Document Cover Page Document Ref.

AML‐DEV‐GOV‐STDFRM‐0016
Policy Document Management Revision 0.1

Document No ‐ 1TB03300-300C04-STC-ITP-ME-0006

Rev ‐ C0

Fire Fighting Pipe Installation


Document Cover Page Document Ref. AML‐DEV‐GOV‐STDFRM‐0016
Policy Document Management Revision 0.1

Revision History
Revision Revision Revision Approved
No. Date by by Description of Revision Status
Shafiq Engnr
C0 18‐06‐2023 Ahmed For Approval For review
Khaled

Distribution
Name Title Department Date Issued
AMAALA WELLNESS CORE SECONDARY INFRASTRUCTURE

INSPECTION TEST PLAN


FIRE FIGHTING NETWORK
(1TB03300) - TB-WELLNESS CORE WIDE

Prepared By Reviewed By Reviewed By Approved By


Rev # Date Remarks
(QA/QC MEP) (Technical Mng) (HSE Mng) (Project Manager)

C0 18-06-2023 M. Abid Shafiq Ahmed Abdul Wasim Khaled Aldossary

Revision Revision History

C0 First Issue
AMAALA W ELLNESS CORE SECONDARY INFRASTRUCTURE

QA/QC Department

Inspection Test Plan

FIRE FIGHTING NETWORK

Inspection Responsibility Assignmrnt


Activity Activity Description Acceptance Criteria Frequency Reference or Verifying Documents Remarks
STL AMAALA

1.0 Documents Submittal & Review:

1.1 Approval of Shop Drawing 1TB03300-008D02-DSA-SPC-FP-0001 Prior to work start Approved SDR R RH All documents must be approved before commencement of activity

Approval of Material Submittal, Method Statement, Material


1.2 1TB03300-008D02-DSA-SPC-FP-0001 Prior to work start MS R RH All documents must be approved before commencement of activity
Test Report, and Risk Assement

2.0 Material Delivery, Receiving Inspection and Storage

1TB03300-008D02-DSA-SPC-FP-0001, EN 12201, 1st Three Deliveries should be


2.1 HDPE100 SDR 9, PN20 1TB03300-300C04-STC-MIR-ME- H W/A 1st delivery lot, Check in detail and after randomly witness
ISO 4427. witness by STL QCI

1TB03300-008D02-DSA-SPC-FP-0001, EN 12201, 1st Three Deliveries should be


2.2 HDPE100 SDR 9, PN20 Fittings 1TB03300-300C04-STC-MIR-ME- H W/A 1st delivery lot, Check in detail and after randomly witness
ISO 4427. witness by STL QCI

3.0 Installation

3.1 Excavation Each Activity 1TB03300-300C04-STC-WIR-ME- H W/S

3.2 Trench Inspection Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/A

3.3 HDPE Pipe Installation 1TB03300-008D02-DSA-SPC-FP-0001 Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/A

3.4 Jointing 1TB03300-008D02-DSA-SPC-FP-0001 Every Completed Portion S W/A/H Butt-welded with electro fusion socket type

3.5 Valve Installation 1TB03300-008D02-DSA-SPC-FP-0001 Each Activity 1TB03300-300C04-STC-WIR-ME- H W/S/A

3.6 Thrust blocks, valve chambers, air vents and wash outs. 1TB03300-008D02-DSA-SPC-ME-0002 Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/S/A

3.7 Backfilling 1TB03300-008D02-DSA-SPC-ME-0002 Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/S/A

3.8 Marker tape, detectable 1TB03300-008D02-DSA-SPC-ME-0002 Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/S/A

3.9 Testing 1TB03300-008D02-DSA-SPC-ME-0002 Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W /A

4.0 Final inspection / Pre-Commissioning

4.1 Flushing Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/S/A

4.2 Final Pressure & Flow Test (LV) Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H W/A/H

Remarks :

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents

W Witness Inspection/Test RH Review and Approval of Documents

S Surveillance I 100% Contractor Inspection

A Approval