MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV

SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA


PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 001/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Friday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 14 August 2020
Location : Cikarang Workshop Days To : 001

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 63 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 002/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Saturday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 15 August 2020
Location : Cikarang Workshop Days To : 002

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 126 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 003/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Sunday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 16 August 2020
Location : Cikarang Workshop Days To : 003

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 189 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 004/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Monday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 17 August 2020
Location : Cikarang Workshop Days To : 004

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 252 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 005/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Tuesday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 18 August 2020
Location : Cikarang Workshop Days To : 005

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 315 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 006/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Wednesday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 19 August 2020
Location : Cikarang Workshop Days To : 006

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 378 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 007/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Thursday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 20 August 2020
Location : Cikarang Workshop Days To : 007

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 441 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 008/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Friday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 21 August 2020
Location : Cikarang Workshop Days To : 008

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 504 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 009/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Saturday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 22 August 2020
Location : Cikarang Workshop Days To : 009

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 567 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 010/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Sunday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 23 August 2020
Location : Cikarang Workshop Days To : 010

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 630 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 011/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Monday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 24 August 2020
Location : Cikarang Workshop Days To : 011

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 693 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 012/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Tuesday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 25 August 2020
Location : Cikarang Workshop Days To : 012

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 756 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 013/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Wednesday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 26 August 2020
Location : Cikarang Workshop Days To : 013

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 819 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 014/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Thursday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 27 August 2020
Location : Cikarang Workshop Days To : 014

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 882 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 015/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Friday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 28 August 2020
Location : Cikarang Workshop Days To : 015

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 945 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 016/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Saturday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 29 August 2020
Location : Cikarang Workshop Days To : 016

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 1008 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 017/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Sunday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 30 August 2020
Location : Cikarang Workshop Days To : 017

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 1071 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager
MPDE - MILLING CAPACITY EXPANSION PROJECT ( MCE - 3101) SUPPLY OF PREFABRICATED LV/MV
SWITCHROOM BATANGTORU - TAPANULI SELATAN - SUMATERA UTARA
PT. AGINCOURT RESOURCES

PT. MULTIPANEL INTERMITRA MANDIRI

DAILY ACTIVITY REPORT

Project : MPDE - Milling Capacity Expansion Project ( MCE - 3101) Supply of Switchroom PO Number : 1079612
Customer : PT. Agincourt Resources Report No. : 018/MIM/PTAR/8/2020
Contractor : PT. Multipanel intermitra Mandiri Days : Monday
Equip./Tag No. : MCE - 3101 - LV/MV Switchroom Date : 31 August 2020
Location : Cikarang Workshop Days To : 018

TODAY ACTIVITIES TOMORROW ACTIVITIES PLAN


NO. NO.
ACTIVITY WORK QTY UNIT REMARK'S ACTIVITY WORK QTY UNIT REMARK'S
Preparation documentation drawing and Continue Preparation documentation drawing
1. 1.
procedure and procedure

MANPOWER LIST MATERIAL


NO.
NO. INDIRECT MANPOWER QTY NO. DIRECT MANPOWER QTY DESCRIPTION QTY UNIT REMARK'S
1. Project Manager 1 1. Fitter I 1.
2. Project Engineer 2. Fitter II 2.
3. Project Control 1 3. Helper 3.
4. Manager 4. Welder 4.
5. Const. Superintendent 5. Cold Cutter 5.
6. Engineer Mechanical 1 6. NDT Personel 6.
7. Engineer Electrical 1 7. Storeman / Logistic 7.
8. Drafter 2 8. Rigger
9. QA/QC. 9. Scaffolder TOOL
NO.
10. Safety Officer 10. Operator Genset DESCRIPTION QTY UNIT REMARK'S
11. Material Control 11. Operator Forklift 1.
12. Document Control 12. Operator Crane 2.
13. Purchasing 13. Electric Supporting 3.
14. Supervisor 14. Electrician Instrument 4.
15. Foreman 15. 5.
16. Security (PK) 1 16. 6.
17. Surveyor 17. 7.
8.
9.
MANPOWER TOTAL 7 MANPOWER TOTAL 0 10.

EQUIPMENT
NO. MAN-HOURS WEATHER OBSERVATION NO.
DESCRIPTION QTY UNIT REMARKS
1. 08.00 s/d 17.00 WIB Sunny : 08.00 s/d 17.00 WIB 1.
2. 08.00 s/d 17.00 WIB Cloudy : 08.00 s/d 17.00 WIB 2.
3. 08.00 s/d 17.00 WIB Drizzle : 08.00 s/d 17.00 WIB 3.
4. 08.00 s/d 17.00 WIB Rain : 08.00 s/d 17.00 WIB 4.
5. 5.

HSE REPORT
NO. SAFETY RECORD QTY REMARK'S NO. SAFE WORKING HOURS
1. Near Miss 0 1. Total Workers : 7 Person
2. Incident 0 2. Man-Hours : 9 Hours
3. Accident 0 3. Total Man-Hours Last 24 Hours : 63 Hours of People
4. Fatality 0 4. Total Cumulative Man-Hours : 1134 Hours of People

Notes : Total Man-Hours Last 24 Hours x Total Workers

Prepared By, Checked By, Acknowledged By,

Hamdan Nasution Andreas Setya Nugroho PT. Agincourt Resources


Project Control Construction/Project Manager