ID Task Task Name June 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr

tart Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 61% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE

2 Preliminary and General Works 72% 290 days Wed 1/11/23 Fri 25/10/24

3 Contractor's Site Management 71% 290 days Wed 1/11/23 Fri 25/10/24

4 Contractor's Site Office 71% 290 days Wed 1/11/23 Fri 25/10/24

5 Worker's Quarters and Servies 71% 290 days Wed 1/11/23 Fri 25/10/24

6 Mobilization and demobilization of 100% 60 days Fri 1/12/23 Tue 13/2/24


excavator and lorry for excavation
works
7 Mobilization and demobilization of 100% 40 days Fri 1/12/23 Thu 18/1/24
piling rig

8 Mobilization and demobilization of 40% 55 days Sat 15/6/24 Wed


mobila crane for roof works 21/8/24

9 Substructure 100% 70 days Wed 1/11/23 Tue 23/1/24

10 Piling 100% 70 days Wed 1/11/23 Tue 23/1/24

11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23

12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab

13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile

14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23

15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap

16 Formwork 100% 25 days Sat 23/12/23 Tue 23/1/24

17 Sawn formwork, steel 100% 20 days Sat 23/12/23 Wed


reinforcement, vibrated concrete 17/1/24
to pile cap and stump

18 Sawn formwork, steel 100% 20 days Sat 30/12/23 Tue 23/1/24


reinforcement, vibrate concrete
to ground beam

19 Sawn formwork, steel 100% 10 days Sat 6/1/24 Wed


reinforcement, vibrated concrete 17/1/24
to ground slab

20 Superstructure 56% 200 days Thu 18/1/24 Wed


25/9/24

21 Frame 100% 115 days Thu 18/1/24 Tue 11/6/24

22 Sawn formwork, steel 100% 20 days Thu 18/1/24 Fri 9/2/24


reinforcement, vibrated concrete to
ground column

23 Sawn formwork, steel 100% 20 days Tue 13/2/24 Wed 6/3/24


reinforcement, vibrated concrete to
first floor beam

24 Sawn formwork, steel 100% 20 days Thu 7/3/24 Sat 30/3/24


reinforcement, vibrated concrete to
first floor column

25 Sawn formwork, steel 100% 30 days Mon 1/4/24 Wed 8/5/24


reinforcement, vibrated concrete to
first floor slab

26 Sawn formwork, steel 100% 25 days Thu 9/5/24 Tue 11/6/24


reinforcement, vibrated concrete to
roof beam

27 Roof 35% 60 days Wed 12/6/24 Fri 23/8/24

28 Timber Roof Truss 70% 30 days Wed 12/6/24 Thu 18/7/24

29 Roof Covering 0% 20 days Fri 19/7/24 Mon


12/8/24

30 Gutter and rainwater goods 0% 10 days Tue 13/8/24 Fri 23/8/24

31 Staircase 39% 45 days Wed 12/6/24 Tue 6/8/24

32 Structural Work on Staircase 70% 25 days Wed 12/6/24 Fri 12/7/24

Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 1
ID Task Task Name June 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 0% 20 days Sat 13/7/24 Tue 6/8/24

34 Wall 81% 80 days Sat 6/4/24 Thu 18/7/24

35 Well burnt clay brick on 115mm 65% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall

36 Well burnt clay brick on 115mm 65% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall

37 Bonding Tie 100% 50 days Sat 6/4/24 Tue 11/6/24

38 Window 0% 15 days Fri 19/7/24 Tue 6/8/24

39 Window concrete lintel 0% 15 days Fri 19/7/24 Tue 6/8/24

40 Window frame and finishing 0% 15 days Fri 19/7/24 Tue 6/8/24

41 Door 0% 55 days Fri 19/7/24 Wed


25/9/24

42 Door concrete lintel 0% 15 days Fri 19/7/24 Tue 6/8/24

43 Door frame 0% 15 days Fri 19/7/24 Tue 6/8/24

44 Door leaf 0% 15 days Wed 7/8/24 Fri 23/8/24

45 Door painting 0% 15 days Sat 24/8/24 Wed


11/9/24

46 Iron mongery 0% 10 days Thu 12/9/24 Wed


25/9/24

47 Finishes 10% 70 days Wed 12/6/24 Thu 5/9/24

48 Floor Finishes 43% 40 days Wed 12/6/24 Wed


31/7/24

49 Floor tiles including toilet 90% 20 days Wed 12/6/24 Fri 5/7/24

50 Parquet flooring 20% 40 days Wed 12/6/24 Wed


31/7/24

51 Wall Finishes 0% 40 days Fri 19/7/24 Thu 5/9/24

52 Internal Wall Plastering 0% 30 days Fri 19/7/24 Fri 23/8/24

53 External Wall Plastering 0% 30 days Fri 19/7/24 Fri 23/8/24

54 Wall tiles 0% 20 days Tue 23/7/24 Wed


14/8/24

55 Wall Painting 0% 30 days Thu 25/7/24 Wed


28/8/24

56 Wall flashing 0% 20 days Fri 26/7/24 Sat 17/8/24

57 Chamfered and rebated timber 0% 30 days Thu 1/8/24 Thu 5/9/24


skirting

58 Ceiling Finishes 0% 35 days Fri 19/7/24 Thu 29/8/24

59 Ceiling frame and finishing 0% 15 days Fri 19/7/24 Tue 6/8/24

60 Ceiling Painting 0% 20 days Wed 7/8/24 Thu 29/8/24

61 Electrical Works 55% 225 days Thu 18/1/24 Fri 25/10/24

62 The provision of underground electrical 78% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24

63 Supply and install UPVC pipes on 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall

64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24

65 Supply and install the electrical fittings 0% 20 days Fri 19/7/24 Mon
and switch board 12/8/24

66 Sanitary Works 43% 65 days Wed 12/6/24 Thu 29/8/24

67 Internal Cold-water system 85% 45 days Wed 12/6/24 Tue 6/8/24

68 Internal Sanitary System 0% 45 days Sat 6/7/24 Thu 29/8/24

Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 2