Professional Documents
Culture Documents
010-MOM Dated 02-12-2023 Ms Heritage With Performance Report Form 04-12-2023 To 10-12-2023.
010-MOM Dated 02-12-2023 Ms Heritage With Performance Report Form 04-12-2023 To 10-12-2023.
Points of Discussion:-
Sl Action by M/s Heritage Target Responsible
Points of Discussion M/s AICPL Comments Remarks
no. Infraspace Date Authority
D-wall works to be M/s Heritage agreed to complete 17-12-2023 M/s Heritage team Instructed to escalate the D-Wall
1
speed up 05 Nos. of D-Wall. Work.
Piling Works M/s Heritage agreed to complete 17-12-2023 M/s Heritage team Instructed to escalate the Piling
2
07 Nos. of piles. Work.
D-Wall Anchoring M/s Heritage informed that they 17-12-2023 M/s Heritage team Instructed to escalate the Anchoring
will start the Anchoring work on Work.
3 11-12-2023 and based on that
they will give the anchoring
programme.
TPI and Quality M/s Heritage informed that, 12-12-2023 M/s Heritage team Instructed to submit the TPI and
Reports (invoives & materials are arriving on 04-12- Quality reports.
4
MTC's) to be submitted 2023 and all the material samples
will sent for TPI.
HT Strands Testing M/s Heritage agreed to send HT 11-12-2023 M/s Heritage team Instructed to send HT cables for
5
cables for TPT. Third part Test.
Mud Pump M/s Heritage informed that the 11-12-2023 M/s Heritage team Instructed to mobilize the Mud Not yet arrived at site
6 Mud Pump will be arriving at Pump at site.
site on 11-12-2023.
QA/QC Engineer M/s Heritage informed that on 11- 11-12-2023 M/s Heritage team Instructed to deploy QA/QC
12-2023 they will give the name Engineer.
7
and the contact of the QA/QC
person.
Unloading of Materials M/s Heritage agreed to inform M/s Heritage team Instructed to inform QA/QC person
QA/QC person form M/s AICPL from M/s AICPL before unloading
8
before unloading materials. any recived materials at site.
Survayor and Helper M/s Heritage informed that they 11-12-2023 M/s Heritage team Instructed to deploy surveyor for
9 will discuss with their GM and night shift and assign one helper
confirm on 11-12-23. permanently for survey work.
Adjournment Time: The meeting concluded at 6:30 pm
Planned Vs Achieved for the period from 04-12-2023 To 10-12-2023
12
12 60%
10 50%
8
8 40%
6 30%
5 5 5
4
4 20%
3
2
2 10%
0
0 0%
Piling D-Wall Anchoring