Professional Documents
Culture Documents
Rate Analysis 14-10-22
Rate Analysis 14-10-22
Rate Analysis 14-10-22
BILL # 1 (EarthWork)
Roads
101 Clearing & grubbing Sqm 148,846.40 25.85 3,847,679.44
108c
Formation of Embankment from Borrow Excavation Cum - 438.30 -
in common Material
109a Subgrade preparation in earthcut Sqm 148,846.40 77.89 11,593,646.10
110 Imroved Sub Grade Cum - 599.13 -
Parking Areas (Terminals) ###
108c
Formation of Embankment from Borrow Excavation Cum 1,019,799.00 438.30 446,977,901.70
in common Material
BILL WISE SUMMARY
CONSTRUCTION OF BORDER CROSSING FACILITIES AT CHAMAN
109a Subgrade preparation in earthcut Sqm 167,678.23 77.89 13,060,457.33
110 Imroved Sub Grade Cum 26,242.20 599.13 15,722,489.29
BILL # 2 (Sub Base & Base) ###
Roads ###
209a Breaking of raod pavement structure Cum 3,000.00 612.53 1,837,590.00
201 Granular Sub Base Cum 18,109.75 1,446.67 26,198,833.84
206b Water Bound Macadam Cum 23,473.91 1,777.39 41,722,292.89
203b Asphalt Base Coarse class B Cum 5,626.35 18,726.35 105,360,961.87
BILL WISE SUMMARY
CONSTRUCTION OF BORDER CROSSING FACILITIES AT CHAMAN
Parking Areas (Terminals) ###
201 Granular Sub Base Cum 38,272.83 1,446.67 55,368,161.49
206b Water Bound Macadam Cum 5,015.25 1,777.39 8,914,048.09
BILL # 3 (Surfacing & Road pavement) ###
209b Scarification / Preparation of Existing Rough Surface Sqm 3,847.50 68.64 264,092.40
302a
BITUMINOUS PRIME Sqm 121,977.50 125.45 15,302,077.38
COAT
303a
BITUMINOUS TACK Sqm 121,825.50 50.25 6,121,731.38
COAT.
305b Asphalt Wearing Coarse Class B (Roads) Cum 10,206.42 20,313.45 207,327,642.98
BILL WISE SUMMARY
CONSTRUCTION OF BORDER CROSSING FACILITIES AT CHAMAN
305b Asphalt Wearing Coarse Class B (Parking Areas) Cum 2,507.62 20,313.45 50,938,474.43
Parking Areas (Terminals) RIGID PAVEMENT ###
Culverts ###
107a Str Excavation in Common Material Cum 2,727.79 367.19 1,001,616.48
401f Lean Concrete Cum 142.99 6,540.21 935,151.93
107e Common Backfill Cum 366.15 269.26 98,589.55
401a1ii Concrete class A-1 (Bed) Cum 492.24 11,949.12 5,881,787.03
401a1iii Concrete Class A-1 (Walls) Cum 1,099.23 12,424.68 13,657,543.72
404b Steel Reinforcement Gde-60 Ton 181.43 119,897.49 21,752,615.78
Drains ###
Conduit ###
108a FOE from Roadway Excavation in Common Material Cum 138,600.00 403.91 55,981,926.00
Perforated pipes 125 mm dia for weep holes Rmtr 1,120.00 500.00 560,000.00
509e Grouted Rip Rap Stone Pitching class B Cum 918.00 5,228.83 4,800,065.94
Dikes ###
509e Grouted Rip Rap Stone Pitching class B Cum 1,769.28 5,228.83 9,251,264.34
Flyover ###
604b Metal Guard Rail End Pieces Each 22.00 5,758.36 126,683.92
604d Steel Post of Metal Guard Rail Each 372.50 5,255.90 1,957,822.75
404h Reinforcement (Structural shapes) as per ASTM-A-37 TON 12.75 150,586.00 1,919,971.50
2 Km/Ltr @ 6 Km Lead
11 Ltr/Hour
9 Ltr/Hour 12
2 Ltr/Hour
2 Ltr/Hour
14 Ltr/Hour 18
4 Ltr/Hour
Item No. 101
Description: CLEARING AND GRUBBING
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1021 Supervisor 1 8 336.54 2,692.31
1022 Surveyor 1 2 408.65 817.31
1041 Helper 2 2 134.62 538.46
1051 Labour 8 8 120.19 7,692.31
Total 11,740.38
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3007 Grader 165 HP 1 4 6,314.95 25,259.79
3005 Front End Loader 2.50 Cum 1 8 5,462.78 43,702.22
3033 Dumper 10 T 1 6 2,755.43 16,532.56
Total 85,494.57
(C) MATERIAL
CODE Description Unit Qty Rate Amount
0.00
Total 0.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 97,234.95
D.2 Cost per Sqm 27.78
D.3 Overhead & Profits @ 25% 6.95
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 2 192.31 384.62
1041 Helper 2 2 134.62 538.46
1051 Labour 2 8 120.19 1,923.08
Total 5,538.46
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3008 Grader 140 HP 1 4 5,534.89 22,139.57
3016 Combination Roller 10 - 12 T 1 9 4,464.92 40,184.32
3025 Water Tank Tow Type 4000 Ltr 3 8 2,161.07 51,865.74
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
Total 116,439.15
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2065 Water 1000 Ltr 105 90.00 9,450.00
2009 Soil Class - A 4 Cum 141.28 0.00
Total 9,450.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 131,427.61
D.2 Cost per Sqm. 37.55
D.3 Overhead & Profits @ 25% 9.39
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 2 480.77 961.54
1021 Supervisor 3 8 336.54 8,076.92
1022 Surveyor 1 2 408.65 817.31
1041 Helper 2 2 134.62 538.46
Total 10,394.23
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3002 Bulldozer 120 HP 1 6 5,467.18 32,803.09
3006 Front End Loader 1.50 Cum 2 5 4,514.45 45,144.52
3032 Dumper 18 T 4 6 4,118.89 98,853.34
Total 176,800.95
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2065 Water 1000 Ltr 90.00 0.00
Total 0.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 187,195.18
D.2 Cost per Cum. 415.99
D.3 Overhead & Profits @ 15% 62.40
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1012 Foreman Earthwork 1 8 360.58 2,884.62
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 8 192.31 1,538.46
1041 Helper 2 8 134.62 2,153.85
1051 Labour 2 8 120.19 1,923.08
Total 13,115.38
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3003 Bulldozer 90 HP 1 6 3,806.51 22,839.07
3005 Front End Loader 2.50 Cum 1 6 5,462.78 32,776.66
3008 Grader 140 HP 1 3 5,534.89 16,604.68
3016 Combination Roller 10 - 12 T 2 4 4,464.92 35,719.40
3024 Water Tank Bowser Type 18000 Ltr 1 4 2,893.05 11,572.20
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
3196 Tractor Trolley 4 6 2,391.86 57,404.65
Total 179,166.18
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2065 Water 1000 Ltr 90 90.00 8,100.00
Total 8,100.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 200,381.57
D.2 Cost per Cum. 445.29
D.3 Overhead & Profits @ 25% 111.32
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 2 480.77 961.54
1012 Foreman Earthwork 1 8 360.58 2,884.62
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 8 192.31 1,538.46
1041 Helper 2 8 134.62 2,153.85
1051 Labour 2 8 120.19 1,923.08
Total 12,153.85
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3003 Bulldozer 90 HP 1 6 3,806.51 22,839.07
3005 Front End Loader 2.50 Cum 1 6 5,462.78 32,776.66
3008 Grader 140 HP 1 4 5,534.89 22,139.57
3016 Combination Roller 10 - 12 T 2 4 4,464.92 35,719.40
3023 Tractor 50 HP 4 4 1,901.05 30,416.86
3024 Water Tank Bowser Type 18000 Ltr 2 4 2,893.05 23,144.41
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
3196 Tractor Trolley 9 6 2,391.86 129,160.45
Total 298,445.95
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2065 Water 1000 Ltr 90 90.00 8,100.00
Total 8,100.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 318,699.79
D.2 Cost per Cum. 708.22
D.3 Overhead & Profits @ 25% 177.06
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1012 Foreman Earthwork 1 8 360.58 2,884.62
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 8 192.31 1,538.46
1041 Helper 2 8 134.62 2,153.85
1051 Labour 4 8 120.19 3,846.15
Total 15,038.46
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3008 Grader 140 HP 1 4 5,534.89 22,139.57
3016 Combination Roller 10 - 12 T 2 4 4,464.92 35,719.40
3023 Tractor 50 HP 4 3 1,901.05 22,812.65
3024 Water Tank Bowser Type 18000 Ltr 2 4 2,893.05 23,144.41
3086 Pump 4 " Delivery (Diesel) 1 4 1,124.76 4,499.05
Total 108,315.07
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2009 Soil Class - A 4 Cum 550 141.28 77,704.00
2065 Water 1000 Ltr 90 90.00 8,100.00
Total 85,804.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 209,157.53
D.2 Cost per Cum. 464.79
D.3 Overhead & Profits @ 25% 116.20
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1012 Foreman Earthwork 1 8 360.58 2,884.62
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 8 192.31 1,538.46
1041 Helper 2 8 134.62 2,153.85
1051 Labour 2 8 120.19 1,923.08
Total 13,115.38
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3003 Bulldozer 90 HP 1 6 3,806.51 22,839.07
3005 Front End Loader 2.50 Cum 1 6 5,462.78 32,776.66
3008 Grader 140 HP 1 3 5,534.89 16,604.68
3016 Combination Roller 10 - 12 T 2 4 4,464.92 35,719.40
3024 Water Tank Bowser Type 18000 Ltr 1 4 2,893.05 11,572.20
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
3196 Tractor Trolley 4 6 2,391.86 57,404.65
Total 179,166.18
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2065 Water 1000 Ltr 90 90.00 8,100.00
Total 8,100.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 200,381.57
D.2 Cost per Cum. 445.29
D.3 Overhead & Profits @ 25% 111.32
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1012 Foreman Earthwork 1 8 360.58 2,884.62
1021 Supervisor 1 8 336.54 2,692.31
1022 Surveyor 1 4 408.65 1,634.62
1023 Assistant Surveyor 1 8 192.31 1,538.46
1041 Helper 2 8 134.62 2,153.85
1051 Labour 4 8 120.19 3,846.15
Total 16,673.08
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3007 Grader 165 HP 2 6 6,314.95 75,779.37
3015 Combination Roller 18 T 2 8 4,729.35 75,669.56
3024 Water Tank Bowser Type 18000 Ltr 2 6 2,893.05 34,716.61
3086 Pump 4 " Delivery (Diesel) 1 6 1,124.76 6,748.58
Total 192,914.12
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2018 Granular Sub Base (B) Cum 650 706.40 459,160.00
2065 Water 1000 Ltr 90 90 8,125.20
Total 467,285.20
(D) SUMMARY
D.1 Basic Cost (A + B + C) 676,872.40
D.2 Cost per Cum 1,504.16
D.3 Overhead & Profits @ 25% 376.04
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1012 Foreman Earthwork 1 8 360.58 2,884.62
1021 Supervisor 1 8 336.54 2,692.31
1022 Surveyor 1 8 408.65 3,269.23
1041 Helper 2 8 134.62 2,153.85
1051 Labour 2 8 120.19 1,923.08
Total 14,846.15
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3007 Grader 165 HP 2 6 6,314.95 75,779.37
3015 Combination Roller 18 T 2 7 4,729.35 66,210.87
3024 Water Tank Bowser Type 18000 Ltr 2 4 2,893.05 23,144.41
3086 Pump 4 " Delivery (Diesel) 1 4 1,124.76 4,499.05
Total 169,633.70
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2014 Crushed / Natural Aggregate Base "A" Cum 437.5 1,342.16 587,195.00
2065 Water 1000 Ltr 50 90.00 4,500.00
Total 591,695.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 776,174.85
D.2 Cost per Cum 2,217.64
D.3 Overhead & Profits @ 25% 554.41
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 8 480.77 3,846.15
1002 Asphalt Plant Engineer 1 10 408.65 4,086.54
1011 Foreman Asphalt 1 10 360.58 3,605.77
1021 Supervisor 1 10 336.54 3,365.38
1022 Surveyor 1 8 408.65 3,269.23
1023 Assistant Surveyor 1 8 192.31 1,538.46
1041 Helper 4 8 134.62 4,307.69
1051 Labour 30 10 120.19 36,057.69
Total 60,076.92
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3004 Front End Loader 3.00 Cum 1 8 6,236.48 49,891.81
3011 Tandem Vibratory Roller 10-12 T 2 10 3,369.24 67,384.89
3018 P.T.R. (9 - Wheeler) 21 T 2 10 4,179.55 83,591.00
3025 Water Tank Tow Type 4000 Ltr 1 10 2,161.07 21,610.72
3032 Dumper 18 T 8 8 4,118.89 263,608.91
3055 Asphalt Plant 80 T 1 8 31,727.03 253,816.25
3058 Paver 4 M Wide 1 8 11,793.33 94,346.60
3061 Compressor 300 CFM 1 6 3,808.53 22,851.17
Total 857,101.35
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2024 Aggregate 1-1/2"-3/4" Cum 95.55 1,412.80 134,993.04
2025 Aggregate 3/4" - 3/8" Cum 52.50 1,412.80 74,172.00
2026 Aggregate 3/8"- No. 4 Cum 42.00 1,412.80 59,337.60
2027 Aggregate No. 4 - N0. 200 Cum 80.85 1,412.80 114,224.88
2028 Filter Material Cum 11.55 635.76 7,343.03
2041 Asphalt Grade 60/70 Ton 18.12 157,081.60 2,847,057.50
2065 Water 1000 Ltr 4.00 90.00 360.00
2111 Diesel (LDO) Ltr 5400.00 118.31 638,874.00
Total 3,876,362.05
(D) SUMMARY
D.1 Basic Cost (A + B + C) 4,793,540.33
D.2 Cost per Cum 25,497.55
D.3 Overhead & Profits @ 25% 6,374.39
Total Cost per Cum 31,871.94
Item No. 209a
Description: BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1012 Foreman Earthwork 1 8 360.58 2,884.62
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 8 192.31 1,538.46
1041 Helper 1 8 134.62 1,076.92
Total 8,192.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3001 Bulldozer 200 HP 1 8 10,903.53 87,228.25
3005 Front End Loader 2.50 Cum 1 8 5,462.78 43,702.22
3015 Combination Roller 18 T 1 8 4,729.35 37,834.78
3024 Water Tank Bowser Type 18000 Ltr 1 8 2,893.05 23,144.41
3032 Dumper 18 T 4 8 4,118.89 131,804.46
3086 Pump 4 " Delivery (Diesel) 1 4 1,124.76 4,499.05
Total 328,213.16
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2065 Water 1000 Ltr 85 90.00 7,650.00
Total 7,650.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 344,055.46
D.2 Cost per Sqm. 917.48
D.3 Overhead & Profits @ 25% 229.37
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 3 480.77 1,442.31
1011 Foreman Asphalt 2 7 360.58 5,048.08
1021 Supervisor 2 7 336.54 4,711.54
1023 Assistant Surveyor 1 4 192.31 769.23
1041 Helper 2 4 134.62 1,076.92
1051 Labour 3 8 120.19 2,884.62
Total 15,932.69
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3005 Front End Loader 2.50 Cum 1 2 5,462.78 10,925.55
3019 P.T.R. (9 - Wheeler) 18 T 1 6 3,419.69 20,518.17
3021 Static Tandem Roller 8 T 1 3 2,893.46 8,680.38
3023 Tractor 50 HP 1 6 1,901.05 11,406.32
3033 Dumper 10 T 4 4 2,755.43 44,086.83
3048 Power Broom 1 3 1,265.87 3,797.61
3051 Bitumen Dist. Tow Type 2000 Ltr 1 4 2,439.94 9,759.75
3088 CHIPPING SPREADER 3 METER WIDE 1 4 2,728.40 10,913.59
Total 120,088.21
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2024 Aggregate 1-1/2"-3/4" Cum 4.00 1,412.80 5,651.20
2025 Aggregate 3/4" - 3/8" Cum 39.20 1,412.80 55,381.76
2027 Aggregate No. 4 - N0. 200 Cum 4.40 1,412.80 6,216.32
2041 Asphalt Grade 60/70 Ton 7.42 157,081.60 1,165,545.47
2043 Asphalt M.C 70 Ton 1.91 90,000.00 171,900.00
Total 1,404,694.75
(D) SUMMARY
D.1 Basic Cost (A + B + C) 1,540,715.65
D.2 Cost per Sqm. 821.72
D.3 Overhead & Profits @ 25% 205.43
Total Cost per Sqm 1,027.14
Item No. 302 a
Description: CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 2 480.77 961.54
1011 Foreman Asphalt 1 4 360.58 1,442.31
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 2 192.31 384.62
1041 Helper 2 2 134.62 538.46
1051 Labour 2 8 120.19 1,923.08
Total 7,942.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3023 Tractor 50 HP 1 4 1,901.05 7,604.22
3025 Water Tank Tow Type 4000 Ltr 1 1 2,161.07 2,161.07
3048 Power Broom 1 4 1,265.87 5,063.48
3051 Bitumen Dist. Tow Type 2000 Ltr 1 8 2,439.94 19,519.50
3086 Pump 4 " Delivery (Diesel) 1 1 1,124.76 1,124.76
Total 35,473.03
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2043 Asphalt M.C 70 Ton 8.59 90,000.00 772,650.00
2065 Water 1000 Ltr 2 90.00 180.00
Total 772,830.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 816,245.34
D.2 Cost per Sqm. 136.04
D.3 Overhead & Profits @ 25% 34.01
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 2 480.77 961.54
1011 Foreman Asphalt 1 4 360.58 1,442.31
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 2 192.31 384.62
1041 Helper 2 2 134.62 538.46
1051 Labour 2 8 120.19 1,923.08
Total 7,942.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3023 Tractor 50 HP 1 4 1,901.05 7,604.22
3048 Power Broom 1 4 1,265.87 5,063.48
3051 Bitumen Dist. Tow Type 2000 Ltr 1 8 2,439.94 19,519.50
Total 32,187.19
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2041 Asphalt Grade 60/70 Ton 6.3 157,081.60 989,614.08
Total 989,614.08
(D) SUMMARY
D.1 Basic Cost (A + B + C) 1,029,743.58
D.2 Cost per Sqm. 68.65
D.3 Overhead & Profits @ 25% 17.16
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 8 480.77 3,846.15
1002 Asphalt Plant Engineer 1 10 408.65 4,086.54
1011 Foreman Asphalt 1 10 360.58 3,605.77
1021 Supervisor 1 10 336.54 3,365.38
1022 Surveyor 1 8 408.65 3,269.23
1023 Assistant Surveyor 1 8 192.31 1,538.46
1041 Helper 4 8 134.62 4,307.69
1051 Labour 30 8 120.19 28,846.15
Total 52,865.38
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3004 Front End Loader 3.00 Cum 1 8 6,236.48 49,891.81
3011 Tandem Vibratory Roller 10-12 T 2 10 3,369.24 67,384.89
3019 P.T.R. (9 - Wheeler) 18 T 2 10 3,419.69 68,393.89
3025 Water Tank Tow Type 4000 Ltr 1 10 2,161.07 21,610.72
3032 Dumper 18 T 8 8 4,118.89 263,608.91
3055 Asphalt Plant 80 T 1 8 31,727.03 253,816.25
3058 Paver 4 M Wide 1 8 11,793.33 94,346.60
3061 Compressor 300 CFM 1 8 3,808.53 30,468.22
Total 849,521.30
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2025 Aggregate 3/4" - 3/8" Cum 79.8 1,412.80 112,741.44
2026 Aggregate 3/8"- No. 4 Cum 111.72 1,412.80 157,838.02
2027 Aggregate No. 4 - N0. 200 Cum 77.7 1,412.80 109,774.56
2028 Filter Material Cum 14.7 635.76 9,345.67
2041 Asphalt Grade 60/70 Ton 20.19 157,081.60 3,171,477.50
2065 Water 1000 Ltr 4 90.00 360.00
2111 Diesel (LDO) Ltr 5400 118.31 638,874.00
Total 4,200,411.19
(D) SUMMARY
D.1 Basic Cost (A + B + C) 5,102,797.87
D.2 Cost per Cum 27,142.54
D.3 Overhead & Profits @ 25% 6,785.64
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1021 Supervisor 1 4 336.54 1,346.15
1023 Assistant Surveyor 1 2 192.31 384.62
1041 Helper 2 2 134.62 538.46
Total 4,192.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3032 Dumper 18 T 1 5 4,118.89 20,021.92
3047 Excavator (Track Type) 100 HP 1 4 3,472.00 13,888.00
Total 33,909.92
(C) MATERIAL
CODE Description Unit Qty Rate Amount
Total 0.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 38,102.23
D.2 Cost per Cum. 381.02
D.3 Overhead & Profits @ 25% 95.26
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 1 480.77 480.77
1012 Foreman Earthwork 1 2 360.58 721.15
1021 Supervisor 1 8 336.54 2,692.31
1051 Labour 4 8 120.19 3,846.15
Total 7,740.38
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3006 Front End Loader 1.50 Cum 1 1 4,514.45 4,514.45
3014 Tandem Vibratory Roller 1.50 T 1 5 1,591.76 7,958.81
3025 Water Tank Tow Type 4000 Ltr 1 4 2,161.07 8,644.29
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
Total 18,852.63
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2018 Granular Sub Base (B) Cum 30.87 706.40 21,806.57
2022 Fine Sand Cum 37.38 2,472.40 92,418.31
2065 Water 1000 Ltr 9 90.00 810.00
Total 115,034.88
(D) SUMMARY
D.1 Basic Cost (A + B + C) 141,627.89
D.2 Cost per Cum. 2,832.56
D.3 Overhead & Profits @ 25% 708.14
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1012 Foreman Earthwork 1 2 360.58 721.15
1021 Supervisor 1 4 336.54 1,346.15
1051 Labour 4 8 120.19 3,846.15
Total 5,913.46
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3014 Tandem Vibratory Roller 1.50 T 1 4 1,591.76 6,367.05
3025 Water Tank Tow Type 4000 Ltr 1 3 2,224.00 6,672.00
3086 Pump 4 " Delivery (Diesel) 1 1 1,124.76 1,124.76
Total 14,163.81
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2065 Water 1000 Ltr 9 90.00 810.00
Total 810.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 20,887.27
D.2 Cost per Cum. 464.16
D.3 Overhead & Profits @ 25% 116.04
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 8 480.77 3,846.15
1013 Foreman Concrete 1 8 360.58 2,884.62
1021 Supervisor 1 8 336.54 2,692.31
1031 Mason 2 8 173.08 2,769.23
1032 Carpenter 2 8 173.08 2,769.23
1041 Helper 4 8 134.62 4,307.69
1051 Labour 10 8 120.19 9,615.38
Total 28,884.62
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 4 2,161.07 8,644.29
3073 Concrete Static Mixer 1/4 Cuy 1 4 1,483.21 5,932.85
3196 Tractor Trolley 1 4 2,391.86 9,567.44
3210 Vibrator (Poker 1.5 ") 1 1 1,000.46 1,000.46
Total 25,145.04
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 12.5 2,825.60 35,320.00
2024 Aggregate 1-1/2"-3/4" Cum 16.65 1,412.80 23,523.12
2025 Aggregate 3/4" - 3/8" Cum 8.33 1,412.80 11,768.62
2026 Aggregate 3/8"- No. 4 Cum 8.33 1,412.80 11,768.62
2032a Stone Random Class "C" Cum 33.33 635.76 21,189.88
2053 Cement Type - 1 (OPC) Bag 275 1,140.00 313,500.00
2060 Curing Compound Kg 90 95.00 8,550.00
2065 Water 1000 Ltr 8.0 90.00 720.00
2123 Shuttering (401) C LS 8.0 450.00 3,600.00
Total 429,940.25
(D) SUMMARY
D.1 Basic Cost (A + B + C) 483,969.90
D.2 Cost per Cum. 9,679.40
D.3 Overhead & Profits @ 25% 2,419.85
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1013 Foreman Concrete 1 2 360.58 721.15
1021 Supervisor 1 7 336.54 2,355.77
1023 Assistant Surveyor 1 2 192.31 384.62
1031 Mason 1 7 173.08 1,211.54
1032 Carpenter 1 7 173.08 1,211.54
1041 Helper 3 7 134.62 2,826.92
1051 Labour 10 7 120.19 8,413.46
Total 17,125.00
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 2 2,161.07 4,322.14
3073 Concrete Static Mixer 1/4 Cuy 1 5 1,483.21 7,416.06
3086 Pump 4 " Delivery (Diesel) 1 1 1,124.76 1,124.76
3196 Tractor Trolley 1 4 2,391.86 9,567.44
Total 22,430.41
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 4.160 2,825.60 11,754.50
2023 Aggregate 2" - 1-1/2" Cum 1.400 1,412.80 1,977.92
2024 Aggregate 1-1/2"-3/4" Cum 4.000 1,412.80 5,651.20
2025 Aggregate 3/4" - 3/8" Cum 2.000 1,412.80 2,825.60
2026 Aggregate 3/8"- No. 4 Cum 1.000 1,412.80 1,412.80
2053 Cement Type - 1 (OPC) Bag 32.44 1,140.00 36,981.60
2065 Water 1000 Ltr 2 90.00 180.00
2121 Shuttering (401) A LS 9 150.00 1,350.00
Total 62,133.62
(D) SUMMARY
D.1 Basic Cost (A + B + C) 101,689.02
D.2 Cost per Cum. 11,298.78
D.3 Overhead & Profits @ 25% 2,824.70
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1013 Foreman Concrete 1 4 360.58 1,442.31
1021 Supervisor 2 6 336.54 4,038.46
1022 Surveyor 1 4 408.65 1,634.62
1023 Assistant Surveyor 1 4 192.31 769.23
1031 Mason 2 6 173.08 2,076.92
1032 Carpenter 2 8 173.08 2,769.23
1041 Helper 5 8 134.62 5,384.62
1051 Labour 8 6 120.19 5,769.23
Total 25,807.69
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 4 2,161.07 8,644.29
3072 Concrete Static Mixer 1 Cuy 1 4 2,032.89 8,131.55
3086 Pump 4 " Delivery (Diesel) 1 1 1,124.76 1,124.76
3196 Tractor Trolley 1 4 2,391.86 9,567.44
3210 Vibrator (Poker 1.5 ") 1 4 1,000.46 4,001.84
Total 31,469.88
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 3.98 2,825.60 11,231.76
2023 Aggregate 2" - 1-1/2" Cum 1.37 1,412.80 1,935.54
2024 Aggregate 1-1/2"-3/4" Cum 3.66 1,412.80 5,170.85
2025 Aggregate 3/4" - 3/8" Cum 1.83 1,412.80 2,585.42
2026 Aggregate 3/8"- No. 4 Cum 1.10 1,412.80 1,554.08
2053 Cement Type - 1 (OPC) Bag 45 1,140.00 51,300.00
2060 Curing Compound Kg 10 95.00 950.00
2065 Water 1000 Ltr 2 90.00 180.00
2121 Shuttering (401) A LS 9 150.00 1,345.64
Total 76,253.28
(D) SUMMARY
D.1 Basic Cost (A + B + C) 133,530.86
D.2 Cost per Cum. 14,836.76
D.3 Overhead & Profits @ 25% 3,709.19
Total Cost per Cum 18,545.95
Item No. 401 a 1 ii
Description: CONCRETE CLASS "A1" (ON GROUND)
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 20 480.77 9,615.38
1003 Concrete Plant Engineer 1 4 408.65 1,634.62
1013 Foreman Concrete 1 24 360.58 8,653.85
1021 Supervisor 1 24 336.54 8,076.92
1022 Surveyor 1 20 408.65 8,173.08
1023 Assistant Surveyor 1 20 192.31 3,846.15
1031 Mason 8 8 173.08 11,076.92
1032 Carpenter 10 24 173.08 41,538.46
1041 Helper 15 24 134.62 48,461.54
1051 Labour 10 8 120.19 9,615.38
Total 150,692.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3006 Front End Loader 1.50 Cum 1 2 4,514.45 9,028.90
3024 Water Tank Bowser Type 18000 Ltr 1 3 2,893.05 8,679.15
3071 Concrete Batching Plant 30 Cum / H 1 3 9,920.79 29,762.36
3074 Concrete Transit Mixer 6 Cum 6 4 3,600.13 86,403.18
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
3210 Vibrator (Poker 1.5 ") 2 6 1,000.46 12,005.52
3214 Concrete Pump 1 4 7,768.28 31,073.13
Total 179,201.77
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 32.76 2,825.60 92,566.66
2025 Aggregate 3/4" - 3/8" Cum 12 1,412.80 16,953.60
2026 Aggregate 3/8"- No. 4 Cum 16 1,412.80 22,604.80
2027 Aggregate No. 4 - N0. 200 Cum 24.42 1,412.80 34,500.58
2053 Cement Type - 1 (OPC) Bag 597.4 1,140.00 680,990.40
2060 Curing Compound Kg 160 95.00 15,200.00
2065 Water 1000 Ltr 15.45 90.00 1,390.50
2122 Shuttering (401) B LS 72 350.00 25,200.00
Total 889,406.53
(D) SUMMARY
D.1 Basic Cost (A + B + C) 1,219,300.61
D.2 Cost per Cum. 16,934.73
D.3 Overhead & Profits @ 25% 4,233.68
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 20 480.77 9,615.38
1003 Concrete Plant Engineer 1 4 408.65 1,634.62
1013 Foreman Concrete 1 24 360.58 8,653.85
1021 Supervisor 1 24 336.54 8,076.92
1022 Surveyor 1 20 408.65 8,173.08
1023 Assistant Surveyor 1 20 192.31 3,846.15
1031 Mason 8 8 173.08 11,076.92
1032 Carpenter 10 24 173.08 41,538.46
1041 Helper 15 24 134.62 48,461.54
1051 Labour 10 8 120.19 9,615.38
Total 150,692.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3006 Front End Loader 1.50 Cum 1 2 4,514.45 9,028.90
3024 Water Tank Bowser Type 18000 Ltr 1 3 2,893.05 8,679.15
3071 Concrete Batching Plant 30 Cum / H 1 3 9,920.79 29,762.36
3074 Concrete Transit Mixer 6 Cum 6 4 3,600.13 86,403.18
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
3210 Vibrator (Poker 1.5 ") 2 6 1,000.46 12,005.52
3214 Concrete Pump 1 4 7,768.28 31,073.13
Total 179,201.77
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 31.68 2,825.60 89,515.01
2025 Aggregate 3/4" - 3/8" Cum 25.77 1,412.80 36,407.86
2026 Aggregate 3/8"- No. 4 Cum 15.46 1,412.80 21,841.89
2027 Aggregate No. 4 - N0. 200 Cum 9.45 1,412.80 13,350.96
2053 Cement Type - 1 (OPC) Bag 630.36 1,140.00 718,610.40
2058 Accelerator Lit 44.00 128.00 5,632.00
2060 Curing Compound Kg 160.00 95.00 15,200.00
2065 Water 1000 Ltr 16.00 90.00 1,440.00
2121 Shuttering (401) A LS 72.00 150.00 10,800.00
Total 912,798.11
(D) SUMMARY
D.1 Basic Cost (A + B + C) 1,242,692.19
D.2 Cost per Cum. 17,259.61
D.3 Overhead & Profits @ 25% 4,314.90
Total Cost per Cum 21,574.52
Item No. 401 a 2 ii
Description: CONCRETE CLASS "A2" (ON GROUND)
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 20 480.77 9,615.38
1003 Concrete Plant Engineer 1 4 408.65 1,634.62
1013 Foreman Concrete 1 24 360.58 8,653.85
1021 Supervisor 1 24 336.54 8,076.92
1022 Surveyor 1 20 408.65 8,173.08
1023 Assistant Surveyor 1 20 192.31 3,846.15
1031 Mason 8 8 173.08 11,076.92
1032 Carpenter 10 24 173.08 41,538.46
1041 Helper 15 24 134.62 48,461.54
1051 Labour 10 8 120.19 9,615.38
Total 150,692.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3006 Front End Loader 1.50 Cum 1 2 4,514.45 9,028.90
3024 Water Tank Bowser Type 18000 Ltr 1 3 2,893.05 8,679.15
3071 Concrete Batching Plant 30 Cum / H 1 3 9,920.79 29,762.36
3074 Concrete Transit Mixer 6 Cum 6 4 3,600.13 86,403.18
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
3210 Vibrator (Poker 1.5 ") 2 6 1,000.46 12,005.52
3214 Concrete Pump 1 4 7,768.28 31,073.13
Total 179,201.77
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 31.68 2,825.60 89,515.01
2025 Aggregate 3/4" - 3/8" Cum 25.77 1,412.80 36,407.86
2026 Aggregate 3/8"- No. 4 Cum 15.46 1,412.80 21,841.89
2027 Aggregate No. 4 - N0. 200 Cum 9.45 1,412.80 13,350.96
2053 Cement Type - 1 (OPC) Bag 630.36 1,140.00 718,610.40
2058 Accelerator Ltr 44.00 128.00 5,632.00
2060 Curing Compound Kg 160.00 95.00 15,200.00
2065 Water 1000 Ltr 16.00 90.00 1,440.00
2122 Shuttering (401) B LS 72.00 350.00 25,200.00
Total 927,198.11
(D) SUMMARY
D.1 Basic Cost (A + B + C) 1,257,092.19
D.2 Cost per Cum. 17,459.61
D.3 Overhead & Profits @ 25% 4,364.90
Total Cost per Cum 21,824.52
Item No. 401a3i
Description: CONCRETE CLASS A3 (UNDERGROUND) Pile
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 20 480.77 9,615.38
1003 Concrete Plant Engineer 1 4 408.65 1,634.62
1013 Foreman Concrete 1 24 360.58 8,653.85
1021 Supervisor 1 24 336.54 8,076.92
1022 Surveyor 1 20 408.65 8,173.08
1023 Assistant Surveyor 1 20 192.31 3,846.15
1031 Mason 8 8 173.08 11,076.92
1032 Carpenter 10 24 173.08 41,538.46
1041 Helper 15 24 134.62 48,461.54
1051 Labour 10 8 120.19 9,615.38
Total 150,692.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3006 Front End Loader 1.50 Cum 1 2 4,514.45 9,028.90
3024 Water Tank Bowser Type 18000 Ltr 1 3 2,893.05 8,679.15
3071 Concrete Batching Plant 30 Cum / H 1 3 9,920.79 29,762.36
3074 Concrete Transit Mixer 6 Cum 6 4 3,600.13 86,403.18
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
3210 Vibrator (Poker 1.5 ") 2 6 1,000.46 12,005.52
3214 Concrete Pump 1 4 7,768.28 31,073.13
Total 179,201.77
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 27.51 2,825.60 77,732.26
2025 Aggregate 3/4" - 3/8" Cum 29.36 1,412.80 41,479.81
2026 Aggregate 3/8"- No. 4 Cum 17.71 1,412.80 25,020.69
2027 Aggregate No. 4 - N0. 200 Cum 12.71 1,412.80 17,956.69
2053 Cement Type - 1 (OPC) Bag 638.6 1,140.00 728,004.00
2058 Accelerator Ltr 200 128.00 25,600.00
2060 Curing Compound Kg 0 95.00 0.00
2065 Water 1000 Ltr 15 90.00 1,350.00
2121 Shuttering (401) A Cum 0 150.00 0.00
Total 917,143.44
(D) SUMMARY
D.1 Basic Cost (A + B + C) 1,247,037.52
D.2 Cost per Cum. 17,319.97
D.3 Overhead & Profits @ 25% 4,329.99
Total Cost per Cum 21,649.96
Item No. 401 a 3 ii
Description: CONCRETE CLASS "A3" (ON GROUND)
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 20 480.77 9,615.38
1003 Concrete Plant Engineer 1 4 408.65 1,634.62
1013 Foreman Concrete 1 24 360.58 8,653.85
1021 Supervisor 1 24 336.54 8,076.92
1022 Surveyor 1 20 408.65 8,173.08
1023 Assistant Surveyor 1 20 192.31 3,846.15
1031 Mason 8 8 173.08 11,076.92
1032 Carpenter 10 24 173.08 41,538.46
1041 Helper 15 24 134.62 48,461.54
1051 Labour 10 8 120.19 9,615.38
Total 150,692.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3006 Front End Loader 1.50 Cum 1 2 4,514.45 9,028.90
3024 Water Tank Bowser Type 18000 Ltr 1 3 2,893.05 8,679.15
3071 Concrete Batching Plant 30 Cum / H 1 3 9,920.79 29,762.36
3074 Concrete Transit Mixer 6 Cum 6 4 3,600.13 86,403.18
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
3210 Vibrator (Poker 1.5 ") 2 6 1,000.46 12,005.52
3214 Concrete Pump 1 4 7,768.28 31,073.13
Total 179,201.77
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 27.51 2,825.60 77,732.26
2025 Aggregate 3/4" - 3/8" Cum 29.36 1,412.80 41,479.81
2026 Aggregate 3/8"- No. 4 Cum 17.71 1,412.80 25,020.69
2027 Aggregate No. 4 - N0. 200 Cum 12.71 1,412.80 17,956.69
2053 Cement Type - 1 (OPC) Bag 638.6 1,140.00 728,004.00
2058 Accelerator Ltr 200 128.00 25,600.00
2060 Curing Compound Kg 160 95.00 15,200.00
2065 Water 1000 Ltr 15 90.00 1,350.00
2122 Shuttering (401) B LS 72 350.00 25,200.00
Total 957,543.44
(D) SUMMARY
D.1 Basic Cost (A + B + C) 1,287,437.52
D.2 Cost per Cum. 17,881.08
D.3 Overhead & Profits @ 25% 4,470.27
Total Cost per Cum 22,351.35
Item No. 401a3iii
Description: CONCRETAE CLASS A3 (ELEVATED)
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 20 480.77 9,615.38
1003 Concrete Plant Engineer 1 4 408.65 1,634.62
1013 Foreman Concrete 1 24 360.58 8,653.85
1021 Supervisor 1 24 336.54 8,076.92
1022 Surveyor 1 20 408.65 8,173.08
1023 Assistant Surveyor 1 20 192.31 3,846.15
1031 Mason 8 8 173.08 11,076.92
1032 Carpenter 10 24 173.08 41,538.46
1041 Helper 15 24 134.62 48,461.54
1051 Labour 10 8 120.19 9,615.38
Total 150,692.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3006 Front End Loader 1.50 Cum 1 2 4,514.45 9,028.90
3024 Water Tank Bowser Type 18000 Ltr 1 3 2,893.05 8,679.15
3071 Concrete Batching Plant 30 Cum / H 1 3 9,920.79 29,762.36
3074 Concrete Transit Mixer 6 Cum 6 4 3,600.13 86,403.18
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
3210 Vibrator (Poker 1.5 ") 2 6 1,000.46 12,005.52
3214 Concrete Pump 1 4 7,768.28 31,073.13
Total 179,201.77
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 27.51 2,825.60 77,732.26
2025 Aggregate 3/4" - 3/8" Cum 29.36 1,412.80 41,479.81
2026 Aggregate 3/8"- No. 4 Cum 17.71 1,412.80 25,020.69
2027 Aggregate No. 4 - N0. 200 Cum 10.63 1,412.80 15,018.06
2053 Cement Type - 1 (OPC) Bag 638.6 1,140.00 728,004.00
2058 Accelerator Ltr 200 128.00 25,600.00
2060 Curing Compound Kg 160 95.00 15,200.00
2065 Water 1000 Ltr 15 90.00 1,350.00
2124 Shuttering (401) C LS 72 850.00 61,200.00
Total 990,604.82
(D) SUMMARY
D.1 Basic Cost (A + B + C) 1,320,498.89
D.2 Cost per Cum. 18,340.26
D.3 Overhead & Profits @ 25% 4,585.07
Total Cost per Cum 22,925.33
Item No. 510
Description: DISMANTLING OF STRUCTURE AND OBSTRUCTIONS
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1021 Supervisor 1 4 336.54 1,346.15
1040 Highly Skilled Labour 2 4 134.62 1,076.92
1051 Labour 4 4 120.19 1,923.08
Total 4,346.15
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3061 Compressor 300 CFM 1 4 3,808.53 15,234.11
3208 Jack Hammer 1 2 310.70 621.40
3196 Tractor Trolley 1 4 2,391.86 9,567.44
Total 25,422.95
(C) MATERIAL
CODE Description Unit Qty Rate Amount
0.00
Total 0.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 29,769.11
D.2 Cost per Cum. 2,976.91
D.3 Overhead & Profits @ 25% 744.23
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1021 Supervisor 2 8 336.54 5,384.62
1034 Steel Binder /Cutter 10 8 173.08 13,846.15
1041 Helper 10 8 134.62 10,769.23
Total 31,923.08
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
Total 0.00
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2062 Steel Grade 60 Ton 5.25 295,000.00 1,548,750.00
2070 Cold Steel Wire AASHTO M-32 Ton 0.05 350,000.00 17,500.00
Total 1,566,250.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 1,598,173.08
D.2 Cost per Ton. 319,634.62
D.3 Overhead & Profits @ 25% 79,908.65
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1013 Foreman Concrete 1 8 360.58 2,884.62
1021 Supervisor 1 8 336.54 2,692.31
1031 Mason 4 8 173.08 5,538.46
1032 Carpenter 6 8 173.08 8,307.69
1041 Helper 8 8 134.62 8,615.38
1051 Labour 15 8 120.19 14,423.08
Total 42,461.54
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 4 2,161.07 8,644.29
3073 Concrete Static Mixer 1/4 Cuy 1 6 1,483.21 8,899.27
3086 Pump 4 " Delivery (Diesel) 1 1 1,124.76 1,124.76
3196 Tractor Trolley 1 4 2,391.86 9,567.44
3210 Vibrator (Poker 1.5 ") 1 1 1,000.46 1,000.46
Total 29,236.22
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 2.85 2,825.60 8,052.96
2025 Aggregate 3/4" - 3/8" Cum 0.56 1,412.80 791.17
2026 Aggregate 3/8"- No. 4 Cum 1.66 1,412.80 2,345.25
2027 Aggregate No. 4 - N0. 200 Cum 1.4 1,412.80 1,977.92
2053 Cement Type - 1 (OPC) Bag 60 1,140.00 68,400.00
2058 Accelerator Ltr 11 128.00 1,408.00
2060 Curing Compound Kg 14 95.00 1,330.00
2065 Water 1000 Ltr 1 90.00 90.00
2125 Shuttering (401) E Cum 6 850.00 5,100.00
Total 89,495.30
(D) SUMMARY
D.1 Basic Cost (A + B + C) 161,193.06
D.2 Cost per Cum. 26,865.51
D.3 Overhead & Profits @ 25% 6,716.38
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 8 480.77 3,846.15
1014 General Foreman 2 9 312.50 5,625.00
1040 Highly Skilled Labour 6 9 134.62 7,269.23
Total 16,740.38
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3120 Stressing Equipment 2 9 7,748.86 139,479.52
Total 139,479.52
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2022 Fine Sand Cum 0.09 2,472.40 222.52
2053 Cement Type - 1 (OPC) Bag 5 1,140.00 5,700.00
2063 Prestressing Strand 3/8 " , 1/2 " Ton 2.1 380,000.00 798,000.00
2135 Sheaths (3/8 " ,1/2 ") LM 210 250.00 52,500.00
2136 Line Anchorages (3/8 ", 1/2 ") No. 10 500.00 5,000.00
Total 861,422.52
(D) SUMMARY
D.1 Basic Cost (A + B + C) 1,017,642.42
D.2 Cost per Ton. 508,821.21
D.3 Overhead & Profits @ 25% 127,205.30
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1022 Surveyor 1 2 408.65 817.31
1031 Mason 1 2 173.08 346.15
1041 Helper 1 2 134.62 269.23
1051 Labour 1 2 120.19 240.38
Total 1,673.08
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
0.00
Total 0.00
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2073 Elastomeric Bearing pad M-183 Ccm 21,600 6.00 129,600.00
Total 129,600.00
(D) SUMMARY
D1 Basic Cost (A + B + C) 131,273.08
D2 Cost per Ccm 6.08
D.3 Overhead & Profits @ 25% 1.52
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 3 480.77 1,442.31
1013 Foreman Concrete 1 10 360.58 3,605.77
1021 Supervisor 1 10 336.54 3,365.38
1022 Surveyor 1 2 408.65 817.31
1040 Highly Skilled Labour 6 10 134.62 8,076.92
1041 Helper 2 2 134.62 538.46
1042 Welder 1 2 173.08 346.15
Total 18,192.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3002 Bulldozer 120 HP 1 1 5,467.18 5,467.18
3083 Crane 20 T 1 2 4,158.72 8,317.44
3086 Pump 4 " Delivery (Diesel) 1 10 1,124.76 11,247.63
3198 Welding Plant 1 2 3,804.04 7,608.08
3209 Piling Rig (dia upto 1m) 1 10 14,517.97 145,179.74
Total 177,820.07
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2009 Soil Class - A 4 Cum 25 141.28 3,532.00
2065 Water 1000 Ltr 20 90.00 1,800.00
2099 Bentonite Powder Kg 45 200.00 9,000.00
2118 Electric Charges Commercial kWh 40 4.86 194.40
2139 MOBILIZATION OF PILING
EQUIPMENT (Upto 1.0 m Dia) M 12.5 200.00 2,500.00
Total 17,026.40
(D) SUMMARY
D.1 Basic Cost (A + B + C) 213,038.78
D.2 Cost per M. 17,043.10
D.3 Overhead & Profits @ 25% 4,260.78
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 3 480.77 1,442.31
1013 Foreman Concrete 1 10 360.58 3,605.77
1021 Supervisor 1 10 336.54 3,365.38
1022 Surveyor 1 2 408.65 817.31
1040 Highly Skilled Labour 6 10 134.62 8,076.92
1041 Helper 2 2 134.62 538.46
1042 Welder 1 2 173.08 346.15
Total 18,192.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3002 Bulldozer 120 HP 1 1 5,467.18 5,467.18
3083 Crane 20 T 1 2 4,158.72 8,317.44
3086 Pump 4 " Delivery (Diesel) 1 10 1,124.76 11,247.63
3198 Welding Plant 1 2 3,804.04 7,608.08
3209 Piling Rig (dia upto 1m) 1 10 14,517.97 145,179.74
Total 177,820.07
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2009 Soil Class - A 4 Cum 25 141.28 3,532.00
2065 Water 1000 Ltr 20 90.00 1,800.00
2099 Bentonite Powder Kg 50 200.00 10,000.00
2118 Electric Charges Commercial kWh 50 4.86 243.00
2143 MOBILIZATION OF PILING
EQUIPMENT (1.1m TO 2.0 m Dia) M 12.5 258.00 3,225.00
Total 18,800.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 214,812.38
D.2 Cost per M. 17,184.99
D.3 Overhead & Profits @ 25% 4,296.25
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 3 480.77 1,442.31
1013 Foreman Concrete 1 10 360.58 3,605.77
1021 Supervisor 1 10 336.54 3,365.38
1022 Surveyor 1 2 408.65 817.31
1040 Highly Skilled Labour 6 10 134.62 8,076.92
1041 Helper 2 2 134.62 538.46
1042 Welder 1 2 173.08 346.15
Total 18,192.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3002 Bulldozer 120 HP 1 1 5,467.18 5,467.18
3083 Crane 20 T 1 2 4,158.72 8,317.44
3086 Pump 4 " Delivery (Diesel) 1 10 1,124.76 11,247.63
3198 Welding Plant 1 2 3,804.04 7,608.08
3209 Piling Rig (dia upto 1m) 1 10 14,517.97 145,179.74
Total 177,820.07
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2009 Soil Class - A 4 Cum 25 141.28 3,532.00
2065 Water 1000 Ltr 20 90.00 1,800.00
2099 Bentonite Powder Kg 50 200.00 10,000.00
2118 Electric Charges Commercial kWh 50 4.86 243.00
2143 MOBILIZATION OF PILING
EQUIPMENT (1.1m TO 2.0 m Dia) M 7.5 258.00 1,935.00
Total 17,510.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 213,522.38
D.2 Cost per M. 28,469.65
D.3 Overhead & Profits @ 25% 7,117.41
Assumed Quantity 20 M
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 2 192.31 384.62
1031 Mason 1 8 173.08 1,384.62
1041 Helper 2 2 134.62 538.46
1051 Labour 5 8 120.19 4,807.69
Total 9,807.69
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 3 2,161.07 6,483.22
3047 Excavator (Track Type) 100 HP 0 1 6,853.64 0.00
3086 Pump 4 " Delivery (Diesel) 0 1 1,124.76 0.00
3215 Plate Compactor 1 8 1,426.75 11,414.02
Total 17,897.24
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 0.25 2,825.60 706.40
2053 Cement Type - 1 (OPC) Bag 2.30 1,140.00 2,622.00
2065 Water 1000 Ltr 5.50 90.00 495.00
Total 3,823.40
(D) SUMMARY
D.1 Basic Cost (A + B + C) 31,528.33
D.2 Cost per M 1,576.42
D.3 Overhead & Profits @ 25% 394.10
Assumed Quantity 20 M
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 2 192.31 384.62
1031 Mason 1 8 173.08 1,384.62
1041 Helper 2 2 134.62 538.46
1051 Labour 8 8 120.19 7,692.31
Total 12,692.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 3 2,161.07 6,483.22
3047 Excavator (Track Type) 100 HP 0 1 6,853.64 0.00
3086 Pump 4 " Delivery (Diesel) 0 1 1,124.76 0.00
3215 Plate Compactor 1 8 1,426.75 11,414.02
Total 17,897.24
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 0.30 2,825.60 847.68
2053 Cement Type - 1 (OPC) Bag 2.75 1,140.00 3,135.00
2065 Water 1000 Ltr 6.00 90.00 540.00
Total 4,522.68
(D) SUMMARY
D.1 Basic Cost (A + B + C) 35,112.23
D.2 Cost per M 1,755.61
D.3 Overhead & Profits @ 25% 438.90
Assumed Quantity 20 M
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 2 192.31 384.62
1031 Mason 1 8 173.08 1,384.62
1041 Helper 2 2 134.62 538.46
1051 Labour 8 8 120.19 7,692.31
Total 12,692.31
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 3 2,161.07 6,483.22
3047 Excavator (Track Type) 100 HP 0 2 6,853.64 0.00
3083 Crane 20 T 1 2 4,158.72 8,317.44
3086 Pump 4 " Delivery (Diesel) 0 2 1,124.76 0.00
3215 Plate Compactor 2 8 1,426.75 22,828.04
Total 37,628.70
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 0.35 2,825.60 988.96
2053 Cement Type - 1 (OPC) Bag 3.00 1,140.00 3,420.00
2065 Water 1000 Ltr 7.00 90.00 630.00
Total 5,038.96
(D) SUMMARY
D.1 Basic Cost (A + B + C) 55,359.97
D.2 Cost per M 2,768.00
D.3 Overhead & Profits @ 25% 692.00
Assumed Quantity 20 M
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1021 Supervisor 1 10 336.54 3,365.38
1023 Assistant Surveyor 1 2 192.31 384.62
1031 Mason 1 8 173.08 1,384.62
1041 Helper 2 2 134.62 538.46
1051 Labour 8 10 120.19 9,615.38
Total 15,288.46
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 6 2,161.07 12,966.43
3047 Excavator (Track Type) 100 HP 0 4 6,853.64 0.00
3083 Crane 20 T 1 5 4,158.72 20,793.60
3086 Pump 4 " Delivery (Diesel) 1 5 1,124.76 5,623.82
3215 Plate Compactor 0 2 1,426.75 0.00
Total 39,383.85
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 0.45 2,825.60 1,271.52
2053 Cement Type - 1 (OPC) Bag 4.00 1,140.00 4,560.00
2065 Water 1000 Ltr 10.50 90.00 945.00
Total 6,776.52
(D) SUMMARY
D.1 Basic Cost (A + B + C) 61,448.83
D.2 Cost per M 3,072.44
D.3 Overhead & Profits @ 25% 768.11
Assumed Quantity 22 M
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 2 480.77 961.54
1014 General Foreman 1 4 312.50 1,250.00
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 4 192.31 769.23
1031 Mason 1 8 173.08 1,384.62
1041 Helper 2 4 134.62 1,076.92
1051 Labour 8 8 120.19 7,692.31
Total 15,826.92
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3013 Tandem Vibratory Roller 6 T 1 6 2,677.11 16,062.68
3025 Water Tank Tow Type 4000 Ltr 1 4 2,161.07 8,644.29
3047 Excavator (Track Type) 100 HP 0 5 6,853.64 0.00
3083 Crane 20 T 1 5 4,158.72 20,793.60
3086 Pump 4 " Delivery (Diesel) 0 2 1,124.76 0.00
Total 45,500.57
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 0.5 2,825.60 1,412.80
2053 Cement Type - 1 (OPC) Bag 5 1,140.00 5,700.00
2065 Water 1000 Ltr 12.5 90.00 1,125.00
2082 R.C.C PIPE CULVERT AASHTO-M170 CLA
M 22 0.00
Total 8,237.80
(D) SUMMARY
D.1 Basic Cost (A + B + C) 69,565.29
D.2 Cost per M 3,162.06
D.3 Overhead & Profits @ 25% 790.51
Assumed Quantity 22 M
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1014 General Foreman 1 6 312.50 1,875.00
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 4 192.31 769.23
1031 Mason 2 6 173.08 2,076.92
1041 Helper 2 4 134.62 1,076.92
1051 Labour 8 8 120.19 7,692.31
Total 18,105.77
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3013 Tandem Vibratory Roller 6 T 1 6 2,677.11 16,062.68
3025 Water Tank Tow Type 4000 Ltr 1 4 2,161.07 8,644.29
3047 Excavator (Track Type) 100 HP 0 5 6,853.64 0.00
3083 Crane 20 T 1 5 4,158.72 20,793.60
3086 Pump 4 " Delivery (Diesel) 0 2 1,124.76 0.00
Total 45,500.57
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 0.65 2,825.60 1,836.64
2053 Cement Type - 1 (OPC) Bag 6 1,140.00 6,840.00
2065 Water 1000 Ltr 15 90.00 1,350.00
2082 R.C.C PIPE CULVERT AASHTO-M170 CLA
M 22 0.00
Total 10,026.64
(D) SUMMARY
D.1 Basic Cost (A + B + C) 73,632.98
D.2 Cost per M 3,346.95
D.3 Overhead & Profits @ 25% 836.74
ITEM : SP 614(i) Providing and Laying Precast Concrete Interlocking Paver (80mm thick ) minimum Crushing Strength of 7000
MANPOWER
EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks
SUMMARY
Basic cost for 9.29 SM Rs. 24,852.17
Basic cost per SM Rs. 2,675.15
Add Contractor's Over Heads & Profits @ 25 % Rs. 668.79
MANPOWER
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Foreman Concrete 1 3.00 360.58 1,081.73
EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Water Lorry (Local)(4000 L) tow type 1 2.00 2,161.07 4,322.14
MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks
1 Concrete Class A1 Cum 7.67 21,168.41
3 Shuttering LS 2,000.00
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 1 480.77 480.77
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 2 192.31 384.62
1031 Mason 12 8 173.08 16,615.38
1041 Helper 2 2 134.62 538.46
1051 Labour 25 8 120.19 24,038.46
Total 44,750.00
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
0.00
Total 0.00
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2031 Stone Random Class "B" Cum 31.00 1,059.60 32,847.60
Total 32,847.60
(D) SUMMARY
D.1 Basic Cost (A + B + C) 77,597.60
D.2 Cost per Cum. 3,103.90
D.3 Overhead & Profits @ 25% 775.98
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 2 480.77 961.54
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 2 192.31 384.62
1031 Mason 12 8 173.08 16,615.38
1041 Helper 2 2 134.62 538.46
1051 Labour 25 8 120.19 24,038.46
Total 45,230.77
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 4 2,161.07 8,644.29
3086 Pump 4 " Delivery (Diesel) 1 1 1,124.76 1,124.76
Total 9,769.05
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 5 2,825.60 14,128.00
2030 Stone Random Class "A" Cum 25 1,059.60 26,490.00
2053 Cement Type - 1 (OPC) Bag 43 1,140.00 49,020.00
2065 Water 1000 Ltr 2 90.00 180.00
2110 Quick Lime Kg 2175 8.42 18,313.50
Total 108,131.50
(D) SUMMARY
D.1 Basic Cost (A + B + C) 163,131.32
D.2 Cost per Cum. 6,525.25
D.3 Overhead & Profits @ 25% 1,631.31
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1013 Foreman Concrete 1 8 360.58 2,884.62
1023 Assistant Surveyor 1 2 192.31 384.62
1031 Mason 1 8 173.08 1,384.62
1032 Carpenter 1 8 173.08 1,384.62
1041 Helper 2 2 134.62 538.46
1051 Labour 8 8 120.19 7,692.31
Total 14,269.23
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 2 2,161.07 4,322.14
3073 Concrete Static Mixer 1/4 Cuy 1 2 1,483.21 2,966.42
3086 Pump 4 " Delivery (Diesel) 1 1 1,124.76 1,124.76
3196 Tractor Trolley 1 4 2,391.86 9,567.44
Total 17,980.77
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2025 Aggregate 3/4" - 3/8" Cum 0.85 1,412.80 1,200.88
2026 Aggregate 3/8"- No. 4 Cum 1 1,412.80 1,412.80
2053 Cement Type - 1 (OPC) Bag 16 1,140.00 18,240.00
2065 Water 1000 Ltr 1 90.00 90.00
2101 Traffic Sign Cat 1 (A) No. 15 18,000.00 270,000.00
2122 Shuttering (401) B LS 1.6 350.00 560.00
2137 G.I. PIPE 3" DIA LM 3 1,150.00 3,450.00
Total 294,953.68
(D) SUMMARY
D.1 Basic Cost (A + B + C) 327,203.68
D.2 Cost per Each 21,813.58
D.3 Overhead & Profits @ 25% 5,453.39
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1023 Assistant Surveyor 1 5 192.31 961.54
1031 Mason 1 5 173.08 865.38
1041 Helper 3 5 134.62 2,019.23
Total 3,846.15
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3061 Compressor 300 CFM 1 6 3,808.53 22,851.17
3062 Rock Driller 1 6 362.77 2,176.60
Total 25,027.76
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 0.05 2,825.60 141.28
2053 Cement Type - 1 (OPC) Bag 1 1,140.00 1,140.00
2091 Cats-Eye Single (Raised Profile) No. 100 230.00 23,000.00
Total 24,281.28
(D) SUMMARY
D.1 Basic Cost (A + B + C) 53,155.20
D.2 Cost per Each 531.55
D.3 Overhead & Profits @ 25% 132.89
Assumed Quantity 20 SM
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 4 192.31 769.23
1031 Mason 6 8 173.08 8,307.69
1041 Helper 2 4 134.62 1,076.92
1051 Labour 12 8 120.19 11,538.46
Total 24,384.62
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3025 Water Tank Tow Type 4000 Ltr 1 4 2,161.07 8,644.29
3196 Tractor Trolley 1 4 2,391.86 9,567.44
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
Total 20,461.26
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 1.5 2,825.60 4,238.40
2022 Fine Sand Cum 1.2 2,472.40 2,966.88
2030a Stone Random Class "A" Cum 4.5 635.76 2,860.92
2041 Asphalt Grade 60/70 TON 0.09 157,081.60 14,137.34
2053 Cement Type - 1 (OPC) Bag 11 1,140.00 12,540.00
2065 Water 1000 Ltr 3 90.00 270.00
Total 37,013.54
(D) SUMMARY
D.1 Basic Cost (A + B + C) 81,859.42
D.2 Cost per Sqm. 4,092.97
D.3 Overhead & Profits @ 25% 1,023.24
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1021 Supervisor 1 5 336.54 1,682.69
1031 Mason 1 5 173.08 865.38
1051 Labour 5 5 120.19 3,004.81
Total 5,552.88
(B) EQUIPMENT
CODE Description Unit Qty Rate Amount
3196 Truck (3 axle) 1 4 4,328.02 17,312.08
Total 17,312.08
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2300 LEAN CONCRETE COMPOSITE (401f) CM 3.3 0.00 0.00
2301 CONCRETE CLASS A1 COMPOSITE (401gi) CM 6 0.00 0.00
2302 CONCRETE CLASS B COMPOSITE (401b) CM 2.3 0.00 0.00
Total 0.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 22,864.96
D.2 Cost per Each 228.65
D.3 Overhead & Profits @ 25% 57.16
Assumed Quantity 4M
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1013 Foreman Concrete 1 8 360.58 2,884.62
1021 Supervisor 1 8 336.54 2,692.31
1051 Labour 2 8 120.19 1,923.08
Total 7,500.00
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
Total 0.00
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2168 CEMENTITIOUS GROUT (HIGH
STRENGTH) CM 0.11 10,000.00 1,100.00
BRIDGE EXPANSION JOINT
2183 MONOBLOC TYPE (56 mm
MOVEMENT)- IMPORTED LM 4 45,000.00 180,000.00
Total 181,100.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 188,600.00
D.2 Cost per M. 47,150.00
D.3 Overhead & Profits @ 25% 11,787.50
a) Shuttering Cost :-
Cost of one Jersey Barrier Steel Shutter = Rs. 25,000.00
considering 200 uses of sett of shutter
Cost per Barrier 25000 ÷ 200 = Rs. 125.00
(A) MANPOWER
b) Manpower at Site
Site Engineer 1 8 229.17 1833.328
(C) Material:
CODE Description Unit Qty. Rate Amount
Market Rate MS Vertical Pole (dia 250-mm) Kg 1200.997 116.00 139,315.65
Market Rate MS Horizontal Pipe (dia 150-mm) Kg 132.24 116.00 15,340.30
M.S Base Plate, Stiffner plate and truss
Market Rate Kg 4573.32 90.00 411,598.53
angel etc. as per attached backup
Market Rate Square Pipe for frame Kg 140.20 105.00 14,721.11
Market Rate GI Sheet of 1.8mm thick (1.37 kg/Sqft) Kg 897.74 150.00 134,660.85
Diamond Grade for background and
Market Rate Sft 936.12 580.00 542,949.60
lettering
Market Rate J-Bolts Nos 16.00 1,050.00 16,800.00
Foundation (2-nos)
107a Excavation CM 82.25 476.28 39,173.85
107d Common backfill CM 62.88 580.99 36,529.94
404 b Steel Reinforcement (G-60) Ton 1.74 258,000.00 447,888.00
401a3ii Concrete Class A-3 (On Ground) CM 19.38 22,351.35 433,057.32
401f Lean Concrete CM 2.27 14,123.48 32,032.04
Paint cmplete in all respects (2- Coats of
Market Rate Red Oxide prime Coat with 2-Coat of Sft 1045.10 65.00 67,931.50
Smoke Grey Paint)
Market Rate Cutting and Pasting Charges Sft 982.93 190.00 186,756.70
CONSUMABLE ITEMS
Market Rate boc welding Electrodes E-6013 Kg 150.00 460.00 69,000.00
Market Rate Griding Disc 9" No 15.00 380.00 5,700.00
Market Rate Cutting Disc 14" No 15.00 680.00 10,200.00
(D) SUMMARY
D.1 Basic Cost (A + B + C) 3,070,853.68
D.2 Cost per No. 3,070,853.68
D.3 Overhead & Profits @ 15% -
3"
PREPARED BY. ASGHAR ALI MAHSUD
SITE INSPECTOR SMEC Int / ACC
CONTECT # 0333-9968434
4½"
9"
NLC Engineers
Excavation Quantity
No. Length (ft)Width (ft) Depth (ft) Quantity (Cft) Rate (Rs) Amount (Rs.)
(Cu.m)
1 13 7 7.83 712.53 20.17 465.00
Lean Concrete
1 13 7 0.25 22.75 0.64 9,000.00 5,797.00
Concrete Class A
Base Slab 1 13 7 0.75 68.25
Top Slab 1 13 7 0.83 75.80
Cover Wall 2 3 0.5 1.00 3.00
2 4 0.5 1.00 4.00
151.05
Deduction 1 3 3 0.83 7.47
Net Quantity 143.58 4.07 18500 75,206.27
Brick Masonry
Walls 1 13 7 2.58 234.78 6.65 13214 87,836.44
Excavation Quantity
No. Length (ft)Width (ft) Depth (ft) Quantity (Cft) Rate (Rs) Amount (Rs.)
(Cu.m)
1 9.1868 6.562 0.33 19.89 0.56 465.00
Lean Concrete
1 9.1868 6.562 0.33 19.89 0.56 9,000.00 5,069.16
Concrete Class B
Deduction 1 3 3 -
Net Quantity - - 18500 -
Brick Masonry
Walls 2 7.02134 0.75 4.92 51.83 1.47 13214 19,391.99
2 5.9058 0.75 4.92 43.60 1.23 13214 16,311.02
Plaster
Walls 2 7.02134 4.92 69.11 1.96 15600 30,524.70
2 7.05415 4.92 69.43 1.97 15600 30,667.34
Steel in kg
Assumed Quantity 17 M
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1014 General Foreman 1 6 312.50 1,875.00
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 4 192.31 769.23
1031 Mason 2 6 173.08 2,076.92
1041 Helper 2 4 134.62 1,076.92
1051 Labour 20 8 120.19 19,230.77
Total 29,644.23
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3014 Tandem Vibratory Roller 1.50 T 2 6 1,591.76 19,101.15
3025 Water Tank Tow Type 4000 Ltr 2 4 2,161.07 17,288.58
3047 Excavator (Track Type) 100 HP 1 5 6,853.64 34,268.18
3083 Crane 20 T 1 5 4,158.72 20,793.60
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
Total 93,701.04
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 0.5 2,825.60 1,412.80
2053 Cement Type - 1 (OPC) Bag 5 1,140.00 5,700.00
2065 Water 1000 Ltr 15 90.00 1,350.00
2083 #N/A #N/A 17 #N/A #N/A
Total #N/A
(D) SUMMARY
D.1 Basic Cost (A + B + C) #N/A
D.2 Cost per M #N/A
D.3 Overhead & Profits @ 25% #N/A
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1014 General Foreman 1 6 312.50 1,875.00
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 4 192.31 769.23
1031 Mason 2 4 173.08 1,384.62
1041 Helper 2 4 134.62 1,076.92
1051 Labour 20 8 120.19 19,230.77
Total 28,951.92
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3014 Tandem Vibratory Roller 1.50 T 2 6 1,591.76 19,101.15
3025 Water Tank Tow Type 4000 Ltr 2 4 2,161.07 17,288.58
3047 Excavator (Track Type) 100 HP 1 5 6,853.64 34,268.18
3083 Crane 20 T 1 5 4,158.72 20,793.60
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
Total 93,701.04
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 0.5 2,825.60 1,412.80
2053 Cement Type - 1 (OPC) Bag 5 1,140.00 5,700.00
2065 Water 1000 Ltr 15 90.00 1,350.00
2084 #N/A #N/A 14.6 #N/A #N/A
Total #N/A
(D) SUMMARY
D.1 Basic Cost (A + B + C) #N/A
D.2 Cost per M #N/A
D.3 Overhead & Profits @ 25% #N/A
(A) MANPOWER
CODE Description No. Hr. Rate Amount
1001 Site Engineer 1 4 480.77 1,923.08
1014 General Foreman 1 6 312.50 1,875.00
1021 Supervisor 1 8 336.54 2,692.31
1023 Assistant Surveyor 1 4 192.31 769.23
1031 Mason 2 6 173.08 2,076.92
1041 Helper 2 2 134.62 538.46
1051 Labour 20 8 120.19 19,230.77
Total 29,105.77
(B) EQUIPMENT
CODE Description No. Hr. Rate Amount
3014 Tandem Vibratory Roller 1.50 T 2 6 1,591.76 19,101.15
3025 Water Tank Tow Type 4000 Ltr 2 4 2,161.07 17,288.58
3047 Excavator (Track Type) 100 HP 1 5 6,853.64 34,268.18
3083 Crane 20 T 1 5 4,158.72 20,793.60
3086 Pump 4 " Delivery (Diesel) 1 2 1,124.76 2,249.53
Total 93,701.04
(C) MATERIAL
CODE Description Unit Qty Rate Amount
2021 Coarse Sand Cum 0.5 2,825.60 1,412.80
2053 Cement Type - 1 (OPC) Bag 5 1,140.00 5,700.00
2065 Water 1000 Ltr 15 90.00 1,350.00
2085 #N/A #N/A 12.16 #N/A #N/A
Total #N/A
(D) SUMMARY
D.1 Basic Cost (A + B + C) #N/A
D.2 Cost per M #N/A
D.3 Overhead & Profits @ 25% #N/A