Professional Documents
Culture Documents
AKT-PR-PHI-200-0001 - IFU Updated
AKT-PR-PHI-200-0001 - IFU Updated
AKT-PR-PHI-200-0001 - IFU Updated
X Key Non-Key
Revision Reason for Issue Date Author Checked Approved COMPANY Date
PROVISION OF BLANKET
ENGINEERING TO SUPPORT DOCUMENT NO.
AKATARA FIELD DEVELOPMENT
CONTRACT NO. 093-CO-23
AKT-PR-PHI-200-0001
DOCUMENT REVIEW COMMENT SHEET
PROJECT: AKATARA PHASE 2 DEVELOPMENT CONCEPTUAL PROJECT CLIENT: JADESTONE ENERGY (LEMANG) PTE. LTD.
Discipline: PROCESS
Document Title: Process Design Philosophy
Document No.: AKT-PR-PHI-200-0001 Revision: A
CTR No:
Total Review Duration: 5 Working Days
Responsible / Consolidator: Yulianto Hari Tribroto Reviewers 06 ~ 10 Nov 2023 (4WD)
Responsible 13 November 2023 (+1WD)
Revise and issue as next issuance status with applicable alphabetical revision (B, C, D,
Return Code: REVIEWED WITH MAJOR COMMENTS - etc). Work may not proceed until the document has been resubmitted, reviewed and
returned either code 1 or code 2.
Section/ By
# Rev. No. COMPANY Comments CONTRACTOR Response COMPANY Closed out
Location (Initials)
Up d at e
The comment has been
7 A Ch ap t er 4.3.2 Fo r m in im u m d esig n p r essu r e ........f o r f u ll vacu u m if m eet t h e cr it er ia list ed in YHT
incorporated
sect io n 4.3.1. "
Delet e co n t en t 5.2.1 Pip elin es The comment has been
8 A Ch ap t er 5.2.1 YHT
Th er e is n o f lo w lin e m o d if icat io n incorporated
Up d at e "t h is in clu d es : ............Relief an d b lo 0w d o w n f r o m Fu el Gas Syst em "
Th is is p h ilo so p h y.
Delet e f o llo w in g sen t en ce:"h o w ever t h is is ......f lar e t ip ven d o r ." The comment has been
12 A Ch ap t er 7.2.2 YHT
incorporated
Up d at e t ab le 8-2
Belo w sh all b e ab o ve
Page 1 of 2
DOCUMENT REVIEW COMMENT SHEET
PROJECT: AKATARA PHASE 2 DEVELOPMENT CONCEPTUAL PROJECT CLIENT: JADESTONE ENERGY (LEMANG) PTE. LTD.
Discipline: PROCESS
Document Title: Process Design Philosophy
Document No.: AKT-PR-PHI-200-0001 Revision: A
CTR No:
Total Review Duration: 5 Working Days
Responsible / Consolidator: Yulianto Hari Tribroto Reviewers 06 ~ 10 Nov 2023 (4WD)
Responsible 13 November 2023 (+1WD)
Revise and issue as next issuance status with applicable alphabetical revision (B, C, D,
Return Code: REVIEWED WITH MAJOR COMMENTS - etc). Work may not proceed until the document has been resubmitted, reviewed and
returned either code 1 or code 2.
Section/ By
# Rev. No. COMPANY Comments CONTRACTOR Response COMPANY Closed out
Location (Initials)
Up d at e
Sp ect acle b lin d sh all b e in clo sed p o sit io n
The comment has been
14 A Ch ap t er 8.9.1 YHT
incorporated
Page 2 of 2
Process Design Philosophy
REVISION RECORD
Section/
Rev. No. Reason for Revision
Page Ref.
0 1 Introduction has been revised
0 5.2.1 Section 5.2.1 pipeline has been deleted
0 4.5.1.4 The sentence has been revised
0 4.1.2 "The minimum availability ...........90%. " has been deleted
0 4.3.1 Table number has been revised
A sentence has been revised to add “…for full vacuum if meet the criteria
0 4.3.2
listed in section 4.3.1.”
0 7.1.1-7.1.3 Relief & blowdown system lists have been deleted
0 7.2.2 A sentence has been revised
0 8.3.1 Table 8-2 has been revised
0 8.9.1 Spectable blind has been revised to be in a closed position
2 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
CONTENTS
1 INTRODUCTION .............................................................................................................................................. 6
1.1 Objective ................................................................................................................................................... 7
1.2 Definitions ................................................................................................................................................. 7
1.3 Abbreviations ............................................................................................................................................ 7
2 CODES, STANDARDS, AND REGULATION................................................................................................... 9
3 UNIT OF MEASUREMENT .............................................................................................................................. 9
4 EQUIPMENT PHILOSOPHY .......................................................................................................................... 10
4.1 DESIGN CASE ....................................................................................................................................... 10
4.1.1 Design Margin ................................................................................................................................. 10
4.1.2 Plant Availability .............................................................................................................................. 10
4.1.3 Turndown ........................................................................................................................................ 10
4.2 SPARING PHILOSOPHY ....................................................................................................................... 10
4.2.1 Major Equipment ............................................................................................................................. 10
4.2.2 Instrumentation ............................................................................................................................... 10
4.2.3 Relief Valves ................................................................................................................................... 10
4.2.4 Control Valve .................................................................................................................................. 11
4.3 DESIGN PRESSURE ............................................................................................................................. 11
4.3.1 Maximum Design Pressure ............................................................................................................. 11
4.3.2 Minimum Design Pressure .............................................................................................................. 13
4.4 DESIGN TEMPERATURE ...................................................................................................................... 13
4.4.1 Maximum Design Temperature ...................................................................................................... 13
4.4.2 Minimum Design Temperature ....................................................................................................... 14
4.5 EQUIPMENT SIZING ............................................................................................................................. 15
4.5.1 Separator ........................................................................................................................................ 15
4.5.2 Pumps ............................................................................................................................................. 20
4.5.4 Compressor .................................................................................................................................... 21
4.5.5 Heat Exchanger .............................................................................................................................. 22
4.5.6 Electric Heaters............................................................................................................................... 22
4.5.7 Column ............................................................................................................................................ 22
4.5.8 LPG Storage Vessel ....................................................................................................................... 23
4.5.9 Relief Valves ................................................................................................................................... 23
4.5.10 Control Valve Sizing........................................................................................................................ 24
4.6 LINE SIZING CRITERIA ......................................................................................................................... 24
4.6.1 General ........................................................................................................................................... 24
3 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
4 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
5 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
1 INTRODUCTION
The Akatara Field is located onshore Jambi Province, Sumatra Island, Indonesia, (Figure 1-1), in the Lemang
Block Production Sharing Contract (PSC) and is operated by Jadestone Energy (Lemang) Pte. Ltd. COMPANY
is currently in the stage of developing the Akatara gas field to produce natural gas and liquids (Liquid Petroleum
Gas / LPG and Condensate), with expected first production in Q2 2024. The gas sales agreement (“GSA”) has
been established with PLN Batam as the gas buyer, whereby the gas to be tied-in to the TGI pipeline in Jambi
area. The GSA is in place for 20.5 Bbtud.
The project execution (EPCI) stage of Akatara Gas Processing Facility and Sales Gas Pipeline (AGPF) including
associated facilities such as pipeline and gas metering station is expected to be completed in Q2 2024. The
sales gas will be piped at approximately 17 km from AGPF for further tie-in to the existing Grissik Singapore
Pipeline (“GSPL”) operated by TGI. Meanwhile, the sales point for the LPG and Condensate is at the plant gate
by tank truck.
Fields
South Sumatera Basin
Oil
Basin
Gas
Gas & Condensate
6 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
1.1 Objective
The objectives of this document are:
To provide the minimum process and mechanical design requirements.
To provide a consistent set of guidelines for sizing of equipment and process piping.
To provide guidelines on typical margins to be applied to the sizing of equipment to ensure that
equipment costs are minimized.
To provide a basis for designing relief system, blowdown system, and hydrocarbon disposal system
include sizing of relief valves, blowdown philosophy, and design criteria for sizing disposal equipment.
Define safe isolation methods, draining, purging and venting provisions for on-line plant containing
process and utility liquids and gases, so that operation, maintenance and inspection can take place with
minimum plant shutdown.
Ensure necessary facilities are incorporated in the design.
This philosophy is mandatory to be applied for the new equipment and facilities that will be installed during
project. Specific design criteria for particular items of equipment are described. Turndown and the need for
sparing of equipment are also discussed. The guidance is not intended to substitute for good engineering
practices. Consideration should be given to special circumstances where more or less rigorous criteria should be
applied.
1.2 Definitions
PROJECT Akatara Gas Development Project Phase 2
COMPANY Jadestone Energy (Lemang) PTE. LTD. (JEPL)
CONTRACTOR PT Synergy Engineering
SUB CONTRACTOR Any organization appointed by CONTRACTOR to perform work on the
PROJECT
VENDOR Any organization providing goods to COMPANY, CONTRACTOR, and
SUBCONTRACTOR.
1.3 Abbreviations
Table 1-1 Abbreviations
Abbreviation Definition
AGPF Akatara Gas Processing Facility
AKT Akatara
API American Petroleum Institute
ANSI American National Standards Institute
ASME American Society of Mechanical Engineers
BDV Blowdown Valve
BOD Basis of Design
CSO Car-sealed Open
DBB Double Block and Bleed
DT Design Temperature
EDP Emergency Shutdown with Depressurization
7 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Abbreviation Definition
ESD Emergency Shutdown
FB Full Bore
FEED Front End Engineering Design
HLL High Liquid Level
HP High Pressure
KO Knock Out
LALL Low Low Level Alarm/Trip
LC Locked Closed
LLL Low Liquid Level
LP Low Pressure
LPG Liquefied Petroleum Gas
MAOP Maximum Allowable Operating Pressure
MOP Maximum Operating Pressure
NB Nominal Bore
NLL Normal Liquid Level
NPSHa Net Positive Suction Head Available
NPSHR Net Positive Suction Head Required
PAHH Pressure Alarm High High
PFP Passive Fire Protective Insulation
PSHH Pressure Switch High High
PSV Pressure Safety Valve
RO Restriction Orifice
SB Single Block
SDV Shutdown Valve
TALL Temperature Alarm Low-low
8 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
9 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
4 EQUIPMENT PHILOSOPHY
4.1 DESIGN CASE
4.1.1 Design Margin
The heat and material balance will be prepared without design margin. Design margin will be added and noted
when completing equipment datasheets and performing process calculations.
In general, a design margin of 10% is applied on flow for the design of process facilities, which allows for
uncertainties in the process data and process modelling. However, this margin can be varied on a case-by-case
basis.
For packaged equipment, a guaranteed capacity should be defined, with vendors requested to identify what
design margin has been applied to ensure the guaranteed capacity is achieved.
4.1.2 Plant Availability
The ‘Availability’ of the plant accounts for the times when the plant is producing at reduced capacity or shutdown.
These circumstances can occur due to the following examples:
Production shutdowns in an emergency.
Production shutdowns for scheduled equipment maintenance.
Production shutdowns for equipment failure or unscheduled maintenance.
Reduced production due to operating restrictions e.g. hydrates, slugging.
Reduced production due to environmental constraints.
4.1.3 Turndown
The gas conditioning facility shall be designed to operate over the range of 40% to 100% nominal design
capacity. Individual items of equipment will be designed for the range of operating rates likely to occur during the
life of the facilities. For package equipment/Licensor e.g (compressor, LPG Processing system, etc) shall be
verified with Equipment Vendor/packager and some special justification shall be decided case by case.
4.2 SPARING PHILOSOPHY
Sparing should only be provided if it can be justified based on equipment criticality and availability assessment
basis. Sparing will be determined using RAM based assessment - additional sparing will only be provided if
justified by improvements in facility availability using NPV based assessment.
4.2.1 Major Equipment
Generally, no installed spares will be provided except for critical pumps, for which an N+1 philosophy is adopted,
and for equipment, the loss of which, would cause a hazard, prolonged flaring or unacceptable loss of supply to
a downstream facility. For equipment within package Licensor/Vendor, sparing philosophy will be reviewed under
the same criteria
4.2.2 Instrumentation
Generally, spares are provided for fuel gas control valves and fiscal metering components. For transmitter and
control valves in critical service, the sparing will be examined case by case.
4.2.3 Relief Valves
Spare relief valves are to be provided for all relieving cases excluding thermal relief (but including fire relief),
unless the equipment that the relief valve protects is spared.
Installed spare relief valves shall be provided as follows:
All equipment items which need relief valves and are both in continuous service (without standby
counterpart) and are critical to production shall be equipped with a spare relief valve. If a single valve
10 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
meets the relief requirement (i.e. 1x100%), the spare shall also be 1x100%. Where multiple relief valves
are required for a particular services (e.g. 2x50%), the spare shall be equivalent to the largest size single
relief valve. Preference should be given to install all valves of equal size (e.g. 3x50%). This requirement
includes critical utilities.
Installed spare relief valves are not required on equipment which is in continuous production but is not
critical to production.
All relief valves in standby systems shall be unspared. This includes any stand-by compression trains.
All equipment items which need relief valves and have standby counterpart shall be unspared. Such
equipment includes pumps, filters etc.
Single fire relief valves shall be provided on PCHEs.
Single relief valves shall be provided on non-essential systems (e.g. washdown water, possibly potable
water, etc).
Thermal relief valves (liquid expansion) shall be unspared.
When installed spare relief valves are not provided, then a spare stored relief valve shall be provided.
4.2.4 Control Valve
All unspared control valves for which failure can impact production but where accurate control is not mandatory
should have a bypass installed. The valve shall be a globe valve with a fully open Cv not to exceed the control
valve full open Cv and not less than 50% of the control valve Cv.
All critical control valves where the process requires continuous modulation shall be spared.
Control valves in systems which can be shut down and isolated without impact on production or immediate
impact on the living quarters/control room will be unspared and provided without bypass.
A check valve, if required, shall be located such that it protects the control valve and bypass valve (i.e. outside of
the control valve isolation valves and downstream of the bypass valve tie-in).
4.3 DESIGN PRESSURE
4.3.1 Maximum Design Pressure
For systems protected by a PSV, the criteria in Table 4-1 shall be as a minimum applied.
Table 4-1 Design Pressure Criteria for Pressurized Systems
The limitations given in Table 4-1 are to ensure proper setting of the PSV’s. The MOP (maximum operating
pressure) or PAHH set point is typically 10% above the operating pressure (OP).
Mechanical design codes for piping and equipment have different limitations with regard to maximum allowable
overpressure but such differences should be minimized, consideration may be given to using a reduced design
margin, subject to Company approval, to ensure that the most appropriate design pressure is specified.
11 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
The design pressure of a piping system comprising pipes, fittings, flanges and valves shall in general be
according to ANSI/ASME B31.3. Static head, friction loss and surge pressures shall be taken into consideration.
The design pressure for piping shall be the maximum determined on the basis of the following:
The maximum continuous operating pressure as defined by the process requirements but not less than
75 psig.
The vapor pressure of the commodity in the pipe at maximum design temperature, unless protected by a
pressure relieving device.
The set pressure of a pressure relieving device that protects the pipe.
The maximum pump shut-off or blocked in discharge pressure, adjusted for short-term variations from
design pressure as allowed in ASME B31.3 and ASME B31.1.
An appropriate margin shall be applied between design pressure and the flange rating of associated piping and
equipment to avoid over-stressing of equipment nozzles. A minimum margin of 5% is recommended or 14.5 psi,
whichever is the greater.
Full vacuum design conditions will be applied to equipment (and associated piping) that fulfills one or more of the
following criteria:
Is subject to vacuum during start-up, shut-down or regeneration, draining or pump out
Normally operates full of liquid and can be cooled or blocked in
Can undergo vacuum through the loss of heat input.
Equipment subject to steam out
The vapor pressure of stream in service corresponding to the minimum ambient temperature
The lowest value of maximum design pressure will be 50.75 psig (i.e. 3.5 barg), except for storage tanks
operating at atmospheric pressure.
Atmospheric tanks shall, as a minimum, be designed to be filled “Full of liquid” otherwise the design pressure be
“Full of water” up to the highest possible point and with an overpressure of 1 psig. For cone roofed hydrocarbon
storage tanks, the design pressure will be based on the vapor pressure of the contained fluid at the maximum
temperature that can be reached in the storage and the relief valves (breather valves) will be designed based on
the maximum emergency in-breathing and out-breathing. Reference should be made to API 2000. Vacuum
design condition of tank pressurized by blanket gas shall be determined by the final tank wall thickness. For the
low pressure storage tanks which are blanketed by fuel gas or inert gas are designed for + 0.8 psig / -0.094 psig
For Unfired Pressure Vessel the criteria in Table 4-2 shall be as a minimum applied.
Table 4-2 Design Pressure Criteria for Unfired Pressure Vessel
0 – 50 75
Equipment not protected by PSV and located downstream of a pump or a compressor shall be designed for the
shut-in pressure according to the maximum suction pressure based on suction vessel PSV set pressure and NLL
plus pump shut-in head at the maximum rated speed.
12 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Where data from vendor is unavailable, the shut-in head may be estimated as 1.25 times the differential
pressure developed by the pump at maximum rated speed. Maximum rated speed for variable speed drives is to
be specified as 1.10 times the speed for the normal differential pressure at maximum rated flow.
When there is a large difference in delivery and suction pressures, consideration shall be given to whether the
delivery pressure can be imposed on the suction line. If this is the case, the suction line shall be rated for the
same pressure as the discharge line with the specification break taken at the first block valve on the suction line.
The design pressure at the discharge of a reciprocating pump, (e.g. in chemical injection systems) shall be set at
10% above the maximum expected operating pressure, overpressure protection being provided by an
independent pressure relief valve. The pump shall be capable of pumping at the design pressure of the
discharge vessel or system.
The operating pressure of flowlines shall not exceed the MAOP which is generally a minimum of 10% below
hydrotest pressure. The MAWP shall be set by the mechanical engineering/pipeline engineering department
based on material grade and thickness. Generally the MAWP shall be greater than the hydrotest pressure and at
least 100 psig greater than the MAOP. Design pressure for the wellheads and flowlines shall be normally equal
to or lower than the SITHP. In case the design pressure is lower than the SITHP, the flowlines shall be protected
by a pressure relief device.
4.3.2 Minimum Design Pressure
For minimum design pressure, all piping and vessels shall be designed for full vacuum if meet the criteria listed
in section 4.3.1.
4.4 DESIGN TEMPERATURE
4.4.1 Maximum Design Temperature
In general, the maximum design temperature (DT) is calculated by adding 25°F above the operating temperature
(OT). This can be shown as below (as minimum).
o
T OT 2 F
For equipment operating at ambient conditions, the upper design temperature shall be at least equal to a
maximum black bulb temperature of 65°C (149°F), unless it is insulated or other corrective action is taken. Fire
conditions will not be considered in establishing the design temperature of a vessel.
When establishing design temperature, consideration should be given to all abnormal operating conditions, e.g.
start-up, relieving conditions, shut down, depressuring, regeneration, etc.
For thermally insulated equipment, the maximum design temperature shall not be less than 10°C (18°F) greater
than the maximum ambient air temperature.
A high temperature shutdown function may be used to limit the maximum operating temperature of a system. In
such cases, a minimum margin of 5°C (9°F) shall be provided between the TAHH set point and the maximum
design temperature to allow time for the shutdown system to initiate.
In determining the maximum design temperature of systems located downstream of heat exchangers, the
following should be taken into consideration:
a. Potential for the heat exchanger to be bypassed during normal operation.
b. Loss of cooling in the upstream heat exchanger.
If a system operates with wide ranges of operating pressures and temperatures, the system should be designed
for coincident high pressure and high temperature, unless it can clearly be demonstrated that there is no credible
coincident condition.
13 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Compressor System
The discharge design temperature for compressor systems will initially be set at 200°C (392°F, i.e. maximum
seal design temperature) for centrifugal compressor. For reciprocating compressor, the maximum discharge
temperature shall not exceed 140°C (284°F) and for non-lubricated reciprocating compressor shall not exceed
130°C (266°F).
This will be confirmed against the maximum design temperature from the compressor supplier once the
information is available. The compatibility of the supplier data with the rest of the system should be checked to
ensure the appropriate margins are provided. The discharge temperature with the compressor in full recycle
shall be considered.
Power Generation System
For Gas Engine/Turbine Generator, the ISO power is to be de-rated to the service power at the most severe
o
ambient conditions under which the turbine/engine will operate. Ambient condition of 37 C is to be used, (High
O O O
Ambient Temperature of 35 C + Hot air circulation of 1 C + Global Warming of 1 C).
4.4.2 Minimum Design Temperature
In general, the minimum design temperature of equipment and piping shall be selected to avoid the requirement
for significant quantities of alloy steel.
Minimum design temperature for each system shall be determined by the lowest temperature calculated for the
following conditions:
1. Minimum ambient temperature.
2. Minimum operating temperature experienced during normal operation, startup, shutdown, process
upsets, and other off design cases minus 5°C (9°F).
o
3. Normal operating temperature (in case low operating temperature i.e. less than 20 F).
4. Minimum temperature experienced during depressurization (blowdown) to account for simulation
uncertainty.
5. Minimum temperature experienced during a startup operation following a full system depressurization.
6. Minimum temperature caused by draining activity (from system containing fluids at low temperature)
7. Minimum temperature caused by start-up pressurization (in case of start-up, low process fluid can occur
due to Joule-Thompson effect downstream of any restriction).
For all cases, the minimum design temperature shall be assumed to be coincident with the maximum system
design pressure, unless it can clearly be demonstrated that the case is not credible through HAZOP and LOPA.
The impact of minimum temperature at the estimated pressure for this case shall be evaluated.
If the application of these guidelines affects the material selection or system piping class, consideration should
be given to using a reduced design margin, subject to approval by Company, to ensure that the most appropriate
minimum design temperature is specified.
A low temperature shutdown function may be used to limit the minimum operating temperature of a system. In
such cases, a margin of at least 5°C (9°F) shall be provided between the TALL set point and the minimum
design temperature to allow time for the shutdown system to initiate.
Design temperature for piping shall be maximum continuous operating temperature as defined by process
requirements.
For equipment operating at ambient conditions, the upper design temperature shall be at least equal to a
o
maximum black bulb temperature of 150 F unless the equipment is insulated or other mitigating action is taken.
The design temperature for flowlines shall be the maximum of maximum flowing tubing head temperature plus
14 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
o
25 F or the maximum reservoir temperature. For unfired pressure vessel, when operating temperatures above -
o o
20 F, design temperature shall be the maximum operating temperature plus 25 F. For operating temperatures
o
lower than -20 F, the design temperature shall be the lowest operating temperature. Consideration shall be
given to Joule-Thompson cooling during depressurization.
For Heat exchanger or coolers, consideration should be given to designing downstream equipment for the
upstream design condition. Reliance on devices such as temperature trips to protect downstream equipment in
the event of cooling failure may introduce risk, as the instrument response time may not be sufficiently rapid to
offer adequate protection. This shall be reviewed on a case by case basis. For the shell and tube heat
exchanger type, the following criteria shall be considered:
Cold Fluid On The Shell Side
Design temperature will be equal to the lowest of the maximum operating inlet temperature on the hot
side (excluding process upsets) or the temperature at which the cold fluid has a vapor pressure equal to
the relief valve set pressure.
Cold Fluid On The Tube Side
Design temperature will be equal to the design temperature of the shell side.
The design temperature of the hot side of the heat exchanger will be equal to the greater of the maximum
temperature of the hot fluid (including upset conditions or the normal inlet operating temperature plus 25 °F.
Generally, for the extreme fluid conditions such as hot vaporized fluid, the hot fluid should be placed in the tube
side. For exchanger in series, the design temperature of the second unit will be established taking into
consideration failure of utility on the first unit i.e. the second unit design temperature will be based on the
maximum inlet temperature of the first unit. Detail design of the heat exchanger and cooler should be verified by
o
vendor. For storage tank, when operating temperatures above -20 F, design temperature shall be the maximum
o o
operating temperature plus 25 F. For operating temperatures lower than -20 F, the design temperature shall be
o
the lowest operating temperature. For Pump, when operating temperatures above -20 F, design temperature
o o
shall be the maximum operating temperature plus 25 F. For operating temperatures lower than -20 F, the
design temperature shall be the lowest operating temperature.
4.5 EQUIPMENT SIZING
4.5.1 Separator
4.5.1.1 Separator Sizing Criteria
Separator sizing (both for horizontal and vertical) should be in accordance with spec API 12 J.
Gas capacities of separators shall be determined by a modification of Stokes’ Law, where the capacity is based
on the principle of the minimum droplet size that will settle out of a moving gas stream at a given velocity.
The first step is to determine the drum size required for liquid entrainment separation. Liquid particles separate:
a) When the residence time of the vapor or gas is equal to or greater than the time required to travel the
available liquid droplet.
b) Vertical height at the dropout velocity of the liquid particles, and when the gas velocity is sufficiently low
to permit the liquid dropout to fall. This vertical height is usually taken as the distance from the maximum
liquid level. The vertical velocity of the vapor or gas should be low enough to prevent large slugs of liquid
from entering the flare.
The dropout velocity, expressed in m/s (ft/s), of a particle in a stream is calculated using Equation:
l v
Vc √( )
v
15 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Where:
Vc = Critical entrainment velocity, ft/s
3
l
= Density of the liquid at operating conditions, lb/ft
3
v
= Density of the vapor at operating conditions, lb/ft
The K factors should be reduced by the following factors as a function of operating pressure or service;
Table 4-4 De-rating Factor to K-value for Pressure [Ref. 11]
Adjustment of K Factor for Pressure - % of
Value
design value
Atmospheric 100%
A check will also be made on the minimum droplet size removed in the primary bulk separation section of the
separators to determine whether it is suitable for the vessel service, typically this will be for a 150 micron droplet
without demister installed and 500 micron with demister installed.
For flare/vent knock out drum shall be sized as separator (without mist extractor) which conform to API 521
guidelines. The terminal velocity equation is defined as follows:
√4 g p ( l g
)
Vt
( g
C)
Where:
Vt = Terminal/critical entrainment velocity, m/sec
2
g = Gravitational force, ft/sec
Dp = Droplet diameter, ft
3
ℓ = Liquid density, ft/ft
16 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
3
g = Gas density, lb/ft
C’ = Drag coefficient
This basic equation is widely accepted for all forms of entrainment separation
0. 10 ( )
C( e)2 2
v l v
Where:
= Viscosity of the gas, centipoise;
D = Particle diameter, ft;
l
= Density of the liquid at operating conditions, lb/ft3
v
= Density of the vapor at operating conditions, lb/ft3For air receiver shall be designed to provide 5-10
minutes hold up volume from normal operating pressure of 105-120 psig to low pressure alarm of 60 psig based
on normal demand.
4.5.1.2 Vessel Liquid Levels and Residence Times
2 – Phase Separator
The following liquid level and residence times shall be used for 2 phase separator design:
Table 4-5 Phase Separator Liquid Levels & Residence Time Criteria
HLL to NLL 2 minutes (min 6”) + slug allowance 2 minutes (min 6”) + slug allowance
Note:
1. NLL to be determined case by case but not more than 80% of diameter vessel for Horizontal Vessel.
2. LLLL to BOV/BTL shall also consider closure time of liquid outlet SDV and potential for blowby.
3. The gas compartment of the vessel above HHLL shall be sufficiently large to allow for proper gas / liquid separation.
3 – Phase Separator
Three phase separators are sized in a similar way to two phase separators but, to allow for separation of the two
liquids, residence times are set for both liquid phases. Preliminary sizing of 3 phase separators will be as follows:
Between BOV and NIL (water volume) 5 minutes (minimum)
Between NIL and NLL (oil volume) 5 minutes (minimum)
If the water volumetric flow rate is small and does not warrant the use of a separate baffled settling
compartment, a water boot may be used instead.
4.5.1.3 Vessel Nozzle Sizing Criteria
Nozzle sizing for both vertical and horizontal separators shall be according to the following criteria:
2
a) lnlet and outlet process nozzles should be sized to meet the momentum v limitations outlined in
b) Table 4-6 .
17 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Table 4-6 The Momentum Criterion for Typical Separator Inlet Device
2 2
Nozzle Devices ρv (kg/m-s )
(Note 1)
No inlet device 1000
(Note 1)
Inlet Half Open Pipe 1500
(Note 1)
Schoepentoeter or equivalent 6000
Notes:
1. Criteria are based on v2 when is the fluid density and v is the fluid velocity. The inlet criteria use a mixed gas –
liquid density and superficial velocity.
2. If no upstream straight length is specified, then an inlet Schoepentoeter or equivalent inlet distributor shall be used.
3. Where the liquid outlet supplies a pump or other device requiring low pressure drop, the velocity criteria shall be
reduced to 1m/s.
V > 420 6 4
Vessel cleaning nozzles shall be two each of 2” NB connections. Steam-out connections will be 2” NB. For large
vessels (columns) with diameters greater or equal to 4.6 meter, two each 2” NB steam-out connections will be
provided.
Notes:
1. Purge connections, when specifically required, may not necessarily be located on vessels.
2. Utility connections should be distinct and independent from drains.
3. Vessels of 6 meter or longer (tangent to tangent length) will be provided with at least two man-ways or more
depending upon the vessel internal arrangement. On a case by case basis, additional requirements for manways on
vessels will be specified for operations and maintenance requirements.
18 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
19 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
4.5.2 Pumps
A 10% margin shall be applied in setting the design flow rate (defined as rated flow) for a pump in general
service. No margin shall be added to the differential head.
The procedure for pump calculations shall be:
a) Calculate the rated flow as the design flow rate plus the appropriate margin
b) Determine the size of the pump discharge piping based on pump rated flow rate. The line pressure drop
should be calculated and the 20% design margin added to the pressure drop/100 m to confirm the line
size is acceptable
c) Calculate the pump differential head based on the line size determined above. Calculate pressure drop
excluding the 20% design margin, at the pump rated flow
d) Calculate the NPSHa at rated flow. Design margin of 1 (one) m between NPSHa and NPSHR should be
provided.
Minimum flow provisions shall be made where flow conditions necessitate turndown to less than 30% of the
rated flow. For centrifugal pumps this shall consist of a line from the discharge to the suction source. Minimum
flow requirements shall be based on the pump vendor’s recommendations. However, in the absence of this data
30% of normal flow shall be used for bypass line sizing. Pumps shall be provided with individual minimum flow
recycle lines back to the suction source.
Overplus is a correction factor for difference between calculated or estimated pressure drop and actual site
operating condition. No overplus shall be applied for the following pump systems:
Control valve system
20 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
4.5.4 Compressor
4.5.4.1 Centrifugal Compressor
Rated Capacity
The rated capacity (called as design capacity) shall be 110% of normal flowrate at normal inlet conditions.
Rated Head
The rated head shall be calculated at the rated flow with the minimum normal operating suction pressure and the
maximum normal operating discharge pressure.
Design Pressure
The Maximum Design Pressure on the discharge of a centrifugal compressor is determined from the surge and
also from the setting conditions. The compressor design pressure will normally be determined by vendor and the
design of compressor internals.
The design temperature of the compressor will also be determined by vendor based on the operating condition
and properties of the gas being handled.
4.5.4.2 Reciprocating compressors
Rated Capacity
The rated capacity (called as design capacity) shall be 110% of normal flowrate at normal inlet conditions.
For Air Compressor and Dryer shall be designed with 20% margin above the maximum instrument air and utility
air demand.
Rated Head
The rated head shall be calculated at the rated flow with the minimum normal operating suction pressure and the
maximum normal operating discharge pressure.
Design Pressure
The compressor design pressure will normally be determined by vendor based on the operating conditions and
the design of compressor internals.
A pressure relief valve is required in the discharge of a reciprocating compressor. The MDP of the discharge
side is governed by the relief valve set pressure which will be determined by the following table.
Table 4-8 Minimum Relief Valve Set Pressure Margin
Design Temperature
The design temperature of the compressor will also be determined by vendor based on the operating condition
and properties of the gas being handled.
21 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
22 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Description Value
Vessel Top to HHLL 10% of sphere volume to allow for thermal expansion
Notes:
1. LLLL to Vessel Bottom shall also consider closure time of liquid outlet SDV and potential for blowby or pump damage.
23 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
At the minimum process flow rate the valve Cv should be greater than 10 % of the maximum valve Cv
subject to vendor minimum flow requirements.
4.5.10.3 Compressor Recycle Control Valves
Compressor recycle control valves will be sized by the compressor vendor.
4.6 LINE SIZING CRITERIA
4.6.1 General
Line sizing will generally be based on velocity and/or pressure drop per length. No margin will be applied to flow
rates for the purposes of line sizing.
A 20% margin is added to the calculated pressure drop before comparison with the guideline dP/100 m to
determine that the calculated line size is acceptable. Where the addition of the 20% increases the line size by an
increment, engineering judgement will be applied to determine if the line size increase is in fact warranted based
on system hydraulics and fluid velocities.
Process line sizing criteria shall be accordance to API RP 14E. For firewater distribution piping system, sizing
shall follow applicable NFPA guidelines (NFPA 15, 20).
4.6.2 Piping Sizes
A minimum line size of NB 50mm shall be used for all main process and utility piping, except for instrument
connections where 25mm NB lines are acceptable.
24 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Minimum connection sizes on piping shall be 50 mm for both hazardous and non-hazardous service.
Non-standard pipes sizes shall not be used except where equipment connections and drilling piping systems
require these sizes. Transition to standard commercial pipe sizes shall be made as close to the equipment as
practical.
The minimum nozzle size allowed on vessels and heat exchangers will be 50 mm NB.
4.6.3 Liquid Line Sizing
The liquid line sizing shall refer to API RP 14E.
Single phase liquid lines should be sized primarily based on flow velocity. As a preliminary rule:
Minimum velocity : 3 ft/s, to minimize deposition of sand and other solids
Maximum velocity : 15 ft/s, to minimize flashing ahead of control valve.
The limitations for Velocity and Pressure Drop calculation are shown in the Table 4-12.
Table 4-12 Recommended Velocity and Maximum P for Carbon Steel Liquid Lines
HYDROCARBONS
General Recommendation
3
Liquid Density, lb/ft
100 5.0
50 4.0
20 1.3
Pump Suction Centrifugal 0.2 – 1.1
WATER LINES
25 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Table 4-13 Allowable Pressure Drops and Velocities in Piping for Centrifugal Pumps
Allowable P psi/100ft
Pipe NB
Pump Suction
inch Pump Discharge
Boiling Liquid Sub-cooled Liquid
<4” 0.05-0.20 0.20-0.60 1.0-1.6
4” 0.05-0.20 0.20-0.60 1.0-1.6
6” 0.05-0.30 0.20-0.60 1.0-1.6
” 0.10-0.30 0.50-1.00 1.6-2.0
> ” 0.10-0.30 0.50-1.00 1.6-2.0
Table 4-13 . The positive head available over the fluid vapor pressure at the meter inlet shall be in
excess of the meter pressure drop.
Where pressure drop is critical the line should be sized such that the actual pipe frictional pressure drop
does not exceed 50% of the available pressure drop.
4.6.3.2 Gravity Flow
Line flowing by gravity includes tank overflows, drains (closed and open drains), and other lines where the liquid
flows due to gravity forced instead of pressure difference. Generally, for fixed installations, a minimum downward
slope of 1:100 shall be used. However, with mud and/or sand, the slope shall be at least 1:50.
Pipes that are running full, and do not require a minimum downward slope to avoid particle deposition, shall be
sized according to the total available static pressure head, and the maximum allowable velocities for liquid lines.
Near horizontal pipes not running full shall be sized based on the maximum flows as given in the following table.
Table 4-14 Flow Capacity-Near Horizontal Pipes
26 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Vertical gravity lines (such as produced water discharge) shall be designed to avoid the formation of siphons,
and to avoid pulsation and vibration. One of the following methods can be adopted dependent on the individual
engineering circumstances:
Install a siphon breaker at the system high point.
Size the line for all expected flow rates such that frictional forces offset gravitational forces thus avoiding
sub-atmospheric pressures at the top of the pipe.
Install a back-pressure control near the base of the line.
However, a minimum size of NB 100mm shall be used for headers and NB 75mm for sub-headers. Refer to
Section 4.6.3.2 regarding on the design of gravity flow lines.
4.6.4 Gas Line Sizing
The gas line sizing shall refer to API RP 14E.
Single phase gas lines should be sized primarily based on flow velocity. As a preliminary rule, there may be a
noise problem if the flow velocity exceeds 60 ft/s. Nevertheless, higher velocities are acceptable when the
predicted noise is less than 85 dBA measures 1 m distance from the line. This is also applicable for instrument-
air line sizing.
The design of any piping system where corrosion inhibitor is anticipated should consider increasing the wall
thickness of the piping in the design and/or a reduction in velocity (larger pipe size) to reduce the effect of
stripping inhibitor film from the pipe wall.
Reciprocating and centrifugal compressor piping should be sized to minimize pulsation, vibration and noise.
Table 4-16 Recommended P for Carbon Steel Gas Lines
1. General Recommendation
P > 500 2
200 ≤ P ≤ 00 1.5
0 ≤ P ≤ 1 0 0.3
27 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Sub-atmospheric 0.1
C
Ve
m
Where:
Ve : Erosional velocity (ft/s)
C : Constant (empirical)
3
m : Gas/liquid mixture density at flowing pressure and temperature (lbs/ft )
The empirical constants (C values) are shown in the Table 4-17.
Table 4-17 Empirical Constant (C values)
The design of any piping where solids are anticipated should consider the installation of sand probes, cushion
flow tees, and a minimum of three feet (3 ft) of straight piping downstream of choke outlets.
The minimum velocity in two-phase lines should be about 10 ft/s to minimize slugging of separation equipment.
4.6.6 Relief and Depressuring Lines
Vapor flow in relief and depressuring lines is treated as adiabatic compressible flow. The size of flare headers,
sub-headers and individual relief valves may be estimated by the method of Lapple (refer API RP521) or by
more rigorous proven computer methods. For preliminary engineering, the guidelines given below should be
followed.
28 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
A detailed network analysis will be undertaken in detailed engineering for all controlling relieving/depressuring
cases in order to ensure that the maximum allowable back pressure at each individual relieving device is not
exceeded.
Calculations will be performed in accordance with API RP520/521 or by use of recognized software e.g.
FLARENET/HYSYS.
4.6.6.1 Relief Valve Inlet Lines
The inlet line pressure drop is to be less than 3% of set pressure calculated at rated flow based on installed relief
valve area and relieving conditions. The inlet line shall not be smaller than the inlet flange of the relief valve.
Block valves must be full bore.
4.6.6.2 Relief Valve Outlet Lines
The discharge line shall not be smaller than the outlet flange of the relief valve. Block valves must be full bore.
The PSV discharge laterals shall be sized based on rated valve capacity and the main relief headers shall be
based on total required capacity.
Conventional Valves: The discharge line from conventional valves should be sized to limit backpressure
at the relief valve outlet to less than 10% of the set pressure (gauge).
Balanced Valves: In the case of balanced valves, higher relief valve backpressures are allowed. These
may be used to achieve considerable cost savings. Balanced relief valve outlet lines should be sized to
limit backpressure to 30% of the set pressure (gauge) and to no more than the rating of the internal
bellows. N.B. Always refer to API 526 for maximum allowable bellows rating for a particular valve, prior
to specifying a balanced bellows relief valve.
Pilot operated valves: Pilot operated relief valve outlet lines should be sized to limit backpressure to 50%
of the set pressure (gauge).
Where there are a number of valves discharging into the same manifold, caution should be exercised to ensure
that the backpressure in the manifold allows all relief valves to discharge properly. The recommended maximum
Mach number range is 0.5 – 0.75 calculated at rated flow rate and at the downstream (end of header) conditions.
4.6.6.3 Flare Headers and Sub-Headers
The maximum Mach number is 0.75, calculated at the downstream (end of header) conditions. For main flare
headers, Mach number shall be based on total required flow. For sub-headers, Mach number shall be based on
rated flow if the sub-header is similar in size to the PSV tailpipe. Required relief flow should be used for sub-
headers, which are larger than the tailpipes and are comparable in size to the main flare header.
4.6.6.4 Blowdown Lines
The maximum velocity in blowdown inlet lines should be limited to 60 m/s. The recommended maximum Mach
number for blowdown outlet lines is 0.75 calculated at downstream junction with relief header.
4.6.7 Insulation and Tracing
Insulation shall be considered for heat conservation (hot and cold). Personnel protection insulation shall be
o
considered if equipment or piping operating-temperature is above 158 F.
29 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Protection of assets
Generally, the plant will be designed for safe containment of hazardous materials by guarding against
overpressure incidents using an appropriate combination of the following five main protection measures:
Specification of design pressure higher than the potential source pressure
Pressure control and alarms
30 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
these causes is sufficient to make their classification unrelated. The simultaneous occurrence of two or more
unrelated causes of overpressure (also known as double or multiple jeopardy) is not a basis for design”. This
philosophy is used in establishing the relief scenarios. The relief valve shall be sized for the maximum case.
The relevant relief conditions shall be determined for each relief valve and stated in the relief device summary
table. Relief conditions should be documented for all applicable relief scenarios and the calculations referenced.
All possible causes of over-pressure are to be considered. The following scenarios are typical sources of
overpressure for pressure relief:
Blocked Outlet / Closed Outlet
Thermal Expansion
Power Failure/Voltage Dip
Reflux Failure
31 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
The relief capacity shall be based upon API RP 521. The pressures on the high and low pressure side of the
exchanger shall be taken as the maximum operating and the maximum (accumulated) relieving pressure,
respectively.
5.2.2.3 Utility Failure
Partial failures shall be considered as well as total failures.
5.2.2.4 Instrument Air Failure
All pneumatic control valves are assumed to follow their failure mode specification. Should a control valve fail in
its last position, then the position causing the greatest relief load must be assumed (also refer to Section 5.2.2.7
below).
5.2.2.5 Fire Case
Generally, the hydrocarbon processing facilities will be segregated by sufficient distance to prevent escalation. It
is assumed that during a fire there is no feed to or product from an affected system, and all normal heat inputs
have ceased.
In calculating the heat input to the internally wetted surface of vessels, all interconnected equipment and piping
exposed to the fire will be considered, up to a height of 7.5 m above the level at which the fire is located. Wetted
surface will be based on the maximum feasible liquid level in the vessel plus the normal hold-up of internals. No
credit will be taken for the reduction in wetted area due to liquid boil-off.
No credit will be taken for thermal insulation on vessels. An environment factor, F=1.0, will be used for
determining heat input to vessels. Credit will be taken for passive fire protective insulation (PFP) installed on
vessels. An environmental factor, F = 0.3, will be used where passive fire protection is installed.
In some instances, the calculated value of relieving temperature will exceed 1100°F. In this instance this
indicates that there is a high probability that the vessel may fail before the relief valve will open. This is likely to
occur when the operating pressure is significantly lower than the design pressure. In this case, the following
alternatives will be considered:
Reduce the set pressure of the relief at a value below the design pressure of the vessel. This method
must be used with caution since any reduction may cause the relief valve to be sized in accordance with
different scenario (eg. blocked discharge). Furthermore, possible future lower pressure cases need to
be evaluated.
Provide a nominal (smallest) size relief valve and set at the design pressure.
The process simulation package HYSYS will be used to determine the required relief rate for the fire scenario.
Fire case relief loads will be calculated for pool fire as well as for jet fire case where applicable.
Fire Type
Pool Fire
Systems with significant liquid hydrocarbon inventory will be considered for pool fire case. Heat flux and
required relief rate will be estimated using HYSYS. Credit for a 40% reduction in heat flux may be taken
for good drainage and the presence of prompt firefighting efforts as specified in API RP 521.
Jet Fire
Where potential for jet fire exists, relief load will be calculated for higher heat flux from heat fire. The heat
flux generated by jet fire ranges from 50 kW/m² to 300 kW/m². However, the net heat flux into the fluid
will depend on many factors such as fuel type, vessel temperature, the surface emissivity, the fire
environment, the radiative and convective components of the fire.
rd
Typically, the absorbed flux will be of the order of about 2/3 of the incident flux. A heat flux of 200 kW/m² shall
be used for relief load estimates.
32 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Liquid Content
Heat transfer rates are highest to the liquid phase in a vessel. For liquid-containing vessels the heat transfer
area is the wetted area in contact with the liquid. Heat Transfer to the vapour is not considered, since the heat
transfer coefficient to the liquid is much higher than that to the gas.
It should be noted that this approach generally applies to all liquid/vapour separators, even if these normally
operate “empty”. When a simulation shows no liquid in such a vessel, and the vessel is being supplied for a
particular purpose e.g., a compressor suction scrubber, then the required level of liquid will be provided by using
the liquid from the appropriate upstream vessel.
For gas filled vessels the heat transfer area is the total vessel internal surface area. For gas filled vessels, the
heat transfer from the vessel wall to the bulk fluid is shown to be very low. Typically a heat flux of only about
1000 BTU/hr.ft² (3 kW/m²) is transferred into the gas. However the heat transfer and required relief rate will be
estimated using HYSYS.
Methodology
There are three methods, depending on the state of the fluid at the relieving pressure:
a) Fluid is sub-critical: P<0.9*Pc
b) Fluid is near its critical pressure: 0.9Pc < P < 1.1*Pc
c) Fluid is super critical (dense phase): P > 1.1*Pc
Where, Pc = critical pressure, P = relieving pressure
For cases b) and c), approval from the Lead Process Engineer must be obtained prior to proceeding with either
method.
Sub-Critical Fluid (Boiling Liquid)
a) Jet fire
Heat flux = 200 kW/m²
F (PFP environmental factor) = 0.3
F (no PFP environmental factor) = 1.0
Required relieving rate from HYSYS simulation.
Wetted area = total wetted area in vessel, excluding bottom head in vertical vessels if protected by
skirt.
b) Pool Fire
Refer to API RP 521 to estimate heat absorption (Q) to the wetted surface.
Required relieving rate from HYSYS simulation.
Near-Critical Fluid
a) Jet Fire
Heat flux = 200 kW/m²
Required relieving rate (kg/s) = 200 x F x (wetted area) / 117
F (PFP environmental factor) = 0.3
F (no PFP environmental factor) = 1.0
Latent heat of evaporation = 50 Btu/lb = 117 kJ/kg
Wetted area = total wetted area in vessel, excluding bottom head in vertical vessels if protected by
skirt.
b) Pool Fire
Refer to API RP 521 to estimate heat absorption (Q) to the wetted surface. Latent heat of
evaporation = 50 Btu/lb, as for jet fire above.
Required relieving rate = Q/(latent heat).
33 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Is the piping or equipment continuously in operation and thus unlikely to be isolated without being
depressurised and drained? Most process equipment and piping is in this category.
Is the liquid non-toxic and non-corrosive and does it have an initial boiling point higher than the
maximum ambient temperature?
Is there a weak point in the system such as a flange where expansion could relieve pressure without
unacceptable consequences?
Is it unlikely that the system will be totally liquid-full?
Has the release a safety or environmental impact?
As a general guide, TERVs are not needed for:
Process plant piping
Lines in which there is normally two-phase flow
Systems which are not totally liquid filled.
TERVs are normally fitted to:
The cold side of heat exchangers which can be blocked in
Sections of piping containing more than 500 litres of LPG or toxic liquids which could be blocked in.
Piping in storage areas or transport lines which will be regularly blocked in during normal operation, to
protect against pressure rise due to solar heating or heat tracing.
In all cases, operating procedures should be developed such that overpressure due to thermal expansion cannot
occur, even when a relief valve is fitted. This can be done by prescribing drainage of a small quantity after a
pipe section has been blocked in.
5.2.2.7 Failure of Automatic Controls
Inlet Control Devices
This situation arises from the failure or inadvertent opening of a control or block valve segregating a high
pressure system to a low pressure system. Typical examples of this is the fuel gas pressure letdown systems.
Refer to Section 0 below.
34 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
35 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
36 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
It should be noted that British pressure vessel code PD (BS) 5500 specifies a maximum allowable overpressure
of 10% even for fire case. All local design codes should be checked.
5.3.1.5 Thermal Relief Valves
Thermal relief valves are to be set to 100% of the system design pressure for vessels or heat transfer
equipment, but shall not exceed 110% for piping runs (see Section 5.2.2.6 for equipment and piping thermal
relief requirements).
5.3.2 Relief Valve Inlet and Discharge Piping Sizing
5.3.2.1 Inlet Piping
The inlet piping is defined as that between the entrance to the vessel nozzle and the face of the inlet flange of
the pressure relief valve. The pressure drop in the inlet piping should be minimized and the line should not be
pocketed. The pressure drop between the protected equipment and the inlet to a relief valve shall not exceed 3%
of the set pressure of the device, to minimize chattering of the valve. The 3% specification may be relaxed for
remote pilot operated relief valves however the PSV capacity may be reduced significantly [Ref 5].
Pilot operated PSV’s with remote sensing may be used where there is excessive inlet pressure loss that could
not be avoided in the design, or where the margin between operating and design pressure is small (e.g. LPG
sphere PSVs). Pilot operated PSV’s shall only be used for processes with clean service
The effect of any component along the inlet piping should be considered in terms of potential reduction of relief
capacity. The inlet piping and any fittings should have a bore area at least equal to the PSV inlet flange. All
block valves must be full bore. The PSV should be situated as close to the source of pressure as possible.
The inlet system should be self-draining to source. The inlet piping should be sized using the rated relief rate,
where;
( )
Piping for a regulating type PSV shall be sized using required relief rate.
37 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
If the inlet line losses are excessive and a pilot PSV has been selected, then the capacity of the relief valves
needs to be checked at the reduced inlet pressure. An example is a vessel with a design pressure of 15 barg but
with inlet lines losses of 1 bar (7%). Consequently, to prevent more than 10% accumulation the PSV must be
sized based on a relieving pressure of 15 – 1 = 14 barg.
Note that both inlet piping pressure loss and valve back-pressure is to be calculated using the valve rated flow.
An exception to this will be back-pressure calculations for multiple relief valve lifting scenarios such as fire or
utility failure.
This factor can be neglected for inlet line losses less than 3%.
5.3.2.2 Discharge Piping
The main design criteria for the discharge piping and the relief manifolds is that the back pressure must not
reduce the relieving capacity of the PSV below the amount required to protect the corresponding equipment from
overpressure. In addition, the back pressure during relief should be calculated to ensure that it remains below
piping design pressure.
The discharge line must not be smaller than the outlet flange of the relief valve and sized according to the type of
relief valve in service. All block valves must be full bore.
The piping should be designed with as few restrictions as possible, should not be pocketed and should be
sloped to drain to the flare KO drum.
The rated flow rate in the discharge piping should not exceed 0.75 Mach. Each tailpipe should be sized using the
rated relief flow whereas the headers are sized based on the required relief flow. A back pressure of 3 bara shall
be assumed for preliminary estimates.
5.3.3 PSV Selection Type
The selection of relief valves is based on backpressure, inlet pressure drop, dirty/clean service considerations,
space/size, weight considerations, and seat tightness.
5.3.3.1 Backpressure
Maximum allowable back pressures for different relief valve types are [Ref 5]:
38 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Dry gas
Clean Downstream of cold process
PCHE’s, e-buthanizer, LPG splitter
39 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
The inlet line must not be smaller than the PSV inlet flange, the discharge line must not be smaller than the PSV
outlet flange and inlet/outlet block valves must be full bore, preferably ball valves.
Upstream Isolation
A single upstream block valve will be provided for spared relief valves up to 300# pipe rating. For 600# pipe
rating and above, double block valves shall be used. Maintenance will be performed with single isolation if the
single isolation is proven to seal by the local bleed.
Upstream / Downstream Bleed Connection
A bleed connection will be provided on the upstream side of the relief valves if an isolation valve is provided.
This bleed connection will be used to check the integrity of the upstream isolation valve during maintenance on
the relief valve.
A bleed connection will not be provided on the downstream side of the relief valves. However, a downstream
bleed shall be provided on the flare connections/header to positively confirmed isolation.
Downstream Isolation for Future PSV Installation
An isolation valve with blind flange will be installed on the discharge side for a future PSV installation. This is to
avoid a platform shutdown during installation of the future relief valve. Suitable flanges and piping space for
future installation will be provided.
5.4 Rupture Disc Sizing
The maximum operating pressure should be significantly lower than the design pressure of the vessel and the
rupture disc burst pressure, to prevent premature failure of the rupture disc due to fatigue or creep. A rupture
disc is a pressure differential device, the pressure on both sides of the device should be considered during
design. The disc is also sensitive to temperatures and the normal operating and relief temperature coincident
with the relief pressure must be specified to the manufacturer in the design.
Table 5-3 MAOP for Bursting Disc
Scored Tension Loaded Operating conditions 85% less than burst pressure
The sizing of a rupture device used alone is based on the equations applicable for pressure relief valves for the
particular fluid type. For all liquids an effective coefficient of discharge Kd = 0.62 is used as described in ASME
VIII Divisions 1 and Division 2. For two phase flow use the method described in API 520, to calculate the
required area. The rupture device selected should be the nominal pipe size whose area is equal to or greater
than the required discharge area calculated by the appropriate equation.
For two rupture discs in series a pressure indicator between them will indicate leakage of either disc. The
pressure indicator will detect an increase in back pressure, which would lead to an increase in rupture pressure.
40 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
6 BLOWDOWN PHILOSOPHIES
6.1 General
Blowdown is only required as a safety response, primarily to a fire. The purpose of blowdown is to reduce the
pressure of high pressure process equipment/system by reducing/removing the hydrocarbon inventory in the
equipment/system.
In the event of fire, it will rapidly reduce the pressure by removing the blocked-in pressurized hydrocarbon
inventory. This protects pressure vessels and flowlines from rupture under external fire conditions and to reduce
hydrocarbon inventory and the potential for escalation in a fire.
The Blowdown system is initiated manually with EDP push button by operator intervention, to release the
hydrocarbon gas containment during fire or emergency condition. In the event of a confirmed fire that may
impinge on pressurized hydrocarbon systems the facility will immediately be shutdown but NOT automatically
depressurized. If the simultaneous blowdown rate of the entire facilities proves to be excessive, sequential
blowdown may be considered, in conjunction with QRA studies.
Emergency depressurization facilities will be designed to achieve following pressure levels from initial conditions
to a level equivalent to 50 % of the vessel's design pressure within approximately 15 minutes at carbon steel
vessel with a wall thickness of approximately 1 inch to reduction of the vessel stress during pool fire exposure.
For vessels other than 1 inch carbon steel, the following depressurization criteria shall be applied:
Vessels with wall thickness more than 60 mm to be depressurized to 50% of design pressure.
Vessels with Passive Fire Protection to be depressurized to 50% of design pressure.
Other vessels to be depressurized to 6.9 barg (100 psig)
Depressurization for some process system, such as for the compressor system, shall consider the requirement
of the package design whichever the more stringent. Decision shall be evaluated case by case.
It should be noted that depressurization will not stop after 15 minutes and that the pressure will continue to
decline. This approach will ensure protection against rupture while reducing the initial peak blowdown load to a
manageable level. Vendor equipment, e.g. compressors, will be depressurized at a rate no greater than that
permitted by the equipment supplier. This will be examined in detail with the selected vendor when more precise
details and procedures are known It should be noted that blowdown does not stop after 15 minutes. The
pressure will be allowed to continue to decline to minimize the probability and consequences of rupture.
6.2 Depressurization Calculation
The total blowdown load on the flare system shall be based on a credible combination of individual blowdown
rates. Typically, this would assume only one area exposed to fire as the plant layout will be designed to minimize
escalation between areas. The extent of individual fire areas will be agreed with the safety discipline.
6.2.1 System Volume
Vessel and piping volumes for both the liquid and gases for each sectionalized area based upon the appropriate
liquid level as below:
Storage vessels are assumed to contain their maximum working volume.
Process vessels are assumed to contain their normal working volume.
Columns (packed and tray) are assumed to contain a liquid volume corresponding to the height from the
bottom to the highest level controller connection and the liquid on the trays which can be calculated on
the basis of normal pressure drop over the columns.
Based upon this information the engineer will calculate the required blowdown orifice size and rate. For each
system the following information is required;
The actual volume of hydrocarbon vapour within the isolatable section
41 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Blowdown time Dependent on vessel wall Based on the blowdown Based on the blowdown
(Notes 5, 6)
or 15 minutes. orifice area from the fire orifice area from the fire case
case and estimated by and estimated by manual
manual iteration. iteration.
Vessel Volume Total volume of vessel plus Total volume of vessel plus Total volume of vessel plus
the sum of detail piping the sum of detail piping the sum of detail piping
volume estimation or the volume estimation or the volume estimation or the
assumed of 20% design assumed of 20% design assumed of 20% design
42 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
margin when the piping margin when the piping margin when the piping
calculation is not available to calculation is not available calculation is not available to
account for isolated piping to account for isolated account for isolated piping
volume between S V’s piping volume between volume between S V’s
S V’s
(Note
Liquid volume Based on NLL set-point or Based on LALL set-point Based on LALL set-point
(Note 2,4) 2,4)
HLL if LCVs are on-off type. . .
Wetted Area Based on NLL set-point. Entire vessel surface area Wetted area below LALL set
(for adiabatic case where point with normally no margin
gas filled only) or Wetted to account for piping. Wetted
area below LALL set point piping may be included on a
with normally no margin to case-by-case basis
account for piping (for
adiabatic case where
gas/liquid filled)
(Note 3) (Note 3)
Isentropic efficiency - 100 % 100 %
Vessel Heat Transfer C1: 21,000 Btu/hr-ft2 Heat transfer constant: Heat transfer constant:
Coefficient depressuring module depressuring module
C2: 0.82
calculated calculated
C3: bare vessel F=1
Fire Blanket F=0.3
(Environment factor)
Blowdown Orifice size Estimation by HYSYS to Orifice area calculated by Orifice area calculated by the
achieve the final pressure in the fire case fire case
required time
Notes:
43 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Settle out conditions vary. Worst case settle out conditions shall be considered when determining vessel design
pressures. However coincident worst case settle-out conditions and a jet fire shall not be considered if they are unrelated
events, e.g. worst case settle-out requires the failure of a suction control valve.Minimum Temperature at
Blowdown
The minimum temperature for the blowdown scenario needs to be determined to specify the metallurgy of the
system. The minimum design temperature is determined by the lowest of the following criteria:
20°F below the minimum operating temperature.
Minimum ambient temperature.
The minimum temperature resulting from depressurization after vessel shell and remaining liquid
contents have reached thermal equilibrium.
The minimum temperature resulting from adiabatic or isothermal depressurization in applying the fire
case orifice size to achieve the normal ambient pressure within reasonable depressurization duration.
The minimum temperature resulting from depressurization is determined from the following criteria:
For vessels which are blown down from a vapour filled starting condition the minimum temperature of
the vessel will be taken as the temperature predicted by HYSYS for the vessel wall with a 20°F margin
applied or the temperature of the gas without a margin, whichever is lower.
For vessels, which contain liquid, which boils throughout the blowdown and is present at the end of the
blowdown, the vessel minimum wall temperature is to be set to the minimum fluid temperature without a
margin being applied.
Depressurizing lines are to be assumed to reach the fluid temperature as predicted by HYSYS, due to the
relatively high heat transfer co-efficient obtained compared to inside the vessel itself. Where this requires exotic
material to be employed a more detailed heat transfer analysis may be warranted to determine the acceptability
of carbon steel.
For hydrocarbon containing vessels where the predicted temperature is lower than the specified design
temperature, then preference is to reduce the design temperature. However, if this has a significant impact, eg
leads to exotic materials, then lower temperatures may be acceptable if they occur at pressures significantly less
than design pressure. This shall be approved by the COMPANY and should be checked by Mechanical on a
case-by-case basis. If this approach is adopted, then the P&ID and operating procedures shall clearly note that
the vessel or system shall not be re-pressurised whilst cold.
6.3 Inlet Piping
The inlet piping should not be pocketed and the velocity should not exceed 60 m/s at the rated blowdown
capacity. Refer to section 4.6.6.4 for additional line sizing criteria.
6.4 Discharge Piping
The recommended maximum Mach no is 0.75 calculated for the rated blowdown capacity at the downstream
junction with the flare header. Refer to section 4.6.6.4 for additional line sizing criteria.
6.5 Blowdown Station
The process systems are segregated by ESD valves on shutdown. Any other isolation will be considered as the
lowest priority of isolation, to be determined as special case and the application is subject to Company approval.
Each section will be provided with at least one depressurization valve station. Blowdown releases will be
directed to the appropriate flare system header.
A depressurization station will comprise a full bore actuated ball valve with a downstream restriction orifice. The
blowdown valve will be specified as fail open.
The blowdown valve should be located at the high point in the piping with the inlet line falling back to the source
vessel with no pockets and the outlet line falling to the flare header with no pockets. This feature is to eliminate
44 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
the potential for a condensate/water slug to accumulate upstream or downstream of the blowdown valve (e.g. as
a result of condensation) and thereby avoid resultant excessive pipe stresses when the blowdown valve opens.
Maximum amount of liquid – the LAHH set point in the drum shall ensure that total facility blowdown can
be accommodated. The volume occupied by the liquid should be based on a release that lasts 20 to 30
minutes in accordance with API Standard 521.
Allow liquid droplets of 600 mm minimum to separate.
Be the most economical design (vertical or horizontal vessel), dependent on vapour/liquid relief rates.
7.2.3 Flare Header and Sub-header
Flare headers are sized so that the backpressure which may exist or is developed at any point in the system
from each single contingency, will not reduce the relieving capacity of any related pressure relief devices to
below that required to protect the corresponding vessels, piping and equipment from overpressure.
The HP flare header is sized for the largest of:
Any single pressure relief valve release
Platform total blowdown load
The LP flare header is sized to the largest relief flow connected to the LP Flare system.
Vapour flow through the discharge header will be treated as compressible flow.
7.2.4 Flare Purge
Flammable gas or non-condensable inert gas added to the flare header to mitigate air ingress and burnback.
For safety purposes, a pre-commissioning purge and subsequent continuous purge with a non-condensable
oxygen free gas is required through the flare system. The pre-purge displaces any existing air from the stack and
the continuous purge ensures that atmospheric air does not enter the stack through the flare tip during low-flow
conditions.
Once the required quantity of purge gas has been established, the injection rate should be controlled by a fixed
orifice, rotameter or other device that ensures the supply remains constant and is not subject to instrument
malfunction or maladjustment. Consult the vendor to determine purge rates to prevent burning inside the flare
tip.
7.2.5 Flare Radiation and Dispersion
The methodology used for Radiation and Dispersion is shown below.
46 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
The criteria used to assess the flare thermal radiation and gas dispersion are elaborated in sections below.
7.2.5.1 Dispersion Criteria
During ignition system failure (flame off), un-ignited gas release from the facilities will form gas clouds that are
dispersed by the initial momentum of release, turbulence around obstruction and wind. The hydrocarbon gas
cloud envelopes are defined by the Lower Flammability Limit (LFL) and Upper Flammability Limit (UFL). The
Gaussian plume model will be used for dispersion modeling. The model assumes (on the basis of empirical data)
that Gaussian distribution can adequately describe the concentration profiles in both horizontal and vertical
directions. The Gaussian distribution can also be derived as a solution to the equations describing the diffusion
of a tracer under some (restricted) conditions.
47 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Permissible Design
2 2 Conditions
Level kW/m (Btu/h.ft )
Maximum radiant heat intensity at any location where urgent emergency action by personnel
is required. When personnel enter or work in an area with the potential for radiant heat
2 2
intensity greater than 6.31 kW/m (2000 Btu/h.ft ), radiation shielding and/or special
9.46 (3000) protection apparel (e.g. fire approach suit) should be considered.
Safety Precaution – It is important to recognize that personnel with appropriate
(Note 1) 2 2
clothing cannot tolerate thermal radiation at 9.46 kW/m (3000 Btu/h.ft ) for more
than a few seconds.
Maximum radiant heat intensity in areas where emergency actions lasting up to 30 s can be
6.31 (2000) (Note 1)
required by personnel without shielding but with appropriate clothing
Maximum radiant heat intensity in areas where emergency actions lasting 2 min to 3 min can
4.73 (1500) (Note 1)
be required by personnel without shielding but with appropriate clothing
Maximum radiant heat intensity at any location where personnel with appropriate clothing
1.58 (500) (Note 1)
can be continuously exposed.
Note:
1. Appropriate clothing consists of hard hat, long-sleeved shirts with cuffs buttoned, work gloves, long-legged pants and work shoes.
Appropriate clothing minimizes direct skin exposure to thermal radiation
48 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
2 2
In this study, thermal radiation of 4.73 kW/m (1500 BTU/hr.ft ) is utilized as threshold limit (emergency action as
per API 521) for human exposure during emergency.
7.2.6 Flare Network Hydraulic
Flare and relief piping will not have pockets downstream of the relief blowdown devices. When the discharge
header is sized, the relief contingency that gives the greatest back pressure will be identified. Vapor flow in the
discharge header will be treated as compressible flow. Calculations will begin at the system outlet, (i.e. the flare
tip) where the pressure is known, and work back step wise through the system, checking that the backpressure
is acceptable at each PSV outlet.
A detailed network analysis, carried out on recognized software such as FLARENET, will be undertaken for all
controlling relieving/depressuring cases in order to ensure that the maximum allowable back pressure at each
individual relieving device is not exceeded, with the actual pipe network configuration.
The guidelines given of previous section shall be applied.
7.2.7 Noise Philosophy
Noise generated by the flare should not be at a level such that personnel in normal working areas are exposed
to continuous levels of 85 dB(A). In areas where hearing protection must be worn, and for short duration of
flaring (30 seconds), the maximum noise level should not exceed 115 dB (A). The dispersion shall also cover the
noise dispersion results.
7.3 Drain System
The drainage system normally comprises the above fluids of the following streams:
Instrument drains during normal operation.
Maintenance drains after the equipment has been depressurized and the liquid has been pumped out to
level alarm low-low (LALL).
As part of the plant isolation and maintenance philosophy, each closed drain tail pipe emanating from equipment
maintenance drains could have an assembly consisting of double valve (ball and globe) on drain line and a bleed
valve in between.
All connections will be hard-piped from the equipment item to the relevant drain headers keeping the hazardous
fluids out of contact with the atmosphere. The drains system will be positively isolated from individual items of
equipment during normal operation.
49 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
The Closed Drain Vessel removes liquid droplets from the LP flare releases and will be sized according to API
21 for a liquid droplet size of 00 m for the maximum vapor load with the vessel at high-high liquid level. This
droplet size is consistent with the liquid handling capability of a pipe flare [Ref 7].
7.3.2 Hazardous Open Drain
The following objectives are to be achieved by the system:
Removal of liquids that could fuel a fire
Control the spread of flammable liquids from one fire zone to another
50 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
8 ISOLATION PHILOSOPHY
8.1 General
Isolation within the new AGPF will require the identification of:
Trains
Shutdown and Blowdown Sections
Maintenance Sections
Trains, shutdown and blowdown sections and maintenance sections can overlap and/or coincide across the
facility, which may allow isolation of items on a broader rather than individual basis. Equipment within a train can
generally be isolated at the train boundary, and should this overlap with a shutdown section, may also take
advantage of the section SDV.
Design will also consider isolation requirements for specific items of plant and equipment, related to the service
of the item, its purpose and also its location within the facility. Items that require frequent maintenance may be
spared in order to minimize impact on facility production. These items may be located within a train and require
sufficient isolation for maintenance whilst the train continues to operate.
51 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
2
3 SPECTACLE BLIND
4
6
8
10
12
14
OVER SPADE AND SPACER / REMOVABLE SPOOL
52 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Note that positive isolation may be provided on a train rather than an individual item basis, and for certain items
more specific requirements may apply, e.g. PSVs.
Application Method
Isolated
Blinds/spade shall be located as close to the vessel
Section Valve
nozzle as practically possible to avoid dead legs Isolation
Maintenance
All hydrocarbon/hazardous chemical handling
equipment
Table 8-4 shows the SBB & SB configuration with Globe Valve.
53 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
DBB isolation is valve isolation that consists of two valves in series with an interposing bleed facility. The vent
allows personnel to monitor the performance of the first valve for leaks and prevent a build-up of pressure on the
second.
Application Method
Pressure
Source
The use of a SDV as the second valve in a DBB configuration is acceptable provided that the SDV actuator is
deactivated; i.e. the control and power connections must be designed to be isolated/ disconnected to prevent
actuation.
54 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Double block and bleed will be used for services requiring isolation against operating pressures greater than the
design pressure of the flare system as well as to enable positive isolation to be affected by swinging a blind. For
sour system a double block and bleed isolation will be required even at operating pressures less than the flare
design pressure.
installation of positive isolation while the remainder of the facility is live. Provision of vent or bleed shall
be provided to check the integrity of the isolation valving before intervention for installed positive
isolation.
8.6 Equipment
Equipment that is not within a train but which is spared, and sufficiently critical to operations that
servicing of that equipment while the facility is live may be required, shall have provision for positive
isolation (including DBB if required by the service).
Equipment, including spared equipment, which is within a properly isolatable train, will only be provided
with single isolation valves (i.e. spared pumps, filters, etc). If upon isolation the single block valve
arrangement is found to be leaking, then the train can be shutdown and isolated for servicing to
continue.
Where spared equipment arrangements are installed that are not within a train and recurring failures are
not expected, single block valves may be used to isolate the failed, plugged, or dirty unit and allow the
plant to run on the spare until an appropriate shutdown can be initiated to properly isolate and repair the
unit. Where such an approach is employed in the initial design, the piping configuration shall allow for a
second block valve to be subsequently installed by shortening of removable spools.
Equipment not intended to be disconnected or taken out of service while the facility is live does not
require isolation. However, isolation may still be provided to facilitate operation and maintenance, and to
minimize purging volumes and duration and reduce maintenance intervals.
8.7 Valves
8.7.1 Control Valves
The requirements for isolation of control valves will be generally as follows:
Table 8-7 Control Valve Isolation
Application Diagram
DIRECTION OF FLOW
Critical Service with Spare Provided
__x__ __x__
56 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Application Diagram
57 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Application Diagram
RO
SDV
600min
PDT
service
600min
PDT
58 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Application Diagram
PDT
The need for pressurization bypasses will be determined by the start-up philosophy and start-up procedure. The
size of the bypass is determined by the volume of the system to be pressurized and the pressure differential
across the valve. If a large pressure differential may exist, shutdown valves with start-up bypass shall have a
differential pressure (ΔP> bar) permissive to prevent the shutdown valve from opening under high differential
pressure. All transmitter tapping points used for differential pressure permissive shall be local to the valve.
Manual valves acting with shutdown valves to provide DBB isolation of a train or pipeline shall always be
positioned “outboard” of the shutdown valves.
Shutdown valves on vessel liquid outlets should be located as close to the vessel outlet flange as possible.
8.7.4 Blowdown Valves
The general configuration for isolation of blowdown valves will be as follows:
Table 8-9 Blowdown Valve Isolation
Application Diagram
Blowdown Valve
Downstream isolation valve is required to be locked DIRECTION OF FLOW
open and full bore (equal to the outlet flare
connection line) provided the inlet line size and BD RO
upstream block valve are equal to the BDV size. 600 mm
MIN
LO
A restriction orifice (RO) will be provided on the
FB
downstream side of the BDV. This RO will be sized System to
such that in high pressure systems the pressure Blowdown
drop (and the required flow to flare system) occurs
across the orifice rather than the BDV.
Application Diagram
59 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Application Diagram
the PSV is removed.
60 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
DRAIN
DRAIN
DRAIN
61 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
valve arrangement should consist of a ball or gate on the upstream side and a globe or other suitable throttling
valve downstream. Where auto-refrigeration is possible the valves should be at least 600 mm apart.
8.10 Instrumentation
8.10.1 Level Instrumentation
Vessels shall have isolation for level instrumentation as shown:
Vessel LG LT
(NOTES 4,5) (NOTES 1,3)
(NOTE 7B)
(NOTES 1,2)
NC
VENT
NC NC
(NOTE 8)
NC NC
CONNECTION FROM
CSO
(SAME AREA ONLY)
(NOTE 6)
INSTRUMENTS
OTHER LEVEL
LT
Vessel
CSO
(NOTES 1,2) NC NC
(NOTE 8)
NC NC
NC
DRAIN
Note:
1. For 3-phase applications, an additional nozzle is required for lighter liquid (middle) phase.
2. Valve isolation (Table 4.2) should be consulted to determine whether double block valve assembly is required.
3. Where two level devices are used for control and trip functions, the elevation of nozzle tappings shall be identical to facilitate
discrepancy checking as much as possible.
4. One bridge cannot be used for both control and safety instruments.
5. Level bridle connections are always ”, however vessel nozzle connections could be 4”.
6. Isolation valve connection to instruments where connected to ESD and fire protection systems shall be car-sealed open (CSO).
62 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
Application Diagram
For pressure instrumentation connections requiring double
block and bleed valve. Minimum size of valve is ¾”.
PT PI
SCOPE OF
INSTRUMENTATION
SCOPE OF PIPING
SCOPE OF
INSTRUMENTATION
SCOPE OF PIPING
PI
SCOPE OF
INSTRUMENTATION
SCOPE OF PIPING
Vessel
63 of 64 AKT-PR-PHI-200-0001 Rev 0
Process Design Philosophy
9 REFERENCES
1. AKATARA Project Development, AKATARA Gas Plant & Sales Gas Pipeline, Basis of Design for FEED,
Doc No. AKT-GEN-BOD-70-000-001, Rev 0.
2. AKATARA Project Development, Akatara Project Development, Basis of Design for New Gas Plant, Doc
No. AKT-PG-BOD-200-0001
3. API Specification 12 J, “API Specification for Oil and Gas Separators”, Seventh Edition, October 1, 1 .
4. API, “API ecommended Practice 14E – Recommended Practice for Design and Installation of Offshore
Production Platform Piping Systems, Fifth Edition, October 1991, Reaffirmed March 2007.
64 of 64 AKT-PR-PHI-200-0001 Rev 0