Professional Documents
Culture Documents
Critical Path
Critical Path
Critical Path
108 days Thu 5/10/23 Mon 4/03/24 Mon 16/10/23 Mon 4/03/24
17 days Thu 5/10/23 Fri 27/10/23 Mon 16/10/23 Mon 4/03/24
5 days Mon 16/10/23 Fri 20/10/23 Tue 7/11/23 Tue 14/11/23
2 days Mon 23/10/23 Tue 24/10/23 Fri 1/03/24 Mon 4/03/24
3 1 wk Mon 23/10/23 Fri 27/10/23 Tue 27/02/24 Mon 4/03/24
2 wks Thu 5/10/23 Wed 18/10/23 Tue 20/02/24 Mon 4/03/24
1 wk Thu 5/10/23 Wed 11/10/23 Tue 27/02/24 Mon 4/03/24
10 days Tue 14/11/23 Mon 27/11/23 Tue 14/11/23 Mon 4/03/24
3 3 days Tue 14/11/23 Thu 16/11/23 Tue 14/11/23 Thu 16/11/23
9 1 wk Fri 17/11/23 Thu 23/11/23 Fri 17/11/23 Thu 23/11/23
2 days Tue 14/11/23 Wed 15/11/23 Fri 1/03/24 Mon 4/03/24
52 days Thu 23/11/23 Mon 5/02/24 Fri 24/11/23 Mon 5/02/24
10 10 days Thu 23/11/23 Thu 7/12/23 Fri 24/11/23 Fri 8/12/23
13 22 days Fri 8/12/23 Mon 8/01/24 Fri 8/12/23 Mon 8/01/24
13 5 days Fri 8/12/23 Thu 14/12/23 Fri 8/12/23 Thu 14/12/23
15 5 days Fri 15/12/23 Thu 21/12/23 Fri 15/12/23 Thu 21/12/23
16 12 days Fri 22/12/23 Mon 8/01/24 Fri 22/12/23 Mon 8/01/24
17 3 wks Tue 9/01/24 Mon 29/01/24 Tue 9/01/24 Mon 29/01/24
18 5 days Tue 30/01/24 Mon 5/02/24 Tue 30/01/24 Mon 5/02/24
13 days Tue 6/02/24 Thu 22/02/24 Tue 6/02/24 Thu 22/02/24
19 3 days Tue 6/02/24 Thu 8/02/24 Tue 6/02/24 Thu 8/02/24
21 2 wks Fri 9/02/24 Thu 22/02/24 Fri 9/02/24 Thu 22/02/24
7 days Tue 2/01/24 Wed 10/01/24 Fri 23/02/24 Mon 4/03/24
5 days Tue 2/01/24 Mon 8/01/24 Fri 23/02/24 Thu 29/02/24
24 2 days Tue 9/01/24 Wed 10/01/24 Fri 1/03/24 Mon 4/03/24
7 days Fri 23/02/24 Mon 4/03/24 Fri 23/02/24 Mon 4/03/24
22 2 days Fri 23/02/24 Mon 26/02/24 Fri 23/02/24 Mon 26/02/24
27 3 days Tue 27/02/24 Thu 29/02/24 Tue 27/02/24 Thu 29/02/24
28 2 days Fri 1/03/24 Mon 4/03/24 Fri 1/03/24 Mon 4/03/24
Manual Task Start-only Deadline
Page 1
Early Start Early Finish cost Labour Material cost
Critical Slack
Critical Split
Progress
Resource Names
Machines and equipment
October 2023 November 2023 December 2023 January 2024 February 2024
March 2024 April 2
9 14 19 24 29 3 8 13 18 23 28 3 8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2 7 12
17 22 27 1 6
PM,stakeholders,business analytics HR,PM
Finanace personnel,PM sregulatory specialists
PM,legal experts
Office supplies, softwares, administrative expensives Office supplies, softwares, administrative expensives Office P
supplies, softwares, administrative expensives N/a M
N/a ,
s
t
a
k
surveyors Engineers(electrical,civil,environmental)
Procurment specialists
surveying equipment like total station, GPS receiever, level, measuring tape etc Engineering tools softwares
like CAD sof and electrical simulation softwarestwares N/a
construction workers,Machine operators
Earth moving machinery,bulldozers, excavator, grader, compactor, safety gear constructio
n
workers,Ma
chine
construction workers construction workers construction
workers Installation team Electricians
Auger, , safety gear
Concrete mixer, wheelbarrow, level and shovel, safety gear etc scaffolding, welding machine, cranes, power
tools, safety gear lifting equipment, power tools, safety gear
Electrical tools and equipment, safety gear
Electrical engineers,technicians,data analytics
Electricians,Electrical engineer
testing equipment
electrical tools and equipment, lifting machines
Electrical engineer,technicians Training Instrctors
N/a N/a
Ph
ase
5-
O
Inspection team PM,review team PM,administrative staff
Inspection equipment like Multimeters, insulation testers, clamp meters, infrared camera etc N/a
N/a
Project: Hasan.mpp Date: Tue 10/10/23 Task Split Project Summary Inactive Task
Milestone Inactive Milestone
Summary Inactive Summary
M Start-only Finish-only External D
a Tasks e
n External Milestone a
u d
a l
l i
n
T e
a
s C
k Page 2 r
M
a
n
u
a
l
P
r
o
g
il 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 3 8 13 18 23
Page 3
arch 2025 April 2025 May 2025 June
22 27 1 6 11 16 21 26 1 6 11 16 21 26 31
Manual Progress
Slack