Professional Documents
Culture Documents
Critical Task
Critical Task
Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of 60 days Fri 1/12/23 Tue 13/2/24
excavator and lorry for excavation
7 Mobilization and demobilization of 40 days Fri 1/12/23 Thu 18/1/24
piling rig
8 Mobilization and demobilization of 55 days Sat 15/6/24 Wed
mobila crane for roof works 21/8/24
9 Substructure 70 days Wed 1/11/23 Tue 23/1/24
10 Piling 70 days Wed 1/11/23 Tue 23/1/24
11 Supply and transport R.C square pile 20 days Wed 1/11/23 Thu
23/11/23
12 Excavation from existing ground 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
16 Formwork 25 days Sat 23/12/23 Tue 23/1/24
Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone
Page 1
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
17 Sawn formwork, steel 20 days Sat 23/12/23 Wed
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone
Page 2
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
29 Roof Covering 20 days Fri 19/7/24 Mon 12/8/24
30 Gutter and rainwater goods 10 days Tue 13/8/24 Fri 23/8/24
31 Staircase 45 days Wed 12/6/24 Tue 6/8/24
32 Structural Work on Staircase 25 days Wed 12/6/24 Fri 12/7/24
33 Finishes Works on Staircase 20 days Sat 13/7/24 Tue 6/8/24
34 Wall 80 days Sat 6/4/24 Thu 18/7/24
35 Well burnt clay brick on 115mm 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone
Page 3
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
53 External Wall Plastering 30 days Fri 19/7/24 Fri 23/8/24
54 Wall tiles 20 days Tue 23/7/24 Wed 14/8/24
55 Wall Painting 30 days Thu 25/7/24 Wed 28/8/24
56 Wall flashing 20 days Fri 26/7/24 Sat 17/8/24
57 Chamfered and rebated timber 30 days Thu 1/8/24 Thu 5/9/24
skirting
58 Ceiling Finishes 35 days Fri 19/7/24 Thu 29/8/24
59 Ceiling frame and finishing 15 days Fri 19/7/24 Tue 6/8/24
60 Ceiling Painting 20 days Wed 7/8/24 Thu 29/8/24
61 Electrical Works 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 20 days Fri 19/7/24 Mon
and switch board 12/8/24
66 Sanitary Works 65 days Wed 12/6/24 Thu 29/8/24
67 Internal Cold-water system 45 days Wed 12/6/24 Tue 6/8/24
68 Internal Sanitary System 45 days Sat 6/7/24 Thu 29/8/24
Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone
Page 4