Download as pdf or txt
Download as pdf or txt
You are on page 1of 63

Kemptville Water Pollution Control JLR No.: 29475-000.

1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 1 of 27
November 16, 2023

Kemptville Water Pollution Control Plant Expansion – Phase A

ADDENDUM NO. 3
November 16, 2023

Tender Closing Date: December 13, 2023 (see below)

This Addendum forms part of the Contract Documents and amends the original drawings and specifications.
Tenderers are reminded to acknowledge on the Form of Tender that this Addendum has been received.

TENDER CLOSING DATE


The Tender Closing Date has been revised to Wednesday December 13, 2023, at 2:00:00 pm.

RESTRICTED TENDER DOCUMENTS


We have investigated the inquiries regarding the restricted contract documents available on MERX. It was
determined that the encryption of the uploaded contract documents is applied by MERX itself. We were
unable to resolve the issue at this time. To be fair to all bidders, all current and future tender documents
and addenda for this Bid Call will continue to be hosted and distributed in MERX. No distribution outside
of MERX will be provided.

BIDDER QUESTIONS
Question #1:
Room Finish Schedule: Please inform the type of finish required for the North wall of room 800 Exit Stair.

Answer #1:
Refer to drawing revisions below.

Question #2:
Section 9960 High Performance Coatings: Item 1.2 of this section identifies Mechanical and Civil scope of
work, being the civil part as “Refer to the drawings for the extent of new hot-dipped galvanized handrails
and bollards to be painted as per this section”. However, drawing A012A identifies High Performance
Coating on the overhead door. Please clarify the full extent of the scope of work under Section 9960 High
Performance Coatings.

Answer #2:
Refer to Section 09960 subsection 1.1. Also refer to section revision below.

Question #3:
Please refer to drawing 1/A830A: There’s no wall assembly type specified for the wall on Grid Line 8.E.
Please clarify if the type of wall required is W1 as per previous tender.

Answer #3:
Required wall is W1.

Question #3:
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 2 of 27
November 16, 2023

Please refer to drawing 2/A830A: There’s no wall assembly type specified for the wall on Grid Line 8.7.
Please clarify if the type of wall required is W1 as per previous tender.

Answer #3:
Required wall is W1.

Question #4:
Drawing S000A, note 5.2.8 is a spec for Mix # 8 Macro synthetic fibre reinforced concrete. We did not see
this mix specifically requested on the drawings. Is this Mix 8 required? If yes, please advise where.

Answer #4:
Macro synthetic fibre reinforced concrete is required for the topping slab in the basement of the
Headworks Building. Drawings will be amended to clarity in a future addendum.

Question #5:
Detail 5/S011A indicates 'watertight expansion joint (refer to specifications)' and 'below grade expansion
joint (refer to specifications)'. Part 2.1.4 of section 03600 does not provide a standard of acceptance for
expansions joints. If possible, please provide a standard of acceptance for expansion joints, similar to what
is provided for contraction joints and construction joints in part 2.1.2 and 2.1.3 of section 03600.

Answer #5:
An amendment to the documents will be provided in a future Addendum.

Question #6:
Detail 5/S011A indicates 'provide sika combiflex SG over expansion joint. Refer to specification'. Sikadur
Combiflex SG is referred to in part 2.1.3 of section 03600 under Construction joint. Is this the spec for
expansion joints also? Please clarify the area or distance from the joint that is to receive the Combiflex SG.

Answer #6:
Sikadur Combiflex SG is correctly referenced under part 2.1.3 in Section 03600. The sika combiflex
system will need to be provided with a tape width of 300mm. The Contractor should consult with
the manufacturer of the product for further details. Refer to section revision below.

Question #7:
Can you please provide what has been removed from the original tender in the current retender for
Kemptville WWTP Phase A

Answer #7:
In general, the items that were removed from the original tender include (but was not limited to):
• New septage receiving station.
• Two (2) new equalization storage tanks.
• Retrofit existing aeration tanks into new secondary clarifiers.
• Demolition of existing primary clarifiers and construction of new tertiary filter building.
• Final Asphalt placement

Question #8:
Can you please confirm that the Hydro Line scope completed under another separate tender will be
completed prior to Phase A starting.

Answer #8:
The hydro line relocation contract is anticipated to be completed by Spring 2024.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 3 of 27
November 16, 2023

Question #9:
Reference section 01810. This identifies four incoming Forcemains for bypass, whereas drawing C002A
has five, from the north, 300mm Effluent, Northwest Quad & Equinelle, and from the south, East Quad and
Bridge Street. Please confirm which systems are related to section 01810 and what is required for the fifth
system.

Answer #9:
300mm Effluent Forcemain does not require relocation, and shall be supported and protected
during excavation and construction works.

Question #10:
Could you please provide PRV size and specifications for the New Air Blowers?

Answer #10:
PRV to be selected and provided by process air blower vendor. Refer to specification 11427.

Question #11:
Could you please provide specifications for the New Air Blower Check Valves?

Answer #11:
Check valves to be selected and provided by process air blower vendor. Refer to specification
11427.

Question #12:
Is there a flex connection required at the New Air Blowers Discharge? If so, could you please provide the
specifications?

Answer #12:
Flexible connection to be selected and provide by process air blower vendor. Refer to specifications
11427.

Question #13:
Reference the Mixed Liquor Line. Drawing C003A has an MLO at 600mm HDPE DR11, whereas PID402A,
P601A, P602A have an 800mm MLQ HDPE DR?, whereas PID601A has a MLQ at 650mm HDPE DR?,
please clarify what is required.

Answer #13:
MLQ pipe is to be 800mm in diameter. Refer to revisions to PID601A.

Question #14:
Reference drawing PM004A, detail 1, “Pipe Crossing of Structural Expansion joints”. There are several
instances where this may apply. Please confirm you require expansion joints.

Answer #14:
Yes, this detail applies where applicable.

Question #15:
Reference drawing PM005A, detail 12. This has a flushing connection for Heating, Effluent water, and ‘clear’
water. Please confirm as per section 15349, item 3.2.17.2.1 you require a flushing point every 30 metres
on all these systems.

Answer #15:
Yes, drains are required every 30m on specified systems.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 4 of 27
November 16, 2023

Question #16:
Reference drawing PM005A, please confirm which sleeve detail applies to pipes entering/ leaving channels/
tanks within the building.

Answer #16:
No additional information will be provided.

Question #17:
Reference drawing PID001A, please confirm the type of check valve required.

Answer #17:
No additional information will be provided.

Question #18:
Reference drawing PID803, there is a ball valve Cake Sampling line from Centrifuge #1; please confirm the
relevant datasheet for the valve.

Answer #18:
No additional information will be provided.

Question #19:
Reference drawing PID402A. This has the drop legs to each Diffuser Grid as 200mm. Whereas P502A has
the drops at this point as 100mm, we were advised on the previous project.

Answer #19:
Change all drop legs from 200mm to 100mm. Refer to revisions to PID402A.

Question #20:
Reference drawing P501A, note “Flow Tap on drop leg at this location typical for 6 drop legs”. Please
provide a detail for a ‘Flow Tap’.

Answer #20:
Flow tap is a 50 mm pipe with a ball valve. Refer to revisions to PID402A.

Question #21:
Reference drawing P801A. The main plan has two ‘Nozzles” within the Digester Tank, can you please
provide a specification of what is required.

Answer #21:
It is an open-ended pipe and valve, refer to section 3/P801A.

Question #22:
Reference section 15100-B3, E1 and E2, please confirm if the valves are to be Epoxy coated/ lined.

Answer #22:
Refer to datasheets & schedules for epoxy requirements.

Question #23:
Reference sections 11304, 11314, 11330, 11345, 11360 and 11380. Please confirm the equipment tag
numbers related to these sections. Without this information, it will be difficult to establish exactly what
equipment is related to what supplier and could lead to errors in the client’s breakdown. Using best
judgement is guessing and the contractors should not be asked to guess.

Answer #23:
Enough information within the tender documents has been provided to infer associated equipment
tags.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 5 of 27
November 16, 2023

Question #24:
Reference section 11345, item 2.1.1 “The Centrifuge Supplier is to perform raw Kemptville WWTP sludge
grab sample analysis during the project tender period…” Please confirm the client has instructed or
arranged for a grab a sample, as this is beyond our remit to comply with.

Answer #24:
Centrifuge suppliers are to reach out to Kemptville WPCP to arrange acquiring a grab sample for
analysis. Refer to Section 00213 item 1.9.2.

Question #25:
Reference section 11360, item 1.1.3 “As noted above the Dewatering System Manufacturer is responsible
in part to provide an emulsion polymer make down system, a shaftless screw conveyor, and a progressive
cavity sludge feed pump.” Is this statement meaning that the Dewatering Equipment supplier is to Supply
the equipment under packages 11314, 11344 and 11345, or just provide coordination with those suppliers
and the engineers to complete the systems?

Answer #25:
Yes dewatering supplier to provide equipment in section 11314, 11345 & both screw conveyor
under section 11334.

Question #26:
Reference Section 15060, item 1.1.2 “retain the services of a third-party pipe support engineer”. Item
1.3.2.4, “Provide certification of the design and installation of the pipe support”. Item 3.2.5.6 “forces imposed
by expansion joints in the system.” etc. For us to comply with this, please confirm you will provide a 3D
model of the piping systems following award, noting CAD files would not be sufficient.

Answer #26:
This will not be provided.

Question #27:
Reference section 11302, item 2.2.6 we have a name manufacturer who can only offer a bearing life of
50,000 hours, would this be acceptable.

Answer #27:
All named manufactures must meet specification.

Question #28:
Reference section 11302, item 2.3, which coatings take preference, 2.3.1 or section 09960.

Answer #28:
Section 11302 Item 2.3 will apply.

Question #29:
Reference section 11304, item 2.2.3, we have a named manufacturer who can only provide pumps at
64.9/45.4 efficiency, is this acceptable.

Answer #29:
All named manufactures must meet specification.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 6 of 27
November 16, 2023

Question #30:
Reference section 11384, item 2.3.1.4. The named supplier is supplying this in 304L, not 304, please
confirm this is acceptable.

Answer #30:
Acceptable.

Question #31:
Reference drawing PM009A, detail 8, please confirm the material specification for the Link Seal backing
plates.
Answer #31:
Refer to detail PM009A, detail no. 8 for material.

Question #32:
Reference drawing PM009A, detail 8 note “Please provide backing plates wherever link seals are used”.
Please confirm if this applies to PM010A, detail 2.

Answer #32:
No Link backing plate required for detail PM010A detail 2.

Question #33:
Reference section 11380, item a named supplier has excluded from the package the following, “The
Supplier is to submit all operating constraints and design requirements related to the successful
commissioning and operation of the hot water boiler package.”. Please confirm this is acceptable.

Answer #33:
Refer to section revision below.

Question #34:
Reference section 11378, the named supplier has qualified their design with the following premises, please
confirm these are acceptable.
a. Item 2.2.4.2 - Pressure at the top of the dropleg for peak condition will be 49.4 kpag.
b. Item 3.2.2.1 - Xylem does not inspect tank construction nor certify the tank
c. Item 3.2.2.2 - Xylem does not train nor certify contractor staff for installation. Xylem will provide
installation guidance and will be available to answer questions.

Answer #34:
a. Acceptable
b. Refer to section revision below
c. Refer to section revision below

Question #35:
Reference section 11380, item a named supplier has excluded from the package the following, “The
Supplier is to submit all operating constraints and design requirements related to the successful
commissioning and operation of the hot water boiler package.”. Please confirm this is acceptable.

Answer #35:
Yes acceptable. Refer to Section revision below.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 7 of 27
November 16, 2023

Question #36:
Reference section 11380, a named supplier has qualified their package with the following, please confirm
these are acceptable.

a. Item 2.3, data Table 2, Idler sprocket sleeve bearings: material – Our sleeve bearings are made
from repro UHMW material.
b. Item 2.3, data Table 2, Drive chain: material – Our drive chain is made from glass filled nylon
material.
c. Item 2.3, data Table 2, Drive sprockets: material – Our drive sprocket is made with a 316 SS
hub and nylon sprocket rim.
d. Item 2.4.1.1, our SEW Euro drive uses DIN specifications not AGMA specifications.
e. Item 2.4.2.1 – The pin on our drive chain has a D head on one end to prevent pin rotation. It
is locked into the sidebar using a roll pin that is inserted into the top of the sidebar.
f. Item 2.4.2.2 – Our drive sprockets have a 316 SS hub and nylon 6 sprocket rim; our driven
sprockets have a 75D urethane body and repro UHMW segmental sprocket rim and our take
up idle sprocket is repro UHMW.
g. Item 2.4.3.1 – Our collector chain has a T head pin design and is locked into the sidebar using
a clip. Pins are glass filled nylon material.
h. Item 2.4.3.2 – Our F228 attachment links are molded integral to the link.
i. Item 2.4.3.3 – Our sleeve bearings use 316 SS band clamps, not through bolts.
j. Item 2.4.3.4 – Our chain tensioner is cast iron c/w UHMW insert, and 316 SS take up screw.
k. Item 2.4.4.1 – Our peak cap wall bearings are cast iron c/w UHMW inserts
l. Item 2.4.4.2 – The nonmetallic lubrication extension lines are not included in our proposal and
are to be provided by others
m. Item 2.4.8.1 – Our wear strip are 3/8” thick x 2 5/8” wide x 120” long
n. Item 2.5.1 – We are only supplying limit switches, drive units and Longitudinal/Cross Collector
control panels for electrical equipment. Any wiring or other electrical equipment is to be
supplied by others
o. Item 2.6.3 – Our flight monitoring system uses proximity sensors instead of limit switches to
sense flight misalignment and no motion.
p. Item 2.6.4.6 – We are not providing any HMI Screens and any related interface software in our
control panels.
q. Item 2.7.2 – Lubrication extension lines are not included in this proposal and are to be provided
by others.
r. Item 2.7.4 – Our manual handwheel does not require a gear reducer, so a gear reducer is not
included in our proposal.

Answer #36:
a. Refer to specification Section 11380.
b. Refer to specification Section 11380.
c. Refer to specification Section 11380.
d. Yes acceptable.
e. Yes acceptable.
f. Yes acceptable.
g. Yes acceptable.
h. Yes acceptable.
i. Yes acceptable.
j. Yes acceptable.
k. Yes acceptable.
l. This shall be provided by the contractor.
m. Yes acceptable.
n. Yes acceptable. Wiring and electrical cables to be provided by electrical contractor.
o. Yes acceptable.
p. Yes acceptable.
q. This shall be provided by the contractor.
r. Yes acceptable.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 8 of 27
November 16, 2023

Question #37:
Reference section 11384, item 2.4.3, “Each LCP to be NEMA 7 and NEMA 4x” The named supplier is
supplying these as “NEMA 12 and NEMA 7”. Please confirm this is acceptable.

Answer #37:
Not acceptable.

Question #38:
Reference section 15100, Process valve Schedule. Can the base schedule as per this phase please be
provided in a spreadsheet format.

Answer #38:
We do not populate our table in excel. This will not be provided.

Question #39:
Reference drawing P805A and the bubbled notes. In the previous P800 series, bubbles were noted as
Provisional Cost items, but not on this drawing, is there a reason for these bubbled notes.

Answer #39:
No reason for this bubble, Ignore this bubble.

Question #40:
Reference section 15100, Process Valve Schedule. Valves VF-511 to 521, Type C2 have ‘Handwheel’
operators, not ‘Gear’ whereas section 15100-C2 states “Valves larger than 150 mm to have manual gear
actuator.”. Please clarify what is required.

Answer #40:
Follow specification section 15100-C2.

Question #41:
Reference section 15100, Process Valve Schedule. Valves VF-710 & VF-714, Type C have ‘Handwheel’
operators, not ‘Gear’ whereas section 15100-C states “Valves larger than 150 mm to have manual gear
actuator.”. Please clarify what is required.

Answer #41:
Follow specification section 15100-C.

Question #42:
On the drawing C006A, the match line at the top of the drawing shows C009 but C009 is the match line for
the bottom of C006A. We would like to find where the fencing extends at the top of the drawing. Any idea
what drawing this may be on?

Answer #42:
Match line to be deleted. Fencing extends 24m to the west and connect to the fence shown on
drawing C006A.

Question #43:
Reference top of drawing C004A. There is a disconnect with the orientation of the chainlink fence, that
previously went around the Equalization tanks. Please confirm this distance is approximately 125.5m in
length, and orientation is shown on drawing E003A.

Answer #43:
Refer to previous response.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 9 of 27
November 16, 2023

Question #44:
Drawing refers the fence to OPSD 972.130 where it shows no barb wire but the specs reference barb. Can
we please confirm if there is barb for both fence and gates?

Answer #44:
Barb Wire is required as per OPSD 972.101

Question #45:
Reference drawing C003A, is the new 75mm Gas Line to the New Dewatering and Digester Control Building
by the Contractor or by the Utility Company.

Answer #45:
The gas line to be installed by the utility company, coordinated and paid by the contractor.
Trenching and backfill are to be provided and coordinated by the contractor.

Question #46:
Reference drawing C007A, details 1 & 2. If applicable, please confirm the drawing/ sleeve detail that applies
to the pipes in the Valve Chambers walls.

Answer #46:
Pipe penetration to be completed as per detail 5/PM005A

Question #47:
Reference drawings C003A (&C004A?) and the 250mm Outlet pipe as per detail OPSD 219.210 This
drawing has no 250mm pipe detail, please clarify what you require?

Answer #47:
A storm pipe (size indicated) is to be installed at base of rock flow check dam, center in dam at the
slopes indicated by the grades

Question #48:
Reference drawing C004A, this has a note referring to Transition and Standpipe chambers, these were on
drawings DP001 and P001, which has been deleted, please clarify what you require?

Answer #48:
Note to be deleted. Refer to drawing revision below.

Question #49:
Reference section 02631, item 2.1.15, “All Precast Chambers not specifically covered by an OPSD shall
be designed by manufacturer and a stamped drawing by a Professional Engineer…” Please confirm if this
applies to item 2.1.3, “Precast concrete trench / Shallow Invert Trench (SIT) to meet Ontario Highway
Designation H20.”

Answer #49:
Yes this applies to the Concrete trenches

Question #50:
Section 02715, 2.1.1 – Would blue DR25 or DR18 pipe be considered an approved equivalent to the DR26
pipe specified?

Answer #50:
Yes, these 2 pipes would be considered equivalent
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 10 of 27
November 16, 2023

Question #51:
On DWG C004A there is a note showing a 14” Odour Duct at Elev 88.6m is this correct and where does it
terminate? This is around the area of TP 22 at the line entry to the Headworks Bldg.

Answer #51:
Note to be deleted. Refer to drawing revision below.

Question #52:
When measuring existing tertiary filter building and existing service building on drawings C001A and
C002A, the scales appear to be off when comparing the same measurement on other drawings. It appears
drawing C001A should have a scale of 1:300, and drawing C002A should have a scale of 1:400. Please
confirm.

Answer #52:
Please update drawing scale on C001A to 1:300 and C002A to 1:400.

Question #53:
Reference section 01810, item 1.11.5. “Contractor to consider use of bypass pumps, vacuum truck or other
methods for flow management.”
a. Please confirm the owner will isolate the various forcemains as they enter the site.
b. To be able to provide this we require plans which detail where we can take the bypass from as the
various forcemains enter the site.
c. Please confirm the bypass discharge point.
d. If the owner is unable to isolate the incoming forcemains, will live taps be acceptable.
e. Please confirm the existing forcemain pipe material.

Answer #53:
a. There is no means near the WPCP to isolate forcemains. Owner will isolate forcemains at
their respective pumping stations.
b. Contractor to develop plan for tie-ins to complete forcemain bypass as required to complete
the work
c. The intent of the forcemain by-pass is to facilitate the installation of new works. By-pass
is intent to discharge into the existing headworks.
d. Yes, live taps are acceptable.
e. The existing forcemains to the south (East Quad & Bridge) are noted on the drawings.
There is a lack of detail on the 2 existing forcemains from the North (North West Quad & Equinelle)
but can be assumed to be PVC. Contractor to confirm.

Question #54:
Reference section 02715, item 2.1. Calls for Bell and Spigot joints, and Ductile Iron Fittings. Item 2.4 refers
to a flange joint restraint, please clarify where ‘flanged’ joints/ restraints are required.

Answer #54:
Flanged joints are referenced for any installation of valves. All fittings are to be restrained are per
the manufacture’s recommendation.

Question #55:
Reference section 02714, item 2.3.2 states that ‘Mechanical joint restraint may be used subject to the prior
approval of the Consultant.’ whereas item 2.8.4 states that ‘Ductile iron fittings shall be cement lined with
mechanical joints.’ please clarify are restraint joints required.

Answer #55:
Restraint joints are required.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 11 of 27
November 16, 2023

Question #56:
Ref Section 02315 Excavation, Trenching & Backfill………1.3 Off-site excavated surplus material
disposal...1 All excess soils will remain onsite for beneficial reuse as directed by the Owner………
3.4 General Excavation .9 Disposal of surplus and unsuitable excavated material off site
3.5 Soils Management .1 – Contractor is responsible for excavation, handling, hauling, & disposal costs for
all soils excavated as part of the work…Please update conflicting spec sections regarding soil disposal

Answer #56:
Refer to section revisions below.

Question #57:
Please provide soil characterization report for any soil that is to be disposed offsite.

Answer #57
All soil is to remain onsite.

Question #58:
Please provide additional laydown area for stockpiling of soil. There is ~20,000m3 of excess soil generated
from excavation & trenching. There is already limited laydown for trailers, dewatering tanks, construction
equipment, material storage etc.

Answer #58:
All material is to be stockpiled along the westerly limits between Grenville St and the plant. Exact
location to be coordinated with the Owner.

Question #59:
Please provide a provisional item for unsuitable soil excavation beyond design grades. It is not reasonable
for the contractor a risk on unsuitable soil conditions.

Answer #59:
Unsuitable soil will be dealt with on a during construction as an unforeseen item

Question #60:
Section 02140 Dewatering.4 Install Clay trench barriers as indicated on civil drawing. Please provide details
for clay trench barriers

Answer #60:
Clay trench plug to be constructed as per OPSD 802.095.

Question #61:
Please clarify the type of chainlink fence roadway entrance gates to be included.

Answer #61:
The South Gate (roadway entrance from County Road 43) to be as per Section 02821, complete
with automated opening as per detail 4/E008A and Section 16895. The North Gate (roadway
entrance from Honour Way) to be a 6000mm wide double swing opening gate as per OPSD
972.102.

Question #62:
Please provide the 3D model for visualization purposes of the project.

Answer #62:
CAD and 3D files will not be provided at this time. The Successful Bidder will be provided the files
following contract award.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 12 of 27
November 16, 2023

Question #63:
Reference drawing DE004A, note 4 calls for the demolition of “Existing headworks and screening
equipment, control panels, devices…”. But the original Process demolition drawing DP201 has been
deleted, please clarify what is required for Process/ Mechanical demolition.

Answer #63:
Refer to addendum #3 drawing package. DP201 is not in contract as it is part of Phase B. DE004A
updated accordingly.

Question #64:
Has all the Plans/Drawing and Specification already been sent ESA Plan review division?

Answer #64:
Yes drawings and specifications have been submitted.

Question #65:
Please confirm all tray sizes for power cable are designed meet the 100% spacing as noted on E000A
General notes I.

Answer #65:
No Response provided, please re-read the note.

Question #66:
Is the other contractor for the 44kV scope extended the duct bank across the road or are they just going
past the ground mat at the new switch.

Answer #66:
Please refer to drawing E003A

Question #67:
Does Hydro One have the new pad mount transformer available.

Answer #67:
Please refer to drawing E003A

Question #68:
Can you confirm the emissions level required for the new generator.

Answer #68:
Please refer to Section 16622

Question #69:
Can you please confirm the conduit type for all new conduits installed in the existing plant and new. Is this
required to be epoxy coated rigid galvanized steel.

Answer #69:
Please refer to drawings as well as Section 16133 3.1.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 13 of 27
November 16, 2023

Question #70:
The following Disconnect switches LD-LC-608, LD-LC-610, LD-CC-609, LD-CC-611, LD-P-728 and LD-
729 that are shown on the electrical single line diagram drawing E301A. Is there an electrical location
drawing shown those Disconnect’s?

Answer #70:
Refer to updated drawing E301A in Addendum #3. LD-LC-608, LD-LC-610, LD-CC-609, LD-CC-
611, LD-P-728, LD-P-729, LD-MIX-704 and LD-MIX-705 are part of Phase B and not in contract.
Addendum #3 drawing package addresses all relevant changes to plans, single line diagrams, etc.

Question #71:
Are there electrical location drawings shown the following LCP-6001, LCP-6004 panels and LD-RH-601 to
LD-RH-606 disconnects for the radiant heaters?

Answer #71:
LCP-6001 and LCP-6004 are part of Phase B and not in contract. Refer to Addendum #3 drawing
package for update drawings. Addendum #3 drawing package addresses all relevant changes to
plans, single line diagrams, etc.

Question #72:
Reference drawing E003A. There are no lines between the electrical MH and the Electrical Building, and
from the Electrical MH to PMH-01. Drawing E003A has lines that are greyed out indicating
existing. Drawing C003A shows dark lines indicating new electrical duct banks. Please confirm new duct
banks are required for these runs.

Answer #72:
Electrical MH referenced in question has been deleted, refer to revisions to E002A.

Question #73:
On drawing E004A heat tracing schedule note, 8, 10, 13, 14 & 16 are on STM Storm drains. Can confirm if
we are to only heat trace the priority going outside of the buildings?

Answer #73:
Updated drawing E004A to refer to drawing detail 5/PM009 for storm water heat trace drain
requirements.

Question #74:
On drawing E008A, there is a note that states, “Gate operation should not require card access at public
side pedestal.” Do they mean the secure side of the gate?

Answer #74:
Yes, updated drawing detail 4/E008A to reflect change. Refer to addendum #3 drawing package.

Question #75:
Reference CCDC2, page 13, GC 3.3.2 “The Contractor shall engage and pay for registered professional
engineering… where such Temporary work is of such a nature that professional engineering skill is required
to produce safe and satisfactory results.” Please confirm is this would apply to the Temporary Boiler and
associated piping for section 01810, item 1.10.4.17.

Answer #75:
Yes
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 14 of 27
November 16, 2023

Question #76:
Please confirm all tray are sized to meet their tray loading capacity?

Answer #76:
Refer to Section 16114 revisions below.

SPECIFICATIONS
General
Item No. 1 Section 00213 Instructions to Bidders

1.1 Clause 1.4.1.2 to be replaced with:

“.2 Bid forms are to be executed, dated, and submitted electronically to the
MERX website before 2:00:00 pm local time on December 13, 2023.”

Civil
Item No. 2 Section 02315 (Excavation Trenching and Backfill)

2.1 Delete Clause 3.4.9 and replace with the following:

“.9 Reserved”

2.2 Delete Clause 3.5.1 and replace with new Clause 3.5.1:

“.1 Contractor is responsible for the excavation, handling, and disposal onsite
all soils excavated as part of the Work.”

Architectural
Item No. 3 Section 09960 (High Performance Coatings)

3.1 Add Clause 1.1.3:

“.3 Refer to the drawings for the extent of other items to be painted as per this
section.”

3.2 Delete Clause 1.2.3 in its entirety.

Structural
Item No. 4 Section 03600 (Concrete Joints and Accessories)

4.1 Delete Clause 1.2.1 and replace with new Clause 1.2.1:

“.1 Pre-installation Meetings: in accordance with Section 01319 - Project


Meetings, convene pre-installation meeting one (1) week prior to beginning
concrete works.
.1 Ensure key personnel, site supervisor, Owner, Consultant,
formwork contractor, concrete producer, and materials testing agent
attend.
.1 Verify project requirements.”
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 15 of 27
November 16, 2023

4.2 Add new Clause 2.1.4.3:

“.3 Expansion Joint Filler: Potable water approved pre-coated, pre-formed,


pre-compressed self-expanding joint system specifically designed for use with
compressed expanding foam joint filler (waterproof). Thickness as noted on the
drawings.
.1 Standard of Acceptance for liquid retaining structures:
Submerseal by Emseal with Sikadur Combiflex SG System by Sika
Canada.
.2 Standard of Acceptance for below-grade elements of non-liquid
retaining structures: Submerseal by Emseal.
.3 Standard of Acceptance for vertical joints above grade in non-
liquid retaining structures: Seismic Colorseal by Emseal.
.4 Standard of Acceptance for horizontal joints at grade or above
grade inside of buildings: Emshield WFR1 by Emseal.
.5 Standard of Acceptance for repair of existing joints: Submerseal
by Emseal with Sikadur Combiflex SG System by Sika Canada.
.6 Manufacturer to select sealant system appropriate to the
movement, head pressure and design requirements at each joint location
that meet the project specifications.
.1 Depth of seal as recommended by manufacturer.”

4.3 Delete Clause 3.1.4.2 and replace with new Clause 3.1.4.2:

“.2 Provide 16 mm/ 5/8" diameter by 900 mm/ 36" long smooth steel rods at
400 mm/ 16" centres across joint at mid-height. unless noted otherwise. Grease or
wrap rod to prevent bond on one side of joint or install into smooth dowel cap as
specified in Section 03200.”

4.4 Delete Clause 3.2.7.2 and replace with new Clause 3.2.7.2:

“.2 Place wall in alternate portions with a distance between vertical


construction joints not exceeding 10m. Horizontal construction joints shall not
exceed 6m.”

Mechanical
Item No. 5 Section 11378 (Fine Bubble Air Diffuser System)

5.1 Delete Clause 3.2.2 in its entirety.

Item No. 6 Section 11380 (Clarification Equipment)

6.1 Delete Clause 1.3.3.2.3 and replace with new Clause 1.3.3.2.3:

“.3 The Supplier is to submit all operating constraints and design


requirements related to the successful commissioning and operation of the
clarification equipment.”
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 16 of 27
November 16, 2023

Electrical
Item No. 7 Section 16114 (Cable Tray)

7.1 Delete Clause 3.3.1 and replace with new Clause 3.3.1:

“.1 Provide supports as required to meet Seismic Restraints as per Section


16010 as well as to meet the manufacturer’s installation requirements. Locate
supports to minimize deflection.”

Item No. 8 Section 17002 (System Integration Services)

8.1 Delete Clause 2.1.1.9 and replace with new Clause 2.1.1.9:

“.9 Re-commission PLC and SCADA communications with remote


sites. Update the existing PLC logic for each remote site as required for full
integration into the new SCADA system. Incorporate the existing remote sites into
the new SCADA system; this includes alarming, trending, event logs, process
screens, process reports, etc.”

Item No. 9 Section 17100 (Control and Instrumentation Basic Material)

9.1 Delete Clause 2.1.2 and replace with new Clause 2.1.2:

“.2 Clause 2.1.2 to read “Shop Drawings to include installation details


including specific piping, valving and mounting for all installation sensitive
instruments. This will require co-ordination from the General, Mechanical,
Electrical, and Control Systems Specialist.”

9.2 Re-number Clause 2.5.1.13 to 2.5.1.15.

9.3 Insert the following new clauses 2.5.1.13 and 2.5.1.14:

“.13 Provide matching Quick Release, Stainless Steel Handrail Mounting


Bracket. Equivalent to YSI 245 8000Y.
.14 Provide a sensor cleaning system, equivalent to Hach 6860000 High
Output Airblast Cleaning System, 115 V.”

9.4 Delete Clause 2.6.1.5 and replace with new Clause 2.6.1.5:

“.5 Accuracy: +/- 0.5%; submit flow calculations for review.”

9.5 Add the following new clauses 2.7.1.1.5 to 2.7.1.1.8:

“.5 Constant temperature sensor


.6 Sensor not to overheat at zero flow
.7 Sensor lead length independent circuitry
.8 Rugged all-welded design”

9.6 Re-number Clauses 2.7.1.10 to 2.7.1.13

9.7 Insert the following new clauses 2.7.1.10 to 2.7.1.12:

“.10 Field configurable electronics


.11 Continuous self-monitoring electronics that verify the integrity of the
sensor wiring and measurements
.12 Velocity-temperature mapping for wide ranging velocities and
temperatures”
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 17 of 27
November 16, 2023

9.8 Delete Clause 2.7.1.5 and replace with new Clause 2.7.1.5:

“.5 CSA Zone 1, NEMA 4X.”

Item No. 10 Section 17051 (Sequence of Operations)

10.1 Change Section Number from 17051 to Section 17501, as per the Table of
Contents.

DRAWINGS
Civil
Item No. 11 Drawings C001A (EXISTING CONDITIONS)

11.1 Update drawing scale to 1:300.

Item No. 12 Drawings C002A (REMOVALS)

12.1 Update drawing scale to 1:400.

Item No. 13 Drawings C004A (SITE SERVICING PLAN)

13.1 Delete the following note:

“TRANSITION AND STANDPIPE CHAMBERS REQUIRING MODIFICATIONS


LOCATED NORTHOF PLANT. COORDINATE WITH MECH FOR
MODIFICATIONS. EXACT LOCATION TO BECOORDINATED WITH
OPERATIONS STAFF.”

13.2 Delete the following note:

” 350mm ODOUR PIPE INV (APPROX) = 88.6m


FORCEMAINS OBV (APPROX) = 87.50m”

Architectural
Item No. 14 Drawings A015A (SCHEDULES & FINISHES)

14.1 In the Room Finish Schedule, add “PT/EC” to the North Wall Finish column for
Room No. 800 (Exit Stair).

14.2 In the Room Finish Schedule, add the following text in the Remarks column for
Room No. 800 (Exit Stair):

“Wall areas above the ground floor to be PT. Wall areas below the ground floor to
be EC.”
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 18 of 27
November 16, 2023

Electrical
Item No. 15 Drawings PID401A (PRIMARY CLARIFIERS)

15.1 Replace entire drawing with the attached revised drawing PID401A. Drawing
revisions include the follow:

.1 Replace LCP-4001, LCP-4004 AND LCP-4007 with revised LCP design. Refer to
drawing.

.2 Add “Run” digital output to LCP-4001, LCP-4004 and LCP-4007. Refer to drawing.

.3 Add “Fault” and “In-Auto” digital inputs to VFC-401, VFC-402, VFC-403, VFC-404
and VFC-614. Refer to drawing.

Item No. 16 Drawings PID402A (AERATION TANKS)

16.1 Replace entire drawing with the attached revised drawing PID402A. Drawing
revisions include the follow:

.1 Add “Fault” and “In-Auto” digital inputs to VFC-409, VFC-410, VFC-411, VFC-412,
VFC-413 and VFC-414. Refer to drawing.

.2 Change drop legs at aeration tanks #1, #2 and #3 from 200mm to 100mm. Refer
to drawing.

.3 Add leader text to flow tap valves on drop legs for aeration tanks #1, #2 and #3.
Text to read “50mm pipe and ball valve typ. 6 locations”. Refer to drawing.

Item No. 17 Drawings PID403A (EQUALIZATION TANKS, PROCESS AIR & COAGULANT DOSING
SYSTEM)

17.1 Replace entire drawing with the attached revised drawing PID403A. Drawing
revisions include the follow:

.1 Remove TC-7010 and associated IO tag.

.2 Add reference bubble “L” to LCP-4019 and LS-4029. Refer to drawing.

.3 Add “Fault” and “In-Auto” digital inputs to VFC-941. Refer to drawing.

Item No. 18 Drawings PID601A (SECONDARY CLARIFIERS)

18.1 Replace entire drawing with the attached revised drawing PID601A. Drawing
revisions include the follow:

.1 Change LCP-6010, LCP-6011, LCP-6012, LCP-6014, LD-P-612, LD-P-613, LD-


LC-608, LD-CC-609, LD-LC-610, LD-CC-611, and associated tags to Phase B and
show as “Not In Contract”. Refer to drawing.

.2 Change LCP-6001, LCP-6004, and associated tags and devices to Phase B and
show as “Not in Contract”. Refer to drawing.

.3 Change mixed liquor pipe diameter from 650mm to 800mm. Refer to drawing.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 19 of 27
November 16, 2023

Item No. 19 Drawings PID803A (POLYMER AND DEWATERING)

19.1 Replace entire drawing with the attached revised drawing PID803A. Drawing
revisions include the follow:

.1 Add “Fault” and “In-Auto” digital inputs to VFC-820. Refer to drawing.

Item No. 20 Drawings MID001A (BOILER SYSTEM)

20.1 Replace entire drawing with the attached revised drawing MID001A. Drawing
revisions include the follow:

.1 Add reference text to BLR-901, BLR-902 and BLR-903. Text to read “Refer to
MID002A.” Refer to drawing.

Item No. 21 Drawings MID002A (BOILER GAS TRAIN SYSTEMS)

21.1 Replace entire drawing with the attached revised drawing MID002A. Drawing
revisions include the follow:

.1 Add reference text to FCP-9010, FCP-9020, and FCP-9030. Text to read “Refer
to MID001A.” Refer to drawing.

Item No. 22 Drawings MID301A (HVAC DIAGRAMS)

22.1 Replace entire drawing with the attached revised drawing MID301A. Drawing
revisions include the follow:

.1 Add reference text to BLR-901, BLR-902 and BLR-903. Text to read “Refer to
MID001A and MID002A.” Refer to drawing.

.2 Add “Fault” and “In-Auto” digital inputs to VFC-901, VFC-902, VFC-903, and VFC-
904. Refer to drawing,

Item No. 23 Drawings ME002A (MOTOR STARTER & CONTROL LIST SHEET 2 OF 4)

23.1 Replace entire drawing with the attached revised drawing MID301A. Drawing
revisions include the follow:

.1 Change Power Source column from “DP-201” to read “HCP-4001” for entries RH-
401, RH-402, and RH-403. Change Power Source column from “DP-201” to read
“HCP-4004” for entries RH-404, RH-405, and RH-406. Change Power Source
column from “DP-201” to read “HCP-4007” for entries RH-407, RH-408, and RH-
409. Refer to drawing.

Item No. 24 Drawings DE004A (SITE PLAN DEMOLITION)

24.1 Replace entire drawing with the attached revised drawing DE004A. Drawing
revisions include the follow:

.1 Change drawing note 4 to Phase B and mark as “Not In Contract”. Refer to


drawing.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 20 of 27
November 16, 2023

Item No. 25 Drawings E002A (SITE PLAN)

25.1 Replace entire drawing with the attached revised drawing E002A. Drawing
revisions include the follow:

.1 Remove manhole between generator and electrical service building. Refer to


drawing.

.2 Add general note I. Note to read “Coordinate buried services with civil.”

Item No. 26 Drawings E004A (HEAT TRACE DETAILS)

26.1 Replace entire drawing with the attached revised drawing E004A. Drawing
revisions include the follow:

.1 Add “Refer to 5/PM009A” to the end of each note for storm drain heat trace: TC-
2030, TC-7011, TC-7012, TC-8050 and TC-9010.

Item No. 27 Drawings E008A (SECURITY & ACCESS CONTROL DETAILS)

27.1 Replace entire drawing with the attached revised drawing E008A. Drawing
revisions include the follow:

.1 Replace leader text on detail 4/E008A on secure side vehicle detection loop. Text
to read “Provide vehicle detection loop controller cabling installed at depth to suit
manufacturer requirements tied to gate controller. Program gate controller to
automatically open gate upon vehicle detection at loop. Gate operation should not
require card access at secure side of pedestal.” Refer to drawing.

Item No. 28 Drawings I001A (TABLE OF PANELS SHEET 1 OF 2)

28.1 Replace entire drawing with the attached revised drawing I001A. Drawing revisions
include the follow:

.1 Change line-item GEN-001 service description from “Generator Enclosure” to


“Standby Generator”. Refer to drawing.

.2 Add “Section 16622” to line-item GEN-001 DWG/Spec detail column. Refer to


drawing.

.3 Add panels GEN-ANUN and GEN-REPO to list of panels. Refer to drawing.

.4 Add JBP-401, JBP-404 and JBP-407 to list of panels. Refer to drawing.

.5 Remove LD-RH-402, LD-RH-403, LD-RH-405, LD-RH-406, LD-RH-408 and LD-


RH-409 from list of panels. Refer to drawing.

.6 Add drawing note bubble 5. Text to read “Junction box complete with EPA series
S/S padlock adapter or approved equivalent compatible with selected panel.
Junction box to include limacoid per item 54 on Bill of Materials (I010A) warning
label. Label to read ‘Disconnect Power Before Opening’.”

.7 Re-arrange table to account for added and removed devices. Refer to drawing.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 21 of 27
November 16, 2023

Item No. 29 Drawings I002A (TABLE OF PANELS SHEET 2 OF 2)

29.1 Replace entire drawing with the attached revised drawing I002A. Drawing revisions
include the follow:

.1 Add RH-401, RH-402, RH-403, RH-404, RH-405, RH-406, RH-407, RH-408, and
RH-409. Refer to drawing.

.2 Re-arrange table to account for added and removed devices. Refer to drawing.

Item No. 30 Drawings I014A (CP-2000 & CP-3000 CONTROL PANEL LAYOUT CONTINUATION)

30.1 Replace entire drawing with the attached revised drawing I014A. Drawing revisions
include the follow:

.1 Re-arrange PLC chassis to account for improved fault tolerances and future
growth.

Item No. 31 Drawings I017A (MISCELLANEOUS CONTROL PANELS AND JUNCTION BOXES)

31.1 Replace entire drawing with the attached revised drawing I017A. Drawing revisions
include the follow:

.1 Change manufacturer from “Hammond” to “Hoffman” for H2OMIT Series Control


Panel Vent. Refer to drawing.

.2 Add Group 22 “Phoenix Contact | UK 6N | Universal terminal block, screw


connection” to table. Refer to drawing.

.3 Add Group 23 “Phoenix Contact | UK 5N | Universal terminal block, screw


connection” to table. Refer to drawing.

.4 Add “Provide auxiliary contact for circuit breaker status 140MT series” to Group 21
Allen Bradley 140 U Series. Refer to drawing.

Item No. 32 Drawings I022A (CONTROL WIRING NOTES AND MISCELLANEOUS LOGIC)

32.1 Replace entire drawing with the attached revised drawing I022A. Drawing revisions
include the follow:

.1 Change “LIT-4029” to “LS-4029” on detail 2/I022A LCP-4019 Wiring logic. Refer


to drawing.

Item No. 33 Drawings I023A (HEATER CONTROL PANEL (HCP) WIRING LOGIC)

33.1 Replace entire drawing with the attached revised drawing I023A. Drawing revisions
include the follow:

.1 Replace detail 1 for improved load balancing and device control. Refer to drawing.

Item No. 34 Drawings E202A (SINGLE LINE DIAGRAM AND PANEL SCHEDULES SHEET 2 OF 2)

34.1 Replace entire drawing with the attached revised drawing E202A. Drawing
revisions include the follow:

.1 Add “HCP-4001” to circuits 43, 45, and 47 on DP-201.

.2 Add “HCP-4004” to circuits 44, 46, and 48 on DP-201.


Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 22 of 27
November 16, 2023

.3 Add “HCP-4007” to circuits 50, 52, and 54 on DP-201.

Item No. 35 Drawings I201A (CONTROL BLOCK DIAGRAM 2 OF 2)

35.1 Replace entire drawing with the attached revised drawing I201A. Drawing revisions
include the follow:

.1 Remove devices LD-RH-402, LD-RH-403, LD-RH-405, LD-RH-406, LD-RH-408,


and LD-RH-409 and associated wiring from control block diagram.

.2 Change wire leader text between LCP-4001 and LD-RH-401 to read “4c #14AWG
RW90 + GND in OCAL Cond.” Refer to drawing.

.3 Change wire leader text between LCP-4004 and LD-RH-404 to read “4c #14AWG
RW90 + GND in OCAL Cond.” Refer to drawing.

.4 Change wire leader text between LCP-4007 and LD-RH-407 to read “4c #14AWG
RW90 + GND in OCAL Cond.” Refer to drawing.

Item No. 36 Drawings I202A (COMPONENT LISTS & IO TABLES – PLC-200)

36.1 Replace entire drawing with the attached revised drawing I202A. Drawing revisions
include the follow:

.1 Re-arrange component list for improved fault tolerances. Refer to drawing.

.2 Re-arrange IO list for improved fault tolerances. Refer to drawing.

Item No. 37 Drawings I203A (IO TABLES – PLC-200 (CON’TD))

37.1 Replace entire drawing with the attached revised drawing I203A. Drawing revisions
include the follow:

.1 Re-arrange IO list for improved fault tolerances. Refer to drawing.

.2 Add “In-Auto” and “Fault” digital inputs for VFC-401, VFC-402, VFC-403, VFC-404,
VFC-409, VFC-410, VFC-411, VFC-412, VFC-413, VFC-414 and VFC-614. Refer
to drawing.

Item No. 38 Drawings I204A (IO TABLES – PLC-200 (CON’TD))

38.1 Replace entire drawing with the attached revised drawing I203A. Drawing revisions
include the follow:

.1 Re-arrange IO list for improved fault tolerances. Refer to drawing.

.2 Add “Run” digital output for LCP-4001, LCP-4004, and LCP-4007. Refer to
drawing.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 23 of 27
November 16, 2023

Item No. 39 Drawings I205A (IO TABLES – PLC-200 (CON’TD))

39.1 Remove the entire drawing from the drawing package.

Item No. 40 Drawings E301A (SINGLE LINE DIAGRAM AND PANEL SCHEDULE)

40.1 Replace entire drawing with the attached revised drawing E301A. Drawing
revisions include the follow:

.1 Move LD-P-728, LD-P-729, LD-MIX-704, LD-MIX-705, LD-LC-608, LD-LC-610,


LD-CC-609, LD-CC-611, LD-P-612, LD-P-613, and all associated wiring, motors,
starters and circuit protectors to Phase B. Mark as “Not in Contract”. Refer to
drawing.

.2 Change wiring leader text on LD-P-715 to read “3c #4 AWG Belden 2950X Series
VFD Cable in 53mm RGS Conduit”. Refer to drawing.

Item No. 41 Drawings E302A (PANEL SCHEDULES)

41.1 Replace entire drawing with the attached revised drawing E302A. Drawing
revisions include the follow:

.1 Move “Travelling Bridge #3 MCP-7025” on circuits 7, 9, and 11 to Phase B. Refer


to drawing.

.2 Move “TX-701 (LP-701)” on circuits 2, 4, and 6 to Phase B. Refer to drawing.

Item No. 42 Drawings I300A (CONTROL BLOCK DIAGRAM)

42.1 Replace entire drawing with the attached revised drawing I300A. Drawing revisions
include the follow:

.1 Add drawing note 7. Note to read “For pricing purposes, contractor to allow for
the wiring indicated. Contractor to coordinate exact wiring requirements with the
generator manufacturer. Refer to E911A for routing. Provide RGS conduit (plus
NEMA 4 painted steel pull boxes) sized to suit inside generator enclosure and
electrical service building to complete routing. Provide direct buried 103mm PVC
conduit outdoors.” Refer to drawing.

.2 Add “GEN-REPO” and “GEN-ANUN” panels and associated wiring to the Electrical
Service Building. Refer to drawing.

.3 Change LD-RH-601 and LD-RH-604 and associated LCPs, HCPs, and wiring to
Phase B. Mark as “Not in Contract”. Refer to drawing.

.4 Change wire leader text between LCP-6001 and LD-RH-601 to read “4c #14AWG
RW90 + GND in OCAL Cond.”. Refer to drawing.

.5 Change wire leader text between LCP-6004 and LD-RH-604 to read “4c #14AWG
RW90 + GND in OCAL Cond.”. Refer to drawing.

.6 Remove LD-RH-602, LD-RH-603, LD-RH-605, LD-RH-606 and all associated


wiring. Refer to drawing.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 24 of 27
November 16, 2023

Item No. 43 Drawings I301A (IO TABLES – PLC-300)

43.1 Replace entire drawing with the attached revised drawing I301A. Drawing revisions
include the follow:

.1 Re-arrange IO list for improved fault tolerances. Refer to drawing.

.2 Move all associated IO with P-612, P-613, P-728, P-729, MIX-704, MIX-705, LC-
608, CC-609, LC-610, CC-611, LCP-6001, and LCP-6004 to Phase B. Mark as
“Not in Contract”. Refer to drawing.

.3 Add drawing note 1. Drawing note to read “N.I.C. – Phase B”. Refer to drawing.

.4 Add “In-Auto” and “Fault” digital inputs to VFC-901, VFC-902, VFC-903, and VFC-
904. Refer to drawing.

Item No. 44 Drawings I302A (IO TABLES CONT’D– PLC-300)

44.1 Replace entire drawing with the attached revised drawing I302A. Drawing revisions
include the follow:

.1 Re-arrange IO list for improved fault tolerances. Refer to drawing.

.2 Add drawing note 2. Drawing note to read “N.I.C. – Phase B. Provide relay for
future I/O, where indicated”. Refer to drawing.

.3 Move all associated IO with P-612, P-613, P-728, P-729, MIX-704, MIX-705, LC-
608, CC-609, LC-610, CC-611, LCP-6001, and LCP-6004 to Phase B. Mark as
“Not in Contract”. Refer to drawing.

Item No. 45 Drawings I303A (COMPONENTS LIST & IO TABLES CONT’D– PLC-300)

45.1 Replace entire drawing with the attached revised drawing I303A. Drawing revisions
include the follow:

.1 Re-arrange component list for improved fault tolerances. Refer to drawing.

.2 Re-arrange IO list for improved fault tolerances. Refer to drawing.

.3 Add drawing note 1. Drawing note to read “N.I.C. – Phase B”. Refer to drawing.

.4 Move all associated IO with P-612, P-613, P-728, P-729, MIX-704, MIX-705, LC-
608, CC-609, LC-610, CC-611, LCP-6001, and LCP-6004 to Phase B. Mark as
“Not in Contract”. Refer to drawing.

Item No. 46 Drawings I410A (POWER AND INSTRUMENTATION PLAN)

46.1 Replace entire drawing with the attached revised drawing I410A. Drawing revisions
include the follow:

.1 Remove LD-RH-402, LD-RH-403, LD-RH-405, LD-RH-406, LD-RH-408, and LD-


RH-409. Refer to drawing.

.2 Add JBP-401, JBP-404, and JBP-407. Refer to drawing.


Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 25 of 27
November 16, 2023

Item No. 47 Drawings I510A (POWER AND INSTRUMENTATION PLAN)

47.1 Replace entire drawing with the attached revised drawing I510A. Drawing revisions
include the follow:

.1 Change AIT-4011, AIT-4012, and AIT-4013 to have a single device and single
element tag instead of two device tags. Refer to drawing.

.2 Add drawing note 8. Drawing note to read “Contractor to allow for heated and
insulated NEMA 4X S/S panel, per group 1 on drawing I017A, complete with
window, to mount the DO analyzer, cleaning kit and any other associated
appurtenances that have an operating temperature that does not conform to the
design low ambient temperature of -30 degrees Celsius, for the site. The panel to
be equipped with R5 foil insulation c/w dual thermostat and heater, per group 15
on drawing I017A. Monitor temperature status via the thermostat and provide
signal wiring via TECK90 in cable tray back to PLC. Provide dedicated circuit in
TECK90 via cable tray for heaters from LP-203, upsize for voltage drop.” Refer to
drawing.

Item No. 48 Drawings I801A (IO TABLES – PLC-800)

48.1 Replace entire drawing with the attached revised drawing I801A. Drawing revisions
include the follow:

.1 Re-arrange IO list for improved fault tolerances. Refer to drawing.

.2 Add “In-Auto” and “Fault” digital inputs for VFC-941 and VFC-820.

Item No. 49 Drawings I802A (COMPONENT LIST & IO TABLES CONT’D – PLC-800)

49.1 Replace entire drawing with the attached revised drawing I802A. Drawing revisions
include the follow:

.1 Re-arrange component list for improved fault tolerances. Refer to drawing.

.5 Re-arrange IO list for improved fault tolerances. Refer to drawing.

Item No. 50 Drawings E911A (GROUND FLOOR HOUSE SERVICES PLAN)

50.1 Replace entire drawing with the attached revised drawing E911A. Drawing
revisions include the follow:

.1 Add “GEN-REPO” and “GEN-ANUN” panels to electrical service building. Refer to


drawing.

.2 Add a 103mm PVC conduit extending between Electrical Service Building and
Generator Enclosure. Refer to drawing.

.3 Change scale on detail 1/E911A from “1:75” to “As Indicated”.

.4 Add drawing note 7. Drawing note to read “For pricing purposes, contractor to
allow for the wiring indicated on drawing I300A. Contractor to coordinate exact
wiring requirements with generator manufacturer. Provide RGS conduit (plus
NEMA 4 painted steel pull boxes) sized to suit inside generator enclosure and
electrical service building to complete routing. Provide direct buried 103mm PVC
conduit outdoors.” Refer to drawing.
Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 26 of 27
November 16, 2023

Item No. 51 Drawings I901A (COMPONENT LIST & IO TABLE – PLC-900)

51.1 Replace entire drawing with the attached revised drawing I901A. Drawing revisions
include the follow:

.1 Re-arrange component list for improved fault tolerances. Refer to drawing.

.2 Re-arrange IO list for improved fault tolerances. Refer to drawing.

ATTACHMENTS
The following documents are attached at the end of this Addendum:

• Revised Drawings:
o PID401A
o PID402A
o PID403A
o PID601A
o PID803A
o MID001A
o MID002A
o MID301A
o ME002A
o DE004A
o E002A
o E008A
o I001A
o I002A
o I014A
o I017A
o I022A
o I023A
o E202A
o I201A
o I202A
o I203A
o I204A
o E301A
o E302A
o I300A
o I301A
o I302A
o I303A
o I410A
o I510A
o I801A
o I802A
o E911A
o I901A

END OF ADDENDUM NO. 3


Kemptville Water Pollution Control JLR No.: 29475-000.1
Plant Expansion – Phase A Owner No.: NG23-44
ADDENDUM NO. 3
Page 27 of 27
November 16, 2023

Mike Finley, P.Eng.


Director of Public Works & Environmental Services
Municipality of North Grenville

cc: All Plan Takers

Addenda to Date:
Addendum 1 October 17, 2023
Addendum 2 November 3, 2023
Addendum 3
Addendum 4
Addendum 5
ENET
PLC-200
O 600 VAC M
FVNR TYPE 13 LD-P-403
PLC-200 GLOBAL-1000

MCC-200 NE DE ATERING AND ELECTRICAL SERVICE


DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
LI 800 SERIES
NE AERATION NE PRIMARY NE
TAN S CLARIFIERS HEAD OR S
LCP-4010 UN ATERING UN 500 SERIES 400 SERIES 200 SERIES
GLOBAL-1000
AI
PRIMARY CLARIFIER 1 2 100-SS-UN 100-DI-UN P2 16 PID202A
CONTROL PANEL TO GRIT DISCHARGE CHANNEL
Y GLOBAL-1000
VC-406 NE TERTIARY
CC-401 LC-401 LC-402 NE SECONDARY
CLARIFIERS FILTER BUILDING
GLOBAL-1000 GLOBAL-1000 GLOBAL-1000

100-SS-PSD 700 SERIES PHASE B


ALARM 600 SERIES PHASE B
FAULT FAULT FAULT ENET PLC-200
DEVICE

YA
DEVICE DEVICE
PLC-200 GLOBAL

PRIMARY SLUDGE PSD


YA YA M
P-401 P-402 ENET
DEVICE

LSL
DEVICE

LIT
RAD GLOBAL

M VFC-404 F YA 50-SS-PSD NA NA
AMBER AMBER AMBER PLC-200 GLOBAL-1000 GLOBAL-1000

PLC-200
G H TYPE 14 M 4030 4015 P-403
1000
1000

DEVICE
TO SAMPLE SIN E ISTING SERVICE
RUNNING RUNNING RUNNING DEVICE DEVICE TC DI BUILDING
DEVICE

SI SI 300 SERIES
YS
DEVICE

YS YS
DEVICE

FI TYPE 14 LD-LC-401 4030


GLOBAL-1000 ELEMENT
RAD VC-405
600 VAC 600 VAC LE GLOBAL-1000 PRIMARY SLUDGE PSD
GREEN GREEN GREEN AI FVNR C 6 4015
FVNR 75-DIG-SCM 100-DIG-PSD 100-SS-PSD 100-SS-PSD P8 2 PID801A
E
STOPPED STOPPED STOPPED FAULT FAULT MCC-200 MCC-200 ALARM SCUM
DEVICE

VF-414 TO DIGESTER
EY PLAN
DEVICE DEVICE

PLC-200
DEVICE DEVICE

YS YS YS GLOBAL-1000
DEVICE
MAG YA YA CROSS COLLECTOR LONGITUDINAL SLUDGE PUMP
FIT FAULT IN-AUTO RUNNING RUN SPEED SPEED REF DISC OPEN
COLLECTOR
RED
HOA
RED RED 4010 AMBER AMBER
M
GLOBAL GLOBAL

M
DEVICE
SA
PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200
LEGEND
HOA HOA RUNNING RUNNING MS
DEVICE
DEVICE DEVICE
LD-CC-401 CC-401 LC-401 4023 YA HS YS YC SI SC YA
HS DI
DEVICE DEVICE

HS HS MAG YS YS GLOBAL-1000
1000 1000

NOT IN CONTRACT N I C -
3 3
ELEMENT

FE LCP-4011
M 4010
GLOBAL-1000

DI DI DI DO AI AO DI
GREEN GREEN PRIMARY SLUDGE PUMP
VF-413 1 2 LOCAL CONTROL A PHASE B SCOPE NOT IN
STOPPED STOPPED
CONTRACT N I C -
GLOBAL-1000

DEVICE DEVICE
PANEL
YS YS
VF-412 RH-401
GLOBAL-1000

RED RED GLOBAL-1000


HG-401 GLOBAL-1000

FAULT IN-AUTO RUNNING RUN SPEED SPEED REF DISC OPEN


PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200
75-SS-PSD HOA HOA
DEVICE

HS HS
DEVICE
P
N YA HS YS YC SI SC YA

DI DI DI DO AI AO DI
POT POT
DEVICE

HR HR
DEVICE

GLOBAL-1000
HG-402 GLOBAL-1000
RH-402 B
PRIMARY PRIMARY EFFLUENT EFF1
RA SE AGE RSE
CLARIFIER
TABLE OF LOCATIONS
P4 8 PID402A
P4 1 PID401A 500-SS-RSE
TAN 1 TO AERATION TAN S
FROM GRIT TAN S
FAULT IN-AUTO OPEN CLOSE OPENED CLOSED
VF-424 HG-403 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200
GLOBAL-1000
GLOBAL-1000

GLOBAL-1000
RH-403
LCP-4001 150-SS- AS
PRIMARY CLARIFIER 1
GLOBAL-1000

YA HS C C SO SC
SCUM HEATERS R
ENET VF-401
LOCAL CONTROL PANEL GLOBAL-1000
DI DI DO DO DI DI
PLC-200
RUNNING
GLOBAL OOD BAFFLE C PRIMARY CLARIFIER 1
GLOBAL-1000
LCP-4004
M
DEVICE

YS
P GLOBAL-1000
LD-P-401 TYPE 70 C VFC-401
1000
FAULT
PLC-200
IN-AUTO
PLC-200
OPEN
PLC-200
CLOSE
PLC-200
OPENED
PLC-200
CLOSED
PLC-200
SCUM HEATERS
600 VAC LOCAL CONTROL PANEL
GREEN VFD A ENET YA HS C C SO SC
HOA MCC-200 RUNNING
PLC-200 DEVICE

I
DEVICE

ENET YS
HS
DI DI DO DO DI DI S
100-SS-PSD

100-SS-PSD
PLC-200
100-SS-UN

R
GLOBAL

M LD-CC-402
GLOBAL-1000
TYPE 14 600 VAC TIPPING TROUGH
SCUM COLLECTOR
D GREEN
600 VAC FVNR ALARM
P-401
1000

FVNR MCC-200
TYPE 14
LD-LC-402 PLC-200 FAULT IN-AUTO OPEN CLOSE OPENED CLOSED HOA
DEVICE

HS
T
GLOBAL-1000
PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200
VF-408 MCC-200 TIPPING TROUGH
VF-404
GLOBAL-1000

SA
GLOBAL-1000

CROSS COLLECTOR M
GLOBAL GLOBAL

M
DEVICE

MS LONGITUDINAL SLUDGE
SCUM COLLECTOR YA HS C C SO SC U
IN-AUTO RUNNING DISC OPEN RUN CC-402 LC-402 4024 DI
1000 1000
COLLECTOR
PLC-200 PLC-200 PLC-200 PLC-200 3 3 DI DI DO DO DI DI
PRIMARY
SLUDGE PUMP 1 HG-410 E
HS YS YA YC GLOBAL-1000

FAULT IN-AUTO OPEN CLOSE OPENED CLOSED


PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 1 PHASE A - ADDENDUM 3 10 11 23
DI DI DI DO RH-404
VF-410 VF-406 HG-404 GLOBAL-1000
IN-AUTO RUNNING DISC OPEN RUN
GLOBAL-1000 GLOBAL-1000
GLOBAL-1000
YA HS C C SO SC PLC-200 PLC-200 PLC-200 PLC-200 0 PHASE A ISSUED FOR TENDER 02 10 23

S DI DI DO DO DI DI HS YS YA YC N ISSUE REVISION DD MM YY
1
F T
DI DI DI DO

HG-405 GLOBAL-1000
RH-405 1 1 L R A L
GLOBAL-1000

PRIMARY PRIMARY EFFLUENT EFF1 VERIFY SHEET SI E AND SCALES BAR TO THE
RA SE AGE RSE
CLARIFIER
TABLE OF LOCATIONS

T P4 9 PID402A RIGHT IS 25 IF THIS IS A FULL SI E DRA ING 0 25


P4 2 PID401A 500-SS-RSE
TAN 2 TO AERATION TAN S SCALE
NTS
FROM GRIT TAN S FAULT IN-AUTO RUNNING RUN DISC OPEN
PLC-200 PLC-200 PLC-200 PLC-200 PLC-200
LCP-4020 HG-406 LCP-4013
GLOBAL-1000
VF-425 GLOBAL-1000
RH-406 GLOBAL-1000

PRIMARY CLARIFIER 2 3
GLOBAL-1000 GLOBAL-1000

YA YA YS YC YS PRIMARY CLARIFIER SCUM PIT AND


150-SS- AS
CONTROL PANEL PEP PUMPS CONTROL PANEL CLIENT

CC-403 LC-403 CC-402


U DI DI DI DO DI
VF-402
G
100-SS-PSD

GLOBAL-1000 GLOBAL-1000 GLOBAL-1000


GLOBAL-1000
100-SS-UN

DEVICE

LI
FAULT FAULT FAULT OOD BAFFLE SCUM PUMP AND
DEVICE DEVICE DEVICE
FAULT IN-AUTO RUNNING RUN DISC OPEN
YA YA YA GLOBAL

PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 RECIRCULATION


M
D P-403 VALVE SYSTEM
100-SS-PSD

VF-407 VFC-402
AMBER AMBER AMBER GLOBAL-1000 1000
GLOBAL-1000

START COMMAND
YA YA YS YC YS FAULT
RUNNING RUNNING RUNNING ENET ENET RUN CMD
DEVICE DEVICE DEVICE
GLOBAL
DEVICE
CONSULTANT
YS YS YS VF-411 M PLC-200 PLC-200 YA PB
DEVICE

DI DI DI DO DI HS
GLOBAL-1000

P-402 600 VAC


L O
H
1000

GREEN GREEN GREEN FVNR TYPE 14 AMBER


LD-CC-403 TYPE 14
STOPPED STOPPED STOPPED VF-405 GLOBAL-1000 MCC-200 RUNNING VFC-404
DEVICE DEVICE DEVICE GLOBAL-1000
600 VAC ALARM FAULT IN-AUTO RUNNING RUN DISC OPEN DEVICE
GLOBAL-1000

YS
YS YS YS
GLOBAL-1000
VF-409 FVNR PLC-200
TIPPING TROUGH
PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 Y RECIRCULATING
MCC-200
DEVICE

RED RED RED LD-LC-403 SCUM COLLECTOR GREEN YS


SA YA YA YS YC YS
150-SS- AS

PRIMARY CROSS COLLECTOR GLOBAL GLOBAL


GLOBAL-1000

LONGITUDINAL SLUDGE STOPPED


HOA HOA HOA
DEVICE

DEVICE DEVICE DEVICE


SLUDGE PUMP 2 M M MS DEVICE CLEAR CONSULTANT
HS HS HS CC-403 LC-403 4025 COLLECTOR YS
150-DI-UN

DI DI DI DI DO DI
DISCHARGING
1000 1000

3 3
ENET
HG-411 I RED
DEVICE

YS
PLC-200
B GLOBAL-1000

HOA
DEVICE
CLEAR
LD-P-402 TYPE 70 HS
GLOBAL-1000
DISCHARGE RECIRCULATE START
600 VAC RH-407 PLC-200 PLC-200 PLC-200
HG-407 GLOBAL-1000

VFD
MCC-200
N GLOBAL-1000

SO SC HS
PROCESS AIR PA
V PROFESSIONAL STAMP PRO ECT NORTH

P2 3 PID403A 100-SS-PA DO DO DI
FROM BLO ERS
HG-408 GLOBAL-1000
RH-408
GLOBAL-1000

PRIMARY PRIMARY EFFLUENT EFF1


4-P

RA SE AGE RSE
CLARIFIER
TABLE OF LOCATIONS
P4 10 PID402A
P4 3 PID401A 500-SS-RSE
TAN 3 TO AERATION TAN S
FAULT IN-AUTO RUNNING RUN DISC OPEN
FROM GRIT TAN S PLC-200 PLC-200 PLC-200 PLC-200 PLC-200
HG-409
3-P

GLOBAL-1000
RH-409 LCP-4007
YA YA YS YC YS
GLOBAL-1000

PRIMARY CLARIFIER 1
GLOBAL-1000

150-SS- AS PRO ECT


SCUM HEATERS
VF-426 DI DI DI DO DI LOCAL CONTROL PANEL
MUNICIPALITY OF NORTH
D

GLOBAL-1000

GRENVILLE - ATER POLLUTION


1 RUNNING
GLOBAL-1000
VF-403 FAULT IN-AUTO RUNNING RUN DISC OPEN
DEVICE

YS
V CONTROL PLANT E PANSION
150-SS- AS

PLC-200 PLC-200 PLC-200 PLC-200 PLC-200


PCP E

OPEN CLOSE OPENED CLOSED IN AUTO FAULT


PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 GLOBAL
GREEN PHASE - A
M
E VFC-403
YA YA YS YC YS HOA
DEVICE
EMPTVILLE ONTARIO
C C SO SC HS YA 1000

RADIANT SCUM HEATER TO BE INSTALLED HS


OOD BAFFLE DI DI DI DO DI DRA ING
COORDINATE MOUNTING DETAILS ITH
PROCESS INSTRUMENTATION

14 2023 9 49 49 AM
DO DO DI DI DI DI E UIPMENT SUPPLIER TYPICAL OF 3
HEATERS PER CLARIFIER TAN
PRIMARY CLARIFIERS
P 29000 29475-000 -

RETURN ACTIVATED SLUDGE RAS


P4 5 PID601A 200-SS-RAS IN-AUTO RUNNING DISC OPEN RUN
PLC-200 PLC-200 PLC-200 PLC-200
FROM ACTIVATED SLUDGE PUMPS
M
GLOBAL

LO OIL 1 PRIMARY CLARIFIERS


VFC-614 FAULT IN-AUTO RUNNING RUN DISC OPEN FAULT IN-AUTO RUNNING RUN DISC OPEN ALARM HS YS YA YC
1000
PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200
DI DI DI DO
UN ATERING UN YA YA YS YC YS YA HS YS YC YS YA DESIGN
C

N
P4 6 PID402A 150-DI-UN
RETURN ACTIVATED SLUDGE RAS DRA N DRA ING
DI DI DI DO DI DI DI DI DO DI DI R

PLOT DATE
FROM AERATION TAN S
P4 11 PID402A
L M CHEC ED
TP
PID401A
L

TO AERATION TAN S
LR
29475
F
NE DE ATE ING AND ELECT ICAL E VICE
DIGE TE CONT OL ENT ANCE B ILDING
B ILDING 900 E IE
800 E IE
NE AE ATION NE IMA NE
TAN CLA IFIE HEAD O
500 E IE 400 E IE 200 E IE

NE ECONDA NE TE TIA
CLA IFIE FILTE B ILDING
600 E IE HA E B 700 E IE HA E B

OCE AI A
300- - A 300- - A 62 ID601A
TO FINAL CLA IFIE
E I TING E VICE
B ILDING
300 E IE

IMA EFFL ENT EFF1


4 12 ID403A
DO LC-200 TO E ALI ATION ET ELL
DEVICE
E LAN
AIT
4011 AI
LEGEND
AI
HG-501 HG-504
GLOBAL-1000 GLOBAL-1000
NOT IN CONT ACT N I C -
AE ATION TAN 1 ELEMENT
DO MI ED LI O ML
AE
FINE B BBLE TABLE OF LOCATION

4011 800-HD E-ML 61 ID601A HA E B CO E NOT IN


DIFF E G ID TO FINAL CLA IFIE CONT ACT N I C -

GLOBAL-1000
HG-502 GLOBAL-1000
HG-505
IMA EFFL ENT EFF1
48 ID401A
F OM IMA CLA IFIE AE ATION IN IDE I E

GLOBAL-1000
HG-503 GLOBAL-1000
HG-506
1

VF-507

- A
GLOBAL-1000

100- - A

300-
O ITION O ITION
FA LT IN-A TO O ENED CLO ED FEEDBAC COMMAND
LC-200 LC-200 LC-200 LC-200 LC-200 LC-200

- A
LABOLG
LABOLG

150-DI- N
GLOBAL-1000
VF-501 M M
VFC-409
0001
VFC-410
0001

50 I E A H O C I C

200-
1
GLOBAL-1000
VF-511 GLOBAL-1000
VF-513 AND BALL
VALVE T DI DI DI DI AI AO
200- - A 6 LOCATION A
LC-200

AI
A B FA LT IN-A TO O ENED
O ITION O ITION
CLO ED FEEDBAC COMMAND
DO AI LC-200 LC-200 LC-200 LC-200 LC-200 LC-200
DEVICE

AIT
HG-519 4012
GLOBAL-1000
A H O C I C

DI DI DI DI AI AO
HG-507 HG-510
GLOBAL-1000 GLOBAL-1000
B
AE ATION TAN 2 ELEMENT
DO
AE
FINE B BBLE TABLE OF LOCATION

4012
DIFF E G ID 1 HA E A - ADDEND M 3 10 11 23
O ITION O ITION
FA LT IN-A TO O ENED CLO ED FEEDBAC COMMAND
HG-508 HG-511 LC-200 LC-200 LC-200 LC-200 LC-200 LC-200 0 HA E A I ED FO TENDE 02 10 23
GLOBAL-1000 GLOBAL-1000

IMA EFFL ENT EFF1 N I E EVI ION DD MM


A H O C I C
49 ID401A
F OM IMA CLA IFIE DI DI DI DI AI AO T

C L A L
GLOBAL-1000
HG-509 GLOBAL-1000
HG-512
1 VE IF HEET I E AND CALE BA TO THE
IGHT I 25 IF THI I A F LL I E D A ING 0 25
O ITION O ITION CALE
VF-508 NT
GLOBAL-1000 FA LT IN-A TO O ENED CLO ED FEEDBAC COMMAND
100- - A LC-200 LC-200 LC-200 LC-200 LC-200 LC-200

A H O C I C
CLIENT

- A
VF-502 LABOLG GLOBAL

150-DI- N
GLOBAL-1000 M M DI DI DI DI AI AO
VFC-411 VFC-412
0001 1000

150-
1
GLOBAL-1000
VF-515 GLOBAL-1000
VF-517

200- - A 200- - A
O ITION O ITION
LC-200 FA LT IN-A TO O ENED CLO ED FEEDBAC COMMAND CON LTANT
HG-520
- A

GLOBAL-1000 LC-200 LC-200 LC-200 LC-200 LC-200 LC-200


AI
C D
200-

A H O C I C

DO AI
DEVICE
DI DI DI DI AI AO
AIT
4013 E
CON LTANT
HG-513 HG-516
- A

GLOBAL-1000 GLOBAL-1000

AE ATION TAN 3 ELEMENT


DO O ITION O ITION
AE FA LT IN-A TO O ENED CLO ED FEEDBAC COMMAND
300-

FINE B BBLE TABLE OF LOCATION

4013 LC-200 LC-200 LC-200 LC-200 LC-200 LC-200


DIFF E G ID
A H O C I C
HG-514 HG-517
DI DI DI DI AI AO
GLOBAL-1000 GLOBAL-1000

OFE IONAL TAM O ECT NO TH


IMA EFFL ENT EFF1
4 10 ID401A
F
F OM IMA CLA IFIE 1

GLOBAL-1000
HG-515 GLOBAL-1000
HG-518
1
4-

GLOBAL-1000
VF-509
100- - A
3-

O ECT

M NICI ALIT OF NO TH
- A

LABOLG GLOBAL

VF-503 M M
150-DI- N
D

GLOBAL-1000

VFC-413 VFC-414
0001 1000

G ENVILLE - ATE OLL TION


100-

1
VF-519 VF-521
GLOBAL-1000
GLOBAL-1000

CONT OL LANT E AN ION


C E

200- - A 200- - A HA E - A
ET N ACTIVATED L DGE A EM TVILLE ONTA IO
50- -D
4 11 ID401A 200- - A
D A ING
TO AE ATION TAN

14 2023 10 45 05 AM
E F OCE IN T MENTATION
OCE AI A
47 ID403A IMA CLA IFIE
29000 29475-000 -

F OM BLO E BF
AE ATION TAN
N ATE ING N
46 ID401A
TO IMA TAN DE IGN
T

N
D A N D A ING

LOT DATE
CHEC ED
C
ID402A
L

L
29475
F
ODOUR CONTROL ODR

NE DE ATERING AND ELECTRICAL SERVICE


REFER TO PID203 FOR DIGESTER CONTROL ENTRANCE BUILDING
ODOUR CONTROL PID BUILDING 900 SERIES
800 SERIES
NE AERATION NE PRIMARY NE
2 TAN S CLARIFIERS HEAD OR S
500 SERIES 400 SERIES 200 SERIES

NE SECONDARY NE TERTIARY
CLARIFIERS FILTER BUILDING
600 SERIES PHASE B 700 SERIES PHASE B

E UALI ATION
TABLE OF LOCATIONS
E UALI ATION
TABLE OF LOCATIONS
E ISTING SERVICE
BUILDING
TAN 1 TAN 2 300 SERIES

300-SS-OF
BF EY PLAN
PRIMARY EFFLUENT EFF1
300-HDPE-EFF1 300-HDPE-EFF1 P2 18 PID202A
LEGEND
OVERFLO OF
300-HDPE-OF 300-HDPE-OF P2 20 PID202A NOT IN CONTRACT N I C -
300-HDPE-EFF1 300-HDPE-EFF1
PHASE B SCOPE NOT IN
BF BF PRIMARY EFFLUENT EFF1 CONTRACT N I C -
300-HDPE-EFF1 300-HDPE-EFF1 P2 19 PID202A

300-SS-EFF1 4 4 300-SS-EFF1
200-SS-EFF1 FC FC
BF
4
GLOBAL-1000
VF-421 GLOBAL-1000
VF-420 GLOBAL-1000
VF-422 VF-423
GLOBAL-1000

FC

E
300-SSS-EFF1 M 300-SS-EFF1
VF-418 VF-419 DR
GLOBAL-1000
VF-415 GLOBAL-1000
VF-416 GLOBAL-1000
VF-417 GLOBAL-1000
GLOBAL-1000

BF
VC-401 VC-402 VC-403
GLOBAL-1000 GLOBAL-1000 GLOBAL-1000
200-SS-EFF1

PRIMARY EFF1
P4 12 PID402A
FROM PRIMARY CLARIFIERS REMOVED FROM SCOPE

E UALI ATION ET THIS DESIGN HAS BEEN REMOVED FROM


TABLE OF LOCATIONS

ELL CONTRACT 29475-000

50-SS-EFF1
1
1 FUTURE E UALI ATION PUMPING STATION PID
PID403A SCALE NTS
100-SS-PA PROCESS AIR PA
300-SS-PA
P2 21 PID202A
LCP-5000 TO HEAD OR S CHANNELS
GLOBAL-1000

DEVICE PROCESS AIR PA 1 PHASE A - ADDENDUM 3 10/11/23


PI BLO ER CONTROL PANEL
P4 7 PID402A
ENET
GLOBAL GLOBAL

M TI 0 PHASE A ISSUED FOR TENDER 02/10/23


E BL-501
1000 1000
GLOBAL-1000
BL-501 GLOBAL-1000
BL-502 GLOBAL-1000
BL-503
PLC-200 TO AERATION TAN S FINAL TAN S

OUTSIDE AIR OA 250-SS-PA PLC-200


DEVICE

SI
DEVICE

SI
DEVICE

SI
E TYPE 70 FAULT IN-AUTO RUNNING RUN SPEED SPEED REF DISC OPEN
N ISSUE / REVISION DD/MM/YY

N/A N/A 250-SS-OA 150-SS-OA PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200
VF-504 T
GLOBAL-1000
PI LD-BL-501
NE PROCESS AIR GLOBAL-1000
YA HS YS YC SI SC YA
BLO ER 1 FAULT FAULT FAULT 600 VAC L R A L
AI DEVICE DEVICE DEVICE

C 6
YA YA YA VFD DI DI DI DO AI AO DI VERIFY SHEET SI E AND SCALES BAR TO THE
DP-201 RIGHT IS 25 IF THIS IS A FULL SI E DRA ING
DEVICE
AMBER AMBER AMBER 0 25
PI DEVICE

PIT RUNNING RUNNING RUNNING ENET SCALE


GLOBAL GLOBAL
NTS
M TI 5010
F PLC-200
DEVICE DEVICE DEVICE

BL-502 ELEMENT
YS YS YS
1000 1000
PE
5010 GREEN GREEN GREEN
F TYPE 70 FAULT IN-AUTO RUNNING RUN SPEED SPEED REF DISC OPEN
OUTSIDE AIR OA 250-SS-PA PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200
N/A N/A 250-SS-OA 150-SS-OA STOPPED STOPPED STOPPED CLIENT
VF-505
DEVICE DEVICE DEVICE

YS YS YS LD-BL-502
YA HS YS YC SI SC YA
GLOBAL-1000
GLOBAL-1000

NE PROCESS AIR 600 VAC


BLO ER 2 RED RED RED C 6
300-SS-PA

VFD DI DI DI DO AI AO DI
HOA HOA HOA DP-201
DEVICE DEVICE DEVICE

DEVICE
HS HS HS
PI ENET
GLOBAL

M
GLOBAL

TI PLC-200
G BL-503
1000 1000
POT
DEVICE
POT
DEVICE
POT
DEVICE G CONSULTANT
HR HR HR TYPE 70 FAULT IN-AUTO RUNNING RUN SPEED SPEED REF DISC OPEN
OUTSIDE AIR OA 250-SS-PA PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200 PLC-200
N/A N/A 250-SS-OA 150-SS-OA
VF-506 LD-BL-503
GLOBAL-1000
GLOBAL-1000
YA HS YS YC SI SC YA
NE PROCESS AIR 600 VAC
C 6
BLO ER 3 VFD DI DI DI DO AI AO DI
DP-201
FAULT IN-AUTO OPENED CLOSED OPEN CLOSE
PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800
CONSULTANT
HIGH LEVEL LO LEVEL 1 PROCESS AIR PA
PLC-800 PLC-800 PLC-800 YA HS SO SC C C 100-SS-PA P4 3 PID401A
TO PRIMARY CLARIFIERS INLET CHANNEL
LAH LAL LI GLOBAL
DI DI DI DI DO DO
M
DI DI AI VFC-941
1000
2 BLO ER SYSTEM PID
PID403A SCALE NTS
50-PVC-FST
VENT PROFESSIONAL STAMP PRO ECT NORTH
100-PVC-VNT N/A N/A
L TO ATMOSPHERE
15-PVC-FST
ALL FERRIC SULFATE PIPING
1
TO HAVE SECONDARY
15-PVC-FST ALARM CONTAINMENT
4-P

U/S RAD FERRIC SULFATE FST


DEVICE

LS
DEVICE

LIT PLC-800
FERRIC SULFATE FST VF-901
GLOBAL-1000
4029 4026 P6 3 PID601A
N/A N/A 75-PVC-FST DEVICE GLOBAL VPR-901
100-PVC-FST LSH M GLOBAL-1000
LAH TO IN ECTION POINT
FROM BUL TRUC 4023 P-408 1000

VPC-901 DI
3-P

UIC DISCONNECT GLOBAL-1000

RED SECONDARY 15-PVC-FST 25-PVC-FST PRO ECT


ELEMENT
U/S ELEMENT
RAD
LE
MUNICIPALITY OF NORTH
DEVICE

LA LE CONTAINMENT
FLOOD 4029 4026 FERRIC SULFATE
D

LCP-4019 DEVICE

LSH
GLOBAL-1000

FERRIC LOCAL CONTROL


ALARM
PLC-800
ALARM
PLC-800
PUMP 1
SECONDARY DR 4022 GRENVILLE - ATER POLLUTION
PANEL AMBER
DEVICE

LS
TH-901 CONTAINMENT F D/REV FAULT LEA IN-AUTO RUNNING RUN SPEED SPEED REF CONTROL PLANT E PANSION
PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800
GLOBAL-1000

LAH LAH
PCP E

15-PVC-FST
PHASE - A
DI DI YC YA YA HS YS YC SI SC EMPTVILLE ONTARIO
HORN
DEVICE DEVICE FERRIC SULFATE
LI LA TABLE OF LOCATIONS

STORAGE TAN DO DI DI DI DI DO AI AO DRA ING

PROCESS INSTRUMENTATION

14 2023 9 58 08 AM
DEVICE
CAP VPR-902
LSH M
GLOBAL
GLOBAL-1000

4021 DR P-409 F D/REV FAULT LEA IN-AUTO RUNNING RUN SPEED SPEED REF PRIMARY CLARIFIERS
P 29000 29475-000 -

VPC-902 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800


1000

HORN LEVEL LEVEL


GLOBAL-1000
E UALI ATION TAN S PROCESS
SILENCE
PLC-800
ALARM
PLC-800
ARNING
PLC-800
15-PVC-FST YC YA YA HS YS YC SI SC AIR COAGULANT DOSING
L FERRIC SULFATE DO DI DI DI DI DO AI AO SYSTEM
YC YC YC PUMP 2
SECONDARY DR
1 DESIGN
DO DO DO
CONTAINMENT C

N
3 FERRIC SULFATE PID DRA N
R DRA ING

PLOT DATE
15-PVC-FST PID403A SCALE NTS CHEC ED
TP
PID403A
L

LR
29475
F
ENET ENET
PLC-300 PLC-300
FAULT IN-AUTO RUNNING RUN DISC OPEN
NOTES
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 TYPE 14 TYPE 14
1 NOT ALL COMPONENTS ARE SHOWN FOR E ISTING
A C SYSTEMS FOR FULL DETAIL ON E ISTING SYSTEMS NEW DEWATERING AND
DIGESTER CONTROL
ELECTRICAL SERVICE
ENTRANCE BUILDING
YA HS YS YC YA REFER TO 1991 DRAWINGS BY GORE STORRIE BUILDING 900 SERIES
LIMITED 800 SERIES
NEW AERATION NEW PRIMARY NEW
DI DI DI DO DI 600 VAC 600 VAC FAULT IN-AUTO RUNNING RUN DISC OPEN TAN S CLARIFIERS HEADWOR S
500 SERIES 400 SERIES 200 SERIES
ALARM PLC-300 PLC-300 PLC-300 PLC-300 PLC-300
1 FVNR PLC-700 FVNR
MCC-300 MCC-300
YA HS YS YC YA
LD-LC-608 SA LD-CC-609 NEW SECONDARY NEW TERTIARY
GLOBAL
DEVICE
0001-LABOLG GLOBAL 0001-LABOLG

CLARIFIERS FILTER BUILDING


M MS M DI DI DI DO DI 600 SERIES PHASE B 700 SERIES PHASE B
MI ED LI UOR ML LC-608 6012 LONGITUDINAL SLUDGE DI CC-609
TIPPING TROUGH 1000 1000

SCUM SCM
P6 1 PID402A 800-HDPE-ML SCUM COLLECTOR COLLECTOR
200-DIG-SCM P7 1 PID701A
FROM AERATION TAN S
TIMBER BAFFLE CROSS COLLECTOR
SECONDARY CLARIFIER 4 TABLE OF LOCATIONS

E ISTING SERVICE
BUILDING
PROCESS AIR PA 300 SERIES
P6 2 PID402A 300-SS-PA
FROM BLOWERS 25-SS-DR RH-606
FERRIC SULFATE FST GLOBAL-1000
HG-608 GLOBAL-1000

EY PLAN
P6 3 PID403A
FROM FERRIC SULFATE PUMPS
L
SECONDARY LEGEND
CONTAINMENT N I C PHASE B
LCP-6010 NOT IN CONTRACT N I C -
GLOBAL-1000

HG-605 HG-607 RH-605


FINAL CLARIFIER GLOBAL-1000 GLOBAL-1000
GLOBAL-1000

LONGITUDINAL COLLECTOR LCP-6001 PHASE B SCOPE NOT IN


FINAL CLARIFIER 3
GLOBAL-1000

WSC

WSC

WSC

WSC

WSC

WSC
LOCAL CONTROL PANEL CONTRACT N I C -
SCUM HEATERS
LC-608 LC-610 LOCAL CONTROL PANEL

GLOBAL-1000

GLOBAL-1000

GLOBAL-1000

GLOBAL-1000

GLOBAL-1000

GLOBAL-1000
GLOBAL-1000
GLOBAL-1000

A FAULT FAULT RUNNING


TP OVERFLOW OF
DEVICE
DEVICE
DEVICE
450-SS-OF P7 3 PID701A
YA YA YS HG-606
G GLOBAL-1000
GLOBAL-1000
RH-604

AMBER AMBER GREEN

B RUNNING
DEVICE
RUNNING
DEVICE
HOA
DEVICE H PLC-700
YS YS HS
BF
GREEN
STOPPED
GREEN
STOPPED
I LI
DEVICE DEVICE
RADIANT SCUM HEATER TO
YS YS BE INSTALLED COORDINATE WSC U/S AI
GLOBAL-1000
ELEMENT U/S DEVICE
SECONDARY EFFLUENT EFF 2
IN-AUTO RUNNING DISC OPEN RUN MOUNTING DETAILS WITH LE LIT
RED RED 6014 6014 P7 2 PID701A
PLC-300 PLC-300 PLC-300 PLC-300 E UIPMENT SUPPLIER GLOBAL-1000

HOA HOA TYPICAL OF 3 HEATERS PER WSC TO FLASH MI ER 2


DEVICE DEVICE

HS HS HS YS YA YC CLARIFIER TAN
HG-604 RH-603
DI DI DI DO TP GLOBAL-1000

GLOBAL-1000

RETURN ACTIVATED SLUDGE RAS


P4 5 PID401A
LCP-6011
I TO AERATION TAN S
GLOBAL-1000

FINAL CLARIFIER
CROSS COLLECTOR LCP-6004 OVERFLOW OF
FINAL CLARIFIER 3
GLOBAL-1000

LOCAL CONTROL PANEL BF HG-601 HG-603 450-SS-OF P7 4 PID701A


SCUM HEATERS GLOBAL-1000 GLOBAL-1000

RH-602
CC-609 LOCAL CONTROL PANEL

0001-LABOLG

0001-LABOLG

0001-LABOLG

0001-LABOLG

0001-LABOLG

0001-LABOLG
GLOBAL-1000
200-SS-PA

GLOBAL-1000

WSC

WSC

WSC

WSC

WSC

WSC
FAULT
DEVICE
RUNNING
DEVICE
H M
UNWATERING UNW
P2 15 PID202A
YA YS

150-DI-RAS

150-DI-RAS
BF TO PRIMARY CLARIFIER INLET
AMBER GREEN FUTURE RETURN
HG-602
RUNNING
GLOBAL-1000
ACTIVATED SLUDGE
HOA RH-601
DEVICE DEVICE

YS HS GLOBAL-1000

BF PLC-300
G F MAG
GREEN
STOPPED
L GLOBAL-1000
VF-603 DEVICE

FIT
FI
BF 6010
DEVICE

VF-601 ELEMENT MAG


YS GLOBAL
FE
GLOBAL-1000

M AI 1 PHASE A - ADDENDUM 3 10/11/23


IN-AUTO RUNNING DISC OPEN RUN
ELEMENT
6010
ALARM P-613 PI
RED PLC-300 PLC-300 PLC-300 PLC-300
ELEMENT 1000

PLC-700 VF-604 PI VF-608


HOA GLOBAL-1000 GLOBAL-1000
GLOBAL-1000
VF-612 VF-614 0 PHASE A ISSUED FOR TENDER 02/10/23
GLOBAL-1000
DEVICE

HS M
HS YS YA YC SA
TIMBER BAFFLE GLOBAL DEVICE
SECONDARY CLARIFIER 3 TABLE OF LOCATIONS

GLOBAL
N ISSUE / REVISION DD/MM/YY
M MS M VF-606 VC-601 BF
DI DI DI DO DI TIPPING TROUGH LC-610 6013 LONGITUDINAL SLUDGE CC-611
GLOBAL-1000

VF-610

200-SS-RAS
VF-605
GLOBAL-1000

1000 1000
GLOBAL-1000 PLC-300 T
SCUM COLLECTOR COLLECTOR
E
GLOBAL-1000

RETURN ACTIVATED MAG


VF-602 SLUDGE
ECIVED

FIT
CROSS COLLECTOR GLOBAL-1000

FI L R A L
PUMP 5 BF 6011
ELEMENT MAG
GLOBAL
FE AI VERIFY SHEET SI E AND SCALES BAR TO THE
M ELEMENT

6011 RIGHT IS 25 IF THIS IS A FULL SI E DRAWING


P-612 PI 0 25
ENET ENET ELEMENT 1000

PLC-300 PLC-300 PI VF-609 VF-613 VF-615 SCALE


GLOBAL-1000
NTS
1
GLOBAL-1000 GLOBAL-1000

600 VAC
FVNR
B 600 VAC
FVNR
D GLOBAL-1000
VF-607 M
TYPE 14 TYPE 14
MCC-300 MCC-300 BF VC-602 BF
GLOBAL-1000

GLOBAL-1000
VF-611
150-SS-RAS CLIENT
BF RETURN ACTIVATED SLUDGE
UNWATERING UNW 1 LD-LC-610 LD-CC-611 PUMP 4
GLOBAL-1000 GLOBAL-1000 BF
P6 5 PID701A
FROM E ISTING TERTIARY FILTERS 150-DI-UNW
N I C PHASE B FAULT IN-AUTO RUNNING RUN DISC OPEN FAULT IN-AUTO RUNNING RUN DISC OPEN
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 OVER FLOW OF
LCP-6012
GLOBAL-1000 P7 6 PID701A
FINAL CLARIFIER YA HS YS YC YA YA HS YS YC YA
150-SS-UNW TO UV CHANNEL CONSULTANT
CROSS COLLECTOR
LOCAL CONTROL PANEL DI DI DI DO DI DI DI DI DO DI
SECONDARY EFFLUENTS EFF2
GLOBAL-1000
CC-611 P7 5 PID701A
TP TO FLASH MI ER
FAULT
DEVICE

YA

AMBER
CONSULTANT
D RUNNING
DEVICE
ELEMENT

FE
YS GLOBAL

M TP
1000

GREEN
STOPPED
DEVICE M
YS
GLOBAL-1000
HG-609
RED
E SECONDARY PROFESSIONAL STAMP PRO ECT NORTH
150-SS-PA

HOA TABLE OF LOCATIONS


RETURN ACTIVATED SLUDGE
DEVICE

HS ENET CLARIFIER 2 PUMP 1


PLC-300
600 VAC
VFD TYPE 70
MCC-300 GLOBAL

TP M
4-P

1000

LCP-6014
GLOBAL-1000 LD-P-612
RETURN ACTIVATED GLOBAL-1000

SLUDGE PUMP 4 5
LOCAL CONTROL PANEL RUN RUNNING IN-AUTO FAULT SPEED REF SPEED DISC OPEN
3-P

PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300


P-612 P-613 RETURN ACTIVATED SLUDGE PRO ECT
GLOBAL-1000 GLOBAL-1000

YC YS HS YA SC SI YA PUMP 2 MUNICIPALITY OF NORTH


D

GRENVILLE - WATER POLLUTION


DEVICE DEVICE

SI SI DO DI DI DI AO AI DI

FAULT
DEVICE
FAULT
DEVICE
CONTROL PLANT E PANSION
WPCP E

YA YA
F PHASE - A
AMBER AMBER EMPTVILLE ONTARIO
ENET
RUNNING RUNNING HG-610
DEVICE DEVICE PLC-300 GLOBAL-1000
DRAWING
YS YS 600 VAC GLOBAL
ELEMENT

FE

14 2023 10 47 20 AM
M
GREEN GREEN
VFD TYPE 70
SECONDARY TABLE OF LOCATIONS
1000
PROCESS INSTRUMENTATION
MCC-300 CLARIFIER 1
STOPPED STOPPED SECONDARY CLARIFIERS
P 29000 29475-000 -

DEVICE

YS YS
DEVICE

LD-P-613
RED RED GLOBAL-1000
SECONDARY CLARIFIERS
POT POT
DEVICE DEVICE

RUN RUNNING IN-AUTO FAULT SPEED REF SPEED DISC OPEN RETURN ACTIVATED SLUDGE
HR HR
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 TP PUMP 3 OVERFLOW OF
P7 7 PID701A DESIGN
HOA HOA CW

N
DEVICE DEVICE
YC YS HS YA SC SI YA TO UV CHANNEL
HS HS DRAWN DRAWING
R

PLOT DATE
DO DI DI DI AO AI DI CHEC ED
TP
PID601A
L

LR
29475
F
NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
800 SERIES
NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES

NEW SECONDARY NEW TERTIARY


CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)

EFFLUENT WATER (EW)


3 MID802A 50-SS-EW 75-SS-EW
EXISTING SERVICE
FROM EW PUMPS BUILDING
300 SERIES
HB-1

25-SS-EW

25-SS-EW
KEY PLAN

GENERAL NOTES:

1. ALL PROCESS MECHANICAL EQUIPMENT ASSOCIATED


OPEN OPEN WITH DEWATERING & POLYMER TO BE PROVISIONAL
PLC-801 PLC-801 PLC-800 PLC-801 PLC-801 PLC-801 PLC-800 E-STOP LCP-8002 SCOPE.
PLC-801 GLOBAL-1000

E-STOP CONTROL PANEL


PI FI ZC TI VI TI ZC PROVISIONAL ITEMS:
YA
AI AI DO AI AI AI DO 2. WHERE PIPES NOTED AS PROVISIONAL PASS

\
E-STOP

\
DI DEVICE
THROUGH BUILDING STRUCTURE, SUCH AS A
HS WALL, FLOOR, OR ROOF, THE SECTION OF PIPE

\
\ \

\
1 PASSING THROUGH THE STRUCTURE IS NOT

\
PART OF THE PROVISIONAL ITEMS, AND IF THE
GLOBAL

\
VFC-822 REMAINING PIPE IS REMOVED AS A PROVISIONAL
OPEN CLOSE OPENED CLOSED IN AUTO FAULT GLOBAL
1000

ITEM, THEN BLIND FLANGES ARE TO BE


PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 100-SS-VNT M
VFC-840 PROVIDED ON EACH SIDE OF THE PIPE PASSING
1000

THROUGH THE STRUCTURE.


ZC ZC ZSO ZSC HS YA 3. PORTIONS OF PIPES ROUTED UNDERGROUND
OR THROUGH THE SIT TRENCH ARE NOT
DO DO DI DI DI DI GLOBAL
ENET INCLUDED AS PART OF THE PROVISIONAL ITEM.
\ \ \ \ \ \ \ \ \ \ \ \ \ \ \ M PLC-801
VFC-820 VC-807
DRAWING NOTES:
1000 0001-LABOLG

GLOBAL

DIGESTED SLUDGE (DSL) DEVICE DEVICE


MAG
TT
DEVICE

VT
DEVICE

TT
DEVICE
M
C A EXACT SIGNALS TO CENTRIFUGE CONTROL PANEL
P8.4 PID801A 100-SS-DSL A PIT
8013
FIT
8101 8102
ELEMENT
8104
ELEMENT
8103
ELEMENT
CNT-802 1000

3 BACK 1 TO BE COORDINATED WITH THE CENTRIFUGE


FROM DIGESTER ALARM ALARM
ELEMENT
TE VE TE DRIVE SHOP DRAWING.
PE MAG
PLC-800 PLC-800 PLC-800 8013
ELEMENT
8102 8104 8103
GLOBAL
FE GLOBAL
600 VAC Cat 6 Cat 6

LAHH LALL LI
M
P-813
8101 M
CNT-801 B ZERO SPEED
VFD LEGEND:
1000 1000

3 MAIN MCP-8001 \ \ \ \ \ \

SLUDGE HOLDING PLC-801


TABLE OF LOCATIONS VF-854 M 50-SS-DSL DRIVE DRY RUN NOT IN CONTRACT (N.I.C.) -
DI DI AI TANK
0001-LABOLG

PLC-801 LD-P-813
75-SS-DSL

\
\

0001-LABOLG

YS
\

DEVICE

LIT CENTRIFUGE DEVICE

TE PHASE B SCOPE, NOT IN


\

YA \ \
\

8030
GLOBAL
SAMPLE NO.1 DI 8013 CONTRACT (N.I.C.) -
CENTRIFUGE SLUDGE M
LOCATION SAMPLING (SMP)

\
MIX-802
DEVICE DEVICE ELEMENT

PSH PSL PE M
GLOBAL

FEED PUMP NO.1 1000


DI
8031 8032 8030 N/A N/A
VENT TO ODOUR

\
MIX-801
FOR GRAB SAMPLES
1000

100-SS-DSL 2 CONTROL
25-PVC-PLY

XX-SS-CAKE
\ \ \ \ \ \ \ \ \ \
ENET
DEVICE PLC-801
GLOBAL
SAMPLE ZSS
M 8106
P-814 LOCATION
1000

SLUDGE CAKE
B
DE-AERATOR CHUTE
25-PVC-PLY

XX-SS-CAKE
LCP-8031
GLOBAL-1000
SLUDGE CAKE 600 VAC Cat 6 Cat 6 1 PHASE A - ADDENDUM #3 10/11/23
SLUDGE HOLDING TANK MIXER ENET CHUTE
PLC-800 POLYMER DOSING
GLOBAL
VFD
LOCAL CONTROL PANEL M
PUMP SCV-802
1000
E MCP-8001 \ \ \ \ \ \
0 PHASE A ISSUED FOR TENDER 02/10/23
TYPE 14 SLUDGE SAMPLE 3
MIX-801 SLUDGE SCREW LD-CNT-801
GLOBAL-1000

FAULT D CONVEYOR 2
0001-LABOLG
No. ISSUE / REVISION DD/MM/YY
DEVICE

YA ENET This drawing is copyright protected and may not be reproduced or


600 VAC PLC-801 used for purposes other than execution of the described work without
Cat 6 Cat 6 GLOBAL

150-SS-DR
AMBER M the express written consent of J.L. Richards & Associates Limited.
\ \
FVNR
SCV-801
RUNNING
DEVICE

YS
MCC-800 \ \ \ \ \ \
3
SLUDGE
1000

C VERIFY SHEET SIZE AND SCALES. BAR TO THE


RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING.
POLYMER TOTE 0 25mm
SCREW
\

LD-MIX-801 WASTE BIN

150-SS-CNT
0001-LABOLG
MINICAS CONVEYOR 1 PLC-800 SCALE:
GREEN (BY OTHERS) NTS
\

FAULT IN-AUTO RUNNING DISC OPEN RUN ALARM

25-SS-MW
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 600 VAC Cat 6 Cat 6
STOPPED FI
\

DEVICE
VFD
YS MAG MCP-8001
\

\ \ \ \ \ \
YA HS YS YA YC YA AI FIT
DEVICE

RED 8036 CLIENT:


\

DI DI DI DI DO DI 150-SS-VNT MAG LD-CNT-802


HOA
ELEMENT
0001-LABOLG

VF-822 FE
DEVICE

HS \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ VF-821 0001-LABOLG
0001-LABOLG
8036
OPEN
EQUIPMENT CONTAINED IN THIS PLC-800 FC CENTRATE (CNT)
VC-803 VC-804
BOUNDARY GENERALLY SUPPLIED 0001-LABOLG
0001-LABOLG
100-SS-CNT M P2.17 PID202A
BY CENTRIFUGE SUPPLIER. REFER ZC TO HEADWORKS
TO SPECIFICATIONS FOR FULL ALARM ALARM INLET CHANNEL
SCOPE OF SUPPLY. DO PLC-800 PLC-800 PLC-800 CONSULTANT: www.jlrichards.ca

\
LI LALL LAHH

\
GLOBAL
ENET
S AI DI DI PLC-801
VFC-821

\
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\4-Process\PID001 EFFLUENT WATER SYSTEM.dwg

\
1000
GLOBAL GLOBAL

M M LIT
DEVICE

\
P-811 P-812 D

\
1000 1000 8035
ELEMENT DEVICE DEVICE

SERVICE WATER(SW) PE PSL PSH CONSULTANT:


8035 8034 8033
4 MID801A
600 VAC Cat 6 Cat 6
50-SS-CNT
FVR
MCP-8001 \ \ \ \ \ \

CENTRATE TRANSFER CENTRATE TRANSFER LD-SCV-801 0001-LABOLG

PUMP NO.1 PUMP NO.2


ENET PROFESSIONAL STAMP PROJECT NORTH
LCP-8032
GLOBAL-1000
CENTRATE PUMPING STATION TABLE OF LOCATIONS

PLC-801
CENTRATE TRANSFER
PUMPS LOCAL CONTROL
PANEL E
ENET ENET
GLOBAL-1000
P-811 GLOBAL-1000
P-812 PLC-800 PLC-800
600 VAC Cat 6 Cat 6
TYPE 71 TYPE 71
DEVICE DEVICE

SI SI FVR
MCP-8001 \ \ \ \ \ \

FAULT FAULT 600 VAC 600 VAC


LD-SCV-802
DEVICE DEVICE

YA YA \ \
VFD \ \ \ \ \ \ VFD \ \ \ \ \ \
0001-LABOLG

MCC-800 MCC-800 PROJECT:


AMBER AMBER
LD-P-811 LD-P-812 MUNICIPALITY OF NORTH

\
RUNNING RUNNING GLOBAL-1000 GLOBAL-1000

GRENVILLE - WATER POLLUTION


DEVICE DEVICE

YS YS FAULT IN-AUTO RUNNING RUN SPEED SPEED REF. DISC OPEN FAULT IN-AUTO RUNNING RUN SPEED SPEED REF. DISC OPEN

\
PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800 PLC-800
CONTROL PLANT EXPANSION

\
GREEN GREEN
STOPPED STOPPED YA HS YS YC SI SC YA YA HS YS YC SI SC YA

\
DEVICE

YS
DEVICE

YS PHASE - A

\
DI DI DI DO AI AO DI DI DI DI DO AI AO DI KEMPTVILLE, ONTARIO

\
RED RED \ \ \ \ \ \ \ \ \ \ \ \ \ \

POT POT DRAWING:

\
DEVICE DEVICE

HR HR
PROCESS & INSTRUMENTATION

November 14, 2023 9:55:44 AM


\
HOA
DEVICE
HOA
DEVICE
\ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \
DIGESTER UPGRADES
HS HS

POLYMER AND DEWATERING

DESIGN:
CW
DRAWN: DRAWING #:
AK

PLOT DATE:
CHECKED:

JLR #:
TP
29475
PID803A
VENT
NA NA
TO ATMOSPHERE
NE DE ATERING AND ELECTRICAL SERVICE
VENT DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
NA NA 800 SERIES
NE AERATION NE PRIMARY NE
TO ATMOSPHERE TAN S CLARIFIERS HEAD OR S
500 SERIES 400 SERIES 200 SERIES
DEVICE DEVICE DEVICE

TI TI TI
DEVICE BOILER ROOM DEVICE DEVICE

PE PE PE NE SECONDARY NE TERTIARY
CLARIFIERS FILTER BUILDING
DEVICE DEVICE DEVICE 600 SERIES PHASE B 700 SERIES PHASE B
MD MD MD

NATURAL GAS NG
75-CS-NG 200-CS-NG 75-CS-NG 65-CS-NG
VF E ISTING SERVICE
FROM NG SYSTEM GLOBAL-1000 BUILDING
300 SERIES
DIGESTER GAS DG
1 PID802A 100-SS-DG
FROM DIGESTER GAS SYSTEM VF
GLOBAL-1000

75-SS-DG
EY PLAN

MAIN DIGESTER GAS SHUTOFF


VALVE LOCATED OUTSIDE 100-SS-DG 75-SS-DG
LEGEND
BOILER ROOM PROVIDE
PLC-300
LAMECOID SIGNAGE NOT IN CONTRACT N I C -
INDICATING DIGESTER GAS
MAIN SHUTOFF VALVE TI
100-CS-H R PHASE B SCOPE NOT IN
DEVICE
AI CONTRACT N I C -
50-CS-H R PI
DEVICE
RTD
50-CS-H R TIT TP
HEATING PLANT CONTROL SE UENCE OF OPERATION 9023

200-CS-NG

65-CS-NG

65-CS-NG
VF-907 VF-904 VF-901 HOT ATER SUPPLY H S
1 GENERAL GLOBAL-1000 GLOBAL-1000 GLOBAL-1000

50-CS-H S
1 1 PLANT OPERATION CONTINUOUS CONSTANT SPEED 24 7 365 GLOBAL

M TO E ISTING DIGESTER
2 NORMAL OPERATING CONDITIONS GLOBAL-1000
VB-903 GLOBAL-1000
VB-902 GLOBAL-1000
VB-901 P-9091000

2 1 200F HOT ATER SUPPLY TEMPERATURE HOT ATER RETURN H R


2 2 180F HOT ATER RETURN TEMPERATURE 50-CS-H R
DEVICE
FROM E ISTING DIGESTER
3 SCADA TO
3 1 MONITOR SYSTEM SUPPLY ATER TEMPERATURE
P PI

3 2 MONITOR SUPPLY ATER TEMPERATURE FOR EACH BOILER GLOBAL GLOBAL GLOBAL

3 3 ALARM DIGESTER GAS HIGH AND LO PRESSURE ABNORMAL BOILER FIRING M M M


RATES FLAME FAILURES ABNORMAL SYSTEM SUPPLY ATER TEMPERATURES P-903 1000
A P-902
1000
B P-901 1000
C VC-906 HOT ATER SUPPLY H S
AND TEMPERATURE SENSOR FAILURES GLOBAL-1000

DEVICE DEVICE DEVICE VF-916 75-CS-H S M2 1 MID201A


TI TI TI GLOBAL-1000

VF-917
GLOBAL
GLOBAL-1000
TO HEAD OR S
3 BOILERS BLR-1 AND BLR-2 DUAL GAS BOILERS M
VC-903 VC-902 VC-901 P-908

HEADER TYP
3 1 OPERATE AS LEAD BOILERS STAGING ON AS DEMAND INCREASES HEN 1000
HOT ATER RETURN H R

150-CS-H R
GLOBAL-1000 GLOBAL-1000 GLOBAL-1000

DIGESTER GAS PRESSURE IS SUFFICIENT 75-CS-H R MID201A M0 2


3 2 BOILERS TO ALTERNATE IN OPERATION FOR E UAL RUN TIME
VF-908 VF-905 VF-902 FROM HEAD OR S
3 3 SCADA TO GLOBAL-1000 GLOBAL-1000 GLOBAL-1000

3 3 1 SELECT LEAD BOILER


3 3 2 INITIATE LEAD BOILER START
NE NATURAL
3 3 3 STAGE BOILERS TO MAINTAIN SUPPLY ATER TEMPERATURE SET POINT NE DUAL
GAS BOILER NE DUAL
3 3 4 ALTERNATE DUTY PUMP FOR E UAL RUN TIME FIRE BOILER
3 3 5 MONITOR BOILER STATUS 200BHP FIRE BOILER
15 BHP 15 BHP HOT ATER SUPPLY H S
3 3 6 ALARM GENERAL FAILURE GLOBAL

M 100-CS-H S M8 1 MID801A
G
GLOBAL
GLOBAL

M
4 BOILERS BLR-3 NATURAL GAS BOILER
BLR-903
1000
BLR-902
1000
H M
BLR-901
1000
I TO DIGESTER CONTROL BLDG
4 1 OPERATE AS LAG BOILER STAGING ON AS DEMAND INCREASES HEN 2000 HOT ATER RETURN H R
150 1 150
4 1 1 DIGESTER GAS PRESSURE IS NOT SUFFICIENT TO OPERATE HEATING PLANT 100-CS-H R MID801A M0 1
ON DIGESTER GAS OR REFER TO MID002A REFER TO MID002A REFER TO MID002A
FROM DIGESTER CONTROL BLDG
DEVICE DEVICE DEVICE

TI TI TI
4 1 2 DIGESTER GAS IS SUFFICIENT AND LOAD E CEEDS DUAL GAS BOILERS 1 1 VB-905
GLOBAL-1000
VB-907
GLOBAL-1000
VB-911
GLOBAL-1000

CAPACITY AS DETERMINED BY HEATING SUPPLY ATER TEMPERATURE DEVICE DEVICE DEVICE

4 2 SCADA TO TE TE TE
NO
L NO
M NO
N 1 PHASE A - ADDENDUM 3 10 11 23
4 2 1 INITIATE BOILER START DEVICE
TO DRAIN DEVICE
TO DRAIN DEVICE
TO DRAIN GLOBAL GLOBAL GLOBAL

4 2 2 MONITOR BOILER STATUS PI PI PI PLC-300 PLC-300 NC S NC S NC S


0 PHASE A ISSUED FOR TENDER 02 10 23
4 2 3 ALARM GENERAL FAILURE VFC-901 1000
VFC-902 1000
VFC-904 1000

C C C
TI TI N ISSUE REVISION DD MM YY
VF-909 VF-906 VF-903 VB-904 VB-906 VB-910
ENET 100-CS-H S GLOBAL-1000
75-CS-H S GLOBAL-1000
75-CS-H S GLOBAL-1000

AI AI GLOBAL-1000 GLOBAL-1000 GLOBAL-1000

T
PLC-300

RTD
L R A L
TYPE 14 150-CS-H S DEVICE

VF-915 VF-918 VF-923 VF-924


FAULT IN-AUTO RUNNING RUN DISC OPEN HEADER TYP TIT GLOBAL-1000 GLOBAL-1000

BOILER
GLOBAL-1000
GLOBAL-1000

9021 VERIFY SHEET SI E AND SCALES BAR TO THE


PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 ROOM RIGHT IS 25 IF THIS IS A FULL SI E DRA ING 0 25
A 600 VAC
SCALE
FVNR YA HS YS YC YA DEVICE
NTS
MCC-300 PI
D LD-P-901 DI DI DI DO DI
150-CS-H S

GLOBAL-1000

150-CS-H R
ENET RTD
AAV M
GLOBAL
DEVICE

TIT CLIENT
PLC-300 AIR
P-905 VC-904 9020
DEVICE
SEPARATOR 1000
GLOBAL-1000

TYPE 14 PI 150-CS-H S 150-CS-H S


FAULT IN-AUTO RUNNING RUN DISC OPEN VF-910 150-CS-H S
VF-912 TUNNEL
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 GLOBAL-1000

B
GLOBAL-1000

600 VAC 150-CS-H S VF-911


GLOBAL-1000

VF-919 VF-922 HOT ATER RETURN H R


FVNR PRIMARY HEATING GLOBAL-1000 GLOBAL-1000

YA HS YS YC YA 150-CS-H S 40-CS-H R MID701 M7 1


MCC-300 AAV PUMP 1
E LD-P-902 DEVICE DEVICE VB-908 FROM NE TERTIARY FILTER CONSULTANT
20-CU-S

GLOBAL-1000
DI DI DI DO DI PI PI GLOBAL-1000

O
DEVICE

NC PI HOT ATER SUPPLY H S


NO
GLOBAL
40-CS-H S M7 2 MID701
SERVICE ATER S NC S
GLOBAL
VFC-903 TO NE TERTIARY FILTER
20-CU-S 20-CU-S M 1000

P-906 VC-905 C
FROM PLANT M SUPPLY AUTOMATIC FILL VALVE 1000
GLOBAL-1000

ELEMENT

E PANSION E PANSION PI
TAN 1 TAN 2 VF-914 VB-909 CONSULTANT
GLOBAL-1000
GLOBAL-1000

VF-913 DEVICE

GLOBAL-1000
PI
PRIMARY HEATING VF-920 HOT ATER RETURN H R
ENET GLOBAL-1000

PUMP 2 150-CS-H S
MID001 BOILER SYSTEM

PLC-300 100-CS-H R 100-CS-H R


GLOBAL-1000
ET-301 GLOBAL-1000
ET-302 CHEMICAL FROM E ISTING PLANT HEATING
TYPE 14
POT FEEDER GLOBAL-1000
VF-921 HOT ATER SUPPLY H S
FAULT IN-AUTO RUNNING RUN DISC OPEN 100-CS-H S 100-CS-H S
C 600 VAC PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 GLOBAL-1000
VC-907
RTD TO E ISTING PLANT HEATING
PROFESSIONAL STAMP PRO ECT NORTH

FVNR
DEVICE

TIT TP
MCC-300 YA HS YS YC YA 9022
F LD-P-903 M
GLOBAL

GLOBAL-1000

DI DI DI DO DI
20-CU-S
20-CU-CF P-907 R
1
1000

FAULT IN-AUTO OPEN CLOSE OPENED CLOSED


5-M

LCP-9040 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300


PRIMARY HEATING PUMPS
GLOBAL-1000
1 HYDRONIC HEATING SYSTEM
LOCAL CONTROL PANEL ENET NTS YA HS C C SO SC
ENET RUN SPEED REF SPEED MID001
PLC-300
P-905 P-906 PLC-300 PLC-300 PLC-300 PLC-300
GLOBAL-1000 GLOBAL-1000 FAULT IN-AUTO RUNNING RUN DISC OPEN DI DI DO DO DI DI
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 LCP-9002
3-P

TYPE 14
RUNNING RUNNING TYPE 70 YC SC SI HOT ATER PUMP LOCAL CONTROL PANEL
GLOBAL-1000

L PRO ECT
YA HS YS YC YA
DEVICE DEVICE

YS YS P-907 P-908 P-909


BOILER PUMPS LOCAL CONTROL PANEL
LCP-9001
GLOBAL-1000
DO AO AI P 600 VAC GLOBAL-1000 GLOBAL-1000 GLOBAL-1000
FAULT IN-AUTO OPEN CLOSE OPENED CLOSED MUNICIPALITY OF NORTH
D

600 VAC FVNR FAULT FAULT FAULT PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300
DI DI DI DO DI
P-901 P-902 P-903
GREEN
FAULT
GREEN
FAULT
VFD RUNNING IN-AUTO FAULT DISC OPEN MCC-300
DEVICE

YA
DEVICE

YA
DEVICE

YA
GRENVILLE - ATER POLLUTION
GLOBAL-1000 GLOBAL-1000 GLOBAL-1000

MCC-300 PLC-300 PLC-300 PLC-300 PLC-300 LD-P-909 YA HS C C SO SC


D FAULT FAULT FAULT
DEVICE

YS
DEVICE

YS
GLOBAL-1000

AMBER AMBER AMBER


CONTROL PLANT E PANSION
LD-P-905
PCP E

DEVICE DEVICE DEVICE

YA YA YA
AMBER AMBER
GLOBAL-1000
YS HS YA YA ENET RUNNING RUNNING RUNNING DI DI DO DO DI DI PHASE - A
AMBER AMBER AMBER STOPPED STOPPED
DI DI DI DI
PLC-300 DEVICE

YS
DEVICE

YS
DEVICE

YS M EMPTVILLE ONTARIO
E RUNNING RUNNING RUNNING
DEVICE

YS
DEVICE

YS
FAULT
PLC-300
IN-AUTO RUNNING
PLC-300 PLC-300
RUN DISC OPEN
PLC-300 PLC-300 FAULT IN-AUTO OPEN CLOSE OPENED CLOSED
TYPE 14 GREEN GREEN GREEN DRA ING
DEVICE DEVICE DEVICE
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300
YS YS YS RED RED ENET RUN SPEED REF SPEED STOPPED STOPPED STOPPED
MECHANICAL INSTRUMENTATION

14 2023 9 52 05 AM
PLC-300 PLC-300 PLC-300 PLC-300
F YA HS YS YC YA DEVICE DEVICE DEVICE

HOA HOA YS YS YS YA HS C C SO SC
GREEN GREEN GREEN 600 VAC
DEVICE

HS
DEVICE

HS SITE- IDE
P 29000 29475-000 -

STOPPED STOPPED STOPPED TYPE 70 YC SC SI DI DI DI DO DI FVNR RED RED RED


DEVICE DEVICE DEVICE

MCC-300 DI DI DO DO DI DI
YS YS YS HOA HOA HOA
LD-P-908
DO AO AI GLOBAL-1000
DEVICE

HS
DEVICE

HS HS
DEVICE
N BOILER SYSTEM
RED RED RED DEVICE DEVICE 600 VAC ENET
SI SI VFD FAULT IN-AUTO OPEN CLOSE OPENED CLOSED
HOA HOA HOA RUNNING IN-AUTO FAULT DISC OPEN PLC-300
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300
DEVICE

HS
DEVICE

HS HS
DEVICE

MCC-300 PLC-300 PLC-300 PLC-300 PLC-300 FAULT IN-AUTO RUNNING RUN DISC OPEN
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 TYPE 14
POT POT LD-P-906 YA HS C C SO SC DESIGN
C
GLOBAL-1000
YS HS YA YA LD-P-907

N
DEVICE DEVICE

HR HR GLOBAL-1000

YA HS YS YC YA DRA N DRA ING


R DI DI DO DO DI DI R

PLOT DATE
DI DI DI DI 600 VAC
O CHEC ED
DI DI DI DO DI FVNR TP
MID001A
L

MCC-300
LR
29475
F
NEW DEWATERING AND ELECTRICAL SERVICE
CONTRACTOR TO VENT RELIEF DIGESTER CONTROL ENTRANCE BUILDING
VALVE TO OUTDOORS INSTALL BUILDING 900 SERIES
00 SERIES
TO CSA B1 9 1 AND MAINTAIN NEW AERATION NEW PRIMARY NEW
CLARIFIERS HEADWOR S
TAN S
ALL RE UIRED CLEARANCES VENT VNT VENT VNT 00 SERIES 00 SERIES 200 SERIES
TYPICAL OF ALL NA NA
CONTRACTOR TO VENT RELIEF NA NA
CONTRACTOR TO BRING NATURAL TO ATMOSPHERE VALVE TO OUTDOORS INSTALL TO ATMOSPHERE
GAS TO EACH BOILER AND VENT VNT TO CSA B1 9 1 AND MAINTAIN NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
ALL RE UIRED CLEARANCES
GLOBAL GLOBAL GLOBAL GLOBAL GLOBAL

CONNECT TO PAC AGED GAS NA NA PI PI PI PSH PI 00 SERIES PHASE B 00 SERIES PHASE B


TRAIN SUPPLIED BY BOILER PI
GLOBAL

TYPICAL OF ALL
TO ATMOSPHERE 1000
DIGESTER GAS DG 1000 1000 1000 1000

MANUFACTURER GLOBAL GLOBAL GLOBAL GLOBAL GLOBAL GLOBAL GLOBAL GLOBAL GLOBAL
1000

PSL M M PSH M 1 0-SS-DG PSL M M M


NATURAL GAS NG
1000 1000 1000 1000 1000
FROM DIGESTER GAS SYSTEM 1000 1000 1000 1000

DUAL FUEL E ISTING SERVICE


1 BOILER 1 0-SS-DG F BUILDING
GLOBAL
BOILER 300 SERIES
FROM NG METER PI
1000

GLOBAL GLOBAL GLOBAL


0-SS-DG
PSL S S
1000 1000 1000
PROVIDE DRIP LEG BLOW EY PLAN
OFF AND CONNECTION TO
PILOT PAC AGE GAS TRAIN
LEGEND
PROVIDE DIRT POC ET
NOT IN CONTRACT N I C -
AT PIPE RISER

PHASE B SCOPE NOT IN


1 TYPICAL NATURAL GAS TRAIN TO EACH BOILER 2 TYPICAL DIGESTER GAS TRAIN TO DUAL FIRE BOILERS CONTRACT N I C -
MID002A NTS MID002A NTS

FCP-9030
GLOBAL-1000
FCP-9020
GLOBAL-1000

BOILER FIELD CONTROL PANEL BOILER FIELD CONTROL PANEL

GLOBAL-1000
BLR-903 GLOBAL-1000
BLR-902
REFER TO MID001A G REFER TO MID001A H
1 1

HMI HMI

POWER ON PILOT ON NATURAL GAS DIGESTER GAS ALARM SPARE SPARE POWER ON PILOT ON NATURAL GAS DIGESTER GAS ALARM SPARE SPARE
DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE

YS YS YS YS YA YS YS YS YS YA

WHITE GREEN BLUE AMBER AMBER WHITE WHITE WHITE GREEN BLUE AMBER AMBER WHITE WHITE
POWER BURNER DIGESTER GAS REMOTE BOOSTER ON POWER BURNER DIGESTER GAS REMOTE BOOSTER ON
DEVICE DEVICE DEVICE DEVICE DEVICE ALARM DEVICE DEVICE DEVICE DEVICE DEVICE ALARM
HS HS HS HS YS PLC-300 HS HS HS HS YS PLC-300
ON OFF ON OFF NATURAL GAS LOCAL GREEN ON OFF ON OFF NATURAL GAS LOCAL GREEN
YA YA

DI DI
GLOBAL-1000
LCP-9031 LCP-9021
GLOBAL-1000

E-STOP LOCAL E-STOP LOCAL


IN-AUTO ALARM ALARM ALARM MODE MODE ALARM ALARM ALARM ALARM CONTROL PANEL IN-AUTO ALARM ALARM ALARM MODE MODE ALARM ALARM ALARM ALARM CONTROL PANEL
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300
E-STOP E-STOP
DEVICE DEVICE
1 PHASE A - ADDENDUM 3 10 11 23
HS YA LAL TAH NG DG PAH PAL PAH PAL YS I I PB HS YA LAL TAH NG DG PAH PAL PAH PAL YS I I PB

DI DI DI DI DI DI DI DI DI DI DI DI DI RED DI DI DI DI DI DI DI DI DI DI DI DI DI RED 0 PHASE A ISSUED FOR TENDER 02 10 23

N ISSUE REVISION DD MM YY

L R A L

ALARM ALARM ALARM ALARM VERIFY SHEET SI E AND SCALES BAR TO THE
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 RIGHT IS 2 IF THIS IS A FULL SI E DRAWING 0 2
SCALE
FAL PAL YS YS YS YC YC BI FF FF TC BC FAL PAL YS YS YS YC YC BI FF FF TC BC NTS

DI DI DI DI DO DO DO AI AI AI AO AO DI DI DI DI DO DO DO AI AI AI AO AO

CLIENT

CONSULTANT
FCP-9010
GLOBAL-1000

BOILER FIELD CONTROL PANEL

GLOBAL-1000
BLR-901
REFER TO MID001A I
1
CONSULTANT
HMI
MID001 BOILER SYSTEM

POWER ON PILOT ON NATURAL GAS DIGESTER GAS ALARM SPARE SPARE


DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE DEVICE

YS YS YS YS YA

WHITE GREEN BLUE AMBER AMBER WHITE WHITE PROFESSIONAL STAMP PRO ECT NORTH
POWER BURNER DIGESTER GAS REMOTE BOOSTER ON
DEVICE DEVICE DEVICE DEVICE DEVICE ALARM
HS HS HS HS YS PLC-300
ON OFF ON OFF NATURAL GAS LOCAL GREEN
YA
-M

DI
LCP-9011
GLOBAL-1000

E-STOP LOCAL
IN-AUTO ALARM ALARM ALARM MODE MODE ALARM ALARM ALARM ALARM CONTROL PANEL
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300
E-STOP
3-P

DEVICE

HS YA LAL TAH NG DG PAH PAL PAH PAL YS I I PB


PRO ECT
DI DI DI DI DI DI DI DI DI DI DI DI DI RED
MUNICIPALITY OF NORTH
D

GRENVILLE - WATER POLLUTION


CONTROL PLANT E PANSION
WPCP E

PHASE - A
ALARM ALARM
EMPTVILLE ONTARIO
PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300
DRAWING

MECHANICAL INSTRUMENTATION

AM
FAL PAL YS YS YS YC YC BI FF FF TC BC

DI DI DI DI DO DO DO AI AI AI AO AO SITE-WIDE
-000 -

2023 9
BOILER GAS TRAIN SYSTEMS
P 29000 29

1
DESIGN
CW

N
DRAWN DRAWING
R

PLOT DATE
CHEC ED
TP
MID002A
L

LR
29
F
SEQUENCE OF OPERATION GLOBAL
SEQUENCE OF OPERATION
M
1. EXHAUST FAN EF-302 TO MODULATE TO MAINTAIN EF-304 1. DRIP TRAP ROOM FAN EF-304 TO OPERATE
L-303 L-304 1000

GLOBAL-1000 GLOBAL-1000
HEATING PUMP ROOM OPERATOR ADJUSTABLE SET CONTINUOUSLY. NEW DEWATERING AND ELECTRICAL SERVICE
2. LOW FLOW SWITCH IN DUCT TO ALARM IF AIR FLOW DIGESTER CONTROL ENTRANCE BUILDING
TEMPERATURE. BUILDING 900 SERIES
2. IF FAN IS AT ITS LOWEST SPEED, AND TEMPERATURE DROPS BELOW 65L/S 800 SERIES
NEW AERATION NEW PRIMARY NEW
CONTINUES TO DROP BELOW SET TEMPERATURE LESS TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES
DEADBAND, THEN EF-302 TO DE-ENERGIZE. WHEN SHAFT
SPACE TEMPERATURE RISES TO SET TEMPERATURES
PLUS DEADBAND, FAN TO RE-ENERGIZE AND
MODULATE TO MAINTAIN SET TEMPERATURE. NEW SECONDARY NEW TERTIARY
L-302 CLARIFIERS FILTER BUILDING
GLOBAL-1000 3. IF FAN IS ON MAXIMUM SPEED AND SPACE 600 SERIES (PHASE B) 700 SERIES (PHASE B)
TEMPERATURE CONTINUES TO RISE BEYOND HIGH
TEMPERATURE SET POINT OF 30°C, THEN SYSTEM IS TO

600x500-GS-EA

500x500-GS-EA
650x800-GS-SA

600-SS-VNT

200-SS-VNT

200-SS-VNT
ALARM.

150-GS-EA
4. EXHAUST FAN EF-303 TO MODULATE TO MAINTAIN
BOILER ROOM OPERATOR ADJUSTABLE SET L-305 EXISTING SERVICE
FD GLOBAL-1000

BUILDING
TEMPERATURE. 300 SERIES
5. IF FAN IS AT ITS LOWEST SPEED, AND TEMPERATURE
L-301 CONTINUES TO DROP BELOW SET TEMPERATURE LESS
GLOBAL-1000

DEADBAND, THEN EF-303 TO DE-ENERGIZE. WHEN


SPACE TEMPERATURE RISES TO SET TEMPERATURES ALARM
PLC-300 KEY PLAN
PLUS DEADBAND, FAN TO RE-ENERGIZE AND
MODULATE TO MAINTAIN SET TEMPERATURE.
6. IF FAN IS ON MAXIMUM SPEED AND SPACE FAL
TEMPERATURE CONTINUES TO RISE BEYOND HIGH
DI GENERAL NOTES:
TEMPERATURE SET POINT OF 30°C, THEN SYSTEM IS TO

\
ALARM.
1. REFER TO SCHEDULES FOR EQUIPMENT BALANCING
ENET REQUIREMENTS.
PLC-300

\
2540 L/s O 2540 L/s O
BDD BDD FD DRAWING NOTES:
2540 L/s U 2540 L/s U DEVICE

TYPE 70 FD FSL
66 L/s O BD 1 PROVIDE RELAY INSIDE CP-3000.
700x800-GS-SA

3015

150x150-GS-SA
66 L/s U
BD BD PLC-300
M
GLOBAL
GLOBAL

M A
\
600 VAC
RUN RUNNING IN-AUTO FAULT SPEED REF. SPEED DISC OPEN LEGEND:
EF-302 1000
A EF-303
1000
B VFD
\ \ \ \ PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300

MCC-300 \ NOT IN CONTRACT (N.I.C.) -


C
\
300x200-GS-SA YC YS HS YA SC SI YA

\
DO DI DI DI AO AI DI PHASE B SCOPE, NOT IN
\ \ \
\ CONTRACT (N.I.C.) -
LD-EF-302
FD
GLOBAL-1000

ELEMENT
H2S ELEMENT
CH4
PLC-300 PLC-300 AE AE
3300 3301
RTD RTD 66 L/s O
DEVICE

TIT
DEVICE

TIT ENET H2S CH4


TI TI PLC-300 66 L/s U DEVICE DEVICE

3013 3014 AIT AIT


3300 3301
AI AI COLD AIR TRAP
TYPE 70
700x800-GS-CA
PLC-300

\
HEATING PUMP ROOM FD COMBUSTION BOILER ROOM DRIP TRAP ROOM BOILER ROOM
B
\ RUN RUNNING IN-AUTO FAULT SPEED REF. SPEED DISC OPEN
AIR 600 VAC \ \ \ \ PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300 PLC-300
GLOBAL GLOBAL GLOBAL VFD
M M M

\
MCC-300 \
D
\
BLR-903 BLR-902 BLR-901 YC YS HS YA SC SI YA FAULT ALARM WARNING FAULT ALARM WARNING
PLC-300 PLC-300 PLC-300 PLC-300

\
1000 1000 1000
PLC-300 PLC-300 PLC-300 PLC-300
REFER TO MID001A AND MID002A.
DO DI DI DI AO AI DI

\
\ \ \ AI AAY AAY AAY AAY AAY AAY AI
1 \
LD-EF-303
BOILER ROOM AND PUMP ROOM VENTILATION MID
GLOBAL-1000

1 AI DI DI DI DI DI DI AI

\
DEVICE DEVICE DEVICE
DEVICE DEVICE DEVICE

MID301A NTS AAY AAY AAY AAY AAY AAY

\
1 1 1 1 1 1
GLOBAL

S \ \ \ \ \ \
VFC-307 1000

HOT WATER SUPPLY (HWS)


25-CU-HWS
FROM ADMIN BUILDING GLOBAL

M 2 DRIP TRAP ROOM VENTILATION MID 1 PHASE A - ADDENDUM #3 10/11/23


DISTRIBUTION
UH-336 NTS
GLOBAL GLOBAL
1000

MID301A
S S 0 PHASE A ISSUED FOR TENDER 02/10/23
VFC-3051000
VFC-306
1000

HOT WATER RETURN (HWR) No. ISSUE / REVISION DD/MM/YY


25-CU-HWR
HOT WATER SUPPLY (HWS) This drawing is copyright protected and may not be reproduced or
TO ADMIN BUILDING VB-307
GLOBAL-1000
used for purposes other than execution of the described work without
DISTRIBUTION 30-CU-HWS 25-CU-HWS
the express written consent of J.L. Richards & Associates Limited.
T FROM ADMIN BUILDING
DISTRIBUTION VERIFY SHEET SIZE AND SCALES. BAR TO THE
VB-305 VB-306
GLOBAL-1000 GLOBAL-1000
RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
GLOBAL GLOBAL GLOBAL GLOBAL

S S S S SCALE:
VFC-301
1000
VFC-302
1000
VFC-303 1000
VFC-304
1000
NTS

HOT WATER RETURN (HWR)


GLOBAL GLOBAL 30-CU-HWR 25-CU-HWR
M M
UH-334 UH-335 TO ADMIN BUILDING CLIENT:
1000 1000

DISTRIBUTION

T T GLOBAL-1000
VB-301 GLOBAL-1000
VB-302 GLOBAL-1000
VB-303 GLOBAL-1000
VB-304

CONSULTANT: www.jlrichards.ca
PUMP ROOM DRIP TRAP ROOM GLOBAL GLOBAL GLOBAL GLOBAL

M M M M
UH-330
1000
UH-331
1000
UH-332 1000
UH-333
1000

3 PUMP ROOM & DRIP TRAP ROOM


T T T T
MID301A NTS

OPENED OPEN OPENED OPEN


PLC-300 PLC-300 PLC-300 PLC-300
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\5-Mech\SERVICE-BLDG-HVAC SCHEM.dwg

CONSULTANT:

ZSO ZC ALARM ALARM ZSO ZC


PUMP ROOM
PLC-300 PLC-300
DI DO DI DO
TAH TAH
406 L/s O 158 L/s O 3 BOILER ROOM
\

47 L/s O
0 L/s U 0 L/s U NTS
0 L/s U DI DI 612 L/s O MID301A
\

0 L/s U PROFESSIONAL STAMP PROJECT NORTH


\

L
\

L-306
GLOBAL-1000
L-307 GLOBAL-1000
SEQUENCE OF OPERATION LCP-3900 LCP-3901
\

GLOBAL-1000 GLOBAL-1000

SERVICE BUILDING HEATING PUMP SERVICE BUILDING BOILER ROOM


\
\

DEVICE DEVICE
ELECTRICAL ROOM: ROOM LOCAL CONTROL PANEL LOCAL CONTROL PANEL
SD SD LABOLG

M 1. WHEN SPACE IS OCCUPIED, SF-301 IS TO BE


3011 3012 MD-301 ENERGIZED. WHEN SPACE IS UNOCCUPIED, SF-301 TO GLOBAL-1000
EF-302 GLOBAL-1000
EF-303
M

M
M

0001
\

M
GLOBAL GLOBAL

M DE-ENERGIZE.
M

EF-310 EF-305 2. MD-301 AND MD-302 ARE TO BE INTERLOCKED WITH DEVICE DEVICE

SI SI
GLOBAL

M 1000

GLOBAL GLOBAL
1000

SF-301 SUCH THAT WHEN SF 301 IS ON, THE DAMPERS


MD-302 M M
1000

406 L/s O MD-PS-2 MD-303 ARE OPEN, AND WHEN THE FAN IS OFF, THE DAMPERS
FILTER 158 L/s O
M

PLC-300
GLOBAL

M 0 L/s U
1000 1000 GLOBAL

M ARE CLOSED.
0 L/s U 3. EUH-301 TO MODULATE TO MAINTAIN OPERATOR FAULT FAULT
RTD MD-PS-1
1000
MD-GE-9
1000
DEVICE DEVICE

YA YA
DEVICE

TIT ADJUSTABLE SPACE TEMPERATURE OF 18°C. PROJECT:


TI
3010 4. AC-3001 TO MODULATE TO MAINTAIN SPACE
S LABOLG S
GLOBAL

TEMPERATURE OF 25°C. AMBER AMBER MUNICIPALITY OF NORTH


M AI
SF-301
VFC-3081000

PARTS STORAGE ROOM:


RUNNING
DEVICE
RUNNING
DEVICE
GRENVILLE - WATER POLLUTION
YS YS
0001

HOT WATER SUPPLY (HWS)


C D CONTROL PLANT EXPANSION
\ \
1. RE-INSTATE CONTROLS FOR PARTS STORAGE ROOM
25-CU-HWS
AS INDICATED IN THE GORE AND STORRIE 1994 GREEN GREEN
FROM ADMIN BUILDING
DISTRIBUTION GLOBAL
RECORD DRAWINGS. STOPPED STOPPED PHASE - A
47 L/s O GLOBAL
M DEVICE

YS
DEVICE

YS KEMPTVILLE, ONTARIO
0 L/s U M UH-337
1000
CLOSET:
EUH-301 HOT WATER RETURN (HWR) 1. WHEN TOGGLE SWITCH IS ON, EF-305 TO BE DRAWING:
1000

RED RED
5kW 25-CU-HWR ENERGIZED, AND WHEN OFF, EF-305 TO BE
MECHANICAL & INSTRUMENTATION

November 14, 2023 9:53:43 AM


HOA HOA
M
GLOBAL

HEATER VB-308 DE-ENERGIZED.


TO ADMIN BUILDING
DEVICE DEVICE

GLOBAL-1000

2. MD-GE-9 AND MD-303 TO BE INTERLOCKED WITH EF-305 HS HS


M
GLOBAL
AC-301 1000 DISTRIBUTION
SUCH THAT WHEN THE FAN IS ENERGIZED, THE
SERVICE BUILDING
CND-301 1000
DAMPERS ARE OPEN, AND WHEN THE FAN IS
T DE-ENERGIZED, THE DAMPERS ARE CLOSED. POT POT
T 3. UH-337 AND ASSOCIATED CONTROL VALVE TO
DEVICE

HR HR
DEVICE
HVAC DIAGRAMS
MODULATE TO MAINTAIN SPACE SET TEMPERATURE OF
ELECTRICAL ROOM PARTS STORAGE CLOSET 20C.
REFRIGERANT PIPING
BOILER ROOM, PUMP ROOM, AND DRIP TRAP ROOM UNIT DESIGN:
CW
HEATERS: DRAWN: DRAWING #:
AK
SERVICE BUILDING ELECTRICAL ROOM 2 HVAC MID

PLOT DATE:
3 1. UNIT HEATERS TO MAINTAIN OPERATOR ADJUSTABLE
SPACE SET TEMPERATURE OF 18C. CHECKED:
MID301A NTS
JLR #:
TP
29475
MID301A
EC5
EngCAD Database Data Exported on: 2023-11-10 9:40:39 AM
MOTOR STARTER AND CONTROL LIST NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
CONTROL DETAILS & RESPONSIBILITiES BUILDING
800 SERIES
900 SERIES

GENERAL MOTOR NEW AERATION


TANKS
NEW PRIMARY NEW
CLARIFIERS HEADWORKS
STARTER AT MOTOR AUTOMATION COMMENTS 500 SERIES 400 SERIES 200 SERIES

NEW TERTIARY

GENERATOR SEQUENCE
NEW SECONDARY
CLARIFIERS FILTER BUILDING
700 SERIES (PHASE B)

TOTAL LINKS IN DATABASE


600 SERIES (PHASE B)

CONTROL WIRED BY
DETAIL REFERENCE
COMMISSIONED BY

COMMISSIONED BY

COMMISSIONED BY

COMMISSIONED BY
DEVICE LOCATION

STARTER NOTES
PROJECT PHASE

POWER SOURCE

INSTALLED BY

INSTALLED BY

INSTALLED BY

INSTALLED BY
DESCRIPTION

SUPPLIED BY

SUPPLIED BY

SUPPLIED BY

SUPPLIED BY
DEVICE TAG
EXISTING SERVICE
BUILDING

WIRED BY

WIRED BY

WIRED BY
VOLTAGE
300 SERIES

PHASE

LOAD

TYPE
KEY PLAN

0 MD 901 A MOTORIZED DAMPER 0 900 LP 902 120 1 7 W M M E G INTEGRAL N/A M M E G E E E G E E E G


0 MD 902 A MOTORIZED DAMPER 0 900 LP 902 120 1 7 W M M E G INTEGRAL N/A M M E G E E E G E E E G
2 MIX 201 A GRIT TANK 1 VORTEX INDUCER 0 202 MCP 2002 600 3 2 HP M M E G TYPE 14 2/E022 M M E G M M E G M E E G
2 MIX 202 A GRIT TANK 2 VORTEX INDUCER 0 202 MCP 2002 600 3 2 HP M M E G TYPE 14 2/E022 M M E G M M E G M E E G
3 MIX 801 A SLUDGE HOLDING TANK MIXER 0 8XX MCC 800 600 3 3 HP M M E G TYPE 13 1/E023 M M E G E E E G E E E G
0 MIX 802 A POLYMER INLINE MIXER 0 810 CP 8005 120 1 0.75 HP M M E G INTEGRAL N/A
5 MIX 803 A DIGESTER TANK MIXER 0 8XX MCC 800 600 3 7.5 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
2 MS 201 A RAW SEWAGE MECHANICAL SCREEN NO. 1 0 202 MCP 2001 600 3 1 HP M M E G TYPE 30 1/E022 M M E G M M E G M E E G
2 MS 202 A RAW SEWAGE MECHANICAL SCREEN NO. 2 0 202 MCP 2001 600 3 1 HP M M E G TYPE 30 1/E022 M M E G M M E G M E E G
3 OCU 201 A HEADWORKS ODOUR CONTROL UNIT #1 0 EXT MCC 200 600 3 50 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G PROVIDE FIRE DETECTION INTERFACE FOR SHUTDOWN
3 OCU 202 A HEADWORKS ODOUR CONTROL UNIT #2 0 EXT MCC 200 600 3 50 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G PROVIDE FIRE DETECTION INTERFACE FOR SHUTDOWN
2 OCU 801 A DIGESTER BUILDING ODOUR CONTROL UNIT 0 EXT MCC 800 600 3 50 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G PROVIDE FIRE DETECTION INTERFACE FOR SHUTDOWN
1 P 201 A GRIT SLURRY PUMP 1 0 202 MCP 2002 600 3 7.5 HP M M E G TYPE 14 2/E022 M M E G M M E G M E E G
1 P 202 A GRIT SLURRY PUMP 2 0 202 MCP 2002 600 3 7.5 HP M M E G TYPE 14 2/E022 M M E G M M E G M E E G
3 P 205 A BIN ROOM SUMP PUMP 0 201 LCP 2030 600 3 1.1 HP M M E G INTEGRAL N/A M M E G E E E G E E E G
3 P 206 A PIPE GALLERY SUMP PUMP 0 200 LCP 2031 600 3 1.1 HP M M E G INTEGRAL N/A M M E G E E E G E E E G
2 P 207 A HEADWORKS GLYCOL HEATING PUMP 0 200 MCC 200 600 3 10 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
0 P 208 A EFFLUENT BOOSTER PUMP 0 201 MCC 200 600 0 1 HP M M E E TYPE 14 2/E022 M M E G E E E G E E E G
2 P 401 A PRIMARY SLUDGE PUMP 1 0 200 MCC 200 600 3 5 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G
2 P 402 A PRIMARY SLUDGE PUMP 2 0 200 MCC 200 600 3 5 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G
2 P 403 A PRIMARY SCUM PUMP 0 TS-4XX MCC 200 600 3 5 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
0 P 408 A FERRIC SULFATE METERING PUMP 0 812 LP 803 120 1 10 W M M E G INTEGRAL N/A M M E G E E E G E E E G
0 P 409 A FERRIC SULFATE METERING PUMP 0 812 LP 803 120 1 10 W M M E G INTEGRAL N/A M M E G E E E G E E E G
2 P 715 A EFFLUENT PUMP NO. 6 0 1-B06 MCC 300 600 3 40 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G
3 P 807 A DIGESTER SLUDGE RECIRC PUMP NO. 3 0 803 MCC 800 600 3 20 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G
3 P 808 A DIGESTER SLUDGE RECIRC PUMP NO. 4 0 803 MCC 800 600 3 20 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G
3 P 809 A DIGESTER HEX HOT WATER RECIRC PUMP 0 803 MCC 800 600 3 5 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
3 P 811 A CENTRATE TRANSFER PUMP NO.1 0 8XX MCC 800 600 3 1.7 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G
3 P 812 A CENTRATE TRANSFER PUMP NO.2 0 8XX MCC 800 600 3 1.7 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G
1 PHASE A - ADDENDUM #3 10/11/23
2 P 813 A CENTRIFUGE FEED PUMP NO. 1 0 810 MCP 8001 600 3 5 HP M M E G TYPE 70 1/E020 M M E G M M E G M E E G
0 P 814 A POLYMER DOSING PUMP NO.1 0 810 CP 8005 120 1 0.5 HP M M E G INTEGRAL N/A M M E G M M E G M E E G 0 PHASE A ISSUED FOR TENDER 02/10/23
1 P 815 A DIGESTER GLYCOL HEATING PUMP 0 803 MCC 800 600 3 2 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
No. ISSUE / REVISION DD/MM/YY
1 P 816 A DIGESTER SANITARY SUMP PUMP NO.1 0 803 LCP 8051 600 3 1.1 HP M M E G INTEGRAL N/A M M E G E E E G E E E G
This drawing is copyright protected and may not be reproduced or
1 P 817 A DIGESTER SANITARY SUMP PUMP NO.2 0 803 LCP 8051 600 3 1.1 HP M M E G INTEGRAL N/A M M E G E E E G E E E G used for purposes other than execution of the described work without
2 P 818 A DIGESTER HEATING LOOP PUMP 0 803 MCC 800 600 3 1.5 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G the express written consent of J.L. Richards & Associates Limited.
0 P 819 A MUNICIPAL HOT WATER RECIRC PUMP 0 803 LP 802 120 1 28 W M M E G INTEGRAL N/A M M E G E E E G E E E G VERIFY SHEET SIZE AND SCALES. BAR TO THE
RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
2 P 901 A BOILER FEED PUMP NO.1 0 1-B03 MCC 300 600 3 1 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
SCALE:
2 P 902 A BOILER FEED PUMP NO.2 0 1-B03 MCC 300 600 3 1 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G N.T.S.

2 P 903 A BOILER FEED PUMP NO.3 0 1-B03 MCC 300 600 3 15 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
1 P 905 A PRIMARY HEATING DISTRIBUTION PUMP NO.1 0 1-B04 MCC 300 600 3 20 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
CLIENT:
1 P 906 A PRIMARY HEATING DISTRIBUTION PUMP NO.2 0 1-B04 MCC 300 600 3 20 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
2 P 907 A SERVICE BUILDING HEATING PUMP 0 1-B04 MCC 300 600 3 5 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
2 P 908 A HEADWORKS HEATING PUMP 0 1-B04 MCC 300 600 3 10 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
2 P 909 A EXISTING DIGESTER HEX HOT WATER RECIRC PUMP 0 1-B04 MCC 300 600 3 1 HP M M E G TYPE 14 2/E022 M M E G E E E G E E E G
0 RH 401 A SCUM HEATER 1 0 TS-4XX HCP 4001 600 1 3.6 KW M M E G INTEGRAL N/A M M E G E E E G E E E G REFER TO SECTION 16850
0 RH 402 A SCUM HEATER 2 0 TS-4XX HCP 4001 600 1 3.6 KW M M E G INTEGRAL N/A M M E G E E E G E E E G REFER TO SECTION 16850 CONSULTANT: www.jlrichards.ca
0 RH 403 A SCUM HEATER 3 0 TS-4XX HCP 6001 600 1 3.6 KW M M E G INTEGRAL N/A M M E G E E E G E E E G REFER TO SECTION 16850
0 RH 404 A SCUM HEATER 4 0 TS-4XX HCP 4004 600 1 3.6 KW M M E G INTEGRAL N/A M M E G E E E G E E E G REFER TO SECTION 16850
0 RH 405 A SCUM HEATER 5 0 TS-4XX HCP 4004 600 1 3.6 KW M M E G INTEGRAL N/A M M E G E E E G E E E G REFER TO SECTION 16850
0 RH 406 A SCUM HEATER 6 0 TS-4XX HCP 4004 600 1 3.6 KW M M E G INTEGRAL N/A M M E G E E E G E E E G REFER TO SECTION 16850
0 RH 407 A SCUM HEATER 7 0 TS-4XX HCP 4007 600 1 3.6 KW M M E G INTEGRAL N/A M M E G E E E G E E E G REFER TO SECTION 16850
CONSULTANT:
0 RH 408 A SCUM HEATER 8 0 TS-4XX HCP 4007 600 1 3.6 KW M M E G INTEGRAL N/A M M E G E E E G E E E G REFER TO SECTION 16850
0 RH 409 A SCUM HEATER 9 0 TS-4XX HCP 4007 600 1 3.6 KW M M E G INTEGRAL N/A M M E G E E E G E E E G REFER TO SECTION 16850
1
2 SCV 201 A SCREENINGS CONVEYOR 0 202 MCP 2001 600 3 2 HP M M E G TYPE 30 1/E022 M M E G M M E G M E E G
2 SCV 801 A SCREW CONVEYOR NO. 1 0 811 MCP 8001 600 3 3 HP M M E G TYPE 30 1/E022 M M E G M M E G M E E G
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475 MSCL.dwg

2 SCV 802 A SCREW CONVEYOR NO. 2 0 811 MCP 8001 600 3 3 HP M M E G TYPE 30 1/E022 M M E G M M E G M E E G
PROFESSIONAL STAMP PROJECT NORTH
2 SF 201 A PIPE GALLERY SUPPLY FAN 0 205 MCC 200 600 3 1 HP M M E G TYPE 70 1/E020 M M E G E E E G E E E G PROVIDE FIRE DETECTION INTERFACE FOR SHUTDOWN
0 SF 202 A ELECTRICAL ROOM SUPPLY FAN 0 205 LP 202 120 1 0.5 HP M M E G INTEGRAL N/A M M E G E E E G E E E G
0 SF 301 A SERVICE BUILDING ELECTRICAL ROOM SUPPLY FAN 0 3XX LP 302 120 1 0.25 HP M M E G INTEGRAL N/A M M E G E E E G E E E G
0 SF 801 A EXISTING DIGESTER CONTROL BUILDING BASEMENT SUPPLY FAN 0 XXX 120 1 0.33 HP M M E G INTEGRAL N/A M M E G E E E G E E E G

PROJECT:

MUNICIPALITY OF NORTH
GENERAL NOTES: GRENVILLE - WATER POLLUTION
LEGEND:
A. FOR ALL HOUSE SYSTEM EQUIPMENT PROVIDE CONDUIT AND WIRING FROM CONTROL PLANT EXPANSION
THE INDICATED SOURCE PANEL OR MCC TO THE LOAD AS PER THE HOUSE
A => Architectural SYSTEM WIRING SCHEDULE E001A. PHASE - -
M => Mechanical Contractor KEMPTVILLE, ONTARIO
E => Electrical Contractor B. FOR POWER SOURCES THAT ARE LABELLED LP or BP THE PANEL SCHEDULES
G => General Contractor WILL GOVERN WHEN CONFLICTS EXIST DRAWING:
PS1 => Process Equipment Supplier/Contractor
MECHANICAL / ELECTRICAL

November 14, 2023 9:50:25 AM


C. FOR POWER SOURCES THAT ARE LABELLED DP or BP, THE PANEL SCHEDULES
WILL GOVERN WHEN CONFLICTS EXIST
SITE-WIDE
D. COORDINATE EXACT LOAD AND WIRE SIZE WITH ACTUAL EQUIPMENT
REQUIREMENTS. MOTOR STARTER & CONTROL LIST
E. WHERE CONFLICTS ARISE REFER TO LAYOUT DRAWINGS FOR SHEET 2 OF 4
EQUIPMENT/DEVICE LOCATIONS.

F. FOR CONFLICTS BETWEEN THIS AND OTHER DRAWINGS REFER TO OTHER DESIGN:
LO
DRAWINGS FOR CLARIFICATION. ADVISE CONSULTANT.
DRAWN: DRAWING #:
IDM

PLOT DATE:
CHECKED:

JLR #:
JO
29475
ME002A
DEMOLISH EXISTING 8.32kV HYDRO POLES WHEN NEW ALTERNATIVE SERVICE IS INSTALLED. REFER TO SPECIFICATIONS AS WELL AS E003A
NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
800 SERIES
NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES

1
NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)

EXISTING SERVICE
BUILDING
300 SERIES

KEY PLAN

1 PHASE A - ADDENDUM #3 10/11/23

0 PHASE A ISSUED FOR TENDER 02/10/23

2
No. ISSUE / REVISION DD/MM/YY

This drawing is copyright protected and may not be reproduced or


used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.

VERIFY SHEET SIZE AND SCALES. BAR TO THE


RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
SCALE:
N.T.S.

1 3 CLIENT:

EXISTING DRAWING
FROM 1994
BY: GORE & STORRIE LIMITED
CONSULTANT: www.jlrichards.ca

CONSULTANT:
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475 DEMO SUBSTATION.dwg

PROFESSIONAL STAMP PROJECT NORTH

DRAWING NOTES:
1 EXISTING BURIED FIBRE OPTIC COMMUNICATIONS IN THIS AREA IS APPROXIMATED AND TO BE LOCATED BY THE
CONTRACTOR. EXISTING FIBRE OPTIC COMMUNICATIONS TO BE PRESERVED AND REMAIN IN SERVICE WITH
GENERAL NOTES: MINIMAL/PLANNED INTERRUPTIONS DURING CONSTRUCTION. RE-ROUTE EXISTING BURIED FIBRE OPTIC
COMMUNICATIONS THROUGH EXISTING TUNNEL TO MAKE WAY FOR THE PLANT EXPANSION. PROVIDE TEMPORARY
A. REFER TO "DE" SERIES DRAWINGS FOR EQUIPMENT TO BE REUSED. UNLESS INDICATED J. DEMOLISH ALL REDUNDANT CONDUITS, CABLE TRAYS, WIRING, SUPPORTS AND APPURTENANCES INSTALLATIONS TO HP-02 UNTIL NEW PERMANENT INSTALLATIONS ARE PROVIDED. REFER TO SPECIFICATIONS AS PROJECT:
OTHERWISE REMOVE ALL ELECTRICAL AND CONTROL WIRING, CONDUITS, CABLE TRAYS, SUPPORTS ASSOCIATED WITH THE REMOVAL OF EQUIPMENT, DEVICES, INSTRUMENTS AND LIGHTING. WELL AS NEW WORKS ELECTRICAL SITE PLAN ON DRAWING E002A AND E003A. DEMOLISH ALL EXPOSED CONDUITS,
ETC. BACK TO SOURCE PANELS. PULL BOXES AND APPURTENANCES ON BUILDING EXTERIOR ASSOCIATED WITH THE EXISTING FIBRE OPTIC CABLE.
MUNICIPALITY OF NORTH
B. UPDATE PANEL SCHEDULES AND SUBMIT UPDATED PANEL SCHEDULES TO THE CONSULTANT.
K. PATCH ALL CONDUIT OPENINGS IN WALLS AND CEILINGS AFFECTED BY THE REMOVAL OF ANY
ELECTRICAL EQUIPMENT, WIRING, CONDUITS, OR APPURTENANCES.
THIS INCLUDES ON THE NORTH SIDE OF THE SERVICE BUILDING. GRENVILLE - WATER POLLUTION
CONTROL PLANT EXPANSION
C. DEMOLITION DRAWINGS ARE BASED ON ORIGINAL INSTALLATION AND DO NOT NECESSARILY L. DEMOLISH WIRING BETWEEN MCC AND EACH LOAD. WHERE A DISCONNECT EXISTS, UPSTREAM OF 2 DEMOLISH GENERATOR EQUIPMENT, CONTROL PANELS, MTS, ATS AND ALL ASSOCIATED WIRING, CONDUITS AND
REFLECT ALL DETAILS, PIPING, CONDUITS, CABLE TRAYS, ETC. TO BE REMOVED. THE LOAD, DEMOLISH WIRING BETWEEN THE MCC AND THE DISCONNECT, AS WELL AS WIRING APPURTENANCES BACK TO SOURCE PANELS. REFER TO SPECIFICATIONS AS WELL AS GENERATOR ROOM DEMOLITION PHASE - A
BETWEEN DISCONNECT AND LOAD, UNLESS OTHERWISE INDICATED. KEMPTVILLE, ONTARIO
PLAN DE311A.
D. CONTRACTOR TO VISIT SITE DURING TENDER TO DETERMINE EXACT SCOPE.
M. RELOCATE, SPLICE, REPLACE AND MODIFY EXISTING WIRING AS REQUIRED TO FACILITATE DRAWING:
E. UNLESS INDICATED OTHERWISE, ALL DEMOLISHED MATERIALS ARE TO BE REMOVED FROM SITE CONSTRUCTION SEQUENCING AND TO MAINTAIN EXISTING SYSTEMS TO FACILITATE THE 3 DEMOLISH SUBSTATION, SWITCHGEAR, ALL CABLES, FENCING, GROUND GRID, POLES AND ALL ASSOCIATED
ELECTRICAL

November 14, 2023 9:52:49 AM


AND DISPOSED OF IN AN APPROVED MANNER. CONSTRUCTION ACTIVITIES. APPURTENANCE TO THE SUBSTATION BACK TO UPSTREAM POLE. COORDINATE WITH HYDRO ONE. REFER TO

F. UNLESS INDICATED OTHERWISE, CONSULT MOTOR STARTER AND CONTROL LIST FOR ITEMS TO N. RE-COMMISSION ANY EXISTING OR ANY MODIFIED SYSTEMS TO CONFIRM PROPER OPERATION TO
SPECIFICATIONS AS WELL AS DRAWINGS DE002A AND DE003A.
N.I.C. PHASE B SITE-WIDE
REMAIN. THE SATISFACTION OF THE OWNER.
4 DEMOLISH EXISTING HEADWORKS AND SCREENING EQUIPMENT, CONTROL PANELS, DEVICES, AND ALL ASSOCIATED
G. DEMOLITION TO BE PHASED TO MAINTAIN PLANT OPERATION AT ALL TIMES. O. AS-CONSTRUCTED DRAWINGS FROM A PREVIOUS PROJECT HAVE BEEN USED AS THE BASE FOR WIRING, CONDUITS AND APPURTENANCES BACK TO SOURCE PANELS. REFER TO SPECIFICATIONS. SITE PLAN DEMOLITION
THE DEMOLITION SCOPE OF WORK. APPLICABLE DRAWING NOTES ARE DENOTED BY A DIAMOND
H. DEMOLISH ALL EXISTING ELECTRICAL EQUIPMENT, DEVICES, INSTRUMENTS, WIRING, CONDUITS AND " X ".
ASSOCIATED APPURTENANCES MADE OBSOLETE BY NEW INSTALLATION. 5 DEMOLISH EXISTING HYDRO SERVICE FOR THE GATE CONTROLLER AND POLE LIGHT. COORDINATE WITH HYRDO ONE.
P. REFER ALSO TO SECTION 16070 FOR ADDITIONAL DEMOLITION REQUIREMENTS. DEMOLISH EXISTING GATE CONTROLS, VEHICLE DETECTION IN-GROUND LOOPS, SENSORS, ASSOCIATED PANELS, DESIGN:
LO
I. REFER TO DRAWINGS OF ALL DISCIPLINES FOR TYPICAL DETAILS FOR MAKING GOOD SURFACES, WIRING, CONDUITS, AND APPURTENANCES BACK TO SOURCE PANELS. REPLACE EXISTING POLE MOUNTED LIGHT DRAWN: DRAWING #:
TERMINATING PIPING, FILLING OPENINGS AND SLEEVES, ETC. Q. REFER TO DP (PROCESS DEMOLITION) AND DM (MECHANICAL DEMOLITION) SERIES DRAWINGS FOR IDM

PLOT DATE:
WITH NEW REPLACEMENT LIGHT. SEE DRAWINGS E002A AND E003A.
ADDITIONAL DEMOLITION SCOPE. COORDINATE WITH DIVISION 15. 1 CHECKED:

JLR #:
JO
29475
DE004A
X
DRAWING NOTES:

X
1 POWER AND FIBRE DUCT BANKS TO BE INSTALLED 3 CONDUITS TO STOP SHORT OF THE TUNNEL WALL BY 4 ROUTE NEW FIBRE CABLE INSIDE THE TUNNEL. 6 DIRECT BURIED RIGID PVC CONDUITS c/w RWU90 8 PROVIDE A NEMA4 PULL BOX FOR POWER AS WELL 10 REFER TO DETAIL 5/E009A FOR FURTHER POLE

X
OVER THE GALLERY ROOF DEPRESSION SLAB. ENSURE 500mm AND SHOULD NOT ENTER THE TUNNEL. COORDINATE EXACT PATH ON-SITE. PROVIDE PULL WIRING AND CAT6 CABLING (RESPECTIVELY) TO AS A NEMA4 PULL BOX FOR COMMUNICATIONS INSIDE REQUIRMENTS. NEW DEWATERING AND ELECTRICAL SERVICE
A MINIMUM COVER OF 100mm OVER TOP OF CONDUITS. PROVIDE AN OPENING IN THE CONDUIT CAP FOR THE BOXES ALONG ROUTE TO SUIT. PULL BOXES TO BE LIGHT STANDARD(s) AND ASSOCIATED CAMERA(s). THE DIGESTER BUILDING BASEMENT FOR TRANSITION DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES

X
ENSURE DUCT BANKS ARE SECURED TO THE ROOF FIBRE CABLE. PROVIDE A REMOVABLE SEAL AROUND NEMA 4 PAINTED STEEL, HAMMOND ECLIPSE SERIES REFER TO DETAIL 7/E007A. MINIMUM CONDUIT SIZE TO OUTSIDE WIRING. ENSURE PULL BOXES ARE NOT 11 REFER TO DETAIL 2/S016A FOR LIGHT POLE 800 SERIES
NEW AERATION NEW PRIMARY NEW
SLAB TO AVOID SHEERING OF THE CONDUITS AND THE CABLE TO PREVENT WATER AND DIRT INGRESS. OR HOFFMAN EQUIVALENT. REFER TO DRAWING OF 53mm BELOW GRADE. LOCATED INSIDE THE SAMPLE ROOM (HAZARDOUS STRUCTURAL SUPPORT TO TANK WALL. COORDINATE TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES

X
REFER TO E003A FOR CONTINUATION. CABLES. COORDINATE WITH STRUCTURAL. ENSURE THE OPENING IN THE CAP DOES NOT N001A. AREA). COORDINATE ON-SITE. REFER TO DRAWING WITH STRUCTURAL. REFER TO DETAIL 3/E010A FOR
DAMAGE THE CABLE. PROVIDE AN IRON STAKE AT 7 CONCRETE ENCASED RIGID PVC CONDUITS c/w E003A. ADDITIONAL POLE REQUIREMENTS.
2 EXACT LOCATIONS OF END POINT TERMINATIONS TO THE END OF THE CONDUITS TO ASSIST WITH FINDING 5 PROVIDE WIRING FOR NEW REPLACEMENT FAN AND RWU90 WIRING AND CAT6 CABLING (RESPECTIVELY)

X
BE DETERMINED AND MODIFIED BY THE CONTRACTOR THE CONDUIT ENDS IN THE FUTURE. THE FIBRE ASSOCIATED DAMPER INSIDE THE EXISTING TO LIGHT STANDARD(s) AND ASSOCIATED CAMERA(s). 9 THE FOLLOWING EQUIPMENT IS LOCATED INSIDE THIS 12 DIRECT BURIED RIGID PVC CONDUITS c/w RWU90 NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
TO SUIT INSTALLATIONS REQUIREMENTS OF THE CABLE TO BE DIRECT BURIED FROM THE CONDUIT DIGESTER BUILDING. REFER TO DETAIL 4/MID802A. REFER TO RETAIL 3/E009A. MINIMUM CONDUIT SIZE BUILDING: WIRING TO LIGHT STANDARD(s). REFER TO DETAIL 700 SERIES (PHASE B)

X
600 SERIES (PHASE B)
GENERATOR MANUFACTURER, AT NO EXTRA COST TO END TO THE TUNNEL. OF 103mm BELOW GRADE. TRANSITION TO SMALLER ATS-001, ATS-002, CP-9000, SB-001, SB-002A, SB-002B, 7/E007A. MINIMUM CONDUIT SIZE OF 53mm BELOW
THE PROJECT. CONDUIT AT POLE. SB-003A, SB-003B GRADE.

X
13 CONTRACTOR TO PROVIDE A MINIMUM SETBACK OF

X
1.5m BETWEEN THE MANHOLE AND THE FACE OF THE EXISTING SERVICE
BUILDING
WALL. COORDINATE WITH CIVIL AND STRUCTURAL. 300 SERIES

X
TO CMH-06 TO TX-001
SLOPE TO CMH-01 SLOPE TO TRANSFORMER BASE
X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X

X
X X X X X X X

1. FIBRE TO SERVICE BLDG FROM HP-04A IN 103mmC


2. COMMUNICATIONS TO SERVICE BLDG FROM HP-04A IN 103mmC KEY PLAN
3. 103mmC SPARE TO HP-04A
4. 103mmC SPARE TO HP-04A
1 2 A
1 2
GENERAL NOTES:
3 4
1 2 3 4 A. ALL BELOW GRADE CONDUIT SYSTEMS ARE CONCRETE
1 2
1 2
ENCASED DUCTS. UNLESS NOTED OTHERWISE, THE
3 4 1. POWER TO MCC-200 IN 103mmC
3 4 TYPICAL CONCRETE ENCASED DUCT BANK SYSTEM TO
3 4 1. POWER IN 103mmC 2. POWER TO MCC-200 IN 103mmC
2. POWER IN 103mmC 3. POWER TO MCC-1 IN 103mmC BE PROVIDED AS A 2 WIDE BY 2 DEEP CONFIGURATION
1. THREE PHASE POWER FROM TX-001 IN 103mmC 3. POWER IN 103mmC 4. 103mmC SPARE WITH 103mmC DUCTS TO OESC REQUIREMENTS.
2. THREE PHASE POWER FROM TX-001 IN 103mmC 1. POWER TO MCC-800 IN 103mmC 4. 103mmC SPARE
3. THREE PHASE POWER FROM TX-001 IN 103mmC 2. POWER TO UP-990 IN 103mmC 1 2
B. REFER TO 3/E009A FOR TYPICAL TRENCHING DETAIL.
4. 103mmC SPARE 3. 103mmC SPARE
4. 103mmC SPARE 3 4
1 2 C. FOR LARGE MAN HOLES (PMH OR CMH) REFER TO
B 2/E009A. FOR SMALL MAN HOLES (PMH OR CMH) REFER
1. FIBRE TO DIGESTER BLDG IN 103mmC 1 2 3 3 4 1. POWER TO MCC-200 IN 103mmC TO 4/E009A.
2. 103mmC SPARE TO DIGESTER BLDG 2. POWER TO MCC-200 IN 103mmC
4 5 6 3. 103mmC SPARE
D. ARRANGEMENT OF WIRING AND CABLES IN THE DUCT
1. POWER TO MCC-300 IN 103mmC 4. 103mmC SPARE
1 2 2. POWER TO MCC-1 IN 103mmC
BANKS SHOWN FOR QUOTATION PURPOSES. FINAL
1. SHORE POWER IN 103mmC 3. 103mmC SPARE ARRANGEMENTS TO BE COORDINATED ON SITE BY THE
LP-802-5 2. DISCRETE ALARMS IN 103mmC 4. 103mmC SPARE CONTRACTOR AND SUBMITTED VIA SHOP DRAWINGS
O1 3. SPARE FOR APPROVAL PRIOR TO INSTALLATION.
4. GEN/ATS START IN 103mmC
5. FIBRE/COMM IN 103mmC
E. ALL BELOW GRADE DUCT BANKS TO SLOPE AWAY FROM
O1 6. SPARE 1 2
LP-802-5 1 2 3 BUILDINGS TOWARDS MAN HOLES/HAND HOLES.
POWER AND CONTROLS VIA
RWU90 WIRING.
4 5 6
PC LP-802-5 1. FIBRE TO HEADWORKS BLDG IN 103mmC F. CONTRACTOR TO COORDINATE FINAL ROUTES OF THE
2. 103mmC SPARE TO HEADWORKS BLDG POWER AND COMMUNICATIONS WIRING TO THE
1. FIBRE TO SERVICE BLDG FROM HP-04A IN 103mmC VARIOUS LIGHT POLES ON-SITE PRIOR TO TRENCHING
2. COMMUNICATIONS TO SERVICE BLDG FROM HP-04A IN 103mmC FM FM FM FM W W
AND INSTALLATION. REFLECT FINAL ROUTES ON THE
GAS

PMH-03:

FM

W
ROUTE 2X2 3. 103mmC SPARE TO HP-04A FM FM FM RED LINE DRAWINGS FOR INCLUSION IN THE AS-BUILT
POWER MANHOLE FM
COMM DUCTS 4. 103mmC SPARE TO HP-04A DRAWINGS.

FM
FM
(SMALL) FM FM FM FM
BELOW 2X2 5. FIBRE TO ELECTRICAL SERVICE ENTRANCE BLDG IN 103mmC
O1 LP-802-5

FM
FM
M W W W W W W

FM
POWER DUCTS 6. 103mmC SPARE TO ELECTRICAL SERVICE ENTRANCE BLDG
G. REFER TO TANK LAYOUT DRAWINGS FOR FURTHER
ABOVE. DRAIN

W
2X2 COMMS TO FM FM FM FM DETAILS ON THE WIRING REQUIREMENTS FOR LIGHT
CMH-01 POLES AT THE TANKS.
O1
DC

DC

O1 11 11 11 11
GAS

DC
GAS

CP-8000 GENERATOR H. REFER TO E014A FOR SURVEILLANCE SYSTEM SITE


LP-802-5 T1 T1 T1 T1 FM FM
MCC-800 PLAN.
8 GEN-001 LP-202-5 FM FM
LP-202-9.1 LP-202-9.1 LP-202-9.1 LP-202-9.1 FM FM
FM I. COORDINATE BURIED SERVICES WITH CIVIL.
D FM
LP-802-5 FM

FM
FM
SLOPE TO PMH-03
FM

O1 O1 LP-202-5 H3 LP-202-5 FM

FM
FM
GAS

FM
GAS

GAS
LP-202-9.1 TOC=90.35
1
SLOPE TO CMH-07
T1 CP-2000
GAS

CMH-07: MCC-200
GAS

LP-802-5 FM FM FM
O1 COMMUNICATIONS
11

FM
FM FM FM

FM
MANHOLE (SMALL)

FM
CMH-01:

FM
COMMUNICATIONS O1 LP-202-5 PC LP-202-5 1 PHASE A - ADDENDUM #3 10/11/23
MANHOLE (LARGE)

FM
FM
FM

D GAS GAS
C 9 2
GAS

FM
LP-802-5 O1
SLOPE TO CMH-02 MECHANICAL SIT TRENCH 0 PHASE A ISSUED FOR TENDER 02/10/23

FM
E LP-202-9.1 LP-202-9.1 LP-202-9.1
PC LP-901-2 LP-202-9.1
LP-202-9.1
GAS

10 No. ISSUE / REVISION DD/MM/YY


LP-202-5 LP-202-5 LP-202-5 LP-202-5 LP-202-5
T1 T1 T1 T1
LP-802-12
S1 S1

FM
This drawing is copyright protected and may not be reproduced or

FM
FM
11 11 11 11

FM
O1
DC

12 1 LP-202-12 LP-202-12 O1 H3 H3 H3 H3 used for purposes other than execution of the described work without
S1
DC

LP-901-2 50mmØ SERVICE WATER the express written consent of J.L. Richards & Associates Limited.
GAS

PA

12
FM

W W
FM NEW 150mmØ WATERMAIN NEW 150mmØ WATERMAIN EX. 150mmØ WATERMAIN VERIFY SHEET SIZE AND SCALES. BAR TO THE

FM
NEW 150mmØ WATERMAIN
WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW WW W WW WW WW WW WW WW WW W RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING.
GAS

10 A B W 0 25mm
EX. 250mmØ PVC SAN FM (EAST QUAD) S1 W
LP-802-12 EX. 200mmØ PVC SAN FORCEMAIN EX. 200mmØ PVC SAN FORCEMAIN SCALE:
FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM AS INDICATED
PA

W
FM SLOPE TO PMH-02
FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM W
FM FM FM

W
FM

FM FM FM FM FM FM FM FM 0 5 10 15 20m
FM FM FM FM FM
GAS

FM FM FM FM FM FM FM FM FM FM FM FM
FM FM
REFER TO E014A FOR CONTINUATION. FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM
FM FM FM FM FM W W CLIENT:
FM FM

W
FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM FM
FM GAS

FM
GAS

EX. 30mmØ NATURAL PIPE EX. 300mmØ EFFLUENT FORCEMAIN EX. 300mmØ EFFLUENT FORCEMAIN
PA

FM FM PMH-02: FM FM FM FM FM
GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS
FM
FM FM POWER MANHOLE NIN
AAI W
(LARGE) EMM

W
FM 1. FIBRE TO DIGESTER BLDG IN 103mmC E
CC FM FM
RR FM

W
FM
2. 103mmC SPARE TO DIGESTER BLDG FFOO
FM FM
T FM
3. FIBRE TO SERVICE BLDG FROM HP-04A IN 103mmC SLOPE TO CMH-02 O1 O1 FMEENNT FM FM FM
PMH-01: LP-701-17 U W
LP-701-17 U

W
4. COMMUNICATIONS TO SERVICE BLDG FROM HP-04A IN 103mmC L
F L W WW WW WW
PA

POWER MANHOLE 13 F
GAS

GAS GAS GAS F


EEF
GAS GAS
5. 103mmC SPARE TO HP-04A
FM

X X
Ø
X X
(LARGE)
X
6. 103mmC SPARE TO HP-04A T1 T1 T1 mmØ CMH-03: CONSULTANT: www.jlrichards.ca
m

W
00m
X

7. FIBRE TO ELECTRICAL SERVICE ENTRANCE BLDG IN 103mmC LP-701-15 LP-701-15 LP-701-15 .3300 COMMUNICATIONS

X
8. 103mmC SPARE TO ELECTRICAL SERVICE ENTRANCE BLDG X.
LP-701-17 EEX MANHOLE (LARGE)

FM
DIGESTER
CMH-02: LP-701-17 1
X

O1

EX. 200mmØ SAN FM

X
COMMUNICATIONS
O1
GAS

1 2 3 4 MANHOLE (LARGE)
GAS
EX. 300mmØ RAW SEWAGE FM

CP-7000

X
FM
5 6 7 8

FM
FM

FM
PC
3 CMH-04: EXISTING SECONDARY CLARIFIERS

X
CONSULTANT:
COMMUNICATIONS T.O.C = 89.70m
MANHOLE (SMALL)
GAS

X
SLOPE TO CMH-02
EXISTING CONTROL 4
FIBRE TO EXISTING DIGESTER BUILDING FROM IT-3000 O1
GAS

& DIGESTER BLDG O1

X
1 2 F.F = 5
89.90 LP-701-17 LP-701-17
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475 SITE PLAN.dwg

CP-3000
FM

EX. 300mmØ RAW


1. FIBRE TO DIGESTER BLDG IN 103mmC MCC-300

SEWAGE FM
GAS

2. 103mmC SPARE TO DIGESTER BLDG GAS


PROFESSIONAL STAMP PROJECT NORTH

FM
EXISTING SERVICE CP-1000
EXISTING SECONDARY CLARIFIERS EXISTING TERITARY BUILDING MCC-1
T.O.C = 89.70m FILTER BUILDING F.F = 89.85 MCC-3
F.F = 89.85 MCC-3B
C 1 2
MECHANICAL SIT TRENCH
GAS

GAS

REFER TO CIVIL DRAWINGS.


FM

FM
1. FIBRE TO ELECTRICAL SERVICES BLDG IN 103mmC EX. 300mmØ RAW SEWAGE FM
2. 103mmC SPARE TO ELECTRICAL SERVICES BLDG

FM
EX. 30mmØ NATURAL GAS HEADER
GAS GAS

O1
GAS GAS GAS GAS GAS GAS GAS GAS GAS

1 2 DIGESTER EX. 100mmØ DIGESTER GAS PIPE


GAS

D GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS LP-302-19
3 4 FM FM FM FM FM FM FM FM FM
FM EX. 300mmØ RAW SEWAGE FM PROJECT:
FM

1. 208V 3-PHASE TO FCP-9000 IN 103mmC MUNICIPALITY OF NORTH


2. UPS POWER TO FCP-9000 IN 103mmC
3. 103mmC SPARE TO FCP-9000 1 2 GRENVILLE - WATER POLLUTION
4. POWER TO POLE MOUNTED LIGHTS IN 103mmC FM
ALL WIRING IN ALL 4 DUCTS TO BE RWU90.
A G
E M
F 3 4 CONTROL PLANT EXPANSION
EW
W
S PHASE - A
RA 1. POWER TO MCC-300 IN 103mmC
FM

1 2 Ø
EXISTING STORAGE KEMPTVILLE, ONTARIO
GARAGE 2. 103mmC SPARE TO SERVICE BLDG
m
E 0 0m 3. POWER TO MCC-1 IN 103mmC DRAWING:
3 4
X .3 M 4. POWER TO MCC-1 IN 103mmC

November 14, 2023 12:42:45 PM


E F
EX. 300mmØ RAW SEWAGE FM ELECTRICAL
FM FM FM FM FM FM FM
1. FIBRE TO FCP-9000 IN 103mmC
1 2 3 4
SITE-WIDE
2. CONTROLS TO FCP-9000 IN 103mmC
3. 103mmC SPARE TO FCP-9000
5 6 7 8
4. CAT6 TO CAMERAS IN103mmC SITE PLAN
1. FIBRE TO HEADWORKS BLDG IN 103mmC
2. 103mmC SPARE TO HEADWORKS BLDG
3. FIBRE TO SERVICE BLDG FROM HP-04A IN 103mmC DESIGN:
4. COMMUNICATIONS TO SERVICE BLDG FROM HP-04A IN 103mmC JJT/LO
5. 103mmC SPARE TO HP-04A DRAWN: DRAWING #:
IDM

PLOT DATE:
6. 103mmC SPARE TO HP-04A
7. FIBRE TO ELECTRICAL SERVICE ENTRANCE BLDG IN 103mmC CHECKED:
8. 103mmC SPARE TO ELECTRICAL SERVICE ENTRANCE BLDG
JLR #:
JO
29475
E002A
SPLICE CONNECTION INSULATION TEE OR SPLICE INSTALLATION
POINT
SEE DETAIL NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
9/E004A. BUILDING 900 SERIES
SEE DETAIL SEE DETAIL 4/E004A 800 SERIES
NEW PRIMARY NEW
PIPE AND SEE NEW AERATION
8/E004A. FOR HEAT TRACE TANKS CLARIFIERS HEADWORKS
INSULATION BY SEE NOTE 500 SERIES 400 SERIES 200 SERIES
SEE INSTALLATION
DIVISION 15 NOTE No.1
NOTE No.2 DETAILS
No.1
HEATING CABLE NEW SECONDARY NEW TERTIARY
HOT COLD END SEAL CLARIFIERS FILTER BUILDING
700 SERIES (PHASE B)
THERMOSTAT SPLICE KIT
600 SERIES (PHASE B)

SEE PIPE STRAP. HEAT TRACE. SEE PIPE STRAP. LP-XXX


NOTE No.1 SEE DETAIL 3/E004A. DETAIL 10/E004A. SEE DETAIL
RTD 3/E004A.
END SEAL XXA GFCI EXISTING SERVICE
MONITORING BUILDING
300 SERIES

SEE DETAIL
SEE DETAIL PIPE STRAP
8/E004A. PIPE INSULATION
6/E004A. BY DIVISION 15
DETAIL NOTES: INSTALL RTD REFER TO PANELBOARD SCHEDULES KEY PLAN
OPPOSITE TO SEE HEATING CABLE
1. PROVIDE A MIN. OF ONE (1) PIPE DIAMETER OF SLACK SEE HEAT TRACE NOTE GENERAL NOTES:
BEFORE AND AFTER COMPONENT AS SHOWN. NOTE No.1
No.2 A. FINAL QUANTITIES INDICATED UNDER THE
2. PROVIDE RIGID T-CONNECTOR AND CONDUIT DRAIN 'INSTALLATION NOTES' SECTION OF THE HEAT TRACE
PLUG BEFORE TERMINATING TO COMPONENT WITH SCHEDULE ARE TO BE CONFIRMED ON SITE PRIOR TO
FLEXIBLE CONDUIT. (NOT REQUIRED IF FED WITH INSTALLATION.
PIPE STRAP. PIPE STRAP.
TECK90 CABLE).
SEE DETAIL SEE DETAIL B. INSTALL ADDITIONAL HEAT TRACE AT ALL HEAT SINK
3/E004A. 3/E004A. LOCATIONS. ENSURE HEAT TRACE CAN BE
UNWRAPPED FROM IN-LINE EQUIPMENT FOR FUTURE

1 TYPICAL HEAT TRACE INSTALLATION DIAGRAM 2 HEAT TRACE CABLE GENERAL SCHEMATIC 11 RESERVED MAINTENANCE / REPLACEMENT.

E004A SCALE: NTS SCALE: NTS


SCALE: NTS E004A C. PROVIDE SPLICE KITS ON EACH SIDE OF VALVES AND
E004A
OTHER IN-LINE EQUIPMENT FOR EASE OF FUTURE
MAINTENANCE / REPLACEMENT.

X. D. ENSURE SITE ACCEPTANCE TESTING BY THE HEAT


AT A MA PROVIDE END SEAL FOR HEATING CABLE, c/w TRACE MANUFACTURER OCCURS BEFORE
AP
STR F 300mm COLD-APPLIED HEATING CABLE CORE SEAL. INSTALLATION OF INSULATION.
O
E. ELECTRICAL HEAT TRACE SCHEDULE TO BE READ IN
CE CONJUNCTION WITH PROCESS/MECHANICAL AND
T TRA
HEA ELECTRICAL DRAWINGS INDICATED IN SCHEDULE
PROVIDE STAINLESS BELOW.
19mm CONDUIT DRAIN
STEEL PIPE STRAPS TO
PLUG.
ATTACH HEAT TRACE F. PROVIDE ADDITIONAL CIRCUITS AS REQUIRED DUE TO
COMPONENTS. SIZE TO 6 END SEAL CONNECTION DEVICE ADDITIONAL CABLING WHICH MAY BE REQUIRED FOR
SUIT PIPE DIAMETER. LARGER DIAMETER PIPES.
STRAP WITH RAYCHEM E004A SCALE: NTS
GT-66 GLASS TAPE AS
SHOWN. (TYPICAL). G. NUMBER OF POWER CONNECTION ITEMS TO SUIT.

12 HEAT TRACING - PIPE SUPPORT


3 PIPE STRAP 4 STRAPPING 5 CONDUIT DRAIN CONNECTOR E004A SCALE: NTS

E004A SCALE: NTS E004A SCALE: NTS E004A SCALE: NTS

FLUOROPOLYMER OUTER JACKET

TINNED-COPPER BRAIDED GROUND

MODIFIED POLYOLEFIN INNER JACKET


WARNING
SELF REGULATING CONDUCTIVE CORE
PROVIDE POWER CONNECTION DEVICE FOR PROVIDE TEE OR SPICE CONNECTION FOR UP
1 PHASE A - ADDENDUM #3 10/11/23
ELECTRIC HEAT ONE HEATING CABLE, c/w COLD-APPLIED TO THREE HEATING CABLES, c/w SPACER
HEATING CABLE CORE SEAL. COLD-APPLIED HEATING CABLE CORE SEAL.
TRACE NICKEL PLATED COPPER BUS WIRE 0 PHASE A ISSUED FOR TENDER 02/10/23

PROVIDE ELECTRIC HEAT TRACE WARNING No. ISSUE / REVISION DD/MM/YY


LABEL ON EXTERIOR OF INSULATION AT 3m FIBRE WRAPPED HEATING CABLE. INDIVIDUAL POWER OUTPUT RATINGS WILL
INTERVALS. (TYPICAL). This drawing is copyright protected and may not be reproduced or
INDICATED ON LAYOUT DRAWINGS. (TYPICAL).
used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.
SPLICE OR TEE
VERIFY SHEET SIZE AND SCALES. BAR TO THE
7 ELECTRIC HEAT TRACE WARNING 8 POWER CONNECTION DEVICE 9 CONNECTION DEVICE 10 HEAT TRACE CABLE 13 HEAT TRACING - PIPE FLANGE 14 HEAT TRACING - VALVE RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
E004A SCALE: NTS E004A SCALE: NTS E004A SCALE: NTS E004A SCALE: NTS E004A SCALE: NTS E004A SCALE: NTS SCALE:
NTS

CLIENT:
HEAT TRACE SCHEDULE

REFERENCE INFORMATION RESPONSIBILITY MECHANICAL SPECIFICATION ENVIRONMENTAL SPECIFICATION ELECTRICAL SPECIFICATION INSTALLATION NOTES

CONSULTANT: www.jlrichards.ca

NUMBER OF POWER CONNECTION SPLICES


NUMBER OF POWER CONNECTIONS, TEES
TEMPERATURE HEAT TRACE OUTER SOURCE APPROVED FOR NUMBER OF
PIPE INFORMATION INSULATION INFORMATION CONTROLS
PARAMETERS JACKET TYPE VOLTAGE INSTALLATION VALVES AND TYPE

NUMBER OF PIPE SHOE SUPPORTS


POWER SOURCE (PANELBOARD)
EXPOSURE TEMPERATURE (°C)

FORM C CONTACT FOR ALARM


CIRCUIT PROTECTIVE DEVICE
MAINTAIN TEMPERATURE (°C)
SUITABLE FOR CLASS 1 DIV 2

PIPE MOUNTED ELECTRONIC

AMBIENT AIR TEMPERATURE


POLYOLEFIN OUTER JACKET

EXTERIOR OF PIPE, UNDER


PIPE MOUNTED / SURFACE
FLUOROPOLYMER OUTER

PIPE TEMPERATURE RTD


MAXIMUM INTERMITTENT
HAZARDOUS LOCATIONS

MOUNTED MECHANICAL
HEAT TRACE STARTING

SIZE (DIAMETER IN mm)

LIGHTED END SEAL KIT


PIPE IDENTIFIER AT

CONSULTANT:

120V, SINGLE-PHASE

208V, SINGLE-PHASE
MINIMUM START-UP
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475 HEAT TRACE DETAILS.dwg

TEMPERATURE (°C)

INTERIOR OF PIPE

PIPE LENGTH (m)


THICKNESS (mm)
[MAIN / BRANCH]

DIAMETER (mm)

DIAMETER (mm)
ANNUNCIATION
POINT

CONTROLS BY
INSTALLED BY

THERMOSTAT
CONTROLLER
START-UP BY
SUPPLIED BY

RTD SENSOR

INSULATION
RATING (A)

QUANTITY

QUANTITY
MATERIAL
WIRED BY

SENSOR
JACKET
FINISH
TYPE

DRAWING HEAT TRACE DESCRIPTION GRID LOCATION OTHER


No. REFERENCE THERMOSTAT OF SYSTEM START POINT REFERENCE NOTES
1 100-SS-SAN PID201/P201 TC-2010 ADMIN BUILDING - FORCE MAIN ZONE 2 REFER TO E201A FOR PANEL SCHEDULE. PROFESSIONAL STAMP PROJECT NORTH
E E E E E 100 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET 10 -40 35 15A LP-202 2 100 -- -- --
2 250-SS-RSE PID201/P201 TC-2012 RAW SEWAGE - FORCE MAIN E E E E E 250 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-202 2 250 -- -- -- REFER TO E201A FOR PANEL SCHEDULE.
3 250-SS-RSE PID201/P201 TC-2013 RAW SEWAGE - FORCE MAIN E E E E E 250 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-202 2 250 -- -- -- REFER TO E201A FOR PANEL SCHEDULE.
4 250-SS-RSE PID201/P201 TC-2014 RAW SEWAGE - FORCE MAIN E E E E E 250 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-202 2 250 -- -- -- REFER TO E201A FOR PANEL SCHEDULE.
5 300-SS-RSE PID201/P201 TC-2015 RAW SEWAGE - FORCE MAIN E E E E E 300 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-202 2 300 -- -- -- REFER TO E201A FOR PANEL SCHEDULE.
6 300-SS-RSE PID201/P201 TC-2016 RAW SEWAGE - FORCE MAIN E E E E E 300 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-202 2 300 -- -- -- REFER TO E201A FOR PANEL SCHEDULE.
7 250-SS-RSE PID201/P201 TC-2017 RAW SEWAGE - FORCE MAIN E E E E E 250 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-202 2 250 -- -- -- REFER TO E201A FOR PANEL SCHEDULE.
8 200-SS-STM MID201/M201 TC-2030 HEADWORKS STORM - GRAVITY DRAINED E E E E E 200 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-202 2 200 -- -- -- REFER TO E201A FOR PANEL SCHEDULE. REFER TO 5/PM009A .
9 100-DI-SCM PID401/P402 TC-4030 SCUM COLLECTOR - PUMPED E E E E E 100 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-202 21 100 1 -- -- 1 REFER TO E201A FOR PANEL SCHEDULE.
10 100-CI-STM MID701 TC-7011 TERTIARY STORM - GRAVITY DRAINED E E E E E 15A LP-701 REFER TO E302A FOR PANEL SCHEDULE. REFER TO 5/PM009A .
11 100-SS-DG PID802 TC-8020 DIGESTER GAS - TO BURNER E E E E E 100 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-803 20 100 2 -- -- 1 REFER TO E802A FOR PANEL SCHEDULE.
PROJECT:
12 100-SS-DG PID802 TC-8030 DIGESTER GAS - ON DIGESTER ROOF E E E E E 100 SS 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-803 12 100 -- -- -- REFER TO E802A FOR PANEL SCHEDULE.
13 150-CI-STM MID802 TC-8050 DIGESTER BUILDING STORM - GRAVITY DRAINED E E E E E 150 CI 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-803 -- 2 150 -- -- -- REFER TO E802A FOR PANEL SCHEDULE. REFER TO 5/PM009A .
MUNICIPALITY OF NORTH
14 100-CI-STM MID901 TC-9010 ELECTRICAL SUBSTATION STORM - GRAVITY DRAINED E E E E E 150 CI 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-902 -- 2 150 -- -- -- 1 REFER TO E911A FOR PANEL SCHEDULE. REFER TO 5/PM009A . GRENVILLE - WATER POLLUTION
15 25-CU-CND MID901 TC-9011 ELECTRICAL SUBSTATION AC CONDENSATE - GRAVITY DRAINED E E E E E 25 CU 50 IP-5 FOAM GLASS ALUMINIUM JACKET ZONE 2 10 -40 35 15A LP-902 2 100 -- -- -- REFER TO E911A FOR PANEL SCHEDULE.
16 100-CI-STM MID701 TC-7012 EXISTING TUNNEL STORM - GRAVITY DRAINED E E E E E 15A LP-701 REFER TO E302A FOR PANEL SCHEDULE. REFER TO 5/PM009A .
CONTROL PLANT EXPANSION
17 100-SS-RSE PID802 TC-8032 DIGESTER GAS - GRAVITY DRAINED E E E E E 15A LP-803 1 REFER TO E802A FOR PANEL SCHEDULE. PHASE - A
18 25-SS-DR PID802 TC-8034 FLAME ARRESTOR - ON DIGESTER ROOF E E E E E 25 SS 50 10 -40 35 15A LP-803 REFER TO E802A FOR PANEL SCHEDULE. KEMPTVILLE, ONTARIO
DRAWING:

ELECTRICAL

November 14, 2023 2:54:26 PM


SITE-WIDE
15 HEAT TRACE SCHEDULE
E004A SCALE: NTS HEAT TRACE DETAILS

DESIGN:
LO/MM
DRAWN: DRAWING #:
MM

PLOT DATE:
CHECKED:

JLR #:
JO
29475
E004A
NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
800 SERIES
NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES

NEW SECONDARY NEW TERTIARY


CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)

EXISTING SERVICE
BUILDING
300 SERIES
GOOSENECK WALL BRACKET

KEY PLAN

PROVIDE ADEQUATE WEATHER


PROOF GASKET/SEALANT TO
PREVENT WATER INGRESS

PROVIDE ADEQUATE WEATHER PARAPET


ALUMINUM POLE PROOF GASKET/SEALANT TO
PREVENT WATER INGRESS
FASTENERS TO BE MINIMUM
200mm FROM ROOF MEMBRANE
PROVIDE ADEQUATE WEATHER
PROOF GASKET/SEALANT TO
PREVENT WATER INGRESS

OUTDOOR CCTV CAMERA


MOUNT BRACKET
WALL

OUTDOOR DOME
CAMERA

2 EXTERIOR WALL MOUNTED CAMERA DETAIL 3 PARAPET MOUNTED CAMERA DETAIL


1 POLE MOUNTED CAMERA DETAIL E008A SCALE: N.T.S. E008A SCALE: N.T.S.

E008A SCALE: N.T.S.

1 PHASE A - ADDENDUM #3 10/11/23

0 PHASE A ISSUED FOR TENDER 02/10/23


DETAIL NOTES:
No. ISSUE / REVISION DD/MM/YY
1. REFER TO CIVIL AND STRUCTURAL FOR FURTHER DETAILS PROVIDE DETECTION LOOP CONTROLLER CABLING INSTALLED
PROVIDE 2x INTERCOM (TYPE AIPHONE IX-DV) AND COMPATIBLE This drawing is copyright protected and may not be reproduced or
2. LIGHT STANDARD AND HYDRO POLE NOT SHOWN. REFER TO
AT DEPTH TO SUIT MANUFACTURER REQUIREMENTS TIED TO ℄ ℄ CARD READER AT GATE PEDESTAL MOUNTED AT 1016mm AND used for purposes other than execution of the described work without
GATE CONTROLLER. PROGRAM GATE CONTROLLER TO GATE CONTROL PEDESTAL 305mm
SITE PLAN ON DRAWING E003A. 2235mm A.F.G. FOR CAR AND TRUCK TRAFFIC. RUN CAT6 CABLE the express written consent of J.L. Richards & Associates Limited.
AUTOMATICALLY OPEN GATE UPON VEHICLE DETECTION AT
AND CONDUIT TO FCP-9000. PROVIDE ASSOCIATED NEMA 4X


LOOP. GATE OPERATION SHOULD NOT REQUIRE CARD VERIFY SHEET SIZE AND SCALES. BAR TO THE
3. PROVIDE OCAL CONDUITS BETWEEN THE GATE WEATHERPROOF ENCLOSURE AND ALL ASSOCIATED RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING.
ACCESS AT SECURE SIDE PEDESTAL. 0 25mm
CONTROLLER (FCP-9001) AND FCP-9000 FOR POWER AND APPURTENANCES TO SUIT.

1422mm
COMMUNICATIONS. SCALE:
N.T.S.
SECURE SIDE VEHICLE DETECTION LOOP


4. CONTROL CABLE BENEATH TRAFFIC AREAS TO BE RUN IN
CONCRETE ENCASED CONDUIT.
1


CLIENT:
5. COORDINATE FINAL DIMENSIONS WITH GATE CONTROLS
MANUFACTURER. PROVIDE 208V 3 PHASE CIRCUIT FROM PANEL LP-900 FOR
NEW GATE OPERATOR (FCP-9001).
6. REFER TO SECTION 16895 FOR FURTHER DETAILS.

2023mm
TYPICAL BOLLARD, REFER TO STRUCTURAL

3962mm
7. CONTRACTOR TO PROVIDE A CENTRAL INTERCOM STATION
INSIDE THE MAIN SCADA CONTROL ROOM, AS INDICATED IN
DRAWING E311A. THE GATE CONTROL SYSTEM SUPPLIER ℄

3048mm
TO PROVIDE END-TO-END VERIFICATION AND CONSULTANT: www.jlrichards.ca
COMMISSIONING OF THE ENTIRE GATE CONTROL SYSTEM,
INCLUDING COMMUNICATION WITH THE CENTRAL INTERCOM


STATION.
℄ 7468mm ℄ 2743mm ℄ 7315mm CLEAR MINIMUM

1219mm
FCP-9000
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 ELECTRICAL DETAILS.dwg


CONSULTANT:

1219mm

1219mm
TYPICAL GATE FOUNDATION, REFER TO STRUCTURAL
OPEN PHOTOEYE OPEN PHOTOEYE CLOSE PHOTOEYE CLOSE PHOTOEYE
REST POST PROVIDE POWER TO FCP-9000 FROM LP-802 AND UP-890.
REFER TO E002A AND E802A. PROVIDE COMMUNICATIONS TYPICAL BOLLARD, REFER TO STRUCTURAL
CENTRE LINE OF GATE


TO FCP-9000 VIA FIBRE CABLING. REFER TO E002A AND
3048mm

N001A.
PROFESSIONAL STAMP PROJECT NORTH

8962mm
5006mm

7029mm

HYDRO ACCESS ROAD

VEHICLE DETECTION LOOP PROJECT:

MUNICIPALITY OF NORTH
℄ GRENVILLE - WATER POLLUTION
GATE CONTROL PEDESTAL CONTROL PLANT EXPANSION

PHASE - A
1422mm

KEMPTVILLE, ONTARIO
PUBLIC SIDE

DRAWING:

November 14, 2023 10:15:37 AM


PROVIDE 2X INTERCOM (TYPE AIPHONE IX-DV) AND COMPATIBLE PROVIDE DETECTION LOOP CONTROLLER CABLING INSTALLED AT
ELECTRICAL

CARD READER AT GATE PEDESTAL MOUNTED AT 1016MM AND DEPTH TO SUIT MANUFACTURER REQUIREMENTS TIED TO GATE SITE-WIDE
2235MM A.F.G. FOR CAR AND TRUCK TRAFFIC. RUN CAT6 CABLE CONTROLLER. PROGRAM GATE CONTROLLER TO AUTOMATICALLY

305mm
AND CONDUIT TO FCP-9000. PROVIDE ASSOCIATED NEMA 4X
WEATHERPROOF ENCLOSURE AND ALL ASSOCIATED
OPEN GATE ONCE ACCESS HAS BEEN GRANTED VIA THE CARD
READER SYSTEM. GATE OPERATION REQUIRES CARD ACCESS AT
SECURITY & ACCESS CONTROL
APPURTENANCES TO SUIT. PUBLIC SIDE PEDESTAL. DETAILS

DESIGN:
MM/LO
4 SECURITY GATE DETAIL DRAWN: DRAWING #:
MM

PLOT DATE:
E008A SCALE: NTS
CHECKED:

JLR #:
JO
29475
E008A
TOTAL LINKS

TOTAL LINKS
EC5 EC5
TABLE OF PANEL AND ELECTRICAL EQUIPMENT TABLE OF PANEL AND ELECTRICAL EQUIPMENT

PROJECT
EngCAD Database Data Exported on: 2023-11-13 8:05:53 PM EngCAD Database Data Exported on: 2023-11-13 8:05:53 PM

PROJECT
PHASE

PHASE
DEVICE DEVICE FIELD WORK DEVICE DEVICE FIELD WORK NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
TAG SERVICE DWG / SPEC SUPPLY INSTALL WIRE COMM. TAG SERVICE DWG / SPEC SUPPLY INSTALL WIRE COMM. BUILDING 900 SERIES
800 SERIES
IDENTIFIER DESCRIPTION LOCATION DETAIL AMPS kAIC VOLTS Ø W BY BY BY BY IDENTIFIER DESCRIPTION LOCATION DETAIL AMPS kAIC VOLTS Ø W BY BY BY BY NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES
4 ATS 001 AUTOMATIC TRANSFER SWITCH #1 ELECTRICAL SERVICE ENTRANCE BUILDING E011A 600 3 3 E E E G A 3 LCP 8002 E-STOP CONTROL PANEL NEW DIGESTER BUILDING PROCESS AREA PID803A / I017A [ 1, 7, 22 ] CSS E E G A
4 ATS 002 AUTOMATIC TRANSFER SWITCH #2 ELECTRICAL SERVICE ENTRANCE BUILDING E010A 600 3 3 E E E G A 3 LCP 8013 DIGESTER MIXER CONTROL PANEL NEW DIGESTER BUILDING DIGESTER ROOF PID801A / I017A [ 1, 2, 22 ] CSS E E G A
3 ATS 390 AUTOMATIC TRANSFER SWITCH ELECTRICAL SERVICE BUILDING (UPS-390) SERVICE BUILDING ELECTRICAL ROOM E301A 208 3 4 E E E G A 3 LCP 8018 P-807 / 808 DIGESTER RECIRC. PUMP CONTROL PANEL NEW DIGESTER BUILDING BASEMENT PID801A / I017A [ 1, 2, 3, 4, 22 ] CSS E E G A NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
700 SERIES (PHASE B)
2 CP 1000 EXISTING SERVICE BLDG CONTROL PANEL SERVICE BUILDING ELECTRICAL ROOM I304A 120 1 2 EX EX E G A 3 LCP 8019 P-809 HOT WATER RECIRC. PUMP CONTROL PANEL NEW DIGESTER BUILDING BASEMENT PID801A / I017A [ 1, 2 ] CSS E E G A 600 SERIES (PHASE B)

5 CP 2000 HEADWORKS PLC PANEL HEADWORKS ELECTRICAL ROOM I013A, I014A 120 1 2 CSS E E G A 3 LCP 8020 DIGESTER MAKE-UP AIR UNIT CONTROL PANEL EXTERIOR MID801A / I017A [ 1, 2, 3, 4 ] CSS E E G A
4 CP 2001 SCREENING PLC PANEL HEADWORKS ELECTRICAL ROOM PID201A, SECTION 17052 120 1 2 M E E G A 3 LCP 8021 DIGESTER ODOUR CONTROL UNIT CONTROL PANEL EXTERIOR MID801A / I017A [ 1, 2, 3, 4 ] CSS E E G A
4 CP 2002 DEGRIT PLC PANEL HEADWORKS ELECTRICAL ROOM PID202A, SECTION 17052 120 1 2 M E E G A 3 LCP 8022 HEATING LOOP PUMP CONTROL PANEL NEW DIGESTER BUILDING BASEMENT MID801A / I017A [ 1, 2 ] CSS E E G A EXISTING SERVICE
BUILDING
300 SERIES
1 CP 2003 UPS POWER CONTROL PANEL HEADWORKS ELECTRICAL ROOM 4/E007A, I017A [1,2,12,13, 22] 208 1 3 CSS E E G A 3 LCP 8023 GLYCOL HEATING PUMP CONTROL PANEL NEW DIGESTER BUILDING BASEMENT MID801A / I017A [ 1, 2 ] CSS E E G A
12 CP 2004 HEADWORKS LIGHTING & VENTILATION CONTROL PANEL HEADWORKS ELECTRICAL ROOM 9/E006A, 5/E007A, 6/E007A, I017A [1,2,5,8,12,13,19, 23] 120 1 2 CSS E E G A 3 LCP 8031 SLUDGE TANK MIXER CONTROL PANEL EXTERIOR PID803A / I017A [ 1, 2 ] CSS E E G A
5 CP 3000 SERVICE BUILDING PLC PANEL SERVICE BUILDING ELECTRICAL ROOM I013A, I014A 120 1 2 CSS E E G A 3 LCP 8032 CENTRATE PUMPS CONTROL PANEL NEW DIGESTER BUILDING PROCESS AREA PID803A / I017A [ 1, 2, 3, 4 ] CSS E E G A
KEY PLAN
13 CP 3004 SERVICE BUILDING LIGHTING & VENTILATION CONTROL PANEL SERVICE BUILDING ELECTRICAL ROOM 9/E006A, 5/E007A, 6/E007A, I017A [1,2,5,8,12,13,19, 23] 120 1 2 CSS E E G A 2 LCP 8051 DIGESTER BUILDING SUMP PUMP CONTROL PANEL NEW DIGESTER BUILDING BASEMENT MID802A, SECTION 17052 M E E G A
5 CP 8000 DIGESTER PLC PANEL NEW DIGESTER BUILDING I&C ROOM I012A 120 1 2 CSS E E G A 3 LCP 9001 BOILER FEED PUMPS LOCAL CONTROL PANEL SERVICE BUILDING BOILER ROOM MID001A / I017A [ 1, 2 ] CSS E E G A
LEGEND:
6 CP 8001 CENTRIFUGE PLC PANEL NEW DIGESTER BUILDING I&C ROOM PID803A, SECTION 17052 120 1 2 M E E G A 2 LCP 9002 HOT WATER PUMP LOCAL CONTROL PANEL SERVICE BUILDING BLOWER ROOM MID001A / I017A [ 1, 2 ] CSS E E G A G: GENERAL CONTRACTOR
E: ELECTRICAL CONTRACTOR
1 CP 8003 UPS POWER CONTROL PANEL NEW DIGESTER BUILDING I&C ROOM 4/E007A, I017A [1,2,12,13] 208 1 3 CSS E E G A 3 LCP 9011 BOILER #1 E-STOP LOCAL CONTROL PANEL SERVICE BUILDING BOILER ROOM MID002A, SECTION 17052 M E E G A M: MECHANICAL CONTRACTOR
12 CP 8004 DIGESTER LIGHTING & VENTILATION CONTROL PANEL NEW DIGESTER BUILDING I&C ROOM 9/E006A, 5/E007A, 6/E007A, I017A [1,2,5,8,12,13,19, 23] 120 1 2 CSS E E G A 3 LCP 9021 BOILER #2 E-STOP LOCAL CONTROL PANEL SERVICE BUILDING BOILER ROOM MID002A, SECTION 17052 M E E G A EX: EXISTING
CSS: CONTROL SYSTEM SPECIALIST
2 CP 8005 POLYMER SYSTEM CONTROL PANEL NEW DIGESTER BUILDING PROCESS AREA PID803A, SECTION 17052 120 1 2 M E E G A 3 LCP 9031 BOILER #3 E-STOP LOCAL CONTROL PANEL SERVICE BUILDING BOILER ROOM MID002A, SECTION 17052 M E E G A FTE: FLOAT TIPPING ELEVATION
0 CP 8100 EXISTING DIGESTER BUILDING CONTROL PANEL EXISTING DIGESTER BUILDING N001A 120 1 2 EX EX E G A 3 LCP 9040 PRIMARY HEATING PUMPS LOCAL CONTROL PANEL SERVICE BUILDING BLOWER ROOM MID001A / I017A [ 1, 2, 3, 4 ] E E E G A SSS: SECURITY SYSTEM SPECIALIST
FDS: FIRE DETECTION SYSTEM SPECIALIST
5 CP 9000 ELECTRICAL SERVICE ENTRANCE BUILDING PLC PANEL ELECTRICAL SERVICE ENTRANCE BUILDING I015A 120 1 2 CSS E E G A 4 LD-BL 501 NEW PROCESS AIR BLOWER #1 DISCONNECT HEADWORKS PIPE GALLERY E201A 600 3 3 E E E G A
1 CP 9004 ELECTRICAL SERVICE BUILDING LIGHTING & VENTILATION CONTROL PANEL ELECTRICAL SERVICE ENTRANCE BUILDING 9/E006A, 5/E007A, 6/E007A, I017A [1,2,5,8,12,13,19, 23] 120 1 2 E E E G A 4 LD-BL 502 NEW PROCESS AIR BLOWER #2 DISCONNECT HEADWORKS PIPE GALLERY E201A 600 3 3 E E E G A GENERAL NOTES:
3 DP 201 HEADWORKS DISTRIBUTION PANEL HEADWORKS ELECTRICAL ROOM E202A 600 3 3 E E E G A 4 LD-BL 503 NEW PROCESS AIR BLOWER #3 DISCONNECT HEADWORKS PIPE GALLERY E201A 600 3 3 E E E G A A. REFERENCES ON DRAWING I017A PERTAIN TO
GROUPS OF COMPONENTS TO BE PROVIDED FOR
2 DP 301 SERVICE BUILDING DISTRIBUTION PANEL SERVICE BUILDING ELECTRICAL ROOM E302A 600 3 3 E E E G A 4 LD-CC 401 PRIMARY CLARIFIER #1 CROSS COLLECTOR DISCONNECT PRIMARY TANK #1 E201A 600 3 3 E E E G A
THAT PANEL. CONTRACTOR TO DESIGN THE PANEL
3 DP 801 DIGESTER DISTRIBUTION PANEL NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 600 3 3 E E E G A 4 LD-CC 402 PRIMARY CLARIFIER #2 CROSS COLLECTOR DISCONNECT PRIMARY TANK #1 E201A 600 3 3 E E E G A USING THOSE COMPONENTS, AS OUTLINED IN THE
BILL OF MATERIALS ON DRAWING I017A.
3 DP 901 ELECTRICAL SERVICE ENTRANCE BUILDING DISTRIBUTION PANEL ELECTRICAL SERVICE ENTRANCE BUILDING E911A 600 3 3 E E E G A 4 LD-CC 403 PRIMARY CLARIFIER #3 CROSS COLLECTOR DISCONNECT PRIMARY TANK #1 E201A 600 3 3 E E E G A
3 FCP 8050 FLARE PILOT CONTROL PANEL EXTERIOR PID802A, SECTION 17052 M E E G A 4 LD-CNT 801 CENTRIFUGE MAIN DRIVE DISCONNECT NEW DIGESTER BUILDING PROCESS AREA E801A 600 3 3 E E E G A B. FOR PANELS SUPPLIED BY THE MECHANICAL
CONTRACTOR, REFER TO PERTINENT DIVISION 11 OR
1 FCP 9000 GATE FIELD CONTROL PANEL EXTERIOR I016A 208 3 4 CSS E E G A 4 LD-CNT 802 CENTRIFUGE BACK DRIVE DISCONNECT NEW DIGESTER BUILDING PROCESS AREA E801A 600 3 3 E E E G A DIVISION 15 SPECIFICATIONS.
0 FCP 9001 GATE CONTROLLER PANEL EXTERIOR 208 3 4 G E E G A 4 LD-EF 201 ELECTRICAL ROOM EXHAUST FAN DISCONNECT HEADWORKS ELECTRICAL ROOM E201A 600 3 3 E E E G A
C. NOTE THAT NOT ALL DISCONNECTS ARE SHOWN IN
3 FCP 9010 BOILER #1 FIELD CONTROL PANEL SERVICE BUILDING BOILER ROOM MID002A, SECTION 17052 600 3 3 M E E G A 4 LD-EF 302 HEATING PUMP ROOM EXHAUST FAN DISCONNECT SERVICE BUILDING MECHANICAL ROOM E301A 600 3 3 E E E G A THIS TABLE. REFER TO E000A AND OTHER DRAWINGS
FOR FURTHER DETAILS.
3 FCP 9020 BOILER #2 FIELD CONTROL PANEL SERVICE BUILDING BOILER ROOM MID002A, SECTION 17052 600 3 3 M E E G A 4 LD-EF 303 BOILER ROOM EXHAUST FAN DISCONNECT SERVICE BUILDING BOILER ROOM E301A 600 3 3 E E E G A
3 FCP 9030 BOILER #3 FIELD CONTROL PANEL SERVICE BUILDING BOILER ROOM MID002A, SECTION 17052 600 3 3 M E E G A 4 LD-GC 201 GRIT CLASSIFIER DISCONNECT HEADWORKS SCREEN AND DEGRIT ROOM E202A 600 3 3 E E E G A D. NOTE THAT ADDITIONAL PULL BOXES MAY BE
REQUIRED BASED ON SITE CONDITIONS.
2 FDP 2001 HEADWORKS FIRE DETECTION PANEL HEADWORKS ELECTRICAL ROOM SECTION 16899 FDS E E G A 4 LD-LC 401 PRIMARY CLARIFIER #1 LONGITUDINAL COLLECTOR DISCONNECT PRIMARY TANK #1 E201A 600 3 3 E E E G A CONTRACTOR TO PROVIDE SUCH ADDITIONAL PULL
2 FDP 8001 DIGESTER FIRE DETECTION PANEL NEW DIGESTER BUILDING ELECTRICAL ROOM SECTION 16899 FDS E E G A 4 LD-LC 402 PRIMARY CLARIFIER #2 LONGITUDINAL COLLECTOR DISCONNECT PRIMARY TANK #1 E201A 600 3 3 E E E G A BOXES, AS REQUIRED.

3 GEN 001 STANDBY GENERATOR EXTERIOR E011A, SECTION 16622 600 3 4 E E E G A 4 LD-LC 403 PRIMARY CLARIFIER #3 LONGITUDINAL COLLECTOR DISCONNECT PRIMARY TANK #1 E201A 600 3 3 E E E G A
2 GEN ANUN GENERATOR ANNUNCIATOR PANEL ELECTRICAL SERVICE ENTRANCE BUILDING SECTION 16622 E E E G A 4 LD-MAU 201 MAKEUP AIR UNIT DISCONNECT EXTERIOR E201A 600 3 3 E E E G A
2 GEN REPO GENERATOR REPO PANEL ELECTRICAL SERVICE ENTRANCE BUILDING SECTION 16622 E E E G A 4 LD-MAU 801 DIGESTER MAKE-UP AIR UNIT DISCONNECT NEW DIGESTER BUILDING DIGESTER ROOF E801A 600 3 3 E E E G A
2 HCP 4001 PRIMARY CLARIFIER TANK NO. 1 SCUM HEATERS HEATER CONTROL PANEL HEADWORKS ELECTRICAL ROOM I017A [ 1, 2, 5, 12, 13, 20, 21, 22 ] 600 3 3 E E E G A 4 LD-MIX 201 GRIT TANK MIXER #1 DISCONNECT HEADWORKS SCREEN AND DEGRIT ROOM E202A 600 3 3 E E E G A
2 HCP 4004 PRIMARY CLARIFIER TANK NO. 2 SCUM HEATERS HEATER CONTROL PANEL HEADWORKS ELECTRICAL ROOM I017A [ 1, 2, 5, 12, 13, 20, 21, 22 ] 600 3 3 E E E G A 4 LD-MIX 202 GRIT TANK MIXER #2 DISCONNECT HEADWORKS SCREEN AND DEGRIT ROOM E202A 600 3 3 E E E G A
2 HCP 4007 PRIMARY CLARIFIER TANK NO. 3 SCUM HEATERS HEATER CONTROL PANEL HEADWORKS ELECTRICAL ROOM I017A [ 1, 2, 5, 12, 13, 20, 21, 22 ] 600 3 3 E E E G A 4 LD-MIX 801 SLUDGE HOLDING TANK MIXER DISCONNECT EXTERIOR E801A 600 3 3 E E E G A
2 IB 201 HEAT TRACE TEMPERATURE CONTROL BOARD HEADWORKS SCREEN AND DEGRIT ROOM E007A CSS E E G A 4 LD-MIX 803 DIGESTER TANK MIXER DISCONNECT NEW DIGESTER BUILDING DIGESTER ROOF E801A 600 3 3 E E E G A
2 IB 202 PROCESS FLOW INSTRUMENTATION CONTROL BOARD HEADWORKS PIPE GALLERY E007A CSS E E G A 4 LD-MS 201 MECHANICAL SCREEN #1 DISCONNECT HEADWORKS SCREEN AND DEGRIT ROOM E202A 600 3 3 E E E G A
2 IB 203 PROCESS FLOW INSTRUMENTATION CONTROL BOARD HEADWORKS PIPE GALLERY E007A CSS E E G A 4 LD-MS 202 MECHANICAL SCREEN #2 DISCONNECT HEADWORKS SCREEN AND DEGRIT ROOM E202A 600 3 3 E E E G A
32 ISJBD 800 INTRINSICALLY SAFE DISCRETE JUNCTION BOX NEW DIGESTER BUILDING I&C ROOM I017A [ 10, 11 ] CSS E E G A 4 LD-OC 201 ODOUR CONTROL UNIT #1 DISCONNECT EXTERIOR E201A 600 3 3 E E E G A 1 PHASE A - ADDENDUM #3 10/11/23

2 IT 2000 HEADWORKS BUILDING IT CABINET HEADWORKS ELECTRICAL ROOM N002A 120 1 2 CSS E E G A 4 LD-OC 202 ODOUR CONTROL UNIT #2 DISCONNECT EXTERIOR E201A 600 3 3 E E E G A
0 PHASE A ISSUED FOR TENDER 02/10/23
3 IT 3000 SERVICE BUILDING SERVICE BUILDING ELECTRICAL ROOM N002A 208 1 3 CSS E E G A 4 LD-OC 801 DIGESTER ODOUR CONTROL UNIT DISCONNECT EXTERIOR E801A 600 3 3 E E E G A
2 IT 8000 DIGESTER BUILDING IT CABINET NEW DIGESTER BUILDING I&C ROOM N002A 120 1 2 CSS E E G A 4 LD-P 201 GRIT TANK PUMP #1 DISCONNECT HEADWORKS SCREEN AND DEGRIT ROOM E202A 600 3 3 E E E G A No. ISSUE / REVISION DD/MM/YY

2 JBA 500 ANALOG JUNCTION BOX EQUALIZATION WET WELL I017A [ 10 ] CSS E E G A 4 LD-P 202 GRIT TANK PUMP #2 DISCONNECT HEADWORKS SCREEN AND DEGRIT ROOM E202A 600 3 3 E E E G A This drawing is copyright protected and may not be reproduced or
2 JBD 201 HEAT TRACE DISCRETE JUNCTION BOX EXTERIOR I017A [ 10 ] CSS E E G A 2 LD-P 205 BIN ROOM SUMP PUMP DISCONNECT HEADWORKS SCREENINGS BIN AREA E202A 600 3 3 E E E G A used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.
2 JBD 500 DISCRETE JUNCTION BOX EQUALIZATION WET WELL I017A [ 10 ] CSS E E G A 2 LD-P 206 PIPE GALLERY SUMP PUMP DISCONNECT HEADWORKS PIPE GALLERY E202A 600 3 3 E E E G A
VERIFY SHEET SIZE AND SCALES. BAR TO THE
2 JBD 800 DISCRETE JUNCTION BOX NEW DIGESTER BUILDING DIGESTER ROOF I017A [ 10 ] CSS E E G A 4 LD-P 207 HEADWORKS GLYCOL HEATING PUMP DISCONNECT HEADWORKS PIPE GALLERY E201A 600 3 3 E E E G A RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
2 JBN 1000 NETWORK JUNCTION BOX SERVICE BUILDING ELECTRICAL ROOM N001A CSS E E G A 4 LD-P 401 PRIMARY SLUDGE PUMP DISCONNECT HEADWORKS PIPE GALLERY E201A 600 3 3 E E E G A SCALE:
N.T.S.
1 JBN 8000 NETWORK JUNCTION BOX EXISTING DIGESTER BUILDING N001A CSS E E G A 4 LD-P 402 PRIMARY SLUDGE PUMP 2 DISCONNECT PRIMARY TANK #1 E201A 600 3 3 E E E G A
3 JBP 001 PORTABLE GENERATOR CONNECTION ELECTRICAL SERVICE ENTRANCE BUILDING E011A 600 3 3 E E E G A 4 LD-P 403 PRIMARY SCUM PUMP DISCONNECT EQUALIZATION WET WELL E201A 600 3 3 E E E G A
1 JBP 201 HEAT TRACE POWER JUNCTION BOX EXTERIOR I211A / I017A [ 10 ] 120 1 2 CSS E E G A 4 LD-P 715 EFFLUENT PUMP #6 DISCONNECT SERVICE BUILDING BASEMENT E301A 600 3 3 E E E G A CLIENT:

51 JBP 401 SCUM HEATER JUNCTION BOX PRIMARY TANK #1 I017A [ 10, 20 ] CSS E E G A 4 LD-P 807 DIGESTER SLUDGE RECIRC. PUMP #4 DISCONNECT NEW DIGESTER BUILDING BASEMENT E801A 600 3 3 E E E G A
51 JBP 404 SCUM HEATER JUNCTION BOX PRIMARY TANK #2 I017A [ 10, 20 ] CSS E E G A 4 LD-P 808 DIGESTER SLUDGE RECIRC. PUMP #4 DISCONNECT NEW DIGESTER BUILDING BASEMENT E801A 600 3 3 E E E G A
51 JBP 407 SCUM HEATER JUNCTION BOX PRIMARY TANK #3 I017A [ 10, 20 ] CSS E E G A 4 LD-P 809 DIGESTER HEX HOT WATER RECIRC. PUMP DISCONNECT NEW DIGESTER BUILDING BASEMENT E801A 600 3 3 E E E G A
1 JBP 500 POWER JUNCTION BOX EQUALIZATION WET WELL I017A [ 10 ] CSS E E G A 4 LD-P 811 CENTRATE TRANSFER PUMP #1 DISCONNECT NEW DIGESTER BUILDING PROCESS AREA E801A 600 3 3 E E E G A
3 LCP 2011 MECHANICAL SCREEN #1 CONTROL PANEL HEADWORKS SCREEN AND DEGRIT ROOM PID201A, SECTION 17052 M E E G A 4 LD-P 812 CENTRATE TRANSFER PUMP #2 DISCONNECT NEW DIGESTER BUILDING PROCESS AREA E801A 600 3 3 E E E G A
CONSULTANT: www.jlrichards.ca
3 LCP 2012 MECHANICAL SCREEN #2 CONTROL PANEL HEADWORKS SCREEN AND DEGRIT ROOM PID201A, SECTION 17052 M E E G A 4 LD-P 813 CENTRIFUGE SLUDGE FEED PUMP DISCONNECT NEW DIGESTER BUILDING PROCESS AREA E801A 600 3 3 E E E G A
3 LCP 2013 CONVEYOR CONTROL PANEL HEADWORKS SCREEN AND DEGRIT ROOM PID201A, SECTION 17052 M E E G A 4 LD-P 815 DIGESTER GLYCOL HEATING PUMP DISCONNECT NEW DIGESTER BUILDING PROCESS AREA E801A 600 3 3 E E E G A
3 LCP 2014 SCREENINGS WASH PRESS LOCAL CONTROL PANEL HEADWORKS SCREENINGS BIN AREA PID201A, SECTION 17052 M E E G A 1 LD-P 816 DIGESTER SANITARY SUMP PUMP #1 DISCONNECT NEW DIGESTER BUILDING PROCESS AREA E801A 600 3 3 E E E G A
3 LCP 2015 GRIT TANK PUMP #1 CONTROL PANEL HEADWORKS SCREEN AND DEGRIT ROOM PID202A, SECTION 17052 M E E G A 1 LD-P 817 DIGESTER SANITARY SUMP PUMP #2 DISCONNECT NEW DIGESTER BUILDING PROCESS AREA E801A 600 3 3 E E E G A
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475 TABLE OF PANELS & DEVICES.dwg

3 LCP 2016 VORTEX INDUCER #1 LOCAL CONTROL PANEL HEADWORKS SCREEN AND DEGRIT ROOM PID202A, SECTION 17052 M E E G A 4 LD-P 818 DIGESTER HEATING LOOP PUMP DISCONNECT NEW DIGESTER BUILDING PROCESS AREA E801A 600 3 3 E E E G A
3 LCP 2017 GRIT CLASSIFIER CONTROL PANEL HEADWORKS SCREEN AND DEGRIT ROOM PID202A, SECTION 17052 M E E G A 4 LD-P 901 BOILER FEED PUMP #1 LOCAL DISCONNECT SERVICE BUILDING BOILER ROOM E301A 600 3 3 E E E G A CONSULTANT:

3 LCP 2018 HEADWORKS GLYCOL HEATING PUMP CONTROL PANEL HEADWORKS PIPE GALLERY MID201A / I017A [ 1, 2, 22 ] CSS E E G A 4 LD-P 902 BOILER FEED PUMP #2 LOCAL DISCONNECT SERVICE BUILDING BOILER ROOM E301A 600 3 3 E E E G A
3 LCP 2019 HEADWORKS ELECTRICAL ROOM VENTIALTION CONTROL PANEL (EF/SF-201) HEADWORKS ELECTRICAL ROOM MID201A / I017A [ 1, 2, 3, 4, 22 ] CSS E E G A 4 LD-P 903 BOILER FEED PUMP #3 LOCAL DISCONNECT SERVICE BUILDING BOILER ROOM E301A 600 3 3 E E E G A
3 LCP 2020 HEADWORKS MUA UNIT CONTROL PANEL EXTERIOR MID201A / I017A [ 1, 2, 3, 4, 22 ] CSS E E G A 4 LD-P 905 PRIMMARY HEATING DISTRIBUTION PUMP #1 LOCAL DISCONNECT SERVICE BUILDING BLOWER ROOM E301A 600 3 3 E E E G A
3 LCP 2021 GRIT TANK PUMP #2 CONTROL PANEL HEADWORKS SCREEN AND DEGRIT ROOM PID202A, SECTION 17052 M E E G A 4 LD-P 906 PRIMMARY HEATING DISTRIBUTION PUMP #2 LOCAL DISCONNECT SERVICE BUILDING BLOWER ROOM E301A 600 3 3 E E E G A
3 LCP 2022 GRIT TANK MIXER #2 CONTROL PANEL HEADWORKS SCREEN AND DEGRIT ROOM PID202A, SECTION 17052 M E E G A 4 LD-P 907 HOT WATER PUMP LOCAL DISCONNECT SERVICE BUILDING BLOWER ROOM E301A 600 3 3 E E E G A PROFESSIONAL STAMP PROJECT NORTH
1 LCP 2030 SCREEN BIN AREA SANITARY PUMP CONTROL PANEL HEADWORKS SCREENINGS BIN AREA MID201A, SECTION 17052 M E E G A 4 LD-P 908 HOT WATER PUMP LOCAL DISCONNECT SERVICE BUILDING BLOWER ROOM E301A 600 3 3 E E E G A
3 LCP 2031 GALLERY LEVEL SANITARY PUMP CONTROL PANEL HEADWORKS PIPE GALLERY MID201A, SECTION 17052 M E E G A 4 LD-P 909 HOT WATER PUMP LOCAL DISCONNECT SERVICE BUILDING BLOWER ROOM E301A 600 3 3 E E E G A
3 LCP 2901 ODOUR CONTROL UNIT #1 LOCAL CONTROL PANEL EXTERIOR PID203A / I017A [ 1, 2, 3, 4, 22 ] CSS E E G A 2 LD-RH 401 PRIMARY CLARIFIER TANK NO. 1 SCUM HEATERS LOCAL DISCONNECT PRIMARY TANK #1 I410A 600 3 3 E E E G A
3 LCP 2902 ODOUR CONTROL UNIT #2 LOCAL CONTROL PANEL EXTERIOR PID203A / I017A [ 1, 2, 3, 4, 22 ] CSS E E G A 2 LD-RH 404 PRIMARY CLARIFIER TANK NO. 2 SCUM HEATERS LOCAL DISCONNECT PRIMARY TANK #2 I410A 600 3 3 E E E G A
3 LCP 3900 SERVICE BLDG HEATING PUMP ROOM CONTROL PANEL (EF-302) SERVICE BUILDING MECHANICAL ROOM MID301A / I017A [ 1, 2, 3, 4, 22 ] CSS E E G A 2 LD-RH 407 PRIMARY CLARIFIER TANK NO. 3 SCUM HEATERS LOCAL DISCONNECT PRIMARY TANK #3 I410A 600 3 3 E E E G A
3 LCP 3901 SERVICE BLDG BOILER ROOM CONTROL PANEL (EF-303) SERVICE BUILDING BOILER ROOM MID301A / I017A [ 1, 2, 3, 4, 22 ] CSS E E G A 4 LD-SCV 201 CONVEYOR DISCONNECT HEADWORKS SCREEN AND DEGRIT ROOM E202A 600 3 3 E E E G A
2 LCP 4001 PRIMARY CLARIFIER TANK NO. 1 SCUM HEATERS LOCAL CONTROL PANEL PRIMARY TANK #1 PID401A / I017A [ 1, 2, 5, 12, 13, 20, 21, 22 ] CSS E E G A 4 LD-SCV 801 SLUDGE CONVEYOR #1 DISCONNECT NEW DIGESTER BUILDING WASTE BIN ROOM E801A 600 3 3 E E E G A
2 LCP 4004 PRIMARY CLARIFIER TANK NO. 2 SCUM HEATERS LOCAL CONTROL PANEL PRIMARY TANK #2 PID401A / I017A [ 1, 2, 5, 12, 13, 20, 21, 22 ] CSS E E G A 4 LD-SCV 802 SLUDGE CONVEYOR #2 DISCONNECT NEW DIGESTER BUILDING WASTE BIN ROOM E801A 600 3 3 E E E G A
PROJECT:
2 LCP 4007 PRIMARY CLARIFIER TANK NO. 3 SCUM HEATERS LOCAL CONTROL PANEL PRIMARY TANK #3 PID401A / I017A [ 1, 2, 5, 12, 13, 20, 21, 22 ] CSS E E G A 4 LD-SF 201 ELECTRICAL ROOM SUPPLY FAN DISCONNECT HEADWORKS ELECTRICAL ROOM E201A 600 3 3 E E E G A
3 LCP 4010 PRIMARY CLARIFIER #1 & #2 CONTROL PANEL PRIMARY TANK #1 PID401A / I017A [ 1, 2 , 22 ] CSS E E G A 4 LD-SWP 201 SCREENINGS WASH PRESS DISCONNECT HEADWORKS SCREENINGS BIN AREA E202A 600 3 3 E E E G A
MUNICIPALITY OF NORTH
43 LCP 4011 PRIMARY SLUDGE PUMP #1 & #2 CONTROL PANEL HEADWORKS PIPE GALLERY PID401A / I017A [ 1, 2, 3, 4, 22 ] CSS E E G A 3 LP 001 GENERATOR POWER PANEL ELECTRICAL SERVICE ENTRANCE BUILDING E011A, E911A 208 3 4 E E E G A GRENVILLE - WATER POLLUTION
3 LCP 4013 PRIMARY CLARIFIER SCUM PIT LOCAL CONTROL PANEL PRIMARY TANK #1 PID401 / I017A [ 1, 2, 3, 4, 14 ] G A 3 LP 202 HEADWORKS POWER PANEL HEADWORKS ELECTRICAL ROOM E201A 208 3 4 E E E G A CONTROL PLANT EXPANSION
2 LCP 4019 FERRIC SULPHATE TANK LOCAL CONTROL PANEL EXTERIOR PID403A / I017A [ 1, 4, 6, 9, 13, 22 ] CSS E E G A 3 LP 203 HEADWORKS POWER PANEL HEADWORKS ELECTRICAL ROOM E202A 208 3 4 E E E G A PHASE - A
3 LCP 4020 PRIMARY CLARIFIER #2 & #3 CONTROL PANEL PRIMARY TANK #1 PID401A / I017A [ 1, 2, 22 ] CSS E E G A 2 LP 302 SERVICE BUILDING POWER PANEL SERVICE BUILDING ELECTRICAL ROOM E302A 208 3 4 E E E G A KEMPTVILLE, ONTARIO
3 LCP 5000 BLOWER CONTROL PANEL HEADWORKS PIPE GALLERY PID403A / I017A [ 1, 2, 3, 4, 22 ] CSS E E G A 2 LP 305 SERVICE BUILDING POWER PANEL SERVICE BUILDING ELECTRICAL ROOM E302A 208 3 4 E E E G A DRAWING:

ELECTRICAL

November 14, 2023 9:57:34 AM


3 LCP 7012 EFFLUENT PUMP #6 CONTROL PANEL SERVICE BUILDING BASEMENT PID701B / I017B [ 1, 2, 3, 4 ] CSS E E G A 3 LP 802 DIGESTER POWER PANEL NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 208 3 4 E E E G A
2 LCP 8001 CENTRIFUGE LOCAL CONTROL PANEL NEW DIGESTER BUILDING PROCESS AREA M E E G A 3 LP 803 DIGESTER POWER PANEL NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 208 3 4 E E E G A SITE-WIDE

1 DRAWING NOTES: TABLE OF PANELS SHEET 1 OF 2

1 REFER ALSO TO DETAILS 9/E006A, 5/E007A AND 6/E007A. 4 REFER TO DETAIL 2/I022A.
DESIGN:
MM/LO
2 MODIFIED BY CSS. 5 JUNCTION BOX COMPLETE WITH EPA SERIES S/S PADLOCK ADAPTER OR APPROVED EQUIVALENT COMPATIBLE WITH DRAWN: DRAWING #:
MM

PLOT DATE:
SELECTED PANEL. JUNCTION BOX TO INCLUDE LAMACOID LABEL PER ITEM 54 ON BILL OF MATERIALS (I010A). LABEL TO
CHECKED:
3 CSS TO COORDINATE WITH THE P. ENG. HIRED BY THE CONTRACTOR TO DESIGN THE INTRINSICALLY SAFE SYSTEM.
SHOP DRAWINGS FOR THIS PANEL TO BE SEALED BY THAT P. ENG. REFER TO DRAWING I800A FOR FURTHER DETAILS.
READ "DISCONNECT POWER BEFORE OPENING".

1
JLR #:
JO
29475
I001A
TOTAL LINKS
EC5
TABLE OF PANEL AND ELECTRICAL EQUIPMENT

PROJECT
EngCAD Database Data Exported on: 2023-11-13 8:05:53 PM

PHASE
NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
DEVICE DEVICE FIELD WORK BUILDING 900 SERIES
800 SERIES
TAG SERVICE DWG / SPEC SUPPLY INSTALL WIRE COMM. NEW AERATION NEW PRIMARY NEW
CLARIFIERS HEADWORKS
TANKS
IDENTIFIER DESCRIPTION LOCATION DETAIL AMPS kAIC VOLTS Ø W BY BY BY BY 500 SERIES 400 SERIES 200 SERIES

1 LP 900 FCP-9000 POWER PANEL EXTERIOR I016A 208 3 4 CSS E E G A


5 LP 902 ELECTRICAL SERVICE ENTRANCE BUILDING POWER PANEL ELECTRICAL SERVICE ENTRANCE BUILDING E010A 208 3 4 E E E G A NEW TERTIARY
NEW SECONDARY
CLARIFIERS FILTER BUILDING
0 MCC 1 EXISTING MOTOR CONTROL CENTRE SERVICE BUILDING EXISTING ELECTRICAL ROOM E311A 600 3 3 EX E E G A 600 SERIES (PHASE B) 700 SERIES (PHASE B)

6 MCC 200 HEADWORKS BUILDING MOTOR CONTROL CENTRE HEADWORKS ELECTRICAL ROOM E201A 600 3 3 E E E G A
0 MCC 3 EXISTING MOTOR CONTROL CENTRE SERVICE BUILDING EXISTING ELECTRICAL ROOM E311A 600 3 3 EX E E G A
6 MCC 300 SERVICE BUILDING MOTOR CONTROL CENTRE SERVICE BUILDING ELECTRICAL ROOM E301A 600 3 3 E E E G A EXISTING SERVICE
BUILDING
0 MCC 3B EXISTING MOTOR CONTROL CENTRE SERVICE BUILDING EXISTING ELECTRICAL ROOM E311A 600 3 3 EX E E G A 300 SERIES

5 MCC 800 NEW DIGESTER BUILDING MOTOR CONTROL CENTRE NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 600 3 3 E E E G A
4 MCP 2001 SCREENING MOTOR CONTROL PANEL HEADWORKS ELECTRICAL ROOM E202A, SECTION 17052 600 3 3 M E E G A
KEY PLAN
4 MCP 2002 GRIT REMOVAL MOTOR CONTROL PANEL HEADWORKS ELECTRICAL ROOM E202A, SECTION 17052 600 3 3 M E E G A
4 MCP 8001 CENTRIFUGE MOTOR CONTROL PANEL NEW DIGESTER BUILDING ELECTRICAL ROOM E801A, SECTION 17052 600 3 3 M E E G A LEGEND:
2 PB 201 PULL BOX HEADWORKS PIPE GALLERY I210A CSS E E G A G: GENERAL CONTRACTOR
2 PB 202 PULL BOX HEADWORKS PIPE GALLERY I210A CSS E E G A E: ELECTRICAL CONTRACTOR
M: MECHANICAL CONTRACTOR
1 PB 203 PULL BOX HEADWORKS PIPE GALLERY I210A CSS E E G A EX: EXISTING
CSS: CONTROL SYSTEM SPECIALIST
1 PB 204 PULL BOX HEADWORKS PIPE GALLERY I210A CSS E E G A
FTE: FLOAT TIPPING ELEVATION
1 PB 301 PULL BOX SERVICE BUILDING BASEMENT I310A CSS E E G A SSS: SECURITY SYSTEM SPECIALIST
FDS: FIRE DETECTION SYSTEM SPECIALIST
1 PB 302 PULL BOX SERVICE BUILDING BASEMENT I310A CSS E E G A
1 PB 303 PULL BOX SERVICE BUILDING BOILER ROOM I310A CSS E E G A GENERAL NOTES:
1 PB 304 PULL BOX SERVICE BUILDING BOILER ROOM I310A CSS E E G A A. REFERENCES ON DRAWING I017A PERTAIN TO GROUPS
1 PB 305 PULL BOX SERVICE BUILDING BOILER ROOM I310A CSS E E G A OF COMPONENTS TO BE PROVIDED FOR THAT PANEL.
CONTRACTOR TO DESIGN THE PANEL USING THOSE
1 PB 306 PULL BOX SERVICE BUILDING BOILER ROOM I310A CSS E E G A COMPONENTS, AS OUTLINED IN THE BILL OF MATERIALS
1 PB 307 PULL BOX SERVICE BUILDING BOILER ROOM I310A CSS E E G A ON DRAWING I017A.

0 PB 308 PULL BOX SERVICE BUILDING BASEMENT I310A CSS E E G A B. FOR PANELS SUPPLIED BY THE MECHANICAL
CONTRACTOR, REFER TO PERTINENT DIVISION 11 OR
1 PB 801 PULL BOX NEW DIGESTER BUILDING BASEMENT I810A CSS E E G A
DIVISION 15 SPECIFICATIONS.
1 PB 802 PULL BOX NEW DIGESTER BUILDING BASEMENT I810A CSS E E G A
C. NOTE THAT NOT ALL DISCONNECTS ARE SHOWN IN
1 PB 803 PULL BOX NEW DIGESTER BUILDING BASEMENT I810A CSS E E G A
THIS TABLE. REFER TO E000A AND OTHER DRAWINGS
1 PB 804 PULL BOX NEW DIGESTER BUILDING BASEMENT I810A CSS E E G A FOR FURTHER DETAILS.

3 PFP 100 ACTIVE POWER FACTOR PANEL SERVICE BUILDING ELECTRICAL ROOM E011A 600 3 3 E E E G A D. NOTE THAT ADDITIONAL PULL BOXES MAY BE
3 PFP 200 ACTIVE POWER FACTOR PANEL HEADWORKS ELECTRICAL ROOM E201A 600 3 3 E E E G A REQUIRED BASED ON SITE CONDITIONS. CONTRACTOR
IS TO PROVIDE ADDITIONAL PULL BOXES, AS REQUIRED.
3 PFP 300 ACTIVE POWER FACTOR PANEL SERVICE BUILDING ELECTRICAL ROOM E301A 600 3 3 E E E G A
3 PFP 800 ACTIVE POWER FACTOR PANEL NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 600 3 3 E E E G A
0 RH 401 SCUM HEATER 1 PRIMARY TANK #1 I023A 600 1 3 E E E G A
0 RH 402 SCUM HEATER 2 PRIMARY TANK #1 I023A 600 1 3 E E E G A
0 RH 403 SCUM HEATER 3 PRIMARY TANK #1 I023A 600 1 3 E E E G A
0 RH 404 SCUM HEATER 4 PRIMARY TANK #2 I023A 600 1 3 E E E G A
0 RH 405 SCUM HEATER 5 PRIMARY TANK #2 I023A 600 1 3 E E E G A
0 RH 406 SCUM HEATER 6 PRIMARY TANK #2 I023A 600 1 3 E E E G A
0 RH 407 SCUM HEATER 7 PRIMARY TANK #3 I023A 600 1 3 E E E G A
0 RH 408 SCUM HEATER 8 PRIMARY TANK #3 I023A 600 1 3 E E E G A
0 RH 409 SCUM HEATER 9 PRIMARY TANK #3 I023A 600 1 3 E E E G A 1 PHASE A - ADDENDUM #3 10/11/23
3 SB 001 UTILITY INCOMMING SWITCHGEAR ELECTRICAL SERVICE ENTRANCE BUILDING E011A 600 3 4 E E E G A
0 PHASE A ISSUED FOR TENDER 02/10/23
4 SB 002A LOAD SWITCHGEAR ELECTRICAL SERVICE ENTRANCE BUILDING E011A 600 3 3 E E E G A
4 SB 002B LOAD SWITCHGEAR ELECTRICAL SERVICE ENTRANCE BUILDING E011A 600 3 3 E E E G A No. ISSUE / REVISION DD/MM/YY

3 SB 003A STANDBY POWER INCOMING SWITCHBOARDS ELECTRICAL SERVICE ENTRANCE BUILDING E011A 600 3 4 E E E G A
This drawing is copyright protected and may not be reproduced or
4 SB 003B STANDBY POWER INCOMING SWITCHBOARDS ELECTRICAL SERVICE ENTRANCE BUILDING E011A 600 3 4 E E E G A used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.
2 SPD 001 SURGE PROTECTION DEVICE GENERATOR ENCLOSURE E011A 208 3 4 E E E G A
VERIFY SHEET SIZE AND SCALES. BAR TO THE
1 SPD 002A SURGE PROTECTION DEVICE ELECTRICAL SERVICE ENTRANCE BUILDING E011A 600 3 3 E E E G A RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
1 SPD 002B SURGE PROTECTION DEVICE ELECTRICAL SERVICE ENTRANCE BUILDING E011A 600 3 3 E E E G A SCALE:
N.T.S.
2 SPD 200 SURGE PROTECTION DEVICE HEADWORKS ELECTRICAL ROOM E202A 600 3 3 E E E G A
3 SPD 202 SURGE PROTECTION DEVICE HEADWORKS ELECTRICAL ROOM E202A 208 3 4 E E E G A
3 SPD 203 SURGE PROTECTION DEVICE HEADWORKS ELECTRICAL ROOM E202A 208 3 4 E E E G A CLIENT:
2 SPD 290 SURGE PROTECTION DEVICE HEADWORKS ELECTRICAL ROOM E202A 208 1 3 E E E G A
2 SPD 300 SURGE PROTECTION DEVICE SERVICE BUILDING ELECTRICAL ROOM E301A 600 3 3 E E E G A
2 SPD 302 SURGE PROTECTION DEVICE SERVICE BUILDING ELECTRICAL ROOM E301A 208 3 4 E E E G A
1 SPD 390 SURGE PROTECTION DEVICE SERVICE BUILDING ELECTRICAL ROOM E301A 208 3 4 E E E G A
2 SPD 800 SURGE PROTECTION DEVICE NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 600 3 3 E E E G A
CONSULTANT: www.jlrichards.ca
3 SPD 802 SURGE PROTECTION DEVICE NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 208 3 4 E E E G A
3 SPD 803 SURGE PROTECTION DEVICE NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 208 3 4 E E E G A
2 SPD 890 SURGE PROTECTION DEVICE NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 208 1 3 E E E G A
1 SPD 900 SURGE PROTECTION DEVICE EXTERIOR I016A 208 3 4 CSS E E G A
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475 TABLE OF PANELS & DEVICES.dwg

3 SPD 901 SURGE PROTECTION DEVICE ELECTRICAL SERVICE ENTRANCE BUILDING E011A 208 3 4 E E E G A
1 SPD 990 SURGE PROTECTION DEVICE ELECTRICAL SERVICE ENTRANCE BUILDING E011A 208 1 3 E E E G A CONSULTANT:

22 TCP 100 EXISTING TELECOMMUNICATIONS PANEL SERVICE BUILDING EXISTING ELECTRICAL ROOM N001A EX EX E G A
32 TX 001 UTILITY TRANSFORMER EXTERIOR E011A E E E G A
2 TX 202 HEADWORKS POWER PANEL TRANSFORMER HEADWORKS ELECTRICAL ROOM E202A 600 3 3 E E E G A
1 TX 203 HEADWORKS POWER PANEL TRANSFORMER HEADWORKS ELECTRICAL ROOM E202A 600 3 3 E E E G A
1 TX 302 SERVICE BUILDING TRANSFORMER SERVICE BUILDING ELECTRICAL ROOM E301A 600 3 3 E E E G A
PROFESSIONAL STAMP PROJECT NORTH
2 TX 305 SERVICE BUILDING TRANSFORMER SERVICE BUILDING ELECTRICAL ROOM E301A 600 3 3 E E E G A
1 TX 802 DIGESTER POWER TRANSFORMER NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 600 3 3 E E E G A
2 TX 803 DIGESTER POWER TRANSFORMER NEW DIGESTER BUILDING ELECTRICAL ROOM E801A 600 3 3 E E E G A
3 TX 901 ELECTRICAL SERVICE ENTRANCE BUILDING TRANSFORMER ELECTRICAL SERVICE ENTRANCE BUILDING E011A 600 3 3 E E E G A
3 UP 290 HEADWORKS UPS POWER PANEL HEADWORKS ELECTRICAL ROOM E202A 208 1 3 E E E G A
2 UP 390 SERVICE BUILDING UPS POWER PANEL SERVICE BUILDING ELECTRICAL ROOM E302A 208 3 4 E E E G A
2 UP 890 DIGESTER UPS POWER PANEL NEW DIGESTER BUILDING I&C ROOM E801A 208 1 3 E E E G A
1 UP 990 ELECTRICAL SERVICE ENTANCE BUILDING UPS POWER PANEL ELECTRICAL SERVICE ENTRANCE BUILDING E901A 208 1 3 E E E G A
3 UPS 290 HEADWORKS UPS HEADWORKS ELECTRICAL ROOM E007A 208 1 3 CSS E E G A PROJECT:

0 UPS 300 IT-3000 CABINET UPS SERVICE BUILDING ELECTRICAL ROOM N002A 208 1 3 CSS E E G A MUNICIPALITY OF NORTH
1
3 UPS 390 SERVICE BUILDING UPS SERVICE BUILDING ELECTRICAL ROOM E301A 208 3 4 CSS E E G A GRENVILLE - WATER POLLUTION
4 UPS 890 DIGESTER UPS NEW DIGESTER BUILDING I&C ROOM E007A 208 1 3 CSS E E G A CONTROL PLANT EXPANSION
PHASE - A
1 KEMPTVILLE, ONTARIO
DRAWING NOTES: DRAWING:

November 14, 2023 12:47:00 PM


ELECTRICAL
1 REFER TO TABLE OF DEVICES.
SITE-WIDE
2 MODIFIED BY CSS
TABLES OF PANELS SHEET 2 OF 2
3 HONI SUPPLIED SERVICE TRANSFORMER. COORDINATE WITH HONI.

DESIGN:
MM/LO
DRAWN: DRAWING #:
MM

PLOT DATE:
CHECKED:

JLR #:
JO
29475
I002A
NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
800 SERIES
NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES

864 1778 NEW SECONDARY NEW TERTIARY


CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)
356 356

39 43 40

120VAC 40 120VAC 120VAC 120VAC 24VDC/COMMS 24VDC 24VDC 40 EXISTING SERVICE


BUILDING
300 SERIES

46 RACK 0 RACK 0 DO-SLOT-3 48 3 24VDC


30 29
29 120VAC (NON-UPS) DI-SLOTXX - 24VDC DI-SLOTXX - 24VDC 24VDC RELAYS
39 AI-SLOTXX

SPD0.1

30 31 32

ETHERNET SWITCH
ETHERNET POWER
AI-SLOTXX
KEY PLAN
DI-SLOTXX - 24VDC DI-SLOTXX - 24VDC

10 11
AI-SLOTXX

3 25 25 17 38
DI-SLOTXX - 24VDC DI-SLOTXX - 24VDC
19 20 9
AI-SLOTXX
NEUTRAL (NON-UPS) 24VDC/COMMS 120VAC
26

FIELD COMMUNICATION CABLES


AI-SLOTXX
120VAC (UPS)
29 30 DI-SLOTXX - 24VDC DI-SLOTXX - 24VDC
POWER ETHERNET ETHERNET ETHERNET
AC Input AC Input AC Input AC Input AC Input AC Input AC Input AC Input AC Input AC Input AC Input AC Input 23 24
RACK 0
RXD TXD OK RXD TXD OK RXD TXD OK

SPD1.1
31 32
AI-SLOTXX

15
25
DI-SLOTXX - 24VDC DI-SLOTXX - 24VDC

AI-SLOTXX

41 2
AI-SLOTXX

8 DI-SLOTXX - 24VDC DI-SLOTXX - 24VDC


COMMUNICATION CABLES 47
120VAC

AI-SLOTXX

I/O WIRING/24VDC

24VDC/COMMUNICATIONS
DI-SLOTXX - 24VDC DI-SLOTXX - 24VDC
AO-SLOTXX
120VAC

43
1981

AC Input AC Input AC Input AC Input AC Input AC Input Relay Output Relay Output Relay Output Relay Output Relay Output Relay Output
AO-SLOTXX
POWER ETHERNET

RACK 1
DI-SLOTXX - 24VDC DO-SLOTXX - 24VDC
RXD TXD OK

1
16

24VDC WIRING
AO-SLOTXX
NEUTRAL (UPS)

120VAC WIRING

24VDC WIRING
24VDC WIRING
47

120VAC WIRING
24VDC FIELD WIRING

24VDC FIELD WIRING


DI-SLOTXX - 24VDC DO-SLOTXX - 24VDC

24VDC WIRING
24VDC WIRING
1981

1981
41 2
29
COMMUNICATION CABLES 0VDC
DI-SLOTXX - 24VDC DO-SLOTXX - 24VDC

14
43 47
I/O WIRING/24VDC

24VDC/COMMUNICATIONS
NON - UPS RECEPT.

DI-SLOTXX - 24VDC DO-SLOTXX - 24VDC

POWER FAIL RELAYS


Analog In Analog In Analog In Analog In Analog In Analog In Analog In Analog In Analog In Analog Out Analog Out Analog Out Analog Out Analog Out
POWER ETHERNET

RACK 2
RXD TXD OK

UPS RECEPT. DI-SLOTXX - 24VDC

16
17 40
DI-SLOTXX - 24VDC

1 2
1 PHASE A - ADDENDUM #3 10/11/23
COMMUNICATION CABLES
DI-SLOTXX - 24VDC 40 24VDC 0 PHASE A ISSUED FOR TENDER 02/10/23
40 3
21
No. ISSUE / REVISION DD/MM/YY

DI-SLOTXX - 24VDC This drawing is copyright protected and may not be reproduced or
42 used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.
27 24VDC
VERIFY SHEET SIZE AND SCALES. BAR TO THE
RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
10 11 12 13 36
SCALE: NTS
40

24VDC POWER

24VDC POWER

24VDC POWER
24VDC
CLIENT:
39

120VAC 40 120VAC 120VAC 24 VDC MISC. 24VDC

33 34 CORNER DUCT 40
44 39 39 2 45

CONSULTANT: www.jlrichards.ca

1 LEFT DEPTH PANEL 2 REAR PANEL 3 RIGHT DEPTH PANEL


I014A SCALE: NTS I014A SCALE: NTS SCALE: NTS
I014A
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475 CONTROL PANEL LAYOUT.dwg

CONSULTANT:

NOTES: GENERAL NOTES:


1 EACH DEPTH PANEL TO BE MOUNTED AS FAR FORWARD AS A. PROVIDE A SUFFICIENT NUMBER OF RELAYS AS CONTROL PANELS BILL OF MATERIALS
POSSIBLE IN THE CABINET TO MINIMIZE OBSTRUCTION OF THE REQUIRED IN EACH PLC PANEL FOR VOLTAGE PROFESSIONAL STAMP PROJECT NORTH
ITEMS ON THE REAR PANEL. CHANGES AS WELL AS TO IMPLEMENT HARDWIRED
LOGIC. ITEM MANUFACTURER PART NUMBER DESCRIPTION COMMENTS
2 DUCTING FOR PLC COMMUNICATIONS CABLING TO BE
ELEVATED USING PANEL STANDOFFS (OR EQUIVALENT). FINAL B. REFER TO BILL OF MATERIALS ON DRAWING I010A AS
HEIGHT OF COMMUNICATIONS DUCTING TO MATCH THAT OF WELL AS SPECIFICATIONS 17051. 1 HAMMOND 1422 MD SERIES 86" X 112" X 20" MULTI DOOR FREE STANDING NEMA 12 ANSI 61 GREY ENCLOSURE. 1. HOFFMAN EQUIVALENT IS ACCEPTABLE. 4
ADJACENT DUCTING. PLC I/O WIRING TO BE ROUTED BENEATH
PLC COMMUNICATIONS DUCTING. C. REFER TO DRAWINGS I018A - I022A FOR FURTHER
REQUIREMENTS. IN ADDITION, REFER TO PERTINENT 78" X 70" AND 78" X 34" WHITE STEEL REAR PANELS FOR 86" X 112" X 20" 1422 MD
2 HAMMOND 1422 MD SERIES 1. HOFFMAN EQUIVALENT IS ACCEPTABLE.
3 EXPANSION AND SFP MODULES NOT SHOWN. PROVIDE I/O TABLES FOR ADDITIONAL DETAILS. SERIES ENCLOSURE
EXPANSION MODULES TO SUIT. PROVIDE SFP MODULES, AS
SPECIFIED REFER TO N001A AND SECTION 17051. 3 HAMMOND 72FD14 78" X 14" WHITE STEEL SIDE (DEPTH) PANEL FOR 1422 MD SERIES ENCLOSURE. 1. HOFFMAN EQUIVALENT IS ACCEPTABLE.

4 MANUFACTURER TO MODIFY THE DESIGN OF STOCK PROJECT:


ENCLOSURE TO ACCOMODATE THE INSTALLATION OF DEPTH REFER TO I010A FOR TYPICAL CONTROL PANEL BOM LIST FOR OTHER DEPICTED ITEMS.
PANELS AS INDICATED. MUNICIPALITY OF NORTH
GRENVILLE - WATER POLLUTION
CONTROL PLANT EXPANSION
PHASE - A
KEMPTVILLE, ONTARIO

DRAWING:

ELECTRICAL

November 14, 2023 9:57:20 AM


SITE-WIDE
CP-2000 & CP-3000 CONTROL
PANEL LAYOUT CONTINUATION

DESIGN:
MM/LO
DRAWN: DRAWING #:
MM

PLOT DATE:
CHECKED:

JLR #:
JO
29475
I014A
PANELS BILL OF MATERIALS JUNCTION BOX BILL OF MATERIALS NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
800 SERIES
NEMA 4X, STAINLESS STEEL, WALL MOUNT ENCLOSURE c/w MATCHING WHITE 1. JUNIOR ECLIPSE EJ SERIES IS ACCEPTABLE. NEMA 4X, STAINLESS STEEL, WALL MOUNT ENCLOSURE c/w MATCHING WHITE 1. JUNIOR ECLIPSE EJ SERIES IS ACCEPTABLE. NEW AERATION NEW PRIMARY NEW
HAMMOND ECLIPSE, EN4SD SERIES HAMMOND ECLIPSE, EN4SD SERIES TANKS CLARIFIERS HEADWORKS
REAR PANEL. SIZE ENCLOSURE TO SUIT. 2. HOFFMAN EQUIVALENT IS ACCEPTABLE. REAR PANEL. SIZE ENCLOSURE TO SUIT. 2. HOFFMAN EQUIVALENT IS ACCEPTABLE. 500 SERIES 400 SERIES 200 SERIES

35mm X 15mm SYMMETRICAL ZINC PLATED DIN RAIL. PROVIDE MATCHING 1. PHOENIX CONTACT EQUIVALENT IS
HOFFMAN H2OMIT SERIES CONTROL PANEL VENT DRAIN ALLEN-BRADLEY 199-DR1
STAND-OFFS AS REQUIRED TO RAISE HEIGHT OF COMPONENTS. ACCEPTABLE.
NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)
HOFFMAN 1 EX E SERIES CLASS 1 DIVISION 1 HAZARDOUS AREA CONTROL PANEL VENT DRAIN 1. AS REQUIRED PER AREA CLASSIFICATION PHOENIX CONTACT UK 5 N UNIVERSAL TERMINAL BLOCK, SCREW CONNECTION 1. USED FOR 120VAC/24VDC CONNECTIONS.

PHOENIX CONTACT USLKG 5 GROUND TERMINAL BLOCK, SCREW CONNECTION PHOENIX CONTACT USLKG 5 GROUND TERMINAL BLOCK, SCREW CONNECTION
EXISTING SERVICE
GROUP 1 BUILDING
300 SERIES
LAMACOID WITH WHITE BACKGROUND AND BLACK 5mm HIGH CHARACTERS 1. SIZE LAMACOID TO SUIT. PHOENIX CONTACT CLIPFIX 35 SNAP-ON END BRACKET
GROUP 10
35mm X 15mm SYMMETRICAL ZINC PLATED DIN RAIL. PROVIDE MATCHING 1. PHOENIX CONTACT EQUIVALENT IS
ALLEN-BRADLEY 199-DR1 PHOENIX CONTACT KLM + ESL 26X6 TERMINAL STRIP MARKERS / GROUP LABELS
STAND-OFFS AS REQUIRED TO RAISE HEIGHT OF COMPONENTS. ACCEPTABLE. KEY PLAN

ALLEN-BRADLEY 800TC SERIES


FINGER-SAFE PUSH-TO-TEST PILOT LIGHT c/w 800T SERIES ALUMINUM LEGEND
COPPER GROUND BAR GENERAL NOTES:
PLATE
A. REFER TO TABLE OF PANELS ON DRAWINGS I001A AND
50mm X 150mm LAMACOID WITH WHITE BACKGROUND AND BLACK 25mm HIGH I002A AS WELL AS CONTROL PANEL BILL OF MATERIALS
ALLEN-BRADLEY 800T SERIES ALUMINUM LEGEND PLATE (STANDARD SIZE). ENGRAVED BY MANUFACTURER.
CHARACTERS ON I010A.

FINGER SAFE MULTI-POSITION SELECTOR SWITCH, BLACK W/ WHITE INSERT.


ALLEN-BRADLEY 800TC SERIES HOFFMAN H2OMIT SERIES CONTROL PANEL VENT DRAIN
NUMBER OF CONTACTS TO SUIT.
GROUP 2
ALLEN-BRADLEY 800T SERIES ALUMINUM LEGEND PLATE (STANDARD SIZE). ENGRAVED BY MANUFACTURER. HOFFMAN EX E SERIES CLASS 1 DIVISION 1 HAZARDOUS AREA CONTROL PANEL VENT DRAIN

FINGER-SAFE POTENTIOMETER c/w 800T SERIES ALUMINIUM LEGEND PLATE.


GROUP 3 ALLEN BRADLEY 800TC SERIES ALLEN-BRADLEY 1489-M SERIES MINIATURE CIRCUIT BREAKER (120VAC) 1. SCHNEIDER EQUIVALENT IS ACCEPTABLE.
SELECT IMPEDANCE RANGE TO SUIT
GROUP 11
DIGITAL DATA DISPLAY. c/w SUNBRIGHT 0.6" DUAL LINE, 6 DIGIT, LED DISPLAY; 4
GROUP 4 PRECISION DIGITAL PD6000 SERIES 1. VOLTAGE TO SUIT. ALLEN-BRADLEY 1492-SP SERIES SUPPLEMENTARY PROTECTOR (24VDC) 1. SCHNEIDER EQUIVALENT IS ACCEPTABLE.
RELAYS AND 4-20 mA OUTPUT.

24VDC 2-POLE SLIM LINE RELAY C/W PUSH-TO-TEST, MANUAL OVERRIDE AND LED. 1. VOLTAGE AND NUMBER OF CONTACTS TO
ALLEN-BRADLEY 700-HK32Z24-3-4 1. QUANTITY AND NUMBER OF POLE TO SUIT. PEPPERS + FUCHS K SERIES INTRINSICALLY SAFE RELAY
PROVIDE 700-HN222 SOCKET AND 700-ADL1R DIODE WITH LED SURGE SUPPRESSOR. SUIT.

24VDC 4-POLE MINIATURE SQUARE BASE RELAY C/W PUSH-TO-TEST AND LED. PROVIDE
ALLEN-BRADLEY 700-HC24Z24-3-4 1. QUANTITY AND NUMBER OF POLE TO SUIT. GROUP 22 PHOENIX CONTACT UK 6N UNIVERSAL TERMINAL BLOCK, SCREW CONNECTION
700-HN104 MINI 14-BLADE SOCKET AND 700-ADL1 DIODE LED SURGE SUPPRESSOR.
GROUP 5
120VAC 2-POLE SLIM LINE RELAY C/W PUSH-TO-TEST, MANUAL OVERRIDE AND LED.
ALLEN-BRADLEY 700-HK32A1-3-4 1. QUANTITY AND NUMBER OF POLE TO SUIT. GROUP 23 PHOENIX CONTACT UK 5N UNIVERSAL TERMINAL BLOCK, SCREW CONNECTION
PROVIDE 700-HN222 SOCKET AND 700-ADL1R DIODE WITH LED SURGE SUPPRESSOR.
120VAC 4-POLE MINIATURE SQUARE BASE RELAY C/W PUSH-TO-TEST AND LED.
ALLEN-BRADLEY 700-HC24A1-3-4 PROVIDE 700-HN104 MINI 14-BLADE SOCKET AND 700-AV3R VARISTOR LED SURGE 1. QUANTITY AND NUMBER OF POLE TO SUIT. 1
SUPPRESSOR.

GROUP 6 ALLEN-BRADLEY 855T SERIES (70mm) STACK LIGHTS

GROUP 7 ALLEN-BRADLEY 800TC/800H 2- POSITION PUSH-PULL MUSHROOM HEAD EMERGENCY STOP BUTTON GENERAL NOTES FOR JUNCTION BOXES: DETAIL NOTES:
A. PROVIDE ENOUGH TERMINALS TO TERMINATE ALL CONDUCTORS OF ALL CABLES 1. NEMA 4 ENCLOSURES ARE ACCEPTABLE IN ELECTRICAL ROOMS. ALL OTHER AREAS
ALLEN-BRADLEY 1489-M SERIES CIRCUIT BREAKER (120VAC) 1. SCHNEIDER EQUIVALENT IS ACCEPTABLE. CONNECTED TO THE JUNCTION BOX. REFER TO BLOCK DIAGRAMS. EXCEPT HAZARDOUS AREAS TO BE NEMA 4X STAINLESS STEEL.
1.1. JUNCTION BOXES IN HAZARDOUS AREAS SHALL BE RATED NEMA 7.
GROUP 8 B. SIZE EACH JUNCTION BOX TO ACCOMMODATE THE NUMBER OF TERMINALS.
ALLEN BRADLEY 100L SERIES LIGHTING CONTACTOR 2. PROVIDE H2OMIT PANEL VENT DRAIN FOR ALL EXTERIOR JUNCTION BOXES EXCEPT
C. SIZE THE DIN RAIL TO ACCOMMODATE THE NUMBER OF TERMINALS PLUS 10% SPARE. HAZARDOUS AREAS.
2.1. EX E SERIES FOR HAZARDOUS AREA PANEL VENT DRAIN.
ALLEN-BRADLEY 1489-M SERIES CIRCUIT BREAKER (120VAC) 1. SCHNEIDER EQUIVALENT IS ACCEPTABLE. D. ALTERNATIVE LAYOUT MAY BE CONSIDERED AT TIME OF SHOP DRAWINGS REVIEW.
3. ALL ITEMS LISTED ABOVE TO BE USED AS REQUIRED FOR A COMPLETE ASSEMBLY.
GROUP 9
E. PROVIDE AT LEAST 50mm SPACE BETWEEN WIRE DUCT AND TERMINAL.
ALLEN-BRADLEY 1492-SP SERIES SUPPLEMENTARY PROTECTOR (24VDC) 1. SCHNEIDER EQUIVALENT IS ACCEPTABLE. 1 PHASE A - ADDENDUM #3 10/11/23
F. TERMINAL BLOCKS TO BE LABELED NUMERICALLY, STARTING AT 1 AND INCREMENTING
BY 1. 0 PHASE A ISSUED FOR TENDER 02/10/23
GROUP 12 ALLEN-BRADLEY 100 C SERIES CONTACTOR
G. JUNCTION BOX WIRING SHALL BE IP2X. PROVIDE ALL ACCESSORIES REQUIRED FOR A No. ISSUE / REVISION DD/MM/YY
IP2X RATING.
GROUP 13 ILSCO COPPER LUG FOR TWO (2) 12AWG TO 2/0 GROUND WIRE
This drawing is copyright protected and may not be reproduced or
H. PROVIDE A LAMACOID LABEL AS INDICATED ON THE DRAWINGS. used for purposes other than execution of the described work without
1. PUSHBUTTON TO BE FLUSH HEAD UNLESS the express written consent of J.L. Richards & Associates Limited.
GROUP14 ALLEN-BRADLEY 800TC SERIES PUSH BUTTON I. USE SUITABLE CONSTRUCTION GRADE ADHESIVE TO SECURE LAMACOID TO JUNCTION
OTHERWISE NOTED.
BOX. ENSURE ADHESIVE IS RATED FOR THE INTENDED ENVIRONMENTAL CONDITIONS. VERIFY SHEET SIZE AND SCALES. BAR TO THE
1. HAMMOND EQUIVALENT IS ACCEPTABLE. RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
120VAC ELECTRIC HEATER WITH BUILT-IN FAN AND THERMOSTAT. BRUSHED SCREWS, OR OTHER MEANS REQUIRING PUNCTURING OF THE ENCLOSURE, IS NOT
HOFFMAN DAH SERIES 2. SIZE HEATER TO SUIT ENCLOSURE. PROVIDE
ALUMINUM FINISH. THERMOSTAT RANGE: -18°C TO 38°C. ACCEPTABLE. SCALE:
HEAT CALCULATIONS FOR REVIEW. NTS
GROUP 15
TWIN THERMOSTAT WITH TWO INDEPENDENTLY SWITCHABLE THERMOSTATS. J. REFER TO DRAWING I010A AND SECTION 17051 FOR FURTHER DETAILS.
HAMMOND SKTD SERIES 1. HOFFMAN EQUIVALENT IS ACCEPTABLE.
RANGE: 0°C TO 60°C (MINIMUM). UNIT IN CELSIUS.

SINGLE DOOR NEMA 4 ANSI 61 GREY ENCLOSURE WITH WINDOW. SIZE CLIENT:
HAMMOND ECLIPSE, EN4SD SERIES 1. HOFFMAN EQUIVALENT IS ACCEPTABLE.
ENCLOSURE TO SUIT.
GROUP 16 TERMINAL STRIP
END
HAMMOND EP SERIES INNER PANEL FOR ECLIPSE EN4SD SERIES PANEL. SIZE ENCLOSURE TO SUIT. 1. HOFFMAN EQUIVALENT IS ACCEPTABLE.
ANCHOR (TYP.)

24VDC FLASHER (REPAEAT CYCLE STARTS W/ PULSE) HIGH PERFORMANCE TIMER


GROUP 17 ALLEN BRADLEY 700-FS SERIES
(0.15 TO 3 SECONDS) C/W FORM C CONTACT.
CONSULTANT: www.jlrichards.ca
24VDC ONE SHOT HIGH PERFORMANCE TIMER (0.5 TO 10MIN) C/W FORM C 50
GROUP 18 ALLEN BRADLEY 700-FS SERIES
CONTACT.
WIRING
1. PROVIDE REMOTE RESET ACCESSORY c/w
GROUP 19 ALLEN-BRADLEY E100 SERIES ELECTRONIC OVERLOAD RELAY
PUSHBUTTON ON PANEL DOOR
DUCT (TYP.)
1. REFER TO SPECIFICATIONS SECTION 17051.
FERRAZ SHAWMUT
FSPDB SERIES FINGER-SAFE POWER DISTRIBUTION BLOCKS 2. PROVIDE FSPIN1 (PIN) ABD FSCAPX (CAP
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475 CONTROL PANEL LAYOUT.dwg

GROUP 20 (MERSEN)
PLUG) SERIES ACCESSORIES. CONSULTANT:
1. c/w ROTARY VARIABLE DEPTH OPERATING DIN RAIL
H-FRAME MOULDED CASE SWITCH
ALLEN-BRADLEY 140 U SERIES MECHANISM AND OPERATING ROD, SIZED TO SUIT
PROVIDE AUXILIARY CONTACT FOR CIRCUIT BREAKER STATUS 140MT SERIES INNER
2. EATON EQUIVALENT IS ACCEPTABLE
PANEL
FERRAZ SHAWMUT
GROUP 21 (MERSEN) ULTRASAFE SERIES FUSE HOLDER 1 1. c/w MATCHING BUSSMAN FUSES
GROUND BAR
1. c/w IP2X APPURTENANCES, AS REQUIRED FOR
ALLEN-BRADLEY 1497 SERIES CONTROL CIRCUIT TRANSFORMER IP2X WIRING RATING
PROFESSIONAL STAMP PROJECT NORTH
2. OR APPROVED EQUIVALENT

GENERAL NOTES FOR MISCELLANEOUS PANELS: DETAIL NOTES:


A. REFER TO PANEL WIRING LOGIC DIAGRAMS. 1. NEMA 4 ENCLOSURES ARE ACCEPTABLE IN ELECTRICAL ROOMS. ALL OTHER AREAS
EXCEPT HAZARDOUS AREAS TO BE NEMA 4X STAINLESS STEEL.
B. PROVIDE SHOP DRAWINGS FOR EACH PANEL. SHOP DRAWING PACKAGE TO INCLUDE DETAILED 1.1. ENCLOSURES IN HAZARDOUS AREAS SHALL BE RATED NEMA 7.
PROPOSED FACEPLATE AND REAR PANEL LAYOUTS, DETAILED WIRING DIAGRAMS AND
DATASHEETS FOR EACH PROPOSED COMPONENT. 2. PROVIDE H2OMIT PANEL VENT DRAIN FOR ALL EXTERIOR PANELS EXCEPT HAZARDOUS
AREAS.
C. THE PANEL BUILDER IS RESPONSIBLE FOR THE REAR PANEL LAYOUTS. PROJECT:
2.1. EX E SERIES FOR HAZARDOUS AREA PANEL VENT DRAIN.
D. WIRE EACH PANEL PER THE INTENT OF THE WIRING LOGIC PROVIDED.
MUNICIPALITY OF NORTH
3. RELAY VOLTAGES AND NUMBER OF POLES TO SUIT APPLICATION.
GRENVILLE - WATER POLLUTION
E. PROVIDE A LAMACOID FOR EACH PANEL.
4. PROVIDE R5, R FOIL INSULATION IN ALL HEATED ENCLOSURES.
CONTROL PLANT EXPANSION
F. FOR EACH 800T SERIES OPERATOR INTERFACE DEVICE PROVIDE THE CORRESPONDING
MANUFACTURER ENGRAVED LEGEND PLATE PER GROUP 2. PHASE - A
KEMPTVILLE, ONTARIO
G. REFER TO DRAWING I010A AND SECTION 17051 FOR FURTHER DETAILS.
DRAWING:
H. PROVIDE TERMINAL BLOCKS, WIRE DUCTS, GROUND BARS AND OTHER ACCESSORIES, AS
ELECTRICAL

November 14, 2023 9:52:37 AM


REQUIRED, FOR A COMPLETE INSTALLATION, PER DRAWING I010A. PROVIDE TERMINALS AND
WIRE DUCTS FOR ALL LOCAL CONTROL PANELS AND ALL CONTROL PANELS. PROVIDE END
ANCHORS TO SECURE TERMINALS.
SITE-WIDE
I. PROVIDE ENOUGH TERMINAL BLOCKS TO TERMINATE ALL CONDUCTORS OF ALL CABLES MISCELLANEOUS CONTROL
CONNECTED TO THE PANEL. REFER TO BLOCK DIAGRAMS AND OTHER PERTINENT DRAWINGS. PANELS AND JUNCTION BOXES
J. SIZE DIN RAILS TO ACCOMMODATE ALL THE TERMINALS AND COMPONENTS PLUS 10% SPARE.
DESIGN:
K. LABEL TERMINAL BLOCKS NUMERICALLY, STARTING AT 1 AND INCREMENTING BY 1. MM/LO
DRAWN: DRAWING #:
LO

PLOT DATE:
L. PROVIDE AT LEAST 50mm SPACE BETWEEN WIRE DUCT AND TERMINALS.
CHECKED:

JLR #:
JO
29475
I017A
GENERAL NOTES (APPLIES TO ALL CONTROL PANELS): NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
GAS MONITOR HIGH LEVEL ALARM 800 SERIES
A. ALL WIRES TO BE TERMINATED USING CRIMP-ON FERRULES. ONLY ONE WIRE PER FERRULE. ENSURE ALL STRANDS OF 1 NEW AERATION NEW PRIMARY NEW
THE WIRE ARE CRIMPED WITHIN THE FERRULE AND THAT THERE ARE NO STRAY STRANDS OF WIRE.
FAULT STACK LIGHT (RED) TANKS CLARIFIERS HEADWORKS
(PLC DI) 500 SERIES 400 SERIES 200 SERIES

B. NO MORE THAN TWO (2) WIRES TO BE CONNECTED TO THE SAME SIDE OF A TERMINAL. PROVIDE ADDITIONAL TERMINALS
AS REQUIRED.
NEW SECONDARY NEW TERTIARY
C. WIRING TO BE IN ACCORDANCE WITH THE LATEST REVISION OF THE ONTARIO ELECTRICAL SAFETY CODE AS WELL AS GAS ALARM HIGH LEVEL ALARM FILTER BUILDING
1 CLARIFIERS
700 SERIES (PHASE B)
APPLICABLE CSA STANDARDS. (PLC DI) HORN 600 SERIES (PHASE B)

D. FOLLOW MANUFACTURER'S RECOMMENDATIONS FOR INSTALLATION AND WIRING OF COMPONENTS.


1
E. SECURE WIRES IN WIRE DUCT USING CABLE TIES. LEAVE ENOUGH SLACK ON THE CABLE TIES FOR WIRE MANIPULATION.
REMOVE EXCESS CABLE TIE ENDS. CABLE TIE APPLICATION TO BE DONE IN A NEAT ORGANIZED MANNER. GAS WARNING EXISTING SERVICE
1 BUILDING
(PLC DI) 300 SERIES
F. ALL PLC AND MIO I/O POINTS TO BE TERMINATED, INCLUDING SPARE I/O POINTS. REFER TO THE I/O SCHEDULES FOR A
LISTING OF ALL I/O POINTS. HIGH LEVEL WARNING
STACK LIGHT (AMBER)
G. THESE DRAWINGS TO BE READ IN CONJUNCTION WITH THE PLC/MIO I/O TABLES AND SHOP DRAWINGS FOR THE PERTINENT
EQUIPMENT/DEVICES. THE CONTRACTOR IS RESPONSIBLE FOR REVIEWING THE DOCUMENTATION OF ALL HORN SILENCE KEY PLAN
EQUIPMENT/DEVICES CONNECTED TO PLC PANEL FOR PREPARATION OF THE PLC PANEL SHOP DRAWING.

H. PERFORM A "PULL TEST" ON EACH WIRE TO CONFIRM THAT IT IS SECURELY TERMINATED. KNIFE TERMINAL (TYP.) DRAWING NOTES:
I. LABEL EACH WIRE AS INDICATED. CONTRACTOR TO SELECT APPROPRIATE CONTACT TO
1
NOTES: SUIT.
J. THE PANEL BUILDER IS RESPONSIBLE FOR IDENTIFYING THE CORRECT TERMINALS FOR ALL DEVICES WIRED IN EACH
CONTROL PANEL AS WELL AS THOSE OF THE FIELD DEVICES WIRED TO EACH CONTROL PANEL. THE FINAL TERMINAL
A. PROVIDE RELAYS TO DUPLICATE THE SIGNALS FROM THE CONTACTS INSIDE THE ULTRASONIC SWITCH (LS-4029).
DESIGNATIONS ARE TO BE INCLUDED ON THE AS-BUILT DOCUMENTATION.
LOCATE THOSE RELAYS INSIDE CP-8000. USE 24VDC SIGNALS TO PICKUP THE RELAY STATUSES FROM THE
ULTRASONIC SWITCH.
K. ALL NEW ALARMS TO BE WIRED IN A FAIL-SAFE MANNER, SUCH THAT AN INPUT IS ALWAYS PRESENT ON THE PLC INPUT
CARD, UNLESS THERE IS AN ALARM. FOR EXAMPLE, IN THE CASE OF THE UPS ALARMS SELECT THE CONTACT (FORM A OR HORN SILENCE B. PROVIDE A DEDICATED CIRCUIT FOR THE STACK LIGHT.
FORM B) TO PROVIDE FAIL-SAFE WIRING. PROVIDE ALL RELAYS AND ACCESSORIES REQUIRED TO PROVIDE FAIL-SAFE RESET
WIRING.
C. PROVIDE A DEDICATED 24VDC CIRCUIT FOR THE DISPLAY.
L. REFER TO THE I/O LIST FOR CIRCUIT MONITORING (POWER FAILURE RELAYS) INPUTS TO THE PLC/MIO. IN SOME CASES
D. HORN CAN ONLY BE SILENCED FROM SCADA VIA SCADA PUSHBUTTON. RED AND AMBER LIGHTS TO REMAIN
MORE THAN ONE RELAYS ARE USED TO MONITOR CIRCUITS FOR A PARTICULAR PLC OR MIO I/O CARD. IN SUCH CASES,
ENERGIZED AS LONG AS THE CONDITION EXISTS.
THE RELAY CONTACTS SHALL BE WIRED IN SERIES.
E. PROVIDE A KNIFE STYLE TERMINAL BLOCK FOR EACH STACK LIGHT AS WELL AS THE HORN. KNIFE TERMINAL TO ACT
M. PROVIDE 120VAC DISCRETE OUTPUT WIRING AS REQUIRED FOR FIELD DEVICES.
GAS ALARM AS A DISCONNECT.
N. PROVIDE DRY CONTACT WIRING FOR THE DISCRETE OUTPUT CARDS OF EACH PLC AND MIO AS REQUIRED BY THE FIELD STACK LIGHT
F. PROVIDE A LAMACOID LABEL WITH A DESCRIPTION OF TANK ALARM AND WARNING LEVELS.
DEVICE/EQUIPMENT. (RED UAL)
O. PROVIDE LOOP POWERED OR FIELD POWERED WIRING FOR THE ANALOG INPUT CARDS OF EACH PLC AND MIO AS
REQUIRED BY THE FIELD DEVICE/EQUIPMENT.
GAS ALARM 2 LCP-4019 WIRING LOGIC
P. REFER TO THE INSTALLATION DOCUMENTATION FOR THE REQUIREMENTS OF EACH FIELD DEVICE/EQUIPMENT.
HORNS (YA) SCALE: NTS
I022A
Q. PROVIDE A TWO-TIER KNIFE TERMINAL BLOCK FOR EACH DISCRETE I/O. WIRE EACH DISCRETE I/O AS PER THE GENERAL
INTENT OF THE EXAMPLES PROVIDED AND AS PER THE MANUFACTURERS' RECOMMENDATIONS. SOME DISCRETE I/O
REQUIRE ISOLATION RELAYS, PROVIDE ALL SUCH RELAYS. THE ACCEPTABLE ISOLATION RELAYS ARE SPECIFIED IN THE
CONTROL PANELS BILL OF MATERIALS.

R. PROVIDE A TWO-TIER KNIFE TERMINAL BLOCK FOR EACH ANALOG I/O. WIRE EACH ANALOG I/O AS PER THE GENERAL
INTENT OF THE EXAMPLES PROVIDED AND AS PER THE MANUFACTURERS' RECOMMENDATIONS. SOME ANALOG I/O GAS WARNING
REQUIRE ISOLATION AMPLIFIERS/DUPLICATORS. PROVIDE ALL SUCH AMPLIFIERS/DUPLICATORS. THE ACCEPTABLE STACK LIGHT
ANALOG ISOLATING AMPLIFIERS/DUPLICATORS ARE SPECIFIED IN THE CONTROL PANELS BILL OF MATERIALS. 4-20mA
DEVICES IN SERIES IS UNACCEPTABLE. PROVIDE DUPLICATIONS FOR 4-20mA SIGNAL MULTIPLEXING.
(AMBER UAL)

S. EACH DIN RAIL IN EACH CONTROL PANEL SHALL BE BONDED. REFER TO BONDING DETAIL. PROVIDE A GROUND TERMINAL
FOR EACH DIN RAIL. GROUND TERMINALS NOT SHOWN ON LAYOUT DRAWINGS.

T. BREAKERS TO BE "C CURVE" UNLESS OTHERWISE INDICATED. COORDINATE BREAKER SIZES AND CHARACTERISTICS WITH
EQUIPMENT MANUFACTURER'S RECOMMENDATIONS.

U. CIRCUIT BREAKERS AND CIRCUIT MONITORS TAGS TO BE SEQUENTIAL.

V. PROVIDE ADDITIONAL BREAKERS AS REQUIRED FOR POWER DISTRIBUTION.

W. PANEL BUILDER TO SIZE BREAKERS TO SUIT. HVAC FAULT


STACK LIGHT
X. PROVIDE (ADDITIONAL) RELAYS AND OTHER APPURTENANCES REQUIRED TO IMPLEMENT THE LOGIC SHOWN AND TO MEET (CLEAR UAL)
THE GENERAL INTENT OF THE DESIGN. 1 PHASE A - ADDENDUM #3 10/11/23

Y. PANEL BUILDER TO VERIFY THE WIRING REQUIREMENTS OF THE EXISTING SIGNALS PRIOR TO PREPARING SHOP 0 PHASE A ISSUED FOR TENDER 02/10/23
DRAWINGS FOR THE NEW PLC PANELS.

No. ISSUE / REVISION DD/MM/YY

This drawing is copyright protected and may not be reproduced or


POWER AND CONTROL WIRE (INTERNAL TO ENCLOSURE) SPECIFICATIONS: used for purposes other than execution of the described work without
OCCUPIED STATUS the express written consent of J.L. Richards & Associates Limited.
SIZE: STACK LIGHT
1. USE A MINIMUM OF 14AWG FOR POWER WIRING, EXCEPT AS OTHERWISE NOTED. (BLUE UAL) VERIFY SHEET SIZE AND SCALES. BAR TO THE
2. USE A MINIMUM OF 16AWG FOR CONTROL WIRING, EXCEPT AS OTHERWISE NOTED. RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
COLOUR: SCALE:
NTS
1. 24VAC/120VAC (NON-UPS): BLACK (LINE); WHITE (NEUTRAL).
2. 24VAC/120VAC (UPS): ORANGE (LINE); GREY (NEUTRAL). KNIFE TERMINAL (TYP.)
3. 24VDC: YELLOW (+VE); BROWN (-VE).
4. GROUND: GREEN.
5. INTRINSIC SAFETY: BLUE. CLIENT:

TYPE:
1. EACH POWER AND CONTROL WIRE TO MEET THE FOLLOWING SPECIFICATIONS:
1.1. RW 90, 600V RATED NOTES:
1.2. COPPER CONDUCTOR WITH XLP INSULATION
1.3. 90°C WET OR DRY A. THE ABOVE LOGIC USES ONE GAS MONITOR AS AN EXAMPLE. UPDATE LOGIC TO SUIT SCENARIOS WHERE MULTIPLE
1.4. IN ACCORDANCE WITH CSA C22.2 No. 38 GAS MONITORS ARE PRESENT. IN SUCH CASES, ENSURE THE HORN IS RE-TRIGGERED UPON EACH GAS MONITOR
1.5. ANIXTER 6CL SERIES SINGLE STRANDED CONDUCTOR FAILURE/ALARM IF CURRENTLY SILENCED FROM A PREVIOUS ALARM/FAULT CONDITION. PROVIDE TIMERS, RELAYS AND
ALL APPURTENANCES TO SUIT.
CONSULTANT: www.jlrichards.ca
ANALOG WIRE (INTERNAL TO ENCLOSURE) SPECIFICATIONS: B. REFER TO THE I/O LIST AND BLOCK DIAGRAMS FOR AREAS THAT HVAC FAULT AND OCCUPIED STATUS STACK LIGHTS.

TYPE: C. ALL PLC DIGITAL INPUTS MAY NOT HAVE BEEN IDENTIFIED IN THIS LOGIC. REFER TO THE I/O LIST AND P&ID'S.
1. BELDEN 8761 FOR PAIRS
2. BELDEN 22660 FOR TRIADS D. PROVIDE ADDITIONAL RELAYS AS REQUIRED.

E. R1 ENERGIZED WHEN THERE IS NO FAULT.


NOTES:
F. R2 ENERGIZED WHEN THERE IS NO ALARM. CONSULTANT:
A. WIRE TO MEET THE REQUIREMENTS OF THE COMPONENT MANUFACTURERS.
B. PROVIDE SHOP DRAWINGS FOR WIRES TO BE USED. G. R3 ENERGIZED WHEN THERE IS NO WARNING.

H. R6 TO DE-ENERGIZE UPON PLC FAILURE. REFER TO I/O TABLES FOR NOTES ON PLC WATCHDOG MONITORING
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475 WIRING LOGIC.dwg

REQUIREMENTS.

I. ALL THE STACK LIGHTS AND HORNS WILL BE ENERGIZED SIMULTANEOUSLY IF THE GAS MONITOR HAS FAULTED OR THE
PLC HAS FAILED.

J. THIS LOGIC IS TO BE IMPLEMENTED IN EACH PLC PANEL THAT MONITORS GAS MONITORS AND CONTROLS THE PROFESSIONAL STAMP PROJECT NORTH
CORRESPONDING STACK LIGHTS.

K. PROVIDE A KNIFE STYLE TERMINAL BLOCK FOR EACH STACK LIGHT AS WELL AS THE HORN. KNIFE TERMINAL TO ACT AS
A DISCONNECT.

L. L. PROVIDE A DEDICATED CIRCUIT INSIDE THE PLC PANEL FOR EACH STACK LIGHT ASSEMBLY, SO EACH STACK LIGHT
ASSEMBLY CAN BE REMOVED FROM SERVICE FOR MAINTENANCE WITHOUT IMPACTING THE OTHERS IN THE CHAIN.

1 TYPICAL STACK LIGHT WIRING LOGIC PROJECT:

I022A SCALE: NTS MUNICIPALITY OF NORTH


GRENVILLE - WATER POLLUTION
CONTROL PLANT EXPANSION
PHASE - A
KEMPTVILLE, ONTARIO

DRAWING:

ELECTRICAL

November 14, 2023 9:54:31 AM


SITE-WIDE
CONTROL WIRING NOTES AND
MISCELLANEOUS LOGIC

DESIGN:
MM/LO
DRAWN: DRAWING #:
MM

PLOT DATE:
CHECKED:

JLR #:
JO
29475
I022A
FINGER SAFE POWER DISTRIBUTION BLOCK (TYPICAL) 600 VAC, 1Ø HEATER
CIRCUIT BREAKER c/w MOLDED CASE LOCAL JUNCTION BOX SIZE AS INDICATED
AUXILIARY CONTACTS 'BK-1' DISCONNECT CONTACTOR DISCONNECT (JBP-XXX) NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
L1 800 SERIES
NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
L2 500 SERIES 400 SERIES 200 SERIES

L3

BREAKER SIZE TO SUIT NEW SECONDARY NEW TERTIARY


SIZE TO SUIT HEATER CLARIFIERS FILTER BUILDING
HEATER LOAD. 600 VAC, 1Ø HEATER 600 SERIES (PHASE B) 700 SERIES (PHASE B)
SIZE AS INDICATED

INSIDE POWER INSIDE HEATER FIELD WIRING


DISTRIBUTION PANELBOARD CONTROL PANEL EXISTING SERVICE
BUILDING
300 SERIES

600 VAC, 1Ø HEATER


SIZE AS INDICATED KEY PLAN

FUSE

FUSE
SUPPLIER TO SIZE FUSE TO
SUIT CONTROL CIRCUIT

600V/120V CONTROL TRANSFORMER


SUPPLIER TO SIZE FUSE TO VA SIZE TO SUIT STARTER CONTROL
SUIT CONTROL CIRCUIT CIRCUIT
FUSE
100 GND

AT HCP AT LCP
101 OFF OFF
HAND AUTO HAND AUTO
R2
x x HEATER RUN
M1 HEATER HOLDING CONTACTOR RELAY
102

x x AUTO MODE
R1
102 RELAY

x x R2 PLC DO
103 P.T.T.
HEATER RUNNING
RUN CMD REMOTE PILOT LIGHT AT LCP
x x
104 M1 P.T.T.
HEATER RUNNING
PILOT LIGHT AT HCP
105
DISC
R2 DISCONNECT
RELAY
SEE NOTE 5

R1 M1 R2

1 PHASE A - ADDENDUM #3 10/11/23

0 PHASE A ISSUED FOR TENDER 02/10/23

No. ISSUE / REVISION DD/MM/YY

PLC DI PLC DI PLC DI


This drawing is copyright protected and may not be reproduced or
(IN AUTO) (RUNNING) (DISCONNECT OPEN)
used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.

VERIFY SHEET SIZE AND SCALES. BAR TO THE


RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
SCALE:
NTS

CLIENT:
1

DETAIL NOTES: 5. FOR EACH STARTER, PROVIDE TERMINALS TO 6. MONITOR THE STATUS OF EACH LOCAL
INTERLOCK THE STARTER VIA EXTERNAL DISCONNECT VIA A RELAY. PROVIDE RELAY TO
1. PILOT LIGHTS TO BE 'PUSH TO TEST' (P.T.T.) 120V HARDWIRED SIGNALS. CONTRACTOR TO SUIT. NOTE THE DISCONNECTS HAVE 2
LED LAMPS. LAMP COLOURS TO BE CONFIRMED PROVIDE JUMPERS IF THE INTERLOCKS ARE CONTACTS. BOTH TO BE WIRED TO THE CONSULTANT: www.jlrichards.ca
PRIOR TO MANUFACTURING. REFER TO NOT USED. PROGRAM THE STARTERS TO STARTER: ONE CONTACT TO BE WIRED TO THE
SECTION 17051. IMMEDIATELY SHUTDOWN IF THE INTERLOCKS ENABLE INPUT, THE OTHER WIRED TO A RELAY.
ARE REMOVED. NOTE SUCH INTERLOCKS MAY
2. PROVIDE TERMINAL BLOCKS ( ) AS INDICATED. INCLUDE A LOCAL DISCONNECT; IN WHICH CASE 7. BREAKER TO BE UL 489 LISTED AS A BRANCH
NUMBER OF TERMINALS AND MARKINGS TO AN EARLY BREAK CONTACT ON THE BREAKER - EQUIVALENT TO ALLEN-BRADLEY
SUIT. DISCONNECT WILL TRIGGER A SHUTDOWN OF 1489-M SERIES.
THE STARTER AND THE STARTER SHOULD
3. SIZE CIRCUIT BREAKERS TO SUIT HEATER RESPOND ACCORDINGLY TO PREVENT
LOADS. EQUIPMENT DAMAGE. CONSULTANT:

4. REFER TO CONTROL PANEL BOM (I017A) FOR


CONTACTOR REQUIREMENTS.
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475 WIRING LOGIC.dwg

PROFESSIONAL STAMP PROJECT NORTH

PROJECT:

MUNICIPALITY OF NORTH
GRENVILLE - WATER POLLUTION
CONTROL PLANT EXPANSION
PHASE - A
KEMPTVILLE, ONTARIO
DRAWING:

November 14, 2023 12:39:04 PM


ELECTRICAL
SITE-WIDE
HEATER CONTROL PANEL (HCP)
WIRING LOGIC

HEATER CONTROL PANEL DESIGN:


LO
1 WIRING LOGIC DRAWN:
NB DRAWING #:

PLOT DATE:
CHECKED:

I023A
I023A SCALE: NTS JO
JLR #:
29475
GLOBAL-1000
DP-201 3c #12 AWG RW90 + GND IN EMT
600 VOLT, 3Ø-3W NEW DEWATERING AND ELECTRICAL SERVICE
SURFACE MOUNTED DIGESTER CONTROL ENTRANCE BUILDING
900 SERIES
BUILDING
35kAIC 800 SERIES
NEW AERATION NEW PRIMARY NEW
400 AMP MAIN BREAKER TANKS CLARIFIERS HEADWORKS
FED FROM MCC-200 500 SERIES 400 SERIES 200 SERIES
SEE DWG E201A FOR
DETAILS 15A
MCP-2001 GLOBAL-1000
2
LOAD DESCRIPTION BRKR CCT CCT BRKR DESCRIPTION LOAD
3P
100A, 600V, 3ɸ, 3W, 35kAIC 2
NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
1 2 700 SERIES (PHASE B)
600 SERIES (PHASE B)
SPARE 15A, 3P 3 4 15A, 3P SPARE
5 6
7 8
SPARE 15A, 3P 9 10 15A, 3P SPARE
11 12
EXISTING SERVICE
13 14 BUILDING
200A, 15A 15A 15A 15A
SPARE 15 16 15A, 3P SPARE 300 SERIES
3P 3P 3P 3P 3P
17 18
19 20

FVR

FVR

FVR

FVR
SPARE 15A, 3P 21 22 15A, 3P P-205 BIN ROOM SUMP
23 24
25 26 KEY PLAN
P-206 PIPE GALLERY SUMP 15A, 3P 27 28 15A, 3P VFC-614
29 30
31 32 DRAWING NOTES:
TX-202 (LP-202) 60A, 3P 33 34 60A, 3P TX-203 (LP-203)
35 36 1 COORDINATE EXACT BREAKER SIZE WITH SPD
37 38 MANUFACTURER.
MCP-2001 15A, 3P 39 40 50A, 3P MCP-2002
41 42
43 44
2 BREAKER, BUS SIZES AND OTHER DETAILS SHOWN
HCP-4001
20A, 3P 45 46 20A, 3P
HCP-4004 DP-201 FOR QUOTATION PURPOSES. FINAL DETAILS TO BE

3c #6 AWG RW90 +
(RH-401, RH-402, RH-403) (RH-404, RH-405, RH-406)

3c #6 AWG RW90 +
GLOBAL-1000

47 48 COORDINATED WITH THE MOTOR CONTROL PANEL


49 50 SUPPLIER.
HCP-4007
20A, 3P 51 52 20A, 3P SPARE TO CP-2001

GND IN EMT
GND IN EMT
(RH-407, RH-408, RH-409)
53 54
55 56 3c #12 AWG TECK90 AL ARMOUR
SPARE 15A, 3P 57 58 20A, 3P SPARE

Cat 6

Cat 6

Cat 6

Cat 6
1 ANIXTER 7TK SERIES GLOBAL-1000

59 60

TOTAL CONNECTED LOAD: LCP-2030


GLOBAL-1000
LCP-2031
GLOBAL-1000

PHASE LOAD TO BE FILLED IN BY CONTRACTOR:


LOAD PHASE A: LOAD PHASE B: LOAD PHASE C:
H2 TX-202 H2 TX-203 STARTER STARTER
Cat 6 Cat 6 Cat 6 Cat 6 Cat 6
0001-LABOLG 0001-LABOLG
PANEL PANEL
REMARKS
H3 H1 600V H3 H1 600V
1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED. NOTE: PROVIDE PADLOCKABLE CLASPS
2. DEDICATED NEUTRAL FOR ALL BREAKERS PROVIDED.
3.
*
GFI 45kVA 45kVA LD-MS-201
GLOBAL-1000
LD-MS-202
GLOBAL-1000
LD-SCV-201
GLOBAL-1000
LD-SWP-201
GLOBAL-1000

4. LOCKED
5. ARC FAULT CIRCUIT INTERRUPTER X2 X1 120/208V X2 X1 120/208V
X0 X0
LD-P-205 LD-P-206
1 DP-201 PANEL SCHEDULE X3 X3 GLOBAL-1000 GLOBAL-1000

E202A SCALE: N.T.S.

LP-203

4c #2/0 AWG RW90 +

4c #2/0 AWG RW90 +


GLOBAL-1000

120/208 VOLT, 3Ø-4W

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR


SURFACE MOUNTED 1 1 2 2
ELECTRICAL ROOM

GND IN EMT

GND IN EMT

3c #12 AWG ARMOURED BELDEN

3c #12 AWG ARMOURED BELDEN


225 AMP MAINS
NOTE 'A' NOTE 'A' 1.1 1.1

SCV-201

SCREENINGS WASH PRESS


SWP-201
SCREENINGS CONVEYOR
RAW SEWAGE MECHANICAL SCREEN No. 1
MS-201

RAW SEWAGE MECHANICAL SCREEN No. 2


MS-202
10 kAIC

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES


BIN ROOM SUMP PUMP

PIPE GALLERY SUMP PUMP


P-205

P-206
LOAD DESCRIPTION BRKR CCT CCT BRKR DESCRIPTION LOAD
CC-401 HEATER 15A,1P 1 2 15A,1P CC-402 HEATER
LC-401 / LC-402 HEATER 15A,1P 3 4 25A,1P ELEC. RM. SUPPLY FAN SF-202
VFC-401 SLUDGE CONTROL VALVE 15A,1P
15A,1P
5 6 15A,1P
15A,1P
VFC-402 SLUDGE CONTROL VALVE 1 LP-202 1 LP-203
VFC-403 SLUDGE CONTROL VALVE 7 8 VFC-404 PRIMARY SCUM 3-WAY VALVE 0001-LABOLG 0001-LABOLG
1 PHASE A - ADDENDUM #3 10/11/23

VFD CABLE

VFD CABLE
VFC-409 TANK 1 AERATION VALVE 1 15A,1P 9 10 15A,1P VFC-411 TANK 2 AERATION VALVE 1
VFC-410 TANK 1 AERATION VALVE 2 15A,1P 11 12 15A,1P VFC-412 TANK 2 AERATION VALVE 2
VFC-413 TANK 3 AERATION VALVE 1 15A,1P 13 14 15A,1P SPARE 0 PHASE A ISSUED FOR TENDER 02/10/23
VFC-414 TANK 3 AERATION VALVE 2 15A,1P 15 16 15A,1P SPARE
17 18
COOL. CDN-201 (AC-201) 40A,2P
19 20
40A,2P COOL. CDN-202 (AC-202)
GLOBAL-1000
SPD-202 GLOBAL-1000
SPD-203 No. ISSUE / REVISION DD/MM/YY
21 22 20A,1P SERV. RECP. - MUA UNIT *
COOL. CDN-203 (AC-203) 40A,2P This drawing is copyright protected and may not be reproduced or
23 24 20A,1P SERV. RECP. - OC UNIT * 3c #8 AWG RW90 + GND IN EMT
RECP. PRIMARY CLAR. TANK #1 20A,1P 25 26 20A,1P SERV. RECP. - EQUALIZATION PUMPS * used for purposes other than execution of the described work without
RECP. PRIMARY CLAR. TANK #2 20A,1P 27 28 20A,1P SERV. RECP. - LONG. COLLECTORS * the express written consent of J.L. Richards & Associates Limited.
RECP. PRIMARY CLAR. TANK #3 20A,1P 29 30 15A,1P SPARE
HEAT. UH-201, VFC-215 15A,1P 31 32 15A,1P HEAT. UH-202, VFC-216 VERIFY SHEET SIZE AND SCALES. BAR TO THE
RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING.
HEAT. UH-203, VFC-218
HEAT. UH-205, VFC-219
15A,1P
15A,1P
33
35
34
36
15A,1P
15A,1P
VFC-217
HEAT. UH-206, VFC-220
4 SINGLE LINE DIAGRAM (CONTINUED) 0 25mm
SCALE:
HEAT. UH-207, VFC-221 15A,1P 37 38 15A,1P HEAT. UH-208, VFC-222 E202A SCALE: N.T.S.
50A
MCP-2002 N.T.S.
SPARE 15A,1P 39 40 15A,1P SPARE 2
GLOBAL-1000

SPARE 15A,1P 41 42 15A,1P SPARE 3P


100A, 600V, 3ɸ, 3W, 35kAIC 2
SPARE 20A,1P 43 44 20A,1P SPARE
SPARE 20A,1P 45 46 20A,1P SPARE
SPARE 20A,1P 47 48 20A,1P SPARE CLIENT:
49 50
EUH-201 ELECTRICAL RM. UNIT HEATER 20A,3P 51 52 20A,3P EUH-202 ELECTRICAL RM. UNIT HEATER
53 54
55 56
SPARE 60A,3P 57 58 XXA,3P SPD-203 1 15A 15A 20A 20A 15A
59 60
3P 3P 3P 3P 3P

FVNR

FVNR

FVNR

FVNR

FVR
CONSULTANT: www.jlrichards.ca
TOTAL CONNECTED LOAD: _________ GENERAL NOTES:
PHASE LOAD TO BE FILLED IN BY CONTRACTOR:
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 HEADWORKS BLDG SINGLE LINE.dwg

LOAD PHASE A: _________ LOAD PHASE B: _________ LOAD PHASE C: _________ A. PROVIDE GROUND AS PER SPD MANUFACTURER'S
REQUIREMENTS. REFER TO SPECIFICATIONS FOR
REMARKS ADDITIONAL DETAIL. SCHEDULE OF SPDs
1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED.
2. DEDICATED NEUTRAL B. ALL INDICATED CABLES SHOWN AS "ARMOURED BELDEN
3. * GFI TYPE MANUFACTURER PART #
VFD CABLE" TO BE ALUMINUM ARMOURED BELDEN VFD CONSULTANT:
4. LOCKED CABLE SERIES 12295XX SERIES.
5. ARC FAULT CIRCUIT INTERRUPTER SPD-200 TOTAL PROTECTION TK-ST160-600NN-FLB
SOLUTIONS CANADA
C. REFER TO MOTOR STARTER AND CONTROL LIST IN THE ME
2 LP-203 PANEL SCHEDULE SERIES DRAWINGS FOR ADDITIONAL DETAILS.
SPD-202 TOTAL PROTECTION TK-ST080-3Y208-FLB
SOLUTIONS CANADA TO CP-2002
E202A SCALE: N.T.S. D. MCP BREAKER SIZES SHOWN FOR QUOTATION PURPOSES
ONLY. FINAL BREAKER SIZES TO BE DETERMINED BY
SPD-203 TOTAL PROTECTION TK-ST080-3Y208-FLB
MANUFACTURER, SUBJECT TO THE APPROVAL OF THE

Cat 6

Cat 6

Cat 6

Cat 6

Cat 6
GLOBAL-1000

SOLUTIONS CANADA PROFESSIONAL STAMP PROJECT NORTH


ENGINEER.

E. REFER TO DRAWING N001A FOR CAT6 NETWORK DETAILS. SPD-290 TOTAL PROTECTION TK-ST080-1S240-FLB

GLOBAL-1000
UP-290 SOLUTIONS CANADA
F. WHERE CONDUIT IS NOTED WITHOUT TRADE SIZE,
120/208 VOLT, 1PH, 3W, 60A BUS, 10KA CONTRACTOR TO PROVIDE SIZE IN COMPLIANCE WITH
40 AMP MAIN BREAKER ONTARIO ELECTRICAL SAFETY CODE REQUIREMENTS.
Cat 6 Cat 6 Cat 6 Cat 6 Cat 6
SURFACE MOUNTED
ELECTRICAL ROOM
LD-MIX-201
GLOBAL-1000
LD-MIX-202
GLOBAL-1000 GLOBAL-1000
LD-P-201 GLOBAL-1000
LD-P-202 LD-GC-201
GLOBAL-1000

LOAD DESCRIPTION BKR CCT CCT BKR DESCRIPTION LOAD


MCC-200 15A,1P 1 2 20A,1P FDP-2001 PROJECT:
CP-2000 15A,1P 3 4 15A,1P SPARE
CP-2001 15A,1P 5 6 15A,1P SPARE
MUNICIPALITY OF NORTH
CP-2002
SPARE
15A,1P
20A,1P
7
9
8
10
15A,1P
XXA,2P
SPARE
SPD-290
GRENVILLE - WATER POLLUTION
1
SPARE 20A,1P 11 12 CONTROL PLANT EXPANSION
TOTAL CONNECTED LOAD:
PHASE - A
KEMPTVILLE, ONTARIO

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR


PHASE LOAD TO BE FILLED IN BY CONTRACTOR: 2 2 7.5 7.5 1
LOAD PHASE A: __________ LOAD PHASE B: __________ DRAWING:

November 14, 2023 11:07:55 AM


GRIT PUMP 1

GRIT PUMP 2
GRIT TANK 1 VORTEX INDUCER

GRIT TANK 2 VORTEX INDUCER

P-201

P-202

GRIT CLASSIFIER
MIX-201

MIX-202

GC-201
REMARKS
1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED.
ELECTRICAL
HEADWORKS BUILDING

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES


2. DEDICATED NEUTRAL
3. GFI
4. LOCKED SINGLE LINE DIAGRAM AND PANEL
5. ARC FAULT CIRCUIT INTERRUPTER
SCHEDULES SHEET 2 OF 2

3 UP-290 PANEL SCHEDULE DESIGN:


MM/LO
SCALE: N.T.S. DRAWN: DRAWING #:
E202A MM

PLOT DATE:
CHECKED:

JLR #:
JO
29475
E202A
PRIMAR CLARIFIERS PID401A ELECTRICAL ROOM E ALI ATION TAN S PROCESS AIR PRIMAR CLARIFIERS PID401A
NE DE ATERING AND ELECTRICAL SERVICE
COAG LANT DOSING S STEM PID403A DIGESTER CONTROL
B ILDING
ENTRANCE B ILDING
900 SERIES
2P 16 A G 7 24 00 SERIES
NE PRIMAR NE
LD-LC-401 0001-LABOLG 4 14 A G STRAND AL ARMO RED
NE AERATION
TAN S CLARIFIERS HEAD OR S
RAD 500 SERIES 400 SERIES 200 SERIES
TEC 90 CABLE DEVICE

LIT
4015
ELEMENT
RAD
PRIMAR CLARIFIER 1 2 LE
NE TERTIAR
CONTROL PANEL 10 14 A G 4015 NE SECONDAR
FILTER B ILDING
LD-LC-402 4 14 A G 50 14 A G
CLARIFIERS
700 SERIES PHASE B
0001-LABOLG
TEC 90 CABLE GLOBAL
600 SERIES PHASE B
TEC 90 CABLE TEC 90 CABLE M
LCP-4010 VFC-404
1000

0001-LABOLG

LD-P-403
GLOBAL-1000

LD-CC-401 4 14 A G E ISTING SERVICE


0001-LABOLG 4 14 A G B ILDING
TEC 90 CABLE 300 SERIES
TEC 90 CABLE
4 14 A G
MCC-200 TEC 90 CABLE DEVICE

CP-2000 LSL
4 14 A G GLOBAL-1000

4030
DEVICE
TEC 90 CABLE 50 14 A G TEC 90 CABLE E PLAN
MS
4023
4 14 A G
DEVICE

MS
TEC 90 CABLE PLC
LCP-4013
GLOBAL-1000 GENERAL NOTES
4024 CONTROL PANEL
P 16 A G 7 24 STRAND AL ARMO RED
A REFER TO PID AS ELL AS MID DRA INGS
PRIMAR CLARIFIERS
SC M PIT LOCAL
LD-LC-403 CONTROL PANEL B REFER TO N001A FOR NET OR DETAILS
0001-LABOLG

4 14 A G
TEC 90 CABLE
C REFER TO THE ASSOCIATED MID S AND PID S
PRIMAR CLARIFIER 2 3 FOR COMM NICATION REFERENCE BET EEN
CONTROL PANEL VARIO S E IPMENT AND THE PLC PANEL
LD-CC-402 0001-LABOLG

4 14 A G 50 14 A G
TEC 90 CABLE TEC 90 CABLE D REFER TO DRA ING E000A FOR ADDITIONAL
LCP-4020 0001-LABOLG
CABLE RE IREMENTS

LD-CC-403 0001-LABOLG

4 14 A G
TEC 90 CABLE 4 14 A G LD-BL-501
GLOBAL-1000

TEC 90 CABLE

4 14 A G
DEVICE
TEC 90 CABLE
MS 6 TRIADS 16 A G 7 24
4025
STRAND AL ARMO RED 4 14 TEC 90 LD-BL-502
GLOBAL-1000

CABLE
LCP-5000
2 40 14 50 14 TEC 90 CABLE GLOBAL-1000

TEC 90 CABLE AERATION TAN S PID402A P 16 A G 7 24


STRAND AL ARMO RED BLO ER CONTROL PANEL 4 14 A G LD-BL-503
6 TRIADS 16 A G 7 24 GLOBAL-1000

STRAND AL ARMO RED TEC 90 CABLE


16 P 16 A G 7 24
STRAND AL ARMO RED
4 TRIADS 16 A G 7 24
STRAND AL ARMO RED 2P 16 A G 7 24
STRAND AL ARMO RED DEVICE

2 TRIADS 16 A G 7 24 PIT
STRAND AL ARMO RED INTEGRAL CABLE IN OCAL 5010
LD-P-401 DO COND IT ELEMENT

0001-LABOLG 4 14 A G 4P 16 A G 7 24 DEVICE DO
ELEMENT
PE
AIT AE 5010
TEC 90 CABLE STRAND AL ARMO RED 4011
4011
6 14 A G TEC 90 INTEGRAL CABLE IN OCAL
LCP-4011 0001-LABOLG

CABLE DO COND IT
DEVICE DO
ELEMENT

AIT AE
40 14 A G TEC 90 4012
LD-P-402 4012
4 14 A G PRIMAR SL DGE P MP CABLE INTEGRAL CABLE IN OCAL
0001-LABOLG

TEC 90 CABLE 1 2 LOCAL CONTROL 6 14 A G TEC 90


CABLE DO COND IT
PANEL DEVICE DO
ELEMENT
1 PHASE A - ADDEND M 3 10 11 23
GLOBAL-1000 GLOBAL-1000
AIT AE
JBD-500 JBA-500 4013 4013
10 14 A G 0 PHASE A ISS ED FOR TENDER 02 10 23
6 14 A G TEC 90
TEC 90 CABLE
LABOLG CABLE
M 4P 16 A G 7 24 10 14 A G N ISS E REVISION DD MM
VFC-614
0001
STRAND AL ARMO RED TEC 90 CABLE LABOLG

M T
10 14 A G VFC-409 0001

LABOLG
TEC 90 CABLE 4P 16 A G 7 24 10 14 A G JL R A L
M STRAND AL ARMO RED TEC 90 CABLE
VFC-401 LABOLG
VERIF SHEET SI E AND SCALES BAR TO THE
0001
M RIGHT IS 25 IF THIS IS A F LL SI E DRA ING
10 14 A G VFC-410 0 25
0001

LABOLG
TEC 90 CABLE 4P 16 A G 7 24 10 14 A G SCALE
NTS
M STRAND AL ARMO RED TEC 90 CABLE
VFC-402 LABOLG

0001
M
10 14 A G VFC-411
0001

TEC 90 CABLE 4P 16 A G 7 24 10 14 A G
LABOLG
CLIENT
M STRAND AL ARMO RED TEC 90 CABLE
VFC-403 GLOBAL

0001
M
10 14 A G VFC-412
1000

LABOLG
TEC 90 CABLE 4P 16 A G 7 24 10 14 A G
M STRAND AL ARMO RED TEC 90 CABLE
VFC-404 4P 16 A G 7 24
LABOLG

0001
M
STRAND AL ARMO RED VFC-413
29475 HEAD OR S B ILDING CONTROL BLOC DIAGRAM

0001

MAG
ELEMENT
MAG DEVICE
4P 16 A G 7 24 10 14 A G CONS LTANT
FE FIT
4010 4010 STRAND AL ARMO RED TEC 90 CABLE
GLOBAL

M
GLOBAL-1000
IB-202 VFC-414
1000

3 40 14
INTEGRAL CABLE 4 14 A G
TEC 90 CABLE
IN OCAL COND TEC 90 CABLE DEVICE

TC
4030

CONS LTANT
ELECTRICAL ROOM
LD-RH-401 0001-LABOLG 4 14 A G R 90 40 14 A G
GND IN OCAL COND TEC 90 CABLE
LCP-4001 0001-LABOLG
HCP-4001
0001-LABOLG

PROFESSIONAL STAMP PROJECT NORTH


6-E

LD-RH-404 0001-LABOLG 4 14 A G R 90 40 14 A G
GND IN OCAL COND TEC 90 CABLE
3-P

LCP-4004 0001-LABOLG
HCP-4004
0001-LABOLG

PROJECT

M NICIPALIT OF NORTH
D

GRENVILLE - ATER POLL TION


CONTROL PLANT E PANSION
PCP E

PHASE - A
EMPTVILLE ONTARIO
DRA ING

ELECTRICAL

14 2023 9 51 00 AM
LD-RH-407 0001-LABOLG 4 14 A G R 90 40 14 A G
GND IN OCAL COND TEC 90 CABLE
HEAD OR S B ILDING
P 29000 29475-000 -

LCP-4007 0001-LABOLG
HCP-4007
0001-LABOLG

CONTROL BLOC DIAGRAM 2 OF 2

1
DESIGN
MM LO

N
DRA N DRA ING
MM

PLOT DATE
CHEC ED
JO
I201A
L

JLR
29475
F
XLS XLS
PLC-200
Excel Sheet Data Exported on: 2017-07-11 11:25:22 AM Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-09
13:24:46 8:23:02 PM
COMPONENT SUMMARY COMPONENT I/O LIST
SLOT CATALOG IO IO CONTROLLER ISA NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
NUMB. NUMBER MANUFACTURER DESCRIPTION IO TYPE RACK COUNT COMMENTS IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS BUILDING 900 SERIES
800 SERIES
NEW AERATION NEW PRIMARY NEW
0 1756-A17 AB/RA 17 Slot ControlLogix Chassis Miscellaneous 0 0 DI - 25 YA SPD-200 SPD-200 (MCC-200) Alarm Headworks Electrical Room 0 = ALARM 0 5 9 TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES
0 1756-PB75 AB/RA 24VDC Power Supply (13A @ 5V) Miscellaneous 0 0 DI - 26 YA SPD-202 SPD-202 (LP-202) Alarm Headworks Electrical Room 0 = ALARM 0 5 10

0 1756-L84E AB/RA ControlLogix Processor with 20MB NV Memory Processor 0 0 DI - 27 YA SPD-203 SPD-203 (LP-203) Alarm Headworks Electrical Room 0 = ALARM 0 5 11
NEW TERTIARY
DI - 28 YA SPD-290 SPD-290 (UP-290) Alarm Headworks Electrical Room 0 = ALARM 0 5 12 NEW SECONDARY
0 1784-SD2 AB/RA 2Gb Secure Digital Memory Card Miscellaneous 0 0 CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)
DI - 29 0 5 13
1 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 0 0
DI - 30 YA FDP-2001 Headworks Fire Detection Panel Alarm Headworks Electrical Room 0 = ALARM 0 5 14 Provide interposing relay to suit
2 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 0 0 Used for direct connection to Rack 1.
DI - 31 YA FDP-2001 Headworks Fire Detection Panel Alarm Headworks Electrical Room 0 = ALARM 0 5 15 Provide interposing relay to suit
3 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 0 0 Used for direct connection to Rack 2.
DI - 32 YA CP-2000 Rack 0 DI Card 6 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 6 0 EXISTING SERVICE
4 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block BUILDING
300 SERIES
DI - 33 YA UPS-290 UPS AC Line Failure Headworks SCADA Room 0 = FAILURE 0 6 1
5 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
DI - 34 YA UPS-290 UPS Battery Low Headworks SCADA Room 0 = LOW 0 6 2
6 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
DI - 35 YA UPS-290 UPS Alarm Headworks SCADA Room 0 = ALARM 0 6 3
7 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block KEY PLAN
DI - 36 YA UPS-290 UPS On Bypass Headworks SCADA Room 0 = BYPASS 0 6 4
8 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
DI - 37 YA SD-2001 Headworks Pipe Gallery Smoke Detector Alarm Pipe Gallery 0 = ALARM 0 6 5 Provide interposing relay to suit
9 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block DI - 38 YA SD-2002 Headworks Pipe Gallery Smoke Detector Alarm Pipe Gallery 0 = ALARM 0 6 6 Provide interposing relay to suit GENERAL NOTES:
10 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block DI - 39 YA SD-2003 Headworks Pipe Gallery Smoke Detector Alarm Pipe Gallery 0 = ALARM 0 6 7 Provide interposing relay to suit
A. AMOUNT AND LOCATION OF INTERPOSING RELAYS,
11 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block DI - 40 YA SD-2004 Headworks Elec. Rm. Smoke Detector Alarm Headworks Electrical Room 0 = ALARM 0 6 8 Provide interposing relay to suit INTRINSICALLY SAFE BARRIERS, SIGNAL SPLITTERS,
12 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block AND ISOLATION MODULES TBD.
DI - 41 YA SD-2005 Headworks Elec. Rm. Smoke Detector Alarm Headworks Electrical Room 0 = ALARM 0 6 9 Provide interposing relay to suit
13 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block DI - 42 YA SD-2006 Headworks Elec. Rm. Smoke Detector Alarm Headworks Electrical Room 0 = ALARM 0 6 10 Provide interposing relay to suit
14 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block DI - 43 YA SD-2007 Headworks Elec. Rm. Smoke Detector Alarm Headworks Electrical Room 0 = ALARM 0 6 11 Provide interposing relay to suit
15 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block DI - 44 YA SD-2008 Headworks Screen/Degrit Smoke Detector Alarm Headworks Screen And Degrit Room 0 = ALARM 0 6 12 Provide interposing relay to suit

16 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block DI - 45 YA SD-2009 Headworks Screen/Degrit Smoke Detector Alarm Headworks Screen And Degrit Room 0 = ALARM 0 6 13 Provide interposing relay to suit

0 1756-A17 AB/RA 17 Slot ControlLogix Chassis Miscellaneous 1 0 DI - 46 YA SD-2010 Headworks Screen/Degrit Smoke Detector Alarm Headworks Screen And Degrit Room 0 = ALARM 0 6 14 Provide interposing relay to suit

0 1756-PB75 AB/RA 24VDC Power Supply (13A @ 5V) Miscellaneous 1 0 DI - 47 YA SD-2011 Headworks Screen Bin Smoke Detector Alarm Headworks Screen And Degrit Room 0 = ALARM 0 6 15 Provide interposing relay to suit

1 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 1 0 Used for direct connection to Rack 0. DI - 48 YA CP-2000 Rack 0 DI Card 7 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 7 0
DI - 49 YA TC-2010 Heat Trace Piping Status Alarm Headworks Screen And Degrit Room 0 = ALARM 0 7 1
2 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
DI - 50 YA TC-2012 Heat Trace Piping Status Alarm Headworks Screen And Degrit Room 0 = ALARM 0 7 2
3 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
DI - 51 YA TC-2013 Heat Trace Piping Status Alarm Headworks Screen And Degrit Room 0 = ALARM 0 7 3
4 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
DI - 52 YA TC-2014 Heat Trace Piping Status Alarm Headworks Screen And Degrit Room 0 = ALARM 0 7 4
5 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
DI - 53 YA TC-2015 Heat Trace Piping Status Alarm Headworks Screen And Degrit Room 0 = ALARM 0 7 5
6 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
DI - 54 YA TC-2016 Heat Trace Piping Status Alarm Headworks Screen And Degrit Room 0 = ALARM 0 7 6
7 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
DI - 55 YA TC-2017 Heat Trace Piping Status Alarm Headworks Screen And Degrit Room 0 = ALARM 0 7 7
8 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block
DI - 56 YA TC-2018 Heat Trace Piping Status Alarm Headworks Screen And Degrit Room 0 = ALARM 0 7 8
9 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block
DI - 57 YA TC-2019 Heat Trace Piping Status Alarm Headworks Screen And Degrit Room 0 = ALARM 0 7 9
10 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block DI - 58 YA TC-2030 Heat Trace Piping Status Alarm Storm Drain 0 = ALARM 0 7 10
11 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block DI - 59 YA TC-4030 Heat Trace Piping Status Alarm Primary Clarifiers - Primary Sludge 0 = ALARM 0 7 11
12 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block DI - 60 0 7 12
13 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block DI - 61 0 7 13
14 1756-N2 AB/RA Slot Filler Miscellaneous 1 0 DI - 62 0 7 14
15 1756-N2 AB/RA Slot Filler Miscellaneous 1 0 DI - 63 0 7 15
16 1756-IF8I AB/RA Slot Filler Miscellaneous 1 0 DI - 64 YA CP-2000 Rack 0 DI Card 8 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 8 0

0 1756-A17 AB/RA 17 Slot ControlLogix Chassis Miscellaneous 2 0 DI - 65 YA LC-401 Prim. Clarifier #1 Long. Collector - Fault Primary Clarifiers #1 0 = FAULT 0 8 1

0 1756-PB75 AB/RA 24VDC Power Supply (13A @ 5V) Miscellaneous 2 0 DI - 66 HS LC-401 Prim. Clarifier #1 Long. Collector - In-Auto Primary Clarifiers #1 1 = IN-AUTO 0 8 2

1 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 2 0 Used for direct connection to Rack 0. DI - 67 YS LC-401 Prim. Clarifier #1 Long. Collector - Running Primary Clarifiers #1 1 = RUNNING 0 8 3
1 PHASE A - ADDENDUM #3 10/11/23
DI - 68 YA LC-401 Prim. Clarifier #1 Long. Collector - Disconnect Open Primary Clarifiers #1 0 = ALARM 0 8 4
2 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block
DI - 69 YA CC-401 Prim. Clarifier #1 Cross Collector - Fault Primary Clarifiers #1 0 = FAULT 0 8 5
3 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block 0 PHASE A ISSUED FOR TENDER 02/10/23
DI - 70 HS CC-401 Prim. Clarifier #1 Cross Collector - In-Auto Primary Clarifiers #1 1 = IN-AUTO 0 8 6
4 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block
DI - 71 YS CC-401 Prim. Clarifier #1 Cross Collector - Running Primary Clarifiers #1 1 = RUNNING 0 8 7 No. ISSUE / REVISION DD/MM/YY
5 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block
DI - 72 YA CC-401 Prim. Clarifier #1 Cross Collector - Disconnect Open Primary Clarifiers #1 0 = ALARM 0 8 8 This drawing is copyright protected and may not be reproduced or
6 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block
DI - 73 YA BL-501 Aeration Blower #1 - Fault Pipe Gallery 0 = FAULT 0 8 9 used for purposes other than execution of the described work without
7 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block the express written consent of J.L. Richards & Associates Limited.
DI - 74 HS BL-501 Aeration Blower #1 - In-Auto Pipe Gallery 1 = IN-AUTO 0 8 10
8 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block VERIFY SHEET SIZE AND SCALES. BAR TO THE
DI - 75 YS BL-501 Aeration Blower #1 - Running Pipe Gallery 1 = RUNNING 0 8 11 RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING.
9 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block 0 25mm
DI - 76 YA BL-501 Aeration Blower #1 - Disconnect Open Pipe Gallery 0 = ALARM 0 8 12 SCALE:
10 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block N.T.S.
DI - 77 YA P-205 Bin Room Sump Pump - Alarm Bin Room 0 = ALARM 0 8 13
11 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 2 8 Provide 1756-TBCH Screw Clamp Block DI - 78 YA P-206 Pipe Gallery Sump Pump - Alarm Pipe Gallery 0 = ALARM 0 8 14
12 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 2 8 Provide 1756-TBCH Screw Clamp Block DI - 79 0 8 15
CLIENT:
13 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 2 8 Provide 1756-TBCH Screw Clamp Block DI - 80 YA CP-2000 Rack 0 DI Card 9 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 9 0
14 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 2 8 Provide 1756-TBCH Screw Clamp Block DI - 81 YA LC-402 Prim. Clarifier #2 Long. Collector - Fault Primary Clarifiers #2 0 = FAULT 0 9 1
15 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 2 8 Provide 1756-TBCH Screw Clamp Block DI - 82 HS LC-402 Prim. Clarifier #2 Long. Collector - In-Auto Primary Clarifiers #2 1 = IN-AUTO 0 9 2
16 1756-N2 AB/RA Slot Filler Miscellaneous 2 0 DI - 83 YS LC-402 Prim. Clarifier #2 Long. Collector - Running Primary Clarifiers #2 1 = RUNNING 0 9 3
DI - 84 YA LC-402 Prim. Clarifier #2 Long. Collector - Disconnect Open Primary Clarifiers #2 0 = ALARM 0 9 4
DI - 85 YA CC-402 Prim. Clarifier #2 Cross Collector - Fault Primary Clarifiers #2 0 = FAULT 0 9 5 CONSULTANT: www.jlrichards.ca
DI - 86 HS CC-402 Prim. Clarifier #2 Cross Collector - In-Auto Primary Clarifiers #2 1 = IN-AUTO 0 9 6
1
DI - 87 YS CC-402 Prim. Clarifier #2 Cross Collector - Running Primary Clarifiers #2 1 = RUNNING 0 9 7
1 COMPONENT LIST - PLC - 200 DI - 88 YA CC-402 Prim. Clarifier #2 Cross Collector - Disconnect Open Primary Clarifiers #2 0 = ALARM 0 9 8
I202A SCALE: NTS
DI - 89 YA BL-502 Aeration Blower #2 - Fault Pipe Gallery 0 = FAULT 0 9 9
DI - 90 HS BL-502 Aeration Blower #2 - In-Auto Pipe Gallery 1 = IN-AUTO 0 9 10
DI - 91 YS BL-502 Aeration Blower #2 - Running Pipe Gallery 1 = RUNNING 0 9 11 CONSULTANT:
XLS
PLC-200 DI - 92 YA BL-502 Aeration Blower #2 - Disconnect Open Pipe Gallery 0 = ALARM 0 9 12
Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-09
13:24:46 8:23:02 PM
COMPONENT I/O LIST DI - 93 AAY AIT-2011 Headworks H2S Analysis - Fault Headworks Screen And Degrit Room 1 = ALARM 0 9 13 Provide interposing relay to suit
CONTROLLER ISA DI - 94 AAY AIT-2011 Headworks H2S Analysis - Alarm Headworks Screen And Degrit Room 1 = ALARM 0 9 14 Provide interposing relay to suit
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 IO List.dwg

IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS
DI - 95 AAY AIT-2011 Headworks H2S Analysis - Warning Headworks Screen And Degrit Room 1 = ALARM 0 9 15 Provide interposing relay to suit
DI - 0 YA CP-2000 Rack 0 DI Card 4 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 0
DI - 96 YA CP-2000 Rack 0 DI Card 10 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 10 0
DI - 1 YA CP-2000 Rack 1 DO Card 8 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 1 PROFESSIONAL STAMP PROJECT NORTH
DI - 97 YA LC-403 Prim. Clarifier #3 Long. Collector - Fault Primary Clarifiers #3 0 = FAULT 0 10 1
DI - 2 YA CP-2000 Rack 1 DO Card 9 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 2
DI - 98 HS LC-403 Prim. Clarifier #3 Long. Collector - In-Auto Primary Clarifiers #3 1 = IN-AUTO 0 10 2
DI - 3 YA CP-2000 Rack 1 DO Card 10 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 3
DI - 99 YS LC-403 Prim. Clarifier #3 Long. Collector - Running Primary Clarifiers #3 1 = RUNNING 0 10 3
DI - 4 YA CP-2000 Rack 1 DO Card 11 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 4
DI - 100 YA LC-403 Prim. Clarifier #3 Long. Collector - Disconnect Open Primary Clarifiers #3 0 = ALARM 0 10 4
DI - 5 0 4 5
DI - 101 YA CC-403 Prim. Clarifier #3 Cross Collector - Fault Primary Clarifiers #3 0 = FAULT 0 10 5
DI - 6 0 4 6
DI - 102 HS CC-403 Prim. Clarifier #3 Cross Collector - In-Auto Primary Clarifiers #3 1 = IN-AUTO 0 10 6
DI - 7 0 4 7
DI - 103 YS CC-403 Prim. Clarifier #3 Cross Collector - Running Primary Clarifiers #3 1 = RUNNING 0 10 7
DI - 8 0 4 8
DI - 104 YA CC-403 Prim. Clarifier #3 Cross Collector - Disconnect Open Primary Clarifiers #3 0 = ALARM 0 10 8
DI - 9 0 4 9
DI - 105 YA BL-503 Aeration Blower #3 - Fault Pipe Gallery 0 = FAULT 0 10 9
PROJECT:
DI - 10 YA CP-2000 Rack 2 AI Card 2 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 10
DI - 106 HS BL-503 Aeration Blower #3 - In-Auto Pipe Gallery 1 = IN-AUTO 0 10 10
DI - 11 YA CP-2000 Rack 2 AI Card 3 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 11 MUNICIPALITY OF NORTH
DI - 107 YS BL-503 Aeration Blower #3 - Running Pipe Gallery 1 = RUNNING 0 10 11
DI - 12 YA CP-2000 Rack 2 AI Card 4 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 12
DI - 108 YA BL-503 Aeration Blower #3 - Disconnect Open Pipe Gallery 0 = ALARM 0 10 12
GRENVILLE - WATER POLLUTION
DI - 13 YA CP-2000 Rack 2 AI Card 5 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 13
DI - 109 AAY AIT-2012 Headworks CH4 Analysis - Fault Headworks Screen And Degrit Room 1 = ALARM 0 10 13 Provide interposing relay to suit CONTROL PLANT EXPANSION
DI - 14 YA CP-2000 Rack 2 AI Card 6 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 14
DI - 110 AAY AIT-2012 Headworks CH4 Analysis - Alarm Headworks Screen And Degrit Room 1 = ALARM 0 10 14 Provide interposing relay to suit PHASE - A
DI - 15 YA CP-2000 Rack 2 AI Card 7 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 4 15 KEMPTVILLE, ONTARIO
DI - 111 AAY AIT-2012 Headworks CH4 Analysis - Warning Headworks Screen And Degrit Room 1 = ALARM 0 10 15 Provide interposing relay to suit
DI - 16 YA CP-2000 Rack 0 DI Card 5 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 5 0
DI - 112 YA CP-2000 Rack 0 DI Card 11 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 11 0 DRAWING:
DI - 17 YA CP-2000 Rack 2 AI Card 8 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 5 1
DI - 113 YA OCU-201 Headworks Odor Control Unit #1 - Fault Headworks Building 0 = FAULT 0 11 1
ELECTRICAL

November 14, 2023 9:54:06 AM


DI - 18 YA CP-2000 Rack 2 AI Card 9 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 5 2
DI - 114 HS OCU-201 Headworks Odor Control Unit #1 - In-Auto Headworks Building 1 = IN-AUTO 0 11 2
DI - 19 YA CP-2000 Rack 2 AI Card 10 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 5 3 HEADWORKS BUILDING
DI - 115 YS OCU-201 Headworks Odor Control Unit #1 - Running Headworks Building 1 = RUNNING 0 11 3
DI - 20 YA CP-2000 Rack 2 AO Card 11 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 5 4
DI - 116 YA OCU-201 Headworks Odor Control Unit #1 - Disconnect Open Headworks Building 0 = ALARM 0 11 4 COMPONENT LISTS & IO TABLES -
DI - 21 YA CP-2000 Rack 2 AO Card 12 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 5 5
DI 22 YA CP-2000 Rack 2 AO Card 13 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 5 6
DI - 117 YA P-401 Prim. Sludge Pump #1 - Fault Pipe Gallery 0 = FAULT 0 11 5 PLC-200
DI - 118 HS P-401 Prim. Sludge Pump #1 - In-Auto Pipe Gallery 1 = IN-AUTO 0 11 6
DI - 23 YA CP-2000 Rack 2 AO Card 14 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 5 7
DI - 119 YS P-401 Prim. Sludge Pump #1 - Running Pipe Gallery 1 = RUNNING 0 11 7 DESIGN:
DI - 24 YA CP-2000 Rack 2 AO Card 15 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 5 8 1 LO
DRAWN: DRAWING #:
NB

PLOT DATE:
2 I/O LIST - PLC - 200 1 3 I/O LIST (CONT'D) - PLC - 200 CHECKED:
I202A SCALE: NTS I202A SCALE: NTS
JLR #:
JO
29475
I202A
XLS XLS
PLC-200 PLC-200
Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-09
13:24:46 8:23:02 PM Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-09
13:24:46 8:23:02 PM
COMPONENT I/O LIST COMPONENT I/O LIST
CONTROLLER ISA CONTROLLER ISA NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS BUILDING 900 SERIES
800 SERIES
DI - 120 YA P-401 Prim. Sludge Pump #1 - Disconnect Open Pipe Gallery 0 = ALARM 0 11 8 NEW AERATION NEW PRIMARY NEW
DI - 215 YA VFC-409 Tank 1 Aeration Grid Control Valve #1 - Fault Aeration Tank #1 0 = FAULT 1 2 7 TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES
DI - 121 0 11 9 DI - 216 ZSO VFC-410 Tank 1 Aeration Grid Control Valve #2 - Open Aeration Tank #1 1 = OPEN 1 2 8
DI - 122 0 11 10 DI - 217 ZSC VFC-410 Tank 1 Aeration Grid Control Valve #2 - Closed Aeration Tank #1 1 = CLOSED 1 2 9
DI - 123 0 11 11 DI - 218 HS VFC-410 Tank 1 Aeration Grid Control Valve #2- In Auto Aeration Tank #1 1 = AUTO 1 2 10 NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)
DI - 124 0 11 12 DI - 219 YA VFC-410 Tank 1 Aeration Grid Control Valve #2 - Fault Aeration Tank #1 0 = FAULT 1 2 11
DI - 125 0 11 13 DI - 220 ZSO VFC-401 Primary Sludge Control Valve #1 - Open Pipe Gallery 1 = OPEN 1 2 12
DI - 126 0 11 14 DI - 221 ZSC VFC-401 Primary Sludge Control Valve #1 - Closed Pipe Gallery 1 = CLOSED 1 2 13
DI - 127 0 11 15 DI - 222 HS VFC-401 Primary Sludge Control Valve #1- In Auto Pipe Gallery 1 = AUTO 1 2 14 EXISTING SERVICE
BUILDING
DI - 128 YA CP-2000 Rack 0 DI Card 12 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 12 0 300 SERIES
DI - 223 YA VFC-401 Primary Sludge Control Valve #1 - Fault Pipe Gallery 0 = FAULT 1 2 15
DI - 129 YA OCU-202 Headworks Odor Control Unit #2 - Fault Headworks Building 0 = FAULT 0 12 1 DI - 224 YA CP-2000 Rack 1 DI Card 3 24 VDC Failure Headworks PLC Panel 0 = FAILURE 1 3 0
DI - 130 HS OCU-202 Headworks Odor Control Unit #2 - In-Auto Headworks Building 1 = IN-AUTO 0 12 2 DI - 225 ZSO VFC-402 Primary Sludge Control Valve #2 - Open Pipe Gallery 1 = OPEN 1 3 1
DI - 131 YS OCU-202 Headworks Odor Control Unit #2 - Running Headworks Building 1 = RUNNING 0 12 3 DI - 226 ZSC VFC-402 Primary Sludge Control Valve #2 - Closed Pipe Gallery 1 = CLOSED 1 3 2 KEY PLAN

DI - 132 YA OCU-202 Headworks Odor Control Unit #2 - Disconnect Open Headworks Building 0 = ALARM 0 12 4 DI - 227 HS VFC-402 Primary Sludge Control Valve #2 - In Auto Pipe Gallery 1 = AUTO 1 3 3
DI - 133 YA P-402 Prim. Sludge Pump #2 - Fault Pipe Gallery 0 = FAULT 0 12 5 DI - 228 YA VFC-402 Primary Sludge Control Valve #2- Fault Pipe Gallery 0 = FAULT 1 3 4 GENERAL NOTES:
DI - 134 HS P-402 Prim. Sludge Pump #2 - In-Auto Pipe Gallery 1 = IN-AUTO 0 12 6 DI - 229 ZSO VFC-411 Tank 2 Aeration Grid Control Valve #1 - Open Aeration Tank #2 1 = OPEN 1 3 5
A. AMOUNT AND LOCATION OF INTERPOSING RELAYS,
DI - 135 YS P-402 Prim. Sludge Pump #2 - Running Pipe Gallery 1 = RUNNING 0 12 7 DI - 230 ZSC VFC-411 Tank 2 Aeration Grid Control Valve #1 - Closed Aeration Tank #2 1 = CLOSED 1 3 6 INTRINSICALLY SAFE BARRIERS, SIGNAL SPLITTERS,
DI - 136 YA P-402 Prim. Sludge Pump #2 - Disconnect Open Pipe Gallery 0 = ALARM 0 12 8 DI - 231 HS VFC-411 Tank 2 Aeration Grid Control Valve #1 - In Auto Aeration Tank #2 1 = AUTO 1 3 7
AND ISOLATION MODULES TBD.

DI - 137 0 12 9 DI - 232 YA VFC-411 Tank 2 Aeration Grid Control Valve #1 - Fault Aeration Tank #2 0 = FAULT 1 3 8
DI - 138 0 12 10 DI - 233 ZSO VFC-412 Tank 2 Aeration Grid Control Valve #2 - Open Aeration Tank #2 1 = OPEN 1 3 9
DI - 139 0 12 11 DI - 234 ZSC VFC-412 Tank 2 Aeration Grid Control Valve #2 - Closed Aeration Tank #2 1 = CLOSED 1 3 10
DI - 140 0 12 12 DI - 235 HS VFC-412 Tank 2 Aeration Grid Control Valve #2 - In Auto Aeration Tank #2 1 = AUTO 1 3 11
DI - 141 0 12 13 DI - 236 YA VFC-412 Tank 2 Aeration Grid Control Valve #2 - Fault Aeration Tank #2 0 = FAULT 1 3 12
DI - 142 0 12 14 DI - 237 1 3 13
DI - 143 0 12 15 DI - 238 1 3 14
DI - 144 YA CP-2000 Rack 0 DI Card 13 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 13 0 DI - 239 1 3 15
DI - 145 HS EF-201 Pipe Gallery Exhaust Fan - In Auto Pipe Gallery 1 = AUTO 0 13 1 DI - 240 YA CP-2000 Rack 1 DI Card 4 24 VDC Failure Headworks PLC Panel 0 = FAILURE 1 4 0
DI - 146 YA EF-201 Pipe Gallery Exhaust Fan - Fault Pipe Gallery 0 = ALARM 0 13 2 DI - 241 ZSO VFC-403 Primary Sludge Control Valve #3 - Open Pipe Gallery 1 = OPEN 1 4 1
DI - 147 YS EF-201 Pipe Gallery Exhaust Fan - Running Pipe Gallery 1 = RUNNING 0 13 3 DI - 242 ZSC VFC-403 Primary Sludge Control Valve #3 - Closed Pipe Gallery 1 = CLOSED 1 4 2
DI - 148 YA EF-201 Pipe Gallery Exhaust Fan - Disconnect Open Pipe Gallery 0 = ALARM 0 13 4 DI - 243 HS VFC-403 Primary Sludge Control Valve #3 - In Auto Pipe Gallery 1 = AUTO 1 4 3
DI - 149 YA P-403 Primary Scum Pump - Fault Primary Clarifiers 0 = FAULT 0 13 5 DI - 244 YA VFC-403 Primary Sludge Control Valve #3- Fault Pipe Gallery 0 = FAULT 1 4 4
DI - 150 HS P-403 Primary Scum Pump - In-Auto Primary Clarifiers 1 = IN-AUTO 0 13 6 DI - 245 ZSO VFC-413 Tank 3 Aeration Grid Control Valve #1 - Open Aeration Tank #3 1 = OPEN 1 4 5
DI - 151 YS P-403 Primary Scum Pump - Running Primary Clarifiers 1 = RUNNING 0 13 7 DI - 246 ZSC VFC-413 Tank 3 Aeration Grid Control Valve #1 - Closed Aeration Tank #3 1 = CLOSED 1 4 6
DI - 152 YA P-403 Primary Scum Pump - Disconnect Open Primary Clarifiers 0 = ALARM 0 13 8 DI - 247 HS VFC-413 Tank 3 Aeration Grid Control Valve #1- In Auto Aeration Tank #3 1 = AUTO 1 4 7
DI - 153 YA P-403 Primary Scum Pump - Low Oil (LSL 4030) Primary Clarifiers 0 = ALARM 0 13 9 DI - 248 YA VFC-413 Tank 3 Aeration Grid Control Valve #1 - Fault Aeration Tank #3 0 = FAULT 1 4 8
DI - 154 AAY AIT-2013 Headworks H2S Analysis - Fault Headworks Screen And Degrit Room 1 = ALARM 0 13 10 Provide interposing relay to suit DI - 249 ZSO VFC-414 Tank 3 Aeration Grid Control Valve #2 - Open Aeration Tank #3 1 = OPEN 1 4 9
DI - 155 AAY AIT-2013 Headworks H2S Analysis - Alarm Headworks Screen And Degrit Room 1 = ALARM 0 13 11 Provide interposing relay to suit DI - 250 ZSC VFC-414 Tank 3 Aeration Grid Control Valve #2 - Closed Aeration Tank #3 1 = CLOSED 1 4 10
DI - 156 AAY AIT-2013 Headworks H2S Analysis - Warning Headworks Screen And Degrit Room 1 = ALARM 0 13 12 Provide interposing relay to suit DI - 251 HS VFC-414 Tank 3 Aeration Grid Control Valve #2- In Auto Aeration Tank #3 1 = AUTO 1 4 11
DI - 157 YA GFS-201 Glycol Fill Station Alarm Pipe Gallery 0 = ALARM 0 13 13 DI - 252 YA VFC-414 Tank 3 Aeration Grid Control Valve #2 - Fault Aeration Tank #3 0 = FAULT 1 4 12
DI - 158 0 13 14 DI - 253 1 4 13
DI - 159 0 13 15 DI - 254 1 4 14
DI - 160 YA CP-2000 Rack 0 DI Card 14 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 14 0 DI - 255 1 4 15
DI - 161 HS SF-201 Pipe Gallery Supply Fan - In Auto Pipe Gallery 1 = AUTO 0 14 1 DI - 256 YA CP-2000 Rack 1 DI Card 5 24 VDC Failure Headworks PLC Panel 0 = FAILURE 1 5 0
DI - 162 YA SF-201 Pipe Gallery Supply Fan - Fault Pipe Gallery 0 = ALARM 0 14 2 DI - 257 YS LCP-4001 Primary Clarifier Tank #1 Scum Heaters - Running Primary Clarifiers 1 = RUNNING 1 5 1
DI - 163 YS SF-201 Pipe Gallery Supply Fan - Running Pipe Gallery 1 = RUNNING 0 14 3 DI - 258 HS LCP-4001 Primary Clarifier Tank #1 Scum Heaters - In-Auto Primary Clarifiers 1 = IN-AUTO 1 5 2 1 PHASE A - ADDENDUM #3 10/11/23

DI - 164 YA SF-201 Pipe Gallery Supply Fan - Disconnect Open Pipe Gallery 0 = ALARM 0 14 4 DI - 259 YA LCP-4001 Primary Clarifier Tank #1 Scum Heaters - Disc. Open Primary Clarifiers 0 = FAULT 1 5 3
0 PHASE A ISSUED FOR TENDER 02/10/23
DI - 165 AAY AIT-2014 Headworks CH4 Analysis - Fault Headworks Screen And Degrit Room 0 14 5 Provide interposing relay to suit DI - 260 1 5 4
DI - 166 AAY AIT-2014 Headworks CH4 Analysis - Alarm Headworks Screen And Degrit Room 0 14 6 Provide interposing relay to suit DI - 261 1 5 5 No. ISSUE / REVISION DD/MM/YY

DI - 167 AAY AIT-2014 Headworks CH4 Analysis - Warning Headworks Screen And Degrit Room 0 14 7 Provide interposing relay to suit DI - 262 1 5 6 This drawing is copyright protected and may not be reproduced or
DI - 168 ZSO VFC-614 Ras 3-Way Valve - Open Pipe Gallery 1 = OPEN 0 14 8 DI - 263 1 5 7 used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.
DI - 169 ZSC VFC-614 Ras 3-Way Valve - Closed Pipe Gallery 1 = CLOSED 0 14 9 DI - 264 1 5 8
DI - 170 HS VFC-614 Ras 3-Way Valve - In Auto Pipe Gallery 1 = AUTO 0 14 10 VERIFY SHEET SIZE AND SCALES. BAR TO THE
DI - 265 1 5 9
RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
DI - 171 YA VFC-614 Ras 3-Way Valve - Fault Pipe Gallery 0 = ALARM 0 14 11 DI - 266 1 5 10
SCALE:
N.T.S.
DI - 172 0 14 12 DI - 267 1 5 11
DI - 173 0 14 13 DI - 268 1 5 12
DI - 174 0 14 14 DI - 269 1 5 13
CLIENT:
DI - 175 0 14 15 DI - 270 1 5 14
DI - 176 YA CP-2000 Rack 0 DI Card 15 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 15 0 DI - 271 1 5 15
DI - 177 HS MAU-201 Headworks Make-up Air Unit - In Auto Headworks Screen And Degrit Room 1 = AUTO 0 15 1 DI - 272 YA CP-2000 Rack 1 DI Card 6 24 VDC Failure Headworks PLC Panel 0 = FAILURE 1 6 0
DI - 178 YA MAU-201 Headworks Make-up Air Unit - Fault Headworks Screen And Degrit Room 0 = ALARM 0 15 2 DI - 273 ZSO VFC-404 Primary Scum 3-Way Valve - Open Primary Clarifiers 1 = OPEN 1 6 1
DI - 179 YS MAU-201 Headworks Make-up Air Unit - Running Headworks Screen And Degrit Room 1 = RUNNING 0 15 3 DI - 274 ZSC VFC-404 Primary Scum 3-Way Valve - Closed Primary Clarifiers 1 = CLOSED 1 6 2
DI - 180 YA MAU-201 Headworks Make-up Air Unit - Disconnect Open Headworks Screen And Degrit Room 0 = ALARM 0 15 4 DI - 275 HS VFC-404 Primary Scum 3-Way Valve - In Auto Pipe Gallery 1 = AUTO 1 6 3 CONSULTANT: www.jlrichards.ca
DI - 181 HS P-207 Headworks Glycol Heating Pump - In Auto Pipe Gallery 1 = AUTO 0 15 5 DI - 276 YA VFC-404 Primary Scum 3-Way Valve- Fault Pipe Gallery 0 = FAULT 1 6 4
DI - 182 YA P-207 Headworks Glycol Heating Pump - Fault Pipe Gallery 0 = ALARM 0 15 6 DI - 277 YS LCP-4004 Primary Clarifier Tank #2 Scum Heaters - Running Primary Clarifiers 1 = RUNNING 1 6 5
DI - 183 YS P-207 Headworks Glycol Heating Pump - Running Pipe Gallery 1 = RUNNING 0 15 7 DI - 278 HS LCP-4004 Primary Clarifier Tank #2 Scum Heaters - In-Auto Primary Clarifiers 1 = IN-AUTO 1 6 6
DI - 184 YA P-207 Headworks Glycol Heating Pump - Disconnect Open Pipe Gallery 0 = ALARM 0 15 8 DI - 279 YA LCP-4004 Primary Clarifier Tank #2 Scum Heaters - Disc. Open Primary Clarifiers 0 = FAULT 1 6 7
DI - 185 YA P-207 Headworks Glycol Heating Pump - E-Stop Pipe Gallery 0 = ALARM 0 15 9 DI - 280 SA MS-4025 Primary Tank #3 Longitudinal Collector Alarm Primary Clarifiers 0 = ALARM 1 6 8
DI - 186 0 15 10 DI - 281 1 6 9 CONSULTANT:

DI - 187 0 15 11 DI - 282 1 6 10
DI - 188 0 15 12 DI - 283 1 6 11
DI - 189 0 15 13 DI - 284 1 6 12
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 IO List.dwg

DI - 190 0 15 14 DI - 285 1 6 13
DI - 191 0 15 15 DI - 286 1 6 14
PROFESSIONAL STAMP PROJECT NORTH
DI - 192 YA CP-2000 Rack 0 DI Card 16 24 VDC Failure Headworks PLC Panel 0 = FAILURE 0 16 0 DI - 287 1 6 15
DI - 193 FAL FSL-2011 Headworks Electrical Room Exhaust Low Flow Headworks Electrical Room 0 = ALARM 0 16 1 DI - 288 YA CP-2000 Rack 1 DI Card 7 24 VDC Failure Headworks PLC Panel 0 = FAILURE 1 7 0
DI - 194 FAL FSL-2012 Headworks Electrical Room Supply Low Flow Headworks Electrical Room 0 = ALARM 0 16 2 DI - 289 YS LCP-4007 Primary Clarifier Tank #3 Scum Heaters - Running Primary Clarifiers 1 = RUNNING 1 7 1
DI - 195 FAL FSL-2013 Headworks MUA Low Flow Rate Alarm Headworks Screen And Degrit Room 0 = ALARM 0 16 3 DI - 290 HS LCP-4007 Primary Clarifier Tank #3 Scum Heaters - In-Auto Primary Clarifiers 1 = IN-AUTO 1 7 2
DI - 196 FAL FSL-2031 Odour Control Unit #1 Low Flow Alarm Septage Receiving 0 = ALARM 0 16 4 DI - 291 YA LCP-4007 Primary Clarifier Tank #3 Scum Heaters - Disc. Open Primary Clarifiers 0 = FAULT 1 7 3
DI - 197 FAL FSL-2032 Odour Control Unit #2 Low Flow Alarm Septage Receiving 0 = ALARM 0 16 5 DI - 292 YA P-208 Effluent Booster Pump - Fault Headworks Screen And Degrit Room 0 = FAULT 1 7 4
DI - 198 PAL PSL-2011 Headworks Hot Water Low Pressure Alarm Pipe Gallery 0 = ALARM 0 16 6 DI - 293 HS P-208 Effluent Booster Pump - In-Auto Headworks Screen And Degrit Room 1 = IN-AUTO 1 7 5
DI - 199 SA MS-4023 Primary Tank #1 Longitudinal Collector Alarm Primary Clarifiers 0 = ALARM 0 16 7 DI - 294 YS P-208 Effluent Booster Pump - Running Headworks Screen And Degrit Room 1 = RUNNING 1 7 6
DI - 200 LAH LS-2013 Mechanical Screen #2 Level Alarm High Headworks Screen And Degrit Room 0 = ALARM 0 16 8 DI - 295 YA P-208 Effluent Booster Pump - Disconnect Open Headworks Screen And Degrit Room 0 = ALARM 1 7 7
PROJECT:
DI - 201 LAHH LS-2013 Mechanical Screen #2 Level Alarm High High Headworks Screen And Degrit Room 0 = ALARM 0 16 9 DI - 296 1 7 8
MUNICIPALITY OF NORTH
DI - 202 0 16 10 DI - 297 1 7 9
DI - 203 0 16 11 DI - 298 1 7 10
GRENVILLE - WATER POLLUTION
DI - 204 0 16 12 DI - 299 1 7 11 CONTROL PLANT EXPANSION
DI - 205 0 16 13 DI - 300 1 7 12 PHASE - A
DI - 206 0 16 14 DI - 301 1 7 13 KEMPTVILLE, ONTARIO
DI - 207 0 16 15 DI - 302 1 7 14 DRAWING:
DI - 208 YA CP-2000 Rack 1 DI Card 2 24 VDC Failure Headworks PLC Panel 0 = FAILURE 1 2 0 DI - 303 1 7 15
ELECTRICAL

November 14, 2023 9:56:40 AM


DI - 209 YS LCP-4012 Prim. Clar. Scum Pit/Pep Pumps LCP - Start Primary Clarifiers 1 = STATUS 1 2 1 DO - 0 ZC LCP-4012 Prim. Clar. Scum Pit/Pep Pumps LCP - Recirculate Primary Clarifiers 1 = RECIRC 1 8 0 Provide interposing relay to suit
HEADWORKS BUILDING
DI - 210 LAHH LSHH-2033 Screen Bin Area Sanitary Drain High High Headworks Screen And Degrit Room 0 = ALARM 1 2 2 DO - 1 ZC LCP-4012 Prim. Clar. Scum Pit/Pep Pumps LCP - Discharge Primary Clarifiers 1 = DISCHRG 1 8 1 Provide interposing relay to suit
DI - 211 LAHH LSHH-2034 Gallery Level Sanitary Drain High High Pipe Gallery 0 = ALARM 1 2 3 DO - 2 YA YA-2200 Headworks Stack Light - Horn Headworks Building 1 = ON 1 8 2 Provide interposing relay to suit
DI - 212 ZSO VFC-409 Tank 1 Aeration Grid Control Valve #1 - Open Aeration Tank #1 1 = OPEN 1 2 4 DO - 3 UAL UAL-2201 Headworks Stack Light - Red Headworks Building 1 = ON 1 8 3 Provide interposing relay to suit
IO TABLES - PLC-200 (CONT'D)
DI - 213 ZSC VFC-409 Tank 1 Aeration Grid Control Valve #1 - Closed Aeration Tank #1 1 = CLOSED 1 2 5 DO - 4 UAL UAL-2202 Headworks Stack Light - Amber Headworks Building 1 = ON 1 8 4 Provide interposing relay to suit
DI - 214 HS VFC-409 Tank 1 Aeration Grid Control Valve #1- In Auto Aeration Tank #1 1 = AUTO 1 2 6 DO - 5 UAL UAL-2203 Headworks Stack Light - Clear Headworks Building 1 = ON 1 8 5 Provide interposing relay to suit
DESIGN:
1 LO
1
DRAWN: DRAWING #:
NB

PLOT DATE:
1 I/O LIST (CONT'D) - PLC - 200 2 I/O LIST (CONT'D) - PLC - 200 CHECKED:
I203A SCALE: NTS I203A SCALE: NTS
JLR #:
JO
29475
I203A
XLS XLS
PLC-200 PLC-200
Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-09
13:24:46 8:23:02 PM Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-09
13:24:46 8:23:02 PM
COMPONENT I/O LIST COMPONENT I/O LIST
CONTROLLER ISA CONTROLLER ISA NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS BUILDING 900 SERIES
800 SERIES
NEW AERATION NEW PRIMARY NEW
DO - 6 UAL UAL-2204 Headworks Stack Light - Blue Headworks Building 1 = ON 1 8 6 Provide interposing relay to suit AI - 35 AI AIT-4011 Aeration Tank #1 Diffuser Grid Analyzer Indicator Aeration Tank #1 2 6 3 TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES
DO - 7 ZC VFC-614 RAS 3-Way Valve - Drive Open Pipe Gallery 1 = OPEN 1 8 7 Provide interposing relay to suit AI - 36 AI AIT-4012 Aeration Tank #2 Diffuser Grid Analyzer Indicator Aeration Tank #2 2 6 4
DO - 8 ZC VFC-614 RAS 3-Way Valve - Drive Closed Pipe Gallery 1 = CLOSED 1 8 8 Provide interposing relay to suit AI - 37 AI AIT-4013 Aeration Tank #3 Diffuser Grid Analyzer Indicator Aeration Tank #3 2 6 5
DO - 9 YC P-207 Headworks Glycol Heating Pump - Run Pipe Gallery 1 = RUN 1 8 9 Provide interposing relay to suit AI - 38 2 6 6 NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)
DO - 10 YC LCP-4001 Primary Clarifier Tank #1 Scum Heaters - Run Primary Clarifiers 1 = RUN 1 8 10 Provide interposing relay to suit AI - 39 2 6 7
DO - 11 1 8 11 Provide interposing relay to suit AI - 40 AI AIT-2011 Headworks H2S Analyzer Indicator Headworks Screen And Degrit Room 2 7 0
DO - 12 1 8 12 Provide interposing relay to suit AI - 41 AI AIT-2012 Headworks CH4 Analyzer Indicator Headworks Screen And Degrit Room 2 7 1
DO - 13 1 8 13 Provide interposing relay to suit AI 42 AI AIT-2013 Headworks H2S Analyzer Indicator Headworks Screen And Degrit Room 2 7 2 EXISTING SERVICE
BUILDING
300 SERIES
DO - 14 1 8 14 Provide interposing relay to suit AI - 43 AI AIT-2014 Headworks CH4 Analyzer Indicator Headworks Screen And Degrit Room 2 7 3
DO - 15 1 8 15 Provide interposing relay to suit AI - 44 AI AIT-2015 Headworks Pipe Gallery H2S Gas Monitor Pipe Gallery 2 7 4
DO - 16 YC LC-401 Prim. Clarifier #1 Long. Collector - Run Primary Clarifier #1 1 = RUN 1 9 0 Provide interposing relay to suit AI - 45 AI AIT-2016 Headworks Pipe Gallery CH4 Gas Monitor Pipe Gallery 2 7 5
DO - 17 YC CC-401 Prim. Clarifier #1 Cross Collector - Run Primary Clarifier #1 1 = RUN 1 9 1 Provide interposing relay to suit AI - 46 2 7 6 KEY PLAN

DO - 18 YC BL-501 Aeration Blower #1 - Run Pipe Gallery 1 = RUN 1 9 2 Provide interposing relay to suit AI - 47 2 7 7 GENERAL NOTES:
DO - 19 YC EF-201 Pipe Gallery Exhaust Fan - Run Pipe Gallery 1 = RUN 1 9 3 Provide interposing relay to suit AI - 48 FI FIT-2017 Primary Clarifier #1 Inlet Flow Indicator Pipe Gallery 2 8 0
A. AMOUNT AND LOCATION OF INTERPOSING RELAYS,
DO - 20 YC OCU-201 Odor Control Unit #1 - Run Septage Receiving 1 = RUN 1 9 4 Provide interposing relay to suit AI - 49 FI FIT-2018 Primary Clarifier #2 Inlet Flow Indicator Pipe Gallery 2 8 1
INTRINSICALLY SAFE BARRIERS, SIGNAL SPLITTERS,
DO - 21 YC P-401 Primary Sludge Pump #1 - Run Pipe Gallery 1 = RUN 1 9 5 Provide interposing relay to suit AI 50 FI FIT-2019 Primary Clarifier #3 Inlet Flow Indicator Pipe Gallery 2 8 2 AND ISOLATION MODULES TBD.
DO - 22 ZC VFC-401 Primary Sludge Control Valve #1 - Drive Open Pipe Gallery 1 = OPEN 1 9 6 Provide interposing relay to suit AI - 51 FI FIT-4010 Primary Sludge Flow Indicator Pipe Gallery 2 8 3
B. REFER TO DETAIL 1/I022A FOR THE REQUIRED
DO - 23 ZC VFC-401 Primary Sludge Control Valve #1 - Drive Closed Pipe Gallery 1 = CLOSED 1 9 7 Provide interposing relay to suit AI - 52 2 8 4 HARDWIRED LOGIC FOR CONTROLLING THE
ASSOCIATED STACK LIGHTS AND HORNS.
DO - 24 ZC VFC-404 Primary Scum 3-Way Valve - Drive Open Primary Clarifiers 1 = OPEN 1 9 8 Provide interposing relay to suit AI - 53 2 8 5
DO - 25 ZC VFC-404 Primary Scum 3-Way Valve - Drive Closed Primary Clarifiers 1 = CLOSED 1 9 9 Provide interposing relay to suit AI - 54 2 8 6
DRAWING NOTES:
DO - 26 YC LCP-4004 Primary Clarifier Tank #2 Scum Heaters - Run Primary Clarifiers 1 = RUN 1 9 10 Provide interposing relay to suit AI - 55 2 8 7
DO - 27 1 9 11 Provide interposing relay to suit AI - 56 LI LIT-4015 Primary Scum Pump Level Indicator Primary Clarifiers 2 9 0 Provide analog signal duplicator 1 PROGRAM THE PLC TO PROVIDE A WATCHDOG
PULSE. THIS PULSE IS TO BE MONITORED BY THE
DO - 28 1 9 12 Provide interposing relay to suit AI - 57 2 9 1
WATCHDOG TIMING RELAY INSIDE THE PANEL.
DO - 29 1 9 13 Provide interposing relay to suit AI 58 2 9 2 COORDINATE PULSE WIDTH AND RELAY SELECTION
TO SUIT. THE INTENT OF THIS FEATURE IS TO
DO - 30 1 9 14 Provide interposing relay to suit AI - 59 2 9 3
DETECT PLC FAILURE. PROVIDE HARD-WIRED LOGIC
DO - 31 1 9 15 Provide interposing relay to suit AI - 60 2 9 4 INSIDE THE PLC PANEL TO ENERGIZE ALL STACK
LIGHTS AND ASSOCIATED HORNS CONNECTED TO
DO - 32 YC LC-402 Prim. Clarifier #2 Long. Collector - Run Primary Clarifier #2 1 = RUN 1 10 0 Provide interposing relay to suit AI - 61 2 9 5
THIS PLC IN EVENT OF A PLC FAILURE. PROVIDE
DO - 33 YC CC-402 Prim. Clarifier #2 Cross Collector - Run Primary Clarifier #2 1 = RUN 1 10 1 Provide interposing relay to suit AI - 62 2 9 6 LOGIC TO SILENCE THE HORNS VIA A FLUSH HEAD
PUSHBUTTON ON THE PLC PANEL DOOR. LABEL THE
DO - 34 YC BL-502 Aeration Blower #2 - Run Pipe Gallery 1 = RUN 1 10 2 Provide interposing relay to suit AI - 63 2 9 7
PUSHBUTTON "SILENCE HORNS". PUSHBUTTON
DO - 35 YC SF-201 Pipe Gallery Supply Fan - Run Pipe Gallery 1 = RUN 1 10 3 Provide interposing relay to suit AI - 64 2 10 0 COLOUR TO BE BLUE. HORNS TO BE RE-TRIGGERED
EACH TIME THE PLC FAILS.
DO - 36 YC OCU-202 Odor Control Unit #2 - Run Septage Receiving 1 = RUN 1 10 4 Provide interposing relay to suit AI - 65 2 10 1
DO - 37 ZC VFC-402 Primary Sludge Control Valve #2 - Drive Open Pipe Gallery 1 = OPEN 1 10 5 Provide interposing relay to suit AI - 66 2 10 2
DO - 38 ZC VFC-402 Primary Sludge Control Valve #2 - Drive Closed Pipe Gallery 1 = CLOSED 1 10 6 Provide interposing relay to suit AI - 67 2 10 3
DO - 39 YC LCP-4007 Primary Clarifier Tank #3 Scum Heaters - Run Primary Clarifiers 1 = RUN 1 10 7 Provide interposing relay to suit AI - 68 2 10 4
DO - 40 1 10 8 Provide interposing relay to suit AI - 69 2 10 5
DO - 41 1 10 9 Provide interposing relay to suit AI - 70 2 10 6
DO - 42 1 10 10 Provide interposing relay to suit AI - 71 2 10 7
DO - 43 1 10 11 Provide interposing relay to suit AO - 0 SC BL-501 Aeration Blower #1 Speed Control Pipe Gallery 2 11 0
DO - 44 1 10 12 Provide interposing relay to suit AO - 1 SC P-401 Primary Sludge Pump #1 Speed Control Pipe Gallery 2 11 1
DO - 45 1 10 13 Provide interposing relay to suit AO - 2 SC OCU-201 Odor Control Unit #1 Speed Control Septage Receiving 2 11 2
DO - 46 1 10 14 Provide interposing relay to suit AO - 3 ZC VFC-409 Tank #1 Aeration Grid Control Valve #1 Position Control Aeration Tank #1 2 11 3
DO - 47 1 10 15 Provide interposing relay to suit AO - 4 ZC VFC-411 Tank #2 Aeration Grid Control Valve #1 Position Control Aeration Tank #2 2 11 4
DO - 48 YC LC-403 Prim. Clarifier #3 Long. Collector - Run Primary Clarifier #3 1 = RUN 1 11 0 Provide interposing relay to suit AO - 5 2 11 5
DO - 49 YC CC-403 Prim. Clarifier #3 Cross Collector - Run Primary Clarifier #3 1 = RUN 1 11 1 Provide interposing relay to suit AO - 6 2 11 6 1 PHASE A - ADDENDUM #3 10/11/23

DO - 50 YC BL-503 Aeration Blower #3 - Run Pipe Gallery 1 = RUN 1 11 2 Provide interposing relay to suit AO - 7 ZC VFC-413 Tank #3 Aeration Grid Control Valve #1 Position Control Aeration Tank #3 2 12 7
0 PHASE A ISSUED FOR TENDER 02/10/23
DO - 51 YC MAU-201 Headworks Make-Up Air Unit - Run Headworks Screen And Degrit Room 1 = RUN 1 11 3 Provide interposing relay to suit AO - 8 SC BL-502 Aeration Blower #2 Speed Control Pipe Gallery 2 12 0
DO - 52 YC P-403 Primary Scum Pump - Run Primary Clarifiers 1 = RUN 1 11 4 Provide interposing relay to suit AO - 9 SC P-402 Primary Sludge Pump #2 Speed Control Pipe Gallery 2 12 1 No. ISSUE / REVISION DD/MM/YY

DO - 53 ZC VFC-403 Primary Sludge Control Valve #3 - Drive Open Pipe Gallery 1 = OPEN 1 11 5 Provide interposing relay to suit AO - 10 SC OCU-202 Odor Control Unit #2 Speed Control Septage Receiving 2 12 2 This drawing is copyright protected and may not be reproduced or
DO - 54 ZC VFC-403 Primary Sludge Control Valve #3 - Drive Closed Pipe Gallery 1 = CLOSED 1 11 6 Provide interposing relay to suit AO - 11 ZC VFC-410 Tank #1 Aeration Grid Control Valve #2 Position Control Aeration Tank #1 2 12 3 used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.
DO - 55 YC P-208 Effluent Booster Pump - Run Headworks Screen And Degrit Room 1 = RUN 1 11 7 Provide interposing relay to suit AO - 12 ZC VFC-412 Tank #2 Aeration Grid Control Valve #2 Position Control Aeration Tank #2 2 12 4
VERIFY SHEET SIZE AND SCALES. BAR TO THE
DO - 56 1 11 8 Provide interposing relay to suit AO - 13 ZC VFC-414 Tank #3 Aeration Grid Control Valve #2 Position Control Aeration Tank #3 2 12 5
RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
DO - 57 1 11 9 Provide interposing relay to suit AO - 14 2 12 6
SCALE:
NTS
DO - 58 1 11 10 Provide interposing relay to suit AO - 15 2 12 7
DO - 59 1 11 11 Provide interposing relay to suit AO - 16 SC BL-503 Aeration Blower #3 Speed Control Pipe Gallery 2 13 0
DO - 60 1 11 12 Provide interposing relay to suit AO - 17 SC SF-201 Pipe Gallery Supply Fan Speed Selection Pipe Gallery 2 13 1
CLIENT:
DO - 61 1 11 13 Provide interposing relay to suit AO - 18 2 13 2
DO - 62 1 11 14 Provide interposing relay to suit AO - 19 2 13 3
1 DO - 63 YS CP-2000 PLC Watchdog Pulse 1 13 15 Provide interposing relay to suit AO - 20 2 13 4
AO - 21 2 13 5
AO - 22 2 13 6
AI - 0 SI BL-501 Aeration Blower #1 Speed Indicator Pipe Gallery 2 2 0 Provide analog signal duplicator AO - 23 2 13 7 CONSULTANT: www.jlrichards.ca
AI - 1 SI OCU-201 Odor Control Unit #1 Speed Indicator Septage Receiving 2 2 1 Provide analog signal duplicator AO - 24 SC MAU-201 Headworks Make-Up Air Unit Speed Control Headworks Screen And Degrit Room 2 14 0
AI - 2 SI P-401 Primary Sludge Pump #1 Speed Indicator Pipe Gallery 2 2 2 Provide analog signal duplicator AO - 25 ZC VFC-214 Hydronic Control Valve Position Control Pipe Gallery 2 14 1
AI - 3 SI EF-201 Pipe Gallery Exhaust Fan Speed Indicator Pipe Gallery 2 2 3 Provide analog signal duplicator AO - 26 2 14 2
AI - 4 ZI VFC-214 Hydronic Control Valve Position Status Pipe Gallery 2 2 4 AO - 27 2 14 3
AI - 5 2 2 5 AO - 28 2 14 4
AI - 6 2 2 6 AO - 29 2 14 5 CONSULTANT:

AI - 7 2 2 7 AO - 30 2 14 6
AI - 8 SI BL-502 Aeration Blower #2 Speed Indicator Pipe Gallery 2 3 0 Provide analog signal duplicator AO - 31 2 14 7
AI - 9 SI OCU-202 Odor Control Unit #2 Speed Indicator Septage Receiving 2 3 1 Provide analog signal duplicator AO - 32 SC EF-201 Pipe Gallery Exhaust Fan Speed Selection Pipe Gallery 2 15 0
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 IO List.dwg

AI 10 SI P-402 Primary Sludge Pump #2 Speed Indicator Pipe Gallery 2 3 2 Provide analog signal duplicator AO - 33 ZC VFC-223 Glycol Heating Control Valve Position Control Pipe Gallery 2 15 1
AI - 11 SI SF-201 Pipe Gallery Supply Speed Indicator Pipe Gallery 2 3 3 Provide analog signal duplicator AO - 34 ZC VFC-224 MAU Glycol Heating Control Valve Position Control Headworks Screen And Degrit Room 2 15 2
PROFESSIONAL STAMP PROJECT NORTH
AI - 12 ZI VFC-223 Glycol Heating Control Valve Position Status Pipe Gallery 2 3 4 AO - 35 2 15 3
AI - 13 ZI VFC-224 MAU Glycol Heating Control Valve Position Status Headworks Screen And Degrit Room 2 3 5 AO - 36 2 15 4
AI - 14 2 3 6 AO - 37 2 15 5
AI - 15 2 3 7 AO - 38 2 15 6
AI - 16 SI BL-503 Aeration Blower #3 Speed Indicator Pipe Gallery 2 4 0 Provide analog signal duplicator AO - 39 2 15 7
AI - 17 SI MAU-201 Headworks Make-Up Air Unit Speed Indicator Headworks Screen And Degrit Room 2 4 1 Provide analog signal duplicator
AI - 18 TI TIT-2011 Headworks Hot Water Temperature Indicator Pipe Gallery 2 4 2
AI - 19 TI TT-2012 Pipe Gallery Supply Air Temperature Indicator Pipe Gallery 2 4 3
AI - 20 TI TT-2013 Headworks MUA Temperature Indicator Headworks Screen And Degrit Room 2 4 4
PROJECT:
AI - 21 TI TIT-2014 Headworks Electrical Room Temperature Indicator Headworks Electrical Room 2 4 5
1 MUNICIPALITY OF NORTH
AI 22 PI PIT-5010 New Process Air Blowers Pressure Indicator Pipe Gallery 2 4 6
AI - 23 2 4 7
GRENVILLE - WATER POLLUTION
AI - 24 ZI VFC-409 Tank #1 Aeration Grid Control Valve #1 Position Status Aeration Tank #1 2 5 0 CONTROL PLANT EXPANSION
AI - 25 ZI VFC-411 Tank #2 Aeration Grid Control Valve #1 Position Status Aeration Tank #2 2 5 1 PHASE - A
AI - 26 ZI VFC-413 Tank #3 Aeration Grid Control Valve #1 Position Status Aeration Tank #3 2 5 2 KEMPTVILLE, ONTARIO
AI - 27 LI LIT-2010 Sewage Receiving Channel Level Indicator Headworks Screen And Degrit Room 2 5 3 Provide analog signal duplicator DRAWING:
AI - 28 2 5 4
ELECTRICAL

November 14, 2023 9:55:32 AM


AI - 29 2 5 5
HEADWORKS BUILDING
AI - 30 2 5 6
AI - 31 2 5 7
AI - 32 ZI VFC-410 Tank #1 Aeration Grid Control Valve #2 Position Status Aeration Tank #1 2 6 0
IO TABLES - PLC-200 (CONT'D)
AI - 33 ZI VFC-412 Tank #2 Aeration Grid Control Valve #2 Position Status Aeration Tank #2 2 6 1
AI - 34 ZI VFC-414 Tank #3 Aeration Grid Control Valve #2 Position Status Aeration Tank #3 2 6 2
DESIGN:
LO
1 DRAWN: DRAWING #:
NB

PLOT DATE:
1 I/O LIST (CONT'D) - PLC - 200 2 I/O LIST (CONT'D) - PLC - 200 CHECKED:
I204A SCALE: NTS I204A SCALE: NTS
JLR #:
JO
29475
I204A
FED FROM SB-002A
TO CP-300
SEE DWG E011A FOR
DETAILS
TO CP-300
GLOBAL-1000
N.I.C. PHASE B
NEW DEWATERING AND ELECTRICAL SERVICE
GLOBAL-1000
DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
800 SERIES
MCC-300 GLOBAL-1000
MCC-310 GLOBAL-1000
NEW AERATION
TANKS
NEW PRIMARY NEW
CLARIFIERS HEADWORKS
400AT 400AT 500 SERIES 400 SERIES 200 SERIES
400AT
3P
400A, 600V, 3ɸ, 3W, 35 KAIC 3P 3P 400A, 600V, 3ɸ, 3W, 35 KAIC
LSI MCS
NEW TERTIARY

Cat 6
NEW SECONDARY
CLARIFIERS FILTER BUILDING

Cat 6
600 SERIES (PHASE B) 700 SERIES (PHASE B)

20AT 100AT
3P 3P 50A 15A 15A 100A 15A 15A 15A 15A 15A 15A 15A 15A 25A 25A
3P 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P 3P

TYPE 14

TYPE 70

TYPE 70

TYPE 70

TYPE 13

TYPE 13

TYPE 14

TYPE 14

TYPE 14

TYPE 14

TYPE 14

TYPE 14

TYPE 70

TYPE 70
OWNER'S
POWER METER EXISTING SERVICE
BUILDING
300 SERIES

3% RF 3% RF 3% RF 3% RF 3% RF KEY PLAN
M 1

DRAWING NOTES:
SPD-300 1 COORDINATE EXACT BREAKER SIZE WITH SPD
GLOBAL-1000
PM-300 GLOBAL-1000
VFD-IGBT VFD-IGBT VFD-IGBT VFD-IGBT VFD-IGBT
MANUFACTURER
Cat 6

Cat 6
PROVIDE GROUND AS PER SPD MANUFACTURER'S
REQUIREMENTS. REFER TO SPECIFICATIONS FOR
ADDITIONAL DETAIL.

2 MCC SUPPLIER TO PROVIDE DISCONNECTING MEANS

Cat 6

Cat 6

Cat 6
5% 5% 5% 5% 5% FOR POWER MONITOR INSIDE POWER MONITOR
CELL.

Cat 6 Cat 6 Cat 6 Cat 6 Cat 6 Cat 6 Cat 6 Cat 6

LD-P-906 0001-LABOLG
LD-EF-302 0001-LABOLG
LD-EF-303 0001-LABOLG
LD-P-715 0001-LABOLG
LD-P-728 0001-LABOLG
LD-P-729 0001-LABOLG
LD-LC-608 0001-LABOLG
LD-LC-610 0001-LABOLG
LD-CC-609 0001-LABOLG
LD-CC-611 0001-LABOLG
LD-MIX-704 0001-LABOLG
LD-MIX-705 0001-LABOLG
LD-P-612 0001-LABOLG
LD-P-6130001-LABOLG

APFC
600V
3c #4 AWG RW90 + GND IN EMT

3c #10 AWG ARMOURED BELDEN

3c #10 AWG ARMOURED BELDEN


VFD CABLE IN 35mm RGS CONDUIT

VFD CABLE IN 35mm RGS CONDUIT

VFD CABLE IN 53mm RGS CONDUIT


3c #8 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR


50 kVAR

3c #12 AWG BELDEN 2950X SERIES

3c #12 AWG BELDEN 2950X SERIES

3c #4 AWG BELDEN 2950X SERIES


IN 10 kVAR 20 1.5 1.5 40 2.7 2.7 0.5 0.5 0.5 0.5 2 1 10 10

GLOBAL-1000
STEPS HEATING PUMP ROOM EXHAUST FAN

WASHWATER SUMP PUMP No. 3

WASHWATER SUMP PUMP No. 4

FLOC TANK #3 MIXER


PRIMARY HEATING DISTRIBUTION PUMP No.2

SECONDARY CLARIFIER No. 3 LONGITUDINAL COLLECTOR

SECONDARY CLARIFIER No. 4 LONGITUDINAL COLLECTOR


P-906

P-715

P-728

P-729

MIX-705

P-613
EF-302

BOILER ROOM EXHAUST FAN


EF-303

SECONDARY CLARIFIER No. 4 CROSS COLLECTOR

MIX-704

P-612
EFFLUENT PUMP No. 6

LC-608

LC-610

SECONDARY CLARIFIER No. 3 CROSS COLLECTOR

FLASH TANK #2 MIXER

RAS PUMP No. 4

RAS PUMP No. 5


CC-609

CC-611
PFP-300
ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES


INTEGRAL CABLE

INTEGRAL CABLE

VFD CABLE

VFD CABLE
2 PHASE A - ADDENDUM #3 10/11/23

1 PHASE A - ADDENDUM #2 03/11/23

1 0 PHASE A ISSUED FOR TENDER 02/10/23

No. ISSUE / REVISION DD/MM/YY

This drawing is copyright protected and may not be reproduced or


used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.

VERIFY SHEET SIZE AND SCALES. BAR TO THE


RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
SCALE:
N.T.S.

MCC-300 2
400A, 600V, 3ɸ, 3W, 35 KAIC
GLOBAL-1000

SCHEDULE OF SPDs
CLIENT:
TYPE MANUFACTURER PART #

SPD-300 TOTAL PROTECTION TK-ST160-600NN-FLB


SOLUTIONS CANADA
15A 15A 40A 50A 15A 25A 15A 250A
3P
3P 3P 3P 3P 3P 3P 3P DP-301
TYPE 14

TYPE 14

TYPE 14

TYPE 14

TYPE 14

TYPE 14

TYPE 14

SPD-302 TOTAL PROTECTION TK-ST080-3Y208-FLB


GLOBAL-1000
SOLUTIONS CANADA
3c #6 AWG TECK90 AL ARMOUR ANIXTER 7TK SERIES CONSULTANT: www.jlrichards.ca
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 EXISTING SERVICE BLDG SINGLE LINE.dwg

SPD-390 TOTAL PROTECTION TK-ST080-3Y208-FLB


N.I.C. PHASE B SOLUTIONS CANADA

3c #4 AWG TECK90 AL ARMOUR ANIXTER 7TK SERIES SPD-701 TOTAL PROTECTION TK-ST080-3Y208-FLB
SOLUTIONS CANADA

H2 TX-305 GENERAL NOTES:


3c 250MCM RW90 + GND IN EMT

0001-LABOLG

LD-TX-701 0001-LABOLG
H3 H1 600V CONSULTANT:
A. PROVIDE GROUND AS PER SPD MANUFACTURER's REQUIREMENTS. REFER TO
45kVA SPECIFICATIONS FOR ADDITIONAL DETAIL.
3c #6 AWG RW90 + GND
IN EMT 3c #4 AWG TECK90 AL ARMOUR B. ALL INDICATED CABLES SHOWN AS "ARMOURED BELDEN VFD CABLE" TO BE
X2 X1 120/208V
ANIXTER 7TK SERIES ALUMINUM ARMOURED BELDEN VFD CABLE 12295XX SERIES.
X0
H2 TX-302 0001-LABOLG
H2 TX-701 0001-LABOLG
X3 C. REFER TO MOTOR STARTER AND CONTROL LIST IN THE ME SERIES DRAWINGS FOR
ADDITIONAL DETAILS.
H3 H1 600V H3 H1 600V 4c #2/0 AWG RW90 PROFESSIONAL STAMP PROJECT NORTH
+ GND IN EMT D. PROVIDE AN ETHERNET POWER MONITOR FOR MCC BEING SUPPLIED.
45kVA 45kVA
Cat 6 Cat 6 Cat 6 Cat 6 4c #3 AWG RW90 4c #3 AWG RW90
E. THE POWER MONITOR WILL BE FED FROM AN EXTERNAL 120VAC UPS POWER
X2 X1 120/208V X2 X1 120/208V SOURCE. REFER TO CONTROL PANEL DRAWINGS FOR DETAILS. PROVIDE ALL
+ GND IN EMT + GND IN EMT
X0 X0 APPURTENANCES REQUIRED TO FACILITATE THIS.
LD-P-901
0001-LABOLG
LD-P-902 0001-LABOLG
LD-P-903 0001-LABOLG
LD-P-905 0001-LABOLG
LD-P-907 0001-LABOLG
LD-P-908 0001-LABOLG
LD-P-909 0001-LABOLG X3 X3
F. MOTOR STARTERS TO BE HARDWIRED TO PLC I/O. STARTERS TO ALSO BE
CONNECTED VIA ETHERNET.

LP-305 G. MCC BREAKER SIZES SHOWN FOR QUOTATION PURPOSES ONLY. FINAL BREAKER
4c #2/0 AWG RW90 + GND IN EMT

0001-LABOLG SIZES TO BE DETERMINED BY MCC MANUFACTURER, SUBJECT TO THE APPROVAL


OF THE ENGINEER.
4c #2/0 AWG TECK90 AL ARMOUR

PROJECT:

UPS-390 H. REFER TO DRAWING N001A FOR CAT6 NETWORK DETAILS. MUNICIPALITY OF NORTH
0001-LABOLG
ATS-390
20kVA
208V
100A, 3Ø-4W
0001-LABOLG
I. MCC ETHERNET SWITCH POWER SUPPLIES TO BE FED FROM AN EXTERNAL 120VAC GRENVILLE - WATER POLLUTION
UPS POWER SOURCE. MCC MANUFACTURER TO MAKE THE NECESSARY
ANIXTER 7TK SERIES
3c #8 AWG TECK90 AL ARMOUR
3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #10 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

3c #12 AWG TECK90 AL ARMOUR

1 1 15 20 5 10 1 3ɸ, 4W ARRANGEMENTS TO DISTRIBUTE THIS POWER INSIDE THE MCC. REFER TO THE CONTROL PLANT EXPANSION
BYPASS PANEL BOARD SCHEDULES.
PHASE - A
BOILER FEED PUMP No.1
P-901

BOILER FEED PUMP No.2


P-902

BOILER FEED PUMP No.3


P-903

PRIMARY HEATING DISTRIBUTION PUMP No.1


P-905

SERVICE BUILDING HEATING PUMP


P-907

HEADWORKS HEATING PUMP


P-908

P-909
DIGESTER HEX HOT WATER RECIRC PUMP

J. LOCATION OF MCC ETHERNET SWITCHES NOT SHOWN. MCC MANUFACTURER TO KEMPTVILLE, ONTARIO
NOTE 'A'
ANIXTER 7TK SERIES

IDENTIFY THIS LOCATION.


ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

ANIXTER 7TK SERIES

DRAWING:
NOTE 'A'

LP-302

November 14, 2023 11:11:25 AM


NORMAL K. REFER TO SECTION 16801 FOR MCC REQUIREMENTS. REFER TO SECTION 16812
0001-LABOLG
FOR VFD REQUIREMENTS. ELECTRICAL
LP-701 LOAD
0001-LABOLG
4c #3 AWG
L. REFER TO DWG E020A - E023A (INCLUSIVE) FOR MOTOR STARTER SCHEMATICS.
SERVICE BUILDING
RW90 + GND EMERGENCY
SPD-302 IN EMT SINGLE LINE DIAGRAM AND PANEL
NOTE 'A'

GLOBAL-1000
M. REFER TO DWG E007A FOR UPS POWER DISTRIBUTION DETAIL.
SPD-701 SCHEDULE
UP-390
GLOBAL-1000
N. CONTRACTOR TO COORDINATE SHIPPING SPLITS TO ENSURE MCC CAN BE MOVED
0001-LABOLG
ATS TO ITS FINAL LOCATION INSIDE THE ELECTRICAL ROOM.
700 SERIES
DESIGN:
TERTIARY FILTER BUILDING O. MCC SUPPLIER TO PROVIDE DRY FORM C CONTACTS INSIDE THE MCC FOR MM/LO
1 SINGLE LINE DIAGRAM SPD-390 MONITORING OF THE 24VDC P/S. REFER TO SECTION 16801. DRAWN:
MM DRAWING #:

PLOT DATE:
GLOBAL-1000

SCALE: N.T.S. P. WHERE CONDUIT IS NOTED WITHOUT TRADE SIZE, CONTRACTOR TO PROVIDE SIZE CHECKED:
E301A
IN COMPLIANCE WITH ONTARIO ELECTRICAL SAFETY CODE REQUIREMENTS,
JLR #:
JO
29475
E301A
DP-301 UP-390 NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
900 SERIES
600 VOLT, 3Ø-3W BUILDING
120/208 VOLT, 3Ø-4W 800 SERIES
NEW AERATION NEW PRIMARY NEW
SURFACE MOUNTED TANKS CLARIFIERS HEADWORKS
35kAIC 50A MAIN BREAKER 500 SERIES 400 SERIES 200 SERIES

250 AMP MAIN BREAKER SURFACE MOUNTED


ELECTRICAL ROOM
NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)
LOAD DESCRIPTION BRKR CCT CCT BRKR DESCRIPTION LOAD LOAD DESCRIPTION BRKR CCT CCT BRKR DESCRIPTION LOAD
1 2 MCC-300 15A,1P 1 2 15A,1P CP-3000
TX-302 (LP-302) 60A, 3P 3 4 60A, 3P TX-701 (LP-701) 5 3 TRAVELING BRIDGE #3 15A,1P 3 4 15A,1P CP-7000 3
5 6 FCP-9010 15A,1P 5 6 15A,1P CP-1000
7 8 FCP-9020 15A,1P 7 8 20A,1P SCADA RECEPTACLE
TRAVELLING BRIDGE #3 1 EXISTING SERVICE
5 20A, 3P 9 10 25A, 3P BOILER #1 BLR-901 2 FCP-9030 15A,1P 9 10 20A,1P SCADA RECEPTACLE BUILDING
(MCP-7025) 300 SERIES
11 12 TCP-100 15A,1P 11 12 15A,1P AUTO-DIALER 4
13 14 SECURITY STATION RECEPTACLE 20A,1P 13 14 15A,1P SCADA RECEPTACLE
1 2 BOILER #2 BLR-902 25A, 3P 15 16 25A, 3P BOILER #3 BLR-903 2 SECURITY STATION RECEPTACLE 20A,1P 15 16 15A,1P SPARE
17 18 17 18 15A,1P SPARE
IT-3000 30A,2P
19 20 19 20
TX-305 (UPS-390) 60A, 3P 21 22 20A, 3P RH-601, RH-602, RH-603 SPARE 15A,1P 21 22 XXA,3P SPD-390 1 KEY PLAN
23 24 SPARE 15A,1P 23 24
25 26
SPARE 20A, 3P 27
29
28
30
20A, 3P RH-604, RH-605, RH-606 TOTAL CONNECTED LOAD: _________ GENERAL NOTES:
31 32 PHASE LOAD TO BE FILLED IN BY CONTRACTOR:
SPARE 20A, 3P 33 34 20A, 3P SPARE LOAD PHASE A: _________ LOAD PHASE B: _________ LOAD PHASE C: _________ A. PROVIDE GROUND AS PER SPD MANUFACTURER'S
35 36 REQUIREMENTS. REFER TO SPECIFICATIONS FOR
37 38 REMARKS ADDITIONAL DETAIL.
SPARE 20A, 3P 39 40 20A, 3P SPARE 1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED.
41 42 2. DEDICATED NEUTRAL
3. * GFI
TOTAL CONNECTED LOAD: _________ 4. LOCKED
DRAWING NOTES:
PHASE LOAD TO BE FILLED IN BY CONTRACTOR:
LOAD PHASE A: LOAD PHASE B: LOAD PHASE C:
4 UP-390 PANEL SCHEDULE
1 COORDINATE EXACT BREAKER SIZE WITH SPD
REMARKS SCALE: N.T.S. MANUFACTURER.
E302A
1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED. NOTE: PROVIDE PADLOCKABLE CLASPS
2. DEDICATED NEUTRAL FOR ALL BREAKERS PROVIDED.
3. GFI 2 COORDINATE FINAL BREAKER REQUIREMENTS WITH
* EQUIPMENT MANUFACTURER PRIOR TO ORDERING
4. LOCKED
5. ARC FAULT CIRCUIT INTERRUPTER BREAKER.

3 PROVIDE TECK90 CABLING TO THE TERTIARY FILTER


BUILDING. FOLLOW THE PATH OF THE OTHER TECK90
CABLES BETWEEN THE SERVICE BUILDING AND THE
1 DP-301 PANEL SCHEDULE TERTIARY FILTER BUILDING.
E302A SCALE: N.T.S.
4 PROVIDE A NEW UPS CIRCUIT TO THE EXISTING ALARM
AUTO-DIALER. PROVIDE RW90 WIRING IN EMT. ROUTE
CONDUIT IN CEILING SPACE. PAINT EXPOSED CONDUIT
TO MATCH WALL COLOUR.
N.I.C. PHASE B
5 PROVIDE BREAKER FOR FUTURE EQUIPMENT.
LP-302 LP-701
120/208 VOLT, 3Ø-4W 120/208 VOLT, 3Ø-4W
SURFACE MOUNTED SURFACE MOUNTED
ELECTRICAL ROOM ELECTRICAL ROOM
225A MAINS 100 AMP MAIN BREAKER
10 kAIC 10 kAIC

LOAD DESCRIPTION BRKR CCT CCT BRKR DESCRIPTION LOAD LOAD DESCRIPTION BRKR CCT CCT BRKR DESCRIPTION LOAD
SF-301 ELEC. RM. SUPPLY FAN 15A,1P 1 2 15A,1P EF-304 DRIP TRAP RM. EXHAUST FAN LTG. TERTIARY FIILTER BUILDING 20A,1P 1 2 15A,1P LTG. EXTERIOR
UH-330, VFC-301 15A,1P 3 4 15A,1P UH-331, VFC-302 CP-7000 15A,1P 3 4 20A,1P RCPT. SERVICE *
UH-332, VFC-303 15A,1P 5 6 15A,1P UH-333, VFC-304 * RCPT. EXTERIOR 20A,1P 5 6 20A,1P RCPT. SERVICE *
UH-334, VFC-305 15A,1P 7 8 15A,1P UH-335, VFC-306 TRAVELLING BRIDGE #3 (CP-7025) 20A,1P 7 8 15A,1P LC-608 / LC-610 HEATERS
CP-3000 15A,1P 9 10 15A,1P UH-336, VFC-307 CC-609 HEATER 15A,1P 9 10 15A,1P CC-611 HEATER
LIGHTING - BLOWER ROOM 15A,1P 11 12 15A,1P LIGHTING - BOILER ROOM SF-701, MD-701 20A,1P 11 12 15A,1P UH-711, VFC-701 1 PHASE A - ADDENDUM #3 10/11/23
LIGHTING - ELECTRICAL RM. 15A,1P 13 14 20A,1P RECP - BLOWER ROOM EF-702, MD-702 20A,1P 13 14 15A,1P UH 713, VFC-703
* RECP. - ELECTRICAL RM. 20A,1P 15 16 20A,1P RECP - BOILER ROOM CLARIFIER TANK LIGHTING 15A,1P 15 16 15A,1P UH-715, VFC-705
SCADA TELEVISION RECP 15A,1P 17 18 15A,1P UH-337, VFC-308 FILTER BLDG EXT LIGHTING 15A,1P 17 18 15A,1P SPARE 0 PHASE A ISSUED FOR TENDER 02/10/23
SPARE 15A,1P 19 20 15A,1P SPARE UH-712, VFC-702 15A,1P 19 20 15A,1P HEAT TRACE - TERT. STRM DRN (TC-7011) *
SPARE 15A,1P 21 22 15A,1P SPARE UH-714, VFC-704 15A,1P 21 22 15A,1P HEAT TRACE - TERT. FLR. DRN. (TC-7012) * No. ISSUE / REVISION DD/MM/YY
SPARE 15A,1P 23 24 15A,1P SPARE * RCPT. EXTERIOR 20A,1P 23 24 15A,1P SPARE
SPARE 15A,1P 25 26 15A,1P SPARE SPARE 15A,1P 25 26 15A,1P SPARE
SPARE 15A,1P 27 28 15A,1P SPARE SPARE 15A,1P 27 28 15A,1P SPARE This drawing is copyright protected and may not be reproduced or
SPARE 15A,1P 29 30 15A,1P SPARE SPARE 15A,1P 29 30 15A,1P SPARE used for purposes other than execution of the described work without
SPARE 15A,1P 31 32 SPARE 15A,1P 31 32 15A,1P SPARE the express written consent of J.L. Richards & Associates Limited.
33 34 20A,3P EUH-301 ELECTRIC UNIT HEATER SPARE 15A,1P 33 34 15A,1P SPARE
COOL. CND-301 (AC-301) 40A,2P VERIFY SHEET SIZE AND SCALES. BAR TO THE
35 36 SPARE 15A,1P 35 36 15A,1P SPARE
37 38 20A,1P SPARE SPARE 15A,1P 37 38 RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
1 SPD-302 XXA,3P 39 40 20A,1P SPARE SPARE 15A,1P 39 40 XXA,3P SPD-701
SCALE:
41 42 20A,1P SPARE SPARE 15A,1P 41 42 N.T.S.

TOTAL CONNECTED LOAD: _________ TOTAL CONNECTED LOAD: _________

PHASE LOAD TO BE FILLED IN BY CONTRACTOR: PHASE LOAD TO BE FILLED IN BY CONTRACTOR:


LOAD PHASE A: _________ LOAD PHASE B: _________ LOAD PHASE C: _________ LOAD PHASE A: _________ LOAD PHASE B: _________ LOAD PHASE C: _________ CLIENT:

REMARKS REMARKS
1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED. 1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED.
2. DEDICATED NEUTRAL 2. DEDICATED NEUTRAL
3. * GFI 3. * GFI
4. LOCKED 4. LOCKED

2 LP-302 PANEL SCHEDULE 5 LP-701 PANEL SCHEDULE CONSULTANT: www.jlrichards.ca


File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 EXISTING SERVICE BLDG SINGLE LINE.dwg

E302A SCALE: N.T.S. E302A SCALE: N.T.S.

LP-305 CONSULTANT:

120/208 VOLT, 3Ø-4W


225A MAINS
SURFACE MOUNTED
ELECTRICAL ROOM

LOAD DESCRIPTION BRKR CCT CCT BRKR DESCRIPTION LOAD PROFESSIONAL STAMP PROJECT NORTH
1 2
UPS-390 100A,3P 3 4 100A,3P UPS-390 BYPASS
5 6
7 8 15A,1P SPARE
IT-3000 30A,2P
9 10 15A,1P SPARE
SPARE 15A,1P 11 12 15A,1P SPARE
SPARE 15A,1P 13 14 15A,1P SPARE
SPARE 15A,1P 15 16 15A,1P SPARE
SPARE 15A,1P 17 18 15A,1P SPARE
SPARE 15A,1P 19 20 15A,1P SPARE
SPARE 15A,1P 21 22 15A,1P SPARE
SPARE 15A,1P 23 24 15A,1P SPARE

TOTAL CONNECTED LOAD: _________ PROJECT:

PHASE LOAD TO BE FILLED IN BY CONTRACTOR: MUNICIPALITY OF NORTH


LOAD PHASE A: _________ LOAD PHASE B: _________ LOAD PHASE C: _________
GRENVILLE - WATER POLLUTION
REMARKS
1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED. CONTROL PLANT EXPANSION
2. DEDICATED NEUTRAL
3. * GFI PHASE - A
4. LOCKED KEMPTVILLE, ONTARIO
DRAWING:
3 LP-305 PANEL SCHEDULE
ELECTRICAL

November 14, 2023 9:51:22 AM


E302A SCALE: N.T.S.
SERVICE BUILDING

PANEL SCHEDULES

DESIGN:
IDM
DRAWN: DRAWING #:
IDM

PLOT DATE:
CHECKED:

JLR #:
JO
29475
E302A
600 - SECONDARY CLARIFIERS 300 - SERVICE BUILDING ELECTRICAL AND I C ROOM
LD-RH-601 4 14 A G R 90 6
0001-LABOLG
40 14 A G NE DE ATERING AND ELECTRICAL SERVICE
GND IN OCAL COND TEC 90 CABLE UPS-390 DIGESTER CONTROL ENTRANCE BUILDING
0001-LABOLG
BUILDING 900 SERIES
8 18A G PORTABLE
LCP-6001 HCP-6001 800 SERIES
NE AERATION NE PRIMARY NE
0001-LABOLG 0001-LABOLG
CONTROL CABLE IN EMT TAN S CLARIFIERS HEAD OR S
500 SERIES 400 SERIES 200 SERIES
15 14A G TEC 90 CABLE
ATS-390
0001-LABOLG

C 6 C 6 C 6 C 6 C 6 C 6 C 6 C 6 C 6 C 6 C 6 C 6 C 6 C 6
NE SECONDARY NE TERTIARY
4 16A G PORTABLE CLARIFIERS FILTER BUILDING
2 RUNS CATEGORY 6 IN EMT 600 SERIES PHASE B 700 SERIES PHASE B
CONTROL CABLE IN EMT
SPD-300
0001-LABOLG MCC-300
REFER TO
CP-3000 IT-3000
4 16A G PORTABLE GLOBAL-1000
DRA ING N001A GLOBAL-1000

CONTROL CABLE IN EMT FOR CABLE E ISTING SERVICE


BUILDING
LD-RH-604 SPD-302 DETAILS 300 SERIES
0001-LABOLG 4 14 A G R 90 40 14 A G
0001-LABOLG

GND IN OCAL COND TEC 90 CABLE PLC


4 16A G PORTABLE FBR FBR FBR FBR FBR IT CABINET
LCP-6004 HCP-6004 CONTROL PANEL
0001-LABOLG 0001-LABOLG
CONTROL CABLE IN EMT
SPD-390 EY PLAN
0001-LABOLG

N I C PHASE B
UPS-300
GENERAL NOTES
0001-LABOLG

2 40 14 4 14 A G R 90
ECIVED TEC 90 CABLE GND IN EMT
1 SD
3011 8 18A G PORTABLE A REFER TO PID AS ELL AS MID DRA INGS
4 14 A G R 90 CONTROL CABLE IN EMT 4 5
ECIVED

SD GND IN EMT B REFER TO N001A FOR NET OR DETAILS


FBR FBR FBR FBR FBR FBR
3012
2P 16 A G 7 24 STRAND C REFER TO THE ASSOCIATED MID S AND PID S
RTD
ECIVED
UNARMOURED IN EMT FOR COMMUNICATION REFERENCE BET EEN
TIT
3010 VARIOUS E UIPMENT AND THE PLC PANEL

FBR
FBR
D REFER TO DRA ING E000A FOR ADDITIONAL
CABLE RE UIREMENTS

1
300 - SERVICE BUILDING BOILER ROOM 900 - ELECTRICAL SERVICE ENTRANCE BUILDING

FBR
REFER TO

FBR
DRA ING
BOILER 1 FIELD N001A FOR GLOBAL-1000
CP-9000 GEN-ANUN
GLOBAL-1000
GEN-REPO
GLOBAL-1000

BOILER 1 E-STOP PANEL CONTROL PANEL 50 14 A G


CABLE
TEC 90 CABLE
8 14 A G DETAILS GENERATOR GENERATOR
TEC 90 CABLE PLC
FBR ANNUNCIATOR REPO
8P 16 A G 7 24 2P 16 A G 7 24 CONTROL PANEL
LCP-9011 FCP-9010 STRAND AL ARMOURED STRAND AL ARMOURED RTD ECIVED
PANEL PANEL
GLOBAL-1000 GLOBAL-1000
TIT
3014

FBR
4 14 A G TEC 90 CABLE ECIVED

BOILER 2 FIELD FSL


BOILER 2 E-STOP PANEL 50 14 A G 3015
CONTROL PANEL
TEC 90 CABLE
8 14 A G
TEC 90 CABLE REFER TO

6
8P 16 A G 7 24 DRA ING 3 4 14 A G R U90 GND
LCP-9021 FCP-9020

C
ECIVED

GLOBAL-1000 GLOBAL-1000 STRAND AL ARMOURED HEATING PUMP ROOM E HAUST N001A FOR SD
FAN CONTROL PANEL 0001

FBR
CABLE
20 14 A G TEC 90 CABLE 4 14 A G R 90
DETAILS
GND IN EMT ECIVED

BOILER 3 FIELD 4P 16 A G 7 24 SD
BOILER 3 E-STOP PANEL 50 14 A G 9011

6
CONTROL PANEL STRAND AL ARMOURED LCP-3900
TEC 90 CABLE GLOBAL-1000

4 14 A G TEC 90 LD-EF-302 2

C
8 14 A G 4 14 A G R 90 GND DEVICE

CABLE
GLOBAL-1000
TC
TEC 90 CABLE 2 TRIADS 16 A G 7 24 9010
8P 16 A G 7 24
LCP-9031 FCP-9030 STRAND AL ARMOURED STRAND AL ARMOURED 2
GLOBAL-1000 GLOBAL-1000
4 14 A G R 90 GND

FBR
DEVICE

TC

6
9011 1 PHASE A - ADDENDUM 3 10 11 23
BOILER ROOM E HAUST FAN

C
4 14 A G 2P 16 A G 7 24 STRAND
CONTROL PANEL RTD
TEC 90 CABLE 20 14 TEC 90 A G CABLE UNARMOURED IN EMT ECIVED

0 PHASE A ISSUED FOR TENDER 02 10 23


TIT
9010
BOILER FEED PUMP 4P 16 A G 7 24 2P 16 A G 7 24
2 N ISSUE REVISION DD MM YY
LD-P-901 CONTROL PANEL STRAND AL ARMOURED LCP-3901 STRAND UNARMOURED RTD

6
ECIVED
GLOBAL-1000 GLOBAL-1000

4 14 A G TEC 90 LD-EF-303 TIT


4 14 A G 50 14 A G 9030 T

C
CABLE
GLOBAL-1000

FBR
TEC 90 CABLE TEC 90 CABLE
2 TRIADS 16 A G 7 24
LCP-9001 STRAND AL ARMOURED L R A L
GLOBAL-1000

LD-P-902
GLOBAL-1000
VERIFY SHEET SI E AND SCALES BAR TO THE

6
RIGHT IS 25 IF THIS IS A FULL SI E DRA ING 0 25
4 14 A G ATS-002

C
TEC 90 CABLE 20 14 A G R 90 GND IN EMT
0001-LABOLG

SCALE
NTS

LD-P-903 PRIMARY HEATING PUMP

FBR
GLOBAL-1000

CONTROL PANEL 40 14 A G ATS-001

GND
TEC 90 CABLE 20 14 A G R 90 GND IN EMT
0001-LABOLG

4 14 A G CLIENT

C
TEC 90 CABLE
4P 16 A G 7 24

14 A G R U90
LCP-9040 STRAND AL ARMOURED

GND
SPD-002A
GLOBAL-1000

GND
LD-P-905
GLOBAL-1000
4 16 A G PORTABLE CONTROL
0001-LABOLG

6
4 14 A G 4 TRIADS 16 A G 7 24 CABLE IN EMT

14 A G R U90
C
STRAND AL ARMOURED

14 A G R U90
TEC 90 CABLE

FBR
SPD-002B
4 16 A G PORTABLE CONTROL 0001-LABOLG

CONSULTANT
LD-P-906 CABLE IN EMT

20
GLOBAL-1000

4 16 A G PORTABLE CONTROL

6
CABLE IN EMT

C
SPD-901 0001-LABOLG

300 - SERVICE BUILDING BASEMENT

25

20
4 16 A G PORTABLE CONTROL

FBR
2P 16 A G 7 24
EFFLUENT PUMP 6 RTD CABLE IN EMT
20 14 A G STRAND AL ARMOURED ECIVED

TIT

6
CONTROL PANEL SPD-990
TEC 90 CABLE 3013 0001-LABOLG
CONSULTANT

C
4 14 A G N I C PHASE B
TEC 90 CABLE 3
4P 16 A G 7 24
LCP-7012 STRAND AL ARMOURED
GLOBAL-1000
4P 16 A G 7 24 INTEGRAL CABLE IN
MAG

GND
LD-P-715 STRAND AL ARMOURED DEVICE
MAG OCAL COND
ELEMENT

GLOBAL-1000
FIT FE
2 TRIADS 16 A G 7 24 7002 7002

FBR
D

GND
DRA ING NOTES STRAND AL ARMOURED 4P 16 A G 7 24 GEN-001

14 A G R U90
INTEGRAL CABLE IN GLOBAL-1000

MAG MAG 3
STRAND AL ARMOURED ECIVED ELEMENT

OCAL COND
FIT FE PROFESSIONAL STAMP PRO ECT NORTH
29475 300 C

14 A G R U90
1 DAISY CHAIN TO NE T STAC LIGHT USING SAME CABLE AS RETURN ACTIVATED 6011 6011
SLUDGE PUMP 4 5 4P 16 A G 7 24 INTEGRAL CABLE IN
FIRST ONE IN THE CHAIN 40 14 A G MAG MAG
LOCAL CONTROL PANEL STRAND AL ARMOURED ECIVED ELEMENT

OCAL COND
TEC 90 CABLE FIT FE
4 14 A G 6010 6010 3
2 PROVIDE OCAL OUTDOORS AND EMT INDOORS
TEC 90 CABLE 4P 16 A G 7 24 INTEGRAL CABLE IN
4P 16 A G 7 24 MAG

FBR
MAG OCAL COND GENERATOR

20
LCP-6014 STRAND AL ARMOURED DEVICE ELEMENT

3 VIA DUCTBAN PROVIDE EMT INDOORS STRAND AL ARMOURED FIT FE


ENCLOSURE
6-E

GLOBAL-1000

LD-P-612 7017 7017

20
GLOBAL-1000
7
4 CONTRACTOR TO PROVIDE A MINIMUM OF 212 - 14 A G 4 14 A G 4 TRIADS 16 A G 7 24
2P 16 A G 7 24
IRING VIA TEC 90 CABLING TO THE TEC 90 CABLE STRAND AL ARMOURED RTD 7
STRAND AL ARMOURED ECIVED

PLC PANEL VIA THE MCC E ACT CONDUCTOR COUNT PER TIT
3-P

9020
CABLE AND ASSOCIATED NUMBER OF CABLES TO BE LD-P-613 2P 16 A G 7 24
GLOBAL-1000

RTD PRO ECT


COORDINATED ITH THE PROPOSED MCC LAYOUT AND SITE STRAND AL ARMOURED

FBR
ECIVED

CONDITIONS REFER TO DRA ING E000A FOR CABLE N I C PHASE B TIT


9021 MUNICIPALITY OF NORTH
D

DETAILS 4 14 A G
TEC 90 CABLE
2P 16 A G 7 24
STRAND AL ARMOURED ECIVED
RTD GRENVILLE - ATER POLLUTION
TIT
5 CONTRACTOR TO PROVIDE A MINIMUM OF 8 PAIRS OF 16 9022 700 - TERTIARY FILTER 3 4 BUILDING CONTROL PLANT E PANSION
A G 7 24 STRAND IRING VIA TEC 90 CABLING TO THE PLC HOT ATER PUMP LOCAL 2P 16 A G 7 24
PCP E

PANEL VIA THE MCC E ACT PAIR COUNT PER CABLE AND
LD-P-907 0001-LABOLG
CONTROL PANEL STRAND AL ARMOURED
TIT
ECIVED
RTD ECIVED HORN ECIVED HORN N I C PHASE B PHASE - A
4 14 A G YA YA EMPTVILLE ONTARIO
ASSOCIATED NUMBER OF CABLES TO BE COORDINATED 40 14 A G 9023 3200 3205

FBR
TEC 90 CABLE TEC 90 CABLE
ITH THE PROPOSED MCC LAYOUT AND SITE CONDITIONS ECIVED
RED ECIVED
RED
10 14 A G TEC 90 CABLE UAL UAL DRA ING
LCP-9002
GLOBAL

REFER TO DRA ING E000A FOR CABLE DETAILS 0001-LABOLG


M 3201 3206
ELECTRICAL

14 2023 9 53 00 AM
LD-P-908 VFC-901
1000
ECIVED AMBER ECIVED AMBER GLOBAL-1000
CP-7000
0001-LABOLG

UAL UAL
6 OPEN ENDED CONDUIT AT UPS
1 4 14 A G GLOBAL

M
10 14 A G TEC 90 CABLE 3202 3207 SERVICE BUILDING
P 29000 29475-000 -

TEC 90 CABLE VFC-902 CLEAR CLEAR REMOTE I O PLC


ECIVED ECIVED

FOR PRICING PURPOSES CONTRACTOR TO ALLO FOR THE


1000
UAL UAL FBR
7 2 TRIADS 16 A G 7 24 3203 3208 CONTROL PANEL
10 14 A G TEC 90 CABLE
IRING INDICATED CONTRACTOR TO COORDINATE E ACT ELEMENT
H2S DEVICE
H2S STRAND AL ARMOURED
GLOBAL

M ECIVED BLUE ECIVED BLUE CONTROL BLOC DIAGRAM


IRING RE UIREMENTS ITH THE GENERATOR AE AIT VFC-903 UAL UAL
LD-P-909 3300 3300
1000

3204 3209
MANUFACTURER REFER TO E911A FOR ROUTING PROVIDE 0001-LABOLG

6 14 A G TEC 90 CABLE GLOBAL 10 14 A G TEC 90 CABLE


M 1
RGS CONDUIT PLUS NEMA 4 PAINTED STEEL PULL BO ES
2 TRIADS 16 A G 7 24 VFC-904 DESIGN
LO IDM
SI ED TO SUIT INSIDE GENERATOR ENCLOSURE AND 1000

N
CH4 CH4 STRAND AL ARMOURED 10 14 A G TEC 90 CABLE
ELECTRICAL SERVICE BUILDING TO COMPLETE ROUTING ELEMENT

AE
DEVICE

AIT REFER TO DRA ING I700B DRA N


IDM DRA ING

PLOT DATE
PROVIDE DIRECT BURIED 103 PVC CONDUIT OUTDOORS 3301 3301
6 14 A G TEC 90 CABLE CHEC ED
O
I300A
L

LR
29475
F
XLS XLS
PLC-300 PLC-300
Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-13
13:24:46 9:03:51 AM Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-13
13:24:46 9:03:51 AM
COMPONENT I/O LIST COMPONENT I/O LIST
CONTROLLER ISA CONTROLLER ISA NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS BUILDING 900 SERIES
800 SERIES
DI - 0 YA CP-3000 Rack 0 DI Card 4 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 0 DI - 95
0 YA CP-3000 Rack 0 DI Card 4 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 94 15
0 NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES
DI - 1 YA CP-3000 Rack 1 DO Card 7 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 1 DI - 96 YA CP-3000 Rack 0 DI Card 10 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 10 0
DI - 2 YA CP-3000 Rack 1 DO Card 8 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 2 DI - 97 AAY AIT-3300 Drip Trap Room H2S Analyzer - Fault Service Building Boiler Room 1 = ALARM 0 10 1 Provide interposing relay to suit
DI - 3 YA CP-3000 Rack 1 DO Card 9 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 3 DI - 98 AAY AIT-3300 Drip Trap Room H2S Analyzer - Alarm Service Building Boiler Room 1 = ALARM 0 10 2 Provide interposing relay to suit NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
700 SERIES (PHASE B)
DI - 4 YA CP-3000 Rack 1 DO Card 10 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 4 DI - 99 AAY AIT-3300 Drip Trap Room H2S Analyzer - Warning Service Building Boiler Room 1 = ALARM 0 10 3 Provide interposing relay to suit 600 SERIES (PHASE B)

DI - 5 YA CP-3000 Rack 1 DO Card 11 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 5 DI - 100 HS EF-302 Heating Pump Room Exhaust Fan - Auto Service Building Mechanical Room 1 = AUTO 0 10 4
DI - 6 YA CP-3000 Rack 1 AI Card 12 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 6 DI - 101 YA EF-302 Heating Pump Room Exhaust Fan - Fault Service Building Mechanical Room 0 = FAULT 0 10 5
DI - 7 YA CP-3000 Rack 1 AI Card 13 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 7 DI - 102 YS EF-302 Heating Pump Room Exhaust Fan - Running Service Building Mechanical Room 1 = RUNNING 0 10 6 EXISTING SERVICE
BUILDING
DI - 8 YA CP-3000 Rack 1 AI Card 14 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 8 DI - 103 YA EF-302 Heating Pump Room Exhaust Fan - Disc. Open Service Building Mechanical Room 0 = FAULT 0 10 7 300 SERIES

DI - 9 YA CP-3000 Rack 1 AI Card 15 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 9 DI - 104 YA P-908 Headworks Heating Pump - Fault Service Building Mechanical Room 0 = FAULT 0 10 8
DI - 10 YA CP-3000 Rack 1 AI Card 16 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 10 DI - 105 HS P-908 Headworks Heating Pump - Auto Service Building Mechanical Room 1 = AUTO 0 10 9
DI - 11 YA CP-3000 Rack 2 AI Card 2 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 11 DI - 106 YS P-908 Headworks Heating Pump - Running Service Building Mechanical Room 1 = RUNNING 0 10 10 KEY PLAN

DI - 12 YA CP-3000 Rack 2 AO Card 3 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 12 DI - 107 YA P-908 Headworks Heating Pump - Disc. Open Service Building Mechanical Room 0 = FAULT 0 10 11
DI - 13 YA CP-3000 Rack 2 AO Card 4 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 13 DI - 108 YA MIX-704 Flash Tank #2 Mixer - Fault Tertiary Filter 0 = FAULT 0 10 12 GENERAL NOTES:
DI - 14 YA CP-3000 Rack 2 AO Card 5 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 14 DI - 109 HS MIX-704 Flash Tank #2 Mixer - In-Auto Tertiary Filter 1 = IN-AUTO 0 10 13
1 A. AMOUNT AND LOCATION OF INTERPOSING RELAYS,
DI - 15 0 4 15 DI - 110 YS MIX-704 Flash Tank #2 Mixer - Running Tertiary Filter 1 = RUNNING 0 10 14 INTRINSICALLY SAFE BARRIERS, SIGNAL SPLITTERS,
DI - 16 YA CP-3000 Rack 0 DI Card 5 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 5 0 DI - 111 YA MIX-704 Flash Tank #2 Mixer - Disconnect Open Tertiary Filter 0 = ALARM 0 10 15 AND ISOLATION MODULES TBD.

DI - 17 YA ATS-390 ATS-390 Out Of Service Service Building Electrical Room 1 = SERVICE 0 5 1 DI - 112 YA CP-3000 Rack 0 DI Card 11 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 11 0
DI - 18 YA ATS-390 ATS-390 Fault Service Building Electrical Room 0 = FAULT 0 5 2 DI - 113 AAY AIT-3301 Drip Trap Room CH4 Analyzer - Fault Service Building Boiler Room 1 = ALARM 0 11 1 Provide interposing relay to suit
DRAWING NOTES:
DI - 19 YA ATS-390 ATS-390 Remote Service Building Electrical Room 1 = REMOTE 0 5 3 DI - 114 AAY AIT-3301 Drip Trap Room CH4 Analyzer - Alarm Service Building Boiler Room 1 = ALARM 0 11 2 Provide interposing relay to suit 1 N.I.C. - PHASE B
DI - 20 YA ATS-390 ATS-390 On Normal Power Service Building Electrical Room 1 = NORMAL 0 5 4 DI - 115 AAY AIT-3301 Drip Trap Room CH4 Analyzer - Warning Service Building Boiler Room 1 = ALARM 0 11 3 Provide interposing relay to suit
1
DI - 21 YA ATS-390 ATS-390 Normal Power Available Service Building Electrical Room 1 = AVAIL. 0 5 5 DI - 116 HS EF-303 Boiler Room Exhaust Fan - Auto Service Building Boiler Room 1 = AUTO 0 11 4
DI 22 YA UPS-390 UPS AC Line Failure Service Building Electrical Room 0 = FAILURE 0 5 6 DI - 117 YA EF-303 Boiler Room Exhaust Fan - Fault Service Building Boiler Room 0 = FAULT 0 11 5
DI - 23 YA UPS-390 UPS Battery Low Service Building Electrical Room 0 = LOW 0 5 7 DI - 118 YS EF-303 Boiler Room Exhaust Fan - Running Service Building Boiler Room 1 = RUNNING 0 11 6
DI - 24 YA UPS-390 UPS Alarm Service Building Electrical Room 0 = ALARM 0 5 8 DI - 119 YA EF-303 Boiler Room Exhaust Fan - Disc. Open Service Building Boiler Room 0 = FAULT 0 11 7
DI - 25 YA UPS-390 UPS On Bypass Service Building Electrical Room 0 = BYPASS 0 5 9 DI - 120 YA P-909 Exist. Digester Hot Water Recirc. Pump - Fault Service Building Mechanical Room 0 = FAULT 0 11 8
DI - 26 YA UPS-300 UPS AC Line Failure Service Building Electrical Room 0 = FAILURE 0 5 10 DI - 121 HS P-909 Exist. Digester Hot Water Recirc. Pump - Auto Service Building Mechanical Room 1 = AUTO 0 11 9
DI - 27 YA UPS-300 UPS Battery Low Service Building Electrical Room 0 = LOW 0 5 11 DI - 122 YS P-909 Exist. Digester Hot Water Recirc. Pump - Running Service Building Mechanical Room 1 = RUNNING 0 11 10
DI - 28 YA UPS-300 UPS Alarm Service Building Electrical Room 0 = ALARM 0 5 12 DI - 123 YA P-909 Exist. Digester Hot Water Recirc. Pump - Disc. Open Service Building Mechanical Room 0 = FAULT 0 11 11
DI - 29 YA UPS-300 UPS On Bypass Service Building Electrical Room 0 = BYPASS 0 5 13 DI - 124 YA MIX-705 Floc Tank #3 Mixer - Fault Tertiary Filter 0 = FAULT 0 11 12
DI - 30 TAH SD-3011 Service Building Electrical Room Smoke Detector Service Building Electrical Room 0 = ALARM 0 5 14 DI - 125 HS MIX-705 Floc Tank #3 Mixer - In-Auto Tertiary Filter 1 = IN-AUTO 0 11 13
1
DI - 31 TAH SD-3012 Service Building Electrical Room Smoke Detector Service Building Electrical Room 0 = ALARM 0 5 15 DI - 126 YS MIX-705 Floc Tank #3 Mixer - Running Tertiary Filter 1 = RUNNING 0 11 14
DI - 32 YA CP-3000 Rack 0 DI Card 6 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 6 0 DI - 127 YA MIX-705 Floc Tank #3 Mixer - Disconnect Open Tertiary Filter 0 = ALARM 0 11 15
DI - 33 YA SPD-300 SPD-300 (MCC-300) Alarm Service Building Electrical Room 0 = ALARM 0 6 1 DI - 128 YA CP-3000 Rack 0 DI Card 12 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 12 0
DI - 34 YA SPD-302 SPD-302 (LP-302) Alarm Service Building Electrical Room 0 = ALARM 0 6 2 DI - 129 YA P-728 Washwater Sump Pump #3 - Fault Tertiary Filter 0 = FAULT 0 12 1
DI - 35 YA SPD-390 SPD-390 (UP-390) Alarm Service Building Electrical Room 0 = ALARM 0 6 3 DI - 130 HS P-728 Washwater Sump Pump #3 - In-Auto Tertiary Filter 1 = IN-AUTO 0 12 2
DI - 36 FAL FSL-3015 Drip Trap Room Exhaust Flow Rate Switch Service Building Boiler Room 0 = FAULT 0 6 4 DI - 131 YS P-728 Washwater Sump Pump #3 - Running Tertiary Filter 1 = RUNNING 0 12 3 1
DI - 37 ZSO VFC-901 Hot Water Supply to Ex. Digester Control Valve - Open Service Building Mechanical Room 1 = OPEN 0 6 5 DI - 132 YA P-728 Washwater Sump Pump #3 - Disconnect Open Tertiary Filter 0 = ALARM 0 12 4
DI - 38 ZSC VFC-901 Hot Water Supply to Ex. Digester Control Valve - Closed Service Building Mechanical Room 1 = CLOSED 0 6 6 DI - 133 YA P-728 Washwater Sump Pump #3 - MiniCAS Tertiary Filter 0 = ALARM 0 12 5
DI - 39 YA VFC-901 Hot Water Supply to Ex. Digester Control Valve - Fault Service Building Mechanical Room 0 = FAULT 0 6 7 DI - 134 YS LCP-6001 Secondary Clarifier Tank #3 Scum Heaters - Running Final Clarifiers 1 = RUNNING 0 12 6
DI - 40 HS VFC-901 Hot Water Supply to Ex. Digester Control Valve - In Auto Service Building Mechanical Room 1 = AUTO 0 6 8 DI - 135 HS LCP-6001 Secondary Clarifier Tank #3 Scum Heaters - In-Auto Final Clarifiers 1 = IN-AUTO 0 12 7
DI - 41 0 6 9 DI - 136 YA LCP-6001 Secondary Clarifier Tank #3 Scum Heaters - Disc. Open Final Clarifiers 0 = FAULT 0 12 8
DI - 42 0 6 10 DI - 137 YA P-905 Prim. Heating Distribution Pump #1 - Fault Service Building Mechanical Room 0 = FAULT 0 12 9
DI - 43 0 6 11 DI - 138 HS P-905 Prim. Heating Distribution Pump #1 - Auto Service Building Mechanical Room 1 = AUTO 0 12 10 1 PHASE A - ADDENDUM #3 10/11/23

DI - 44 0 6 12 DI - 139 YS P-905 Prim. Heating Distribution Pump #1 - Running Service Building Mechanical Room 1 = RUNNING 0 12 11
0 PHASE A ISSUED FOR TENDER 02/10/23
DI - 45 0 6 13 DI - 140 YA P-905 Prim. Heating Distribution Pump #1 - Disc. Open Service Building Mechanical Room 0 = FAULT 0 12 12
DI - 46 0 6 14 DI - 141 0 12 13 No. ISSUE / REVISION DD/MM/YY

DI - 47 0 6 15 DI - 142 0 12 14
This drawing is copyright protected and may not be reproduced or
DI - 48 YA CP-3000 Rack 0 DI Card 7 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 7 0 DI - 143 0 12 15 used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.
DI - 49 YA P-901 Boiler Feed Pump No. 1 - Fault Service Building Boiler Room 0 = FAULT 0 7 1 DI - 144 YA CP-3000 Rack 0 DI Card 13 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 13 0
DI - 50 HS P-901 Boiler Feed Pump No. 1 - Auto Service Building Boiler Room 1 = AUTO 0 7 2 DI - 145 YA P-729 Washwater Sump Pump #4 - Fault Tertiary Filter 0 = FAULT 0 13 1 VERIFY SHEET SIZE AND SCALES. BAR TO THE
RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
DI - 51 YS P-901 Boiler Feed Pump No. 1 - Running Service Building Boiler Room 1 = RUNNING 0 7 3 DI - 146 HS P-729 Washwater Sump Pump #4 - In-Auto Tertiary Filter 1 = IN-AUTO 0 13 2
SCALE:
N.T.S.
DI - 52 YA P-901 Boiler Feed Pump No. 1 - Disc. Open Service Building Boiler Room 0 = FAULT 0 7 4 DI - 147 YS P-729 Washwater Sump Pump #4 - Running Tertiary Filter 1 = RUNNING 0 13 3 1
DI - 53 YA P-715 Effluent Pump #6 - Fault Service Building Basement 0 = FAULT 0 7 5 DI - 148 YA P-729 Washwater Sump Pump #4 - Disconnect Open Tertiary Filter 0 = ALARM 0 13 4
DI - 54 HS P-715 Effluent Pump #6 - In-Auto Service Building Basement 1 = IN-AUTO 0 7 6 DI - 149 YA P-729 Washwater Sump Pump #4 - MiniCAS Tertiary Filter 0 = ALARM 0 13 5
CLIENT:
DI - 55 YS P-715 Effluent Pump #6 - Running Service Building Basement 1 = RUNNING 0 7 7 DI - 150 YS LCP-6004 Secondary Clarifier Tank #4 Scum Heaters - Running Final Clarifiers 1 = RUNNING 0 13 6
DI - 56 YA P-715 Effluent Pump #6 - Disconnect Open Service Building Basement 0 = ALARM 0 7 8 DI - 151 HS LCP-6004 Secondary Clarifier Tank #4 Scum Heaters - In-Auto Final Clarifiers 1 = IN-AUTO 0 13 7
DI - 57 ZSO VFC-902 Hot Water Supply to Headworks Control Valve - Open Service Building Mechanical Room 1 = OPEN 0 7 9 DI - 152 YA LCP-6004 Secondary Clarifier Tank #4 Scum Heaters - Disc. Open Final Clarifiers 0 = FAULT 0 13 8
DI - 58 ZSC VFC-902 Hot Water Supply to Headworks Control Valve - Closed Service Building Mechanical Room 1 = CLOSED 0 7 10 DI - 153 YA P-906 Prim. Heating Distribution Pump #2 - Fault Service Building Mechanical Room 0 = FAULT 0 13 9
DI - 59 YA VFC-902 Hot Water Supply to Headworks Control Valve - Fault Service Building Mechanical Room 0 = FAULT 0 7 11 DI - 154 HS P-906 Prim. Heating Distribution Pump #2 - Auto Service Building Mechanical Room 1 = AUTO 0 13 10
DI - 60 HS VFC-902 Hot Water Supply to Headworks Control Valve - In Auto Service Building Mechanical Room 1 = AUTO 0 7 12 DI - 155 YS P-906 Prim. Heating Distribution Pump #2 - Running Service Building Mechanical Room 1 = RUNNING 0 13 11 CONSULTANT: www.jlrichards.ca
DI - 61 0 7 13 DI - 156 YA P-906 Prim. Heating Distribution Pump #2 - Disc. Open Service Building Mechanical Room 0 = FAULT 0 13 12
DI - 62 0 7 14 DI - 157 0 13 13
DI - 63 0 7 15 DI - 158 0 13 14
DI - 64 YA CP-3000 Rack 0 DI Card 8 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 8 0 DI - 159 0 13 15
DI - 65 YA P-902 Boiler Feed Pump No. 2 - Fault Service Building Boiler Room 0 = FAULT 0 8 1 DI - 160 YA CP-3000 Rack 0 DI Card 14 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 14 0
DI - 66 HS P-902 Boiler Feed Pump No. 2 - Auto Service Building Boiler Room 1 = AUTO 0 8 2 DI - 161 YA LC-608 Sec. Clarifier #3 Long. Collector - Fault Final Clarifiers 0 = FAULT 0 14 1 CONSULTANT:

DI - 67 YS P-902 Boiler Feed Pump No. 2 - Running Service Building Boiler Room 1 = RUNNING 0 8 3 DI - 162 HS LC-608 Sec. Clarifier #3 Long. Collector - In-Auto Final Clarifiers 1 = IN-AUTO 0 14 2
DI - 68 YA P-902 Boiler Feed Pump No. 2 - Disc. Open Service Building Boiler Room 0 = FAULT 0 8 4 DI - 163 YS LC-608 Sec. Clarifier #3 Long. Collector - Running Final Clarifiers 1 = RUNNING 0 14 3
DI - 69 YA P-612 Ras Pump #4 - Fault Service Building Basement 0 = FAULT 0 8 5 DI - 164 YA LC-608 Sec. Clarifier #3 Long. Collector - Disconnect Open Final Clarifiers 0 = ALARM 0 14 4
1
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 IO List.dwg

DI - 70 HS P-612 Ras Pump #4 - In-Auto Service Building Basement 1 = IN-AUTO 0 8 6 DI - 165 YA CC-609 Sec. Clarifier #3 Cross Collector - Fault Final Clarifiers 0 = FAULT 0 14 5
1
DI - 71 YS P-612 Ras Pump #4 - Running Service Building Basement 1 = RUNNING 0 8 7 DI - 166 HS CC-609 Sec. Clarifier #3 Cross Collector - In-Auto Final Clarifiers 1 = IN-AUTO 0 14 6
PROFESSIONAL STAMP PROJECT NORTH
DI - 72 YA P-612 Ras Pump #4 - Disconnect Open Service Building Basement 0 = ALARM 0 8 8 DI - 167 YS CC-609 Sec. Clarifier #3 Cross Collector - Running Final Clarifiers 1 = RUNNING 0 14 7
DI - 73 ZSO VFC-903 Hot Water Supply to Plant Heat Control Valve - Open Service Building Mechanical Room 1 = OPEN 0 8 9 DI - 168 YA CC-609 Sec. Clarifier #3 Cross Collector - Disconnect Open Final Clarifiers 0 = ALARM 0 14 8
DI - 74 ZSC VFC-903 Hot Water Supply to Plant Heat Control Valve - Closed Service Building Mechanical Room 1 = CLOSED 0 8 10 DI - 169 YA P-907 Service Building Heating Pump - Fault Service Building Mechanical Room 0 = FAULT 0 14 9
DI - 75 YA VFC-903 Hot Water Supply to Plant Heat Control Valve - Fault Service Building Mechanical Room 0 = FAULT 0 8 11 DI - 170 HS P-907 Service Building Heating Pump - Auto Service Building Mechanical Room 1 = AUTO 0 14 10
DI - 76 HS VFC-903 Hot Water Supply to Plant Heat Control Valve - In Auto Service Building Mechanical Room 1 = AUTO 0 8 12 DI - 171 YS P-907 Service Building Heating Pump - Running Service Building Mechanical Room 1 = RUNNING 0 14 11
DI - 77 0 8 13 DI - 172 YA P-907 Service Building Heating Pump - Disc. Open Service Building Mechanical Room 0 = FAULT 0 14 12
DI - 78 0 8 14 DI - 173 0 14 13
DI - 79 0 8 15 DI - 174 0 14 14
DI - 80 YA CP-3000 Rack 0 DI Card 9 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 9 0 DI - 175 0 14 15
PROJECT:
DI - 81 YA P-903 Boiler Feed Pump No. 3 - Fault Service Building Boiler Room 0 = FAULT 0 9 1 DI - 176 YA CP-3000 Rack 0 DI Card 15 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 15 0
DI - 82 HS P-903 Boiler Feed Pump No. 3 - Auto Service Building Boiler Room 1 = AUTO 0 9 2 DI - 177 YA LC-610 Sec. Clarifier #4 Long. Collector - Fault Final Clarifiers 0 = FAULT 0 15 1
MUNICIPALITY OF NORTH
DI - 83 YS P-903 Boiler Feed Pump No. 3 - Running Service Building Boiler Room 1 = RUNNING 0 9 3 DI - 178 HS LC-610 Sec. Clarifier #4 Long. Collector - In-Auto Final Clarifiers 1 = IN-AUTO 0 15 2
GRENVILLE - WATER POLLUTION
DI - 84 YA P-903 Boiler Feed Pump No. 3 - Disc. Open Service Building Boiler Room 0 = FAULT 0 9 4 DI - 179 YS LC-610 Sec. Clarifier #4 Long. Collector - Running Final Clarifiers 1 = RUNNING 0 15 3 CONTROL PLANT EXPANSION
DI - 85 YA P-613 Ras Pump #5 - Fault Service Building Basement 0 = FAULT 0 9 5 DI - 180 YA LC-610 Sec. Clarifier #4 Long. Collector - Disconnect Open Final Clarifiers 0 = ALARM 0 15 4
1
PHASE - A
DI - 86 HS P-613 Ras Pump #5 - In-Auto Service Building Basement 1 = IN-AUTO 0 9 6 DI - 181 YA CC-611 Sec. Clarifier #4 Cross Collector - Fault Final Clarifiers 0 = FAULT 0 15 5 KEMPTVILLE, ONTARIO
1
DI - 87 YS P-613 Ras Pump #5 - Running Service Building Basement 1 = RUNNING 0 9 7 DI - 182 HS CC-611 Sec. Clarifier #4 Cross Collector - In-Auto Final Clarifiers 1 = IN-AUTO 0 15 6 DRAWING:
DI - 88 YA P-613 Ras Pump #5 - Disconnect Open Service Building Basement 0 = ALARM 0 9 8 DI - 183 YS CC-611 Sec. Clarifier #4 Cross Collector - Running Final Clarifiers 1 = RUNNING 0 15 7
ELECTRICAL

November 14, 2023 9:55:18 AM


DI - 89 ZSO VFC-904 Hot Water Supply to New Digester - Open Service Building Mechanical Room 1 = OPEN 0 9 9 DI - 184 YA CC-611 Sec. Clarifier #4 Cross Collector - Disconnect Open Final Clarifiers 0 = ALARM 0 15 8
DI - 90 ZSC VFC-904 Hot Water Supply to New Digester - Closed Service Building Mechanical Room 1 = CLOSED 0 9 10 DI - 185 0 15 9
SERVICE BUILDING
DI - 91 YA VFC-904 Hot Water Supply to New Digester - Fault Service Building Mechanical Room 0 = FAULT 0 9 11 DI - 186 0 15 10
DI - 92 HS VFC-904 Hot Water Supply to New Digester - In Auto Service Building Mechanical Room 1 = AUTO 0 9 12 DI - 187 0 15 11
IO TABLE - PLC-300
DI - 93 0 9 13 DI - 188 0 15 12
DI - 94 0 9 14 DI - 189 0 15 13
DESIGN:
LO
1
DRAWN: DRAWING #:
1 NB

PLOT DATE:
1 I/O LIST - PLC - 300 2 I/O LIST (CONT'D) - PLC - 300 CHECKED:
I301A SCALE: NTS I301A SCALE: NTS
JLR #:
JO
29475
I301A
XLS XLS
PLC-300 PLC-300
Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-13
13:24:46 9:03:51 AM Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-13
13:24:46 9:03:51 AM
COMPONENT I/O LIST COMPONENT I/O LIST
CONTROLLER ISA CONTROLLER ISA NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS BUILDING 900 SERIES
800 SERIES
DI - 0190 YA CP-3000 Rack 0 DI Card 4 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 4 0 DI - 0285 YA CP-3000 Rack 0 DI Card 4 24 VDC Failure Service Building PLC Panel 0 = FAILURE 01 46 0 NEW AERATION NEW PRIMARY NEW
15 14 13 TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES
DI - 191 0 15 15 DI - 286 1 6 14
DI - 192 YA CP-3000 Rack 0 DI Card 16 24 VDC Failure Service Building PLC Panel 0 = FAILURE 0 16 0 DI - 287 1 6 15
DI - 193 HS FCP-9010 Boiler #1 Field Control Panel - In Auto Service Building Boiler Room 0 16 1 DO - 0 YS FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 1 7 0 Provide interposing relay to suit NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)
DI - 194 YA FCP-9010 Boiler #1 Field Control Panel - Alarm Service Building Boiler Room 0 16 2 DO - 1 YC FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 1 7 1 Provide interposing relay to suit
DI - 195 LAL FCP-9010 Boiler #1 Field Control Panel - Alarm Service Building Boiler Room 0 16 3 DO - 2 YC FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 1 7 2 Provide interposing relay to suit
DI - 196 TAH FCP-9010 Boiler #1 Field Control Panel - Alarm Service Building Boiler Room 0 16 4 DO - 3 YC P-612 Ras Pump #4 - Run Service Building Basement 1 = RUN 1 7 3 Provide interposing relay to suit 2
DI - 197 NG FCP-9010 Boiler #1 Field Control Panel - Mode Service Building Boiler Room 0 16 5 DO - 4 YC EF-302 Heating Pump Room Exhaust Fan - Run Service Building Mechanical Room 1 = RUN 1 7 4 Provide interposing relay to suit EXISTING SERVICE
BUILDING
300 SERIES
DI - 198 DG FCP-9010 Boiler #1 Field Control Panel - Mode Service Building Boiler Room 0 16 6 DO - 5 ZC VFC-901 Hot Water Supply to Ex. Digester Control Valve - Drive Open Service Building Mechanical Room 1 = OPEN 1 7 5 Provide interposing relay to suit
DI - 199 PAH FCP-9010 Boiler #1 Field Control Panel - Alarm Service Building Boiler Room 0 16 7 DO - 6 ZC VFC-901 Hot Water Supply to Ex. Digester Control Valve - Drive Closed Service Building Mechanical Room 1 = CLOSE 1 7 6 Provide interposing relay to suit
DI - 200 PAL FCP-9010 Boiler #1 Field Control Panel - Alarm Service Building Boiler Room 0 16 8 DO - 7 YC P-901 Boiler Feed Pump #1 - Run Service Building Boiler Room 1 = RUN 1 7 7 Provide interposing relay to suit
DI - 201 PAH FCP-9010 Boiler #1 Field Control Panel - Alarm Service Building Boiler Room 0 16 9 DO - 8 YC P-905 Prim. Heating Distribution Pump #1 - Run Service Building Mechanical Room 1 = RUN 1 7 8 Provide interposing relay to suit KEY PLAN

DI - 202 PAL FCP-9010 Boiler #1 Field Control Panel - Alarm Service Building Boiler Room 0 16 10 DO - 9 YC MIX-704 Flash Tank #2 Mixer - Run Tertiary Filter 1 = RUN 1 7 9 Provide interposing relay to suit
GENERAL NOTES:
DI - 203 YS FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 0 16 11 DO - 10 YC LC-608 Sec. Clarifier #3 Long. Collector - Run Final Clarifiers 1 = RUN 1 7 10 Provide interposing relay to suit
DI - 204 JI FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 0 16 12 DO - 11 YC CC-609 Sec. Clarifier #3 Cross Collector - Run Final Clarifiers 1 = RUN 1 7 11 Provide interposing relay to suit 2 A. AMOUNT AND LOCATION OF INTERPOSING RELAYS,
INTRINSICALLY SAFE BARRIERS, SIGNAL SPLITTERS,
DI - 205 JI FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 0 16 13 DO - 12 YC P-728 Washwater Sump Pump #3 - Run Tertiary Filter 1 = RUN 1 7 12 Provide interposing relay to suit AND ISOLATION MODULES TBD.
DI - 206 FAL FCP-9010 Boiler #1 Field Control Panel - Alarm Service Building Boiler Room 0 16 14 DO - 13 YC LCP-6001 Secondary Clarifier Tank #3 Scum Heaters - Run Final Clarifiers 1 = RUN 1 7 13 Provide interposing relay to suit
B. REFER TO DETAIL 1/I022A FOR THE REQUIRED
DI - 207 PAL FCP-9010 Boiler #1 Field Control Panel - Alarm Service Building Boiler Room 0 16 15 DO 14 1 7 14 Provide interposing relay to suit HARDWIRED LOGIC FOR CONTROLLING THE
DI - 208 YA CP-3000 Rack 1 DI Card 2 24 VDC Failure Service Building PLC Panel 0 = FAILURE 1 2 0 DO - 15 1 7 15 Provide interposing relay to suit ASSOCIATED STACK LIGHTS AND HORNS.

DI - 209 YS FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 1 2 1 DO - 16 YS FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 1 8 0 Provide interposing relay to suit
DRAWING NOTES:
DI - 210 YS FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 1 2 2 DO - 17 YC FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 1 8 1 Provide interposing relay to suit
DI - 211 YA FCP-9010 Boiler #1 Field Control Panel - E-Stop Service Building Boiler Room 1 2 3 DO - 18 YC FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 1 8 2 Provide interposing relay to suit 1 PROGRAM THE PLC TO PROVIDE A WATCHDOG
PULSE. THIS PULSE IS TO BE MONITORED BY THE
DI - 212 1 2 4 DO - 19 YC P-613 Ras Pump #5 - Run Service Building Basement 1 = RUN 1 8 3 Provide interposing relay to suit 2 WATCHDOG TIMING RELAY INSIDE THE PANEL.
DI - 213 1 2 5 DO - 20 YC EF-303 Boiler Room Exhaust Fan - Run Service Building Boiler Room 1 = RUN 1 8 4 Provide interposing relay to suit COORDINATE PULSE WIDTH AND RELAY SELECTION
TO SUIT. THE INTENT OF THIS FEATURE IS TO
DI - 214 1 2 6 DO - 21 ZC VFC-902 Hot Water Supply to Headworks Control Valve - Drive Open Service Building Mechanical Room 1 = OPEN 1 8 5 Provide interposing relay to suit DETECT PLC FAILURE. PROVIDE HARD-WIRED LOGIC
DI - 215 1 2 7 DO - 22 ZC VFC-902 Hot Water Supply to Headworks Control Valve - Drive Closed Service Building Mechanical Room 1 = CLOSE 1 8 6 Provide interposing relay to suit INSIDE THE PLC PANEL TO ENERGIZE ALL STACK
LIGHTS AND ASSOCIATED HORNS CONNECTED TO
DI - 216 1 2 8 DO - 23 YC P-902 Boiler Feed Pump #2 - Run Service Building Boiler Room 1 = RUN 1 8 7 Provide interposing relay to suit
THIS PLC IN EVENT OF A PLC FAILURE. PROVIDE
DI - 217 1 2 9 DO - 24 YC P-906 Prim. Heating Distribution Pump #2 - Run Service Building Mechanical Room 1 = RUN 1 8 8 Provide interposing relay to suit LOGIC TO SILENCE THE HORNS VIA A FLUSH HEAD
PUSHBUTTON ON THE PLC PANEL DOOR. LABEL THE
DI - 218 1 2 10 DO - 25 YC MIX-705 Floc Tank #3 Mixer - Run Tertiary Filter 1 = RUN 1 8 9 Provide interposing relay to suit
PUSHBUTTON "SILENCE HORNS". PUSHBUTTON
DI - 219 1 2 11 DO - 26 YC LC-610 Sec. Clarifier #4 Long. Collector - Run Final Clarifiers 1 = RUN 1 8 10 Provide interposing relay to suit COLOUR TO BE BLUE. HORNS TO BE RE-TRIGGERED
EACH TIME THE PLC FAILS.
DI - 220 1 2 12 DO - 27 YC CC-611 Sec. Clarifier #4 Cross Collector - Run Final Clarifiers 1 = RUN 1 8 11 Provide interposing relay to suit 2
DI - 221 1 2 13 DO - 28 YC P-729 Washwater Sump Pump #4 - Run Tertiary Filter 1 = RUN 1 8 12 Provide interposing relay to suit 2 N.I.C. - PHASE B. PROVIDE RELAY FOR FUTURE I/O,
DI - 222 1 2 14 DO - 29 YC LCP-6004 Secondary Clarifier Tank #4 Scum Heaters - Run Final Clarifiers 1 = RUN 1 8 13 Provide interposing relay to suit WHERE INDICATED.

DI - 223 1 3 15 DO - 30 1 8 14 Provide interposing relay to suit


1
DI - 224 YA CP-3000 Rack 1 DI Card 3 24 VDC Failure Service Building PLC Panel 0 = FAILURE 1 3 0 DO - 31 1 8 15 Provide interposing relay to suit
DI - 225 HS FCP-9020 Boiler #2 Field Control Panel - In Auto Service Building Boiler Room 1 3 1 DO - 32 YS FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 1 9 0 Provide interposing relay to suit
DI - 226 YA FCP-9020 Boiler #2 Field Control Panel - Alarm Service Building Boiler Room 1 3 2 DO - 33 YC FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 1 9 1 Provide interposing relay to suit
DI - 227 LAL FCP-9020 Boiler #2 Field Control Panel - Alarm Service Building Boiler Room 1 3 3 DO - 34 YC FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 1 9 2 Provide interposing relay to suit
DI - 228 TAH FCP-9020 Boiler #2 Field Control Panel - Alarm Service Building Boiler Room 1 3 4 DO - 35 YC P-715 Effluent Pump #6 - Run Service Building Basement 1 = RUN 1 9 3 Provide interposing relay to suit
DI - 229 NG FCP-9020 Boiler #2 Field Control Panel - Mode Service Building Boiler Room 1 3 5 DO - 36 ZC VFC-903 Hot Water Supply to Plant Heat Control Valve - Drive Open Service Building Mechanical Room 1 = OPEN 1 9 4 Provide interposing relay to suit
DI - 230 DG FCP-9020 Boiler #2 Field Control Panel - Mode Service Building Boiler Room 1 3 6 DO - 37 ZC VFC-903 Hot Water Supply to Plant Heat Control Valve - Drive Closed Service Building Mechanical Room 1 = CLOSE 1 9 5 Provide interposing relay to suit
DI - 231 PAH FCP-9020 Boiler #2 Field Control Panel - Alarm Service Building Boiler Room 1 3 7 DO - 38 YC P-903 Boiler Feed Pump #3 - Run Service Building Boiler Room 1 = RUN 1 9 6 Provide interposing relay to suit
DI - 232 PAL FCP-9020 Boiler #2 Field Control Panel - Alarm Service Building Boiler Room 1 3 8 DO - 39 YC P-907 Service Building Heating Pump - Run Service Building Mechanical Room 1 = RUN 1 9 7 Provide interposing relay to suit
DI - 233 PAH FCP-9020 Boiler #2 Field Control Panel - Alarm Service Building Boiler Room 1 3 9 DO - 40 1 9 8 Provide interposing relay to suit 1 PHASE A - ADDENDUM #3 10/11/23

DI - 234 PAL FCP-9020 Boiler #2 Field Control Panel - Alarm Service Building Boiler Room 1 3 10 DO - 41 1 9 9 Provide interposing relay to suit
0 PHASE A ISSUED FOR TENDER 02/10/23
DI - 235 YS FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 1 3 11 DO - 42 1 9 10 Provide interposing relay to suit
DI - 236 JI FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 1 3 12 DO - 43 1 9 11 Provide interposing relay to suit No. ISSUE / REVISION DD/MM/YY

DI - 237 JI FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 1 3 13 DO - 44 1 9 12 Provide interposing relay to suit This drawing is copyright protected and may not be reproduced or
DI - 238 FAL FCP-9020 Boiler #2 Field Control Panel - Alarm Service Building Boiler Room 1 3 14 DO - 45 1 9 13 Provide interposing relay to suit used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.
DI - 239 PAL FCP-9020 Boiler #2 Field Control Panel - Alarm Service Building Boiler Room 1 3 15 DO - 46 1 9 14 Provide interposing relay to suit
VERIFY SHEET SIZE AND SCALES. BAR TO THE
DI - 240 YA CP-3000 Rack 1 DI Card 4 24 VDC Failure Service Building PLC Panel 0 = FAILURE 1 4 0 DO - 47 1 9 15 Provide interposing relay to suit
RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
DI - 241 YS FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 1 4 1 DO - 48 ZC VFC-904 Hot Water Supply to New Digester - Drive Open Service Building Mechanical Room 1 = OPEN 1 10 0 Provide interposing relay to suit
SCALE:
N.T.S.
DI - 242 YS FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 1 4 2 DO - 49 ZC VFC-904 Hot Water Supply to New Digester - Drive Closed Service Building Mechanical Room 1 = CLOSE 1 10 1 Provide interposing relay to suit
DI - 243 YA FCP-9020 Boiler #2 Field Control Panel - E-stop Service Building Boiler Room 1 4 3 DO - 50 YC P-908 Headworks Heating Pump - Run Service Building Mechanical Room 1 = RUN 1 10 2 Provide interposing relay to suit
DI - 244 1 4 4 DO - 51 1 10 3 Provide interposing relay to suit
CLIENT:
DI - 245 1 4 5 DO - 52 1 10 4 Provide interposing relay to suit
DI - 246 1 4 6 DO - 53 1 10 5 Provide interposing relay to suit
DI - 247 1 4 7 DO - 54 1 10 6 Provide interposing relay to suit
DI - 248 1 4 8 DO - 55 1 10 7 Provide interposing relay to suit
DI - 249 1 4 9 DO - 56 1 10 8 Provide interposing relay to suit
DI - 250 1 4 10 DO - 57 1 10 9 Provide interposing relay to suit CONSULTANT: www.jlrichards.ca
DI - 251 1 4 11 DO - 58 1 10 10 Provide interposing relay to suit
DI - 252 1 4 12 DO - 59 1 10 11 Provide interposing relay to suit
DI - 253 1 4 13 DO - 60 1 10 12 Provide interposing relay to suit
DI - 254 1 4 14 DO - 61 1 10 13 Provide interposing relay to suit
DI - 255 1 4 15 DO - 62 1 10 14 Provide interposing relay to suit
DI - 256 YA CP-3000 Rack 1 DI Card 5 24 VDC Failure Service Building PLC Panel 0 = FAILURE 1 5 0 DO - 63 1 10 15 Provide interposing relay to suit CONSULTANT:

DI - 257 HS FCP-9030 Boiler #3 Field Control Panel - In Auto Service Building Boiler Room 1 5 1 DO - 64 YC P-909 Exist. Digester Hot Water Recirc. Pump - Run Service Building Mechanical Room 1 = RUN 1 11 0 Provide interposing relay to suit
DI - 258 YA FCP-9030 Boiler #3 Field Control Panel - Alarm Service Building Boiler Room 1 5 2 DO - 65 YA YA-3200 Service Building Stack Light - Horn Service Building 1 = ON 1 11 1 Provide interposing relay to suit
DI - 259 LAL FCP-9030 Boiler #3 Field Control Panel - Alarm Service Building Boiler Room 1 5 3 DO - 66 UAL UAL-3201 Service Building Stack Light - Red Service Building 1 = ON 1 11 2 Provide interposing relay to suit
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 IO List.dwg

DI - 260 TAH FCP-9030 Boiler #3 Field Control Panel - Alarm Service Building Boiler Room 1 5 4 DO - 67 UAL UAL-3202 Service Building Stack Light - Amber Service Building 1 = ON 1 11 3 Provide interposing relay to suit
DI - 261 NG FCP-9030 Boiler #3 Field Control Panel - Mode Service Building Boiler Room 1 5 5 DO - 68 UAL UAL-3203 Service Building Stack Light - Clear Service Building 1 = ON 1 11 4 Provide interposing relay to suit
PROFESSIONAL STAMP PROJECT NORTH
DI - 262 DG FCP-9030 Boiler #3 Field Control Panel - Mode Service Building Boiler Room 1 5 6 DO - 69 UAL UAL-3204 Service Building Stack Light - Blue Service Building 1 = ON 1 11 5 Provide interposing relay to suit
DI - 263 PAH FCP-9030 Boiler #3 Field Control Panel - Alarm Service Building Boiler Room 1 5 7 DO - 70 1 11 6 Provide interposing relay to suit
DI - 264 PAL FCP-9030 Boiler #3 Field Control Panel - Alarm Service Building Boiler Room 1 5 8 DO - 71 1 11 7 Provide interposing relay to suit
DI - 265 PAH FCP-9030 Boiler #3 Field Control Panel - Alarm Service Building Boiler Room 1 5 9 DO - 72 1 11 8 Provide interposing relay to suit
DI - 266 PAL FCP-9030 Boiler #3 Field Control Panel - Alarm Service Building Boiler Room 1 5 10 DO - 73 1 11 9 Provide interposing relay to suit
DI - 267 YS FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 1 5 11 DO - 74 1 11 10 Provide interposing relay to suit
DI - 268 JI FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 1 5 12 DO - 75 1 11 11 Provide interposing relay to suit
DI - 269 JI FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 1 5 13 DO - 76 1 11 12 Provide interposing relay to suit
DI - 270 FAL FCP-9030 Boiler #3 Field Control Panel - Alarm Service Building Boiler Room 1 5 14 DO - 77 1 11 13 Provide interposing relay to suit
PROJECT:
DI - 271 PAL FCP-9030 Boiler #3 Field Control Panel - Alarm Service Building Boiler Room 1 5 15 DO - 78 YC ATS-390 ATS-390 Transfer to Normal Power Command Service Building Electrical Room 1 = TRANSFER 1 11 14 Provide interposing relay to suit
MUNICIPALITY OF NORTH
DI - 272 YA CP-3000 Rack 1 DI Card 6 24 VDC Failure Service Building PLC Panel 0 = FAILURE 1 6 0 DO - 79 YS CP-3000 PLC Watchdog Pulse 1 11 15 Provide interposing relay to suit 1
DI - 273 YS FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 1 6 1
GRENVILLE - WATER POLLUTION
DI - 274 YS FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 1 6 2 CONTROL PLANT EXPANSION
DI - 275 YA FCP-9030 Boiler #3 Field Control Panel - E-stop Service Building Boiler Room 1 6 3 AI - 0 BI FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 2 2 0 PHASE - A
DI - 276 1 6 4 AI - 1 FF FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 2 2 1 KEMPTVILLE, ONTARIO
DI - 277 1 6 5 AI - 2 FF FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 2 2 2 DRAWING:

November 14, 2023 11:14:41 AM


DI - 278 1 6 6 AI - 3 SI EF-302 Heating Pump Room Exhaust Fan Speed Indicator Service Building Mechanical Room 2 2 3 Provide analog signal duplicator
ELECTRICAL
DI - 279 1 6 7 AI - 4 SI P-905 Prim. Heating Distribution Pump #1 Speed Indicator Service Building Mechanical Room 2 2 4 Provide analog signal duplicator
SERVICE BUILDING
DI - 280 1 6 8 AI - 5 2 2 5
DI - 281 1 6 9 AI - 6 SI P-612 Ras Pump #4 Speed Indicator Service Building Basement 2 2 6 2
DI - 282 1 6 10 AI - 7 AI AIT-3300 Drip Trap Room H2S Analyzer Indicator Service Building Boiler Room 2 2 7
IO TABLES CONT'D - PLC-300
DI - 283 1 6 11 AI - 8 BI FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 2 3 0
DI - 284 1 6 12 AI - 9 FF FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 2 3 1 DESIGN:
1 LO
1
DRAWN: DRAWING #:
NB

PLOT DATE:
1 I/O LIST (CONT'D) - PLC - 300 2 I/O LIST (CONT'D) - PLC - 300 CHECKED:
I302A SCALE: NTS I302A SCALE: NTS
JLR #:
JO
29475
I302A
XLS XLS
PLC-300
Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-13
13:24:46 9:03:51 AM Excel Sheet Data Exported on: 2017-07-11 11:25:22 AM
COMPONENT I/O LIST COMPONENT SUMMARY
CONTROLLER ISA SLOT CATALOG IO IO NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS NUMB. NUMBER MANUFACTURER DESCRIPTION IO TYPE RACK COUNT COMMENTS BUILDING 900 SERIES
800 SERIES
DI 0 YA CP-3000 Rack 0#2DIField
CardControl
4 24 VDC Failure PLC Panel 0 = FAILURE NEW PRIMARY NEW
AI 10 FF FCP-9020 Boiler Panel - Service Building Boiler Room 20 34 20 0 1756-A17 AB/RA 17 Slot ControlLogix Chassis Miscellaneous 0 0
NEW AERATION
TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES
AI - 11 SI EF-303 Boiler Room Exhaust Fan Speed Indicator Service Building Boiler Room 2 3 3 Provide analog signal duplicator 0 1756-PB75 AB/RA 24VDC Power Supply (13A @ 5V) Miscellaneous 0 0
AI - 12 SI P-906 Prim. Heating Distribution Pump #2 Speed Indicator Service Building Mechanical Room 2 3 4 Provide analog signal duplicator 0 1756-L84E AB/RA ControlLogix Processor with 20MB NV Memory Processor 0 0
AI - 13 2 3 5 NEW SECONDARY NEW TERTIARY
0 1784-SD2 AB/RA 2Gb Secure Digital Memory Card Miscellaneous 0 0 CLARIFIERS FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)
AI - 14 SI P-613 Ras Pump #5 Speed Indicator Service Building Basement 2 3 6 1
1 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 0 0
AI - 15 AI AIT-3301 Drip Trap Room CH4 Analyzer Indicator Service Building Boiler Room 2 3 7
2 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 0 0 Used for direct connection to Rack 1.
AI - 16 BI FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 2 4 0
3 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 0 0 Used for direct connection to Rack 2.
AI - 17 FF FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 2 4 1 EXISTING SERVICE
4 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block BUILDING
300 SERIES
AI - 18 FF FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 2 4 2
5 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
AI - 19 SI P-715 Effluent Pump #6 Speed Indicator Service Building Basement 2 4 3
6 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
AI - 20 2 4 4
7 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block KEY PLAN
AI - 21 2 4 5
8 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
AI 22 2 4 6
AI - 23 2 4 7 9 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block GENERAL NOTES:
AI - 24 2 5 0 10 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
A. AMOUNT AND LOCATION OF INTERPOSING RELAYS,
AI - 25 TI TIT-3010 Service Building Electrical Room Temperature Indicator Service Building Electrical Room 2 5 1 11 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block INTRINSICALLY SAFE BARRIERS, SIGNAL SPLITTERS,
12 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block AND ISOLATION MODULES TBD.
AI - 26 TI TIT-3013 Heating Pump Room Temperature Indicator Service Building Mechanical Room 2 5 2
AI - 27 TI TIT-3014 Boiler Room Temperature Indicator Service Building Boiler Room 2 5 3 13 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
AI - 28 TI TIT-9020 Boiler Hot Water Supply Temperature Indicator (RTD) Service Building Boiler Room 2 5 4
DRAWING NOTES:
14 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
AI - 29 TI TIT-9021 Boiler Hot Water Return Temperature Indicator (RTD) Service Building Boiler Room 2 5 5 15 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block 1 N.I.C. - PHASE B
AI - 30 TI TIT-9022 Hot Water Supply for Existing Plant Heating Temp. Indicator Service Building Basement 2 5 6 16 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block 1
AI - 31 TI TIT-9023 Hot Water Supply to Existing Digester Temp. Indicator Service Building Boiler Room 2 5 7 0 1756-A17 AB/RA 17 Slot ControlLogix Chassis Miscellaneous 1 0
AI - 32 FI FIT-6010 Return Activated Sludge Pump #5 Flow Indicator (Mag) Service Building Basement 2 6 0 0 1756-PB75 AB/RA 24VDC Power Supply (13A @ 5V) Miscellaneous 1 0
1
AI - 33 FI FIT-6011 Return Activated Sludge Pump #4 Flow Indicator (Mag) Service Building Basement 2 6 1
1 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 1 0 Used for direct connection to Rack 0.
AI - 34 FI FIT-7002 Washwater Pump Flow Indicator (Mag) Service Building Basement 2 6 2
2 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
AI - 35 FI FIT-7017 Effluent Pumps (to Outfall) Flow Indicator Tertiary Filter Room 2 6 3
3 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
AI - 36 2 6 4
4 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
AI - 37 2 6 5
5 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
AI - 38 2 6 6
6 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 1 16 Provide 1756-TBCH Screw Clamp Block
AI - 39 2 6 7
7 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block
AI - 40 2 7 0
8 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block
AI - 41 2 7 1
AI - 42 2 7 2
9 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block

AI - 43 2 7 3 10 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block

AI - 44 2 7 4 11 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block

AI - 45 2 7 5 12 1756-N2 AB/RA Slot Filler Miscellaneous 1 0

AI - 46 2 7 6 13 1756-N2 AB/RA Slot Filler Miscellaneous 1 0


AI - 47 2 7 7 14 1756-N2 AB/RA Slot Filler Miscellaneous 1 0
AO - 0 TC FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 2 8 0 15 1756-N2 AB/RA Slot Filler Miscellaneous 1 0
AO - 1 BC FCP-9010 Boiler #1 Field Control Panel - Service Building Boiler Room 2 8 1 16 1756-N2 AB/RA Slot Filler Miscellaneous 1 0
AO - 2 SC P-612 Ras Pump #4 Speed Control Service Building Basement 2 8 2 1 0 1756-A17 AB/RA 17 Slot ControlLogix Chassis Miscellaneous 2 0
AO - 3 SC EF-302 Heating Pump Room Exhaust Fan Speed Control Service Building Mechanical Room 2 8 3 0 1756-PB75 AB/RA 24VDC Power Supply (13A @ 5V) Miscellaneous 2 0
AO - 4 SC P-905 Prim. Heating Distribution Pump #1 Speed Control Service Building Mechanical Room 2 8 4 1 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 2 0 Used for direct connection to Rack 0.
AO - 5 2 8 5
1 PHASE A - ADDENDUM #3 10/11/23
2 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 2 8 Provide 1756-TBCH Screw Clamp Block
AO - 6 2 8 6
3 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 2 8 Provide 1756-TBCH Screw Clamp Block 0 PHASE A ISSUED FOR TENDER 02/10/23
AO - 7 2 8 7
4 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block
AO - 8 TC FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 2 9 0 No. ISSUE / REVISION DD/MM/YY
5 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block
AO - 9 BC FCP-9020 Boiler #2 Field Control Panel - Service Building Boiler Room 2 9 1 This drawing is copyright protected and may not be reproduced or
6 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block
AO - 10 SC P-613 Ras Pump #5 Speed Control Service Building Basement 2 9 2 1 used for purposes other than execution of the described work without
7 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 2 8 Provide 1756-TBCH Screw Clamp Block the express written consent of J.L. Richards & Associates Limited.
AO - 11 SC EF-303 Boiler Room Exhaust Fan Speed Control Service Building Boiler Room 2 9 3
8 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 2 8 Provide 1756-TBCH Screw Clamp Block VERIFY SHEET SIZE AND SCALES. BAR TO THE
AO - 12 SC P-906 Prim. Heating Distribution Pump #2 Speed Control Service Building Mechanical Room 2 9 4 RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING.
9 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 2 8 Provide 1756-TBCH Screw Clamp Block 0 25mm
AO - 13 2 9 5
SCALE:
10 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 2 8 Provide 1756-TBCH Screw Clamp Block N.T.S.
AO - 14 2 9 6
AO - 15 2 9 7 11 1756-N2 AB/RA Slot Filler Miscellaneous 2 0

AO - 16 TC FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 2 10 0 12 1756-N2 AB/RA Slot Filler Miscellaneous 2 0
CLIENT:
AO - 17 BC FCP-9030 Boiler #3 Field Control Panel - Service Building Boiler Room 2 10 1 13 1756-N2 AB/RA Slot Filler Miscellaneous 2 0

AO - 18 SC P-715 Effluent Pump #6 Speed Control Service Building Basement 2 10 2 14 1756-N2 AB/RA Slot Filler Miscellaneous 2 0
AO - 19 2 10 3 15 1756-N2 AB/RA Slot Filler Miscellaneous 2 0
AO - 20 2 10 4 16 1756-N2 AB/RA Slot Filler Miscellaneous 2 0
AO - 21 2 10 5
AO - 22 2 10 6 CONSULTANT: www.jlrichards.ca
AO - 23 2 10 7

1
2 COMPONENT LIST - PLC - 300 CONSULTANT:

I303A SCALE: NTS

1 I/O LIST (CONT'D) - PLC - 300


I302A SCALE: NTS
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 IO List.dwg

PROFESSIONAL STAMP PROJECT NORTH

PROJECT:

MUNICIPALITY OF NORTH
GRENVILLE - WATER POLLUTION
CONTROL PLANT EXPANSION
PHASE - A
KEMPTVILLE, ONTARIO
DRAWING:

ELECTRICAL

November 14, 2023 9:50:51 AM


SERVICE BUILDING
COMPONENTS LIST & IO TABLES
CONT'D - PLC-300

DESIGN:
LO
DRAWN: DRAWING #:
NB

PLOT DATE:
CHECKED:

JLR #:
JO
29475
I303A
DRA ING NOTES
300 CABLE TRA MO NTED 1 PROVIDE PVC SLEEVES MO NTED BELO SLAB FOR CABLE NE DE ATERING AND ELECTRICAL SERVICE
ALONG HAND RAIL REFER TO TRANSITIONS BET EEN TAN S ANTIT AND SI ES TO S IT DIGESTER CONTROL ENTRANCE B ILDING
LD-P-404 LD-P-406 B ILDING 900 SERIES
DETAIL 6 E006A GLOBAL-1000 GLOBAL-1000
800 SERIES
NE AERATION NE PRIMAR NE
2 CONTRACTOR TO PROVIDE PVC SLEEVES THRO GH E TERIOR TAN S CLARIFIERS HEAD OR S

4.B LD-P-405
GLOBAL-1000
LD-P-407
GLOBAL-1000
ALLS
ENVELOPE
ANTIT AND SI E TO S IT MAINTAIN ATER TIGHT 500 SERIES 400 SERIES 200 SERIES

3 PROVIDE OPENING IN CONCRETE SLAB S S STILLING ELL FOR NE SECONDAR NE TERTIAR


CABLE TRA DROPS BELO RADAR SENSOR RADAR SENSOR TO BE MO NTED ON TOP OF THE CLARIFIERS FILTER B ILDING
600 SERIES PHASE B 700 SERIES PHASE B
STAIRS CONCRETE SLAB NE T TO THE P MP DISCHARGE PIPING ENS RE
THE SENSOR IS F LL ACCESSIBLE AND DOES NOT IMPEDE ACCESS
TO AN MECHANICAL E IPMENT COORDINATE OPENING ITH
STR CT RAL PROVIDE A REMOVABLE S S SHRO D FOR THE RADAR
10 SENSOR FOR MECHANICAL PROTECTION OF THE DEVICE ALLO FOR
LCP-4012 E ISTING SERVICE
CABLE TRA MO NTED BELO GLOBAL-1000
P GFCI A 100 S S STILLING ELL TAPERED END INSIDE THE ET ELL B ILDING
LP-203-26 300 SERIES
STAIR MAINTAIN A MINIM M OF COORDINATE DETAILS OF THE STILLING ELL ITH THE SENSOR
300 BELO PLATFORM FOR MAN FACT RER
CABLE ACCESS
4 RESERVED
E PLAN
5 PROVIDE 10 A G TEC 90 CABLE FOR IRING TO LIGHT STANDARD
300-SS-EFF1 FINAL TERMINATION AT LIGHT STANDARD TO BE 12 A G R 90 GENERAL NOTES
CABLE TRA DROPS BELO RO TE THE CABLE INSIDE THE CABLE TRA S S STEM O TLINED
STAIRS
LCP-4013
2.A PROVIDE A PVC SLEEVE NEMA4 J NCTION BO AND OCAL E S
FITTING AT THE POLE TO E TEND IRING INTO THE POLE SI E
A ALL CABLES NOT SHO N REFER TO BLOC DIAGRAM
AND SINGLE LINE DIAGRAM FOR COMPLETE LIST OF
GLOBAL GLOBAL-1000
SLEEVE P LL BO AND FITTINGS TO S IT MINIM M SLEEVE SI E OF CABLES
M
VFC-404 GLOBAL 53 ENS RE SLEEVE DOES NOT PROVIDE A PATH FOR GAS
1000
M LD-P-403 MIGRATION INTO THE POLE REFER TO ME005A FOR HA ARDO S
300 CABLE TRA MO NTED DEVICE
B CONTRACTOR TO COORDINATE CABLE TRA RO TE
P-403
GLOBAL-1000
DEVICE

LSL TC CLASSIFICATION PROVIDE ALL ASSOCIATED APP RTENANCES FOR


ALONG HAND RAIL REFER TO 1000

4030 450 CABLE TRA MO NTED ITH MECHANICAL AND ELECTRICAL S STEMS
DETAIL 6 E006A
DEVICE DEVICE DEVICE
4030 RAD RATED AREAS REFER TO DETAIL 2 E010A COORDINATE ITH
M M M DEVICE
ALONG HAND RAIL REFER TO
P-404 P-405 P-406 LIT STR CT RAL C CABLE TRA BRAC ETS NOT TO E TEND MORE THAN
4015 DETAIL 6 E006A
ELEMENT
RAD 50 BE OND CABLE TRA S
LE 6 PROVIDE 6 A G TEC 90 CABLE FOR IRING TO RECEPTACLE
4015 3 RO TE CABLE INSIDE THE CABLE TRA S STEMS O TLINED PROVIDE D COORDINATE FINAL DIMENSIONS OF HO SE EEPING
50-SS-EFF1 A PVC SLEEVE TO RO TE CABLE THRO GH CONCRETE SEC RE PADS ITH ACT AL E IPMENT DIMENSIONS PROVIDE
4.4 5
CABLE TO ALLS BENEATH THE GRATING ENS RE CABLE DOES NOT
IMPEDE ACCESS TO MECHANICAL E IPMENT AND REMOVAL OF
A MINIM M OF 100 CLEARANCE ON FRONT AND SIDES
EACH HO SE EEPING PAD TO BE 100 HIGH
GRATING ENS RE CABLE IS SEC RED AT AN ELEVATION ABOVE THE
GLOBAL

M TOP ATER LEVEL FINAL TERMINATION AT RECEPTACLE TO BE 12 E REFER TO SITE PLANS ON DRA INGS E002A AND E003A
SGA-401 A G R 90 RECEPTACLE TO BE MO NTED AT 1200 AFF FOR F RTHER DETAILS ON THE POLE-MO NTED
1000

LIGHTING
7 PROVIDE 4 A G TEC 90 CABLE FOR IRING TO RECEPTACLE
RH-409 T O TIER 450 CABLE RO TE CABLE INSIDE THE CABLE TRA S STEMS O TLINED PROVIDE
DP-201-49 51 53
GLOBAL-1000

TRA ON S PPORTS A PVC SLEEVE TO RO TE CABLE THRO GH CONCRETE SEC RE


REFER TO STR CT RAL CABLE TO ALLS BENEATH THE GRATING ENS RE CABLE DOES NOT
300 CABLE TRA MO NTED FOR S PPORT DETAILS IMPEDE ACCESS TO MECHANICAL E IPMENT AND REMOVAL OF
ALONG HAND RAIL REFER TO LP-203-29 COORDINATE FINAL CABLE GRATING ENS RE CABLE IS SEC RED AT AN ELEVATION ABOVE THE
DETAIL 6 E006A TRA ELEVATION ITH TOP ATER LEVEL FINAL TERMINATION AT RECEPTACLE TO BE 12
11
6
P GFCI
PRIMAR HEAD OR S TRA A G R 90 RECEPTACLE TO BE MO NTED AT 1200 AFF
ELEVATION
JBP-500 LCP-4007
CLARIFIER CABLE TRA DO N 8 PROVIDE 4 A G TEC 90 CABLE FOR IRING TO RECEPTACLE
RH-408
TO PLATFORM
2.4 RO TE CABLE INSIDE THE CABLE TRA S STEMS O TLINED PROVIDE
GLOBAL-1000
GLOBAL-1000

DP-201-49 51 53
GLOBAL-1000

JBD-500 TAN NO 3 FLOOR TRANSITION A PVC SLEEVE TO RO TE CABLE THRO GH CONCRETE SEC RE
GLOBAL-1000
LD-RH-407 CABLES TO CABLE TO ALLS BENEATH THE GRATING ENS RE CABLE DOES NOT
GLOBAL-1000
2
JBA-500
GLOBAL-1000
G ARDRAIL IMPEDE ACCESS TO MECHANICAL E IPMENT AND REMOVAL OF
GLOBAL-1000
JBP-407 MO NTED TRA AS GRATING ENS RE CABLE IS SEC RED AT AN ELEVATION ABOVE THE
RE IRED LCP-4010 TOP ATER LEVEL FINAL TERMINATION AT RECEPTACLE TO BE 12
GLOBAL-1000 A G R 90 RECEPTACLE TO BE MO NTED AT 1200 AFF
1
450 CABLE
LD-LC-401 9 PROVIDE 12 A G TEC 90 CABLE FOR IRING TO RECEPTACLE
RH-407 TRA MO NTED GLOBAL-1000 GLOBAL

RO TE CABLE INSIDE THE CABLE TRA S STEMS O TLINED FINAL


GLOBAL-1000

DP-201-49 51 53 M
ALONG HAND RAIL DEVICE

MS
LC-403
GLOBAL

LD-CC-401 M TERMINATION AT RECEPTACLE TO BE 12 A G R 90 MO NT


REFER TO DETAIL 1000

4023 RECEPTACLE AT 1200 AFF


GLOBAL-1000

CC-403
6 E006A 1000

LD-LC-402
10 PROVIDE 8 A G TEC 90 CABLE FOR IRING TO RECEPTACLE
GLOBAL-1000

1
4.3 P GFCI
LP-203-28
RO TE CABLE INSIDE THE CABLE TRA S STEMS O TLINED FINAL
TERMINATION AT RECEPTACLE TO BE 12 A G R 90 MO NT
1 PHASE A - ADDEND M 3 10 11 23
RECEPTACLE AT 1200 AFF
9 GLOBAL

M
DEVICE

MS
1 LC-402 4024 11 450 CABLE TRA MO NTED VERTICALL BENEATH GRATING 0 PHASE A ISS ED FOR TENDER 02 10 23
1000

PROVIDE PVC SLEEVES MO NTED BELO SLAB FOR CABLE


RH-406 TRANSITIONS ANTIT AND SI ES TO S IT ENS RE CABLE TRA N ISS E REVISION DD MM
DP-201-44 46 48
GLOBAL-1000

AND SLEEVES DO NOT IMPEDE REMOVAL OF GRATE OR MECHANICAL


CABLE TRA DO N E IPMENT T
300 CABLE TRA MO NTED TO PLATFORM
ALONG HAND RAIL REFER TO LP-203-27 FLOOR TRANSITION 12 PROVIDE A DEDICATED 103 PVC SLEEVE FOR THE INTEGRAL JL R A L
CABLES TO CABLE FOR EACH F T RE P MP SEC RE SLEEVES TO THE
DETAIL 6 E006A
11 7
P GFCI PRIMAR G ARDRAIL NDERSIDE OF THE CONCRETE SLAB SING S S HARD ARE AND S S VERIF SHEET SI E AND SCALES BAR TO THE
MO NTED TRA AS FASTENERS EACH SLEEVE TO ST B P THRO GH THE CONCRETE RIGHT IS 25 IF THIS IS A F LL SI E DRA ING 0 25
CLARIFIER RE IRED SLAB BENEATH THE RESPECTIVE F T RE P MP DISCONNECT SCALE
LCP-4004 RH-405 AS INDICATED
GLOBAL-1000 COORDINATE ITH STR CT RAL STOP AND CAP EACH SLEEVE AT
DP-201-44 46 48
TAN NO 2 T O TIER 450 TRA
GLOBAL-1000

300 ABOVE THE CONCRETE SLAB IN ADDITION PROVIDE ONE 1


ON S PPORTS REFER
LD-RH-404 SPARE 103 PVC SLEEVE SPARE SLEEVE TO R N FROM THE 0 1 2 3 4
TO STR CT RAL FOR
GLOBAL-1000
LOCATION OF P-405 BENEATH THE CONCRETE SLAB SPARE SLEEVE
S PPORT DETAILS CLIENT
TO ST B P BENEATH THE F T RE LCP-4012 AND BE CAPPED AT
JBP-404 COORDINATE FINAL
GLOBAL-1000
300 ABOVE THE CONCRETE SLAB
LCP-4020
CABLE TRA ELEVATION
ITH HEAD OR S TRA
ELEVATION
GLOBAL-1000

2.2a 1
LD-CC-402
RH-404 GLOBAL-1000

M
GLOBAL

DP-201-44 46 48
GLOBAL-1000

LD-LC-403 CC-402
1000

GLOBAL-1000

GLOBAL

M 2
LD-CC-403
GLOBAL-1000 LC-401 CONS LTANT
1 1000

4.2 P GFCI
LP-203-28
9

GLOBAL

450 CABLE 1 DEVICE


M
MS
TRA MO NTED 4025 CC-401
RH-403 ALONG HAND RAIL
1000
29475 PRIMAR CLARIFIER LA O T

DP-201-43 45 47
GLOBAL-1000

REFER TO DETAIL CONS LTANT


1
6 E006A

LP-203-25

11
8
P GFCI
PRIMAR
LCP-4001
CLARIFIER
300 CABLE TRA MO NTED GLOBAL-1000
RH-402
GLOBAL-1000

DP-201-43 45 47 PROFESSIONAL STAMP PROJECT NORTH


VERTICALL ALONG HAND RAIL
REFER TO DETAIL 6 E006A
TAN NO 1
LD-RH-401
GLOBAL-1000

GLOBAL-1000
JBP-401
150 CABLE TRA MO NTED
ALONG HAND RAIL REFER TO
6-E

DETAIL 6 E006A
RH-401
DP-301-43 45 47
GLOBAL-1000

1
3-P

PROJECT
5
M NICIPALIT OF NORTH
4.1
D

GRENVILLE - ATER POLL TION


CONTROL PLANT E PANSION
PCP E

PHASE - A
EMPTVILLE ONTARIO
DRA ING
1 PRIMAR CLARIFIER TAN PLAN VIE
ELECTRICAL

14 2023 9 56 03 AM
I410A SCALE AS INDICATED
PRIMAR TAN S
P 29000 29475-000 -

PO ER AND INSTR MENTATION


PLAN

DESIGN
LO

N
DRA N DRA ING
IDM

PLOT DATE
CHEC ED
JO
I410A
L

JLR
29475
F
NE DE ATE ING AND ELECT ICAL E VICE
DIGE TE CONT OL ENT ANCE B ILDING
B ILDING 900 E IE
800 E IE
NE AE ATION NE P IMA NE
TAN CLA IFIE HEAD O
500 E IE 400 E IE 200 E IE

NE ECONDA NE TE TIA
CLA IFIE FILTE B ILDING
600 E IE PHA E B 700 E IE PHA E B
CABLE T A D OP BELO
TAI

CABLE T A MO NTED BELO E I TING E VICE


TAI MAINTAIN A MINIM M OF B ILDING
300 E IE
300 BELO PLATFO M FO
CABLE ACCE

CABLE T A D OP BELO
TAI E PLAN

CABLE T A MO NTED ALONG


GENE AL NOTE
HAND AIL EFE TO DETAIL
6 E006A A ALL CABLE NOT HO N EFE TO BLOC DIAG AM
AND INGLE LINE DIAG AM FO COMPLETE LI T OF
CABLE
5 1 4 3

2 B CONT ACTO TO COO DINATE CABLE T A O TE


ITH MECHANICAL AND ELECT ICAL TEM

C CABLE T A B AC ET NOT TO E TEND MO E THAN


50 BE OND CABLE T A
7
HG-518 D COO DINATE FINAL DIMEN ION OF HO E EEPING
GLOBAL-1000

PAD ITH ACT AL E IPMENT DIMEN ION P OVIDE


LO DEN IT HIGH DEN IT A MINIM M OF 100 CLEA ANCE ON F ONT AND IDE
EACH HO E EEPING PAD TO BE 100 HIGH
GLOBAL-1000
HG-517
AE ATION G ID TAN 3 AE ATION G ID TAN 3 JBP-500
GLOBAL-1000

JBD-500
GLOBAL-1000
E EFE TO ITE PLAN ON D A ING E002AAND E003A
FO F THE DETAIL ON THE POLE-MO NTED
JBA-500
ELEMENT
DO
GLOBAL-1000
LIGHTING
AE
GLOBAL-1000
HG-516 4013

DEVICE
DO
AIT GLOBAL GLOBAL

4013 8 M M
VFC-414 VFC-413
DO 1 1000

1 1000

DEVICE GLOBAL GLOBAL 2


1 AIT M M
8
4012 VFC-412
1000
VFC-411
1000

HG-512
ELEMENT
DO
GLOBAL-1000 AE
4012

LO DEN IT HIGH DEN IT


6 GLOBAL-1000
HG-511
AE ATION G ID TAN 2 AE ATION G ID TAN 2

GLOBAL-1000
HG-510

1 1 1 PHA E A - ADDEND M 3 10 11 23
DO
2
GLOBAL GLOBAL

M M
DEVICE

AIT 8
4011 VFC-410 VFC-409
1000 1000

0 PHA E A I ED FO TENDE 02 10 23

ELEMENT
DO
AE N I E EVI ION DD MM
GLOBAL-1000
HG-506 4011
1
LO DEN IT HIGH DEN IT T

JL A L

GLOBAL-1000
HG-505 AE ATION G ID TAN 1 AE ATION G ID TAN 1 VE IF HEET I E AND CALE BA TO THE
IGHT I 25 IF THI I A F LL I E D A ING 0 25
CALE
A INDICATED
1

GLOBAL-1000
HG-504 0 1 2 3 4 6

CLIENT

6 5 4

CON LTANT

1 AE ATION TAN PLAN D A ING NOTE


I510A CALE A INDICATED 1 300 CABLE T A MO NTED VE TICALL ALONG 6 P OVIDE 3 A G TEC 90 CABLE FO I ING TO CON LTANT
G A D AIL EFE TO DETAIL 6 E006A LIGHT TANDA D FINAL TE MINATION AT LIGHT
29475 AE ATION TAN LA O T

TANDA D TO BE 12 A G 90 O TE THE CABLE


2 P OVIDE PVC LEEVE MO NTED BELO LAB FO IN IDE THE CABLE T A TEM O TLINED
CABLE T AN ITION BET EEN TAN ANTIT P OVIDE A PVC LEEVE NEMA 4 J NCTION BO
AND I E TO IT AT THE POLE TO E TEND THE I ING INTO THE POLE
I E LEEVE P LL BO AND FITTING TO IT
3 P OVIDE 8 A G TEC 90 CABLE FO I ING TO MINIM M LEEVE I E OF 53 PVC LEEVE TO
LIGHT TANDA D FINAL TE MINATION AT LIGHT CONNECT TO THE J NCTION BO HE E PO IBLE
TANDA D TO BE 12 A G 90 O TE THE CABLE P OFE IONAL TAMP P OJECT NO TH
IN O DE TO MINIMI E THE AMO NT OF E PO ED
IN IDE THE CABLE T A TEM O TLINED COND IT P OVIDE ALL APP TENANCE FO A
P OVIDE A PVC LEEVE NEMA 4 J NCTION BO COMPLETE IN TALLATION COO DINATE ITH
AT THE POLE TO E TEND THE I ING INTO THE POLE T CT AL
I E LEEVE P LL BO AND FITTING TO IT
MINIM M LEEVE I E OF 53 PVC LEEVE TO 7 EC E CABLE TO ALL BENEATH THE G ATING
CONNECT TO THE J NCTION BO HE E PO IBLE EN E CABLE DOE NOT IMPEDE ACCE TO
6-E

IN O DE TO MINIMI E THE AMO NT OF E PO ED MECHANICAL E IPMENT AND EMOVAL OF


COND IT P OVIDE ALL APP TENANCE FO A G ATING EN E CABLE I EC ED AT AN
COMPLETE IN TALLATION COO DINATE ITH ELEVATION ABOVE THE TOP ATE LEVEL
T CT AL
8 CONT ACTO TO ALLO FO HEATED AND
3-P

4 P OVIDE 6 A G TEC 90 CABLE FO I ING TO IN LATED NEMA 4 PANEL PE G O P 1 ON


LIGHT TANDA D FINAL TE MINATION AT LIGHT D A ING I017A COMPLETE ITH INDO TO MO NT P OJECT
TANDA D TO BE 12 A G 90 O TE THE CABLE
IN IDE THE CABLE T A TEM O TLINED
THE DO ANAL E CLEANING IT AND AN OTHE M NICIPALIT OF NO TH
D

A OCIATED APP TENANCE THAT HAVE AN


P OVIDE A PVC LEEVE NEMA 4 J NCTION BO
AT THE POLE TO E TEND THE I ING INTO THE POLE
OPE ATING TEMPE AT E THAT DOE NOT G ENVILLE - ATE POLL TION
CONFO M TO THE DE IGN LO AMBIENT
I E LEEVE P LL BO AND FITTING TO IT TEMPE AT E OF -30 DEG EE CEL I FO THE CONT OL PLANT E PAN ION
MINIM M LEEVE I E OF 53 PVC LEEVE TO ITE THE PANEL TO BE E IPPED ITH 5 FOIL
PCP E

CONNECT TO THE J NCTION BO HE E PO IBLE IN LATION D AL THE MO TAT AND HEATE PHA E - A
IN O DE TO MINIMI E THE AMO NT OF E PO ED PE G O P 15 ON D A ING I017A MONITO EMPTVILLE ONTA IO
COND IT P OVIDE ALL APP TENANCE FO A TEMPE AT E TAT VIA THE THE MO TAT AND
COMPLETE IN TALLATION COO DINATE ITH P OVIDE IGNAL I ING VIA TEC 90 IN CABLE T A D A ING
T CT AL

14 2023 11 18 19 AM
BAC TO PLC P OVIDE DEDICATED CI C IT IN
TEC 90 VIA CABLE T A FO HEATE F OM LP-203 ELECT ICAL
P OVIDE 4 A G TEC 90 CABLE FO I ING TO
5 P I E FO VOLTAGE D OP AE ATION TAN
P 29000 29475-000 -

LIGHT TANDA D FINAL TE MINATION AT LIGHT


TANDA D TO BE 12 A G 90 O TE THE CABLE
IN IDE THE CABLE T A TEM O TLINED 1 PO E AND IN T MENTATION
P OVIDE A PVC LEEVE NEMA 4 J NCTION BO
AT THE POLE TO E TEND THE I ING INTO THE POLE PLAN
I E LEEVE P LL BO AND FITTING TO IT
MINIM M LEEVE I E OF 53 PVC LEEVE TO
CONNECT TO THE J NCTION BO HE E PO IBLE DE IGN
LO MM

N
IN O DE TO MINIMI E THE AMO NT OF E PO ED D A N D A ING
COND IT P OVIDE ALL APP TENANCE FO A MM IDM

PLOT DATE
COMPLETE IN TALLATION COO DINATE ITH CHEC ED
T CT AL
JO
I510A
L

JL
29475
F
XLS XLS
PLC-800 PLC-800
Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-13
13:24:46 9:06:08 AM Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-13
13:24:46 9:06:08 AM
COMPONENT I/O LIST COMPONENT I/O LIST
CONTROLLER ISA CONTROLLER ISA NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS BUILDING 900 SERIES
800 SERIES
DI - 0 YA CP-8000 Rack 0 DI Card 4 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 0 DI - 95 0 9 15 NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES
DI - 1 YA CP-8000 Rack 1 DO Card 2 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 1 DI - 96 YA CP-8000 Rack 0 DI Card 10 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 10 0
DI - 2 YA CP-8000 Rack 1 DO Card 3 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 2 DI - 97 ZSO VFC-808 Recirc. Sludge Return Valve - Open Digester Building Basement 1 = OPEN 0 10 1
DI - 3 YA CP-8000 Rack 1 DO Card 4 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 3 DI - 98 ZSC VFC-808 Recirc. Sludge Return Valve - Closed Digester Building Basement 1 = CLOSED 0 10 2 NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
700 SERIES (PHASE B)
DI - 4 YA CP-8000 Rack 1 DO Card 5 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 4 DI - 99 HS MAU-801 Digester Bldg. Make-Up Air Unit - In Auto Digester Building Roof 1 = IN-AUTO 0 10 3 600 SERIES (PHASE B)

DI - 5 YA CP-8000 Rack 1 AI Card 6 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 5 DI - 100 YA MAU-801 Digester Bldg. Make-Up Air Unit - Fault Digester Building Roof 0 = FAULT 0 10 4
DI - 6 YA CP-8000 Rack 1 AI Card 7 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 6 DI - 101 YS MAU-801 Digester Bldg. Make-Up Air Unit - Running Digester Building Roof 1 = RUNNING 0 10 5
DI - 7 YA CP-8000 Rack 1 AI Card 8 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 7 DI - 102 YA MAU-801 Digester Bldg. Make-Up Air Unit - Disconnect Open Digester Building Roof 0 = ALARM 0 10 6 EXISTING SERVICE
BUILDING
DI - 8 YA CP-8000 Rack 1 AI Card 9 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 8 DI - 103 HS P-815 Digester Glycol Heating Pump - In Auto Digester Building Basement 1 = IN-AUTO 0 10 7 300 SERIES

DI - 9 YA CP-8000 Rack 1 AI Card 10 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 9 DI - 104 YA P-815 Digester Glycol Heating Pump - Fault Digester Building Basement 0 = FAULT 0 10 8
DI - 10 YA CP-8000 Rack 1 AI Card 11 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 10 DI - 105 YS P-815 Digester Glycol Heating Pump - Running Digester Building Basement 1 = RUNNING 0 10 9
DI - 11 YA CP-8000 Rack 1 AO Card 12 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 11 DI - 106 YA P-815 Digester Glycol Heating Pump - Disconnect Open Digester Building Basement 0 = ALARM 0 10 10 KEY PLAN

DI - 12 YA CP-8000 Rack 1 AO Card 13 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 12 DI - 107 YA P-815 Digester Glycol Heating Pump - E-Stop Digester Building Basement 0 = ALARM 0 10 11
DI - 13 YA CP-8000 Rack 1 AO Card 14 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 4 13 DI - 108 HS P-408 Ferric Sulfate Metering Pump - In Auto Ferric Sulphate Storage Room 1 = AUTO 0 10 12 GENERAL NOTES:
DI - 14 YA SPD-802 SPD-802 (LP-802) Alarm New Digester Building Electrical Room 0 = ALARM 0 4 14 DI - 109 YA P-408 Ferric Sulfate Metering Pump - Fault Ferric Sulphate Storage Room 0 = FAULT 0 10 13
A. AMOUNT AND LOCATION OF INTERPOSING RELAYS,
DI - 15 YA SPD-890 SPD-890 (UP-890) Alarm New Digester Building Electrical Room 0 = ALARM 0 4 15 DI - 110 YS P-408 Ferric Sulfate Metering Pump - Running Ferric Sulphate Storage Room 1 = RUNNING 0 10 14 INTRINSICALLY SAFE BARRIERS, SIGNAL SPLITTERS,
DI - 16 YA CP-8000 Rack 0 DI Card 5 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 5 0 DI - 111 YA P-408 Ferric Sulfate Metering Pump - Leak Ferric Sulphate Storage Room 0 = ALARM 0 10 15 AND ISOLATION MODULES TBD.

DI - 17 YA SPD-900 SPD-900 (LP-900) Alarm Gate Control Panel 0 = ALARM 0 5 1 DI - 112 YA CP-8000 Rack 0 DI Card 11 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 11 0
DI - 18 YA UPS-890 UPS AC Line Failure New Digester Building I&C Room 0 = FAILURE 0 5 2 DI - 113 ZSO VFC-809 Recirc. Sludge Return Valve - Open Existing Control Building 1 = OPEN 0 11 1
DI - 19 YA UPS-890 UPS Battery Low New Digester Building I&C Room 0 = LOW 0 5 3 DI - 114 ZSC VFC-809 Recirc. Sludge Return Valve - Closed Existing Control Building 1 = CLOSED 0 11 2
DI - 20 YA UPS-890 UPS Alarm New Digester Building I&C Room 0 = ALARM 0 5 4 DI - 115 HS OCU-801 Digester Bldg. Odour Control Unit - In Auto Digester Building 1 = IN-AUTO 0 11 3
DI - 21 YA UPS-890 UPS On Bypass New Digester Building I&C Room 0 = BYPASS 0 5 5 DI - 116 YA OCU-801 Digester Bldg. Odour Control Unit - Fault Digester Building 0 = FAULT 0 11 4
DI 22 YA SD-8001 Digester Waste Bin Smoke Detector Alarm Digester Waste Bin Room 0 = ALARM 0 5 6 Provide interposing relay to suit DI - 117 YS OCU-801 Digester Bldg. Odour Control Unit - Running Digester Building 1 = RUNNING 0 11 5
DI - 23 YA SD-8002 Digester Electrical Room Smoke Detector Alarm Digester Electrical Room 0 = ALARM 0 5 7 Provide interposing relay to suit DI - 118 YA OCU-801 Digester Bldg. Odour Control Unit - Disconnect Open Digester Building 0 = ALARM 0 11 6
DI - 24 YA SD-8003 Digester I&C Room Smoke Detector Alarm Digester I&C Room 0 = ALARM 0 5 8 Provide interposing relay to suit DI - 119 HS P-818 Digester Heating Loop Pump - In Auto Digester Building Basement 1 = IN-AUTO 0 11 7
DI - 25 YA SD-8004 Digester Ferric Sulphate Stor. Room Smoke Detector Alarm Ferric Sulphate Storage Room 0 = ALARM 0 5 9 Provide interposing relay to suit DI - 120 YA P-818 Digester Heating Loop Pump - Fault Digester Building Basement 0 = FAULT 0 11 8
DI - 26 YA SD-8005 Digester Sample Room Smoke Detector Alarm Digester Sample Room 0 = ALARM 0 5 10 Provide interposing relay to suit DI - 121 YS P-818 Digester Heating Loop Pump - Running Digester Building Basement 1 = RUNNING 0 11 9
DI - 27 YA SD-8006 Digester Building Basement Smoke Detector Alarm Digester Building Basement 0 = ALARM 0 5 11 Provide interposing relay to suit DI - 122 YA P-818 Digester Heating Loop Pump - Disconnect Open Digester Building Basement 0 = ALARM 0 11 10
DI - 28 YA SD-8007 Digester Building Process Area Smoke Detector Alarm Digester Building Process Area 0 = ALARM 0 5 12 Provide interposing relay to suit DI - 123 YA P-818 Digester Heating Loop Pump - E-Stop Digester Building Basement 0 = ALARM 0 11 11
DI - 29 YA SD-8008 Digester Building Process Area Smoke Detector Alarm Digester Building Process Area 0 = ALARM 0 5 13 Provide interposing relay to suit DI - 124 HS P-409 Ferric Sulfate Metering Pump - In Auto Ferric Sulphate Storage Room 1 = AUTO 0 11 12
DI - 30 YA SD-8009 Digester Building Process Area Smoke Detector Alarm Digester Building Process Area 0 = ALARM 0 5 14 Provide interposing relay to suit DI - 125 YA P-409 Ferric Sulfate Metering Pump - Fault Ferric Sulphate Storage Room 0 = FAULT 0 11 13
DI - 31 YA SPD-800 SPD-800 (MCC-800) Alarm New Digester Building Electrical Room 0 5 15 DI - 126 YS P-409 Ferric Sulfate Metering Pump - Running Ferric Sulphate Storage Room 1 = RUNNING 0 11 14
DI - 32 YA CP-8000 Rack 0 DI Card 6 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 6 0 DI - 127 YA P-409 Ferric Sulfate Metering Pump - Leak Ferric Sulphate Storage Room 0 = ALARM 0 11 15
DI - 33 YA P-807 Digester Sludge Recirc Pump #3 - Fault Digester Building Basement 0 = FAULT 0 6 1 DI - 128 YA CP-8000 Rack 0 DI Card 12 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 12 0
DI - 34 HS P-807 Digester Sludge Recirc Pump #3 - In-Auto Digester Building Basement 1 = IN-AUTO 0 6 2 DI - 129 LAH LSH-8016 Digester Sanitary Pump #1 High Level Digester Building 0 = ALARM 0 12 1
DI - 35 YS P-807 Digester Sludge Recirc Pump #3 - Running Digester Building Basement 1 = RUNNING 0 6 3 DI - 130 LAH LSH-8017 Digester Sanitary Pump #2 High Level Digester Building 0 = ALARM 0 12 2
DI - 36 YA P-807 Digester Sludge Recirc Pump #3 - Disconnect Open Digester Building Basement 0 = ALARM 0 6 4 DI - 131 LAL LSL-8016 Digester Sanitary Pump #1 Low Level Digester Building 0 = ALARM 0 12 3
DI - 37 HS P-811 Centrate Transfer Pump #1 - In Auto Centrate Storage Tank 1 = IN-AUTO 0 6 5 DI - 132 LAL LSL-8017 Digester Sanitary Pump #2 Low Level Digester Building 0 = ALARM 0 12 4
DI - 38 YA P-811 Centrate Transfer Pump #1 - Fault Centrate Storage Tank 0 = FAULT 0 6 6 DI - 133 LAH LSH-8019 Digester Tank High Level Float Digester Tank 0 = ALARM 0 12 5
DI - 39 YS P-811 Centrate Transfer Pump #1 - Running Centrate Storage Tank 1 = RUNNING 0 6 7 DI - 134 LAHH LSHH-8051 Digester Sump Pit High High Level (Float) Digester Basement 0 = ALARM 0 12 6
DI - 40 YA P-811 Centrate Transfer Pump #1 - Disconnect Open Centrate Storage Tank 0 = ALARM 0 6 8 DI - 135 LAHH PSH-8031 Sludge Holding Tank High High Level Sludge Mixing Tank 0 = ALARM 0 12 7
DI - 41 HS MIX-801 Sludge Holding Tank Mixer - In Auto Sludge Mixing Tank 1 = IN-AUTO 0 6 9 DI - 136 LALL PSL-8032 Sludge Holding Tank Low Low Level Sludge Mixing Tank 0 = ALARM 0 12 8
DI - 42 YA MIX-801 Sludge Holding Tank Mixer - Fault Sludge Mixing Tank 0 = FAULT 0 6 10 DI - 137 LAHH PSH-8033 Centrate Tank High Level Centrate Storage Tank 0 = ALARM 0 12 9
DI - 43 YS MIX-801 Sludge Holding Tank Mixer - Running Sludge Mixing Tank 1 = RUNNING 0 6 11 DI - 138 LALL PSL-8034 Centrate Tank Low Level Centrate Storage Tank 0 = ALARM 0 12 10 1 PHASE A - ADDENDUM #3 10/11/23

DI - 44 YA MIX-801 Sludge Holding Tank Mixer - Disconnect Open Sludge Mixing Tank 0 = ALARM 0 6 12 DI - 139 YA FDP-8001 Digester Fire Detection Panel Alarm Digester Electrical Room 0 = ALARM 0 12 11 Provide interposing relay to suit
0 PHASE A ISSUED FOR TENDER 02/10/23
DI - 45 AAY AIT-8300 Sample Room H2S Analyzer - Fault Sample Room 0 = ALARM 0 6 13 Provide interposing relay to suit DI - 140 YA FDP-8001 Digester Fire Detection Panel Alarm Digester Electrical Room 0 = ALARM 0 12 12 Provide interposing relay to suit
DI - 46 AAY AIT-8300 Sample Room H2S Analyzer - Alarm Sample Room 0 = ALARM 0 6 14 Provide interposing relay to suit DI - 141 0 12 13 No. ISSUE / REVISION DD/MM/YY

DI - 47 AAY AIT-8300 Sample Room H2S Analyzer - Warning Sample Room 0 = ALARM 0 6 15 Provide interposing relay to suit DI - 142 0 12 14
This drawing is copyright protected and may not be reproduced or
DI - 48 YA CP-8000 Rack 0 DI Card 7 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 7 0 DI - 143 0 12 15 used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.
DI - 49 YA P-808 Digester Sludge Recirc Pump #4 - Fault Digester Building Basement 0 = FAULT 0 7 1 DI - 144 YA CP-8000 Rack 0 DI Card 13 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 13 0
DI - 50 HS P-808 Digester Sludge Recirc Pump #4 - In-Auto Digester Building Basement 1 = IN-AUTO 0 7 2 DI - 145 ZSO VFC-820 Sludge Holding Tank Inlet Control Valve - Open Digester Building Basement 1 = OPEN 0 13 1 VERIFY SHEET SIZE AND SCALES. BAR TO THE
RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
DI - 51 YS P-808 Digester Sludge Recirc Pump #4 - Running Digester Building Basement 1 = RUNNING 0 7 3 DI - 146 ZSC VFC-820 Sludge Holding Tank Inlet Control Valve - Closed Digester Building Basement 1 = CLOSED 0 13 2
SCALE:
N.T.S.
DI - 52 YA P-808 Digester Sludge Recirc Pump #4 - Disconnect Open Digester Building Basement 0 = ALARM 0 7 4 DI - 147 HS VFC-820 Sludge Holding Tank Inlet Control Valve - In Auto Digester Building Basement 1 = IN-AUTO 0 13 3
DI - 53 HS P-812 Centrate Transfer Pump #2 - In Auto Centrate Storage Tank 1 = IN-AUTO 0 7 5 DI - 148 YA VFC-820 Sludge Holding Tank Inlet Control Valve - Fault Digester Building Basement 0 = FAULT 0 13 4
DI - 54 YA P-812 Centrate Transfer Pump #2 - Fault Centrate Storage Tank 0 = FAULT 0 7 6 DI - 149 YA P-816 Digester Sanitary Sump Pump #1 - Alarm Digester Building Basement 0 = ALARM 0 13 5
CLIENT:
DI - 55 YS P-812 Centrate Transfer Pump #2 - Running Centrate Storage Tank 1 = RUNNING 0 7 7 DI - 150 YA TC-8034 Flame Arrestor Heat Trace Piping New Digester Building Roof 0 = ALARM 0 13 6
DI - 56 YA P-812 Centrate Transfer Pump #2 - Disconnect Open Centrate Storage Tank 0 = ALARM 0 7 8 DI - 151 YA VFC-941 Ferric Sulfate Tank Isolation Valve - Fault Ferric Sulfate Storage Room 0 = FAULT 0 13 7
DI - 57 YA MIX-803 Digester Tank Mixer - Fault Digester Tank 0 = FAULT 0 7 9 DI - 152 HS VFC-941 Ferric Sulfate Tank Isolation Valve - In Auto Ferric Sulfate Storage Room 1 = IN-AUTO 0 13 8
DI - 58 HS MIX-803 Digester Tank Mixer - In-Auto Digester Tank 1 = IN-AUTO 0 7 10 DI - 153 ZSO VFC-941 Ferric Sulfate Tank Isolation Valve - Open Ferric Sulfate Storage Room 1 = OPEN 0 13 9
DI - 59 YS MIX-803 Digester Tank Mixer - Running Digester Tank 1 = RUNNING 0 7 11 DI - 154 ZSC VFC-941 Ferric Sulfate Tank Isolation Valve - Closed Ferric Sulfate Storage Room 1 = CLOSED 0 13 10
DI - 60 YA MIX-803 Digester Tank Mixer - Disconnect Open Digester Tank 0 = ALARM 0 7 12 DI - 155 0 13 11 CONSULTANT: www.jlrichards.ca
DI - 61 AAY AIT-8301 Sample Room CH4 Analyzer - Fault Sample Room 0 = ALARM 0 7 13 Provide interposing relay to suit DI - 156 0 13 12
DI - 62 AAY AIT-8301 Sample Room CH4 Analyzer - Alarm Sample Room 0 = ALARM 0 7 14 Provide interposing relay to suit DI - 157 0 13 13
DI - 63 AAY AIT-8301 Sample Room CH4 Analyzer - Warning Sample Room 0 = ALARM 0 7 15 Provide interposing relay to suit DI - 158 0 13 14
DI - 64 YA CP-8000 Rack 0 DI Card 8 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 8 0 DI - 159 0 13 15
DI - 65 YA P-809 Digester Hot Water Recirc Pump - Fault Digester Building Basement 0 = FAULT 0 8 1 DI - 160 YA CP-8000 Rack 0 DI Card 14 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 14 0
DI - 66 HS P-809 Digester Hot Water Recirc Pump - In-Auto Digester Building Basement 1 = IN-AUTO 0 8 2 DI - 161 0 14 1 CONSULTANT:

DI - 67 YS P-809 Digester Hot Water Recirc Pump - Running Digester Building Basement 1 = RUNNING 0 8 3 DI - 162 0 14 2
DI - 68 YA P-809 Digester Hot Water Recirc Pump - Disconnect Open Digester Building Basement 0 = ALARM 0 8 4 DI - 163 0 14 3
DI - 69 YA TC-8020 Flare Gas Valve Heat Trace Piping New Digester Building Roof 0 = ALARM 0 8 5 DI - 164 0 14 4
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 IO List.dwg

DI - 70 YA TC-8030 Digester Gas Heat Trace Piping New Digester Building Roof 0 = ALARM 0 8 6 DI - 165 0 14 5
DI - 71 YA TC-8032 Flare Drain Heat Trace Piping New Digester Building Roof 0 = ALARM 0 8 7 DI - 166 0 14 6
PROFESSIONAL STAMP PROJECT NORTH
DI - 72 YA TC-8050 Storm Drain Heat Trace Piping Storm Drain 0 = ALARM 0 8 8 DI - 167 0 14 7
DI - 73 BA FCP-8050 Flare Pilot CP - Burner Alarm Digester Building Process Area 0 = ALARM 0 8 9 DI - 168 0 14 8
DI - 74 PAH FCP-8050 Flare Pilot CP - Waste Gas Flare High Pressure Digester Building Process Area 0 = ALARM 0 8 10 DI - 169 0 14 9
DI - 75 PAH FCP-8050 Flare Pilot CP - Flare High Pressure Digester Building Process Area 0 = ALARM 0 8 11 DI - 170 0 14 10
DI - 76 YA FS-8052 Eye Wash Station Flow Alarm Chemical Fill Station 0 = ALARM 0 8 12 DI - 171 0 14 11
DI - 77 YA FS-8053 Eye Wash Station Flow Alarm Ferric Sulphate Storage Room 0 = ALARM 0 8 13 DI - 172 0 14 12
DI - 78 YA FS-8054 Eye Wash Station Flow Alarm Polymer Area 0 = ALARM 0 8 14 DI - 173 0 14 13
DI - 79 YA GFS-801 Glycol Fill Station Alarm Digester Building Basement 0 = ALARM 0 8 15 DI - 174 0 14 14
DI - 80 YA CP-8000 Rack 0 DI Card 9 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 9 0 DI - 175 0 14 15
PROJECT:
DI - 81 ZSO VFC-807 Digested Sludge to Hex Valve - Open Digester Building Basement 1 = OPEN 0 9 1 DI - 176 YA CP-8000 Rack 0 DI Card 14 24 VDC Failure Digester PLC Panel 0 = FAILURE 0 15 0
DI - 82 ZSC VFC-807 Digested Sludge to Hex Valve - Closed Digester Building Basement 1 = CLOSED 0 9 2 DI - 177 0 15 1
MUNICIPALITY OF NORTH
DI - 83 FAL FSL-8038 Glycol Loop Low Flow Digester Building Basement 0 = ALARM 0 9 3 DI - 178 0 15 2
GRENVILLE - WATER POLLUTION
DI - 84 FAL FSL-8040 Sample Room Exhaust Fan Low Flow Digester Building Basement 0 = ALARM 0 9 4 DI - 179 0 15 3 CONTROL PLANT EXPANSION
DI - 85 FAL FSL-8045 Digester Makeup Air Unit Flow Switch Digester Building Process Area 0 = ALARM 0 9 5 DI - 180 0 15 4 PHASE - A
DI - 86 FAL FSL-8046 Digester Odour Control Unit Flow Switch Digester Building 0 = ALARM 0 9 6 DI - 181 0 15 5 KEMPTVILLE, ONTARIO
DI - 87 LAL PSH-8010 New Prim. Digester Overflow Pressure Level Alarm Digester Tank 0 = ALARM 0 9 7 DI - 182 0 15 6 DRAWING:
DI - 88 PAH PSH-8018 Heat Exchanger Water Pressure High Alarm Digester Building Basement 0 = ALARM 0 9 8 DI - 183 0 15 7
ELECTRICAL

November 14, 2023 9:56:25 AM


DI - 89 TAHH TSHH-8014 Heat Exchanger Water Temperature High High Alarm New Digester Building Basement 0 = ALARM 0 9 9 DI - 184 0 15 8
DI - 90 LAH LSH-4021 Ferric Sulphate Tank Leak Detection Ferric Sulphate Storage Room 0 = ALARM 0 9 10 DI - 185 0 15 9
DIGESTER UPGRADES
DI - 91 LAH LSH-4022 Ferric Sulphate Pipe Sec. Leak Detection Ferric Sulphate Storage Room 0 = ALARM 0 9 11 DI - 186 0 15 10
DI - 92 LAH LSH-4023 Ferric Sulphate Tank Sec. Leak Detection Ferric Sulphate Storage Room 1 = ALARM 0 9 12 DI - 187 0 15 11
IO TABLE - PLC-800
DI - 93 LAH LS-4026 Ferric Sulphate Level Switch Ferric Sulphate Storage Room 0 = ALARM 0 9 13 Provide interposing relay to suit DI - 188 0 15 12
DI - 94 LAL LS-4026 Ferric Sulphate Level Switch Ferric Sulphate Storage Room 0 = ALARM 0 9 14 Provide interposing relay to suit DI - 189 0 15 13
DESIGN:
LO
1
1 DRAWN:
NB DRAWING #:

PLOT DATE:
1 IO LIST - PLC - 800 2 IO LIST (CONT'D) - PLC - 800 CHECKED:
I801A SCALE: NTS I801A SCALE: NTS
JLR #:
JO
29475
I801A
XLS XLS
PLC-800 PLC-800
Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-13
13:24:46 9:06:08 AM Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-13
13:24:46 9:06:08 AM
COMPONENT I/O LIST COMPONENT I/O LIST
CONTROLLER ISA CONTROLLER ISA NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS BUILDING 900 SERIES
800 SERIES
DI - 190 0 15 14 AI - 29 LI LIT-8035 Centrate Tank Level Indicator Centrate Storage Tank 1 9 5 NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES
DI - 191 0 15 15 AI - 30 1 9 6
DO - 0 YC P-807 Digester Sludge Recirc Pump #3 - Run Digester Building Basement 1 = RUN 0 2 0 Provide interposing relay to suit AI - 31 1 9 7
DO - 1 YC P-811 Centrate Transfer Pump #1 - Run Centrate Storage Tank 1 = RUN 0 2 1 Provide interposing relay to suit AI - 32 ZI VFC-810 Sludge Hex Hot Water Position Status Centrate Storage Tank 1 10 0 NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
700 SERIES (PHASE B)
DO - 2 ZC VFC-807 Digested Sludge to Hex Valve - Drive Open Digester Building Basement 1 = OPEN 0 2 2 Provide interposing relay to suit AI - 33 ZI VFC-824 Digester Bldg. Heating Water Loop 3-Way Pos. Status Pipe Gallery 1 10 1 600 SERIES (PHASE B)

DO - 3 ZC VFC-807 Digested Sludge to Hex Valve - Drive Closed Digester Building Basement 1 = CLOSED 0 2 3 Provide interposing relay to suit AI - 34 ZI VFC-825 Heating Water Glycol Hex 3-Way Position Status Centrate Storage Tank 1 10 2
DO - 4 YC MIX-801 Sludge Holding Tank Mixer - Run Sludge Mixing Tank 1 = RUN 0 2 4 Provide interposing relay to suit AI - 35 ZI VFC-826 Sample Room Heating Coil Position Status Sample Room 1 10 3
DO - 5 YC MAU-801 Digester Bldg. Make-Up Air Unit - Run Digester Building Roof 1 = RUN 0 2 5 Provide interposing relay to suit AI - 36 ZI VFC-827 Ferric Sulfate Heating Coil Position Status Digester Building Process Area 1 10 4 EXISTING SERVICE
BUILDING
DO - 6 YC P-815 Digester Glycol Heating Pump - Run Digester Building Basement 1 = RUN 0 2 6 Provide interposing relay to suit AI - 37 ZI VFC-828 Digester MAU Glycol Heating Position Status Digester Building Process Area 1 10 5 300 SERIES

DO - 7 ZC P-408 Ferric Sulfate Metering Pump - Run Ferric Sulphate Storage Room 1 = RUN 0 2 7 Provide interposing relay to suit AI - 38 ZI VFC-845 3-Way Valve Existing Digester Building Pos. Status Existing Digester Building 1 10 6
DO - 8 ZC P-408 Ferric Sulfate Metering Pump - Fwd./Rev Ferric Sulphate Storage Room 1 = FWD 0 2 8 Provide interposing relay to suit AI - 39 ZI VFC-846 Polymer Heat Exchange Valve Pos. Status Digester Building 1 10 7
DO - 9 ZC VFC-820 Sludge Holding Tank Inlet Control Valve - Drive Open Digester Building Basement 1 = OPEN 0 2 9 Provide interposing relay to suit AI - 40 1 11 0 KEY PLAN

DO - 10 ZC VFC-820 Sludge Holding Tank Inlet Control Valve - Drive Closed Digester Building Basement 1 = CLOSED 0 2 10 Provide interposing relay to suit AI - 41 1 11 1
GENERAL NOTES:
DO - 11 YA LCP-4019 Ferric Sulphate Tank Stack Light - Horn Silence Digester Building 0 = SILENCE 0 2 11 Provide interposing relay to suit AI - 42 1 11 2
DO - 12 UAL LCP-4019 Ferric Sulphate Tank Stack Light - Red Light and Horn (Alarm) Digester Building 1 = ON 0 2 12 Provide interposing relay to suit AI - 43 1 11 3 A. AMOUNT AND LOCATION OF INTERPOSING RELAYS,
INTRINSICALLY SAFE BARRIERS, SIGNAL SPLITTERS,
DO - 13 UAL LCP-4019 Ferric Sulphate Tank Stack Light - Amber Light (Warning) Digester Building 1 = ON 0 2 13 Provide interposing relay to suit AI - 44 1 11 4 AND ISOLATION MODULES TBD.
DO 14 0 2 14 Provide interposing relay to suit AI - 45 1 11 5
B. REFER TO DETAIL 1/I022A FOR THE REQUIRED
DO - 15 0 2 15 Provide interposing relay to suit AI - 46 1 11 6 HARDWIRED LOGIC FOR CONTROLLING THE
DO - 16 YC P-808 Digester Sludge Recirc Pump #4 - Run Digester Building Basement 1 = RUN 0 3 0 Provide interposing relay to suit AI - 47 1 11 7 ASSOCIATED STACK LIGHTS AND HORNS.

DO - 17 YC P-812 Centrate Transfer Pump #2 - Run Centrate Storage Tank 1 = RUN 0 3 1 Provide interposing relay to suit AO - 0 SC P-408 Ferric Sulfate Pump Speed Control Ferric Sulphate Storage Room 1 12 0
DRAWING NOTES:
DO - 18 ZC VFC-808 Recirc. Sludge Return Valve - Drive Open Digester Building Basement 1 = OPEN 0 3 2 Provide interposing relay to suit AO - 1 SC P-807 Digester Sludge Recirc Pump #3 Speed Control Digester Building Basement 1 12 1
DO - 19 ZC VFC-808 Recirc. Sludge Return Valve - Drive Closed Digester Building Basement 1 = CLOSED 0 3 3 Provide interposing relay to suit AO - 2 SC P-811 Centrate Transfer Pump #1 Speed Control Centrate Storage Tank 1 12 2 1 PROGRAM THE PLC TO PROVIDE A WATCHDOG
PULSE. THIS PULSE IS TO BE MONITORED BY THE
DO - 20 YC MIX-803 Digester Tank Mixer - Run Digester Tank 1 = RUN 0 3 4 Provide interposing relay to suit AO - 3 ZC MAU-801 Digester Make-Up Air Unit Speed Control Digester Building Roof 1 12 3 WATCHDOG TIMING RELAY INSIDE THE PANEL.
DO - 21 YC OCU-801 Digester Bldg. Odour Control Uni - Run Outside Digester Building 1 = RUN 0 3 5 Provide interposing relay to suit AO - 4 1 12 4 COORDINATE PULSE WIDTH AND RELAY SELECTION
TO SUIT. THE INTENT OF THIS FEATURE IS TO
DO - 22 YC P-818 Digester Heating Loop Pump - Run Digester Building Basement 1 = RUN 0 3 6 Provide interposing relay to suit AO - 5 1 12 5 DETECT PLC FAILURE. PROVIDE HARD-WIRED LOGIC
DO - 23 ZC P-409 Ferric Sulfate Metering Pump - Run Ferric Sulphate Storage Room 1 = RUN 0 3 7 Provide interposing relay to suit AO - 6 1 12 6 INSIDE THE PLC PANEL TO ENERGIZE ALL STACK
LIGHTS AND ASSOCIATED HORNS CONNECTED TO
DO - 24 ZC P-409 Ferric Sulfate Metering Pump - Fwd./Rev Ferric Sulphate Storage Room 1 = FWD 0 3 8 Provide interposing relay to suit AO - 7 1 12 7
THIS PLC IN EVENT OF A PLC FAILURE. PROVIDE
DO - 25 ZC VFC-821 Polymer Water Supply Solenoid - Drive Open Digester Building Process Area 1 = OPEN 0 3 9 Provide interposing HOA relay to suit AO - 8 SC P-409 Ferric Sulfate Pump Speed Control Ferric Sulphate Storage Room 1 13 0 LOGIC TO SILENCE THE HORNS VIA A FLUSH HEAD
PUSHBUTTON ON THE PLC PANEL DOOR. LABEL THE
DO - 26 ZC VFC-822 Sludge Conveyor #1 Wash Water - Drive Open Digester Building Waste Room 1 = OPEN 0 3 10 Provide interposing HOA relay to suit AO - 9 SC P-808 Digester Sludge Recirc Pump #4 Speed Control Digester Building Basement 1 13 1
PUSHBUTTON "SILENCE HORNS". PUSHBUTTON
DO - 27 YC LCP-4019 Ferric Sulphate Tank - High Level Alarm Ferric Sulphate Storage Room 1 = ALARM 0 3 11 Provide interposing relay to suit AO - 10 SC P-812 Centrate Transfer Pump #2 Speed Control Centrate Storage Tank 1 13 2 COLOUR TO BE BLUE. HORNS TO BE RE-TRIGGERED
EACH TIME THE PLC FAILS.
DO - 28 YC LCP-4019 Ferric Sulphate Tank - High Level Warning Ferric Sulphate Storage Room 1 = ALARM 0 3 12 Provide interposing relay to suit AO - 11 ZC OCU-801 Digester Odour Control Unit Speed Control Outside Digester Building 1 13 3
DO - 29 YC LCP-4019 Ferric Sulphate Tank - Horn Silence Ferric Sulphate Storage Room 1 = SILENCE 0 3 13 Provide interposing relay to suit AO - 12 1 13 4
DO - 30 0 3 14 Provide interposing relay to suit AO - 13 1 13 5
DO - 31 0 3 15 Provide interposing relay to suit AO - 14 1 13 6
DO - 32 YC P-809 Digester Hot Water Recirc Pump - Run Digester Building Basement 1 = RUN 1 4 0 Provide interposing relay to suit AO - 15 1 13 7
DO - 33 ZC VFC-809 Recirc. Sludge Return Valve - Drive Open Digester Building Basement 1 = OPEN 1 4 1 Provide interposing relay to suit AO - 16 ZC VFC-810 Sludge Hex Hot Water Position Control Centrate Storage Tank 1 14 0
DO - 34 ZC VFC-809 Recirc. Sludge Return Valve - Drive Closed Digester Building Basement 1 = CLOSED 1 4 2 Provide interposing relay to suit AO - 17 ZC VFC-824 Digester Bldg. Heating Water Loop 3-Way Pos. Control Pipe Gallery 1 14 1
DO - 35 ZC VFC-941 Ferric Sulfate Tank Isolation Valve - Drive Open Ferric Sulphate Storage Room 1 = OPEN 1 4 3 Provide interposing relay to suit AO - 18 ZC VFC-825 Heating Water Glycol Hex 3-Way Position Control Centrate Storage Tank 1 14 2
DO - 36 ZC VFC-941 Ferric Sulfate Tank Isolation Valve - Drive Closed Ferric Sulphate Storage Room 1 = CLOSED 1 4 4 Provide interposing relay to suit AO - 19 ZC VFC-826 Sample Room Heating Coil Position Control Sample Room 1 14 3
DO - 37 ZC VFC-840 Centrifuge Effluent Water Control - Drive Open Digester Building Process Area 1 = OPEN 1 4 5 Provide interposing relay to suit AO - 20 ZC VFC-827 Ferric Sulfate Heating Coil Position Control Digester Building Process Area 1 14 4
DO - 38 YA YA-8200 Digester Stack Light - Horn Digester Building 1 = ON 1 4 6 Provide interposing relay to suit AO - 21 ZC VFC-828 Digester MAU Glycol Heating Position Control Digester Building Process Area 1 14 5
DO - 39 UAL UAL-8201 Digester Stack Light - Red Digester Building 1 = ON 1 4 7 Provide interposing relay to suit AO - 22 ZC VFC-845 3-Way Valve Existing Digester Building Pos. Control Existing Digester Building 1 14 6
DO - 40 UAL UAL-8202 Digester Stack Light - Amber Digester Building 1 = ON 1 4 8 Provide interposing relay to suit AO - 23 ZC VFC-846 Polymer Heat Exchange Valve Pos. Control Digester Building 1 14 7
DO - 41 UAL UAL-8203 Digester Stack Light - Clear Digester Building 1 = ON 1 4 9 Provide interposing relay to suit 1 PHASE A - ADDENDUM #3 10/11/23

DO - 42 UAL UAL-8204 Digester Stack Light - Blue Digester Building 1 = ON 1 4 10 Provide interposing relay to suit
0 PHASE A ISSUED FOR TENDER 02/10/23
DO - 43 1 4 11 Provide interposing relay to suit 1
DO - 44 1 4 12 Provide interposing relay to suit 1 IO TABLE CONT'D - PLC - 800 No. ISSUE / REVISION DD/MM/YY

DO - 45 1 4 13 Provide interposing relay to suit SCALE: NTS


I802A This drawing is copyright protected and may not be reproduced or
DO - 46 1 4 14 Provide interposing relay to suit used for purposes other than execution of the described work without
the express written consent of J.L. Richards & Associates Limited.
1 DO - 47 YS CP-8000 PLC Watchdog Pulse 1 4 15 Provide interposing relay to suit XLS

DO - 48 1 5 0 Provide interposing relay to suit VERIFY SHEET SIZE AND SCALES. BAR TO THE
Excel Sheet Data Exported on: 2017-07-11 11:25:22 AM
COMPONENT SUMMARY RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
DO - 49 1 5 1 Provide interposing relay to suit
SLOT CATALOG IO IO SCALE:
N.T.S.
DO - 50 1 5 2 Provide interposing relay to suit NUMB. NUMBER MANUFACTURER DESCRIPTION IO TYPE RACK COUNT COMMENTS
DO - 51 1 5 3 Provide interposing relay to suit 0 1756-A17 AB/RA 17 Slot ControlLogix Chassis Miscellaneous 0 0
DO - 52 1 5 4 Provide interposing relay to suit
0 1756-PB75 AB/RA 24VDC Power Supply (13A @ 5V) Miscellaneous 0 0 CLIENT:
DO - 53 1 5 5 Provide interposing relay to suit
0 1756-L84E AB/RA ControlLogix Processor with 20MB NV Memory Processor 0 0
DO - 54 1 5 6 Provide interposing relay to suit
0 1784-SD2 AB/RA 2Gb Secure Digital Memory Card Miscellaneous 0 0
DO - 55 1 5 7 Provide interposing relay to suit
1 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 0 0
DO - 56 1 5 8 Provide interposing relay to suit
2 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 0 0 Used for direction connection to Rack 1.
DO - 57 1 5 9 Provide interposing relay to suit
3 1756-N2 AB/RA Slot Filler Miscellaneous 0 0
DO - 58 1 5 10 Provide interposing relay to suit CONSULTANT: www.jlrichards.ca
4 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
DO - 59 1 5 11 Provide interposing relay to suit
5 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
DO - 60 1 5 12 Provide interposing relay to suit
6 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
DO - 61 1 5 13 Provide interposing relay to suit
DO - 62 1 5 14 Provide interposing relay to suit 7 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block

DO - 63 1 5 15 Provide interposing relay to suit 8 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block

AI - 0 AI AIT-8300 Sample Room H2S Analyzer Indicator Sample Room 1 6 0 9 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block CONSULTANT:

AI - 1 SI P-807 Digester Sludge Recirc Pump #3 Speed Indicator Digester Building Basement 1 6 1 Provide analog signal duplicator 10 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
AI - 2 SI P-811 Centrate Transfer Pump #1 Speed Indicator Centrate Storage Tank 1 6 2 Provide analog signal duplicator 11 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
AI - 3 SI MAU-801 Digester Make-Up Air Unit Speed Indicator Digester Building Roof 1 6 3 12 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 IO List.dwg

AI - 4 SI P-408 Ferric Sulfate Pump Speed Indicator Ferric Sulphate Storage Room 1 6 4 13 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
AI - 5 FI FIT-8036 Centrate Flow Indicator Digester Building Process Area 1 6 5 14 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block
PROFESSIONAL STAMP PROJECT NORTH
AI - 6 FI FIT-8102 Digester Gas Flow Indicator Digester Building 1 6 6 15 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 0 16 Provide 1756-TBCH Screw Clamp Block
AI - 7 PI PIT-8020 Primary Digester Pressure Indicator Existing Digester Building Roof 1 6 7 16 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 0 16 Provide 1756-TBCH Screw Clamp Block
AI - 8 AI AIT-8301 Sample Room CH4 Analyzer Indicator Sample Room 1 7 0 0 1756-A17 AB/RA 17 Slot ControlLogix Chassis Miscellaneous 1 0
AI - 9 SI P-808 Digester Sludge Recirc Pump #4 Speed Indicator Digester Building Basement 1 7 1 Provide analog signal duplicator
0 1756-PB75 AB/RA 24VDC Power Supply (13A @ 5V) Miscellaneous 1 0
AI 10 SI P-812 Centrate Transfer Pump #2 Speed Indicator Centrate Storage Tank 1 7 2 Provide analog signal duplicator
1 1756-EN2T AB/RA EtherNet/IP 10/100 Mbps Bridge Module (128 TCP) Network Card 1 0 Used for direct connection to Rack 0.
AI - 11 SI OCU-801 Digester Odour Control Unit Speed Indicator Outside Digester Building 1 7 3
2 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 1 16 Provide 1756-TBCH Screw Clamp Block
AI - 12 SI P-409 Ferric Sulfate Pump Speed Indicator Ferric Sulphate Storage Room 1 7 4
3 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 1 8 Provide 1756-TBCH Screw Clamp Block
AI - 13 1 7 5
4 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 1 8 Provide 1756-TBCH Screw Clamp Block
AI - 14 1 7 6
5 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 1 8 Provide 1756-TBCH Screw Clamp Block PROJECT:
AI - 15 1 7 7
AI - 16 TI TIT-8012 Heat Exch. Sludge Temperature Indicator Digester Building Basement 1 8 0
6 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 1 8 Provide 1756-TBCH Screw Clamp Block MUNICIPALITY OF NORTH
AI - 17 TI TIT-8013 Heat Exch. Water Temperature Indicator Digester Building Basement 1 8 1
7 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 1 8 Provide 1756-TBCH Screw Clamp Block GRENVILLE - WATER POLLUTION
AI - 18 TI TIT-8015 Digester Electrical Room Temperature Indicator Digester Building Electrical Room 1 8 2
8 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 1 8 Provide 1756-TBCH Screw Clamp Block CONTROL PLANT EXPANSION
9 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 1 8 Provide 1756-TBCH Screw Clamp Block
AI - 19 TI TIT-8016 Digester Electrical Room Temperature Indicator Digester Building Electrical Room 1 8 3 PHASE - A
AI - 20 TI TIT-8037 Digester Bldg. Hot Water Supply Temperature Indicator Digester Building Basement 1 8 4 10 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 1 8 Provide 1756-TBCH Screw Clamp Block KEMPTVILLE, ONTARIO
AI - 21 TI TT-8042 Ferric Sulfate Room Supply Air Temperature Indicator Digester HVAC 1 8 5 11 1756-OF8I AB/RA Isolated Analog Output Module Analog Output 1 8 Provide 1756-TBCH Screw Clamp Block
DRAWING:
AI 22 TI TIT-8043 Sample Room Exhaust Air Temperature Indicator Sample Room 1 8 6 12 1756-N2 AB/RA Slot Filler Miscellaneous 1 0
ELECTRICAL

November 14, 2023 9:50:13 AM


AI - 23 TI TT-8044 Digester MAU Supply Air Temperature Indicator Digester Building Process Area 1 8 7 13 1756-N2 AB/RA Slot Filler Miscellaneous 1 0
AI - 24 TI TIT-8045 Polymer Service Water Digester Building Process Area 1 9 0 14 1756-N2 AB/RA Slot Filler Miscellaneous 1 0
DIGESTER UPGRADES
AI - 25 TI FCP-8050 Flare Pilot CP - Flare Pilot Temperature Digester Building Process Area 1 9 1 15 1756-N2 AB/RA Slot Filler Miscellaneous 1 0 COMPONENT LIST & IO TABLES
AI - 26 LI LIT-4026 Ferric Sulfate Tank Level Indicator Ferric Sulphate Storage Room 1 9 2 Provide analog signal duplicator 16 1756-N2 AB/RA Slot Filler Miscellaneous 1 0 CONT'D - PLC-800
AI - 27 LI LIT-8011 New Primary Digester Level Indicator Digester Building Basement 1 9 3
AI - 28 LI LIT-8030 Sludge Holding Tank Level Indicator Sludge Holding Tank 1 9 4
DESIGN:
1 LO
1 DRAWN: DRAWING #:
NB

PLOT DATE:
1 IO TABLE CONT'D - PLC - 800 2 COMPONENT LIST - PLC - 800 CHECKED:
I802A SCALE: NTS I802A SCALE: NTS
JLR #:
JO
29475
I802A
NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
BUILDING 900 SERIES
800 SERIES
NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
500 SERIES 400 SERIES 200 SERIES

9.A 9.B DP-901 NEW SECONDARY


CLARIFIERS
NEW TERTIARY
FILTER BUILDING
600 SERIES (PHASE B) 700 SERIES (PHASE B)

600 VOLT, 3Ø-3W


SURFACE MOUNTED
35kAIC
200 AMP MAIN BREAKER EXISTING SERVICE
BUILDING
300 SERIES

LOAD DESCRIPTION BRKR CCT CCT BRKR DESCRIPTION LOAD


1 2
GEN-001
GLOBAL-1000 SPARE 15A, 3P 3 4 20A, 3P SPARE KEY PLAN
5 6
7 8 DRAWING NOTES:
SPARE 15A, 3P 9 10 20A, 3P SPARE
9.2 11
13
12
14
1 COORDINATE EXACT BREAKER SIZE WITH SPD
MANUFACTURER.
SPARE 15A, 3P 15 16 20A, 3P SPARE
17 18 2 REFER TO DRAWING E004A FOR HEAT TRACE
TO REQUIREMENTS.
ATS-002 MCC-800
INCOMING
SPARE 15A, 3P
19
21
20
22 20A, 3P SPARE
GLOBAL-1000

A1
SWGR
GLOBAL-1000
ATS-001 23 24 3 INDOOR EVAPORATOR UNIT IS TO BE FED FROM THE
25 26 OUTDOOR UNIT. ELECTRICAL CONTRACTOR IS TO
LP-902-1.1 A1 SPARE 15A, 3P 27 28 60A, 3P TX-901 (LP-901) PROVIDE POWER AND CONTROL WIRING BETWEEN
29 30 THE OUTDOOR CONDENSING UNIT AND THE INDOOR
EVAPORATOR UNIT. WIRING TO BE RUN IN EMT
INDOORS; OCAL AND METALLIC LIQUID-TIGHT
TOTAL CONNECTED LOAD: __________ FLEXIBLE CONDUITS OUTDOORS. LENGTH OF
T SB-001 LIQUID-TIGHT CONDUITS NOT TO EXCEED 450mm.
ELECTRICAL GLOBAL-1000
PHASE LOAD TO BE FILLED IN BY CONTRACTOR: COORDINATE THE EXACT WIRING REQUIREMENTS
SERIVICE
GLOBAL

M LOAD PHASE A: LOAD PHASE B: LOAD PHASE C: WITH THE MANUFACTURER. SIZE POWER WIRING TO
EUH-901 ENTRANCE SD
DEVICE
LP-902-1.1 REMARKS
1000 SUIT. PROVIDE A DISCONNECT FOR EACH UNIT.
BUILDING 9011 1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED. NOTE: PROVIDE PADLOCKABLE CLASPS PROVIDE SEPARATE CONDUITS FOR POWER AND
GLOBAL-1000

LP-902-3 900 2. DEDICATED NEUTRAL FOR ALL BREAKERS PROVIDED. CONTROL WIRING. REFER TO DRAWING MID901A.
E 3. GFI
CP-9004 GEN-REPO

R-EBU-1 *
A1 4. LOCKED 4 REFER TO DETAIL 9/E006A AND MID901A FOR
E

GLOBAL-1000

GLOBAL-1000
5. ARC FAULT CIRCUIT INTERRUPTER REQUIRED CONTROLS. SF-901, MD-901 AND MD-902
TO BE ENERGIZED ONCE THE ELECTRICAL ROOM IS
SB-003B

SB-003B
LP-902-1.1 LP-902-1 A1 MD
GLOBAL-1000

OCCUPIED, I.E. THE LIGHTS ARE ON INSIDE THE ROOM.

RTD 5 PROVIDE A NEMA 4X SWITCH-RATED DISCONNECTING


GLOBAL-1000

DEVICE

TIT 60A, 120/208V, 3-PHASE+N+GND, 5-WIRE RECEPTACLE


GEN-ANUN

M
9010 GLOBAL
FOR PROVIDING SHORE POWER TO THE PORTABLE
DEVICE
M GENERATOR. PROCURE AND TURN OVER MATCHING
TC MD-902 PLUG TO THE MUNICIPALITY IN UN-OPENED
DEVICE

9010
1000

SD
1 LP-902-7 0001 PACKAGING. RECEPTACLE TO BE HUBBELL
3 DP-901 PANEL SCHEDULE HBLS560R9W SERIES, OR PRE-APPROVED
EQUIVALENT C/W MATCHING PLUG.
E911A SCALE: N.T.S.

A1 A1 6 REFER TO DRAWING E002A.

M LP-902-1.1 LP-902-1.1 7 FOR PRICING PURPOSES, CONTRACTOR TO ALLOW


FOR THE WIRING INDICATED ON DRAWING I300A.
LP-902 CONTRACTOR TO COORDINATE EXACT WIRING
REQUIREMENTS WITH THE GENERATOR
GLOBAL-1000
M LP-902-7 RTD 120/208 VOLT, 3Ø-4W
GLOBAL

DEVICE MANUFACTURER. PROVIDE RGS CONDUIT (PLUS NEMA


4
SB-003A TIT 4 PAINTED STEEL PULL BOXES) SIZED TO SUIT INSIDE
GLOBAL-1000

MD-901 SURFACE MOUNTED


1000
9030 GENERATOR ENCLOSURE AND ELECTRICAL SERVICE
LP-902-7 SB-002B SB-002A ELECTRICAL ROOM
DP-901

BUILDING TO COMPLETE ROUTING. PROVIDE DIRECT


GLOBAL GLOBAL-1000 GLOBAL-1000
225 MAINS 1 BURIED 103 mm PVC CONDUIT OUTDOORS.
M
SF-901 10 kAIC
1000

A1
GLOBAL-1000

LOAD DESCRIPTION BRKR CCT CCT BRKR DESCRIPTION LOAD


GLOBAL-1000

A1 1 PHASE A - ADDENDUM #3 10/11/23


LP-902

LTG. INTERIOR 15A,1P 1 2 15A,1P LTG. EXTERIOR


LP-902-1 RCPT. SERVICE 20A,1P 3 4 20A,1P RCPT. SERVICE *
SPD-901 TX-901

* RCPT. EXTERIOR 20A,1P 5 6 15A,1P SPARE 0 PHASE A ISSUED FOR TENDER 02/10/23
BD PC LP-902-2

LP-001
SF-901 SUPPLY FAN 15A,1P 7 8 15A,1P SPARE
SPARE 15A,1P 9 10 15A,1P SPARE

SPD-001
5 LP-902-1.1 No. ISSUE / REVISION DD/MM/YY
SPARE 20A,1P 11 12 15A,1P SPARE
GLOBAL-1000

GLOBAL-1000
LP-902-31/33/35 LP-902-4 WP/GFCI 7 SPARE 20A,1P 13 14 15A,1P SPARE
SPARE 15A,1P 15 16 15A,1P SPARE This drawing is copyright protected and may not be reproduced or

GLOBAL-1000
LP-902-5 SPARE 15A,1P 17 18 15A,1P HEAT TRACE - STRM DRN. (TC-9010) * used for purposes other than execution of the described work without
LP-902-5 2
UP-990

1 SPARE 15A,1P 19 20 15A,1P HEAT TRACE - AC COND. (TC-9011) * the express written consent of J.L. Richards & Associates Limited.
SPD-990

SPARE 15A,1P 21 22 15A,1P SPARE


EBU-1 SPARE 15A,1P 23 24 15A,1P SPARE VERIFY SHEET SIZE AND SCALES. BAR TO THE
SPARE 15A,1P 25 26 15A,1P SPARE RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
LP-902-1
JBP-001

GLOBAL-1000

A1 A1 27 28 15A,1P SPARE
E COOL. CND-901 (AC-901) 40A,2P SCALE:
PORTABLE 29 30 15A,1P SPARE AS INDICATED
GENERATOR LP-902-1.1 LP-902-1.1 31 32
GLOBAL-1000

E
CP-9000

SHORE POWER FOR PORTABLE GEN. 60A,3P 33 34 20A,3P EUH-901 ELECTRIC UNIT HEATER
CABINET
FBR/PLC

CONNECTION
LP-902-27/29 35 36 0 1 2 3 4m
GLOBAL-1000

GLOBAL

M LP-902-27/29 3 GLOBAL

M 37 38
AC-901 3 CLIENT:
DEVICE

TC
1000

CND-901 6 LP-001 GENERATOR PANEL 60A,3P 39 40 XXA,3P SPD-901 1


RS
LP-902-1.1 RS 1000

9011 T 41 42
GLOBAL-1000

9.1 RL RL
TOTAL CONNECTED LOAD: _________

PHASE LOAD TO BE FILLED IN BY CONTRACTOR:


O1 LOAD PHASE A: _________ LOAD PHASE B: _________ LOAD PHASE C: _________
LP-902-2 REMARKS
1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED.
CONSULTANT: www.jlrichards.ca
2. DEDICATED NEUTRAL
3. * GFI
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 ELECTRICAL SUBSTATION LAYOUT.dwg

4. LOCKED

4 LP-902 PANEL SCHEDULE


E911A SCALE: N.T.S.
CONSULTANT:

UP-990 LP-001

1 ELECTRICAL SERVICE ENTRANCE BUILDING PLAN 120/208 VOLT, 1PH, 3W, 60A BUS, 10KA 120/208 VOLT, 3Ø-4W
AS INDICATED
25 AMP MAIN BREAKER 60A MAIN BREAKER
E911A
SURFACE MOUNTED SURFACE MOUNTED
ELECTRICAL ROOM GEN-001
1 PROFESSIONAL STAMP PROJECT NORTH

GENERAL NOTES: LOAD DESCRIPTION BKR CCT CCT BKR DESCRIPTION LOAD LOAD DESCRIPTION BRKR CCT CCT BRKR DESCRIPTION LOAD
CP-9000 15A,1P 1 2 15A,1P SB-002A POWER MONITOR LIGHTING 15A,1P 1 2 20A,1P RCPT. SERVICE
A. ALL BURIED CONDUITS ARE CONCRETE ENCASED. SPARE 15A,1P 3 4 15A,1P SB-002B POWER MONITOR BATTERY CHARGER 15A,1P 3 4 15A,1P ENGINE BLOCK HEATER
5 6 15A,1P SPARE
SPARE 15A,1P 5 6 15A,1P SPARE
HEATER 15A,1P 7 8 15A,1P SPARE
B. COORDINATE CONCRETE ENCASED BEND RADIUS WITH STRUCTURAL FOUNDATION FORMING TO ENSURE FLOOR PENETRATIONS AS SPARE 15A,1P 7 8 15A,1P SPARE
9 10 15A,1P SPARE
INDICATED. SPARE 20A,1P 9 10 SPARE 15A,1P 11 12 15A,1P SPARE
XXA,1P SPD-990 1
SPARE 20A,1P 11 12 SPARE 15A,1P 13 14 15A,1P SPARE
C. GENERATOR IS PERFORMANCE SPECIFIED. CONTRACTOR TO ALLOW FOR RE-ALIGNMENT OF CONCRETE ENCASED DUCTS TO SUIT FINAL SPARE 15A,1P 15 16 15A,1P SPARE
GENERATOR LAYOUT REQUIREMENTS, AT NO EXTRA COST TO THE OWNER. TOTAL CONNECTED LOAD: _________ SPARE 15A,1P 17 18 15A,1P SPARE
SPARE 15A,1P 19 20 15A,1P SPARE
D. REFER TO DRAWING E011A FOR SCHEDULE OF SPDs. PHASE LOAD TO BE FILLED IN BY CONTRACTOR: SPARE 15A,1P 21 22 15A,1P SPARE PROJECT:
LOAD PHASE A: _________ LOAD PHASE B: _________ LOAD PHASE C: _________ SPARE 15A,1P 23 24 15A,1P SPARE

REMARKS
SPARE 15A,1P 25 26 MUNICIPALITY OF NORTH
SPARE 15A,1P 27 28 XXA,3P SPD-001 1
1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED.
2. DEDICATED NEUTRAL
SPARE 15A,1P 29 30 GRENVILLE - WATER POLLUTION
3. *
4.
GFI
LOCKED
TOTAL CONNECTED LOAD: _________ CONTROL PLANT EXPANSION
PHASE LOAD TO BE FILLED IN BY CONTRACTOR:
LOAD PHASE A: _________ LOAD PHASE B: _________ LOAD PHASE C: _________
PHASE - A
KEMPTVILLE, ONTARIO
REMARKS
1. ALL LOADS ARE IN WATTS, UNLESS OTHERWISE NOTED. DRAWING:

November 14, 2023 12:37:38 PM


2. DEDICATED NEUTRAL
3. * GFI ELECTRICAL
4. LOCKED
SERVICE ENTRANCE BUILDING
GROUND FLOOR HOUSE
2 UP-990 PANEL SCHEDULE 5 LP-001 PANEL SCHEDULE SERVICES PLAN
E911A SCALE: N.T.S. E911A SCALE: N.T.S.

DESIGN:
IDM/JJP
DRAWN: DRAWING #:
IDM

PLOT DATE:
CHECKED:

JLR #:
JO
29475
E911A
XLS XLS
PLC-900
Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-09
13:24:46 7:59:39 PM
Excel Sheet Data Exported on: 2017-07-11 11:25:22 AM
COMPONENT SUMMARY COMPONENT I/O LIST
SLOT CATALOG IO IO CONTROLLER ISA NEW DEWATERING AND ELECTRICAL SERVICE
DIGESTER CONTROL ENTRANCE BUILDING
IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS BUILDING 900 SERIES
NUMB. NUMBER MANUFACTURER DESCRIPTION IO TYPE RACK COUNT COMMENTS 800 SERIES
DO - 12 0 6 12 Provide interposing relay to suit NEW AERATION NEW PRIMARY NEW
TANKS CLARIFIERS HEADWORKS
0 1756-A10 AB/RA 10 Slot ControlLogix Chassis Miscellaneous 0 0 500 SERIES 400 SERIES 200 SERIES
DO - 13 0 6 13 Provide interposing relay to suit
0 1756-PB75 AB/RA 24VDC Power Supply (13A @ 5V) Miscellaneous 0 0
DO - 14 0 6 14 Provide interposing relay to suit
0 1756-L84E AB/RA ControlLogix Processor with 20MB NV Memory Processor 0 0
DO - 15 0 6 15 Provide interposing relay to suit NEW SECONDARY NEW TERTIARY
CLARIFIERS FILTER BUILDING
0 1784-SD2 AB/RA 2Gb Secure Digital Memory Card Miscellaneous 0 0 AI - 0 TI TIT-9010 Electrical Service Entrance Building Temperature Transmitter Electrical Service Entrance Building 0 7 0 600 SERIES (PHASE B) 700 SERIES (PHASE B)

1 1756-MVI56E-MCM AB/RA Modbus Master/Slave Enhanced Network Interface Module Miscellaneous 0 0 Used for direct connection to generator. 1 AI - 1 TI TIT-9030 Outdoor Air Temperature Transmitter Electrical Service Entrance Building 0 7 1
2 1756-MVI56E-MCM AB/RA Modbus Master/Slave Enhanced Network Interface Module Miscellaneous 0 0 Used for direct connection to SB-002A/SB-002B. 3 AI - 2 0 7 2
3 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block AI - 3 0 7 3 EXISTING SERVICE
BUILDING
300 SERIES
4 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block AI - 4 0 7 4

5 1756-IB16I AB/RA 16 Point 24 VDC Input Module Isolated Digital Input 0 16 Provide 1756-TBCH Screw Clamp Block AI - 5 0 7 5
AI - 6 0 7 6
6 1756-OB16I AB/RA 16 Point 24 VDC Output Module Isolated Digital Output 0 16 Provide 1756-TBCH Screw Clamp Block
KEY PLAN
AI - 7 0 7 7
7 1756-IF8I AB/RA Isolated Analog Input Module Analog Input 0 8 Provide 1756-TBCH Screw Clamp Block
8 1756-N2 AB/RA Slot Filler Miscellaneous 0 0
DRAWING NOTES:
9 1756-N2 AB/RA Slot Filler Miscellaneous 0 0
1 CONTRACTOR TO CONFIRM EXACT MAKE AND MODEL
1 WITH SUPPLIER TO SUIT GENERATOR REQUIREMENTS

2 CONTRACTOR TO CONFIRM EXACT STATUS AVAILABLE


WITH THE GENERATOR AND UPDATE THE I/O LIST
3 IO LIST CONT'D - PLC - 900 ACCORDINGLY.
I901A SCALE: NTS
3 CONTRACTOR TO CONFIRM WITH SUPPLIER TO SUIT
SWITCHBOARD POWER MONITORING REQUIREMENTS.

1 COMPONENT LIST - PLC - 900


I901A SCALE: NTS

XLS
PLC-900
Table Sheet
Excel Data Exported
Data Exported
on: 05-23-14
on: 2023-11-09
13:24:46 7:59:39 PM
COMPONENT I/O LIST
CONTROLLER ISA
IO TAG FUNCTION EQUIPMENT DESCRIPTION LOCATION OPERATION RACK SLOT POINT COMMENTS
DI - 0 YA CP-9000 Rack 0 DI Card 3 24 VDC Failure Electrical Service Entrance Building 0 = FAILURE 0 3 0
DI - 1 YA CP-9000 Rack 0 DO Card 6 24 VDC Failure Electrical Service Entrance Building 0 = FAILURE 0 3 1
DI - 2 YA CP-9000 Rack 0 AI Card 7 24 VDC Failure Electrical Service Entrance Building 0 = FAILURE 0 3 2
DI - 3 YA SPD-002A SPD-002A (SB-002A) Alarm Electrical Service Entrance Building 0 = ALARM 0 3 3
DI - 4 YA SPD-002B SPD-002B (SB-002B) Alarm Electrical Service Entrance Building 0 = ALARM 0 3 4
DI - 5 YA SPD-901 SPD-901 (LP-901) Alarm Electrical Service Entrance Building 0 = ALARM 0 3 5
DI - 6 YA SPD-990 SPD-990 (UP-990) Alarm Electrical Service Entrance Building 0 = ALARM 0 3 6
DI - 7 YA ATS-001 ATS-001 Out Of Service Electrical Substation 1 = SERVICE 0 3 7
DI - 8 YA ATS-001 ATS-001 Fault Electrical Substation 0 = FAULT 0 3 8
1 PHASE A - ADDENDUM #3 10/11/23
DI - 9 YA ATS-001 ATS-001 Remote Electrical Substation 1 = REMOTE 0 3 9
DI - 10 YA ATS-001 ATS-001 On Normal Power Electrical Substation 1 = NORMAL 0 3 10 0 PHASE A ISSUED FOR TENDER 02/10/23

DI - 11 YA ATS-001 ATS-001 Normal Power Available Electrical Substation 1 = AVAIL. 0 3 11


No. ISSUE / REVISION DD/MM/YY
DI - 12 0 3 12
This drawing is copyright protected and may not be reproduced or
DI - 13 0 3 13
used for purposes other than execution of the described work without
DI - 14 0 3 14 the express written consent of J.L. Richards & Associates Limited.
DI - 15 0 3 15 VERIFY SHEET SIZE AND SCALES. BAR TO THE
RIGHT IS 25mm IF THIS IS A FULL SIZE DRAWING. 0 25mm
DI - 16 YA CP-9000 Rack 0 DI Card 4 24 VDC Failure Electrical Service Entrance Building 0 = FAILURE 0 4 0
SCALE:
DI - 17 YA ATS-002 ATS-002 Out Of Service Electrical Substation 1 = SERVICE 0 4 1 N.T.S.
DI - 18 YA ATS-002 ATS-002 Fault Electrical Substation 0 = FAULT 0 4 2
DI - 19 YA ATS-002 ATS-002 Remote Electrical Substation 1 = REMOTE 0 4 3
DI - 20 YA ATS-002 ATS-002 On Normal Power Electrical Substation 1 = NORMAL 0 4 4 CLIENT:

DI - 21 YA ATS-002 ATS-002 Normal Power Available Electrical Substation 1 = AVAIL. 0 4 5


DI - 22 YA TX-001 TX-001 Temperature High Electrical Service Entrance Building 0 = ALARM 0 4 6
DI - 23 YA TX-001 TX-001 Oil Level Low Switch Electrical Service Entrance Building 0 = ALARM 0 4 7
DI - 24 YA SD-9011 Electrical Service Entrance Building Smoke Detector Alarm Electrical Service Entrance Building 0 = ALARM 0 4 8
DI - 25 YA TC-9010 Status Alarm Electrical Service Entrance Building 0 = ALARM 0 4 9
CONSULTANT: www.jlrichards.ca
DI - 26 YA TC-9011 Status Alarm Electrical Service Entrance Building 0 = ALARM 0 4 10
DI - 27 0 4 11
DI - 28 0 4 12
DI - 29 0 4 13
DI - 30 0 4 14
DI - 31 0 4 15 CONSULTANT:
DI - 32 YA CP-9000 Rack 0 DI Card 5 24 VDC Failure Electrical Service Entrance Building 0 = FAILURE 0 5 0
DI - 33 0 5 1
DI - 34 YS GEN-001 Generator Status Input Electrical Service Entrance Building 1 = STATUS 0 5 2
File Location: P:\29000\29475-000 - Kemptville WPCP Expansion Design\3-Production\6-Elect\29475-000 IO List.dwg

DI - 35 YS GEN-001 Generator Status Input Electrical Service Entrance Building 1 = STATUS 0 5 3


DI - 36 YS GEN-001 Generator Status Input Electrical Service Entrance Building 1 = STATUS 0 5 4
PROFESSIONAL STAMP PROJECT NORTH
DI - 37 YS GEN-001 Generator Status Input Electrical Service Entrance Building 1 = STATUS 0 5 5
2
DI - 38 YS GEN-001 Generator Status Input Electrical Service Entrance Building 1 = STATUS 0 5 6
DI - 39 YS GEN-001 Generator Status Input Electrical Service Entrance Building 1 = STATUS 0 5 7
DI - 40 YS GEN-001 Generator Status Input Electrical Service Entrance Building 1 = STATUS 0 5 8
DI - 41 YS GEN-001 Generator Status Input Electrical Service Entrance Building 1 = STATUS 0 5 9
DI - 42 0 5 10
DI - 43 0 5 11
DI - 44 0 5 12
DI - 45 0 5 13
PROJECT:
DI - 46 0 5 14
MUNICIPALITY OF NORTH
DI - 47 0 5 15
DO - 0 YC ATS-001 ATS-001 Transfer to Normal Power Command Electrical Service Entrance Building 1 = TRANSFER 0 6 0 Provide interposing relay to suit
GRENVILLE - WATER POLLUTION
DO - 1 YC ATS-002 ATS-002 Transfer to Normal Power Command Electrical Service Entrance Building 1 = TRANSFER 0 6 1 Provide interposing relay to suit CONTROL PLANT EXPANSION
DO - 2 0 6 2 Provide interposing relay to suit PHASE - A
DO - 3 0 6 3 Provide interposing relay to suit KEMPTVILLE, ONTARIO
DO - 4 0 6 4 Provide interposing relay to suit DRAWING:

ELECTRICAL

November 14, 2023 9:51:13 AM


DO - 5 0 6 5 Provide interposing relay to suit
DO - 6 0 6 6 Provide interposing relay to suit
SERVICE ENTRANCE BUILDING
DO - 7 0 6 7 Provide interposing relay to suit
DO - 8 0 6 8 Provide interposing relay to suit COMPONENT LIST & IO TABLE -
DO - 9 0 6 9 Provide interposing relay to suit PLC - 900
DO - 10 0 6 10 Provide interposing relay to suit
DO - 11 0 6 11 Provide interposing relay to suit DESIGN:
LO
1 DRAWN:
IDM DRAWING #:

PLOT DATE:
2 IO LIST - PLC - 900 CHECKED:
I901A SCALE: NTS
JLR #:
JO
29475
I901A

You might also like