Master Schedule PDF
Master Schedule PDF
Master Schedule PDF
Start
2023 Finish December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024
Mode 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31
1 Preliminaries 5 days Mon 04/12/23 Fri 08/12/23
2 Transportation,acomodation,insurance,medical
5 days Mon 04/12/23 Fri 08/12/23
test, car rental, etc
3 Engineering 70 days? Sat 09/12/23 Mon 26/02/24
4 Engineering Stage 30 days Sat 09/12/23 Thu 11/01/24
5 Drawings Submission (Rev. 0) 30 days Sat 09/12/23 Thu 11/01/24
6 Drawings Approval (Rev. 0) 30 days Sat 09/12/23 Thu 11/01/24
7 Detail Design Approval 31 days Sat 09/12/23 Fri 12/01/24
8 Drawings Submission (Rev. 0) 30 days Sat 09/12/23 Thu 11/01/24
9 Drawings Approval (Rev. 0) 30 days Sat 09/12/23 Thu 11/01/24
10 Final BOM Released 1 day Fri 12/01/24 Fri 12/01/24
11 Office Equipment 21 days Mon 11/12/23 Tue 02/01/24
12 Dismantling 3 days Mon 11/12/23 Wed 13/12/23
13 Modification office 8 days Thu 14/12/23 Fri 22/12/23
14 Christmas 3 days Sat 23/12/23 Mon 25/12/23 Christmas
15 Finishing Modification of Office 4 days Tue 26/12/23 Fri 29/12/23
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Master Schedule 2.2
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 19/12/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 1
ID Task Task Name DurationNovember
Start
2023 Finish December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024
Mode 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31
52 Installation Grounding Sistem 5 days Thu 14/03/24 Tue 19/03/24
53 Wiring Cable Power and Control 28 days Wed 20/03/24 Sat 20/04/24
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Master Schedule 2.2
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 19/12/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 2
June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025
31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Master Schedule 2.2
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 19/12/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 3
June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025
31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Master Schedule 2.2
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 19/12/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress