Professional Documents
Culture Documents
Refinery-Engineering Design Basis For Civil-IOCL-2022
Refinery-Engineering Design Basis For Civil-IOCL-2022
DEC 2022
GENERAL OUTLINE OF ENGINEERING DESIGN BASIS (CIVIL)
1. This Engineering Design Basis (EDB) contains Information that identifies the
specific functions to be performed by a structure, system, or component of a
facility, and the specific values or range of values chosen for controlling
parameters as reference bounds of Design.
1.1. Restraints derived from generally accepted good engineering practices for
achieving functional goals, or
4. Approval for any Deviation to the Design Basis, if deemed necessary as per
requirements of the Project/Work, shall be taken from Officer not below the
Grade H.
5. All such deviations shall, however, be brought to the notice of the EDB issuing
Department at Refineries Headquarters for review and suitable incorporation in
the manual after approval.
6. In case, for some reason, the deviation accepted for a specific Project/Work is
not approved for incorporation in the EDB, such deviation shall still be deemed as
accepted for the Project/Work for which it was approved.
7. Any discrepancy noted in the EDB shall be brought to the notice of the EDB
issuing Department at Refineries Headquarters.
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 1 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
ARCHITECTURAL
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 2 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
CONTENTS
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 3 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Referenced Publications
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 4 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
(a) Control Room Buildings & Satellite Rack Rooms for Process Units shall
be designed as per OISD-STD 163, TAC building bye-laws and Factory
Act. Control Room Buildings shall be centrally air-conditioned, RCC blast
resistant (if required), single storied construction without any projection,
designed to fully meet the Instrumentation, Electrical, HVAC, safety and
other requirements.
Generally, Utility and Power Plant Control Rooms need not to be blast
resistant. However, final decision on this shall be taken in consultation with
Owner.
Control Room Buildings shall broadly consist of Console Room, Rack Room,
EC/ PLC Room, Computer Room, UPS Room, Battery Room,
Operators’ Rooms, Shift-in-Charge Rooms, Supervisor’s Office
accommodation, Instruments Calibration Room, Operators’ Check and
Change Room, Toilets (Ladies & Gents), A.C. Plant/ AHU Rooms, Clean
Agent Storage Room etc.
Satellite Rack Rooms shall broadly consist of Rack Room, UPS Room,
Battery Room, A.C. Plant/ AHU Rooms, Clean Agent Storage Room etc.
Operators’ Rooms, Toilets (Ladies & Gents) may be provided if required.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 6 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
(c) Sheds shall be designed as per Factory Act. Ventilation and day-lighting
shall be ensured by means of louvers/ window & ventilators and roof
monitors / air turbo ventilators. Necessary lifting devices (monorail, HOT,
EOT etc.) shall be provided. Depending on the utility of the shed, proper
access and lay-down area shall be planned.
(d) Buildings / Sheds of Process Units shall be designed as per Factory Act
& NBO incorporating special requirements of Licensors if any.
1) Administration Building.
2) Laboratory Building.
3) Bank/ Post Office Building.
4) Canteens.
5) Training Centre.
6) Occupational Health Centre.
7) Utilities Control Room
8) Main Gatehouses/ Security Buildings.
9) Security Cabins.
10) Driver’s Buildings.
11) Satellite Maintenance Buildings.
12) Watch Towers.
13) Air Monitoring Buildings.
14) Radio Building.
15) Tank Monitoring Cabins.
16) Operator Shelters.
17) Telecoms Towers Radio Building.
18) Equipment shelters.
19) Smoking Shelters.
20) Vehicle Parking Shelters.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 7 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
The above mentioned Non Plant Buildings are subjected to confirmation and
finalization during detail engineering.
(ii) Staircases
(iii) Elevators
(iv) Entrance lobby/ Foyer including Reception & waiting
(v) Gangway/walkways
(vi) Equipment loading/unloading platforms
(vii) Emergency Exits
(viii) Ramps for physically challenged and equipment entry/exit as
applicable.
Out of the above-mentioned areas Toilet, Drinking Water and First aid room
enclosure shall be mandatory requirement for buildings with human
occupancy. Other requirements shall be provided as specified.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 9 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
However following are the minimum sizes/ dimensions for various purposes,
which are to be adhered to.
Minimum size of any habitable room 9.5 sq.m. with minimum dimension
not less than 2.5 m.
Scale of accommodation for Industrial @ 14 cum. per occupant.
workspaces Minimum clear height of such
workspaces shall be 3.6m.
Heights above 4.25m shall not be
taken into account.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 10 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Direct solar illumination shall not be considered and only sky radiation shall
be taken as contributing to illumination of the building. Openings shall be
provided with shading devices to avoid glare. For the purpose of illumination,
day lighting shall also be supplemented by artificial illumination particularly at
fire-exit.
2.2.3 Accessibility:
These requirements deal with barrier free access to, movement within and
around buildings. In industrial complexes, which are normally not open to
public, requirement of accessibility shall be applicable to following building
occupancy types where occupancy of differently abled staff / visitor is
expected.
Requirements of accessibility:
2.2.4 Ventilation:
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 11 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
These shall be closed type sheds having full height external walls/
metal sheeting. Natural ventilation shall be by means of windows/
ventilators on side walls.
In case of sheds wider than 30 metre, ventilation shall be
augmented by roof ventilation by means of Roof Monitor, Wind
driven Ridge Ventilator and Air Extractors etc. as necessary for
required air change.
Generally, these sheds shall be open on all sides upto 3000 mm,
thereafter side cladding shall be provided for the remaining height.
Continuous sheet louvers shall be provided in the cladding on
longer sides.
Roof Monitor, Wind driven Ridge Ventilator and Air Extractors etc.
as necessary for required air change shall also be provided.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 12 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
purpose:
Safety from fire and like emergencies shall be taken into account in
building design as per NBC-Part IV; OISD-GDN-115; OISD-STD-116, 117,
173, State Factory Rules and other relevant code/ rules. The buildings shall
be provided with exits sufficient to permit safe escape of occupants in case of
emergency. The exits shall be in terms of doorway, corridors, etc. to
internal/ external staircase or to areas having access to the outside. Control
room building shall be provided with emergency exit on the other side of the
entrance.
Provisions for life safety in relation to fire prevention and fire protection of
buildings shall be applicable to:
a) All high rise buildings (15 metre or above in height, irrespective of its
occupancy, height being vertical distance measured from average ground
level around to the terrace of last livable floor of the building adjacent to
external wall).
b) Special buildings
(i) Hotel, educational, institutional, business, mercantile, industrial,
storage, hazardous and mixed occupancies, where any of these
buildings have floor area more than 500 m2 on any one or more floors;
(ii) Educational buildings having height 9 m and above;
(iii) Institutional buildings having height 9 m and above;
(iv) All assembly buildings;
(v) Buildings, having area more than 300 m2 of incidental assembly
occupancy on any floor; and
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 13 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
(vi) Buildings with two basements or more, or with one basement of area
more than 500 m2.
Reference shall be made to Chapter-4, NBC for further details on life safety.
b) Exit
Exit doorway
Every exit doorway shall open into an enclosed stairway or a horizontal
exit of a corridor/passageway providing continuous and protected means
of egress.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 14 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
doors of rooms (except for rooms having assembly occupancy) shall open
inwards.
Doors provided in exit passageway (from exit to exit discharge) shall be
fire rated doors of 120 minutes rating.
c) For non-naturally ventilated areas, fire doors with 120 min fire resistance
rating shall be provided and particularly at the entrance to lift lobby and
stair well where a funnel of flue effect may be created, including an
upward spread of fire, to prevent spread of fire and smoke.
f) At least half of the required exit stairs from upper floors (rounded to the
next higher number) shall discharge directly to the exterior or through exit
passageways.
g) All the exits and exit passageways (An exit component that is separated
from other interior spaces of building by fire rated construction and
opening protective, and provides for a protected path of egress travel in a
horizontal direction to an exit or exit discharge) to exit discharge shall
have a clear ceiling height of at least 2.4m. However the height of exit
door shall be at least 2.0m.
h) Number of Exits
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 15 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 16 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Note: Unit of exit width is 500mm, clear width of 250mm shall be additional
half unit. Less than 250mm will not be considered.
Example:
An exit doorway measuring 1000mm in residential occupancy would
provide exit capacity for 1000/6.5 = 153 persons.
The capacity for 1000mm wide stairway shall be 1000/10 = 100 persons.
Exits shall be placed as remote from each other as possible and shall be
in separate directions from any point in the area served.
percent.
Travel distance shall be measured from the most remote point within a
storey along the natural run obstructed path of horizontal or vertical egress
travel to the door to the exit.
Orientation
The buildings should be oriented optimally based on sun-path. Exposure on
the eastern and western side should be minimum.
Building form
Building volume should be reduced with optimum foot-print area.
Site planning of building shall take into account aspects like inter-
relationship of the buildings with the whole system, movement pattern,
traffic and road net-work, safety regulations, service network, fire safety,
climatic and environmental aspects, site conditions like site dimension,
contour, drainage, noise level, view, future expansion, visual aspects, Natural
Light and Ventilation etc.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 18 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Fire tenders and cranes etc. Parking space in accordance with traffic load shall
be provided to all buildings.
Climatic factors like wind direction, solar geometry shall be taken into account
in orienting the buildings depending on type of climate. Orientation of building
shall also consider noise and smell propagation, views, and visual effect from
various directions.
Landscaping elements:
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 19 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
• Tree plantation
• Hedges, shrubs, ground covers, creepers and climbers.
• Flowering, ornamental plants
• Lawns
• Paving
• Earth-forms
• Water body (if feasible)
• Landscape lighting
• Landscaping furniture
• Vertical Gardens
Roof Drainage
Rain water drainage of flat roof shall be through rain water pipes. For
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 20 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Necessary space, rooms, provisions such as AC plant, AHU, Blower room etc.
required for HVAC system shall be provided in buildings.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 21 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
2.4 Aesthetics
to withstand the specified blast pressure. Other buildings (Non blast proof Control
Room Buildings, Sub Stations etc.) shall be R.C.C. framed structure (columns,
beams and R.C.C. roof slab) with brick masonry / Burnt clay fly ash building
bricks / AAC block infill walls. Structural & Construction elements shall be
designed as per the details given in Engineering Design Basis-Structural.
Notes:
1. In case of approaches with different top levels, the highest top
level of approach road/ pavement shall be considered.
4. Cavity flooring on ground floor shall have the grade slab at not less
than 150 mm above HPP.
2.6.3 Steps
Tread and riser of steps shall be 300mm & 150mm respectively. Edge of
treads shall be provided with friction grip strips or similar anti-skid
arrangement.
2.6.4 Ramps
For equipment entry:
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 24 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Slope : 1:7
2.6.6 Walls:
Walls shall be of clay brick/ fly ash brick/ AAC masonry. For blast resistance,
walls shall be of RCC.
Following schedule shall be adhered to for wall material and thickness:
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 25 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
A External walls 230 mm. thk. Brick / fly ash building brick wall
B Internal partition 230/115 mm thk. Brick / fly ash building brick / AAC
block wall depending on the overall length and
height of the wall (refer note below)
C Transformer walls 200mm thk. RCC or 345mm thick (excluding
plastering) fire brick walls as per Electrical
requirements (OISD / IER)
D Fire Rated Wall Minimum 115 mm for 2 hour fire rating
E Concrete wall As per structural design basis
(Blast resistant)
Notes:
1. 115 mm thk. Brick partition walls (with nominal steel requirement as
per structure design) shall be provided with 230 mm thk. brick pillars
for stability depending upon the length and height of wall.
Walls separating various fire zones and separation walls between protected
and non-protected areas of Process Control Rooms / Satellite Rack Rooms
shall also be of 2 hours fire rating.
2.6.7 Doors:
Doors shall be provided for access, security and safety at all entry & exits of
rooms, functional areas & the buildings. Air tight door shall be provided in
pressurized area and in gaseous protection area. Fire check doors shall be
with minimum two hours rating as per statutory requirement. Emergency door
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 26 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
shall be opened outwards. Sizes of the doors shall be determined on the basis
of the following schedule:
Notes:
1. Rolling shutters shall be provided for equipment entry for Switchgear
Room / Electrical Room, A.C. Plant Room etc and wherever area
requirement of openable shutters exceed 2500mm (width) x 2500mm
(height).
2. Mechanically operated Rolling Shutters shall be provided in the main
equipment entry door and for opening Sizes exceeding 8.0 sq.m.
3. Blast resistant Control room entry door shall be provided with blast
Resistant baffle wall in front of entry door and shall have 45 degree / 90
degree overlap on both sides. Refer OISD-STD 163.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 27 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Rooms, spaces, sheds having height more than 4 metre shall have windows
and ventilators at multiple levels to ensure required natural lighting and
ventilation at all levels. Such windows & ventilators must be provided at all
intermediate working levels of such high rooms, spaces, sheds.
Transparent roof light sheeting / Light Pipe / Light Tube shall be provided in
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 28 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
roofing of shed type structures for day lighting. Minimum area of roof light
sheets shall be 10% of roof area.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 29 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Roof Monitors shall be located over openings at ridge of metal sheet roofing
mainly for natural ventilation.
The Monitors shall consist of metal sheet roofing and louvers at the sides.
Glass may also be used in combination with louvers for additional benefit of
natural light. Bird wire mesh should be provided to prevent entry of birds.
The Monitors shall be suitably designed and detailed to ensure that the
leakage of rain water is prevented.
Opening size at roofing sheet near ridge should be minimum 10% of the span.
Height shall be suitably decided.
Ridge ventilators shall be wind driven/operated type and shall be factory made.
The size shall be as required for required ventilation.
Qv = (VxN) / (Rx3600)
The Ridge ventilators shall be suitably designed and detailed to ensure that
the leakage of rain water is prevented.
If required for necessary ventilation, wind driven / operated Roof Air Extractors
shall also be provided.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 30 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Roof Air Extractors shall be Wind Driven/operated type and shall be factory
made. The size and numbers shall be as required for required ventilation.
No. of Air Extractors = Volume of Room x Reqd. Air change per hour
Exhaust capacity of one extractor
They shall be suitably designed and detailed to ensure that the leakage of
rainwater is prevented.
2.6.14 Parapet
Constructional details of rainwater gutters and downpipes and their fittings for
drainage shall be as per the provisions given in IS: 2527.
For rain water harvesting system, site specific scheme shall be developed.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 31 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Where,
V= Velocity in m/s.
R= Hydraulic radius in M
For gutter, R = (d x w) / 2 x d + w, where d = effective depth
of gutter & w = width of gutter.
n= Manning coefficient of roughness
S= Slope of hydraulic gradient
Q= d x w x V (discharge)
If Q > D, gutter size is correct. If Q < D, then ‘d’ and ‘w’ of the gutter need
to be re-sized.
Finished terrace surface shall be even and slope in 1 in 48. Rain water
pipes shall be embedded in concrete / concealed as far as possible. RCC /
PVC / GI spouts shall not be used for drainage of chajja/small canopies to
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 32 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
If feasible, the pipes shall be located at the back-side of the buildings, which,
in cases of un-important buildings (visually) may be kept exposed.
Space provision for security check, waiting lounge, reception etc. shall be kept
in Entrance lobby as required.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 33 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
2.6.23 Staircases
Staircases shall be provided for vertical circulation system, Exits and roof
access.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 34 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Requirements of stairs for fire and life safety are tabulated below:
Types of Staircase:
Internal staircases are located inside the
Internal staircase
building and may be with an external wall.
These are the staircases provided on the
External staircase external wall/facade. These shall be open
on at-least one side.
Curved stairs shall not be treated as part of
means of egress. These may be used as
Curved staircase
part of exit access, provided depth of tread
is not less than 280 mm.
Shall be limited to low occupant load and to
Spiral staircase a building not exceeding 9 metre in height.
Diameter shall not be less than 1500mm.
Number of staircases Minimum 2 numbers
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 35 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Handrail:
• Handrail shall be provided on one side for width less than 1500mm and
on both sides for width 1500mm and more.
• Projections of handrails in the staircase width shall not be more than
115mm.
External Staircases:
External staircases shall meet following requirements :
External stairs shall be directly connected to
Discharge
the ground.
Any doorway leading to external staircase
Door to external staircase shall be minimum 120 minutes fire rated
door.
Inclination shall not be more than 45
Inclination of staircase
degree.
Width Not less than 1500 mm.
1000 mm high, on both sides with
Handrails provisions of balusters with maximum gap
of 150 mm.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 36 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
2.6.24 Railings
Railings (1100 mm high) shall be provided in stairs, and in all
unprotected openings in slabs as a safety device. Steel railings in loading/
unloading bay of shall be of removable type. Parapets shall be given
precedence over railings on roofs.
2.6.25 Toilet:
Number of fixtures:
Number of fixtures shall be in accordance with clause 4.2.5, Part-9 of NBC.
Minimum one number Unisex Toilet for persons with disability shall be
provided in each floor fulfilling following requirements:
People.
• Toilet door shall be outward opening door with clear opening width of
900mm. The door shall be provided with minimum 600 mm long
horizontal pull bar at a height of 900 mm and horizontal pull handle at
700 mm height, both on the inside of the door.
2.6.26 Pantry:
Pantry (for tea / coffee preparation, drinking water, snacks distribution etc.)
shall be provided in all buildings having considerable human occupancy.
2.6.29 Partitions:
Partitions shall be provided for flexible space arrangement in Office spaces if
specified, Control Room etc. The partitions shall be of removable type. Glazed
panels shall be provided for visibility in the partitions as per requirement.
In fire rated areas where walls and doors are required to be fire rated, false
ceiling shall also have complementing fire rating. It is appreciated that false
ceiling have limitations in their fire performance due to openings in them for
lighting and air-conditioning. Therefore, alternative systems to prevent
puncturing the ceiling must be employed.
Wherever applicable, False flooring shall be fire rated to the level of fire rating
of the walls, doors and suspended ceiling in the compartment.
All the buildings shall be provided with Architectural finishes such as floor
finishes, plastering & painting on walls & ceilings, doors/ windows/ ventilators,
roof treatment, plinth protection etc. as below:
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 41 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Office area of Type "A" Buildings Vitrified Tiles (full body type)
Laminated Wooden Flooring
(with min. AC4 class)
skid type)
Ceramic tile flooring (anti skid
type)
Kitchen, Pantry, Dining Hall Granite Stone (slabs only)
Vitrified Tiles (full body type)
Kota Stone
With,
Granite stone counter-top (Kitchen
& Pantry).
Note:
1. Only the back of CRT and small channel in front for carrying the
cables of CRT etc. shall be provided with false flooring. The area in
front of panels shall have Vitrified tiles or as specified.
2. Skirting shall be provided in all areas which shall be of same
material as that of flooring. Panel dividers shall be provided in
cement concrete flooring.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 43 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Office areas of Type “A” & “B” Cement plaster, POP punning &
of Buildings plastic emulsion paint.
Partitions shall be modular type,
with pre-laminated board & / or
glazed.
Office area of other buildings Cement plaster, POP punning & Oil
Bound Distemper.
Partitions shall be modular type,
with pre-laminated board & / or
glazed.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 44 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Note:
Grooves in plaster shall be provided at all junctions of different material
cladding and as per external façade treatment. POP moulding shall be
provided in “A” & “B” type buildings as per Architectural scheme.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 45 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Other areas of Type “A” & “B" Cement plaster, POP punning &
Buildings plastic emulsion paint
All areas of Type “C” Buildings Cement plaster with Oil bound
and Other Buildings distemper
Other Air-conditioned areas Gypsum Board False Ceiling
where False Ceiling is required
Note:
1. Office area, Corridors circulation areas to be provided with false
ceiling.
2. For Other areas – Architectural scheme shall be followed.
3. False ceiling to be provided in Air conditioned areas of other types of
buildings also depending upon the requirement.
The schedule of Doors, Windows & Ventilators shall be finalized w.r.t the Type
of Buildings from among the following by selecting the respective options or a
combination of the options:
3.3.1 Doors
Entrance / Exit doors of Type A & Block board flush shutter with
B building decorative Teak veneered finish /
laminated finish on both sides.
Powder coated Aluminium
glazed shutter.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 46 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
All doors of Electrical Room, A.C. Pressed steel frame with Pressed
Plant Room, Battery Room steel shutter
Inside Control Room / Satellite Fire Check door with minimum
Rack Room building 2 hours rating as required in
perfect partition wall separating
various fire zones:
Glazed steel Fire check door,
Solid type steel fire check door
(with 300mm x 300mm vision
panel),
Wooden, Teakwood veneered
fire check door (with 300mm x
300mm vision panel)
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 47 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 48 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
/ sliding shutters
Windows/ventilators of Type Glazed, Anodized Aluminium
"B" Buildings window
uPVC glazed Window
All the plumbing fixtures including toilets, faucet aerators and showerheads
shall be preferably fixed with low-flow plumbing fixtures (in line with Green
Building requirements) that save substantial amounts of water compared to
conventional fixtures while providing the same utility.
Water Closet (European) for Wall hung type white European type
type “A” Building WC
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 49 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Note:
All toilets shall be provided with “Geysers” and automatic “No touch Hand
drier”.
3.7 Cladding
Precoated, profiled colour coated alloy / Galvalume / Zincalume steel sheeting
shall be of clip-lock arrangement.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 50 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
LGFS technology shall use cold formed steel (galvanized for corrosion
resistance) as the construction material for wall, floor and roof system. Since,
inside structure shall be with LGFS, external panels from both outside and inside
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 51 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
may be used comprising of pre cast concrete panels, polyurethane based panels
etc. LGFS construction is recommended upto G+3 structures, since the system
is light. Precautions shall be taken in design and connections of foundation with
LGFS components. Impact resistance to such structures may be less compared
to conventional ones.
In Hybrid Steel structure, a combination of LGFS and Steel structure can be
used and then higher number of storeys can be constructed.
Sandwich panels may be used for walling and can be made from different
materials such as EPS, cement based materials, fibre glass or any other light
suitable material. Such panels may be used for load bearing construction for low
rise structures varying from G+1 to G+3. Such panels may also be used in
conventional RCC framed construction for walling in place of brick/block work.
Sandwich panel system shall be ensured for seepage and connectivity when
used in RCC construction.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0001
PAGE 52 OF 52
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
• All free edges of chajjas and slab projections shall have drip mould in plaster
50 mm wide and 20 mm drop unless the need is resolved in some other
manner.
• Sunken Floor slab in WC areas, toilet, pantry, kitchen floor slabs shall be
avoided. Pipes shall be camouflaged by using false ceiling.
However, where required, floor slabs in WC areas shall be sunk by 500 mm
and toilet, pantry, kitchen floor slabs shall be sunk by 200 mm at all levels
(including terrace, where future extension is envisaged).
• All supporting framework members of partition walls within false ceiling areas
shall go up to roof level, partitions shall go up to false ceiling level except
where there are fire compartment wall where it shall be from floor to ceiling.
• Preferably all cut outs in slab shall be provided with 200 high curb. Gaps in
floor cut outs shall be sealed with fireproof material for fire safety.
• Roofs of RCC buildings should have mild slope towards rainwater gutters.
• Walls on steel beams shall be constructed after wall below and up to the
steel beam is constructed. This shall appear in the ‘Notes’ if applicable.
• Water tanks, AC plant, Cooling tower, Chiller units etc., where required, shall
be located on building roof as far as possible and it shall be positioned and
supported to transfer its load on to beams and columns and not to the slab.
Such facilities should not be visible from outside. Suitable side cladding shall
be provided for this purpose.
ARCHITECTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0002
PAGE 1 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
GENERAL CIVIL
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CL-0002
PAGE 2 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
CONTENTS
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 3 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Scope:
This document covers engineering design basis for Civil works such as compound wall,
fencing, site grading, roads, pavements, storm water drainage, water supply, waste
collection & disposal system, tank farm dyke, tank foundations, etc.
Order of Precedence:
1) Statutory Provisions
2) P&IDs
3) Engineering Design Basis
4) IS Codes/ IRC Codes
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 4 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Statutory Provisions:
3. The static and mobile Pressure Vessels (unfired) rules- (For pressure storage of
Gases under Chief Controller of Explosives).
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 5 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Abbreviations:
Code Description
CBR California Bearing Ratio
CRWS Contaminated Rain Water Sewer
FGL Finished Ground Level
HFL High Flood Level
HPP Highest Pavement Point
IRC Indian Road Congress
MSA Million Standard Axle
MSL Mean Sea Level
OWS Oily Waste Sewer
PCC Plain Cement Concrete
RCC Reinforced Cement Concrete
WMM Water Mix Macadam
WBM Water Bound Macadam
EWS Environment, Water & Safety
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 6 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
d. The Overall Plot Plan shall be reviewed, modified and got approved by
the Owner before implementing any project or facility. After receipt of
the Owner's approval only, the Overall Plot Plan shall be valid for further
engineering and statutory approvals.
2. Site Grading:
a. All the tree roots and vegetation shall be grubbed up and removed from site.
b. The grading of the area shall be done by cutting and filling with the following:
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 7 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Top of road, top of paving, FFL will be taken to match with the existing unit / road.
Micrograding shall be carried out by the Contractor over graded areas to bring the
FGL to indicated levels including provision of required slopes and finishes.
3. Roads:
Cross section of roads shall be designed, including roads for crane access, as per
IRC 37. However, the minimum section to be adopted shall be as given below under
'Road Width' (pt. g). Ruling gradient shall be 1 in 30. In case contractor proposes to
use existing roads for erection purposes, the same should be strengthened to cater
for erection loads. Contractor shall ensure that use of existing roads does not hinder
normal activities in existing plants. The contractor shall repair any damage to existing
roads or other facilities, at the earliest, at no extra cost.
Note:
a) Roads susceptible to spillage of petroleum products specifically roads in
loading gantry area shall be of RCC.
b) Plant roads / Access roads shall be of widths as per plot plan and 1.0m
shoulders on both sides.
c) The surface slope of roads shall be 2.5% from the center to both road
edges.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 8 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
b. Road Width:
c. Camber: 1 in 40.
d. Radius of Curve:
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 9 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
g. Road finish:
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 10 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 11 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
4. Concrete Pavement:
a. Pavement Slope:
Pavements below the pipe racks, pipe way bridges should have proper slope
towards storm water drain to avoid accumulation of water. Suitable gap
between wall of pipe-way bridges and sleepers shall be left for smooth
drainage.
b. Type:
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 12 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Area Type
Vehicular movement area
Process Unit Type-I (200 mm thick) RCC M30
(Two layers of 75mm thick WMM
as sub-base course)
Utilities Type-I (200 mm thick) RCC M30
(Two layers of 75mm thick WMM
as sub-base course)
Non- Vehicular movement area
Process Unit & Tank Farm Area Type-II (150 mm thick) RCC M25
Utilities Type-II (150 mm thick) RCC M25
LPG Sphere, Bullet area Type-III (100 mm thick) RCC M25
Off-site pump station Type-III (100 mm thick) RCC M25
Note: 75mm thick PCC 1:5:10 as sub-base shall be provided for Type-
II & Type-III pavement.
Truck Movement area (Solid & Type-I (200 mm thick) RCC M30
Liquid Product) (Two layers of 75mm thick WMM
as sub-base course).
(This is the minimum requirement,
The design shall be done as per
actual load condition and the
same shall be provided).
Truck Movement area & Road Type-I (200 mm thick) RCC M30
Loading/Unloading gantry (Two layers of 75mm thick WMM
as sub-base)
(This is the minimum requirement.
The design shall be done as per
actual load condition and the
same shall be provided).
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 13 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Notes:
2) In case of poor soil, black cotton soil, treatment below base shall be
carried out as per soil investigation report.
4) Hard surface of PCC M20 (100 mm thick) shall be provided below all
pipe rack/ pipe track. This shall extend 600 mm on either side for track
width less than 6 m, 900 mm on either side for pipe track having width
6 M or more and it shall have approach @ 500 m c/c from nearest
road. Hard surface of PCC M20 (100mm thick) of size 1Mx1M shall be
provided with proper approach near drain point of offsite piping, near
drinking water installations, at washing facilities and at other places as
required / instructed by Engineer in charge.
5) Removable type RCC precast slab with leak proof joints using bitumen
fill in all concrete pavement covering underground piping shall be
provided for maintenance/ inspection of pipes.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 14 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
c. Reinforcement:
Reinforcement shall conform to the requirement of IS: 432, IS: 1139 and IS:
1786 as relevant. The dowel bars shall conform to Grade S 240 (with yield
strength 240MPa) and tie bars (deformed/plain) to Grade Fe-500 deformed
steel bars as per IS 1786 / IS 432. If steel mesh is used, it shall conform to IS:
1566.
The area of steel required per meter length of joint shall be computed as per
IRC -15.
d. Joint arrangement:
Heavy-duty paving shall be provided with dowel bars. The dowel bars
shall be provided in the direction of traffic (longitudinal). Design of
Dowel bars shall be done as per provisions given in IRC: 58. Following
shall be design considerations:
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 15 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
5. Site Finish:
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 16 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 17 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
a. Storm water drainage system in the plant shall be designed and constructed
to completely collect, convey and dispose off the storm water as well as the
uncontaminated waste water from the plant. Drainage system shall also be
capable to collect firewater run-off based on fire fighting demand. These shall
be hooked up to nearest storm water drain along existing roads.
Contaminated and uncontaminated areas of units in line with licensor’s
recommendations to be identified and the same will be approved. The
Licensor’s requirements for drainage, for various facilities shall be adhered to.
b. At the road crossing the storm water drain shall be in precast box culvert type
with 25% provision for future expansion. This shall be designed for class A or
class AA IRC loading whichever is stringent.
Type
Units Rectangular type
Other Area Rectangular and/or Trapezoidal type
Construction
Rectangular ditches (Unit) RCC
Rectangular ditches (offsite) Brick work in cement plaster/ pointing
Trapezoidal ditches PCC Lining
Pipe Concrete pipe for road crossing
Note:
• Tank farm drainage shall be provided in such way that the storm water
discharge shall be either sent to storm water drain or to the
contaminated rainwater sewer (CRWS) by providing valve pit outside the
dyke wall depending on its contamination.
• An oil catcher with baffle wall type arrangement shall be on storm water
ditch before it leaves the battery limit of the complex.
Qr = (1/360) X C X I X A.
Where
Qr : Design quantities of storm water (m3/sec)
C : Run-off coefficient (As per the below table)
I : Design rainfall intensity (mm/hr)
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 18 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
e. Hydraulic Design:
Where
V : Velocity (m/sec)
n : Coefficient of Roughness (As per below table)
R : Hydraulic Radius (m)
I : Slope of channel
Q : Discharge Quantity (m3/sec)
A : Hydraulic section (m2)
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 19 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Open Channels:
Lined with Concrete 0.013 - 0.022
Earth, Clean after weathering 0.018 - 0.020
Earth, with grass & some weeds 0.025 - 0.030
Excavated in rock, smooth 0.035 - 0.040
Excavated in rock, jagged & irregular 0.040 - 0.045
• Storm water drainage shall be designed as flowing full and sanitary and
other pipes shall be designed as flowing 2/3 full. (Sanitary flow shall be
designed for 3 times average flow).
a. Surface drain:
For storm water drains, the following specification shall be
adopted:
• Material of Construction:
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 20 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
b. Culverts:
• Storm water drains shall cross the road by suitable precast /
cast-in-situ box culverts as the case may be. Material of
construction of culverts shall be as below:
Box culverts: R.C.C. construction (M30 concrete grade).
• The top of bottom raft of the box culvert shall be sloped and
connected to the nearest storm water drain in a manner so that
any water coming into the box culvert shall be drained off.
Alternate suitable arrangement (e.g. filling up of the box culvert
till FGL etc.) may be adopted so as to ensure that no water gets
accumulated inside the box culvert.
c. Catch Basin:
• Catch basin shall have a minimum internal dimension of 600
mm x 600 mm.
• The bottom level of catch basin shall be lower than 150 mm
from the invert level of the lowest connected pipe.
• The surface travel of the drainage prior to entering catch pit
shall be limited to 15 m.
• The maximum area per catch pit shall be 150 m2.
• Cover for catch basin shall be of Galvanized gratings.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 21 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
e. Trenches:
b. Pipe Trenches:
In paved areas, the top of cable trench will be flush with finished floor
level. Covers shall overlap walls and joints with paving shall be sealed
to prevent water entry.
In unpaved areas, walls shall be raised above ground level by 100 mm.
Trench covers shall be designed for the vehicle load relevant to the
area where the trench is located.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 22 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
7. Water System:
a. Rate of water supply: 135 lpcd (litres per capita per day).
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 23 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
b. Underground piping:
• All underground process pipes if otherwise not specified shall
be C.S. pipes and shall be provided with corrosion resistance
protection.
8. Sewers:
Process drains shall be oily water sewers, closed blow down sewers or
chemical sewers. These shall be provided as per OISD 109 and as per
Mechanical / Piping design basis. Sizing layouts, Material Specifications,
corrosion protection etc. will be as per Mechanical / Piping design basis.
Oily water sewers carry water contaminated with oil, e.g. from reflux drums,
separators, cooling / quench water or compressor / pump, process wash
water, floor and paving drains in oily areas etc. These are conveyed either to
WWTP or oil separators by means of U/G steel pipes through sealed man
holes.
Blow down are liquid streams containing water / oil / chemicals that are
required to be drained from process equipment under different operating
situations like startup, shutdown etc. Hydrocarbon blow down systems are
closed piped systems in which streams are collected in underground
blowdown drums and then pumped to respective slopes / field tanks.
a. Storm water drains shall not be combined with oily waste sewer (OWS)/
Contaminated Rainwater Sewer (CRWS)/ Sanitary Waste Sewer (SWS) /
combined sewer system.
b. OWS/ CRWS within process unit from the equipment and area around
equipment pumps (by providing curb wall) shall be collected and shall be
sent to Effluent Treatment Plant (ETP). OWS from tank farm and other off
sites areas shall be sent to ETP by gravity.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 24 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
• Clean CRWS (after 30 min flush) will not be diverted to the storm
water trench and will flow to CRWS system only.
• All water collected in unit paving shall be treated as contaminated.
d. RCC drain with HDG grating shall be provided all around the unit pavement
to collect non-contaminated water. This drain shall be connected to
main plant drain through double valve pit arrangement. In case of accidental
contamination, in generally non-contaminated areas, the flow can be
diverted to CRWS via double valve pit.
e. Tank farm drainage shall be provided in such a way that the storm water
discharge shall be either sent to storm water open ditch or to the
contaminated rainwater sewer (CRWS) by providing valve pit outside the
dyke wall depending on its contamination. The discharge from tank farm
shall be a released to ETP through gravity sewer at controlled rate to CRWS
by operating two way valve system.
k. Transformer oil (for oil filled transformer of 2000 liter) shall be drained as per
provisions given in OISD 173.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 25 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
l. The maximum depth of sewer (invert level) shall be kept minimum possible.
In case of high-water table, the maximum depth shall be limited to 1.0 M
below the water table.
m. Where sewerage system is absent, septic tank/ soak pit shall be provided.
n. Design of septic tank shall be as per the provisions of IS: 2470 Part-I & Part-
II.
Notes:
• All RCC pipes shall have socket & spigot joints. Suitable concrete
supports at all socket/ spigot joints of underground piping shall be
provided.
• OWS/CRWS of each process unit shall be collected in closed pit within
the process unit battery limit and shall be sent to ETP as per process
design basis. OWS system shall be kept sealed during construction
period to avoid its use for drainage of construction water.
• Any oil drain e.g. pump suction header drain shall be discharged to
OWS even if it is intermittent.
• All exchanger drain shall be routed to OWS or CBD as per process
design basis.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 26 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Note: All underground structures (manholes etc.) should have M-30 grade (As
per IS:456) RCC concrete.
q. Underground Pipes:
r. Manholes:
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 27 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
- Sealed manhole with vent pipes, seal type, shall be used for CS pipes
up to 24 Inch diameter. For CS pipes greater than 24 Inch diameter,
double compartment type sealed manholes shall be used.
• Suitable Clean outs shall be provided at the ends and at the change of
direction of branch headers (where manhole is not provided) for cleaning
of sewers as and when required.
The contaminated rain water sewer shall be designed for the following
combinations:
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 28 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
a. General considerations
Trenches shall be provided all around the Compressor, DG, TGs, IA/PA
compressor & other sources of oily water for collecting Oily floor wash
with a Catch basin. The oily water will be sent to a common pit through
underground pipes, which would be connected to the Oily Water Sewer
system for disposal. The potential source of Oil contamination i.e.
Compressor, DG, TG, IA/PA Compressor will be located inside the shed.
So rain water mixing is not envisaged.
For Hot Oil Storage, two-valve pit will be provided with connection to
OWS & Storm Sewer & if the spillage is substantial, Oil can be collected
in the drums with a barrel pump.
The RCC pit should be sized for 1 month holding capacity. This Hold-up
should be available below the underground inlet nozzle.
An oily water sewer line shall be separated from a parallel potable water
line by a minimum of 3 meters. An oily water sewer line crossing a
potable water line shall be oriented such that the drainage line crosses
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 29 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
under the potable water line with a minimum vertical surface clearance of
300 mm.
Any one of the following requirements must apply to drainage piping that,
due to existing conditions must crossover a potable water line regardless
of vertical separation; and must have less than 300 mm clear separation
even though running beneath the potable water line.
a) The oily water sewer piping crossing a potable water line shall be one
continuous joint of pipe and both ends of the oily water sewer pipe
shall be at least 3 meters beyond the point of crossing.
b) If the oily water sewer piping is lined steel pipe it shall be joined
together by full penetration butt-welds.
c) The oily water sewer piping shall be encased in a concrete sheath for
a minimum distance of 3 meters in both directions beyond the
crossing point. The concrete sheath shall be at least 150 mm thick.
Plastic pipes such as RTR (fiberglass) piping and fittings shall be
wrapped with neoprene wrapping at the edges of concrete
encasement. The wrapping must protrude slightly from the concrete
encasement.
d) The drainage line shall be encased in a sealed casing of either steel
sleeve or RTR (fiberglass) pressure pipe for a minimum distance of 3
meters, in both directions beyond the point of crossing. Steel sleeve
shall be coated for corrosion protection.
b. Discharge Data
The branch sewers from processing areas should be designed for the
greater of the following two situations
i) Rainfall plus process waste water with the sewer flowing at 2/3
of full depth.
ii) Process waste water plus expected fire water runoff with
sewers running full.
The design capacity of the trunk sewer should depend on the cumulative
amount of used cooling water and condensate from various processing
areas and the storm drainage from the paved areas and the largest tank
dyke area. Trunk sewers generally drain large water shed; therefore, fire
water flows are not governing for their sizing. However, this should be
checked.
A PFD of the system shall be made identifying normal flow and design
flow. The normal flow shall be equal to average process flow. After the
design flows shall be identified, sewer shall be designed for running full.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 30 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
c. Sewer Design
Sewers shall be designed as flowing full with peak flow taking future
requirements or flowing 2/3 full without considering expansion. Minimum
size of sewer shall be 150 mm.
All funnel drain shall be of minimum pipe size 100 mm dia. When 2 or
more funnels join together, the OWS size shall be 150 mm.
The main oily waste sewer header shall not be less than 200 mm dia. All
connections from funnel points shall be fire sealed.
Minimum velocity (at half full or running full) shall be 0.6 m/sec. If sewage
consists of large quantities of sediments the minimum velocity shall be
1.0 m/sec. subject to a maximum of 2.4 m/sec.
Sewers shall be designed for the sum of rain water and process water or
fire water and process water whichever is more. Storm water quantities
within tank farm areas shall not be included.
d. Cover
ii) 450mm : For main headers having size 150 mm and above, when
located such that there is no chance of truck movement
or crane movement over then.
iii) 750mm : For headers in open paved areas when crane or truck
movement can be expected. (CS pipes shall also be
encased with 150 mm thick concrete in this case).
e. Vent Pipes
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 31 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
i) At least one vent shall be installed on manhole for every 100 meter in
offsite area,
ii) Vents shall not be located near furnaces etc.
iii) The vent of height shall be 3 metre above the nearest tallest structure
within 15 metre radius.
iv) In critical locations, the vent pipes should be provided with steam
snuffing connections.
v) Vents should be connected to VOC control system to minimise VOC
emissions.
The sanitary sewer shall be designed for 3 times the average flow flowing
half full incase of lateral sewer and flowing 2/3 full in case of Main Sewers.
For trapping of gas or prevention of spread of fire through CRWS/ oily sewer
from one area to another, a liquid seal of minimum 150 mm shall be provided
in manhole along with suitable vents. Location of sealed manholes shall be
decided accordingly. All vent pipes of sealed manholes shall be provided in
line with OISD Guide lines.
vii. Material of Construction for Sewers:
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 32 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Sanitary Sewer- Toilet uPVC pipes (as per IS: 13592, 15328)/
block up to inspection CI pipes (as per IS: 3486/1729)
chamber
Sanitary Sewer- Gravity RCC class P1 (as per IS:458) Socket
main & lateral and spigot, rubber joints (Suitable
concrete supports at all socket / spigot
joints of underground piping shall be
provided)
Sanitary Sewer- Pressure C.I.
main
Manhole for acid/ alkali sewer shall be provided with Acid/ Alkali proof lining.
a. Foundation Type:
Storage tanks shall be supported either on open ring wall type foundations or
sand pads in accordance with the Geotechnical recommendations.
b. Anticorrosive layer:
Anticorrosive layer shall be provided as per specifications for tank pads of 50
thick premix carpet over 50 thick bitumen sand mixed with additions of
kerosene / oil as required.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 33 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
places, for movement of vehicles for tank cleaning purpose. Fire walls, if
required shall be of plastered brickwork and shall be 600 mm high (min) or as
drawings / as instructed. They shall only retain spillage to prevent fire spread.
The wall shall be reinforced concrete column & plastered brickwork with topped
concentric coil. The wall shall generally be of 3.5m high from FGL with the barbed
fencing / concentric coil extending a further 750mm on top of the wall. Structural
system shall be of shallow foundation, column & plinth beams.
Below FGL, the foundation shall be designed to withstand the earth pressure and
Surcharge load of 1 T/sq.m.
If the difference in the Plot Level and the Surrounding area is greater than or equal
to 1.0 m, the R.C.C Retaining Wall shall be provided upto FGL to cater the Earth
Pressure along with a Surcharge of 1 T/sq.m.
Suitable provision of drainage system shall be made outside the plot to divert the
natural storm water drainage into the nearest existing drainage system.
It shall be ensured that no part of construction shall extend outside the battery limits
of plot.
Expansion joints shall be provided in the boundary wall as per relevant IS code.
Spacing between two expansion joint shall not exceed 30m.
Design of boundary wall shall be checked for full submerged soil pressure under
choked condition of weep holes.
For purpose of protection of Land Acquisition Limit, 2.00m high barbed wire
Fencing shall be provided.
Blast Proof Control room shall be sized and designed meeting requirements of
OISD-163 (Process Control Room Safety) - Details given in Structural Design Basis.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 34 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Fire proofing for steel structures and equipment supports that could collapse under
fire condition and contribute to intensity of the fire shall be provided to meet the
requirements of OISD 164 (Fire Proofing in Oil and Gas Industry).
Fire resistance of a material is defined by fire rating, evaluated through a fire test
based on applied thickness and time taken to reach the defined critical steel
temperature. Fire rating adopted is based on UL-1709 rapid rise fire tests of
protection materials for structural steel, conducted by Underwriters Laboratory,
USA. In this test, fire resistance of a material is evaluated on a W10x49 steel
column as per UL-1709 fire curve and fire rating is published in a UL design number
under XR category for thickness and time. In addition to the fire rating, under this
test, material for exterior use is also evaluated for accelerated ageing, high
humidity, salt spray, wet-freeze-dry cycling, acid spray, solvent spray etc.
a) Type-I : In-situ cement concrete for application up to 1.8m from grade level
for steel structures shall be applied with minimum 65mm thickness.
b) Type-II : Structural steel members such as column, beam etc. which shall
be protected for 2 hours from reaching critical temperature 538°C, shall be
applied with vermiculite based lightweight cementitious fireproof of thickness
corresponding to 2 hours fire rating as per respective UL design number
under UL-1709 (XR category) subject to a minimum of 30mm.
The RCC sleepers for process piping and fire water lines shall be designed based
on the soil bearing capacity (to be ascertained by site survey) and the
horizontal/vertical loads of the pipes running full. The sleeper shall confirm to
standard (minimum requirement). Firewater piping sleepers shall be independent of
process piping sleepers. Design of sleepers shall be done taking into account soil
conditions as per soil investigation to be carried out.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 35 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
RCC / brick masonry cable trenches shall be with pre cast cover designed to
sustain the maximum load envisaged. Buried cable trenches shall be made, as per
electrical / instrumentation standards. At crossings electrical trenches shall be
made below the instrumentation trenches. Wherever, storm water drains crosses
the trenches, cable shall be taken below drains with RCC duct.
The cable crossing at roads & pipe way shall be either with group of PVC pipes
(Min. dia. 150 mm encased with PCC M15) or RCC ducts. Clear cover over top of
PVC pipe shall be 1200 mm. In case of less cover, RCC encasement shall be
provided.
16. Barricade:
The height of the barricade shall be; minimum two meters above the highest point
of active work. The barricade shall be properly designed/ constructed as per BIS
codes. The barricade shall be made out of steel framework with galvanized iron
sheets. Steel framework and its foundations shall be properly designed/ constructed
as per BIS codes.
If required, the barricade shall also be provided with suitable piping arrangement to
be connected to a pressurized water source to provide necessary water curtain.
After completion of the work, barricading including its foundations shall be removed
and the site made good.
The Fire Protection system shall be conceived to operate both in prevention and
fighting mode, depending on the relevant actions selected, either manual or
automatic. Details shall be as per guidelines provided in Engineering Design Basis -
Mechanical.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 36 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
The Project site information shall be finalized in as per format given below. Any
other special information shall also be appended along with these details. The soil
testing other testing reports shall form annexures to this site information details.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CV-0001
PAGE 37 OF 37
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
2. PRECIPITATION
Maximum Design
Hourly Daily
a. Rainfall (for minimum of Rain Fall
30 year return period)
Rainy season is
from July to ------- mm ------- mm
September
• Snow Period : ____
b. Snowfall
• Design Snow Load : ____
3. WIND DATA
N % NE %
E % SE %
a. Wind Direction
S % SW %
Percentage
W % NW %
Calm %
f. External Pressure
As specified by latest IS 875.
Coefficient
4. ENVIRONMENT FOR Corrosive Industrial Environment - Severe /
DESIGN OF STRUCTURE Moderate / Mild.
GENERAL CIVIL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 1 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
STRUCTURAL
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 2 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
CONTENTS
1.0 General
2.0 Materials of Construction
3.0 Loads
4.0 Load Combinations
5.0 Foundation Design
6.0 Plinth Protection
7.0 Ramps
8.0 Covering of Pits / Basins
9.0 Flooring details for Buildings & Sheds
10.0 Special considerations for RCC Structures
11.0 Special considerations for Steel Structures
12.0 Special considerations for Masonry Works
13.0 Platform below Air Coolers
14.0 RCC & Steel Chimneys
15.0 Barricading
16.0 Tank Foundations
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 3 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Referenced Standards & Publications (All codes & Standards shall be latest revision with all
amendments issued thereto)
S.No Description Code
1. Paving Bitumen – Specification IS:73
2. Specification for Coarse and Fine aggregates for natural IS:383
sources for Concrete
3. Classification of Commercial Timbers & their zonal IS:399
distribution
4. Specification for expanded metal steel sheets for general IS:412
purposes
5. Specification for mild steel and medium tensile steel bars IS:432
and hard-drawn steel wire for concrete reinforcement.
6. Specification for Portland slag cement IS:455
7. Code of practice for plain & reinforced concrete IS:456
8. Specification for test sieves: Part-1 Wire cloth test sieves IS:460
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 4 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 5 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 6 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 7 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
107. Criteria for design of steel bins for storage of bulk IS:9178
materials
108. Recommendations for metal arc welding of carbon and IS:9595
carbon maganese steel
109. Recommended guidelines for concrete mix design IS:10262
110. Code of practice for design and construction of ring IS:11089
Foundation
111. Specification for one part polysulphide base joints sealant IS:11433
Note The above list is suggestive and not exhaustive. Apart from these basic
codes any other related codes should also be followed wherever
required.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 8 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
1.0 General
1.1 This specification defines the design criteria and loads that should be
taken in to account for the design of all industrial plant and non-plant
structures and buildings.
2.1 General
Unless otherwise specified in the drawings, material specifications should
conform to the following:
a) Cement
Generally, for all concrete works both above and below ground, the use
of one of the following type of cements shall be considered:
• 43 Grade or 53 Grade Ordinary Portland Cement (OPC)
conforming to IS: 8112.
• Portland Pozzolana Cement (PCC, fly ash based) confirming to
IS: 1489 Part 1.
• Portland Pozzolana Cement (PCC, calcined based) confirming to
IS: 1489 Part 2.
• Portland Slag Cement (PSC) confirming to IS: 455.
• Sulphate Resistant Portland Cement (SRC) confirming to IS:
12330 shall be used (if required as per soil recommendation for
respective site).
b) Aggregate
Aggregates used in concrete works shall be conforming to IS: 383.
For most works, graded 20 mm down aggregate shall be used.
Where there is no restriction to the flow of concrete into sections,
40 mm down aggregate shall be used in special cases.
The grading of fine aggregates, when determined as described in
IS: 2386 (Part-I) shall be within the limits as given in IS: 383.
c) Reinforcement
Reinforcement shall be any of the following:
High strength deformed steel bars of grade FE 500 (TMT)/ FE 500 D
(TMT)/ FE 550 (TMT)/ FE 550D (TMT)/ FE 600 conforming to IS:
1786 shall be used as reinforcement for all structures.
Unless specifically stated otherwise use of mild steel is not permitted
in R. C. C. works. If used shall be of Grade I conforming to IS: 432
Part I.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 9 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
d) Binding Wire
18 gauge black soft annealed SWG wire shall be used for binding of
reinforcement bars.
e) Admixtures
Admixtures shall conform to IS:9103 and are to be mixed with
concrete strictly as per manufacturer’s recommendations.
f) Bolts
Unless otherwise specified in the item, Bolts shall be Snug Tight
High Strength Bolts of Grade 8.8 conforming to IS: 1367 as per
requirement.
Nuts & bolts shall conform to IS: 1363 or IS: 1364 as applicable
and as shown in the drawing. Unless otherwise specified nuts and
bolts heads shall be hexagonal. Class of nuts and bolts shall be
compatible. Wherever shown in the drawing, high strength function
grip bolts and nuts conforming to IS: 3757 and IS: 6623
respectively shall be sued.
g) Anchor Bolts
Anchor bolts shall be of mild steel conforming to Grade A of IS:
2062. Minimum two nuts shall be used for all anchor bolts except
for ladder, stair and handrail.
h) Insert Plates
Insert plates should be of structural steel grade E250 (FE 410W)
Quality B0/ Quality BR conforming to IS: 2062 and should be
provided with mild steel lugs and /or TMT bar lugs as per drawings/
standards.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 10 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
i) Gratings
Electro-forged hot dip galvanized MS Gratings should be
minimum 25mm deep. The maximum size of voids in the grating
should be limited to 30mm x 100mm.The minimum thickness of
galvanizing should be 120 microns.
The following are the range of cement content for various grades of
concrete beyond which design mix report should be critically
examined and rechecked:
The above cement content (if OPC used) can be further reduced up
to 35% by use of fly ash.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 11 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
2.3 Unless otherwise specifically stated, all shed type structures such as
Pump House, Compressor house etc. should be in structural steel.
Roofing & side cladding shall be as per Architectural Design basis/
specification. Preferably these buildings shall be designed & constructed
as PEB (Pre-Engineered Buildings).
2.5 All buildings should be of RCC Frame type construction with brick masonry
/ Burnt clay fly ash building bricks / AAC Block infill walls.
2.6 In acid and caustic handling units / dosing areas and sulfur handing units,
steel structure to be avoided. If unavoidable, suitable protective coatings
shall be provided as per site specific exposure conditions / painting
specifications.
2.7 Unless otherwise stated, bricks for masonry works should be class 7.5
conforming to I S: 1077 and /or Burnt clay fly ash building bricks confirming
to IS: 13757.
2.8 Efforts should be made to locate the Main Control Room/Buildings in such a
fashion that it shall be located outside the MAR’s(Major Accident Risk)
circle to obviate the need of Blast Resistant Buildings. Blast Resistant
Control Rooms should conform to OISD-STD-163.
Material Fire
S.
Type of Structure of Level Up to Proofing Remarks
No.
Construction Up to
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 12 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Technological
1.0
Structures
Supporting
2.5m above
1.1 Process RCC NA
HPP
Equipments, with /
without Air Coolers
Supporting For
Above RCC Air Cooler
Process MOC,
1.2 Steel Portion Supporting
Equipments with refer
upto Top Level
Air Coolers Note-a.
Material Fire
S.
Type of Structure of Level Up to Proofing Up Remarks
No.
Construction to
As per
Supporting OISD-
Above RCC STD-164 or
Process
1.3 Steel Portion 9.1 m above
Equipments
upto Top HPP,
without Air Coolers whichever is
higher.
Up to 1st
RCC Tier Level NA
above HPP
As per
Inside Process Unit
2.1 OISD-
(without Air Cooler) Above RCC STD-164 or
Steel Portion 9.1 m above
upto Top HPP,
whichever is
higher.
Up to 1st
Inside Process Unit RCC Tier Level NA
2.2
(with Air Cooler) above HPP
Steel Above RCC Air Cooler For
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 13 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Notes:
a) Blind floor below air cooler shall be in RCC over metal decking (left-in/
sacrificial shuttering).
c) Buildings shall have RCC floors & masonry infill walls, however blast-
resistant buildings shall have RCC walls. Material of construction of
masonry shall be as per Architecture Design Basis.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 14 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
3.0 Loads:
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 15 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
i. Process Building/Technological
Structure (Open/Enclosed type)
Operating area 2
5.0 kN/m
2
Maintenance area 7.5 kN/m
Ground Floor 10 kN/m2
ii Compressor House/TG house
Operating area 2
7.5 kN/m
Maintenance area 7.5 kN/m2
(or as specified by machine
vendor)
Ground Floor 10 kN/m2
iii Substation/Control Room
Panel floor 10.0 kN/m2
Other areas 5.0 kN/m2
Partitions 1.0 kN/m2
iv Office building
Office area 3.0 kN/m2
Lobby 5.0 kN/m2
Exit way 5.0 kN/m2
Partitions / Misc. Portions 1.0 kN/m2
v Laboratory
Upper floors 4.0 kN/m2
Ground floor 5.0 kN/m2
vi Cooling Tower
Operating platform/ 3.0 kN/m2
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 16 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 17 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Apart from specified live loads, any other equipment load or possible
overloading during construction/hydrotest/ maintenance/erection shall also
be considered in design.
b) Hydrotest Load:
All equipment foundations & supporting structures shall be designed
for Hydro-test loads. Hydrotest shall be considered for one
equipment at a time. Further, under hydro-test condition the wind
force shall be taken as 25% of normal wind loading. Seismic forces
shall not be considered while hydro-testing.
b) Structural Steel
Platform Walkways 3 KN
Secondary Floor Trimmers 5 KN
Primary beams 10 KN
The mean probable design life for computation of wind forces for all
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 18 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
To account for surface area of piping, platforms and other attachments fixed
to the equipment the surface area of the equipment (vessel/column)
exposed to wind should be increased by 20% or as specified in the
mechanical data sheet of the equipment.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 19 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
cases.
Requirement of monorails and overhead cranes shall be as per IS: 800, IS:
875 or manufacturer’s data, whichever is more stringent.
Vibration loads should mean the vibration forces caused by heavy vibrating
equipment or machinery and dynamic forces caused by fluids in the normal
operation. Frames, structures and foundations for machinery or
equipment causing vibration should be designed to limit vibrations to an
acceptable level.
Dynamic analysis will be carried out for foundations of critical equipment like
compressors & pumps. While carrying out dynamic analysis of
foundation/structures supporting dynamically loaded equipment’s, the loads
indicated by vendor in his documents shall be used.
However, in the absence of such vendor data, the following load shall be
assumed as the equivalent static loads when the dynamic analysis is not
carried out.
(perpendicular
to centerline of
shaft)
Along direction 0.10 times the weight of equipment
of shaft axis / machinery.
2 Reciprocating Type
0.5 times the weight of equipment /
Vertical
machinery.
Along direction
0.25 times the weight of equipment
of reciprocating
/ machinery.
motion
Horizontal Along direction
perpendicular 0.10 times the weight of equipment
to reciprocating / machinery.
motion
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 21 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Concrete to soil………..0.40
Steel on Steel………….0.30
Steel on concrete…….. 0.45
PTFE to PTFE…………0.10*
* Compressive stress on PTFE (Poly-tetra-fluoro-ethylene / Teflon)
shall be minimum 3.5 N/mm2.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 22 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Liquid Pressure shall mean the pressure of liquid acting on the Pit/Basin
structures.
• Davits shall be designed for the heaviest item to be lifted plus 25 % for
impact but not less than a total of 450 kg. Lateral forces shall be assumed
as 20 % of the lifted load. A line pull of 100 % of the lifted load shall be
included to provide for the possibility of the load being handled by a line
over a single pulley.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 23 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Vertical loads of flare pipe shall be taken as one third full of water
for piping within units & one sixth full for outside unit battery line. All
flare line independent support shall be of four legged braced open
tower type construction.
f) Wind Force:
Transverse wind loading shall be calculated depending on the width
of the Pipe Rack as follows:
a) Basic wind pressure shall be considered as per IS: 875.
b) This force shall be considered irrespective of height between two
tiers as per following table.
Operational load shall be defined as the dead load of Piping plus weight of
any liquids or solids, normally present within piping during operation.
Design of all structures should also consider any other relevant and
consequential load/stress imparted to the structure.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 26 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
maximum values of wind, earthquake, imposed and snow load is not likely.
Design shall be done to resist the worst combination of the above loads.
The overall stability of the structure and foundations may need to be reviewed
against a more critical load combination than combinations defined below
depending upon configuration of structure.
DL : Dead Load
IL : Imposed / Live Load
EE : Equipment Loads for Erection / Empty
EO : Equipment Loads for Operation
ET : Equipment Loads for Testing
BP : Bundle Pull
VL : Impact / Vibratory Load
WL : Wind Load
SL : Seismic / Earthquake Load
PL : Piping Load
PE : Piping Loads for Erection / Empty
PO : Piping Loads for Operation
PT : Piping Loads for Testing
TL : Thermal Load/ Friction Load
TA : Thermal Anchor Load
CRL : Crane Load
H : Earth Pressure Load
Hd : Handling Device Load
Bp : Blast Force / Load
DL + EE
Erection
DL + EE + WL
Operating DL + EO
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 27 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
DL + EO + WL
DL + EO + SL
DL + ET
Test
DL + ET + 0.25 WL
DL + EE
Erection
DL + EE + WL
Operating DL + EO + TL
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 28 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
DL + EO + TL + WL
DL + EO + TL + SL
DL + ET
Test
DL + ET + 0.25 WL
Maintenance DL + EE + BP
(for exchangers only)
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 29 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
DL + EE + PE
DL + EE + PE + IL
Erection
DL + EE + PE + WL
DL + IL + EE + PE + WL
DL + EO + PO + TA + TL
DL + IL + EO + PO + TA + TL
DL + EO + BP + VL + PO + TA + TL
DL + IL + EO + VL + PO + TA + TL
DL + IL + EO + PL + Hd + TL
DL + EO + PO + TA + TL + WL
Operating DL + IL + EO + PO + TA + TL + WL
DL + 0.5IL + EO + BP + PO + TA + WL
DL + 0.5IL + EO + PL + Hd + TL + WL
DL + EO + PO + TA + TL + SL
DL + 0.5IL + EO + PO + TA + TL + SL
DL + 0.5IL + EO + BP + PO + TA + SL
DL + 0.5IL + EO + PL + Hd + TL + SL
DL + ET + PT
DL + ET + PT + IL
Test DL + ET + PT + 0.25 WL
DL + ET + PT + 0.5IL + 0.25 WL
DL + 0.5IL + ET + 0.25WL + PL + Hd
Maintenance DL + 0.5IL + EE + PE + BP
(for exchangers only)
DL + IL + EO + BP + H
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 30 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 31 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
DL + IL + EO + VL + PO + TA + TL
Normal DL + IL + CRL
DL + IL + CRL + 0.5SL
Seismic
DL + 0.5IL + 0.5CRL + SL
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 32 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
4.5 For General Buildings & Buildings (with or without Equipment) and their
Foundations
DL
DL + IL + Hd
DL + IL + EE
Normal
DL + ET
DL + IL + EO
DL + Bp
DL + WL
DL + IL + WL + Hd
DL + EE + 0.8WL
Wind
DL + EO + 0.8WL
DL + IL + EE + 0.8WL
DL + 0.8IL + ET + 0.8WL
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 33 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
DL + 0.8IL + EO + 0.8WL
DL + SL
DL + 0.5IL + SL + Hd
DL + EE + 0.8SL
Seismic DL + EO + 0.8SL
DL + IL + EE + 0.8SL
DL + 0.8IL + ET + 0.8SL
DL + 0.8IL + EO + 0.8SL
Normal DL + IL
DL + WL
Wind
DL + 0.8IL + 0.8WL
DL + SL
Seismic
DL + 0.4IL + 0.8SL
1.5DL
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 34 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
0.9DL + 1.5SL
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 35 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
9) Foundation for tanks upto 10m diameter shall be of RCC ring wall type,
unless required from anchorage or counterweight considerations.
11)In reinforced and plain concrete footings, the thickness at the edge shall
be not less than 150 mm for footings on soils, nor less than 300 mm
above the tops of piles for footings on piles.
Minimum Factor Of
Safety Against Minimum Factor
Overturning Of
Safety Against
Erection Operating Sliding
Condition Condition
Type Of
Structure With Wind Without With Wind Without With Without
Or Wind Or Or Wind Or Wind Or Wind Or
Seismic Seismic Seismic Seismic Seismic Seismic
All Buildings/
Structures 1.5 1.5 1.5 2.0 1.5 1.75
/Equipments in
Units
1.5 1.5
Over Head water (empty) (empty)
- - 1.5 -
Tank 2.0 2.0
(full) (full)
Flood Light Mast 1.5 - 1.5 - 1.5 -
Retaining Wall - - 1.5 2.0 1.5 1.75
Flare Supporting 1.5 - 1.5 - 1.5 -
Structure
2.0
- - 1.5 or 1.5 1.5
Resistant 1.2#
Structures
Transmission
Tower / Switch 1.5 2.0 1.5 2.0 1.5 1.75
Yard Structure
Pipe Rack
1.5 2.0 1.5 2.0 1.5 1.75
(Offsite)
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 37 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Minimum Factor of safety against Uplift should be 1.2 for all structures. In case
of sumps, lining weight should not be included.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 38 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Allowable Net Safe Bearing Capacity (SBC) of soil for isolated/ raft/
pile/ tank foundations shall be based on the settlement criteria for dead plus
imposed load conditions, as follows:
a. For foundations in Unit areas, Utility areas and foundations
of Plant buildings, settlement shall be considered as 25mm.
b. Allowable total settlement of foundation for Machine foundations
and critical equipment with interconnected piping– 25 mm.
c. For foundations of Non-plant buildings, settlement shall be
considered as 40mm.
d. For Raft foundations, settlement shall be considered as 40mm.
e. For foundation of Cone roof/ Dome roof Storage Tanks,
settlement shall be considered as 300mm at edge and differential
settlement shall be considered as 1 in 300 along periphery.
f. For foundations of Floating roof Storage Tanks, settlement to be
considered as 150mm at edge and differential settlement shall be
considered as 1 in 500 along periphery.
g. For Mounded Bullets, differential Settlement of 25 mm & overall
settlement of 60mm shall be considered for design.
In the design of walls below grade, provision should be made for the
lateral pressure of adjacent soil. Due allowance should be made for
possible surcharge from fixed or moving loads. When a portion or whole
of the adjacent soil is below a free water surface, computations should be
based on the weight of the soil diminished by buoyancy, plus full
hydrostatic lateral pressure.
a) General:
1) Foundation for rotating and reciprocating equipments such
as turbines, engines, compressors and generators should
be designed to secure the dynamic stability of the
foundation system, as well as the static stability.
2) Dynamic stability for foundation supporting heavy vibrating
equipments like the following should be secured by dynamic
analysis in general:
• Heavy vibrating equipment,
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 39 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 40 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
c) Dynamic Analysis:
• General
Dynamic analysis should be performed by suitable and
approved method so that dynamic feature can be evaluated
correctly.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 43 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 44 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
6) Where piles pass through filled ground the available pile safe
working load should be suitably reduced to account for negative
skin friction caused by settlement of fill. Where suitable
consideration should be given to reducing draw down effects by
slip coating the piles.
8) Driven cast in-situ piles should have safe distance (as per IS
Code requirement) from the existing structure to avoid any
damage due to vibration.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 45 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
7) Maximum spacing of bars in walls and roof slab should not exceed
150mm c/c.
All buildings coming in units, offsite and utility areas shall be provided with
Post Constructional anti-termite treatment shall be done as per IS: 6313 and
IS: 8944.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 46 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
The tension capacities of anchor bolts shall be worked out based on the bolt
to bolt spacing and the distance between anchor bolt to the edge of
concrete. If required, additional reinforcement around anchor bolts shall
be provided in the concrete pedestal.
Anchor bolts for heavy towers, which are subject to pull out force, shall be
embedded into the foundation at the time of placing concrete using
templates.
Minimum size of bolts shall be 16mm (10mm & 12mm can be used for
miscellaneous structures). Minimum center-to-center distance of bolts shall
be 2.5 times nominal diameter.
All anchor bolts shall also be provided with a nut and lock nut.
2) All anchor bolt sleeves/ pockets and spaces under column bases,
shoe plates etc. shall be grouted with free flow, non shrink (premix
type) grout with 28 day minimum cube crushing strength of 40 N/sq
mm.
5) Neat cement should not be used for grouting under any condition.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 48 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
9) Ordinary cement sand (1:2) grout should only be used under the
base plates of cross-overs, short pipe supports (not exceeding 1.5
m height) and small operating platforms (not exceeding 2 m
height) not supporting any equipment.
Each building shall be provided with 1.0 m wide (100mm high from top of
Approach Road Level) concrete M15, 75 mm thick laid on 75 mm thick M7.5
concrete with brick bats all round as plinth protection, with building drain around
the building. Paving shall be sloped for a rapid run off of rain water away from
the building.
7.0 Ramps:
1) Open pits and basins without roofing or covering should have safety
railings. Stepladders should also be provided for the pits and
basins having a depth of more than 1 m.
The specifications given hereunder should be adopted for the non- suspended
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 49 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
ground floor slabs for buildings & sheds as categorized in following table:
b) Flooring Type I shall be considered for Control Rooms, Satellite Rack Rooms,
Sub-Stations, Pump Houses, Utility Compressor Houses, Parking Areas,
Stores, Porches.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 50 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
e) Floor finish for all the above three types of flooring shall be as per Engineering
Design Basis - Architecture.
10.2 Concrete:
c) Plain Cement Concrete (PCC) mud mat of grade M20 (nominal mix) of
minimum 150 mm thickness shall be provided under all masonry wall
foundations.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 52 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
h) However, the maximum cement content shall not exceed 450 kg/cum.
Unless specified otherwise, actual concrete cover should not deviate from
required nominal cover by +10 mm.
Nominal cover should be as per IS: 456, however the following minimum clear
cover should be provided for RCC works.
Sr.
Description Minimum clear cover
No.
Slab (roof & floors, canopy,
1 25 mm
cantilever, waist slab)
45 mm or dia. of bar
2 Beam (roof, floor, tie & lintel) whichever is greater
3 Column 50 mm above FGL
75 mm below FGL
Retaining wall, Basement and
4 Pit Wall
a Face in contact with earth 50 mm
45 mm or dia. of bar
b Free face whichever is greater
5 Liquid retaining structure
50 mm or dia. of bar
a Face in contact with liquid whichever is greater
Face away from liquid but in
b 50 mm
contact with earth
45 mm or dia. of bar
c Free face whichever is greater
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 53 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Designer shall ensure that the reinforcement cover, mentioned above shall
in no case be lower than that required by Codes of practices as per
exposure condition of site and other recommendation of confirmatory soil
investigation report.
Sr. Minimum
Description
No. Thickness
Footings (all types with or without beams)
(Note: Tapered footings should not have thickness 300 mm
1 less than 150mm at the edges. Minimum average
thickness should not be less than 300mm)
2 Pile Cap 500mm
Liquid Retaining / Leak-proof structure / Basement
3
/ Underground Pit :
a Walls 150mm
b Base slab with beams 200mm
c Base slab without beams 300mm
Slab thickness in Raft foundations with beam &
4 225mm
slab construction
5 Floor/Roof Slab, Walkway, Canopy Slab 150mm
6 Cable/Pipe Trench/Launder Walls & Base Slab 125mm
7 Parapet 125mm
8 Louvre / Fin 125mm
9 Precast Trench Cover/Precast Floor Slab 125mm
10 Louvre (in contact with liquid) 125mm
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 54 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Piles – Ties 8 mm
Major Foundation 12 mm
Block Foundation - Main Bars & Tie Bars 12 mm
Minor Foundation (Local foundation etc.) 12 mm
Column, Pedestal - Main Bars 12 mm
Column, Pedestal – Ties 8 mm
Beam - Main Bars 12 mm
Beam - Anchor Bars 10 mm
Beam – Stirrups 8 mm
Slab & Wall - Main Bars 10 mm
Slab & Wall - Distribution Bars 8 mm
Minor Elements such as Chajjas, Lintel,
8 mm
Parapet etc.
Slab and Wall for Blast Resistant building 12 mm
10.6 Deflections:
Minimum and maximum bar spacing for Foundations, Slabs, Stirrups for
Beams, Ties for Columns, Pedestals, Walls etc. should be 100 mm and
300 mm respectively. Bar spacing should be provided in multiples of 5
mm.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 55 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
requirements.
f) Hand rails, 1000mm high (from top of grating / top of chequered plate /
FFL), should be provided to all walkways, platforms, staircases. Toe
plate (100mmx5mm) should be provided for all horizontal hand railing
(except for hand railing in inclined portion of staircases). Spacing of
uprights should be 1500mm (maximum).
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 56 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
i) Dedicated monorail for every pump with driver rating of 75 kw and above
shall be provided. The monorail shall be placed longitudinally along the
centerline of the pump and its drive.
Monorail and trolley shall also be arranged for pumps with driver rating of
30 to 75 kw. But in such cases, different clusters can be formed with the
like pumps and a monorail can be placed across every cluster of pumps
over the line joining the CGs of the motors in that cluster.
k) Minimum two nuts should be used for all anchor bolts except for ladder,
stair and handrail.
l) Lock nuts shall be provided for anchor bolts of tall structures, tall process
columns, vibrating equipments etc.
m) Framing and bracing shall be planned so that the stiffness of the structure
can be well balanced with the loads and the structural stability can be
secured.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 57 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Structural Steel shall conform to IS: 2062 with minimum yield Strength of
250 N/mm2 & shapes shall be as per SP 6 of IS: 800 / IS: 12778 (wide
flange/narrow flange sections) or Universal beams and Columns as per BS.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 58 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
The limiting permissible vertical deflection for structural steel members such
as gantry girder for electric overhead crane, manually operated crane, purlin
supporting any type of roofing material under dead + live load or dead +
wind load conditions shall be as specified in IS: 800.
Pipe Rack Beams Span / 325, but not more than 30mm
Equipment Supporting
Structure:
Span / 325, but not more than 30mm
Static Equipment supporting
Beams
Span / 450, but not more than 30mm
Vibrating Equipment / Hoist
Supporting Beams
Span / 325, but not more than 30mm
Other Beams
Duct (refractory lined) Span / 360
2) Crane Girders
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 60 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
3) Miscellaneous
The ends of all tubes shall be sealed by using 6 mm thick plates welded all
round.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 61 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
11.7 Connections:
5) Ordinary black bolts & nuts (property class 4.6) shall conform to IS:
1367, part 3 shall be used for purlins, side runners, platforms,
ladders.etc. High strength bolts (property class 8.8) shall conform to
IS: 1367, part 3 shall be used for main structure members, such as
beams, columns, etc.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 62 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
1) Platform and walkways shall be as per piping design basis and shall
be made of grating flooring unless otherwise specified. Platforms
below the air fin coolers shall be provided with RCC platform.
11.9 Ladders:
11.11 Painting:
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0003
PAGE 63 OF 63
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
b) All masonry walls from ground floor shall be placed on R.C.C grade
beams. However, light internal partitions may be placed on ground floor
slab.
RCC and Steel chimneys should be designed as per the requirements of IS:4998
and IS:6533.
15.0 Barricading:
Foundation and superstructure shall be designed as per plant operation & safety
department/ General Civil requirements of location & height, keeping in view the
mean probable design life of structure.
Storage tanks shall be supported either on open ring wall type foundations or sand
pads in accordance with the Geotechnical recommendations.
STRUCTURAL
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 1 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
SEISMIC
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 2 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
CONTENTS
1.0 General
2.0 Design Consideration
3.0 Permissible Stresses
4.0 Method of Seismic Design
5.0 Ductile Detailing
6.0 Special Provision For Storage Tanks
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 3 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
1.0 General
1.1 Scope:
This establishes the basic inputs required for seismic design of the
plant and provides certain guidelines for the methods used for seismic
analysis of structures/equipment. However, detailed mathematical
formulations of seismic analysis are outside its scope.
Sr.
IS Code Description
No.
Code of practice for plain and reinforced
1 IS 456
concrete.
High strength deformed steel bars and wires for
2 IS 1786
concrete reinforcement.
Criteria for earthquake resistant design of
3 IS 1893
structures.
Criteria for Earthquake Resistant Design of
IS 1893
4 Structures - Part 1 : General Provisions and
Part-1
Buildings
Criteria for Earthquake Resistant Design of
IS 1893
5 Structures Part 4 Industrial Structures Including
Part-4
Stack-Like Structures
6 IS 2062 Steel for general structural purposes
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 4 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Note: The above list is suggestive and not exhaustive. Apart from
these basic codes any other related codes shall be also followed
wherever required.
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 5 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
1.3.1 Category-I :
1.3.2 Category-II:
1.3.3 Category-III:
1.3.4 Category-IV:
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 6 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Reference Seismic
Zone As per IS: 1893 Part-I.
Spectral acceleration
Coefficient (Sa/g) As per IS: 1893 (Part -I).
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 7 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
4.1 General:
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 8 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
Detailed analysis shall be carried out for all structures of Category 2 and
3 in seismic zones III, IV and V.
The estimation of in-plane stiffness and strength of URM infill walls shall
be based on provisions given in IS: 1893 (Part 1).
Buildings shall be designed for the design lateral force VB given by:
VB = Ah x W
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 9 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
If fundamental time period is greater than 0.04 second, one may use
pseudo static method or response spectrum method depending on the
height of structure / equipment. The height above which one should use
response spectrum method shall be as per the discretion of the
designer.
4.8 Damping
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 11 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
To control the serious loss of life and economic loss, the technique of
base isolation can be an alternate damage control strategy, which
should be promoted or encouraged in Seismic Zones III, IV and V. The
commonly used seismic isolators are:
(i) laminated natural rubber bearings,
(ii) high damping rubber bearings,
(iii) laminated lead rubber bearings, and
(iv) sliding bearings.
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0004
PAGE 12 OF 12
ENGINEERING CELL REV 03
PROJECT DEPARTMENT- RHQ
The value of Z and I (refer API 650 Appendix-E/ API 620 Appendix-L)
shall be taken as unity unless otherwise specified..
The spectral acceleration values for periods greater than 3.0 seconds
may be considered same as that for 3.0 seconds.
SEISMIC
CIVIL DESIGN BASIS
RHQ-EC-CL-0005
PAGE 1 OF 31
ENGINEERING CELL REV 00
PROJECT DEPARTMENT- RHQ
GEOTECHNICAL INVESTIGATION
AND REPORT
CONTENTS
1.0 General
2.0 Geotechnical & Topographical Survey Report
3.0 Special Notes
4.0 Appendix-1
1.0 General
1.1 Scope
This document is prepared for the purpose of carrying out detailed Soil
Investigation & Topographical Survey Work at the proposed plant location. This
specification is issued to investigate the geological features at the proposed plant
location, existing conditions, subsoil strata, location of ground water table and
thereby to determine various parameters like shear strength and bearing capacity
of the soil, physical and chemical properties of ground water, etc. Field as well as
laboratory tests are required to be carried out. Proposal shall be made for
foundation systems for different types of structures based on techno-commercial
consideration.
Sr.
IS Code Description
No.
CLASSIFICATION AND IDENTIFICATION OF SOILS FOR
1 IS 1498
GENERAL ENGINEERING PURPOSES
2 IS 1888 METHOD OF LOAD TESTS ON SOILS
CODE OF PRACTICE FOR SITE INVESTIGATION FOR
3 IS 1892
FOUNDATIONS
4 IS 2131 METHOD FOR STANDARD PENETRATION TEST FOR SOILS
CODE OF PRACTICE FOR THIN WALLED TUBE SAMPLING OF
5 IS 2132
SOILS
6 IS 2720 METHOD OF TEST FOR SOILS (RELEVANT PARTS)
7 IS: 3043 CODE OF PRACTICE FOR EARTHING
CODE OF PRACTICE FOR INDEXING AND STORAGE OF
8 IS: 4078
DRILLED CORES
9 IS: 4434 CODE OF PRACTICE FOR IN-SITU VANE SHEAR TEST
PRESENTATION OF DRILLING INFORMATION & CORE
10 IS: 4464
DESCRIPTION IN FOUNDATION INVESTIGATION
11 IS: 4968 METHOD FOR SUBSURFACE SOUNDING FOR SOILS
12 IS 5249 DETERMINATION OF DYNAMIC PROPERTIES OF SOIL –
METHOD OF TEST
13 IS 5313 GUIDE FOR CORE DRILLING OBSERVATIONS
14 IS 5529 IN-SITU PERMEABILITY TESTS, CODE OF PRACTICE FOR TEST
IN OVERBURDEN
Note: The above list is suggestive and not exhaustive. Apart from these basic
codes any other related codes shall be also followed wherever required.
A Geotechnical report is a tool for communicating the Site Conditions and Design
& Construction recommendations to the Structural & Civil Designer and the
Construction Personnel. They have the purpose of providing specific information
on Sub-surface Soil, Rock and Water conditions. It also includes interpretation of
the Site investigation information by a Geotechnical Expert/Engineer with Design
and Construction recommendations for Foundations, Earth Retaining Structures,
Embankments, Cuts and other required Facilities. The information in the Report
establishes a geotechnical baseline to be used in assessing the existence and
scope of changed Site conditions and is often referred to during the design period,
construction period, and frequently after completion of the project. Therefore, the
report should be as clear, concise, and accurate. First, preliminary geo-technical &
Topographical Survey report describing the field investigation with results and
interpretation shall be submitted to the Engineer with information which will benefit
the Design Process. Early submission of the Preliminary Report to the Design
Team is necessary for establishing Basic Design Concepts or Design Criteria.
In general, the geotechnical design report shall address all the geotechnical issues
that may be anticipated on a project. The report to identify each soil and rock unit
of engineering significance and provide recommended design parameters for each
of these units. A summary and analysis of all factual data is to be provided to justify
the recommended index and design properties. Groundwater conditions shall be
carefully assessed and described as it has impact both on Design and
Construction. For every project, the subsurface conditions encountered in the site
investigation need to be compared with the geologic setting to better understand
the nature of the deposits and to predict the degree of variability between borings.
Each geotechnical design issue must be addressed, and the results of these
studies need to be concisely and clearly discussed in the report. Of particular
importance is an assessment of the impact of existing subsurface conditions on
construction operations, phasing and timing. Properly addressing these items in
the report can preclude change-of-conditions claims. Sub-surface conditions
having an impact but not limited to the following are:
a) Vertical and lateral limits for recommended excavation and replacement of any
unsuitable shallow surface deposits (peat, muck, top soil etc.);
b) Excavation and cut requirements (i.e., safe slopes for open excavations or the need
for sheeting or shoring);
c) Anticipated fluctuation of groundwater table along with the consequences of high
groundwater table on excavations and liquefaction potential;
d) Effect of boulders on pile driveability or deep foundation drilling, and
e) Rock hardness on rippability.
Boring Criteria:
The choice of sampling tools, the methods of sampling and the procedure for
taking samples shall be in accordance with IS:1892 and IS:2132. Contractor shall
assign a reference number to each soil and water sample taken from the
borehole. This number shall be unique for that borehole and shall be in order of
depth below ground level. All samples shall be clearly labeled indicating job
number, borehole number, sample number, date of sampling, brief description of
sample, type of sample elevation of sample etc. In case of undisturbed samples,
the top and bottom of samples shall also be clearly labeled.
Every sample taken during the boring and sampling procedure shall be inspected
visually, manipulated by the hands and given a description with consideration
being given to the driller's description of the material and particularly to soil layer
changes. Each layer and/or sample will have a description pertaining to color,
moisture content, relative density, and relative consistency. Method of description
will be at the discretion of the Consultant except that all symbols and all
descriptions be defined on the finished boring log.
Samplers for recovering the undisturbed soil samples shall conform to IS: 2132.
Use of samples less than 65 mm in diameter shall not normally be permitted. The
sampling procedure shall conform to IS: 1892 and IS: 2132. In very hard and
dense soils, use of thick-walled sampler may be permitted, subject to approval of
the Engineer. In very soft or soft clays a piston sampler of an approved design
shall be used.
Immediately upon retrieval, the tubes are to be trimmed and cleaned of excess
soil on the ends, sealed with approved air-tight expanders on the top and sealing
wax on the bottom. Both ends shall be covered with plastic caps, then tape should
be applied in such a manner as to seal the open bolt holes and the lip of the cap.
Samples shall be kept in a vertical position with the top up during transporting
and storage. Samples shall not be jarred or shaken, and shall always be
protected from temperature extremes, especially freezing. Each tube shall be
properly tagged inside and out with all the pertinent information including project
and designation number, boring, depths, recovery percentage and date. The
sample shall be delivered promptly to the laboratory for testing.
Bag Samples:
All bags shall be properly tagged, inside and out, with tags showing the project
designation number, sample number, date and field identification number etc.
• Down –drag on • Interface shear strength • Vane shear • pH, resistivity test
shaft friction parameter (soil and test • Permeability test
• Quality of rock shaft) • CPT • Atterberg Limits
socket • Compressibility parameter • SPT (granular • Moisture content
• Lateral earth • Horizontal earth pressure soils) • Unit weight
pressures coefficients • Dilatometer • Collapse/swell
• Settlement • Chemical composition of • Piezometers potential test
(magnitude & rate) soil/rock • Rock coring • Slake durability
• Groundwater • Unit weights (RQD) • Rock uniaxial
seepage/dewaterin • Permeability of water- • Geophysical compression test and
g bearing soils testing intact rock modulus
• Presence of • Presence of artesian • Pont load strength test
boulders/very hard conditions • Slake durability
layers • Presence of shrink/swell
• Scour (for water soils (limits skin frication)
crossing) • Geologic mapping
• Extreme loading including orientation and
characteristics of rock
discontinuities
• Degradation of soft rock in
presence of water and/or air
(e.g. rock sockets in sales)
Embankmen • Settlement • Subsurface profile (soil, • Nuclear • 1-D Oedometer
ts and (magnitude & rate) ground water, rock) density • Triaxial tests
Embankmen • Bearing capacity • Compressibility parameter • Plate load test • Direct shear test
t foundations • Slope stability • Shear strength parameter • Test fill • Grain size distribution
• Lateral pressure • Unit weights • CPT • Atterberg Limits
• Internal stability • Time-rate consolidation • SPT (granular • Organic content
• Borrow source parameters soils) • Moisture-density
evaluation • Horizontal earth pressure • Dilatometer relationship
(available quantity coefficients • Vane shear • Hydraulic
and quality of • Interface friction • Rock coring conductivity
borrow soil) parameters (RQD) • Geosynthetic-soil
• Required • Pullout resistance • Geophysical testing
reinforcement • Geologic mapping testing • Shrink/swell
including orientation and • Slake durability
characteristics of rock • Unit weight
discontinuities
• Shrink/swell/degradation of
soil and rock fill
Excavations • slope stability • Subsurface profile (soil, • Test cut to • Hydraulic
and Cut • Bottom heave ground water, rock) evaluate-up conductivity
slops • Liquefaction • Shrink/swell Properties time • Grain size distribution
• Dewatering • Unit weight • Piezometers • Atterberg Limits
• Soil • Hydraulic conductivity • CPT • Triaxial tests
softening/progress • Time-rate consolidation • SPT (granular • Direct shear test
ive failure parameters soils) • Moisture content
• Pore pressures • Shear strength of soil and • Vane shear • Slake durability
rock (including • Dilatometer • Rock uniaxial
discontinuities) • Rock coring compression test and
• Geologic mapping (RQD) intact rock modulus
including orientation and
Settlement
Settlement
Soil Type
Pressure
Analysis
Capacity
Stability
Analysis
Analysis
Analysis
Analysis
Stability
Bearing
Unified
Lateral
Slope
Earth
GRAVEL Generally Generally Required for Generally not GW, SP, SW All walls
GW Well- not required not required spread needed & SP soils should be
graded if cut or fill except footings, except for SC generally designed to
GRAVEL slope is possibly for pile or drilled soils or for suitable for provide
GP Poorly- 1.5H to 1V SC soils. shaft large, heavy backfill minimum F.S.
graded or flatter, foundations. structures. behind or in = 2 against
GRAVEL and Spread Empirical retaining or overturning &
GM underdrains footings correlations reinforced F.S. = 1.5
Silty
GRAVEL are used to generally with SPT soil walls. against sliding
GC draw down adequate values usually GM, GC, SM along base.
Clayey
SAND the water except used to & SC soils External slope
SW Well- table in a cut possibly for estimate generally stability
graded slope. SC soils settlement suitable if consideration
SAND Erosion of have less s same as
SP Poorly- slopes may than 15% previously
graded be a fines. Lateral given for cut
SAND problem for earth slopes &
SM SW or SM pressure embankments
Silty
soils. analysis .
required
SAND using soil
SC angle of
Clayey
internal
friction.
Required Required Required. Required. These soils
unless non- unless non- Spread Can use SPT are not
SILT plastic. plastic. footing values if non- recommend
ML Inorganic Erosion of generally plastic. ed for use
silt Sandy slopes may adequate. directly
be a behind or in
problem. retaining or
CLAY Required Required reinforced
CL Inorganic soil walls.
Lean Clay
SILT Required Required
OL
Organic
Required. Required. Required. Required. These soils All walls
Erosion of are not should be
SILT
MH slopes may Deep Consolidation recommend designed to
Inorganic
be a foundation test data ed for use provide
problem. generally needed to directly minimum F.S.
CLAY Required. Required. required estimate behind or in = 2 against
CH Inorganic unless soil settlement retaining overturning &
Fat Clay has been amount and walls. F.S. = 1.5
OH CLAY Required. Required. preloaded. time. against sliding
Organic along base.
Required. Required. Deep Highly External slope
PEAT stability
PT Long term foundation compressible
Muck
and not
Notes:
A finished boring log based on the driller's field boring log and containing all
laboratory test results will be prepared for each test boring. The finished boring
log title page will contain
a. Boring number
b. Project number
c. Surface elevation
d. Latitude and Longitude
e. Type of drilling equipment
f. SPT hammer type (auto or manual)
g. SPT hammer calibration information (in notes column)
h. Drillers notes describing whether drilling mud was used
i. Definition of all symbols and terms that are otherwise not self-explanatory;
j. Sheet number and total number of log sheets for each boring
k. Date of drilling.
a. Depth scale
b. Horizontal line at stratum change
c. Elevation of bottom of boring
d. All drillers' notes tabulated in relation to the zone where the conditions were
encountered
e. All laboratory test results tabulated in relation to the exact depth from which the
sample was retrieved.
f. Percent Core recovery and RQD values
g. Description of material of each stratum
h. Water level observation and a description of how water level was determined
i. SPT Blow Counts and corrected Standard Penetration Test values tabulated in
relation to the exact depth that the test was conducted.
GEOTECHNICAL INVESTIGATION & REPORT
CIVIL DESIGN BASIS
RHQ-EC-CL-0005
PAGE 15 OF 31
ENGINEERING CELL REV 00
PROJECT DEPARTMENT- RHQ
In addition to the Basic information listed in clause 2.3.1, the following additional
information to be provided in the Report.
a. Descriptions of the Existing surface and subsurface drainage.
b. Evidence of excessively Wet Areas.
c. Slides, Slumps and faults noted along the Alignment.
Soil Cuts:
Fills:
Where embankments are to be built over soft grounds (such as clays, organic
silts, or peat), stability and settlement of the fill shall be carefully evaluated.
Following information to be provided:
Embankment Stability:
a. Stability of Embankment to be evaluated for minimum F.S. = 1.25 for side slopes
and 1.30 for end slopes.
b. Shear Strength of Foundation Soil to be determined from Lab Testing and / or
Field Vane Shear or Cone Penetrometer Tests.
c. Recommendations or feasible treatment alternates for increasing the factor of
safety to minimum acceptable level (such as change of alignment, lower grade,
excavation and replacement of weak subsoil, lightweight fill, geotextile fabric
reinforcement etc.).
Settlement of Subsoil:
2. Recommendations for alternate wall designs and reasons for the choice and/or
exclusion of certain wall types.
4. Estimated total, differential and time rate of settlement if the retaining structure
is placed on compressible foundation soils.
Construction Considerations:
6. Requirements for Excavation including safe slopes for open excavations or need
for sheeting or shoring.
In addition to the basic information listed in clause 2.3.1, the following information
to be also provided:
3. Allowable Soil bearing pressure and estimated footing Settlement and Time for
different sizes at different founding depths below ground level starting from 1.0
M.
4. Reasons for the type of Shear Failure adopted in the calculation for the Allowable
Soil bearing pressure.
Construction Considerations:
7. Requirements for Safe slope in open excavations i.e. need for shoring or
sheeting etc.
3. Estimated Pile Lengths and estimated Tip elevations for the recommended
allowable Pile Design Loads.
4. Estimation of Pile Group Settlement for friction pile groups ending in cohesive
soils.
6. Design analysis for verification that the pile section can be driven to the
estimated or specified tip elevation without damage. Applicable especially for
dense gravel-cobble-boulder layers or other obstructions.
7. P-y Curves (load vs deflection) or Soil parameters for evaluation of lateral load
capacity of piles.
Construction Considerations:
10. Need for preaugering, jetting, spudding, pile tip reinforcement, driving shoes etc.
11. Pile driving control recommendations for large no. of Piles via Dynamic Testing
or wave equation analysis.
In addition to the basic information listed in clause 2.3.1, if bored pile support is
recommended or given as an alternative, following conclusion/recommendations
to be provided:
3. P-y Curves (load vs deflection) or Soil parameters for evaluation of lateral load
capacity of piles.
Construction Considerations:
2. For lightweight fill, recommendations to include the material properties (φ, c, γ),
permeability, compressibility, and drainage requirements.
All results shall be properly tabulated giving reduced levels of ground and
boreholes at various borehole locations, depth of ground water table. Necessary
calculations and inferences shall be cross-referred and wherever references to
specific papers or documents are made in arriving at final figures, copies of such
references shall be attached.
d) Recommendation for the type of cement to be used and any treatment to the
underground concrete structures based on the chemical composition of soil
and sub-soil water.
b) The Location of Borehole for investigation shall be jointly finalized by the Geo-
tech Consultant & OWNER/IOCL before commencement of the Boring Works.
c) Loss or Make of drilling fluid: The “Loss” or “Make” of drilling fluid, if observed
during the boring, shall be noted and brought to the attention of the
OWNER/IOCL. Attempts shall be made to detect joints, fissures, artesian
conditions etc. Geotechnical Consultant shall include recommendations for the
Foundation works in the Final Geotechnical Report in the vicinity of such
discoveries.
d) Transportation and storage of samples: Contractor shall store properly all the
samples at the site till they are transported to his laboratory for testing. All rock
cores and samplers with undisturbed soil samples shall be placed in order of
their occurrence in strong wooden boxes, suitably partitioned and provided with
hinged wooden covers, so that the samples are not damaged during transit by
impact or improper handling. To minimize disturbance during shipment,
samplers containing undisturbed soil samples shall be packed with sawdust or
similar other resilient material and as directed by the OWNER/IOCL.
e) The record of the cores recovered during boring for all boreholes shall be
maintained and submitted in photographs along with the report.
g) The ‘N’ value obtained from the SPT field investigations shall be corrected to
arrive at the ‘Nc’ value by applying corrections for the field procedure,
Overburden pressure and Dilatancy. The energy ratio for the ‘N’ value obtained
GEOTECHNICAL INVESTIGATION & REPORT
CIVIL DESIGN BASIS
RHQ-EC-CL-0005
PAGE 22 OF 31
ENGINEERING CELL REV 00
PROJECT DEPARTMENT- RHQ
shall also be specified. Sample Calculation shall be provided for ‘Nc’ value
calculations in the Geotechnical Report.
h) The Particle Size Distribution Test, Atterberg Limits, Natural Moisture Content
Tests, Void Ratio, Specific Gravity, Relative Density, Classification of Soils as
per IS Code shall be carried out at every 1.5 m interval within continuous
stratum or at every change of stratum whichever is less.
m) For carrying out the Field and Laboratory Tests the following accreditation and
documentation requirements shall have to be met with:
ii. All machines should qualify the criteria of design, installation, operations
and performance qualification as required by NABL.
iv. At least 1% soil samples may be referred to the standard referral NABL /
equivalent Govt. authority accredited laboratories for cross checking so as
to ensure the accuracy and reproducibility of the soil test results.
4.0 APPENDIX 1
A4-1 Introduction
A4-1.1 Purpose and scope of investigation
A4-1.2 Abstract of findings and recommendations
A4-2 Site Conditions
A4-2.1 Site geology, general description
A4-2.2 Potential geologic hazards
A4-2.3 Site surface description
A4-2.4 Site topography, general description
A4-2.5 Description of above ground obstructions
A4-3 Surface Conditions
A4-3.1 Stratigraphy
A4-3.2 Subsurface material properties, general description
A4-3.3 Groundwater elevations and expected variations
A4-3.4 Description of underground obstructions encountered or otherwise
identified.
A4-4 Field Investigation
A4-4.1 Summary of operations
A4-4.2 Description of sampling procedures
A4-4.3 Description of field tests
A4-4.4 Logs of borings, pits, etc. containing :
A4-4.4.1 Complete description and thickness of all strata, including near-surface
materials such as paving, base course, topsoil, fill etc.
A4-4.4.2 Locations referenced to plant coordinate system.
foundations.
A4-8.2.2 Any increase in capacity for hydrotest loads, or for short term loads such
A4-8.4 Ultimate and allowable axial uplift capacity for various diameters
A4-8.4.1 Uplift capacity v/s length
A4-8.4.2 Any increase in capacity for hydrotest loads or for short term loads such
A4-10.4.1 pH value
A4-10.4.2 Electrical conductivity (laboratory determination)
A4-10.7 Permeability
A4-14 Earthwork
A4-14.1 Topsoil: Thickness for stripping; definition for contract documents
A4-14.2 Suitability soils at the site for use in compacted fills
A4-14.3 Special preparations or other requirements for use of on-site material
A4-14.4 Availability of imported fill
A4-14.5 Subgrade preparation
A4-14.6 Recommended compaction criteria and moisture content control
A4-14.7 Potential compaction difficulties and recommended solutions
A4-16.6 Cutting & Filling quantities for the Recommended Level of F.G.L.