Project: REPAIR OF CEILING EAVES, CORRIDOR AND GUTTER
Location: NCB BUILDING & EXTENSION
Duration: 40 WORKING CALENDAR DAYS

LABOR COST
SCOPE OF WORKS QTY UNIT
I. CIVIL WORKS
1 Mobilization / Demobilization 1.0 lot
Supervision and Safety Requirements needed in
2 working at heights (Safety Officer & PPE including full 1.0 lot
body harness and lanyard)
Supply, Installation and Dismantling of Scaffolding
3 1.0 lot
and working flat forms needed to complete the work.
Repair and Waterproofing (primer and topcoat)
4 84.10 lm
application in the concrete gutter
Finishing and painting of inside and outside surface of
5 84.10 lm
concrete gutter.
Removal / Dismantling of existing damaged valley
6 45.0 lm
gutter and affected damaged roofing.
Bending / Fabrication and Installation of valley gutter
7 45.0 lm
and affected damaged roofing.
Removal of damaged colored metal gutter and
8 63.0 lm
support.
Hauling, Bending and Installation of stainless gutter
9 63.0 lm
ga.24x8ft.
Removal/Dismantling of damaged wooden ceiling
10 661.68 m2
eaves joists.
Installation of metal double furring replacement to
11 807.68 m2
damaged joists corridor and eaves.
Removal/Dismantling of damaged ceiling board at the
12 146.00 m2
2nd-3rd floor corridors.
Fabrication and Installation of hard flex board 4.5-
13 661.68 m2
6mm for ceiling eaves.
Fabrication and Installation of hard flex board 4.5-
14 146.00 m2
6mm for ceiling boards in the corridors (2nd-3rd floor)
Fabrication and installation of ceiling ventilation (see
15 80.00 lm
attached drawing)
Re-painting of ceiling eaves including preparations
16 661.68 m2
(Off-White/2coats)
Re-painting of affected ceiling board in the corridors
17 146.00 m2
(2nd-3rd floor)
Cleaning, Installation and painting of PVC downspout
18 260.00 lm
and elbow 4” diameter including metal support.
Dismantling, Re-orientation of downspout 4” dia. pipe
19 260.00 lm
and elbow 45.
Hauling and Disposal of all condemned and foreign
20 1.0 lot
objects from working area to zero waste area
21 Cleaning / Clearing of the areas 1.0 lot
Supply of Consumables (screws, paint roller, paint
22 1.0 lot
brush and any consumable items)
23 Tax, Vat & Profit 1.0 lot

GRAND TOTAL

Alabang-Zapote Road, Pamplona 3, Las Piñas City, 1740 Philippines • Tel. No.: (+6322) 8871.06.39
www.perpetualdalta.edu.ph
Las Piñas Campus
UNIVERSITY OF
PERPETUAL HELP
SYSTEM DALTA

Submitted by:
Engr. Amelyn Se
Building Care Supervisor
Recommended Approval:
ENGR. EDILBERTO D. MATIBAG
Administrative Officer/GSM

Alabang-Zapote Road, Pamplona 3, Las Piñas City, 1740 Philippines • Tel. No.: (+6322) 8871.06.39
www.perpetualdalta.edu.ph
Las Piñas Campus

You might also like