ZEALCON- HSE-MAN-F004

ZEALCON ENGINEERING (PVT.) LTD

Part 1: Job Description: Repairing of Water Spouts with the Help of Cherry Picker & Scaffolding Location: FEC Switch Room
Platform at FEC Switch Room
JRA Date: 25-02-2011 JRA No./ Revision: 11-194 JRA Leader: Michael Middleton Scribe: Abrar-ul-Hassan
Review Team: (e.g. Ops Review Team) M Ramzan, Imdadullah, Haji Sadiq, Jawad Rasool & Abrar-ul-Hassan
List Associated Procedures/work instructions or Temporary WIs:
Hazard Check List (FRCP identified below must reference applicable FRCP Control Measures – refer to FRCP Handbooks)
√ Falls from Heights √ Access / Egress Confined Space √ Manual Handling √ Fatigue/Over Exertion √ Slips, Trips & Falls
√ Competence of
√ Falling Objects √ Collisions Noise Illumination Environmental
Personnel
Liquid/Gas Under √ Flaring/Hydrocarbon
Oil/Chemical Flammable Materials √ Moving Machinery Electricity
Pressure Release
Surface Mobile
Ignition Source Light Vehicles
Corrosive Substance Chemical Exposure Naked Flames Equipment
(Sparks/Electrical) (FRCP)
(FRCP)
Hazardous Materials Equipment Other
Isolation √ Working at Heights Lifting Operations (please specify)
Management Safeguarding
(FRCP) (FRCP) (FRCP)
(FRCP) (FRCP)

Part 2: Job Risk Assessment

Step
Hazard Hazard Effect Hazard Controls Controls Acceptable
Job Steps Use Checklist as a Guide to Injury/Damage or
No. Use Hierarchy of Controls/FRCP Control Measures Y/N
be Specific Environmental Effect

01 Mobilization of  Un inducted  Personal  Ensure inducted and medically fit and Yes
personals, people injury approved people only should be enter in
Equipment and the working area
Hand Tools
 Workers  Risk to  Emergency response requirements,
unaware of property Emergency access, Muster Points and
access & other relevant protocols as per standard
protocols of FRCP shall be reinforced during
toolbox meeting.
 Discussed work scope with team

CONTROLLED DOCUMENT
PF03.02 Page 1 of 5 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal
ZEALCON- HSE-MAN-F004
ZEALCON ENGINEERING (PVT.) LTD

 Conduct daily Tool box Meeting before


the job starts

 Hydrocarbons
 Ensure that continuous gas testing is
 Fire/ carried out during Cherry Picker
Explosion Operation at FEC Switch Room
 Snacks
 Bite/ Fatality  Be aware of snakes
 If a snake is seen in the working area
stop the job inform to everyone to keep
clear report to BHPB FEC HSEC team &
DEL HSE
 First aid kit is available at worksite
 Immediately report to Projects HSEC
team and Doctor (DEL) in case of Snake
Biting
02 Repairing of  Un inspected  Injury to  Ensure that all equipment’s is inspected Yes
Water Spouts equipment personnel / by DEL (E & P) and FEC Projects HSEC
with the help of damage to Team and Cherry Picker shall be
Cherry Picker property and Inspected from Ops with valid Vehicle
and Scaffolding Environment entry certificate
Platform
 Cement Burn  Skin and eye  MSDS of cement will be followed
irritation  Wash exposed area with fresh water if
contact with skin and eye
 Use rubber gloves when handling with
cement
 Eye wash bottle on site and kept cool
 Cement dust  Inhalation  Use of dust mask
 Mortar Hand  Injury to  Brick soling, Pit liner or polyethylene
Mixing person sheet must be use underneath of
material prior to mortar hand mixing
 Use good conditioned wheel barrows &

CONTROLLED DOCUMENT
PF03.02 Page 2 of 5 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal
ZEALCON- HSE-MAN-F004
ZEALCON ENGINEERING (PVT.) LTD

other hand tools


 Use PVC/Rubber Gloves during mixing of
mortar and repair work
 Dust proof Google
 Back injury
 Use correct manual handling techniques
 Manual with proper posture of body
Handling
 Take periodic rest and take plenty of
cold water for drinking
 Workers will be oriented about the
proper posture and positioning during the
execution of job
 Hand Injury
 Sharp edges  Be aware of sharp edges
 Use proper hand gloves
 Fall from
height  Use inspected cherry picker and
 Working on approved green tagged scaffolding
height using platform from FEC project HSE for
scaffolding repairing work
platform &
cherry picker  Use full body safety harness belt with
basket suitable anchor point on cherry picker
 Only two persons allowed in the basket
of cherry picker
 Cordon off area
 Drop zone to be maintain and remove
after job make sure Spotter on site
 Ensure no one enter in drop zone during
working
 No material to be stored / left on the
scaffolding platform or cherry picker on
height
 Ensure that after complete the work on
platform must be remove all material
and tools from working platform
 Personal
 Slip, trip and Injury  Ensure that waste material of repairing
CONTROLLED DOCUMENT
PF03.02 Page 3 of 5 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal
ZEALCON- HSE-MAN-F004
ZEALCON ENGINEERING (PVT.) LTD

fall work on Scaffolding platform or on cherry


picker basket should be clean and clear
 Area maintain clean & clear
03 Change  A condition  Safety of  Before any modification or engineering Yes
management arises where people changes, site supervisor shall ensure the
the work  Damage to matter is reported to DEL engineering or
cannot continue equipment HSEC and Del management must report
as planned,  Damage to the matter to FEC team.
such as property  Stop the job
engineering  Notify supervisor
changes or  Notify superintendent.
modification...  DEL Supervision will notify FEC relevant
engineer and HSEC personnel for advice.
 Corrective action will be taken and the
JRA updated with the new work method
instructions.
 Discussions will include the work group
about he changes and the information
about the changes explained to the
workgroup.
04 Demobilization  Poor house  Slip, Trip,  Job supervisor to ensure that area was Yes
keeping Fall left clean and clear
 Remove all unnecessary material from
site to designated stacking place
JRA No./ Revision: Page #

CONTROLLED DOCUMENT
PF03.02 Page 4 of 5 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal
ZEALCON- HSE-MAN-F004
ZEALCON ENGINEERING (PVT.) LTD

Alternatives Considered: What are the other possible means of achieving the job outcome?

Part 3: Contingency Plans: What rescue equipment, PPE etc could be needed if something went wrong? Reference Field ERP

Full time communication with CCR to be made in case of any emergency / muster (Secure the place and go to the designated operation muster
point.

Hazard Controls in place and Effective Yes/No


Participants Signatures: JRA Leader’s Signature:
Mohammad Ramzan Construction Manager Civil (DESCON)
Imdadullah Kalhoro Civil Engineer (DESCON)
Haji Sadiq Civil Supervisor (DESCON)
Abdul Rasheed HSE Supervisor (DESCON)
Abrar-ul-Hassan HSE Supervisor (DESCON)
Part 4: Review
After job has been completed, JRA Leader should note:
 Any hazards which were NOT identified in the original JRA?
 Any practices that need to be captured in the process?
 List actions, changes, and incorporate any changes onto this form below.
Pre-Job and Post-Job Reviews & Updates to the JRA
Review Date 13-03-2011 Review Leader Michael Middleton
Review Comments: NOTE: - This JRA is valid for Two week after Two week it must be reviewed and revised by DEL and BHPB Projects
HSEC team. Please report one day before the due date if another JRA is required.

CONTROLLED DOCUMENT
PF03.02 Page 5 of 5 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal