ID Task Task Name December Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024

Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2023 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 11% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE

2 Preliminary and General Works 11% 290 days Wed 1/11/23 Fri 25/10/24

3 Contractor's Site Management 8% 290 days Wed 1/11/23 Fri 25/10/24

4 Contractor's Site Office 8% 290 days Wed 1/11/23 Fri 25/10/24

5 Worker's Quarters and Servies 8% 290 days Wed 1/11/23 Fri 25/10/24

6 Mobilization and demobilization of 30% 60 days Fri 1/12/23 Tue 13/2/24


excavator and lorry for excavation
works
7 Mobilization and demobilization of 65% 40 days Fri 1/12/23 Thu 18/1/24
piling rig

8 Mobilization and demobilization of 0% 55 days Sat 15/6/24 Wed


mobila crane for roof works 21/8/24

9 Substructure 77% 70 days Wed 1/11/23 Tue 23/1/24

10 Piling 77% 70 days Wed 1/11/23 Tue 23/1/24

11 Supply and transport R.C square 100% 20 days Wed 1/11/23 Thu 100%
pile 23/11/23

12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and
remainder cart away for pile cap,
ground beam and slab

13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile

14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23

15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap

16 Formwork 20% 25 days Sat 23/12/23 Tue 23/1/24

17 Sawn formwork, steel 40% 20 days Sat 23/12/23 Wed


reinforcement, vibrated 17/1/24
concrete to pile cap and stump

18 Sawn formwork, steel 10% 20 days Sat 30/12/23 Tue 23/1/24


reinforcement, vibrate
concrete to ground beam

19 Sawn formwork, steel 0% 10 days Sat 6/1/24 Wed


reinforcement, vibrated 17/1/24
concrete to ground slab

20 Superstructure 0% 225 days Thu 18/1/24 Fri 25/10/24

21 Frame 0% 115 days Thu 18/1/24 Tue 11/6/24

22 Sawn formwork, steel 0% 20 days Thu 18/1/24 Fri 9/2/24


reinforcement, vibrated concrete
to ground column

23 Sawn formwork, steel 0% 20 days Tue 13/2/24 Wed 6/3/24


reinforcement, vibrated concrete
to first floor beam

24 Sawn formwork, steel 0% 20 days Thu 7/3/24 Sat 30/3/24


reinforcement, vibrated concrete
to first floor column

25 Sawn formwork, steel 0% 30 days Mon 1/4/24 Wed 8/5/24


reinforcement, vibrated concrete
to first floor slab

26 Sawn formwork, steel 0% 25 days Thu 9/5/24 Tue 11/6/24


reinforcement, vibrated concrete
to roof beam

27 Roof 0% 60 days Wed 12/6/24 Fri 23/8/24

28 Timber Roof Truss 0% 30 days Wed 12/6/24 Thu 18/7/24

29 Roof Covering 0% 20 days Fri 19/7/24 Mon


12/8/24

30 Gutter and rainwater goods 0% 10 days Tue 13/8/24 Fri 23/8/24

31 Staircase 0% 45 days Wed 12/6/24 Tue 6/8/24

32 Structural Work on Staircase 0% 25 days Wed 12/6/24 Fri 12/7/24

Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 1
ID Task Task Name December Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2023 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 0% 20 days Sat 13/7/24 Tue 6/8/24

34 Wall 0% 80 days Sat 6/4/24 Thu 18/7/24

35 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall

36 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall

37 Bonding Tie 0% 50 days Sat 6/4/24 Tue 11/6/24

38 Window 0% 15 days Fri 19/7/24 Tue 6/8/24

39 Window concrete lintel 0% 15 days Fri 19/7/24 Tue 6/8/24

40 Window frame and finishing 0% 15 days Fri 19/7/24 Tue 6/8/24

41 Door 0% 55 days Fri 19/7/24 Wed


25/9/24

42 Door concrete lintel 0% 15 days Fri 19/7/24 Tue 6/8/24

43 Door frame 0% 15 days Fri 19/7/24 Tue 6/8/24

44 Door leaf 0% 15 days Wed 7/8/24 Fri 23/8/24

45 Door painting 0% 15 days Sat 24/8/24 Wed


11/9/24

46 Iron mongery 0% 10 days Thu 12/9/24 Wed


25/9/24

47 Finishes 0% 70 days Wed 12/6/24 Thu 5/9/24

48 Floor Finishes 0% 40 days Wed 12/6/24 Wed


31/7/24

49 Floor tiles including toilet 0% 20 days Wed 12/6/24 Fri 5/7/24

50 Parquet flooring 0% 40 days Wed 12/6/24 Wed


31/7/24

51 Wall Finishes 0% 40 days Fri 19/7/24 Thu 5/9/24

52 Internal Wall Plastering 0% 30 days Fri 19/7/24 Fri 23/8/24

53 External Wall Plastering 0% 30 days Fri 19/7/24 Fri 23/8/24

54 Wall tiles 0% 20 days Tue 23/7/24 Wed


14/8/24

55 Wall Painting 0% 30 days Thu 25/7/24 Wed


28/8/24

56 Wall flashing 0% 20 days Fri 26/7/24 Sat 17/8/24

57 Chamfered and rebated timber 0% 30 days Thu 1/8/24 Thu 5/9/24


skirting

58 Ceiling Finishes 0% 35 days Fri 19/7/24 Thu 29/8/24

59 Ceiling frame and finishing 0% 15 days Fri 19/7/24 Tue 6/8/24

60 Ceiling Painting 0% 20 days Wed 7/8/24 Thu 29/8/24

61 Electrical Works 0% 225 days Thu 18/1/24 Fri 25/10/24

62 The provision of underground 0% 200 days Thu 18/1/24 Wed


electrical pipe sleeve 25/9/24

63 Supply and install UPVC pipes on 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall

64 Supply and install the electrical 0% 20 days Thu 18/1/24 Fri 9/2/24
wiring

65 Supply and install the electrical 0% 20 days Fri 19/7/24 Mon


fittings and switch board 12/8/24

66 Sanitary Works 0% 65 days Wed 12/6/24 Thu 29/8/24

67 Internal Cold-water system 0% 45 days Wed 12/6/24 Tue 6/8/24

68 Internal Sanitary System 0% 45 days Sat 6/7/24 Thu 29/8/24

Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress