1TB03300 300C04 STC Itp Me 0006
1TB03300 300C04 STC Itp Me 0006
AML‐DEV‐GOV‐STDFRM‐0016
Policy Document Management Revision 0.1
Document No ‐ 1TB03300-300C04-STC-ITP-ME-0006
Rev ‐ C0
Revision History
Revision Revision Revision Approved
No. Date by by Description of Revision Status
Shafiq Engnr
C0 18‐06‐2023 Ahmed For Approval For review
Khaled
Distribution
Name Title Department Date Issued
AMAALA WELLNESS CORE SECONDARY INFRASTRUCTURE
C0 First Issue
AMAALA W ELLNESS CORE SECONDARY INFRASTRUCTURE
QA/QC Department
1.1 Approval of Shop Drawing 1TB03300-008D02-DSA-SPC-FP-0001 Prior to work start Approved SDR R RH All documents must be approved before commencement of activity
3.0 Installation
3.3 HDPE Pipe Installation 1TB03300-008D02-DSA-SPC-FP-0001 Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/A
3.4 Jointing 1TB03300-008D02-DSA-SPC-FP-0001 Every Completed Portion S W/A/H Butt-welded with electro fusion socket type
3.6 Thrust blocks, valve chambers, air vents and wash outs. 1TB03300-008D02-DSA-SPC-ME-0002 Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/S/A
3.8 Marker tape, detectable 1TB03300-008D02-DSA-SPC-ME-0002 Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/S/A
4.2 Final Pressure & Flow Test (LV) Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/A/H
Remarks :
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
A Approval