This document provides instructions for material storage, pipe installation, testing, and quality control for a piping project. Piping must be installed according to manufacturer specifications, receive cladding and insulation, and pass vacuum and pressure tests. The contractor should follow approved shop drawings for pipe sizes, layout, routing, hangers, and mockups to ensure proper installation.
This document provides instructions for material storage, pipe installation, testing, and quality control for a piping project. Piping must be installed according to manufacturer specifications, receive cladding and insulation, and pass vacuum and pressure tests. The contractor should follow approved shop drawings for pipe sizes, layout, routing, hangers, and mockups to ensure proper installation.
This document provides instructions for material storage, pipe installation, testing, and quality control for a piping project. Piping must be installed according to manufacturer specifications, receive cladding and insulation, and pass vacuum and pressure tests. The contractor should follow approved shop drawings for pipe sizes, layout, routing, hangers, and mockups to ensure proper installation.
1. Material storage,protection, installation & testing to be as per
manufacturer recommendations & specifications. 2. Cladding to be provided for the Roof piping after insulation. 3. Vaccum test to be done before filling the nitrogen gas for pressure test. 3. Pipes sizes to be followed as per the latest shop drawings approval and based on the Equipment manufacturer recommendations. 4. Contractor to provide prior to start installation site wide. 5. Contractor to follow the latest coordination layout for installation & pipe routing for the high level and on the roof. 6. Pipe insulation to be provided as per the approved material submittal. 7. Contractor to follow the Shop drawings and installation detail drawings for all the site installations. 8. Hangers spacing schedule to be as per the approved shop drawing. 9. Subject to Mock up approval and Quality maintained on site installations.