DAILY / WEEKLY PROJECT PROGRESS (DAYS)/60

HARI : KAMIS
TANGGAL : 19 OKTOBER 2023
PROYEK : BCC JAKARTA

KEGIATAN PROGRESS KERJA (%) VOLUME YANG DIKERJAKAN BOBOT (M2 / lot ) FOTO TARGET SELESAI JUMLAH MP REMAKS

A. 1 F Walls ( 12. Outdoor wall 1 st floor ) TGL : TGL : TGL : 27 Oktober 2023 4 Orang

Finish Concrete Polished epoxy 12,3 38 308

B. 2 F Walls ( 2. Ewi - 3 Stairs Wall ) TGL : TGL : TGL : 30 Oktober 2023 3 Orang

14,5 37 255,6
Repair, Repaint Epoxy

A. 1 F Floor ( 9. Lantai Kitchen ) TGL : TGL : TGL : 19 Oktober 2023 2 Orang

Repair epoxy coating anti slip 37 29 79

D. AREA SHOWER ( 1.Finishing Area Shower ) TGL : TGL : TGL : 30 Oktober 2023 3 Orang

Semen Plaster, Aci, Polish


18 16 91,28

A. 1 F Walls ( Café Walls & Colum repair polish 05-Nov-23 2 Orang

2 9 522,8
Bar, Roastery, Entrance, Vip lounge 1 St & 2 nd

Pembuat Laporan PT. DKI Supervisi BCC Project Manager

(….........................) (…..........................) (…..........................)