Hydro Test
Hydro Test
HT/PIPELINE/001
Project Name: White Oil Terminal / Classified Project No. :WOT/CLASSIFIED TANKS
Design Pressure: 1.50Mpa / 15 Bar Test Pressure: 19 Bar Holding Time: 24 Hrs
Start location of Hydrostatic test: Outside Road Culvert Near KSPL Compound wall
(Refer Drawing)
End location of test: Up to Product Pump House
(Refer Drawing)
Test medium temperature: Ambient
Signature
Date
Name