Checklist 2nd Backfilling Layer 0+330 To 0+520 R-M ZONE 2
Checklist 2nd Backfilling Layer 0+330 To 0+520 R-M ZONE 2
Doc. Title:
Doc. No:
Checklist (CL) – For Earthworks
Date:1-Nov-2023
Approved Shop
1 Approved Setting-Out Details: Showing area, location & elevation for Drawing/Survey
cut, fill & backfill etc. as per approved Survey controlled points. Report
2 Compact the natural ground platform that will receive filling at least 90%
M.D.D. prior to placing any fill material on top of it.
Place backfill and fill soil materials evenly on all sides of structures to
6 required elevations, and uniformly along the full length of each structure.
☒
Under turf, lawns or unpaved areas: Scarify and re-compact top 150
9 mm below subgrade and compact each layer of backfill or fill soil
material at 98 percent
10 For Utility Trenches: Compact each layer of initial and final backfill soil
material at 98 percent.
☒
MOBCO Site Engineer MOBCO QA/QC Engineer AMAALA R epresentative
.
.