Planned Work October
Planned Work October
Planned Work October
Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 100% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 100% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 100% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 100% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 100% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
30 Gutter and rainwater goods 100% 10 days Tue 13/8/24 Fri 23/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name October Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 100% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
40 Window frame and finishing 100% 15 days Fri 19/7/24 Tue 6/8/24
49 Floor tiles including toilet 100% 20 days Wed 12/6/24 Fri 5/7/24
57 Chamfered and rebated timber 100% 30 days Thu 1/8/24 Thu 5/9/24
skirting
59 Ceiling frame and finishing 100% 15 days Fri 19/7/24 Tue 6/8/24
62 The provision of underground electrical 100% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 100% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 100% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress