BLASTING & PAINTING REPORT


PRECISION EQUIPMENTS (CHENNAI) PVT LTD.,
)
SURFACE PREPARATION & PAINTING INSPECTION REPORT.
J
PROJECT Mis HPCL·MITTAL ENERGY LlMITED(HMEL) DATE: 28.12.2009
)
DESCRIPTION OF ITEM 522·E·203A WO.No.1209/14

LOCATION PRECISION EQUIPMENTS (CHENNAI) PVT L TD.,C~

SURFACE PREPARATION SA 2.5,(AS PER 6922·0642·PT·A08,REV.0) ACTUAL: SA 2.5

PROFILE & CLEANLINESS SPEC 60 TO 100 ACTUAL: 85 MIC

') RECORD OF BLASTING PRESSURE: 7 Kg

QUALITY OF COMPRESSED AIR : OK


')
TIME
ATMOSPHERIC " .
) DATE ACTIVITY
START FINISH
TEMP DEG. C
R.H% SURFACE TEMP
.
27.12.2009 GRITBLASTING 8.15AM 5.15PM 30 71 28

PRIMER COAT

o DATE PRODUCT BATCH NOS


TIME
THINNER%
DRY FILM THICKNESS

START FINISH REQUIRED ACTUAL


o INORGANIC
27.12.2009 ZINC SILICATE
PRIMER
PART A

PARTB
M/1647594

M/1648061
5.30PM 6.30PM c 10% 65 ·75 80 ·85'" V
)

SURFAqE TEMP DEG


DATE ACTIVITY TIME ATMOSPHERIC TEMP DEG C R.H%
'" C

27.12.2009 PRIMER 5.30PM 30 51% 28

o
,.

MIXING RATIO LlQUID:POWDER= 60:40 BY WEIGHT


o AIR LESS SPARY PAINTING DETAILES NOZZLE TIPSIZE 17

~1J'
\;);i.;j:I VISUAL OBSERVATION OF PRIMER COAT OK,/

COLOUR SHADE GREY


o
o NAME:
PECPL QC PECPLQ.C

o SIGNATURE:

o DATE:

o "

()

o
()