JSA Declaration of Green Green Area For Gambat Compression Project

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

Job Safety Analysis

Job Safety Worksheet

Area of Work Considered: PROCUREMENT, CONSTRUCTION & PRE-COMMISSIONING Job No: PPL-
JSA Date: October 06,2022
WORKS FOR GAMBAT (GPF-IV) COMPRESSION PROJECT - Gasco/PPL JSA GAM-22-SD-009

1. Aijaz (HSE Advisor PPL ) 2. Muhammad Haris [SE(Pr) 3. Hamid Surveyor Gasco
JSA participants
4. Shamsheer Mushtaq (HSE Lead) 5.

Job Location & details:

Gambat compression project area. JSA for declaration green area

Prepared By: Shamsher Mushtaq


Distribution:
Reviewed By: Aijaz Ahmed ,

Type of Permit Required Additional PPE Requirements


Special tools or equipment’s required
(Please List)
1. 2. Cold Work Permit 7. Electrical/Instrument Isolation Certificate 1. Face Shield 1. Ambulance / Standby Vehicle
3. Hot Work Permit 8. Confined Space Entry Certificate  2. Dust Mask 2. Hand Tool and Power Tool
4. Vehicle Entry Permit 9. Excavation Certificate  3. Ear plugs 3. Lifting Gears /Equipment, Shackles, belts, Slings &
5. Process/Mechanical Isolation Certificate 10. Radiography Certificate 4. High Visible Vest Hoist
6. Process/Mechanical Isolation Continuation 11. Heavy Lift Certificate 5. Rigging Gloves 4. Trailer
Certificate 12. Safety System Defeat Certificate 6. Safety Shoes 5. Excavator
13. De-Isolation for test Certificate 7. Safety Helmet 6. Water Bowser 
8. Coverall 7. Certified Crane
8. Earth Moving Equipment’s
Job Safety Analysis

9. Tractor 

Approved By: Signature: Date:

Report Number Incident Summary

Activity Assessment Form


JSA for declaration of green area for Gambat compression project
Residual
Task / Activity Responsibilit
Hazard Hazard Effect Risk Rating Control Measures Risk
Description y
Rating
 Work under Gasco PTW system,
 Movement and entry/exit from Gate#4 near raw water tank.
 Third Party Certified & Inspected Equipment Shall be used
 Spark Arrestors Shall be Installed on Exhaust
Mobilization Of
 Route shall be decided & communicated to all drivers & operators in
Equipment, 3D 2A
Movement near Injury / asset case of main gate access for heavy vehicle permit get from PPL
Material & Gasco
operation
personnel Live plant Damage
 Ensured that all drivers have DDC
 Awareness session conducted with all crew for don’t allow in live
plant area and Gasco will make sure the same.

Fire/ Plant shutdown Personal Injury/ 3D 2B


Emergency at Live
Asset Damage
plant  Suspended all activities and report to muster point near gate#4
PPL/Gasco
 Contact with CCR for further advise/action
Job Safety Analysis

 Suspended all activities and report to muster point near gate#4


 Fire
 Inform to CCR in case of any emergency
 Personnel Personal Injury/ 3D Gasco
Emergency at  Paramedic and ambulance available on site for handling any 2B
Project area Injury emergency Contact with CCR for further advise/action.
 Follow Gasco ERP and share emergency contact number with CCR

 Non-
Availability  Fatality
Adequacy of Gasco will make sure availability of emergency equipment, DCP and
of  Asset 3D Gasco
Emergency CO2 fire extinguisher 2B
Equipment Emergency damage
equipment

Gasco permit to work system follow for Hot work and RT and
Personnel Injury indorse from PPL project and CCR.
Hot Work, RT Fire 3D Gasco
Excavation permit will get from CCR, E/I and Mechanical as per 2B
and Excavation Plant shutdown Asset damage
previous practices
Job Safety Analysis