2. Protect the equipment from temperature and humidity 6. Protect rubber lined pumps from heat, light and
extremes and exposure to excessive dust, moisture exposure to ozone.
and vibration.
7. The suction and discharge flange openings are to be
3. Rotate the shaft several turns every three to five covered unless connected to piping.
weeks.
8. All external machined surfaces are factory coated with a
4. Every six months purge the labyrinth with grease to rust preventative prior to shipment. Maintain the coating
prevent dirt and/or moisture contamination of the on these surfaces during storage.
bearings.
9. For outdoor or excessively unfavorable environment,
5. Protect rubber lined pumps from heat, light and cover the equipment with some type of protective
exposure to ozone. tarpaulin that will allow proper air circulation.
6. The suction and discharge flange openings are to be 10. Prior to start-up, inspect the packing to insure that it is
covered unless connected to piping. satisfactory. After a storage period of 18 months or
longer, repacking with fresh dye formed packing is
7. All external machined surfaces are factory coated with required at customer expense.
a rust preventative prior to shipment. Maintain the
protective coating on these surfaces with Kendall Seal 11. Maintain written documentation of labyrinth purging and
N Sound or a comparable product. shaft rotation intervals to be made available to Weir
upon request.
8. For outdoor or excessively unfavorable environment,
cover the equipment with some type of protective Accessories
tarpaulin that will allow proper air circulation.
Consult the original manufacturer for specific
9. Prior to start-up, inspect the packing to insure that it is recommendations on gear drives, electric motors,
satisfactory. mechanical seals, etc. Depending on length of storage
period, addition of rust inhibitors to oil, connection of space
10. Maintain written documentation of labyrinth purging and heaters or other requirements may exist to ensure the
shaft rotation intervals to be made available to Weir factory warranty remains valid.
International upon request for warranty validation.
For storage period greater than 36 months, please contact
LONG-TERM STORAGE PROCEDURE Weir Minerals.
For Periods Greater Than 18 Months,
But Less than 36 Months
Pumps
11/18/2008 © Copyright Weir Slurry Group Inc. IOM – WARMAN SLURRY PUMPS Section 1 – Page 15