Method Statement For Installation of Light Fittings Luminary's Exterior Interior
Method Statement For Installation of Light Fittings Luminary's Exterior Interior
PROJECT
CHEYYAR SEZ DEVELOPERS PVT LTD
INDIA TINDIVANAM FOOTWARES PVT LTD
TINDIVANAM
Rev Register:
Page 1
Doc No: SECPL-MS-01
Method Statement for Installation of Light
Date : 21/09/2023
Fittings Luminary’s Exterior& Interior
Rev:00
Table of Contents
1.Purpose...........................................................................................................................................3
2.Scope of Work................................................................................................................................3
3.Definition........................................................................................................................................3
1.1Abbreviation.................................................................................................................................3
1.2“Approved” or “Approval”............................................................................................................3
1.3“Shop Drawings”...........................................................................................................................3
1.4“Final Inspection”.........................................................................................................................3
1.5“Materials”...................................................................................................................................3
1.6“Method Statements”..................................................................................................................3
4.Reference Documents – Specifications, Drawings. Etc...................................................................4
5.Manpower......................................................................................................................................4
Staff:..................................................................................................................................................4
Labour...............................................................................................................................................4
6.Responsible Personnel on Site........................................................................................................4
7.Material Inspection / Storage.........................................................................................................5
8.MATERIALS.....................................................................................................................................5
9.HANDLING & STORAGE...................................................................................................................5
10.Installation General Requirements...............................................................................................6
11.INSTALLATION PROCEDURE GENERAL FOR INSTALLATION OF LIGHT FITTINGS LUMINARY’S
EXTERIOR INTERIOR...........................................................................................................................6
12.INSPECTION..................................................................................................................................7
13.ATTACH MENTS............................................................................................................................8
Page 2
Doc No: SECPL-MS-01
Method Statement for Installation of Light
Date : 21/09/2023
Fittings Luminary’s Exterior& Interior
Rev:00
1. Purpose
The purpose of this Method Statement for Installation of light fittings luminary’s
exterior interior” to ensure that it complies to Project requirements, specifications
and standards.
2. Scope of Work
This Method Statement applies to all installation of light fittings luminary’s exterior
interior. Manpower and equipment shall be organized to meet the schedule as per
the approved construction program.
3. Definition
1.1 Abbreviation
QAQC - Quality Assurance Quality Control
MS - Method Statement
MEP - Mechanical, Electrical, Plumbing
RFIA - Request for Inspection & Approval
MIR - Materials Inspection Request
ITP - Inspection and Test Plan
TBT - Tool Box Talk
Following tools shall be required for the installation of light fittings & fixtures.
5. Manpower
Staff:
1. Project Manager
2. Site Engineer
3. Supervisor
4. QC Engineer / Inspector
5. HSE Engineer
6. Store Keeper
Labour
1. Trade workers
2. Helpers / Labours
3. Drivers
4. The site Engineer / Supervisor shall check the materials as per the manufacturer’s
recommendation before installation and shall be responsible for the installation
as per approved shop drawings.
5. Safety Officer shall ensure that appropriate/necessary measures are in place at
the work location to avoid any unexpected events.
6. QAQC Inspector shall be responsible for carrying out inspections for the materials
delivered on-site. He shall document such inspections.
7. QAQC Engineer / Inspector shall monitor the installation activities progressively
and shall record all deviation from the specification in a form of snags or further
as non-conformance notification.
8. MATERIALS
The Installation of light fittings luminary’s exterior interior accessories shall be in line with
the approved material submittal and approved drawings as per rules and standards.
Page 5
Doc No: SECPL-MS-01
Method Statement for Installation of Light
Date : 21/09/2023
Fittings Luminary’s Exterior& Interior
Rev:00
1. All Packages for the complete set of Lighting Control systems, reaching the site
shall be identified as per the package list.
2. Where auxiliaries are shipped loose, these will be identified and checked against
the dispatch documents. Any item found missing or damaged will be noted to the
supplier immediately for replacement/repair.
3. All materials received at site shall be inspected and ensured that the materials
are as per approved material submittal, shop drawing and single line diagram.
4. Any discrepancies, damage etc found will be notified and reported for further
action.
5. The site Engineer (Electrical) has to ensure that material used at the site is free
from any damage.
6. All packages shall be stored under a protected dust area.
8. The connection between lighting fixtures and ceiling roses are to be made only
using heat resistance 3 core, 2.5 SQ mm or 1.5 SQ mm flexible / wires. wires.
9. Ceiling rose location shall be easily accessible and should be avoided installation
above AC ducts and cable trays.
10. All lighting fixtures shall be connected with earthing cable.
11. Before fixing lamps, all lighting fixtures are to be cleaned.
12. Gloves shall be used in works.
13. Correct lamps are to be fixed in lighting fixtures.
14. Installation of louvres shall be installed and protected by polyethene sheets.
15. Care should be taken in fixing the fitting louvres and avoiding fingerprints or dust
on the louvre
16. Before installation all wires should be tested, meggered and schedules should be
submitted to Engineers for approval and records shall be maintained.
17. GI boxes, round PVC boxes in concrete must be treated after plaster and the
edges shall be finished good and clean. Wall finish shall be done uniformly
around the box edges.
18. Test results should be submitted to the consultant for the records.
19. Ensure that where luminaries are fixed directly to conduit boxes the final circuit
connections are adequately protected against the heat transfer from the
luminaries
12.INSPECTION
Inspection for Installation of light fittings luminary’s exterior & interior.
13.ATTACHMENTS
1. Risk Assessment
2. Inspection & Test Plan
3. Quality Control Procedure.