Scheduled Planning Proto

Project PG/No Wt/Set Total Total Mass Proto Client Fabrication Assembly Checking Pre Production
Customer Name Project Type Structure ERP Alias Completion Completion Finalisation Dismantling Status
Code n PG (MT) Sets/Nos Weight (MT) Month Commitment Status Status Status Incharge
Date Date Status
RR430 PG Bajaj - QA Navsari TLT 400kV M/C +0.0 MTR BODY EXTN. FO QA0M 5.381 19 102.238 28-11-2023 Dec Completed 25-11-2023 Completed Completed Completed Completed under dismantling Mr. Manish Patle
RR430 PG Bajaj - QA Navsari TLT 400kV M/C +7.5 MTR BODY EXTN. FO QA7.5M 6.823 1 6.823 28-11-2023 Dec Completed 25-11-2023 Completed Completed Completed Completed under dismantling Mr. Manish Patle
RR430 PG Bajaj - QA Navsari TLT Total 12.204 109.061
RR430 PG Bajaj - DC Navsari TLT 400 KV D/C TOWER TYPE DC (+3.0M) 4DC3M 3.782 3 11.346 30-11-2023 Dec Completed 30-11-2023 Completed Completed Completed Completed under dismantling Mr. Manish Patle
RR430 PG Bajaj - DC Navsari TLT 400 KV D/C TOWER TYPE DC (+6.0M) 4DC6M 5.575 2 11.150 30-11-2023 Dec Completed 30-11-2023 Completed Completed Completed Completed under dismantling Mr. Manish Patle
RR430 PG Bajaj - DC Navsari TLT Total 9.357 22.496
RR475 PG Montecarlo Maharasht TLT 400 KV C/ S WZ- 3 TOWER TYPE DB BDB 13.929 1 13.929 15-12-2023 Dec Completed 20-12-2023 Completed In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV C/ S WZ- 3 TOWER TYPE DB DB0M 3.186 1 3.186 15-12-2023 Dec Completed 20-12-2023 Completed In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV C/ S WZ- 3 TOWER TYPE DB+6DB6M 2.812 1 2.812 15-12-2023 Dec Completed 20-12-2023 Completed In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV C/ S WZ- 3 TOWER TYPE DB DBCP 0.882 1 0.882 15-12-2023 Dec Completed 20-12-2023 Completed In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV C/ S WZ- 3 TOWER TYPE DD DD 18.881 2 37.762 22-12-2023 Dec Completed 20-12-2023 In progress In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV C/ S WZ- 3 TOWER TYPE DD DD0M 4.410 2 8.820 22-12-2023 Dec Completed 20-12-2023 In progress In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV C/ S WZ- 3 TOWER TYPE DD DD6M 4.447 2 8.893 22-12-2023 Dec Completed 20-12-2023 In progress In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV C/ S WZ- 3 TOWER TYPE DD DDCP 1.472 2 2.944 22-12-2023 Dec Completed 20-12-2023 In progress In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV M/C QD TOWER TYPE BASICQD 90.869 4 363.474 10-12-2023 Dec Completed 10-12-2023 In progress In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV M/C QD TOWER TYPE (+0M QD0M 15.055 4 60.218 10-12-2023 Dec Completed 10-12-2023 In progress In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV M/C QD TOWER TYPE +3 MQD3M 18.494 1 18.494 10-12-2023 Dec Completed 10-12-2023 In progress In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV M/C QD TOWER TYPE +9 M. QD9M 18.489 1 18.489 10-12-2023 Dec Completed 10-12-2023 In progress In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT 400 KV M/C QD TOWER TYPE (COMQDCP 4.920 1 4.920 10-12-2023 Dec Completed 10-12-2023 In progress In progress Mr. I Krishna Rao
RR475 PG Montecarlo Maharasht TLT Total 197.846 544.825
RR525 PG P Chandra Reddy Cuddalore TLT 230 KV D/C TOWER TYPE DD - Normal2DD 8.325 8 66.597 25-12-2023 Jan --- Mr. Balaram Patel
RR525 PG P Chandra Reddy Cuddalore TLT 230 KV D/C TOWER TYPE DD +3.0m Ex2DD3M 1.865 2 3.731 25-12-2023 Dec 15-12-2023 --- Proto Rel Bal Mr. Balaram Patel
RR525 PG P Chandra Reddy Cuddalore TLT 230 KV D/C TOWER TYPE DD +9.0m Ex2DD9M 4.013 4 16.052 25-12-2023 Dec 15-12-2023 --- Proto Rel Bal Mr. Balaram Patel
RR525 PG P Chandra Reddy Cuddalore TLT Total 14.203 86.380 -
RR534 PG EMC Engineers Thiruvalam TLT 400 KV D/C WZ-2 TOWER TYPE DA - Basic Body 8.311 2 16.622 20-03-2024 Mar Mr. I Krishna Rao
RR534 PG EMC Engineers Thiruvalam TLT 400 KV D/C WZ-2 TOWER TYPE DA ±0.0m Extens 1.843 2 3.686 20-03-2024 Mar Mr. I Krishna Rao
RR534 PG EMC Engineers Thiruvalam TLT 400 KV D/C WZ-2 TOWER TYPE DA +3.0m Extens 1.519 1 1.519 20-03-2024 Mar Mr. I Krishna Rao
RR534 PG EMC Engineers Thiruvalam TLT 400 KV D/C WZ-2 TOWER TYPE DD - SUPER STRU 20.678 6 124.070 25-03-2024 Mar Mr. I Krishna Rao
RR534 PG EMC Engineers Thiruvalam TLT 400 KV D/C WZ-2 TOWER TYPE DD +3.0m Extens 3.179 2 6.357 25-03-2024 Mar Mr. I Krishna Rao
RR534 PG EMC Engineers Sriperumb TLT 400 KVS/C WZ-5 Tower Type DD - Basic Tower Bo 21.868 4 87.470 20-02-2024 Feb Mr. I Krishna Rao
RR534 PG EMC Engineers Sriperumb TLT 400 KVS/C WZ-5 Tower Type DD ±0.0m Extensio 5.277 4 21.109 20-02-2024 Feb Mr. I Krishna Rao
RR534 PG EMC Engineers Sriperumb TLT 400 KVS/C WZ-5 Tower Type DD +3.0m Extensio 7.014 2 14.028 20-03-2024 Feb Mr. I Krishna Rao
RR534 PG EMC Engineers Sriperumb TLT 400 KVS/C WZ-5 Tower Type DD +9.0m Extensio 8.422 2 16.844 20-03-2024 Feb Mr. I Krishna Rao
RR534 PG EMC Engineers TLT Total 78.111 291.705 -
RR542 PG Bajel Raipur TLT Tower DA Basic Body DA2 11.599 180 2,087.808 26-01-2024 Jan Mr. Manish Patle
RR542 PG Bajel Raipur TLT Tower +0m Ext for DA Type Tower DA2 2.697 113 304.752 26-01-2024 Jan Mr. Manish Patle
RR542 PG Bajel Raipur TLT Tower +9m Ext for DA Type Tower DA2 4.114 4 16.457 26-01-2024 Jan Mr. Manish Patle
RR542 PG Bajel Raipur TLT Total 18.410 2,409.016 -
RR462 non PG A K Das - Priority- Aditya TLT 400kV +30.0m extension to DD TowerDD30M 32.554 2 65.107M Drawing Bala Jan Mr. I Krishna Rao
RR462 non PG A K Das - Priority- Aditya TLT 400KV Columns TC1 Type 5.272 6 31.632M Drawing Bala Jan Mr. I Krishna Rao
RR462 non PG A K Das - Priority- Aditya TLT 400KV Beams G1 Type 4G1 3.955 4 15.821M Drawing Bala Jan Mr. I Krishna Rao
RR462 non PG A K Das - Priority- Aditya TLT Total 41.781 112.561 -
RR463 non PG A K Das - DA OPTCL TLT 400kV DA Type - Normal Tower 6.000 1 6.000M Drawing Bala Jan Mr. I Krishna Rao
RR463 non PG A K Das - DA OPTCL TLT 400kV DA Type +9.0m extension to DA Tower 2.000 1 2.000M Drawing Bala Jan Mr. I Krishna Rao
RR463 non PG A K Das - DA OPTCL TLT Total 8.000 8.000 -
RR531 non PG Flowmore MFC- JUSNL TLT 400kV D/C Tower DA - Normal Tower DA 15.085 50 754.229 28-12-2023 Dec 05-01-2023 --- In progress Mr. Balaram Patel
RR531 non PG Flowmore MFC- JUSNL TLT 400kV D/C Tower DA ± 0.0m DA0M 2.985 50 149.231 15-12-2023 Dec 05-01-2023 --- In progress Mr. Balaram Patel
RR531 non PG Flowmore MFC- JUSNL TLT 400kV D/C Tower DB - Normal Tower DB 24.251 8 194.004 28-12-2023 Dec 10-01-2023 --- JC Rel Bal Mr. Balaram Patel
RR531 non PG Flowmore MFC- JUSNL TLT 400kV D/C Tower DB ± 0.0m DB0M 5.282 8 42.256 15-12-2023 Dec 10-01-2023 --- JC Rel Bal Mr. Balaram Patel
RR531 non PG Flowmore MFC- JUSNL TLT 400kV D/C Tower DC - Normal Tower DC 27.279 16 436.460 15-01-2024 Jan Mr. Balaram Patel
RR531 non PG Flowmore MFC- JUSNL TLT 400kV D/C Tower DC ± 0.0m DC0M 6.188 16 99.002 15-01-2024 Jan Mr. Balaram Patel
RR531 non PG Flowmore MFC- JUSNL TLT Total 81.068 1,675.182 -
RR531 non PG Flowmore MFC- JUSNL TLT 400kV D/C Tower DD - Normal Tower DD 33.633 20 672.659 25-01-2024 Jan Mr. Balaram Patel
RR531 non PG Flowmore MFC- JUSNL TLT 400kV D/C Tower DD ± 0.0m DD0M 8.267 20 165.339 25-01-2024 Jan Mr. Balaram Patel
RR531 non PG Flowmore MFC- JUSNL TLT Total 41.900 837.998 -
RR533 non PG Pace Digitek BSNL Teleco 40M GBT Supply - 200 KMPH - (GR/TW40MGBT 9.958 200 1,991.640 02-12-2023 Dec Completed Ongoing Completed Completed Completed Mr. Manish Patle
RR533 non PG Pace Digitek BSNL Teleco Total 9.958 1,991.640 -
GRAND TOTAL 512.838 8,088.866 -

Page 1 of 1