DAILY SHIFT REPORT

DATE: December 05, 2023


SHIFT: Night Shift (7:00PM –7:00AM)
MANPOWER

1. Peter Consebido - Project Engineer

Chiller Operators:
1. Elmer Gica
2. Johann Francis Evangelista

HVAC Technicians:
1. Randy Santos — Trouble Call
2. Harley Balanoba — Trouble Call
3. Ryan Gatbonton — PMS
4. Mark Gil Rizan — PMS
5. Reymund Olivera — PMS
3. Benidick W. Buyayo — Area Temp. /Inspector

OPERATION HIGHLIGHTS

ROUTINE ACTIVITIES

1.Chiller 2 & 4 Hourly Parameter Monitoring. (See Attached Readings)


2.Parameter Monitoring of Chiller Reading 2 & 4 Every Two-Hours. (See Attached Readings)
3.Temperature Reading at Various Areas. Every 3 Hours. (See Attached Readings)
4. Conduct Preventive Maintenance on VAC Equipment. (See Attached Readings)
5.Attended Service Calls. ( See Table Below)

Unit Designation Location Status Action Taken Remarks

Operational/
Chiller No. 1 Chiller Plant Re-conditioning Done Operational
Stand-by mode

True-Temp Corp. www.truetempcorp.com


Unit Designation Location Status Action Taken Remarks

Monitoring of parame-
Chiller No. 2 Chiller Plant Operational ters Operational

Chiller No. 3 Chiller Plant Stand-by mode Operational/Stand-by


Fixed Delta P

Monitoring of parame-
Chiller No. 4 Chiller Plant Operational ters Operational

Monitoring of parame-
Chiller No. 5 Chiller Plant Operational ters Operational

Under Repair (Defective Reported to NAIA-T3


Non-
Chiller No. 6 Chiller Plant Compressor). For Fur-
Operational Eng’g Department
ther Troubleshooting

PUMPS

Unit Designation Location Status Action Taken Remarks

Operational (Standby Daily monitoring Under Good Condition


ChWP No.1 Chiller Plant
-Mode)
Operational Daily monitoring Running in Good Condition
ChWP No.2 Chiller Plant
(Running)
Operational (Standby Daily monitoring Under Good Condition
ChWP No.3 Chiller Plant

Operational Daily monitoring Running in Good Condition


ChWP No.4 Chiller Plant
(Running)
Operational Daily monitoring Under Good Condition
ChWP No.5 Chiller Plant
(Running)
Stand-by Mode Daily monitoring Under Good Condition
ChWP No.6 Chiller Plant

Operational (Standby Daily monitoring Under Good Condition


CoWP No.1 Chiller Plant -Mode)
Operational Daily monitoring Running in Good Condition
CoWP No.2 Chiller Plant

Operational (Standby Daily monitoring Under Good Condition


CoWP No.3 Chiller Plant -Mode)
Operational Daily monitoring Under Good Condition
CoWP No.4 Chiller Plant

Operational Daily monitoring Under troubleshooting


CoWP No.5 Chiller Plant

Operational (Standby Daily monitoring Under Good Condition


CoWP No.6 Chiller Plant

True-Temp Corp. www.truetempcorp.com


COOLING TOWERS

Unit Designation Location Status Action Taken Remarks

COOLING Operational Reported to NAIA-T3


Cooling Tower No.1 TOWER AR- (Running)
Eng’g Department
EA
COOLING Operational Note: Applicable for All Cooling Reported to NAIA-T3
Cooling Tower No.2 TOWER AR- (Running) Towers
Eng’g Department
EA
COOLING Operational Replacement of Return Valves, Bal- Reported to NAIA-T3
Cooling Tower No.3 TOWER AR- (Running) ancing Valves, Fillers,
Eng’g Department
EA

COOLING Operational Float Ball-Bronze Type, Automatic Reported to NAIA-T3


Cooling Tower No.4 TOWER AR- (Running) Chemical Feeders, &
Eng’g Department
EA
COOLING Operational Automatic Water Softener Reported to NAIA-T3
Cooling Tower No.5 TOWER AR- (Running)
Eng’g Department
EA
COOLING Under Worn out Pillow Block Bearings and Reported to NAIA-T3
Cooling Tower No.6 TOWER AR- Mis-aligned Motor Pulley
Eng’g Department
EA Repair

PREVENTIVE MAINTENANCE
UNIT
DESIGNA- LOCATION Team ACTION TAKEN STATUS REMARKS
TION
AHU 23206, Cleaning of coil, housekeep-
22214 ing, Cleaning of AHU body, Operational Done
& 22215 siphoning of drain pan and
M.R. 2.8.03 PMS
Installed new air filters

Cleaning of coil, housekeep-


ing, Cleaning of AHU body,
AHU 23207 siphoning of drain pan, in-
M.R. 2.8.03 PMS Operational Done
stalled new air filter & re-
placed 2pcs. SPA1450 V belts
Cleaning of coil, housekeep-
ing, Cleaning of AHU body, Operational Done
AHU 22216 siphoning of drain pan and
M.R. 2.8.05 PMS
Installed new air filters

True-Temp Corp. www.truetempcorp.com


PREVENTIVE MAINTENANCE

UNIT
DESIGNA- LOCATION Team ACTION TAKEN STATUS REMARKS
TION
Cleaning of coil, housekeep-
AHU 21202 M.R. 2.8.09 PMS ing, Cleaning of AHU body, Operational Done
siphoning of drain pan and
& 23209
Installed new air filters

Cleaning of coil, housekeep-


ing, Cleaning of AHU body,
AHU 22218
siphoning of drain pan, in-
& 23210 M.R. 2.9.08 PMS Operational Done
stalled new air filter & re-
placed 2pcs. SPA1450 V belts

TROUBLE SHOOTING

UNIT
DESIGNA- LOCATION Team ACTION TAKEN STATUS REMARKS
TION

M.R. 2.2.26 TC Checked & Replaced 4 pcs. V Operational Done


AHU 21010 Belts

Checked Supply Air Duct


To verify PAU unit supply– PAU 44003
AHU 33027 M.R. 3.4.46 TC PAU 44003 located at Not operational
M.R.4.4.18

PREPARED BY: CHECKED BY: NOTED BY:

Peter B. Consebido, PME Engr. Rodney Paguio Engr. Romeo Dolores


Project Engineer Mechanical Engineer Head of Engineering Dept. T3