Professional Documents
Culture Documents
1200 Design and Installation Guide
1200 Design and Installation Guide
1200 Design and Installation Guide
REV C.4 2
1.0 Front Matter
1.1 Disclaimer and Confidentiality Notice
This manual is to assist architects, contractors and facility managers in preparing for and
installing a HydroWorx 1200 Series Hydrotherapy system. All information contained
in the guide is general and may not be applicable to every job site or installation.
HydroWorx cannot be held responsible for inaccurate information or omission of certain
details relating to the site preparation or installation of the product. This manual is
protected by US and International Copyright laws. Reproduction, distribution, display
and use of content outside of designing for or installing a HydroWorx product is
prohibited. All drawings included in this guide are for example only and should not
be used to create site-specific packages for the purpose of permit requests. All
drawings are generic in nature.
2.0 Installation
It is very important to consider all aspects of the installation site, including:
REV C.4 3
• Access & Serviceability
• Site Preparation
• Hydrotherapy Room
• Mechanical Pit
• Utility Requirements
Read more about each of these in the sections below.
REV C.4 4
Additional space may be necessary to facilitate installation and provide future service
space around and above the pool. Additional space may also be necessary for these and
similar items:
dehumidification systems
cabinetry
storage
showers
changing rooms
The design of the hydrotherapy area must include floor or perimeter drains. If floor
drains are chosen, several should be placed around the pool with special attention to
the high traffic areas. The finished floor MUST be flat/level and consistent at all edges of
the opening for a minimum distance of 4” beyond the opening edge.
The HydroWorx 1200 includes an HMI control and underwater video monitoring system. The
hydrotherapy room design must include customer supplied cabinetry located near the front of
the unit as well as electrical receptacles that can accommodate two 40” TVs, DVR, HMI, iPad
and an Android TV Streaming Box. The owner shall provide a 3” chase underneath the cabinetry
to route wires from the control panel in the mechanical pit to the equipment in the pool room.
The chase shall be straight pipe or long sweep—no 90-degree elbows. This chase is to be
dedicated to HydroWorx low voltage control cables ONLY.
REV C.4 5
2.4 Mechanical Pit
The mechanical pit design must include adequate, unobstructed access to the pool
walls, electrical control panel, and accessory equipment such as the filter, pumps,
chemical feeder, and heater. Moving any of this equipment may result in the voiding of
warranty coverage.
Minimum dimensions for the mechanical pit are shown in the enclosed drawings. The
design must also include:
HVAC controls that are appropriate for the entire area
Lighting
Sump pump or drains
1 — 30 kW Electric Heater
1 — 4 HP Front Therapy Jet Pump (10,188 BTU/hr)
1 — 10 HP Treadmill Motor (25,470 BTU/hr)
1 — 2 HP Lift Motor (5,094 BTU/hr)
1 — 1 HP Maintenance Pump (2,547 BTU/hr)
REV C.4 6
2.4.2 Floor Requirements
The floor shall be designed to support the weight of the pool and equipment. It is
recommended to build an elevated pad for the pool to sit on. The elevated pad makes it
easier to control the tolerances. The floor/pad below the pool must be built to exacting
specifications. The floor must be level, having no more than a 1/8-inch variance
over 10 feet in any direction—as measured with long level or straightedge. The floor
must be hard-troweled and finished smooth, not left rough as is commonly done in
mechanical rooms. Prior to Phase 1 installation the general contractor must perform a
floor elevation survey that focuses specifically on the areas on which the equipment will
rest. If the slab does not meet the specifications above, then corrective action must be
taken prior to Phase 1 installation.
The structural weight of the pool is 10,000 pounds. Together with the weight of 3,100
gallons of water (which is 26,00 pounds), the total weight is 36,000 pounds. This
weight rests on the mechanical pit floor, therefore it is important to consult a structural
engineer ensure adequate structural requirements for the floor. The pool walls are
fastened to the floor with concrete wedge anchors.
2.4.3 Drain
The HydroWorx pool is drained by gravity through a drain fitting located at the bottom
of the pool wall. The drain fitting must be connected to a sump pit or gravity drain so
the water can discharge during normal maintenance and as necessary for operational
demands of the owner. The sump pit or gravity drain chosen by the owner’s design
professional must accommodate a minimum of 60 GPM. The HydroWorx maintenance
pump CANNOT be used to drain the pool since this will void the pump warranty.
REV C.4 7
2.5.2.1 Hydrotherapy Room
The owner shall provide a GFI protected 110V electrical outlet for the pool controls and video
display. HydroWorx provides (1) 6-receptacle power strip. If all the equipment is not placed in
the same cabinet, additional outlets may need to be provided. The owner shall provide a 3”
chase underneath the cabinetry to route wires from the control panel in the mechanical pit to
the equipment in the pool room.
Note: Ground and neutral wires to be sized at least equal to power conductors
2.5.3 Sanitary
2.5.3.1 Hydrotherapy Room
The owner shall provide perimeter floor drains around the pool to capture bather runoff,
splashing, and hosing down of the pool deck.
REV C.4 8
3.1 Owner/General Contractor Scope-of-Work
The Owner, Customer, or Customer Representative may serve in the role of the General
Contractor for the purpose of a HydroWorx installation.
The General Contractor must ensure that the hydrotherapy room and mechanical pit are
built according to both the (a) owner’s design documents and (b) this HydroWorx
Design & Installation Guide. Specifically, the General Contractor must arrange for the
successful completion of the following:
REV C.4 9
NOTE: Please don’t hesitate to consult with HydroWorx on the delivery plan
proposal.
3.2.1 Phase 1
3.2.1.1 Phase 1 - General Contractor Scopes of Work
The General Contractor is responsible for scheduling and providing of access from the
point of delivery to the final location of the unit and components. The dimension of the
largest component is 9’-6” length x 6’ width x 4’ height with an approximate weight of
3,200 lbs.
To ensure that all Phase 1 tasks are fully complete and correct, the General Contractor is
responsible for completing and returning the Phase 1 Quality Review checklist to
HydroWorx.
REV C.4 10
3. Provide a means to drain the unit and the maintenance system by gravity
through a 2-inch PVC drain line into the sump pit or floor drain, as shown in this
guide. The acceptable minimum draining capacity in the HydroWorx mechanical
space is 60 GPM for HydroWorx equipment (refer to the HydroWorx drain detail).
It is critical to install this piping to drain the entire unit by gravity alone. The pipe
invert shall be lower than the drain invert.
4. Provide a minimum 2-inch diameter water supply line with an anti-siphon device,
auto fill bypass, and hose bib that connects to the fill line as shown in the
HydroWorx drawings.
5. Provide and install all piping, fittings, valves—including ABS 3-way Jandy
directional flow valves. Unless otherwise noted, all conveyance piping, fittings,
and valves, must be Schedule 40 PVC (pressure type), fastened with heavy-bodied
clear pipe glue. Threaded fittings must be connected using silicon and sealant.
DO NOT use plumbing pipe-thread sealer as these can degrade PVC over
time.
6. Install piping such that there is an immediate transition from the supplied 1-½-
inch male adapters for the suction, return, and equalizer pool wall fittings on the
pool to 2-inch schedule 40 PVC pipe (pressure type). Carefully thread the fitting
nut and hand-tighten only. DO NOT USE SILICONE. The final seal will be done
by the HydroWorx approved Phase 2 installer.
3.2.2 Phase 2
3.2.2.1 Phase 2 - Scopes of Work
The General Contractor must also arrange for the installation of pool room finishes
including:
Pool depth markers
Safety equipment
REV C.4 11
Signage
Poolroom cabinetry
Filling or caulking the 1” gap around the pool perimeter decking where it meets
the rough opening
o This needs to be a self-leveling expandable sealant rated for pool room
environments
HydroWorx installers or certified installers WILL NOT perform any installation for
any items not directly supplied by HydroWorx.
At the completion of the Phase 2 system testing and startup, the pool must be left filled
and running for 30 days or until the building is turned over to the customer. During this
time the General Contractor will need to hire a certified pool operator to maintain
water quality. The aim is to ensure that there is no staining of the pool liner and there is
no damage to internal equipment or pool equipment that might result from an
imbalance of the pool. It is also the responsibility of the General Contractor to protect
the pool and components from damage until the final turnover to the owner/customer.
1. Provides all labor, materials, and equipment necessary to support all terms in the:
a. Owner’s contract
b. The conditions specified in this guide
c. Designs for adequate heating, ventilation, air conditioning, and
dehumidification of the hydrotherapy room and mechanical pit.
2. Installing a properly-sized ventilation and humidity control unit. This is to ensure
the mechanical pit temperature does not rise above 85 degrees Fahrenheit while
considering the respective heat loads for the pool equipment.
3. Ensuring that careful heat load calculations are considered for all other disciplines
that relate to the mechanical pit.
4. Ensuring adequate airflow, temperature control, and dehumidification in the
hydrotherapy room —primarily to maintain a comfortable temperature for the
pool occupants and protect against the adverse conditions of a humid
environment.
REV C.4 12
1. Provide and connect a 120/208 volt, 100 amp, 3-phase, 5-wire configuration (L1,
L2, L3, Ground, and Neutral), to the HydroWorx control panel.
NOTE: Ground wire must be at least the same size as the power conductors.
2. Provide and connect a 120/208 volt, 110 amp, 3-phase, 4-wire configuration (L1,
L2, L3, and Ground), to the HydroWorx 30 kW heater.
NOTE: Ground wire must be at least the same size as the power conductors.
4. Install metal conduit and wire from the HydroWorx Control Panel and terminate
the feed to each of the following pool components according to local building
codes:
a. (1) - 10 HP Treadmill Drive Motor
b. (1) - 4 HP Front Jet Pump
c. (1) - 1 HP Maintenance Pump
d. (1) - 2 HP Lift Motor
e. (1) - Automatic Water Level System Solenoid Valve
5. Unless otherwise required by code, all wiring for the devices listed shall be
enclosed in the appropriate size NEMA 4X metal conduit or PVC conduit spaced
at least 8” apart and terminated at the device with 3 feet of flexible Liquidtite
conduit. NEMA 4X metal conduit or PVC conduit spaced at least 8” apart is
required to reduce motor noise and GFCI nuisance tripping. All conduit entry
points must be sealed with UL Listed sealing device. Each motor requires a
separate conduit run.
6. Wire the motor brake to the lift motor. The brake is mounted to the motor but is
not prewired.
7. The pool steel tank walls and all equipment, including the video cameras, must
be bonded with a bonding wire as required by code. The gauge of the ground
wire of any appliance must be as large as the hot wire(s), to be capable of
efficiently conducting electricity away from the device in the event of a short
circuit or stray current—as well as prevent GFCI nuisance tripping.
REV C.4 13
8. When installing field wiring, use at least 75°C stranded copper MTW or THHN
wire of proper size (refer to electrical schematic)—DO NOT use solid wire or
Romex.
9. Prior to connection to the HydroWorx Control Panel, check the voltage at each
leg of the 100 amp 3-phase service feed and ensure the voltages are correct. Do
not turn the power on if the voltages are incorrect; this will void the
warranty of the control panel!
4.0 Checklists
HydroWorx will provide checklists during each stage of the project to ensure that all
requirements are met to provide a smooth install and start-up. These checklists will also
improve the coordination of the HydroWorx pool(s) in the design and construction
phase of the project. All checklists are provided and located in Appendix B
REV C.4 14
Appendix A - Drawings and
Illustrations
REV C.4 15
FILL VOID WITH EPOXY
GROUT, CAULK, OR EQUAL
(BY CONTRACTOR)
1/8" THICK STEEL DECK
(BY HYDROWORX)
2 1/2"
1/2"
(BY HYDROWORX)
4000 PSI CONCRETE
MINIMUM
Level 1
0' - 0"
3/8" MINIMUM DIAMETER
WEDGE ANCHOR 2'-0"
O.C. MAX
-GALVANIZED OR 18-8SS
(NO ZINC PLATED)
3/4" 1 1/2"
Section 1 - Callout 1 1' - 0"
1
3" = 1'-0" 2 1/4"
MINIMUM
1' - 10 1/2"
A101 - EDGE DETAIL
Revision Number:
Date: 4/27/2020 1:52:02 PM
3/8" MINIMUM DIAMETER
1/2"
2 1/2"
2'-0" O.C. 4000 PSI CONCRETE
O.C. MAX
MAXIMUM MINIMUM
-GALVANIZED OR 18-8SS
Level 1 (NO ZINC PLATED)
0' - 0"
Level 1 1
0' - 0" A101 1 1/2"
4000 PSI CONCRETE 3/4"
MINIMUM
2' - 0"
MAX.
FINISHED FLOOR POOL WALLS
(BY CONTRACTOR)
1' - 10 1/2"
3/8" MINIMUM DIAMETER
1' - 2 1/4"
WEDGE ANCHOR 2'-0"
1 1/2"
O.C. MAX
3/4"
-GALVANIZED OR 18-8SS
HOUSE KEEPING (NO ZINC PLATED)
PAD/MECHANICAL
ROOM FLOOR
-8' - 6"
Section 1 TOP VIEW
1 3
1/2" = 1'-0" 3/4" = 1'-0"
A102 - Unnamed
Revision Number:
Date: 4/27/2020 1:52:03 PM
1200-008
July 2021 MM
NTS NLL
NONE NLL
1200 Series - Fill Line & Skimmer Detail
1200-010
July 2021 MM
1/2"=1'-0" NLL
1200 Series - Control Interface
Appendix B - Checklists
REV C.4 16
HydroWorx Scope Verification Checklist
1200 Series Pool
IMPORTANT: The contract that was signed with HydroWorx includes many items of work under the scope of the
General Contractor. This form is intended to ensure that all parties are aware of the pre-delivery and/or pre-
Phase 1 Installation scopes of work.
✓ Regardless of the timing of the pool delivery, a minimum 7’ wide x 7’ high clear rollable access path from the unloading
location to inside the poolroom with turning clearances that can accommodate a 10’ long x 7’ wide pool component and
contractors rigging equipment.
✓ The mechanical pit must be clean, well lit, and dry and have an operational sump pump prior to delivery of the
equipment. It is the customer’s responsibility to protect and secure the pool and components following delivery and
installation of the equipment. Any damage to the pool equipment is the customer’s responsibility and there can be no
standing water in the mechanical pit at any time.
✓ A piece of rigging equipment (all terrain forklift) with 6’ forks – capable of lifting 2 tons at full extension – and operator
are required for the offloading of HydroWorx equipment on the day of arrival of the delivery truck.
✓ HydroWorx does not have the capability to store the pools and equipment at our production facility, and as such, the
undersigned agrees to accept the pool delivery on the agreed upon date. Please note, our production facility runs near
capacity, and any later date requests, will be coordinated with our production schedule. A request for a specific date does
NOT guarantee delivery on that date. HydroWorx will endeavor to honor all requests, but some flexibility may be
required on the part of the customer.
The customer acknowledges that HydroWorx does NOT have the capacity to store the pool and equipment in
its production facility. If delivery is delayed for any reason whether by request of or act of omission by
Customer/Customer’s Representative/Customer’s Contractor, including failure to select colors on time, or
make payments when due, or failure to have the site timely and properly prepared; HydroWorx may incur
extra costs and disruption to its production schedule and prejudice to its other clients may result. Therefore, if
delivery is delayed for any reason other than HydroWorx’ breach of Contract, HydroWorx reserves the right to
establish a new delivery date at HydroWorx’ discretion, and charge customer a delay charge (the “Delivery
Surcharge”) of 4% of total price on the contract, which the Customer shall pay before delivery. HydroWorx
may impose a further Delivery Surcharge for each additional year of delay of delivery. Delivery Surcharges are
payable on demand. ________________ (Authorized Customer Representative Initials)
REVIEWED 60 days PRIOR TO DELIVERY AND/OR PHASE 1 INSTALLATION OF HYDROWORX
POOL. Please provide photos for each item below.
7) A sump pit and pump must be in the mechanical pit and 100% FUNCTIONING properly prior to the Phase 1
installation to ensure that the HydroWorx electrical control system, pumps, motors, etc. are not
damaged. Sump Pump must be sized properly (by Mechanical Engineer) to keep mechanical pit dry and
evacuate any incoming water. Temporary pump is acceptable until permanent pump is
installed/powered.
Yes [ ] No [ ]
8) Are there level and structurally sound floors or temporary platforms from the delivery truck’s unloading
location to the pool room? No changes in elevation between the unloading area and the pool room.
No projections from the floor (rebar, drain pipe rough ins, etc.) can be in place during the delivery.
Yes [ ] No [ ]
9) Electrical power must be available within 50’ for the operation of power tools. Running extension cords
too far has the potential to damage the chain hoist.
Yes [ ] No [ ]
10) There must be lighting in the pit operational and the pool room for Phase 1- Temporary string lights are
acceptable for this.
Yes [ ] No [ ]
11) The wood nailer around the rough opening is completed per the HydroWorx installation guide. This is the
fastening point for the HydroWorx decking and is critical that it is place prior to Phase 1. This wood nailer
MUST be ½” lower than the pool room finish floor surface. We have no vertical tolerance on our pool.
The measurement must be consistent along the entire edge of the pool.
Yes [ ] No [ ]
12) The orientation of the pool must be made clear visually by marking the front of the pool. Typically done
with spray paint on the mechanical pit floor with an arrow pointing in the direction of the front of the
pool. The front of the pool is the area that contains the resistance jets and where the video equipment
will be located in the pool room. Also, the alignment lines need to be snapped per the line snapping
drawing supplied by HydroWorx.
Yes [ ] No [ ]
13) The pool room, mechanical pit and area around the pool are clear and open to avoid damage to pool
equipment. All equipment will be staged in the pool room prior to being lowered down into the
mechanical pit.
Yes [ ] No [ ]
Signature: _______________________________________________
Date: ____________________________________________________
GC to confirm and mark the concrete slab with which end is the FRONT of the pool (where the jets are located). GC
also to mark any under-slab piping within the footprint of the pool.
Verify center of rough opening and snap lines (dotted lines shown in plan view below)
Verify that the concrete slab within the rough opening is level and smooth with no variance greater than 1/8”. If
there is any variance greater than that or non-smooth surface, call your HydroWorx project manager before
proceeding with setting any equipment.
1200 Phase I Install Checklist
Complete this form and submit it along with all required photos to HydroWorx project management within 24 hours of
the completion of Phase 1. Contact HydroWorx (717-902-1923) project management for technical Phase 1 assistance.
Verify slab levelness with straightedge / max is 1/8 inch over 10 feet. What is max variance? _______
Verify that the measurement from the TOP of the wood nailer to the mechanical pit floor on all (4) sides is 8’ 5
1/2”. Note measurements below.
Left Side ______ Right Side_______ Front_______ Back________
Verify the measurement from top of the finished floor to the pit floor the tank walls will be set on. What is the
measurement? ____________
What are your finished floor materials and thickness? __________________________________
Verify that the wood nailer is installed with ¾” spacer per the detailed drawing. YES or NO
Verify that the wood nailer is level and consistent on all four sides YES or NO
Verify that the wood nailer will be ½” down from the finished floor consistently. If NO, what will the dimension of
the top of the wood nailer to the finished floor be: ______
Verify front of pool / before setting ANY equipment (Front is where the two resistance jets and optional video
screens are located)
Snap chalk lines for pool on pit floor to ensure pool is centered in the rough opening.
Unloading – Do not attempt to pick up the treadmill and lift using the attached lifting straps on the treadmill.
The treadmill platform must be separated from the lift system and staged on 4 x 4’s until you need to move it into
place. Photo Required: (1) Picture showing the lift and treadmill being removed from the truck. (1) Picture
showing the treadmill separated and stage.
Assembly
First things in pit are: pumps, filter, heater, electric panel, and all other motors. Recommendation: Set Electrical
panel in the pit in the crate and then remove the crating once down in the mechanical space.
Tighten all tank bolts and square tank. The pool must be centered within the rough opening. (Maximum variance
is ½”). Do not anchor the tank walls to the concrete slab. This will be done on Phase 2.
Place a 4’ Level on the top of each tank wall to confirm the pool structure is level. Photos required of level on all
(4) tank walls.
Install all pump stands, pump motors, gear boxes, treadmill motor and heater. Photo required of all equipment.
Set treadmill motor and ISTECH panel per installation guide. Photos required showing where the equipment is
positioned.
Install all inlet-outlet fittings, drain fittings, skimmers and badu jet housings on tank. Hand tighten fittings only.
Photos required of all fittings inside and outside the pool.
Lower in lift without the wood skid, then the treadmill platform, and all remaining phase 2 boxes, parts, and
maintenance rails. Count and note here how many pieces of blue metal decking are on site: ________ Photos
required: (1) picture showing the gantry crane being used to set the lift, then the treadmill. (1) Picture of all of
the equipment down in the pool.
Post-Assembly
Take pictures of poolroom, tank walls, ISTECH electrical panel, and all equipment staged in tank and all external
pool equipment in mechanical space. The photos are mandatory and will insure a smooth Phase 2 installation.
Cover the pool with the HydroWorx provided blue tarp. Photo Required.
GC to cover the opening with wood to protect the pool and equipment until Phase 2. Photo Required.
Pool equipment electronics (touchscreen controls, TV, underwater cameras) must be stored in a secure
temperature controlled room. Where are they stored? _________________________________
1: _______________ 5:________________
2:_______________ 6:________________
3: ______________ 7:________________
4:_______________ 8:________________
Phase 1 Completion Date: ________________________________________________________________
IMPORTANT: HydroWorx will schedule installation crews, book airline tickets and reserve car and hotels based on the
information and dates provided on this checklist for the second phase of your HydroWorx pool installation. This checklist
and the installation dates must be completed and signed before HydroWorx will make final scheduling arrangements. The
customer and/or the customer’s contractor will be billed for all travel and labor expenses that result from improper or
incomplete checklist data. Return to Meghan Hogan mhogan@hydroworx.com and/or Christina O’Donnell at
codonnell@hydroworx.com, (o) 717-902-1923 (f) 717-902-1933.
Upon completion of the HydroWorx Phase II installation, which takes roughly seven days, the HydroWorx pool will be fully
operational and ready to be used by the customer. All the conditions noted below are required for a successful Phase II
installation. It is important to note that once the Phase II installation is complete, the pool must be left full of water –
chemically treated and heated and maintained daily by the owner for 30 days to allow for the liner to fully cure. The pool
can be used by the customer during this time.
Items 1- 4 must be received 100% complete 30 days (4 weeks) from the Phase 2 install date. GC completes the
following questions and provides supporting pictures. If the items are not returned 30 days prior to install date, then the
job will be rescheduled based on availability which may be if 60 days from receipt of completed form and supporting
pictures.
HydroWorx representatives will make (1) installation trip to install the pool lining system, perform the proprietary
mechanical connections and system test the unit. Saturday and Sunday full day work access is required for the HydroWorx
technician. All plumbing and electrical work on the pool must be completed 30 days prior to the scheduling of the Phase 2
final installation and permanent power and water must be operational.
MUST BE COMPLETED AND RETURNED 30 DAYS PRIOR TO PHASE 2 INSTALL BEING SCHEDULED.
1. Is the permanent electrical power installed and have all connections been made to the pool motor, outlets on the pool,
and is the equipment ready to be started up and tested? All receptacles in the mechanical pit and pool room must be
turned on for use. Provide photo of inside of HydroWorx control panel.
(Provide Photos labeled #1) Confirmed: Yes [ ] No [ ]
2. Have the electricians completed the grounding and bonding on all the pool’s electrical components and code-required
locations? Main grounding conductor to be same size as phase conductors.
(Provide Photos labeled #2) Confirmed: Yes [ ] No [ ]
3. Has the separate electrical service been connected to the heating unit including the ground wire sized the same as the
phase conductors?
(Provide Photos labeled #3) Confirmed: Yes [ ] No [ ]
4. Have the plumbers completed all the plumbing connections to the jet systems, pump motors, filtration equipment and
sump pit, and have all the isolation valves been put in place to allow service to the equipment?
(Provide Photo of all four side of pool piping in Pit)
(Provide Photos labeled #4) Confirmed: Yes [ ] No [ ]
GC must complete and send supporting pictures for items 5-15 below 14 days prior to Phase 2 install.
HydroWorx could send an independent inspector to verify these items are completed. If the inspection is
not 100% completed, the Phase 2 date is rescheduled to the next available install date. There could be up
to a 60 day wait to reschedule, due to our install manpower schedule.
5. The computer control system, video system, and control pendant are all set up by HydroWorx during this installation.
The computer cabinetry must be in place prior to the Phase II. Is the cabinetry in place? The HydroWorx control cable
has a 2.25” connector. A 3” hole must be provided from the mechanical pit to the top of the cabinet for installation of
the control pendant. 3” holes must also be provided between sections of the cabinet to wire the video monitors and
other ancillary equipment.
(Provide Photo including the 3” chase)
(Provide Photos labeled #5) Confirmed: Yes [ ] No [ ]
6. Please have electrician fill out the Electrical Warranty Activation Checklist (located in the Manual inside the panel) and
send to the manufacturer.
(Provide Photos labeled #6) Confirmed: Yes [ ] No [ ]
8. Verify the distance from HydroWorx control panel to the top of the cabinet in the pool room is less than 50’. Measure
through the chase.
(Provide Photos labeled #8) Confirmed: Yes [ ] No [ ]
9. Is all of the finishing work (tile, paint, ceiling, lighting, etc) 100% completed in the pool room
(Provide Photos labeled #9) Confirmed: Yes [ ] No [ ]
13. Has the pool been kept clean, or if not, cleaned out? Is the pool pit clean and trash free?
(Provide Photos labeled #13) Confirmed: Yes [ ] No [ ]
14. Has there been any damage to any of the pool equipment since drop-off?
(Provide Photos labeled #14) Confirmed: Yes [ ] No [ ]
KEY: If yes, please describe the damage:
15. Provide contact information for the individual(s) who will be taking care of the pool at the completion of Phase 2 until the
official HydroWorx start up. Please have them available for a brief technical review on the last day of the Phase 2
Installation. This time will be coordinated with your project manager.
Name:
Phone Number:
Email Address:
I certify that the above checklist is completed to the best of my knowledge.
Name____________________________________________
Date_____________________________________________
Signature_________________________________________
HydroWorx
1200/2000 Warranty Activation
THIS SHEET MUST BE COMPLETED AND SIGNED BY QUALIFIED, LICENCED
ELECTRICIAN AND FAXED OR MAILED TO ISTECH TO ACTIVATE WARRANTY ON THIS
SYSTEM.
Phone Number:
Please complete Design Review Checklist and
submit to Hydroworx
(for informational purposes only)