Document Cover Page Document Ref.

AML‐DEV‐GOV‐STDFRM‐0016
Policy Document Management Revision 0.1

Document No ‐ 1TB03300-300C04-STC-ITP-ME-0005

Rev ‐ C1

Vaccum Drainage System


Document Cover Page Document Ref. AML‐DEV‐GOV‐STDFRM‐0016
Policy Document Management Revision 0.1

Revision History
Revision Revision Revision Approved
No. Date by by Description of Revision Status
Engr
C0 11-12‐2023 Saud khan Shafique For Approval For review

Distribution
Name Title Department Date Issued
AMAALA WELLNESS CORE SECONDARY INFRASTRUCTURE

INSPECTION TEST PLAN


VACCUM DRAINAGE SYSTEM
(1TB03300) - TB-WELLNESS CORE WIDE

Prepared By Reviewed By Reviewed By Approved By


Rev # Date Remarks
(QA/QC MEP) (Technical Mng) (HSE Mng) (Project Manager)

C1 11-12-2023 Saud khan Shafiq Ahmed Abdul Wasim Amin

Revision Revision History

C0 * contractor to include the 3rd party responsibility on the ITP installation. The Vacuum Specialist should be part
of installation works as supervision scope.
AMAALA W ELLNESS CORE SECONDARY INFRASTRUCTURE

QA/QC Department

Inspection Test Plan

VACCUME DRAINAGE SYSTEM

Inspection Responsibility Assignment


Activity Activity Description Acceptance Criteria Frequency Reference or Verifying Documents Remarks
STL AMAALA

1.0 Documents Submittal & Review:

1.1 Approval of Shop Drawing SECTION 22 13 16.1 Prior to work start Approved SDR R RH All documents must be approved before commencement of activity

Approval of Material Submittal, Method Statement, Material Test Report,


1.2 SECTION 22 13 16.1 Prior to work start MS R RH All documents must be approved before commencement of activity
and Risk Assessment

1.4 Equipment Certification / Labels Prior to work start Valid Certificate R RH

2.0 Material Delivery, Receiving Inspection and Storage

1st Three Deliveries should be


2.1 HDPE PE100, PN16, SDR 11 SECTION 22 13 16.1, Part 2 1TB03300-300C04-STC-MIR-ME- H W 1st delivery lot, Check in detail and after randomly witness
witness by STL QCI

HDPE PE 100 Pipe Fittings


2.2 SECTION 22 13 16.1, Part 2 See Remarks See Remarks H W Only Y-fittings, 15°, 30° and 45° elbows shall be used.
Handling, Storage and Preservation

3.0 Installation is of 3rd party Responsibility

3.1 Trench, Bedding and Backfilling 1TB03300-008D02-DSA-SPC-ME-0002 Each Activity 1TB03300 -300C04-STC-WIR-ME- H W/S Visual Inspection

chilled water mains


3.2 Laying of Vacuum Sewer Pipes 1TB03300-008D02-DSA-SPC-ME-0002 Every Completed Portion 1TB03300 -300C04-STC-WIR-ME- H W/A
shall be routed within the right of way with an invert of 2m from the road level.

3.3 Jointing of Sewer Pipes 1TB03300-008D02-DSA-SPC-ME-0002 Every Completed Portion 1TB03300 -300C04-STC-WIR-ME- S S/A

3.4 Division Valves 1TB03300-008D02-DSA-SPC-ME-0002 Each Activity 1TB03300 -300C04-STC-WIR-ME- H W / S/ A

3.5 Collection Chambers Every Completed Portion 1TB03300 -300C04-STC-WIR-ME- H W/S Leak Detection Cable Shall be connected to the BMS in Future

3.6 Vacuum Station Every Completed Portion 1TB03300 -300C04-STC-WIR-ME- H W/A

1TB03300 -008D02-DSA-SPC-ME-0002,
3.7 Testing Every Completed Portion 1TB03300 -300C04-STC-WIR-ME- H W/A/H The pipework shall be tested prior to backfill
EN 16932, Annex B

4.0 Final inspection / Pre-Commissioning

4.1 Final System Test EN 16932, Annex B Every Completed Portion Test Results H W

Remarks :

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents

W Witness Inspection/Test RH Review and Approval of Documents

S Surveillance I 100% Contractor Inspection

A Approval