Construction- MUMBAI-NAGPUR EXPRESSWAY

Project Budget:Estimated ₹55000 Cr. | Baseline ₹ 46000 Cr.

MUMBAI NAGPUR EXPRESSWAY CORRIDOR(Phase-2) PROJECT DURATION


Highway Construction

Task ID Task Description Priority

1 Construction Phase-2 High


1.1 Soil Filling Normal
1.2 Granular Sub Base Normal
1.3 Dry Lean Concrete Normal
1.4 Pavement Quality Concrete Normal
1.5 Joints Low
1.6 Screeding & Finishing Surface Normal
1.7 Curing Low
2 Inaugration Normal
3 Opening of Traffic Low
AGPUR EXPRESSWAY

PROJECT START DATE PROJECT END DATE


5/15/2015 10/24/2023

2020 2021
Start Finish Duration
J F M A M J J A S O N D J F M A M J
1/18/2020 10/24/2023 1375
1/22/2020 8/12/2020 203
8/21/2020 12/15/2020 116
12/11/2020 7/20/2021 221
5/8/2021 2/8/2022 276
12/27/2021 5/13/2022 137
5/15/2022 4/15/2023 335
4/3/2023 9/18/2023 168
10/23/2023 10/23/2023
10/24/2023
Completed
Running

2021 2022 2023


J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D