DMF K-250

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PT.

BORNEO MANUNGGAL PRATAMA

CALCULATION DESIGN MIX FORMULA K-250 USING CONCRETE PUMP


PROJECT : Pembangunan Kantor,Gudang,Workshop,dan Fasilitas Pendukung Insfrastruktur
CUSTOMER : PT Erich Balikpapan
LOCATION : Jalan KM 5.5 Kariangau

Cement = 340 Kg/m3


GRADE : 250 Kg/cm2 Fly Ash = 0 Kg/m3
SLUMP : 10 +/- 2 Cm Silica Fume = Kg/m3
FLOW : Cm Sand = 45,0 %
W/Cm Ratio : 0,55 Screening = %
Standart Deviation : 20 Kg/cm2 Split = 55,0 %
Margin (K = 1,64 * SD) : 32,8 Kg/cm2 Retarder = 0,30% %
Strength after 28 days : 282,8 Kg/cm2 Plastisizer = 0,00%

CHARACTERISTIC OF MATERIALS
Description Source Of Materials
- Cement Type-I : Tonasa = 3,14 gr/cc
- F/Aggr 1 Natural sand : Lariang 100% = 2,62 gr/cc
- Split 1 Split 10/20 : Bojonegara 100% = 2,47 gr/cc
- Water Normal water : Water supply = 1,00 gr/cc
- Additive D Retarder : Sika Plastiment VZ = 1,18 gr/cc
- Additive F Plastisizer : Sika 8097 SV = 1,05 gr/cc

COMPOSITION FOR 1 M3
Water w/c ratio 0,55 = 187,00 Liter 187,00 Cu m
Cement Type-I 340,0 kg = 108,28 Liter 340,00000 Cu m
Add. D Sika Plastiment VZ 0,30% % = 0,86 Liter 0,00086 Cu m
Pasta = Water + Cement = 295,28 Liter Cu m
Aggregate = 1000 - 295,28 = 704,72 Liter
Sand Total 45% = 317 Liter
Coarse Agregate Total 55% = 388 Liter
AGGREGATES
Sand Lariang 100% = 831 kg
Split 10/20 Bojonegara 100% = 957 kg

SUMMARY FRESH CONCRETE


Fine Agg C.Agg C.Agg Add
Cement Water
Quantities (Kg) (Sand) (10/20) (20/30) Tipe D
(Kg) (Kg) (Kg) (Kg) (Kg) (Liter)
2316 340,0 187,0 831 957 - 0,86
Volume Concrete
(m3) 108,28 187,00 317,12 388 - 0,86
1000,00

Disetujui Oleh Dibuat Oleh


Manager Plant Quality Control

Djamaludin Reza Achmad G