Professional Documents
Culture Documents
M A N U A L
M A N U A L
M
A
N
U
A
L
January 2002
ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
https://www.facebook.com/groups/Metal.Structures
Chapter Section Description Page No
2 Erection Procedure
2.1 Preparation
2.2 Erecting Main Frames
https://www.facebook.com/groups/Metal.Structures
2.3 Mezzanine Floors
2.3 Crane Beams
2.4 Sheeting Preparation
2.5 Sheeting - Walls
2.7 Sheeting - Roof
2.8 Miscellaneous
2.9 Fascia
3 Handling of Sheeting
3 Care & Handling
3.1 Unloading
3.2 Storage
3.3 Handling
3.4 Cutting and Fixing
Check-List
1
E R E C T I O N
January 2002
Introduction
This Erection Manual is designed to assist Zamil Steel builders and erection Contractors,
who are engaged in the erection of Pre-Engineered Steel Buildings, to understand some
basic and safe working practices. The manual is also intended to assist them in controlling
building quality and developing the erectors craftsmanship.
Even thogh it is not posible to indide all steel builders erecting practices in this manual
Zamil Steel based on its intensive experience in this fold recammanders careully following
the erection proceses illustrated in this publication It important to not that Zamil Steel issues
this publication as a guide for erection, we keep it up to the erection to learn from the tips
and advice in this manual Zamil Steel becous us responsibility whatsoeva for an erection
to been that meny an se live to improve erection It is worth noting that no matter how good
the design and the fabrication may be it is the perfect erection and the finishing of the
building that remains visible for many years to come.
https://www.facebook.com/groups/Metal.Structures
Erection of pre-engineered steel buildings maid be a simple operation if the basic prin-
ciples are followed and sensible decisions are made at the time of erection.
The major components comprise of, rigid frame columns and rafters, eave struts, purlins and
girts, flange braces, endwall columns and bracing systems which may be cables, rods,
angles or portal.
N M A N U A L 2
January 2002
1 Pre-Erection Steps
Lay-down area
1.1 The Erection Document
Erection Drawings used at site are the ones. marked as
“Issued for Construction.” Ensure that you are using
the latest revision. Drawings marked as “Approval
Drawings” shuld never be used for site works.
https://www.facebook.com/groups/Metal.Structures
Noted,” etc.
3
E R E C T I O N
January 2002
1 Pre-Erection Steps
1.2 Anchor Bolt Setting Plan The details along the bottom of the plan show bolt
The Anchor Bolt Setting Plan drawing shows the layout configuration and bolt projection. If grout is required
of all anchor bolts in a building the plan world under columns, (this applies to fixed base columns and
normally be on one sheet, however, for very large crane columns), the grout thickness is also shown.
buildings, the layout could be on two or more sheets.
It is extremely important to adhere to the dimensions.
The Anchor Bolt Setting Plan layout contains the In all case deviation shuld not exceed 6mm.
anchor bolt schedule, which is in the form of a table at
the bottom left corner showing quantities and sizes. The details along the bottom of the plan show bolt
configuration and bolt projection. If grout is required
The key plan shows out-to-out dimensions, bay under columns, (this applies to fixed base columns and
spacing dimensions, anchor bolt setting details and crane columns), the grout thickness is also shown.
critical dimensions for the building span.
It is extremely important to adhere to the dimensions.
In all case deviation shuld not exceed 6mm.
https://www.facebook.com/groups/Metal.Structures
ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
ANCHOR BOLT KEY PLAN
N M A N U A L 4
January 2002
1.3 Cross Section The Cross Section drawing may be typical, throughout,
The Cross Section is one of the most important draw- in standard buildings. In large and more complex jobs,
ings as it contains a lot of vital information. Columns there may be several Cross Section drawings identified
and rafter references, connection details, bolt sched- by grid numbers.
ules and flange brace schedules where applicable
details of and other details, strut tubes and flange brace
details are all illustrated.
https://www.facebook.com/groups/Metal.Structures
CROSS SECTION ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
CROSS SECTION
E R E C T I O N
January 2002
1.4 Roof Framing Plan
The Roof Framing Plan shows all the purlins and roof
bracing details. The part numbers for purlins, bracing
and eavestruts are clearly indicated including sag rods
and strut tubes (if avilble).
https://www.facebook.com/groups/Metal.Structures
ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
N M A N U A L
January 2002
1.5 Roof Sheeting Layout
On this layout, all roof panels are shown by length and
by part number. The panel laps are clearly indicated. If
the building has skylights, gutters and downspouts then
their positions would be shown clearly on the drawing.
https://www.facebook.com/groups/Metal.Structures
ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
ROOF SHEETING LAYOUT
E R E C T I O N
January 2002
1.6 Sidewall Sheeting & Framing
Depending on the job, sidewall framing and sheeting
may be on one drawing or more.
https://www.facebook.com/groups/Metal.Structures
ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
SIDWALL SHEETING
N M A N U A L
January 2002
Chapter 1 Pre-Erection Steps
Temporary Bracing
https://www.facebook.com/groups/Metal.Structures
Completion of the Main Frames
Sheeting- Roof
5 E R E C T I O N
January 2002
Chapter 1 Pre-Erection Steps
The second page has an index of the various sub- The sub total of weight is shown at the end of each
areas. Each sub-area then has its Bill of Materials (BOM) sub-area and also the total number of items. The last
on the remaining sheets. page indicates the total BOM quantity of items and
weight.
The BOM has 9 columns indicating:
The BOM is a reference to the items shown on the
1 - Line number Erection Drawings and must be used to double check
2 - Part number items against the packing list. It is also used to identify
3 - Quantity frame weights for crane capacities.
https://www.facebook.com/groups/Metal.Structures
ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
N M A N U A L 6
January 2002
Chapter 1 Pre-Erection Steps
https://www.facebook.com/groups/Metal.Structures
as near as possible to the place of erection. The laydown
area shall be cleaned and leveled. Fascias
Crane
7 E R E C T I O N
January 2002
1.11 Unloading Containers
Good preparation will make container unloading a
straightforward operation. Prepare a firm, level, asphalt,
concrete on compacted area. Unloading will be con-
siderably easier if a small step out of ___? wood is
made so that the inside base of the container is lev-
eled with the external ground. Unload the container
from the trailer using a mobile crane and four leg slings
or chains. Set the container on the ground, and level it, Fixing Crane
open the doors before final positioning.
https://www.facebook.com/groups/Metal.Structures
Attach chains to the front of the skid in the container,
and then attach it to the pulling vehicle. Take up the
Correct
strain on the chains, and steadily pull the skid from the
container. When the materials are clear off the con-
tainer, remove the skids from the container floor.
Aviation Snips
N M A N U A L 8
January 2002
2 Erection Procedure
2.1 Preparation
Prepare all materials for the first bay erection. Identify
the rafter sections required by part number, assemble
the rafter sections as near as possible to their lifting
positions. The splice connections are made with high
strength bolts; the sizes are shown on the drawing cross
section, identified as S1, S2, S3 etc. Tighten the splice
bolts and check for correct torque value using a cali-
brated torque wrench, or by turn of nut method. Attach
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
eave strut clips using high strength bolts. Fix flange Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
braces to the rafter using machine bolts, the flange
brace positions and part numbers are shown on the
drawing cross section. Flange braces are fitted on one
side of the rafter only. For uniformity it is preferable to
maintain the same side throughout the building.
https://www.facebook.com/groups/Metal.Structures
guying, they can stretch and break. They are also un-
suitable for aligning purposes.
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
Prepare the mobile crane and Forklift for erection.
E R E C T I O
8
N
January 2002
This formula may require some adjustment depending
on rafter weight and configuration.
https://www.facebook.com/groups/Metal.Structures
Install the high strength bolt nuts and washers in the
knee connection, K1. The bolt is normally placed from
the top, with the nut and washer on the underside.
Hand tighten the bolts. Ratchet pullers are attached to
the guy wires, and connected to suitable
N M A N U A L
January 2002
Chapter 2 Erection Procedure
https://www.facebook.com/groups/Metal.Structures
strength bolts at the knee connection are fully
tightened to their respective torque values. Times spent
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
on correct alignment of the first bay will reap benefits Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
as work proceeds with the remaining bays.
9 E R E C T I O N
January 2002
Chapter 2 Erection Procedure
https://www.facebook.com/groups/Metal.Structures
2.3 Mezzanine Floors
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
When mezzanine floors are provided, they are erected Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
with the main frames, generally prior to sheeting.
The decking panels are attached by 32mm self drilling ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
fasteners without washers. Openings for stairs and pen-
etrations are framed before fixing the reinforcement.
N M A N U A L 10
January 2002
Chapter 2 Erection Procedure
https://www.facebook.com/groups/Metal.Structures
Alignment is achieved by setting each end of the beam
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
to the correct dimension as shown on the drawing, and Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
stretching a line from end to end, alternately, a theodo-
lite or lazer beam can be used if available.
11 E R E C T I O N
January 2002
Chapter 2 Erection Procedure
Girts may sag under their own dead lod, to over come
this the girts are temporarily supported in a horizontal
line with timber props from floor to girt, girt to girt, girt
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
to eave strut. The props remain in place until the wall Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
panels are screwed, they can then be removed and
relocated to the next bay, the girts will remain straight
and horizontal after the panels are installed. In bays
over 8.5m, sag rods are provided and these are used
to align the girts.
https://www.facebook.com/groups/Metal.Structures
relation to the steel line, mark the starting position, and
then mark out the guage of the sheets along the for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
concrete notch.This will provide a check against “creep” Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
or “bunching” of the panels, an important point in or-
der for the corner trims and accessories to fit as de-
tailed.
All screws are self drilling and require an electric screw- ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
gun with a speed of 2000 to 2500 RPM. Depth sensi-
tive or torque regulated screw-guns should be used to
control the screw
https://www.facebook.com/groups/Metal.Structures
The preferred procedure is to complete all wall sheet-
ing before starting the roof, as the eave trim covers the for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
top of the wall panel and fits under the roof panel. Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
Outside foam closures are placed between the wall
panel and the eave trim to provide a dust free junction.
https://www.facebook.com/groups/Metal.Structures
els. When both slopes of the roof panel have been
fixed, the ridge panel. connects both slopes.
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
As work proceeds, it is important to keep the roof area
clean, a soft brush should be readily available to sweep
off drill swarf, which if left will cause surface corrosion.
2.8 Miscellaneous
Having completed the roofing,gable trims are installed,
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
outside foam closures are used against the end-wall Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
https://www.facebook.com/groups/Metal.Structures
adjusting nuts on the trolley trucks should be set equally,
final adjustments can be made after hanging the doors.
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
Bottom running doors (B1) have wheels fixed in the
bottom member of the door framing
2.9 Fascia
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Fascia posts are bolted to the brackets, fascia girts are Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
15 E R E C T I O N
January 2002
Chapter 2 Erection Procedure
https://www.facebook.com/groups/Metal.Structures
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
N M A N U A L 16
January 2002
Chapter
https://www.facebook.com/groups/Metal.Structures
Other useful tips in achieving a quality job are: Use a
torque or depth sensitive screwgun this will ensure cor-
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
rect fixing of fasteners and avoid sheet damage. Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
3.1 Unloading
Sheets are packed in bundles, and may be unloaded
by a suitable forklift truck or crane. Care must be taken
not to “break the back” of the sheets when unloading.
use a spreader if necessory Do not use chains or cable
slings for unloading, unless good protection is provided
for the the corners of the bundle.
3.3 Handling
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Care should be taken when handling sheets. Erectors Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
should use clean gloves to avoid dirty marks, oil or
grease stains on sheets. When handling individual
17 E R E
panels from the stack, each panel should be lifted clear, C T I O N
January 2002
dragging will cause scratches.
Chapter 3 Care & Handling of Zamil Steel Sheeting
https://www.facebook.com/groups/Metal.Structures
should be left clean.
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
3.6 Paint Repair
For minor scratches, a small brush can be used to
apply touch-up paint of matching color to the
damaged area.
I f da m a ge h a s a f fe c te d t h e ga l va n i z e d
coating, then the damaged area should be coated
w i t h s p e c i a l p r i m e r fo l lowe d by a m at c h i n g
polyurethane finish coat.
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
N M A N U A L 18
January 2002
Chapter 3 Care & Handling of Zamil Steel Sheeting
https://www.facebook.com/groups/Metal.Structures
fall as the sprinkler system causes the water to bounce,
thus finding any weakness in lap conditions.
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
19
E R E C T I O N
January 2002
Chapter 3 Care & Handling of Zamil Steel Sheeting
3.9 Reminaers
1. Check starting position for roof and wall panels.
https://www.facebook.com/groups/Metal.Structures
corrugations.
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
7. Foam closures are not well fitted. Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
N M A N U A L 20
January 2002
Chapter
https://www.facebook.com/groups/Metal.Structures
• Check electric cables for hand tools, discard frayed for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
or split cables. attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
• Ensure that high strength bolts are used where indi for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
cated. attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
• Ensure that high strength bolts are correctly tightended. ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
• Maintain a clean and tidy site, thus avoiding meterial
loss or accidents.
21
E R E C T I O N
January 2002
Chapter 4 Safety & loss prevention for safety reasons there are precautions that need to be taken during erection.
• Use the correct tools for the job, wrong tools will
damage materials and produce poor quality.
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
• Finally, take out contractors all Risk Insurance, even
the best can have an accident.
https://www.facebook.com/groups/Metal.Structures
for very large buildxxxxxxxxxings, could be on 2 or more sheetsxxxxxxxxx.
Erection drawingsxxxxxxxxxx are not to scale, so nevxxxxxxxer
attempxxxxxxxxxxxx arexxxxxxxx xxxxxxxxxxx xxxxxxxxxxx xxxxxxxx
N M A N U A L 22
January 2002
C heck list
Job No: Bildings. No: Site Location:
Customer: Inspection Date:
Yes No
1.1 Is the roof & wall bracing installed
1.2 Is the bracing tight
1.3 Are the flange braces installed at rafters & columns
1.4 Are the eave strut & purlin clips fitted (where required)
1.5 Are all high strength bolts fitted in correct locations
1.6 Are the washers installed with H. S. B.
1.7 Is the thread projection correct
Framing
1.8 Are the H. S. B’s crrectly tightened
1.9 Are the main frames correctly plumbed & aligned
1.10 Are the crane beams braced & aligned
https://www.facebook.com/groups/Metal.Structures
1.11 Are stoppers installed on crane beams
1.12 Are purlins & girts straight & aligned
1.13 Are all machine bolts correctly fitted in secondary framing
1.14 Has primer paint been touched-up
2.1 Is the base angle securely fastened to concrete
2.2 Are the sheets fastened in the correct location
2.3 Are the sheets fastened with correct lenght fastener
2.4 Are the sheets plumbed
Wall sheeting 2.5 Are the sheets correctly lapped
2.6 Are the corner trims crrectly fitted & fastened
23
E R E C T I O N
January 2002
Check list
Yes No
https://www.facebook.com/groups/Metal.Structures
5.5 Have the gutter endcaps been fitted, sealed & rivetted
6.1 Are personnel doors operating correctly
6.2 Are locksets, panic devices, closers correctly adjested
6.3 Are the sliding door operating smoothly
6.4 Are the roll-up doors correctly tensioned & operating smoothly
Accessories
6.5 Are the windows sliding freely & locking correctly
6.6 Are ridge vent dampers operating correctly
6.7 Have ridge vent flashing & closures been installed
6.8 Have roof curb or penetrations been sealed
7.1 Has the work been cleaned of, specially roof & gutters
7.2 Has touch-up painting been done (where required) ﻣﺟﻣﻭﻋﺔ ﻣﻬﻧﺩﺳﻳﻥ ﺍﻟﻣﻧﺷﺄﺕ ﺍﻟﻣﻌﺩﻧﻳﺔ
7.3 Have all trims and flashings been installed
7.4 Are all flashing self draining
General
7.5 Have cap trims been sealed at overlaps
7.6 Has trimming been neatly executed
7.7 Are fassias, (where fitted) in line
7.8 IST the general appearance pleasing
N M A N U A L 24
January 2002
HEAD OFFICE
PO Box 877 Dammam 31421
Saudi Arabia
Phone (966 3) 847 1840
Fax (966 3) 847 1291
saudimarketing@zamilsteel.com
www.zamilsteel.com
EGYPT
PO B0x 11 Main Post Office
6th of October City Egypt
Phone (20 11) 34 1250
Fax (2011) 34 1247
egyptmarketin@zamilsteel.com
VIETNAM
Noi Bai Industrial Zone
Quang Tien Commune
Soc Son District Hanoi
Phone (84 4) 885 0800
Fax (84 4) 885 0801
vietnammarketing@zamilsteel.com
https://www.facebook.com/groups/Metal.Structures
CHINA
2605 Jin Mao Tower
88 Shi Ji Avenue
Pudong Shanghai 200120
Phone (86 21) 5047 2600
Fax (86 21) 5047 2606
zsshanghai@zamilsteel.com
INDIA
Nelson Tower
4th wing 117 Nelson
Manickam Road
Aminijikarai Chennai
Phone (91 44) 374 3316
Fax (91 44) 374 3315
zscchennai@zamilsteel.com
AREA OFFICES
E R E C T I O N
January 2002
www.zamilsteel.com