ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr

Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of 60 days Fri 1/12/23 Tue 13/2/24
excavator and lorry for excavation
7 Mobilization and demobilization of 40 days Fri 1/12/23 Thu 18/1/24
piling rig
8 Mobilization and demobilization of 55 days Sat 15/6/24 Wed
mobila crane for roof works 21/8/24
9 Substructure 70 days Wed 1/11/23 Tue 23/1/24
10 Piling 70 days Wed 1/11/23 Tue 23/1/24
11 Supply and transport R.C square pile 20 days Wed 1/11/23 Thu
23/11/23
12 Excavation from existing ground 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab

13 Handle, pitch and drive R.C square 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
16 Formwork 25 days Sat 23/12/23 Tue 23/1/24

Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Progress

Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Critical

Page 1
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
17 Sawn formwork, steel 20 days Sat 23/12/23 Wed
reinforcement, vibrated concrete 17/1/24
to pile cap and stump

18 Sawn formwork, steel 20 days Sat 30/12/23 Tue 23/1/24


reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel 10 days Sat 6/1/24 Wed
reinforcement, vibrated concrete 17/1/24
to ground slab
20 Superstructure 200 days Thu 18/1/24 Wed 25/9/24
21 Frame 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel 20 days Thu 18/1/24 Fri 9/2/24
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel 20 days Tue 13/2/24 Wed 6/3/24
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel 20 days Thu 7/3/24 Sat 30/3/24
reinforcement, vibrated concrete to
first floor column

25 Sawn formwork, steel 30 days Mon 1/4/24 Wed 8/5/24


reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel 25 days Thu 9/5/24 Tue 11/6/24
reinforcement, vibrated concrete to
roof beam
27 Roof 60 days Wed 12/6/24 Fri 23/8/24
28 Timber Roof Truss 30 days Wed 12/6/24 Thu 18/7/24
Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Progress

Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Critical

Page 2
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
29 Roof Covering 20 days Fri 19/7/24 Mon 12/8/24
30 Gutter and rainwater goods 10 days Tue 13/8/24 Fri 23/8/24
31 Staircase 45 days Wed 12/6/24 Tue 6/8/24
32 Structural Work on Staircase 25 days Wed 12/6/24 Fri 12/7/24
33 Finishes Works on Staircase 20 days Sat 13/7/24 Tue 6/8/24
34 Wall 80 days Sat 6/4/24 Thu 18/7/24
35 Well burnt clay brick on 115mm 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall

37 Bonding tie 50 days Sat 6/4/24 Tue 11/6/24


38 Window 15 days Fri 19/7/24 Tue 6/8/24
39 Window concrete lintel 15 days Fri 19/7/24 Tue 6/8/24
40 Window frame and finishing 15 days Fri 19/7/24 Tue 6/8/24
41 Door 55 days Fri 19/7/24 Wed 25/9/24
42 Door concrete lintel 15 days Fri 19/7/24 Tue 6/8/24
43 Door frame 15 days Fri 19/7/24 Tue 6/8/24
44 Door leaf 15 days Wed 7/8/24 Fri 23/8/24
45 Door painting 15 days Sat 24/8/24 Wed 11/9/24
46 Iron mongery 10 days Thu 12/9/24 Wed 25/9/24
47 Finishes 70 days Wed 12/6/24 Thu 5/9/24
48 Floor Finishes 40 days Wed 12/6/24 Wed 31/7/24
49 Floor tiles including toilet 20 days Wed 12/6/24 Fri 5/7/24
50 Parquet flooring 40 days Wed 12/6/24 Wed 31/7/24
51 Wall Finishes 40 days Fri 19/7/24 Thu 5/9/24
52 Internal Wall Plastering 30 days Fri 19/7/24 Fri 23/8/24

Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Progress

Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Critical

Page 3
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
53 External Wall Plastering 30 days Fri 19/7/24 Fri 23/8/24
54 Wall tiles 20 days Tue 23/7/24 Wed 14/8/24
55 Wall Painting 30 days Thu 25/7/24 Wed 28/8/24
56 Wall flashing 20 days Fri 26/7/24 Sat 17/8/24
57 Chamfered and rebated timber 30 days Thu 1/8/24 Thu 5/9/24
skirting
58 Ceiling Finishes 35 days Fri 19/7/24 Thu 29/8/24
59 Ceiling frame and finishing 15 days Fri 19/7/24 Tue 6/8/24
60 Ceiling Painting 20 days Wed 7/8/24 Thu 29/8/24
61 Electrical Works 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall

64 Supply and install the electrical wiring 20 days Thu 18/1/24 Fri 9/2/24

65 Supply and install the electrical fittings 20 days Fri 19/7/24 Mon
and switch board 12/8/24
66 Sanitary Works 65 days Wed 12/6/24 Thu 29/8/24
67 Internal Cold-water system 45 days Wed 12/6/24 Tue 6/8/24
68 Internal Sanitary System 45 days Sat 6/7/24 Thu 29/8/24

Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Progress

Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Critical