Planned Work October

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

ID Task Task Name October Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024

Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 100% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE

2 Preliminary and General Works 100% 290 days Wed 1/11/23 Fri 25/10/24

3 Contractor's Site Management 100% 290 days Wed 1/11/23 Fri 25/10/24

4 Contractor's Site Office 100% 290 days Wed 1/11/23 Fri 25/10/24

5 Worker's Quarters and Servies 100% 290 days Wed 1/11/23 Fri 25/10/24

6 Mobilization and demobilization of 100% 60 days Fri 1/12/23 Tue 13/2/24


excavator and lorry for excavation
works
7 Mobilization and demobilization of 100% 40 days Fri 1/12/23 Thu 18/1/24
piling rig

8 Mobilization and demobilization of 100% 55 days Sat 15/6/24 Wed


mobila crane for roof works 21/8/24

9 Substructure 100% 70 days Wed 1/11/23 Tue 23/1/24

10 Piling 100% 70 days Wed 1/11/23 Tue 23/1/24

11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23

12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab

13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile

14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23

15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap

16 Formwork 100% 25 days Sat 23/12/23 Tue 23/1/24

17 Sawn formwork, steel 100% 20 days Sat 23/12/23 Wed


reinforcement, vibrated concrete 17/1/24
to pile cap and stump

18 Sawn formwork, steel 100% 20 days Sat 30/12/23 Tue 23/1/24


reinforcement, vibrate concrete
to ground beam

19 Sawn formwork, steel 100% 10 days Sat 6/1/24 Wed


reinforcement, vibrated concrete 17/1/24
to ground slab

20 Superstructure 100% 200 days Thu 18/1/24 Wed


25/9/24

21 Frame 100% 115 days Thu 18/1/24 Tue 11/6/24

22 Sawn formwork, steel 100% 20 days Thu 18/1/24 Fri 9/2/24


reinforcement, vibrated concrete to
ground column

23 Sawn formwork, steel 100% 20 days Tue 13/2/24 Wed 6/3/24


reinforcement, vibrated concrete to
first floor beam

24 Sawn formwork, steel 100% 20 days Thu 7/3/24 Sat 30/3/24


reinforcement, vibrated concrete to
first floor column

25 Sawn formwork, steel 100% 30 days Mon 1/4/24 Wed 8/5/24


reinforcement, vibrated concrete to
first floor slab

26 Sawn formwork, steel 100% 25 days Thu 9/5/24 Tue 11/6/24


reinforcement, vibrated concrete to
roof beam

27 Roof 100% 60 days Wed 12/6/24 Fri 23/8/24

28 Timber Roof Truss 100% 30 days Wed 12/6/24 Thu 18/7/24

29 Roof Covering 100% 20 days Fri 19/7/24 Mon


12/8/24

30 Gutter and rainwater goods 100% 10 days Tue 13/8/24 Fri 23/8/24

31 Staircase 100% 45 days Wed 12/6/24 Tue 6/8/24

32 Structural Work on Staircase 100% 25 days Wed 12/6/24 Fri 12/7/24

Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 1
ID Task Task Name October Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 100% 20 days Sat 13/7/24 Tue 6/8/24

34 Wall 100% 80 days Sat 6/4/24 Thu 18/7/24

35 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall

36 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall

37 Bonding Tie 100% 50 days Sat 6/4/24 Tue 11/6/24

38 Window 100% 15 days Fri 19/7/24 Tue 6/8/24

39 Window concrete lintel 100% 15 days Fri 19/7/24 Tue 6/8/24

40 Window frame and finishing 100% 15 days Fri 19/7/24 Tue 6/8/24

41 Door 100% 55 days Fri 19/7/24 Wed


25/9/24

42 Door concrete lintel 100% 15 days Fri 19/7/24 Tue 6/8/24

43 Door frame 100% 15 days Fri 19/7/24 Tue 6/8/24

44 Door leaf 100% 15 days Wed 7/8/24 Fri 23/8/24

45 Door painting 100% 15 days Sat 24/8/24 Wed


11/9/24

46 Iron mongery 100% 10 days Thu 12/9/24 Wed


25/9/24

47 Finishes 100% 70 days Wed 12/6/24 Thu 5/9/24

48 Floor Finishes 100% 40 days Wed 12/6/24 Wed


31/7/24

49 Floor tiles including toilet 100% 20 days Wed 12/6/24 Fri 5/7/24

50 Parquet flooring 100% 40 days Wed 12/6/24 Wed


31/7/24

51 Wall Finishes 100% 40 days Fri 19/7/24 Thu 5/9/24

52 Internal Wall Plastering 100% 30 days Fri 19/7/24 Fri 23/8/24

53 External Wall Plastering 100% 30 days Fri 19/7/24 Fri 23/8/24

54 Wall tiles 100% 20 days Tue 23/7/24 Wed


14/8/24

55 Wall Painting 100% 30 days Thu 25/7/24 Wed


28/8/24

56 Wall flashing 100% 20 days Fri 26/7/24 Sat 17/8/24

57 Chamfered and rebated timber 100% 30 days Thu 1/8/24 Thu 5/9/24
skirting

58 Ceiling Finishes 100% 35 days Fri 19/7/24 Thu 29/8/24

59 Ceiling frame and finishing 100% 15 days Fri 19/7/24 Tue 6/8/24

60 Ceiling Painting 100% 20 days Wed 7/8/24 Thu 29/8/24

61 Electrical Works 100% 225 days Thu 18/1/24 Fri 25/10/24

62 The provision of underground electrical 100% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24

63 Supply and install UPVC pipes on 100% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall

64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24

65 Supply and install the electrical fittings 100% 20 days Fri 19/7/24 Mon
and switch board 12/8/24

66 Sanitary Works 100% 65 days Wed 12/6/24 Thu 29/8/24

67 Internal Cold-water system 100% 45 days Wed 12/6/24 Tue 6/8/24

68 Internal Sanitary System 100% 45 days Sat 6/7/24 Thu 29/8/24

Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 2

You might also like