
AVERAGE 75%
28/10/2023 7 12,45 450 312,95 89%
28/10/2023 7 12,48 412 286,52 82%
28/10/2023 7 12,55 428 297,65 85%
AVERAGE 85%
04/11/2023 14 400 278,18 79%
04/11/2023 14 400 278,18 79%
04/11/2023 14 400 278,18 79%
18/11/2023 28 400 278,18 79%
18/11/2023 28 400 278,18 79%
18/11/2023 28 400 278,18 79%

Known by Approved by Prepared by