Professional Documents
Culture Documents
E02-E01 (IEC) Rev 3 Sep 2015 (A) Power System and Equip. Design Cal
E02-E01 (IEC) Rev 3 Sep 2015 (A) Power System and Equip. Design Cal
16.6.4 The battery charger is sized to recharge the batteries in six (6) hours while the UPS is
carrying 100% load.
New Text:
16.6.4 The battery charger shall be sized to recharge the batteries within 10 times of the
discharge time while the UPS is carrying 100% load.
Notes:
1. Template shall be repeated for each addendum proposal
2. Separate forms shall be used for different standards.
IEC E02-E01 Power System and Equipment Design Calculations.docx
Addendum to SES Addendum No: 2
2 References
Reference is made in this standard to the following documents. The latest issues, amendments,
and supplements to these documents shall apply unless otherwise indicated.
SABIC Engineering Standards (SES)
IEC-E02-G01 Electrical System Design Criteria
IEC-E03-E01 Surge Protection
IEC-E04-S01 Liquid- Immersed Power Transformers (IEC)
IEC-E11-S03 Bonding and Grounding
IEC-E12-S01 Batteries and Racks
IEC-E12-S02 Battery Chargers
IEC-E12-X01 Batteries and Racks – Data Sheet
IEC-E12-X02 Battery Chargers – Data Sheet
IEC-E13-S01 Uninterruptible Power Supply (UPS)
IEC-E13-X01 Uninterruptible Power Supply (UPS) Data Sheet
IEC-E16-E01 Selection and Application of Capacitors for Power Factor Improvement
IEC-E20-E01 Lighting Design Requirements
IEC-E22-C01 Wires and cables installation, splicing and termination requirements
Z01-G03 Metrification
Z01-G04 Measurement Units for Use in SABIC Projects
New Text:
2 References
Reference is made in this standard to the following documents. The latest issues, amendments,
and supplements to these documents shall apply unless otherwise indicated.
SABIC Engineering Standards (SES)
IEC-E02-G01 Electrical System Design Criteria
IEC-E03-E01 Surge Protection
IEC-E04-S01 Liquid- Immersed Power Transformers (IEC)
IEC-E11-S03 Bonding and Grounding
IEC-E12-S01 Batteries and Racks
IEC-E12-S02 Battery Chargers
IEC-E12-X01 Batteries and Racks – Data Sheet
IEC-E12-X02 Battery Chargers – Data Sheet
IEC-E13-S01 Uninterruptible Power Supply (UPS)
IEC-E13-X01 Uninterruptible Power Supply (UPS) Data Sheet
IEC-E16-E01 Selection and Application of Capacitors for Power Factor Improvement
E20-E01 Lighting Design Requirements
IEC-E22-C01 Wires and cables installation, splicing and termination requirements
Z01-G03 Metrification
Z01-G04 Measurement Units for Use in SABIC Projects
Notes:
1. Template shall be repeated for each addendum proposal
2. Separate forms shall be used for different standards.
Addendum SES IEC-E02-E01 Power System and Equipment Design Calculations.docx
Addendum to SES Addendum No: 2
New Text:
16.9 Emergency & Stand by Diesel generator Capacity
16.9 3 The generator shall be capable of serving Level 1 loads to be operated simultaneously as
required in NEC article 700.12, within 10 seconds.
16.9.4 The generator shall be capable of serving Level 2 loads to be operated simultaneously as
required in NEC article 701.12, within 60 seconds.
New Text:
Notes:
1. Template shall be repeated for each addendum proposal
2. Separate forms shall be used for different standards.
Addendum SES IEC-E02-E01 Power System and Equipment Design Calculations.docx
Addendum to SES Addendum No: 1
New Text:
9 Short Circuit and Arc Flash Studies
9.1 Short Circuit Study
9.1.1 Short circuit studies shall be run to determine preliminary equipment rating and confirm
required equipment ratings for purchase.
9.1.2 The secondary of the 480 volt transformers shall be modeled with motor load equivalent
to the kVA rating of the transformer.
9.1.3 Buses with medium voltage motors shall be modeled with the actual motors at their
nameplate rating plus additional motors to represent the capacity provided for future
additions.
9.1.4 Fault calculations for equipment selection shall be based on the system operating
configuration that will result in the maximum available fault current.
9.1.5 Standard transformers impedances shall be used; deviations must be approved by
SABIC. Transformers shall be modeled with maximum allowed negative impedance
tolerance.
9.1.6 Unless otherwise approved, the utility supply to the plant shall be modeled using
Ultimate, Maximum and Minimum short circuit levels as per information in BEDD. For
short circuit studies the ultimate short circuit level shall be used and the power system
shall be modeled in its strongest configuration. For motor starting, the minimum short
circuit level shall be used and the power system shall be modeled in its weakest
Notes:
1. Template shall be repeated for each addendum proposal
2. Separate forms shall be used for different standards.
IEC-E02-E01_(IEC)_Rev_3_Sep_2015_Power_System_and_Equipment_design_calculations.docx
Addendum to SES Addendum No: 1
configuration. For protective device co-ordination the whole range of short circuit levels
shall be plotted on the co-ordination curves.
9.1.7 For revamp, de-bottle necking, and expansion projects, the downstream switchgears and
equipment short circuit ratings shall be determined considering maximum short circuit
rating of upstream switchgear, MCC or distribution boards.
incident energy value and other important safety information as per NFPA 70E Article
130.5 (D) including the required Personal Protective Equipment (PPE) to be worn by
the Technician/Operator. Contractor shall provide such labels of durable materials
such as ‘DuraLabel’ or approved equal, along with the report to be pasted on to the
equipment. The list of equipment to be labeled shall be submitted along with the Arc
Flash Study.
Notes:
1. Template shall be repeated for each addendum proposal
2. Separate forms shall be used for different standards.
IEC-E02-E01_(IEC)_Rev_3_Sep_2015_Power_System_and_Equipment_design_calculations.docx
NUMBER IEC-E02-E01
ENGINEERING REV. No. 3
This document is issued by ECoE, SABIC E&PM, Jubail Industrial City, Kingdom of Saudi Arabia. The information contained in this
document is the confidential property of SABIC. It cannot be disclosed, copied or used for any purpose without approval from SABIC.
If you are not authorized to posses this document, please destroy it immediately.
NUMBER IEC-E02-E01
Power System and Equipment REV. No. 3
CONTENTS
1 Scope ....................................................................................................................... 3
2 References ............................................................................................................... 3
3 General .................................................................................................................... 4
4 Environmental Requirements .................................................................................. 4
4.1 Site Conditions ................................................................................................. 4
5 Calculation Software ................................................................................................ 4
6 Sequence of Work and Approval ............................................................................. 5
7 Electrical Load Summary ......................................................................................... 5
8 Load Flow Study ...................................................................................................... 7
9 Short Circuit Study ................................................................................................... 7
10 Voltage Drop Calculations ....................................................................................... 7
11 Transient Stability Studies ....................................................................................... 8
12 Re-acceleration Studies ........................................................................................... 8
13 Load Shedding Studies ............................................................................................ 8
14 Harmonic Analysis ................................................................................................... 9
15 Power Factor Improvement ..................................................................................... 9
16 Equipment and Cable Sizing ................................................................................. 10
16.1 Definitions....................................................................................................... 10
16.2 Transformer Capacity ..................................................................................... 10
16.3 Switchgear Rating .......................................................................................... 13
16.4 Motor Control Center (MCC) Bus Rating ....................................................... 13
16.5 Battery and Charger Capacities ..................................................................... 13
16.6 Uninterruptable Power Supply Capacities ..................................................... 14
16.7 Cable Sizing ................................................................................................... 14
16.8 Motor Sizing ................................................................................................... 15
16.9 Emergency & Stand by Diesel generator Capacity ........................................ 15
17 Revision History ..................................................................................................... 17
Table 1 ............................................................................................................................11
NUMBER IEC-E02-E01
Power System and Equipment REV. No. 3
1 Scope
This standard defines requirements and procedures for electrical system and equipment design
calculations.
This document is mainly based on lEC Standards and is created by conversion and modification of
the SABIC Engineering Standard (SES) that are ANSI/IEEE based.
2 References
Reference is made in this standard to the following documents. The latest issues, amendments, and
supplements to these documents shall apply unless otherwise indicated.
SABIC Engineering Standards (SES)
IEC-E02-G01 Electrical System Design Criteria
IEC-E03-E01 Surge Protection
IEC-E04-S01 Liquid- Immersed Power Transformers (IEC)
IEC-E11-S03 Bonding and Grounding
IEC-E12-S01 Batteries and Racks
IEC-E12-S02 Battery Chargers
IEC-E12-X01 Batteries and Racks – Data Sheet
IEC-E12-X02 Battery Chargers – Data Sheet
IEC-E13-S01 Uninterruptible Power Supply (UPS)
IEC-E13-X01 Uninterruptible Power Supply (UPS) Data Sheet
IEC-E16-E01 Selection and Application of Capacitors for Power Factor Improvement
IEC-E20-E01 Lighting Design Requirements
IEC-E22-C01 Wires and cables installation, splicing and termination requirements
Z01-G03 Metrification
Z01-G04 Measurement Units for Use in SABIC Projects
International Electrotechnical Commission (IEC)
60038 Standard Voltages
60059 Standard Current Ratings
60076 Power Transformers
60076-12 Loading Guide for Dry-Type Transformers
60364 Low Voltage Electrical installations of Buildings
60909 Short circuit currents in three-phase a.c. Systems
60949 Calculation of thermally permissible short-circuit currents
60986 Short circuit temperature limits of electric cables with rated voltages from 6 kV
(Um-7,2 kV) up to 30 kV ) (Um=36 kV)
61800-2 Adjustable speed electrical power drive systems - Part 2: General
requirements- Rating specifications for low voltage adjustable frequency a.c.
power drive systems
61800-3 Adjustable speed electrical power drive systems - Part 3: EMC requirements
and specific test methods
National Fire Protection Association (NFPA)
70 National Electrical Code
Institute of Electrical and Electronic Engineers (IEEE)
519 Recommended Practice and Requirements for Harmonic Control in Electric
Power Systems
C57.91 Guide for Loading Mineral-Oil-Immersed Transformers
High Commission for Industrial Security, Ministry of Interior, KSA (HCIS)
Security Directives for Industrial Facilities
NUMBER IEC-E02-E01
Power System and Equipment REV. No. 3
3 General
3.1 It is the intent of this practice to define requirements for electrical system calculations and
calculations required for selection and application of power system equipment. Other electrical
design and equipment application calculations are covered by separate standards.
3.2 Grounding system calculations shall be performed in accordance with SES IEC-E11-S03.
3.3 Battery and battery charger sizing calculations shall be performed in accordance with SES
IEC-E12-S01, and SES IEC-E12-S02..
3.4 Lighting calculations shall be performed in accordance with SES IEC-E20-E01.
3.5 Insulation coordination and determination of required insulation levels shall be in accordance
with SES IEC-E03-E01.
3.6 Cable de-rating shall be in accordance with SES IEC-E22-C01.
3.7 The electrical system and equipment design calculations meet all requirements of section 5.2
of SES IEC-E02-G01.
3.8 Any conflict(s) between this standard, SES and industry standards, engineering drawings, and
contract documents shall be resolved at the discretion of SABIC.
3.9 All calculations and documents shall use SI units of measure in accordance with SES Z01-
G04 and SES Z01-G03.
3.10 The design calculations for sizing of electrical power supply and distribution equipment shall
be based upon using 120% of the sum of the operating load plus all known future loads unless
directed otherwise by SABIC.
4 Environmental Requirements
4.1 Site Conditions
Refer SES IEC-E02-G01, Section 3 for details.
5 Calculation Software
5.1 System calculations shall be made using a commercially available analysis program such as
ETAP (Electrical Transient Analysis Program) by OTI (Operational Technology Incorporated)
of which SABIC is a licensee.
5.2 Existing plants will normally have an established electrical system data base. In most cases
the calculations shall be made using the analysis program previously used for the plant. In all
cases SABIC shall approve the software package before calculations are performed.
5.3 Calculations shall be made in accordance with IEC 60909.
5.4 Calculation methods are related to the testing requirements for the equipment. Calculations
for systems using IEC are different than for systems using ANSI/NEMA equipment. Some
programs are capable of performing both type calculations but is important to select the
appropriate mode of calculation.
NUMBER IEC-E02-E01
Power System and Equipment REV. No. 3
voltage at the instant the switch is closed without regard to any affect this lowering of the bus
voltage might have on any other operating loads.
10.4 For very large motors started on the bus with other motors, a transient stability program or
dynamic motor starting program shall be employed to recognize the effect on and from all
loads on the bus.
10.5 The maximum acceptable voltage drops during motor starting are shown below. However in
all cases SABIC must approve the permissible voltage drop limits for each project and approve
individual calculations for motors larger than 2000 kW.
a. For motors on 480volt bus with other loads, the maximum drop on the bus shall be 10%.
The maximum drop to motor terminals shall be 15%.
b. For medium voltage motors on the same bus with other motors the maximum drop on the
bus shall be 15%. The maximum drop to motor terminals shall 20%. If solid state control
devices are used and the devices cannot accept 15% voltage drop, then the bus voltage
drop shall be limited to 10%. The maximum voltage drop at an LV bus due to motor starting
shall be restricted to 10%
c. For motors on captive transformers, the voltage drop at the bus supplying the captive
transformer shall not exceed 10%. The voltage at motor terminals shall be at least 10%
above the minimum value required to accelerate the load.
12 Re-acceleration Studies
12.1 Reacceleration studies shall be performed to determine the impact of automatically restarting
designated process drive motors after a brief power interruption. Typically this control would
permit the motors to restart over some time range. The minimum for the range would be the
time required for the internal voltage to decay, and the maximum would depend upon process
considerations.
12.2 The re-acceleration study is made to determine whether the motors can restarted
simultaneously. If not, additional studies shall be made to establish group sizes and required
time delay between groups.
12.3 This study is a specialized motor starting study with the motors starting simultaneous, modeled
as an equivalent single motor.
14 Harmonic Analysis
14.1 Harmonic currents and voltages have undesirable affects on operation of the electrical power
system including overheating of equipment and overvoltage failures. Aside from the
undesirability from the owners standpoint, the utility generally has strict limits on harmonics
since they flow back into the power grid.
14.2 Harmonics are produced by rectifiers and frequency converters. The larger the loads are, the
greater problem they create, so special attention must be given to large adjustable frequency
drives and electrolytic process equipment.
14.3 A Harmonic analysis study shall be performed for the plant including all harmonic producing
loads and calculating the effect on all buses.
14.4 Even though power factor improvement/VAR compensation equipment do not generate
harmonics, they can influence the magnitudes of harmonic voltages and currents due to
resonance conditions. The Harmonic Analysis study shall include the analysis of system
frequency response characteristics and ascertain whether resonance conditions occur due to
the combination of harmonic producing equipment and the power factor improvement/VAR
compensation capacitors.
14.5 This study shall be performed for the entire distribution system as per methods and
recommendations in accordance with IEEE 519 section 8, using ETAP Harmonic Analysis
study module.
14.6 Harmonic filters shall be provided when equipment, building or plant exceeds the limits of IEEE
519 for Total Harmonic Distortions (THD). The design of the filters shall be included with the
harmonic study.
(*) Average temperature of the cooling air for any 24 h (IEEE C57.12.00, Clause
4.1.2.1)
(**) Increase of average temperatures by 5o C as per IEEE C57.91, Section 6.2.
(***)Effect of Solar Radiation for transformers exposed to sun: Add 10o C. (No sun-
shade)
Nameplate rating of transformer = Choose next higher IEEE rating
Table 1
Unusual Temperature Derating for Liquid-Immersed Power Transformers
Type of Cooling Decrease load for De-rating De-rating when
each °C higher Av. Under shade: Exposed to sun:
Temp. (50 – 30) °C= (60 – 30) °C=
(% of kVA rating) (1) 20 °C 30 °C
Self-Cooled 1.5 30 % 45 %
(ONAN) (TCF=1.43) (TCF=1.82)
Forced-Air- 1.0 20 % 30 %
Cooled – All (TCF= 1.25) (TCF= 1.43)
(1) IEEE C57.91-2011, Table 3
16.2.2 For transformers up to 20 MVA, values of rated power shall be taken from the R10
series given in ISO 3:1973, Preferred numbers – series of preferred numbers, .at usual
service conditions
16.2.3 No further de-rating is required to be done by the manufacturer in addition to 16.2.1.
16.2.4 When synchronous motors with a leading power factor are connected to a bus, the
resulting leading kVAR shall be considered when calculating the transformer kVA
capacity.
16.2.5 Forced-air cooling fans and controls shall be provided on all transformers rated 2500
kVA or larger, and shall not be supplied on transformers rated less than 2500 kVA.
16.2.6 Maximum demand on a transformer serving a secondary selective system shall be the
sum of both buses with tie-breaker closed.
16.2.7 The transformer capacity (highest Forced cooled ONAF rating) shall:
a. be based on an eight hour maximum demand plus known future load,
b. include 10 % load growth factor,
c. Include projected future spare capacity (to be defined during basic design stage,
recommended 20%),
d. Compensate (be de-rated) for site ambient temperature.
NUMBER IEC-E02-E01
Power System and Equipment REV. No. 3
Commentary:
Example: Transformer is located under shade in substation yard – Secondary Selective
Transfomer capacity required at 30 deg C (T)= [(MD+KFL) x LGF x FSC x TCF] kVA
Transformer shall meet the requirements of NEC Article 695 and sized accordingly.
16.2.13 Dry Type Transformer Capacity
The kVA rating (s) of the transformers shall be increased (de-rated) for continuous
operation at higher than usual ambient temperature in compliance with IEC 60076-
12. Loading Guide for Dry-Type Transformers.
16.3 Switchgear Rating
16.3.1 A 15 minute maximum demand shall be the basis for selecting switchgear continuous
ratings.
16.3.2 The main breaker and the main bus of the switchgear shall have a current rating equal
to or greater than the highest current rating of the transformer that feeds the
switchgear.
16.3.3 Bus tie circuit breakers in secondary selective and spot network substations shall be
interchangeable with the incoming breakers.
16.3.4 Each feeder breaker shall have a continuous current rating equal to the higher of the
15 minute maximum of the feeder load or 100% of the full load currents plus 25% of
largest motor current. Loads shall include any provisions for future loads.
16.3.5 Circuit breakers used to control a single motor shall have a continuous rating at least
equal to 1.25 times the motor full load current.
16.3.6 Generator breakers shall have a continuous rating at least equal to 1.15 times the
maximum continuous generator rating.
16.3.7 Circuit breaker interrupting rating shall be adequate for the maximum short circuit
level.
16.3.8 Switchgear momentary rating shall be at least adequate for the maximum short circuit
level, with estimated motor contribution, which would be expected when the
transformer is loaded to its self cooled rated capacity.
16.4 Motor Control Center (MCC) Bus Rating
16.4.1 Low Voltage MCCs (480 V ) shall have main bus current rating as per IEC 60059.
16.4.2 Medium Voltage MCCs (4160 V) shall have main bus current rating as per IEC 60059.
16.5 Battery and Charger Capacities
16.5.1 The 125 VDC systems supplies control power to switchgear, excitation power, backup
for synchronous motors, MCC protective relays, annunciator, etc. The system is
composed of dual, 100% redundant battery chargers and 125 VDC battery banks,
unless otherwise specified at Data sheet IEC-E12-X02.
Battery Chargers shall comply with requirements of SES IEC-E12-S02 and IEC-E12-
X02..
16.5.2 Battery sizing shall be as per criteria given in SES IEC-E12-S01. Additionally batteries
shall be sized to provide power to trip the maximum number of breakers that might trip
once, after supplying power to indicating lights, relays, etc. for four (4) hours with both
battery chargers off. An example would be a bus differential tripping the main breaker,
the tie breaker, and all feeder breakers on one bus.
Backup time for non-redundant battery charger/battery systems is 4 hours. For fully
redundant systems it is 2 hours each.
Batteries and Racks shall comply with requirements of; SES IEC-E12-S01 and IEC-
E12-X01..
NUMBER IEC-E02-E01
Power System and Equipment REV. No. 3
16.7.9 Power cables in underground conduit banks shall be de-rated in accordance with the
Neher-McGrath method in order not to exceed the conductor insulation temperature
specified by the cable manufacturer. Cable capacity calculation shall take into account
the applicable de-rating factors, such as for ambient temperature, ground thermal
resistivity, maximum thermal resistivity of selected backfill, depth of laying and
grouped installation of cables.
a. For sizing of underground cables, use the following criteria:
Ground temperature1 = 35 C (unless otherwise specified)
Ground thermal resistivity = To be measured
Selected backfill thermal resistivity = 120 C.cm/W
Load factor = 1.0
Also refer to latest “Metrological and Hydrological Design Information” from Royal
Commission/Local Authority for ground temperature to be considered for cable
sizing calculations. The most stringent shall apply unless approved in writing from
SABIC.
16.7.10 Cable sizing calculations shall include the 20% future cables installed in the top
positions of the duct bank or trench. The rating shall be for the worst case location
along the route, i.e., exiting the substation, approaching another duct bank, road
crossing, etc.
16.7.11 Medium and high-voltage cables shall be selected to coordinate with the maximum 1
second short circuit rating of the connected equipment.
16.7.12 Medium-voltage feeders to load-center substations shall be sized for the maximum
transformer rating. This size shall include the transformer rating obtainable by forced-
air cooling.
16.7.13 Wire size shall be selected to limit maximum voltage drop for power and high intensity
discharge lighting circuits to 2.5 percent for feeder circuits and 2.5 percent for branch
circuits.
16.7.14 Services, feeders and branch circuits for power and lighting installations other than
specified above shall be sized in accordance with the requirements of IEC.
16.8 Motor Sizing
16.8.1 Refer to SES E02-G01 for selecting the motor voltage. Motors connected to captive
transformers may have voltages other than those shown based on a total system
economic evaluation.
16.8.2 In general, motors 1000 hp and larger shall be synchronous type to correct the overall
plant power factor to 0.9 or better as required by SABIC.
16.8.3 Motor Horse Power (hp), starting and running torques and speed shall be selected as
required for the mechanical drive (Refer SES G series).
16.9 Emergency & Stand by Diesel generator Capacity
16.9.1 Emergency & Stand-by Power generators shall provide power to critical loads when
normal electric power is not available. Emergency & Stand-by loads will include below
given equipment and systems and any other load deemed necessary during the
design development stage; further these loads are categorized under Level 1 and
Level 2 as per NFPA 110.
Level 1 Loads:
a. Security systems and devices shall have provision of emergency generator as
specified in Security Directive SES-07. For loads and details refer to SEC-01 to
SEC-12.
NUMBER IEC-E02-E01
Power System and Equipment REV. No. 3
shall not be greater than 15 percent when the largest motor on essential power is
started.
16.9.7 The systems motor control system and automatic transfer switch shall have a
continuous current rating equal to or greater than the generator’s rated output and a
short circuit rating equal to the greater of the available short circuit current from the
generator or the normal power feed.
17 Revision History
Revision No.1, January 2011 Addendums No. 1 to 3 incorporated,
References updated,
Sections 3.10,16.4, and 16.6.2 revised,
Generally revised.
Revision No.2, December 2012 Addendums No. 1 to 7 incorporated,
References updated,
Revised paragraphs: 4.1, 5.1, 7.2, 9.6, 13.1, 13.3
Deleted paragraphs: 14.7 to 14.10
Addition: 9.7
Revision No.3, September 2015 Addendums No. 1 to 4 incorporated, References
updated, elaborated emergency generator
selection/sizing requirements