Professional Documents
Culture Documents
Bike Work Shop Signalling Annual Plan of 2024
Bike Work Shop Signalling Annual Plan of 2024
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Monthly Plan Format for Signaling System
Workshop__________________________
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. number
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set
standard;whether the cable box is damaged or
not,Whether the lock is good.
4. Faults
Different types of faultes which are out of the plan Time
Handeled
Note:-
1 This format is applicable for each workshops
The Center also submmit to the Department by this format by
2
Summurizing from the workshops
The faults handeled and any othr works done out of the plan can
3
be presented in detail explanation.
This format is a draft format which can be modified if Department
4 and Centers agree
All the numberings should comply with the Annual Plan Summary
5
Frequency Planed Remark
1 time/day
1 time/day
1 time/day
1
No planed only completed and
mention shortly the kind of faults
maintained
Signaling Annual Plan Summary of the 20
Workshop Bik
Scope of Work: From_____________To____________
3. Test the conversion between main and auxiliary filaments of bulb, as well
as the alarm. rack 15
4. Inspection of the turnout appearance ,check/adjust the
close contactness/ fat edge of the turnout
rail;check/adjust of notch of the indication rod;check
whether the external bolt / nut are loose, whether the
cotter pin is complete, whether the opening meets the set 9
standard;whether the cable box is damaged or
not,Whether the lock is good.
section 15
Frequenc Total
Jun Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
y Planed
12 15 15 15 15 15 15 15 15 15 15 15 15
180
12 15 15 15 15 15 15 15 15 15 15 15 15
180
1 15
15
1 15 15
24 18 18 18 18 18 18 18 18 18 18 18 18
216
6 9 9 9 9
36
1 9
9
24 20 20 20 20 20 20 20 20 20 20 20 20
240
1 15
15
366 31 29 31 30 31 30 31 31 30 31 30 31
366
1 14 14
366 31 29 31 30 31 30 31 31 30 31 30 31
1
366 31 29 31 30 31 30 31 31 30 31 30 31
12 1 1 1 1 1 1 1 1 1 1 1 1
12
4 1 1 1 1
4
1 1
2 6 6
12
2 20 20 40
Remark
Yx,X,D1,S1,S2,S3,X1,X2,X3,
D8,D6,D4,D2,S and YS
Yx,X,D1,S1,S2,S3,X1,X2,X3,
D8,D6,D4,D2,S and YS
1#,3#,14#,12#,10#,4#,8#,6#
and 2#
1#,3#,14#,12#,10#,4#,8#,6#
and 2#
XJG,IIAG,1-3DG,IIG,1-
3DG1,3G,1-3DG1,3G,1-
3DG2,14DG,10-12DG,1G,10-
12DG1,,D8G,8DG,4DG,D4G,
2-6DG1,2-6DG,D2G and SJG.