Refurbishment Order - User Manual-Updated
Refurbishment Order - User Manual-Updated
Refurbishment Order - User Manual-Updated
10.Settling Order
11.Closing Order
Usually, before creating refurbishment order, we first need to create Defect Work Order WDF and
describe this process in that order type. For that we use t-code IW31 and press
enter.
2 3
After finishing all, click to save Work Order. The system will show message at the lower left corner.
After creating an order, we must RELEASE. GoTo IW32 and release order with button.
Defected Part Dismantling
Ask master data coordinator to create a serial number for the defected equipment , then after equipment serial
number created on SAP, Go to IQ09, define your selection criteria and execute. / Or go to IQ02 and enter
material and serial.
Double click the part serial number of the defected part.
Go to Structure tab and click on the highlighted icon, you can notice that the equipment status
is INST (Installed).
Click Dismantle, then .
Equipment dismantled and status change from INST (Installed) to AVLB (Available)
Save your changes.
Double click on the material serial number to be updated (Make sure material system status is AVLB –
available)
Click on the Pen icon to change from display mode to change mode.
Change Mater batch from NEW to DAMAGED
Press enter and save your entries
After goods issue of new material and goods receipt of damage materials, Work Execution started.
Time Confirmed for order
Self-repair work must be approved in the system. We show actual work hours ,spent by the brigade for
repair. This process is carried out by the head of the department.
Go to IW41
4
3
5-6
Enter the information:
№ Field Purpose User operation
Determines the actual
1 Actual work Enter manually
time spent on repair
Determines remaining
Remaining
2 hours at the time of Enter manually
work
approve
Make sure that this is the
Final final confirmation and
3 click it
confirmation there is no other
confirmation step.
No Remain. Make sure that there is no
4 click it
Work remained work
5 Date indicating start of
Work start Enter manually
repair works
Save the confirmation. The system will show message at the lower left corner. Number of
confirmations saved for order 4000024: 1
Now open this order with IW32 to technically close the order.
After that process we will create new order with type WRF (Refurbishment Work Order)
Use t-code IW81
S.
Field Target User actions
No.
9-10
S.
Field Target User actions
No.
Then we go to Operations tab. Operation tab contains details related to operations which will be performed
during maintenance processing. Operation contains planned required time which will be the basis of planned
cost calculation based on activity type and cost center defined in the work center. It is defaulted from functional
location task list. It is also possible to adopt general task list in PM order. For that example we don’t use any task
list and try to insert information as shows below.
For next step we need insert external data. For that choice line with operation and press button external as
shown below.
Then fill necessary data as shows below
1 7
2 5
4
3
S.
Field Target User actions
No.
Key that you use to group together Enter manually or select from the list by
several materials or services with pressing F4
2 Material Group
the same attributes, and to assign
them to a particular material group.
3 Key which specifies the purchasing Enter manually or select from the list by
Purchasing Group pressing F4
group of the external processing.
Purchasing Denotes the purchasing Enter manually or select from the list by
4
Organization organization. pressing F4
Cost elements are required to Enter manually or select from the list by
5 Cost Element ensure comprehensive reporting pressing F4
and detailed planning.
Specifies that in this operation click it
subcontracting is provided for, if
6 Subcontracting
necessary with parts to be
provided.
After finishing all, click to save Work Order and click Release. The system will show message at the lower left
corner.
Then select Purchase requisition that have been choice for material and press button in
left side of the screen.
After press save
Document 4900000029 posted